CN101285385A - Undermining method for three-dimensional pipe-roof - Google Patents

Undermining method for three-dimensional pipe-roof Download PDF

Info

Publication number
CN101285385A
CN101285385A CNA2008100478446A CN200810047844A CN101285385A CN 101285385 A CN101285385 A CN 101285385A CN A2008100478446 A CNA2008100478446 A CN A2008100478446A CN 200810047844 A CN200810047844 A CN 200810047844A CN 101285385 A CN101285385 A CN 101285385A
Authority
CN
China
Prior art keywords
pipe
construction
curtain
underground structure
dimensional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100478446A
Other languages
Chinese (zh)
Other versions
CN101285385B (en
Inventor
郭小红
程勇
刘继国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan CCCC Traffic Engineering Co., Ltd.
Original Assignee
CCCC Second Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Highway Consultants Co Ltd filed Critical CCCC Second Highway Consultants Co Ltd
Priority to CN2008100478446A priority Critical patent/CN101285385B/en
Publication of CN101285385A publication Critical patent/CN101285385A/en
Application granted granted Critical
Publication of CN101285385B publication Critical patent/CN101285385B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a three-dimensional pipe-curtain subsurface excavation method. The steps of the method are as follows: A. a vertical working well is formed at the circumference of an underground structure; B. a horizontal working channel is formed on the outer surface of the underground structure; C. a pipe roofing support is formed at the outer surface and a pipe roofing curtain is constructed inside the horizontal working channel; D. grouting and reinforcement are carried out by using pipe roofing steel pipes, and the grouting is carried out by pipe roofing to form a curtain after the pipe roofing construction inside the horizontal working channel is finished; E. digging is started; when the pipe roofing grouting curtain reaches the strength, the digging construction of soil mass inside the three-dimensional curtain is carried out; afterwards, the construction of the underground structure is carried out. The method is simple and convenient, and safe and convenient in construction. Particularly, for a large span underground structure under a crossroad, the method only digs half of one side of a certain road, thus the method can ensure that the road is unblocked in the construction process. Accordingly, the method can be widely applied to projects with roads and other buildings, etc., such as subway stations of a city, road tunnels with large span, underground parking areas with large span and down-traversing tunnels under main roads of the city.

Description

Undermining method for three-dimensional pipe-roof
Technical field
The present invention relates to a kind of Undermining method for three-dimensional pipe-roof, it is applicable to the construction of shallow embedding UNDERGROUND STRUCTURES.
Background technology
Along with the acceleration of Chinese Urbanization's process, under downtown roads, build Large Underground Structure and get more and more, as subway station, city road tunnel, underground parking or the like.At present, below existing road, build engineerings such as city underground station, city road tunnel, underground parking, mainly contain cut and cover method, hidden construction process and non-excavation pipe curtain method.Cut and cover method has not only destroyed environment, and original road is excavated, and has hindered the unimpeded of traffic, disturbs bigger to the city productive life.Relatively poor when the geology condition, when buried depth was dark, if adopt the hidden construction process construction, security risk was bigger, in case construction accident occurs, the social influence that causes is remarkable.Non-excavation pipe curtain method has been avoided the shortcoming of cut and cover method and hidden construction process substantially, but to being in the project at place, crossroad, still will a road wherein be excavated, and just can construct.Therefore how to find the shallow embedding UNDERGROUND STRUCTURES hidden construction process of a kind of suitable multiple ambient conditions and geological conditions very urgent.
Summary of the invention
The objective of the invention is to be to provide a kind of Undermining method for three-dimensional pipe-roof, method is easy, easy construction, especially for the UNDERGROUND STRUCTURES that is in below the crossroad, this method is only excavated half of certain bar road one side, in work progress, can guarantee The coast is clear, noiseless to the city productive life.
In order to realize above-mentioned task, the present invention adopts following technical measures:
The present invention relates to the novel tunneling construction method of a kind of shallow embedding UNDERGROUND STRUCTURES; comprise at first and form active well at the underground structure periphery; form the horizontal operation passage in the outside of underground structure then; external surface at underground structure forms three-dimensional pipe shed support at last; and utilize side pipe boron steel pipe to carry out grouting and reinforcing, under the protection of frame, underground structure is carried out excavation construction.
The invention solves the tunneling construction of city landform restricted area shallow embedding UNDERGROUND STRUCTURES, have wide future in engineering applications and market popularization value.
A kind of Undermining method for three-dimensional pipe-roof the steps include:
A, form vertical active well at underground structure periphery, this vertical active well can adopt hand excavation's pore-forming, also can adopt mechanical equivalent of light excavation.The size of vertical active well should satisfy the requirement of horizontal operation passage and underground structure excavation construction, in 3 * 5m~4 * 8m scope, select, vertical active well section configuration is rectangle or circle or polygon, and the support pattern of vertical active well is steel concrete supporting or diaphragm wall supporting or open caisson supporting.
B, form the horizontal operation passage in the underground outside of planning to build works, the horizontal operation passage adopts comparatively ripe at present pipe jacking method " Encyclopadia Sinica " or hidden construction process construction, the structural meterials of horizontal operation passage is steel concrete or steel pipe, shape can be circle, rectangle or polygon, and size can be selected in 2 * 2~3 * 3m scope.
C, form three-dimensional pipe shed support at the underground external surface of planning to build works, three-dimensional pipe canopy be meant by the slip casting of pipe boron steel pipe about the proposed building, about and before and after all form grouting curtain.Pipe canopy curtain construction method has incremental launching method (incremental launching method Process Discussion, Liu Dayang, " Sichuan building materials "), boring method etc., the diameter of pipe canopy is 100~400mm, spacing is 500~1500mm, and the pipe canopy is the steel pipe of interior concrete placing or the pvc pipe of interior hot-metal carburized steel reinforced concrete;
D, utilize side pipe boron steel pipe to carry out grouting and reinforcing.For the stable outside soil body, generally should consider to utilize the pipe canopy to carry out peripheral grouting and reinforcing.After pipe roof construction finishes in the horizontal operation passage, carry out slip casting, form curtain, the soil body is reinforced by the pipe canopy.
E, excavation construction.After the tube shed grouting curtain reaches intensity, carry out the excavation construction of the inner soil body of three-dimensional curtain, promptly can divide step, adopt mechanical equivalent of light excavation to go out the required space of underground structure step by step, carry out underground structure then and apply.
The present invention compared with prior art has the following advantages and effect:
(1) tunneling that is applicable to landform restricted area shallow embedding UNDERGROUND STRUCTURES is constructed;
(2) avoided the excavation of road as far as possible, do not had the blocked path traffic, disturbed little the city productive life;
(3) for the underground space utilization that is in below the crossroad, has bigger advantage.
Description of drawings
Fig. 1 Undermining method for three-dimensional pipe-roof layout plan
Fig. 2 Undermining method for three-dimensional pipe-roof construction I-I sectional drawing
Fig. 3 Undermining method for three-dimensional pipe-roof construction II-II sectional drawing
Fig. 4 Undermining method for three-dimensional pipe-roof construction III-III sectional drawing
Fig. 5 Undermining method for three-dimensional pipe-roof construction three-view diagram (six facial canal curtains)
Fig. 6 Undermining method for three-dimensional pipe-roof construction three-view diagram (five facial canal curtains)
The vertical active well of 1-wherein; 2-horizontal operation passage; The 3-curtain; The 4-road; The 5-building.
The specific embodiment
Below in conjunction with accompanying drawing the present invention is described in further detail:
According to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6 as can be known, for being in road 4 following and road surrounding buildings thing 5 intensive areas, Undermining method for three-dimensional pipe-roof the steps include: for the construction in this location provides a kind of good solution
A, form vertical active well 1 at underground structure periphery, the size of vertical active well 1 generally should satisfy the requirement of horizontal operation passage 2 and underground structure excavation construction, generally can in 3 * 5m~4 * 8m scope, select, its section configuration generally can be rectangle, also can be the polygon of circular or other shapes, vertical active well can be according to 2~4 of geology condition setting, the support pattern of vertical active well 1 and the size and the section size of active well have relation, and ordinary priority is selected the steel concrete supporting for use.When the non-constant of geology condition, also can adopt diaphragm wall supporting or open caisson supporting.The effect of vertical active well 1 is for follow-up construction provides condition, can carry out backfill or as transport channel between the operating period and pipeline passway to active well after construction is finished.
B, form large-sized horizontal operation passage 2 at the external surface (containing side and bottom surface) of underground structure then.Adopting incremental launching method or other hidden construction process construction level service aisles 2 in vertical active well 1, is the construction technology of comparative maturity at present, and the efficiency of construction height is safe and reliable, and cost is not high.The structural meterials of horizontal operation passage 2 can be a steel concrete, also can be steel pipe, its shape can be circle, rectangle or polygon, its quantity can be adjusted between 2~8 according to geological conditions, its size can be selected in 2 * 2~3 * 3m scope, mainly should consider to satisfy the construction needs of next stage pipe canopy curtain 3.After pipe roof construction finishes, tackle it and carry out backfill, as the basis of pipe canopy curtain 3, also can be used as the part on permanent structure basis.Apply at the peripheral tubes curtain and the pushing tow pipe to be adopted concrete or reinforced concrete earthen backfill after finishing.
C, form pipe shed support at external surface.Construction pipe canopy curtain 3 in the horizontal operation passage, its job practices has multiple: incremental launching method, boring method etc., the diameter of pipe canopy generally can be selected in 100~400mm scope, spacing can be selected between 500~1500mm, the pipe canopy can be steel pipe (interior concrete placing), or pvc pipe (interior hot-metal carburized steel reinforced concrete).Since in advance the construction pore be trifle section steel pipe or plastic pipe, intensity is lower, generally should the pipe in fill concrete or steel concrete.For the stable outside soil body, generally should consider to utilize the pipe canopy to carry out perimeter reinforcement slip casting.
D, utilization pipe boron steel pipe carry out grouting and reinforcing.After pipe roof construction finishes in the horizontal operation passage 2, promptly carry out slip casting, form curtain 3, the soil body is reinforced by the pipe canopy.
E, excavation.After tube shed grouting curtain 3 reaches intensity, carry out the excavation construction of the three-dimensional curtain 3 inner soil bodys, carry out applying of underground structure subsequently.

Claims (3)

1, a kind of Undermining method for three-dimensional pipe-roof the steps include:
A, form vertical active well (1) at underground structure periphery, the horizontal operation passage (2) and the underground structure excavation construction of vertical active well (1), in 3 * 5m~4 * 8m scope, select, vertical active well (1) section configuration is rectangle or circle or polygon, and the support pattern of vertical active well (1) is steel concrete supporting or diaphragm wall supporting or open caisson supporting;
B, form horizontal operation passage (2) at the external surface of underground structure, in vertical active well (1), adopt incremental launching method or hidden construction process construction level service aisle (2), the structural meterials of horizontal operation passage (2) is steel concrete or steel pipe, be shaped as circle, rectangle or polygon, size is selected in 2 * 2~3 * 3m scope;
C, form pipe shed support at external surface, construction pipe canopy curtain (3) in horizontal operation passage (2), its job practices is incremental launching method or boring method, the diameter of pipe canopy is 100~400mm, spacing is 500~1500mm, and the pipe canopy is the steel pipe of interior concrete placing or the pvc pipe of interior hot-metal carburized steel reinforced concrete;
D, utilization pipe boron steel pipe carry out grouting and reinforcing, after the interior pipe roof construction of horizontal operation passage (2) finishes, carry out slip casting by the pipe canopy, form curtain (3), and the soil body is reinforced;
E, excavation after tube shed grouting curtain (3) reaches intensity, carry out the excavation construction of the inner soil body of three-dimensional curtain (3), carry out applying of underground structure subsequently.
2, a kind of Undermining method for three-dimensional pipe-roof according to claim 1 is characterized in that: described vertical active well (1) is provided with 2~4.
3, a kind of Undermining method for three-dimensional pipe-roof according to claim 1 is characterized in that: described horizontal operation passage (2) is provided with 2~8.
CN2008100478446A 2008-05-29 2008-05-29 Undermining method for three-dimensional pipe-curtain Active CN101285385B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100478446A CN101285385B (en) 2008-05-29 2008-05-29 Undermining method for three-dimensional pipe-curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100478446A CN101285385B (en) 2008-05-29 2008-05-29 Undermining method for three-dimensional pipe-curtain

Publications (2)

Publication Number Publication Date
CN101285385A true CN101285385A (en) 2008-10-15
CN101285385B CN101285385B (en) 2010-06-02

Family

ID=40057767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100478446A Active CN101285385B (en) 2008-05-29 2008-05-29 Undermining method for three-dimensional pipe-curtain

Country Status (1)

Country Link
CN (1) CN101285385B (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101798931A (en) * 2010-03-12 2010-08-11 中铁隧道集团有限公司 Construction technology method of large-scale lead pipe roofs of tunnels and underground engineering without workshops
CN102031974A (en) * 2010-12-02 2011-04-27 武汉大学 Tubal curtain advanced support constructing method for deep mine roadway of coal mine passing through fault fracture zone
CN102277965A (en) * 2011-05-06 2011-12-14 杭州岩土工程有限公司 Method for building underground garage through non-surface excavation on open space
CN101929340B (en) * 2009-12-31 2012-08-29 平煤建工集团有限公司 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN102744772A (en) * 2012-07-30 2012-10-24 东南大学 Porous concrete ball forming die of three-dimensional dislocation channel
CN102900100A (en) * 2012-10-26 2013-01-30 杭州岩土工程有限公司 Method for building underground room under old building by using pipe sheds
CN103321659A (en) * 2013-07-22 2013-09-25 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN103437789A (en) * 2013-08-15 2013-12-11 北京市轨道交通设计研究院有限公司 Method for constructing water proof structure and constructing underground construction in water proof mode
CN104074525A (en) * 2014-07-02 2014-10-01 南京林业大学 Full-sectional grouting, rectangular horizontal freezing and pipe roof combined reinforcing structure and method
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN104895121A (en) * 2015-05-27 2015-09-09 北京市市政工程设计研究总院有限公司 Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN105370287A (en) * 2015-10-10 2016-03-02 中铁工程装备集团有限公司 Mechanical underground excavation construction method for large underground parking lot
CN105863649A (en) * 2015-11-23 2016-08-17 迟新宋 Underground space construction technique adopting underground excavation and causing little ruin to land surface
CN106640155A (en) * 2017-01-19 2017-05-10 中铁工程装备集团有限公司 Large-span underground space structure and construction method thereof
CN106812530A (en) * 2015-12-29 2017-06-09 又炅技术株式会社 Use projection shaped steel supporting material and the method for construction of the steel pipe multistage tunnel of nose girder
CN107083966A (en) * 2017-05-23 2017-08-22 梁美欣 Pipe with small pipe diameter hidden digging structure and tunneling method
CN107100650A (en) * 2017-05-23 2017-08-29 中铁四局集团第五工程有限公司 A kind of rectangular steel pipe curtain foot's attachment structure and its construction method
CN108019211A (en) * 2018-01-23 2018-05-11 中国铁路设计集团有限公司 Waterproof of man and its construction method in a kind of pilot tunnel of rich water sand-pebble layer
CN108979641A (en) * 2017-05-31 2018-12-11 植村技研工业株式会社 The construction method of structure in ground
CN110130951A (en) * 2019-05-27 2019-08-16 中铁工程装备集团有限公司 A kind of Large Underground parking lot structure mechanization method of construction
CN110756570A (en) * 2019-10-22 2020-02-07 中冶南方都市环保工程技术股份有限公司 Subsurface excavation remediation method for deep polluted soil
CN111794757A (en) * 2020-07-29 2020-10-20 徐州市城市轨道交通有限责任公司 Underground water treatment method for composite stratum subsurface excavation construction under existing building
CN114109393A (en) * 2021-10-18 2022-03-01 中交第二公路勘察设计研究院有限公司 Underground tunnel underground excavation construction method combining bundle pipe curtain with top pipe freezing
CN114352288A (en) * 2021-12-30 2022-04-15 南京工大交通科学研究院(滁州)有限公司 Shield short-distance upward-penetrating existing shield tunnel construction structure and construction method

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101929340B (en) * 2009-12-31 2012-08-29 平煤建工集团有限公司 Coal mine underground flat inclined tunnel pipe shed pre-grouting advance support construction process
CN101798931A (en) * 2010-03-12 2010-08-11 中铁隧道集团有限公司 Construction technology method of large-scale lead pipe roofs of tunnels and underground engineering without workshops
CN102031974A (en) * 2010-12-02 2011-04-27 武汉大学 Tubal curtain advanced support constructing method for deep mine roadway of coal mine passing through fault fracture zone
CN102031974B (en) * 2010-12-02 2013-05-01 武汉大学 Tubal curtain advanced support constructing method for deep mine roadway of coal mine passing through fault fracture zone
CN102277965A (en) * 2011-05-06 2011-12-14 杭州岩土工程有限公司 Method for building underground garage through non-surface excavation on open space
CN102744772A (en) * 2012-07-30 2012-10-24 东南大学 Porous concrete ball forming die of three-dimensional dislocation channel
CN102900100B (en) * 2012-10-26 2014-10-22 岩土科技股份有限公司 Method for building underground room under old building by using pipe sheds
CN102900100A (en) * 2012-10-26 2013-01-30 杭州岩土工程有限公司 Method for building underground room under old building by using pipe sheds
CN103321659A (en) * 2013-07-22 2013-09-25 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN103321659B (en) * 2013-07-22 2015-04-22 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN103437789A (en) * 2013-08-15 2013-12-11 北京市轨道交通设计研究院有限公司 Method for constructing water proof structure and constructing underground construction in water proof mode
CN104074525A (en) * 2014-07-02 2014-10-01 南京林业大学 Full-sectional grouting, rectangular horizontal freezing and pipe roof combined reinforcing structure and method
CN104074525B (en) * 2014-07-02 2016-02-24 南京林业大学 Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
CN104763433A (en) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN104895121A (en) * 2015-05-27 2015-09-09 北京市市政工程设计研究总院有限公司 Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN105370287A (en) * 2015-10-10 2016-03-02 中铁工程装备集团有限公司 Mechanical underground excavation construction method for large underground parking lot
CN105863649A (en) * 2015-11-23 2016-08-17 迟新宋 Underground space construction technique adopting underground excavation and causing little ruin to land surface
CN106812530A (en) * 2015-12-29 2017-06-09 又炅技术株式会社 Use projection shaped steel supporting material and the method for construction of the steel pipe multistage tunnel of nose girder
CN106812530B (en) * 2015-12-29 2019-04-02 又炅技术株式会社 Use the method for construction of protrusion fashioned iron supporting material and the steel pipe multistage tunnel of nose girder
CN106640155A (en) * 2017-01-19 2017-05-10 中铁工程装备集团有限公司 Large-span underground space structure and construction method thereof
CN107083966A (en) * 2017-05-23 2017-08-22 梁美欣 Pipe with small pipe diameter hidden digging structure and tunneling method
CN107100650A (en) * 2017-05-23 2017-08-29 中铁四局集团第五工程有限公司 A kind of rectangular steel pipe curtain foot's attachment structure and its construction method
CN107100650B (en) * 2017-05-23 2023-09-26 中铁四局集团第五工程有限公司 Rectangular steel pipe curtain foot connecting structure and construction method thereof
CN108979641A (en) * 2017-05-31 2018-12-11 植村技研工业株式会社 The construction method of structure in ground
CN108979641B (en) * 2017-05-31 2021-04-27 植村技研工业株式会社 Construction method for underground structure
CN108019211B (en) * 2018-01-23 2023-09-12 中国铁路设计集团有限公司 Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN108019211A (en) * 2018-01-23 2018-05-11 中国铁路设计集团有限公司 Waterproof of man and its construction method in a kind of pilot tunnel of rich water sand-pebble layer
CN110130951A (en) * 2019-05-27 2019-08-16 中铁工程装备集团有限公司 A kind of Large Underground parking lot structure mechanization method of construction
CN110756570A (en) * 2019-10-22 2020-02-07 中冶南方都市环保工程技术股份有限公司 Subsurface excavation remediation method for deep polluted soil
CN111794757A (en) * 2020-07-29 2020-10-20 徐州市城市轨道交通有限责任公司 Underground water treatment method for composite stratum subsurface excavation construction under existing building
CN114109393A (en) * 2021-10-18 2022-03-01 中交第二公路勘察设计研究院有限公司 Underground tunnel underground excavation construction method combining bundle pipe curtain with top pipe freezing
CN114109393B (en) * 2021-10-18 2023-11-14 中交第二公路勘察设计研究院有限公司 Underground tunnel underground excavation construction method combining beam-combination pipe curtain and pipe-jacking freezing
CN114352288A (en) * 2021-12-30 2022-04-15 南京工大交通科学研究院(滁州)有限公司 Shield short-distance upward-penetrating existing shield tunnel construction structure and construction method
CN114352288B (en) * 2021-12-30 2024-04-16 南京工大交通科学研究院(滁州)有限公司 Construction structure and construction method for shield tunneling in short distance

Also Published As

Publication number Publication date
CN101285385B (en) 2010-06-02

Similar Documents

Publication Publication Date Title
CN101285385B (en) Undermining method for three-dimensional pipe-curtain
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN102704957B (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN101922303B (en) Method for treating tunnel passing through underground river karst hall
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN204418187U (en) Subway protection region soil nail wall is in conjunction with double-row pile deep foundation ditch composite supporting construction
CN102758632A (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN102162250B (en) Protective construction method of excavating large area deep foundation pit in running sand confined water soil layer
CN103437339A (en) Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN101793023A (en) Foundation pit construction method
CN102787607A (en) Deep foundation pit precipitation support construction method applicable to coastal region
CN102808627A (en) Underground excavation construction method of steel pipe shed
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN104775439A (en) Foundation pit support and water stop integrated structure and construction method thereof
CN107165640B (en) Tunnels and underground engineering surely builds method certainly
CN102116036B (en) Method for constructing underground large building by combining top-down construction method technology with sequence construction method technology
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN204609897U (en) A kind of pipe curtain freezing process supporting and protection structure
CN108978709B (en) Urban comprehensive pipe gallery branch construction method in space-limited environment
CN205894086U (en) Little decompoed rock layer supporting construction of subway foundation ditch
CN210459195U (en) Composite supporting anti-slide pile suitable for tunnel portal

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: WUHAN CCCC TRAFFIC ENGINEERING CO., LTD.

Free format text: FORMER OWNER: CCCC SECOND HIGHWAY CONSULTANT CO., LTD.

Effective date: 20121119

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430056 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20121119

Address after: 430050, 498 parrot Avenue, Hanyang District, Hubei, Wuhan

Patentee after: Wuhan CCCC Traffic Engineering Co., Ltd.

Address before: 430056 No. 18, entrepreneurial road, Wuhan economic and Technological Development Zone, Hubei, Wuhan

Patentee before: China Communications Second Highway Survey Design and Research Institute Co., Lt