CN107100650B - A rectangular steel tube curtain foot connection structure and its construction method - Google Patents

A rectangular steel tube curtain foot connection structure and its construction method Download PDF

Info

Publication number
CN107100650B
CN107100650B CN201710370630.1A CN201710370630A CN107100650B CN 107100650 B CN107100650 B CN 107100650B CN 201710370630 A CN201710370630 A CN 201710370630A CN 107100650 B CN107100650 B CN 107100650B
Authority
CN
China
Prior art keywords
vertical
steel pipe
shaped foundation
pipe
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710370630.1A
Other languages
Chinese (zh)
Other versions
CN107100650A (en
Inventor
王圣涛
汪家雷
张效铭
李慎刚
夏云朋
徐松苗
赵文
肖俊航
刘恒
程诚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of CTCE Group
Northeastern University China
Original Assignee
Fifth Engineering Co Ltd of CTCE Group
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of CTCE Group, Northeastern University China filed Critical Fifth Engineering Co Ltd of CTCE Group
Priority to CN201710370630.1A priority Critical patent/CN107100650B/en
Publication of CN107100650A publication Critical patent/CN107100650A/en
Application granted granted Critical
Publication of CN107100650B publication Critical patent/CN107100650B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a rectangular steel pipe curtain foot connecting structure and a construction method thereof, wherein the rectangular steel pipe curtain foot connecting structure comprises an L-shaped foundation arranged in a pilot tunnel, a vertical steel pipe arranged outside the pilot tunnel and two rows of vertical bolts used for connecting the vertical steel pipe and the L-shaped foundation, two rows of bolt holes corresponding to the vertical bolts are formed in one surface of the vertical steel pipe, facing the L-shaped foundation, of the vertical steel pipe, one end of each vertical bolt penetrates through the bolt hole in the vertical steel pipe, and the other end of each vertical bolt is connected with the L-shaped foundation through an embedded bar. The invention has simple structure, is convenient for construction, reduces the jacking quantity of the vertical pipe curtains, greatly reduces the construction period, and can be suitable for the basic forms of various pipe curtain construction methods; the L-shaped foundation form can be perfectly matched with the later-stage main body structure, so that the space utilization rate is increased, the construction is convenient, and the economic benefit is improved.

Description

一种矩形钢管幕脚部连接结构及其施工方法A rectangular steel tube curtain foot connection structure and its construction method

技术领域Technical field

本发明涉及以管幕结构作为支护结构的地铁暗挖车站,主要涉及管幕结构脚部基础的构造及管幕结构与基础的连接方法。The invention relates to a subway underground excavation station using a tube curtain structure as a supporting structure, and mainly relates to the structure of the foot foundation of the tube curtain structure and the connection method between the tube curtain structure and the foundation.

背景技术Background technique

近年来,城市地下工程修建进入黄金时期。随着科技的进步,用于开挖的支护理念及方式也逐渐发生改变。其中采用管幕支护形式下的开挖对地表及周边环境的影响较小,且管幕工法在一定程度上可以起到阻水的效果。因此,我国多个在建或已建工程均采用管幕支护的形式进行施工。一般的管幕结构形式为半封闭的拱形结构,这种结构受力性能较好,但其空间利用率较小,因此出现了平顶形式的矩形管幕结构。为了保证该种管幕结构不在开挖管幕下方土体时出现整体下沉,需在管幕结构的脚部进行加固,常常将多根钢管并排连接在一起,以增加管幕结构脚部的承载力,见图1。但此种加固方式需要增加顶管的数量,延长施工工期,加之顶管施工过程中,顶进精度难以控制,如果偏差较大,相邻钢管的连接比较困难,则会降低管幕端部的加固效果,进而造成管幕结构的整体下沉,进而影响管幕结构的支护效果。In recent years, urban underground engineering construction has entered a golden period. As technology advances, the support concepts and methods used for excavation are gradually changing. Among them, excavation under the form of pipe curtain support will have less impact on the surface and surrounding environment, and the pipe curtain construction method can block water to a certain extent. Therefore, many projects under construction or already built in my country are constructed in the form of pipe curtain support. The general form of tube curtain structure is a semi-enclosed arch structure. This structure has better mechanical performance, but its space utilization is small. Therefore, a flat-top rectangular tube curtain structure has emerged. In order to ensure that this kind of pipe curtain structure does not sink as a whole when the soil beneath the pipe curtain is excavated, it is necessary to reinforce the feet of the pipe curtain structure. Multiple steel pipes are often connected side by side to increase the strength of the feet of the pipe curtain structure. Bearing capacity, see Figure 1. However, this reinforcement method requires increasing the number of pipe jacking and prolonging the construction period. In addition, during the pipe jacking construction process, the jacking accuracy is difficult to control. If the deviation is large, it will be difficult to connect adjacent steel pipes, which will reduce the strength of the ends of the pipe curtain. The reinforcement effect will cause the overall sinking of the pipe curtain structure, thereby affecting the support effect of the pipe curtain structure.

发明内容Contents of the invention

本发明提供一种便于施工,并且能够有效的加固管幕结构脚部的连接结构及施工方法,加固效果更为显著,与后期车站的侧墙和底板的施工相结合,优化了施工步序。The invention provides a connection structure and construction method that is easy to construct and can effectively reinforce the feet of the tube curtain structure. The reinforcement effect is more significant. It is combined with the later construction of the side walls and bottom plates of the station to optimize the construction steps.

为解决上述技术问题,本发明采用如下技术方案:In order to solve the above technical problems, the present invention adopts the following technical solutions:

一种矩形钢管幕脚部连接结构,包括置于导洞内的L型基础、位于导洞外的竖向钢管,以及用于连接竖向钢管和L型基础的两排竖向螺栓,所述竖向钢管朝向L型基础的一面上开设有两排与竖向螺栓对应的螺栓孔,所述竖向螺栓一端穿过竖向钢管上的螺栓孔,另一端通过预埋钢筋与L型基础连接。A rectangular steel pipe curtain foot connection structure, including an L-shaped foundation placed in a guide hole, a vertical steel pipe located outside the guide hole, and two rows of vertical bolts for connecting the vertical steel pipe and the L-shaped foundation, said There are two rows of bolt holes corresponding to the vertical bolts on the side of the vertical steel pipe facing the L-shaped foundation. One end of the vertical bolts passes through the bolt holes on the vertical steel pipe, and the other end is connected to the L-shaped foundation through embedded steel bars. .

所述竖向钢管与L型基础之间的区域竖向布置有小直径钢管,该小直径钢管用于穿过竖向螺栓。Small-diameter steel pipes are vertically arranged in the area between the vertical steel pipes and the L-shaped foundation, and the small-diameter steel pipes are used to pass through vertical bolts.

所述竖向螺栓与预埋钢筋在所述小直径钢管内焊接。The vertical bolts and embedded steel bars are welded in the small diameter steel pipe.

本发明还提供一种矩形钢管幕脚部连接结构的施工方法,包括如下步骤:The invention also provides a construction method for a rectangular steel pipe curtain foot connection structure, which includes the following steps:

1)首先采用台阶法施工管幕下方的导洞,边开挖边进行支护,直至沿着管幕轴向贯通,在导洞施工时根据竖向钢管的螺栓孔的间距,在暗挖初支内预埋小直径钢管;1) First, use the step method to construct the guide tunnel under the pipe curtain, and perform support while excavation until it is penetrated along the axial direction of the pipe curtain. During the construction of the guide tunnel, according to the spacing of the bolt holes of the vertical steel pipes, at the beginning of the underground excavation Small diameter steel pipes are embedded in the branch;

2)接着对L型基础进行施工,钢骨架开始绑扎时在其顶部设置预埋钢筋,预埋时根据导洞上预埋的小直径钢管的孔位进行随机调整,确保两者在同一中心线上,以,钢骨架搭接完成后,支模浇筑混凝土;2) Next, construct the L-shaped foundation. When the steel frame starts to be tied, pre-embedded steel bars are set on the top. During pre-embedding, random adjustments are made according to the hole positions of the small-diameter steel pipes embedded in the guide holes to ensure that they are on the same center line. Above, after the steel frame overlap is completed, concrete is poured into the formwork;

3)顶进竖向钢管;3) Jack up the vertical steel pipe;

4)顶管完成后,将竖向螺栓从螺栓孔内下穿,保证在不需要破除导洞支护的情况下能通过小直径钢管与L型基础的预埋钢筋焊接;4) After the pipe jacking is completed, pass the vertical bolts through the bolt holes to ensure that the small diameter steel pipe can be welded to the embedded steel bars of the L-shaped foundation without removing the guide tunnel support;

5)竖向螺栓与预埋钢筋焊接完毕后,针对连接处支模,进行整体浇筑混凝土,整体管幕结构和脚部加固施工完毕。5) After the vertical bolts and embedded steel bars are welded, concrete is poured as a whole for the joint formwork, and the overall pipe curtain structure and foot reinforcement are completed.

由以上技术方案可知,本发明结构简单,便于修建,减少了竖向管幕的顶进数量,大大减少了施工工期,可适用于各种管幕工法的基础形式;L型基础形式,可以与后期主体结构完美契合,增大了空间利用率,方便施工,提高了经济效益。It can be seen from the above technical solutions that the present invention has a simple structure, is easy to construct, reduces the number of vertical pipe curtain jackings, greatly reduces the construction period, and can be applied to the foundation forms of various pipe curtain construction methods; the L-shaped foundation form can be used with The main structure in the later stage fits perfectly, which increases space utilization, facilitates construction, and improves economic benefits.

附图说明Description of the drawings

图1为本发明矩形钢管幕脚部连接结构的示意图;Figure 1 is a schematic diagram of the connection structure of the rectangular steel pipe curtain foot part of the present invention;

图2为使用本发明矩形管幕脚部连接结构的车站剖面图;Figure 2 is a cross-sectional view of a station using the rectangular tube curtain foot connection structure of the present invention;

图3为本发明中竖向钢管的俯视图。Figure 3 is a top view of the vertical steel pipe in the present invention.

具体实施方式Detailed ways

下面结合附图对本发明的一种优选实施方式作详细的说明。A preferred embodiment of the present invention will be described in detail below with reference to the accompanying drawings.

如图2所示,矩形钢管幕脚部连接结构10是管幕支护的一部分,用于对管幕结构的脚部进行加固,并与后期主体结构20完美契合,增大了空间利用率,方便施工。As shown in Figure 2, the rectangular steel tube curtain foot connection structure 10 is part of the tube curtain support, used to reinforce the foot of the tube curtain structure, and perfectly fits the later main structure 20, increasing space utilization. Convenient for construction.

如图1和3所示,矩形钢管幕脚部连接结构10包括L型基础30和竖向钢管40,L型基础置于暗挖的导洞70内部,竖向钢管置于导洞外侧,其中竖向钢管面向导洞的一侧开设有两排螺栓孔41,竖向钢管与L型基础通过竖向螺栓50进行固定连接。As shown in Figures 1 and 3, the rectangular steel tube curtain foot connection structure 10 includes an L-shaped foundation 30 and a vertical steel pipe 40. The L-shaped foundation is placed inside the underground guide tunnel 70, and the vertical steel pipe is placed outside the guide tunnel, where Two rows of bolt holes 41 are provided on the side of the vertical steel pipe facing the guide hole. The vertical steel pipe and the L-shaped foundation are fixedly connected through vertical bolts 50.

所述竖向螺栓50一端穿过竖向钢管上的螺栓孔41,另一端通过预埋钢筋31与L型基础30连接。所述竖向钢管与L型基础之间的区域竖向布置有小直径钢管60,该小直径钢管用于穿过竖向螺栓,使得竖向螺栓与预埋钢筋在小直径钢管内焊接。One end of the vertical bolt 50 passes through the bolt hole 41 on the vertical steel pipe, and the other end is connected to the L-shaped foundation 30 through the embedded steel bar 31. A small-diameter steel pipe 60 is vertically arranged in the area between the vertical steel pipe and the L-shaped foundation. The small-diameter steel pipe is used to pass through the vertical bolts, so that the vertical bolts and the embedded steel bars are welded in the small-diameter steel pipe.

本发明矩形钢管幕脚部连接结构用于管幕结构施工的具体方法如下:The specific method for using the rectangular steel tube curtain foot connection structure in the construction of the tube curtain structure according to the present invention is as follows:

一、首先采用台阶法施工管幕下方的导洞70,边开挖边进行支护,直至沿着管幕轴向贯通。并在导洞施工时根据竖向钢管的螺栓孔的间距,在暗挖初支内预埋φ45@150的小直径钢管60,预埋前两端采用塑料胶带进行封堵防止混凝土进入,并采用格栅进行固定,防止喷混凝土时小直径钢管发生偏移。1. First, use the step method to construct the guide tunnel 70 below the pipe curtain, and perform support while excavation until it is penetrated along the axial direction of the pipe curtain. During the construction of the guide tunnel, a φ45@150 small-diameter steel pipe 60 was pre-buried in the first branch of the underground excavation according to the spacing between the bolt holes of the vertical steel pipes. The two ends of the pre-buried pipe were sealed with plastic tape to prevent concrete from entering. The grid is fixed to prevent the small-diameter steel pipe from shifting during concrete spraying.

二、对L型基础进行施工,钢筋骨架开始绑扎时应在其顶部设置预埋钢筋31,预埋长度满足35d,外露长度大于32d,预埋时根据暗挖导洞上的小直径钢管的孔位进行随机调整,确保两者在同一中心线上,以便后续进行连接。钢骨架搭接完成后,支模浇筑混凝土。2. When constructing the L-shaped foundation, pre-embedded steel bars 31 should be set on the top of the steel frame when starting to be tied. The pre-embedded length should meet 35d, and the exposed length should be greater than 32d. When pre-embedded, the holes of the small-diameter steel pipes in the guide tunnel should be dug underground. Randomly adjust the position to ensure that the two are on the same center line for subsequent connection. After the steel frame overlap is completed, the formwork is poured with concrete.

三、在钢管顶进过程中,对于在暗挖导洞内连接的竖向钢管顶进时精度的控制至关重要,其不仅影响到上部顶管的方向,而且影响与L型基础的连接,施工时应不间断性进行测量,及时纠偏,力争竖向钢管的上下孔位水平,使其螺栓孔与小直径钢管上下连接孔相通。3. During the steel pipe jacking process, it is crucial to control the accuracy of the vertical steel pipes connected in the underground guide tunnel. It not only affects the direction of the upper pipe jacking, but also affects the connection with the L-shaped foundation. During construction, continuous measurements should be taken, deviations should be corrected in time, and the upper and lower holes of the vertical steel pipe should be level, so that the bolt holes are connected with the upper and lower connecting holes of the small diameter steel pipe.

四、顶管完成后,将竖向螺栓50从螺栓孔41内下穿,保证在不需要破除导洞支护的情况下能通过暗挖预埋小直径钢管60与L型基础的预埋钢筋31焊接,焊接长度不小于10d。4. After the pipe jacking is completed, pass the vertical bolts 50 through the bolt holes 41 to ensure that the small-diameter steel pipes 60 and the embedded steel bars of the L-shaped foundation can be pre-buried through underground excavation without removing the support of the guide tunnel. 31 Welding, the welding length is not less than 10d.

五、竖向螺栓与预埋钢筋焊接完毕后,进行质量检查,检验合格后,针对连接处支模,进行整体浇筑混凝土,整体管幕结构和脚部加固施工完毕。5. After the vertical bolts and embedded steel bars are welded, quality inspection is carried out. After passing the inspection, concrete is poured as a whole for the joint formwork, and the overall pipe curtain structure and foot reinforcement construction are completed.

以上所述实施方式仅仅是对本发明的优选实施方式进行描述,并非对本发明的范围进行限定,在不脱离本发明设计精神的前提下,本领域普通技术人员对本发明的技术方案作出的各种变形和改进,均应落入本发明的权利要求书确定的保护范围内。The above-described embodiments are only descriptions of preferred embodiments of the present invention and do not limit the scope of the present invention. Various modifications to the technical solutions of the present invention may be made by those of ordinary skill in the art without departing from the design spirit of the present invention. and improvements shall fall within the protection scope determined by the claims of the present invention.

Claims (3)

1. A construction method of a rectangular steel pipe curtain foot connecting structure is characterized in that,
the rectangular steel pipe curtain foot connecting structure comprises an L-shaped foundation arranged in a pilot tunnel, a vertical steel pipe arranged outside the pilot tunnel and two rows of vertical bolts used for connecting the vertical steel pipe and the L-shaped foundation, wherein two rows of bolt holes corresponding to the vertical bolts are formed in one face of the vertical steel pipe, facing the L-shaped foundation, of each vertical steel pipe, one end of each vertical bolt penetrates through the bolt hole in the vertical steel pipe, and the other end of each vertical bolt is connected with the L-shaped foundation through an embedded steel bar; a small-diameter steel pipe is vertically arranged in the area between the vertical steel pipe and the L-shaped foundation and is used for penetrating through a vertical bolt, and the vertical bolt and the embedded steel bar are welded in the small-diameter steel pipe;
the construction method comprises the following steps:
1) Firstly, constructing a pilot tunnel below a pipe curtain by adopting a step method, excavating while supporting until the pilot tunnel is penetrated along the axial direction of the pipe curtain, and pre-burying small-diameter steel pipes in a pre-excavated primary support according to the intervals of bolt holes of vertical steel pipes during pilot tunnel construction;
2) Then constructing an L-shaped foundation, arranging embedded bars at the top of the L-shaped foundation when the steel skeleton starts to be bound, randomly adjusting the embedded bars according to the hole positions of the small-diameter steel pipes embedded in the pilot tunnel when the embedded bars are embedded, ensuring that the embedded bars and the steel skeleton are on the same central line, and supporting a mold to pour concrete after the steel skeleton is overlapped;
3) Jacking a vertical steel pipe;
4) After the jacking pipe is completed, the vertical bolts penetrate downwards from the bolt holes, so that the welding between the small-diameter steel pipes and embedded bars of the L-shaped foundation can be ensured under the condition that the pilot tunnel support is not required to be broken;
5) After the welding of the vertical bolts and the embedded bars is finished, the formwork is supported at the joint, the concrete is integrally poured, and the whole pipe curtain structure and the foot reinforcement construction are finished.
2. The construction method according to claim 1, wherein in step 1), both ends of the small-diameter steel pipe before embedding are plugged with plastic tapes to prevent concrete from entering, and are fixed with a grid.
3. The construction method according to claim 1, wherein the measurement is performed continuously and the correction is performed in time during the jacking of the vertical steel pipe, so that the level of the upper and lower hole positions of the vertical steel pipe is ensured, and the bolt holes of the vertical steel pipe are communicated with the upper and lower connecting holes of the small-diameter steel pipe.
CN201710370630.1A 2017-05-23 2017-05-23 A rectangular steel tube curtain foot connection structure and its construction method Active CN107100650B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710370630.1A CN107100650B (en) 2017-05-23 2017-05-23 A rectangular steel tube curtain foot connection structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710370630.1A CN107100650B (en) 2017-05-23 2017-05-23 A rectangular steel tube curtain foot connection structure and its construction method

Publications (2)

Publication Number Publication Date
CN107100650A CN107100650A (en) 2017-08-29
CN107100650B true CN107100650B (en) 2023-09-26

Family

ID=59670675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710370630.1A Active CN107100650B (en) 2017-05-23 2017-05-23 A rectangular steel tube curtain foot connection structure and its construction method

Country Status (1)

Country Link
CN (1) CN107100650B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007332638A (en) * 2006-06-14 2007-12-27 Ohbayashi Corp Underground space construction method, underground space constructed in the method, and underground structure constructed in the method
CN101285385A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Undermining method for three-dimensional pipe-roof
CN102704957A (en) * 2012-05-11 2012-10-03 北京工业大学 Shed-frame method for shallowly burying large-sized underground structure construction
CN103321659A (en) * 2013-07-22 2013-09-25 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN104453948A (en) * 2014-12-01 2015-03-25 中铁隆工程集团有限公司 Vertical prestress steel pipe supporting structure for large-section subsurface tunnel and construction process
CN205225281U (en) * 2015-12-14 2016-05-11 中建六局土木工程有限公司 For a short time, it secretly digs section support construction structures than super shallow rectangle that buries to cover to stride
CN105888703A (en) * 2016-06-03 2016-08-24 北京城建设计发展集团股份有限公司 Method for constructing super-shallow-burial subway station under transverse canopy erected inside micro pilot tunnel
CN106089243A (en) * 2016-06-12 2016-11-09 东北大学 A kind of pipe curtain supporting construction connected based on concrete filled steel tube
CN206957743U (en) * 2017-05-23 2018-02-02 中铁四局集团第五工程有限公司 A kind of rectangular steel pipe curtain foot attachment structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007332638A (en) * 2006-06-14 2007-12-27 Ohbayashi Corp Underground space construction method, underground space constructed in the method, and underground structure constructed in the method
CN101285385A (en) * 2008-05-29 2008-10-15 中交第二公路勘察设计研究院有限公司 Undermining method for three-dimensional pipe-roof
CN102704957A (en) * 2012-05-11 2012-10-03 北京工业大学 Shed-frame method for shallowly burying large-sized underground structure construction
CN103321659A (en) * 2013-07-22 2013-09-25 中铁隧道集团有限公司 Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN104453948A (en) * 2014-12-01 2015-03-25 中铁隆工程集团有限公司 Vertical prestress steel pipe supporting structure for large-section subsurface tunnel and construction process
CN205225281U (en) * 2015-12-14 2016-05-11 中建六局土木工程有限公司 For a short time, it secretly digs section support construction structures than super shallow rectangle that buries to cover to stride
CN105888703A (en) * 2016-06-03 2016-08-24 北京城建设计发展集团股份有限公司 Method for constructing super-shallow-burial subway station under transverse canopy erected inside micro pilot tunnel
CN106089243A (en) * 2016-06-12 2016-11-09 东北大学 A kind of pipe curtain supporting construction connected based on concrete filled steel tube
CN206957743U (en) * 2017-05-23 2018-02-02 中铁四局集团第五工程有限公司 A kind of rectangular steel pipe curtain foot attachment structure

Also Published As

Publication number Publication date
CN107100650A (en) 2017-08-29

Similar Documents

Publication Publication Date Title
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN104452812B (en) The construction method of outer wall of basement
CN203229874U (en) Repeatedly used cast-in-place support system for simply-supported beam
CN103669866B (en) The construction method of basement reinforced concrete post node connecting structure
CN103205964A (en) Cast-in-place pile construction method using steel pipe column splicing piles
CN110700237A (en) Construction method of diaphragm wall for preventing concrete from flowing around
CN104389315B (en) Consolidation grouting drilled pile wall and construction method thereof
CN104947681A (en) Super large super deep basement ground pit construction method
CN109235507B (en) A ground reinforcement system and method for reinforcing existing tunnels
CN208267862U (en) A kind of bracing means at tunnel road surface crack
CN105220720B (en) Collapsible Loess District building strengthening of foundation stake and pressing pile construction method thereof
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN203904971U (en) Reinforcement cage protective device capable of controlling necking, bar leakage and mud inclusion of underground diaphragm wall
CN204185845U (en) A kind of water-proof pile board wall supporting and protection structure
CN111305141B (en) Drainage method for underground comprehensive pipe gallery in dry season canal penetrating
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN205242441U (en) Oval contrary shaft of doing of suspension type
CN204959787U (en) Novel tower crane combination formula basis
CN204326059U (en) A kind of soft soil layer diaphragm wall filling concrete constructing structure
CN107503355B (en) Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof
CN105041348A (en) Underground space subsurface excavation construction method adopting combined roof
CN105275013A (en) Core tube inverse superimposed underground diaphragm wall and construction method thereof
CN110994523B (en) Method and system for protecting cable
CN210766861U (en) Portal formula building pile foundation underpins structure under narrow and small space
CN205046592U (en) Building foundation consolidates stake

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant