CN101252264B - Equipotential electrical highfield hot-line working method - Google Patents

Equipotential electrical highfield hot-line working method Download PDF

Info

Publication number
CN101252264B
CN101252264B CN2008100582399A CN200810058239A CN101252264B CN 101252264 B CN101252264 B CN 101252264B CN 2008100582399 A CN2008100582399 A CN 2008100582399A CN 200810058239 A CN200810058239 A CN 200810058239A CN 101252264 B CN101252264 B CN 101252264B
Authority
CN
China
Prior art keywords
insulated
equipotential
electrician
sling
flexible ladder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2008100582399A
Other languages
Chinese (zh)
Other versions
CN101252264A (en
Inventor
字美荣
施昌泰
张灿昆
谢文义
李建云
曾为
何永东
杨文波
赖炬强
苏建新
杨晋
肖鹏飞
赵向东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dali Power Supply Bureau Of Yunnan Power Grid Corp
Dali Power Supply Bureau of Yunnan Power Grid Co Ltd
Original Assignee
Dali Power Supply Bureau Of Yunnan Power Grid Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dali Power Supply Bureau Of Yunnan Power Grid Corp filed Critical Dali Power Supply Bureau Of Yunnan Power Grid Corp
Priority to CN2008100582399A priority Critical patent/CN101252264B/en
Publication of CN101252264A publication Critical patent/CN101252264A/en
Application granted granted Critical
Publication of CN101252264B publication Critical patent/CN101252264B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

Disclosed is a live operation method of equipotential tools in a high electric field. In the method which makes use of an insulated jack ladder(3)and a motor winch (2), an insulated pulley(5) and an insulated sling(4)are carried onto an iron tower(1)by an electric tool, and the insulated pulley(5) is hitched at an appropriate position; the insulated sling(4) is threaded through the insulated pulley(5) and then is dropped onto the ground by the electric tool on the tower; one end of the insulated sling is tied onto the insulated jack ladder(3) and the other end is wound on the motor winch (2)by an electric tool on the ground. The motor winch (2)tows the insulated sling(4)and slings the insulated jack ladder(3) and the equipotential electric tools, and when the equipotential electric tools are 1.6-2.6m away from the leads, the motor winch (2)stops towing the insulated sling(4), then the equipotential electric tools enter the electric field through the insulated jack ladder(3) to be potentially equalized with the leads. The method is of good flexibility, safety, reliability and is time-saving and labor-saving.

Description

A kind of Equipotential electrical highfield hot-line working method
Technical field:
The invention belongs to the Equipotential electrical highfield hot-line working method technical field.
Technical background: the operational method that traditional equipotential electrician adopts insulated flexible ladder to enter electric field generally has two kinds: the one, and climb rope ladder from ground and enter electric field; Another kind is to enter electric field from body of the tower with hanging blue pendulum people.Preceding a kind of mode wastes time and energy, and especially the iron tower of 500kV circuit mostly is 40-50 rice, and equipotential electrician tires out after climbing to lead, has a strong impact on next step work; A kind of method in back is loaded down with trivial details time-consuming, and fail safe, reliability are bad.
Summary of the invention:
Above-mentioned existing operational method wastes time and energy, the shortcoming of fail safe poor reliability in order to overcome just in the present invention, and provide a kind of new equipotential electrician to enter highfield live line working method, promptly adopt the equipotential electrician to take advantage of insulated flexible ladder to enter highfield by the lifting simultaneously of motor-driven strand mill.
Concrete steps are as follows:
(1) electrician carries the insulation coaster on the tower, insulated sling is climbed up iron tower and hung up properly coaster at correct position;
(2) electrician is put to ground after insulated sling is passed the insulation coaster on the tower;
(3) the ground electrician on insulated flexible ladder, the other end is on motor-driven strand mill with an end bolt of insulated sling;
(4) the isopotential electrical work area is on insulated flexible ladder and the good safety belt of bolt;
(5) the ground electrician uses motor-driven strand mill traction insulated sling, and insulated flexible ladder and equipotential electrician are lifted by crane simultaneously;
(6) stop traction during at about 1.6~2.6 meters from lead as the equipotential electrician, oneself climb insulated flexible ladder by the equipotential electrician and enter electric field, with the lead equipotential.
The invention has the beneficial effects as follows:
Equipotential electrician takes advantage of insulated flexible ladder to enter in the process of electric field by the lifting simultaneously of motor-driven strand mill, equipotential electrician need not oneself exert all one's strength and climb rope ladder, operate motor-driven strand mill by the ground electrician equipotential electrician and insulated flexible ladder are elevated near the electric field simultaneously reposefully, the equipotential electrician is again from being advanced into highfield then.Adopt this operational method to greatly reduce the labour intensity that the equipotential electrician enters electric field, the present invention has that flexibility is good, fail safe is good, good reliability, time saving and energy saving remarkable advantage.
Further set forth content of the present invention below in conjunction with drawings and Examples.
Description of drawings:
Fig. 1 is the inventive method schematic diagram.
Embodiment:
As shown in Figure 1, the present invention adopts insulated flexible ladder 3 and motor-driven strand mill 2, by electrician on the tower carry insulation coaster 5, insulated sling 4 is climbed up iron tower 1 and is hung up properly insulation coaster 5 at correct position; The electrician is put to ground after insulated sling 4 is passed the insulation coaster on the tower; On insulated flexible ladder 3, the other end is on motor-driven strand mill 2 with an end bolt of insulated sling for the ground electrician; The isopotential electrical work area is on insulated flexible ladder 3 and the good safety belt of bolt; The ground electrician uses motor-driven strand mill 2 traction insulated slings 4, and insulated flexible ladder and equipotential electrician are lifted by crane simultaneously; When equipotential electrician 7 stops traction during at 1.6~2.6 meters from lead 6, enter electric field by equipotential electrician 7 by oneself climbing insulated flexible ladder, with the lead equipotential.The casual elder brother I of transmission of electricity management place 500kV of Dali Power Supply Bureau, Yunnan Power Grid Corporation returns the #58 tower to carry out in the operation process of the two string of charged for replacement A phase straight line lightning stroke flashover insulator, the operational method that has adopted equipotential electrician to take advantage of insulated flexible ladder to enter electric field by the lifting simultaneously of motor-driven strand mill, respond well.
Big and II loop line #89 tower carries out in the operation process of charged for replacement 500kV circuit L insulator string at 500kV, has adopted equipotential electrician to take advantage of insulated flexible ladder to lift by crane the operational method that enters electric field simultaneously by motor-driven strand mill, and is respond well.

Claims (1)

1. an Equipotential electrical highfield hot-line working method is characterized in that, adopts insulated flexible ladder (3) and motor-driven strand mill (2), by electrician on the tower carry insulation coaster (5), insulated sling (4) is climbed up iron tower (1) and is hung up properly the coaster (5) that insulate at correct position; The electrician is put to ground after insulated sling (4) is passed the insulation coaster on the tower; On insulated flexible ladder (3), the other end grinds on (2) around motor-driven strand the ground electrician with an end bolt of insulated sling; The isopotential electrical work area is gone up and the good safety belt of bolt at insulated flexible ladder (3); The ground electrician uses motor-driven strand mill (2) traction insulated sling (4), and insulated flexible ladder and equipotential electrician are lifted by crane simultaneously; When the equipotential electrician stops traction during at 1.6~2.6 meters from lead, the electrician enters electric field by insulated flexible ladder by equipotential, with the lead equipotential.
CN2008100582399A 2008-04-02 2008-04-02 Equipotential electrical highfield hot-line working method Active CN101252264B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008100582399A CN101252264B (en) 2008-04-02 2008-04-02 Equipotential electrical highfield hot-line working method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008100582399A CN101252264B (en) 2008-04-02 2008-04-02 Equipotential electrical highfield hot-line working method

Publications (2)

Publication Number Publication Date
CN101252264A CN101252264A (en) 2008-08-27
CN101252264B true CN101252264B (en) 2010-08-18

Family

ID=39955500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008100582399A Active CN101252264B (en) 2008-04-02 2008-04-02 Equipotential electrical highfield hot-line working method

Country Status (1)

Country Link
CN (1) CN101252264B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102136693B (en) * 2010-12-28 2013-01-02 中国南方电网有限责任公司超高压输电公司百色局 Method and device for realizing long-distance equal electric potential access of winch hanging basket guide rail
CN103001148A (en) * 2012-12-04 2013-03-27 铜川供电局 Simple-root breakage high-altitude connecting method for 330kVdouble-bundled conductor
CN103606842A (en) * 2013-11-08 2014-02-26 国家电网公司 220 KV linear same-tower double-loop live-line operation method
CN103683105A (en) * 2013-12-17 2014-03-26 国家电网公司 Live working method of phase conductor insulating arm aerial platform truck under 66kV electric transmission line
CN103787217A (en) * 2014-02-21 2014-05-14 中国南方电网有限责任公司超高压输电公司南宁局 Small-tooth-difference transmission light hand winch and using method thereof
CN104638565A (en) * 2015-01-30 2015-05-20 国家电网公司 Method for performing equipotential live line work by putting +/-800kV tangent tower electric transmission line into electric field
CN105375395B (en) * 2015-12-17 2017-10-20 国家电网公司 ± 800kV DC lines hotline maintenance turns ladder and operational method with insulation
CN109038365B (en) * 2018-08-10 2019-12-31 国网四川省电力公司检修公司 Load hoisting system for live replacement of 500kV linear insulator string
CN109406930A (en) * 2018-10-24 2019-03-01 云南电网有限责任公司电力科学研究院 A kind of method that U-shaped short-circuit test device is installed in livewire work
CN117712915B (en) * 2023-12-05 2024-06-11 江苏恒康电力科技有限公司 Maintenance device and maintenance method for drilling span type angle steel tower insulator

Also Published As

Publication number Publication date
CN101252264A (en) 2008-08-27

Similar Documents

Publication Publication Date Title
CN101252264B (en) Equipotential electrical highfield hot-line working method
CN105162039A (en) Portable grounding wire transmitter and using method
CN112357847A (en) Portable lifting auxiliary device for live-wire work
CN214141460U (en) Portable lifting auxiliary device for live-wire work
CN206379675U (en) The yoke plate clamp of electrified replacing linear tower V insulator string wires
CN104836156A (en) Synthetic insulator simple ladder
CN202488034U (en) Lifting device for electric transmission line of angle iron tower
CN203553745U (en) A 800kV extra high voltage direct current line 150kN level soft insulation pull rod
CN202917897U (en) Cable hoisting horizontal pulley
CN203242965U (en) Sag adjuster
CN203398638U (en) Operation ladder for painting insulator string in power transmission line
CN109346996A (en) A kind of power construction wire tensioning device and line tightening method
CN201332246Y (en) Large-tonnage conducting wire lifter
CN201272256Y (en) Insulated three-sheave block double hook hoist
CN202353102U (en) Lead lifting device for power line erection
CN202444204U (en) Traction lifting device for high-altitude circuit tools and appliances
CN202906291U (en) Operation rope ladder hanging equipment
CN105762702A (en) Method for replacing L-shaped insulator string of +/-800kV direct current transmission line
CN203553744U (en) An ultra extra high voltage AC-DC overhead transmission line ground wire optical cable armour clamp replacing apparatus
CN202488035U (en) Hoisting device for maintenance of power transmission line above concrete poles
CN201252363Y (en) Combined tool for replacing a linear insulator of an electric transmission line
CN203461758U (en) Electric derrick mast device
CN203466502U (en) Electric power mounting wire tightening device
CN104201606A (en) Separating clamp for 500KV strain insulator string
CN202268650U (en) Insulation pulling plate of transmission wire lifter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant