CN101205702A - Beam and mold combined mobile formwork - Google Patents
Beam and mold combined mobile formwork Download PDFInfo
- Publication number
- CN101205702A CN101205702A CNA2007101686102A CN200710168610A CN101205702A CN 101205702 A CN101205702 A CN 101205702A CN A2007101686102 A CNA2007101686102 A CN A2007101686102A CN 200710168610 A CN200710168610 A CN 200710168610A CN 101205702 A CN101205702 A CN 101205702A
- Authority
- CN
- China
- Prior art keywords
- formwork
- mobile formwork
- mold
- steel box
- box girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域Technical field
本发明涉及桥梁工程上部结构箱梁建造技术,具体为混凝土箱梁现浇采用的梁模合一型移动模架。The invention relates to a bridge engineering superstructure box girder construction technology, in particular to a beam-mold-integrated mobile formwork used in cast-in-place concrete box girders.
背景技术 Background technique
移动模架浇筑混凝土箱梁技术在我国的应用已十分广泛。常规移动模架的模板系统和承重梁系统是分离的,在过孔走行时,会将模板系统(特别是底模系统)在横桥向一分为二,分别向两侧横移至墩身宽度范围以外,利用墩身两侧的空档通过。上述移动模架施工得以实现的前提条件是墩身宽度与砼箱梁底板宽度相近。对墩身宽度远远大于混凝土箱梁底板宽度的桥梁,常规移动模架的过孔技术将不能适应,即使勉强为之,也大大增加了施工成本和施工难度。The technology of pouring concrete box girder with moving formwork has been widely used in our country. The formwork system and load-bearing beam system of conventional mobile formwork are separated. When traveling through the hole, the formwork system (especially the bottom formwork system) will be divided into two in the direction of the bridge, and they will be moved to the pier body on both sides. Outside the width range, use the gaps on both sides of the pier body to pass through. The prerequisite for the above-mentioned mobile formwork construction to be realized is that the width of the pier body is similar to the width of the bottom plate of the concrete box girder. For bridges whose pier body width is much larger than that of the concrete box girder bottom plate, the hole-through technology of conventional mobile formwork will not be able to adapt, even if it is barely done, it will greatly increase the construction cost and construction difficulty.
发明内容Contents of Invention
本发明的目的是针对以上不足,为满足宽墩身桥梁的施工,充分结合主体构造特性,提供了一种构造简捷、受力明确,操作简便,功能齐全、安全可靠的新型移动模架。The purpose of the present invention is to address the above shortcomings, in order to meet the construction of wide pier bridges, and fully combine the structural characteristics of the main body, to provide a new type of mobile formwork with simple structure, clear force, easy operation, complete functions, safety and reliability.
本发明目的的实现方式为梁模合一型移动模架。模架主要由承重主梁、导梁、支承装置、模板系统、底模开合系统、纵横移系统及辅助结构组成。The way to realize the object of the present invention is a beam-mold-integrated mobile formwork. The formwork is mainly composed of load-bearing main beams, guide beams, supporting devices, formwork systems, bottom mold opening and closing systems, vertical and horizontal movement systems and auxiliary structures.
承重主梁采用异型钢箱,其顶板及内侧斜腹板与砼箱梁轮廓线一致,因此除承重外还兼有外模功能;承重主梁分为若干节段制造,节段间采用螺栓连接,钢箱自设反拱。The load-bearing main girder adopts a special-shaped steel box, and its top plate and inner inclined web are consistent with the outline of the concrete box girder, so in addition to load-bearing, it also has the function of an outer mold; the load-bearing main girder is manufactured in several segments, and the segments are connected by bolts , The steel box has its own anti-arch.
导梁由型钢组焊成桁架结构。The guide beam is welded into a truss structure by section steel.
支承装置采用自锁式千斤顶,制梁时混凝土箱梁自重及施工荷载由千斤顶承受,模架下降也由此完成。The supporting device adopts self-locking jacks, and the self-weight of the concrete box girder and the construction load are borne by the jacks when the beams are made, and the lowering of the formwork is also completed.
模板系统4主要包括底模、翼板模。由于砼箱梁底与墩顶高度所限,底模自动开启必须越过墩顶,基于此底模采用了低高度大块正交异性板结构,在底模两侧装有长滑道供底模开合所用。底模与主梁由抗剪螺栓和抗剪销连接。
底模开合系统包括底模横移液压千斤顶、千斤顶支承及换向体系、千斤顶连接座及吊辊等。过孔时底模向一侧水平开启,过墩后复位。The bottom mold opening and closing system includes the bottom mold lateral movement hydraulic jack, jack support and reversing system, jack connecting seat and hanging roller, etc. When passing through the hole, the bottom mold opens horizontally to one side, and resets after passing through the pier.
纵横移系统包括纵移和横移两种装置。The vertical and horizontal moving system includes two devices for vertical and horizontal movement.
辅助结构包括小门吊、走行轨道及操作吊篮。Auxiliary structures include small door cranes, running tracks and operating baskets.
本移动模架可借鉴应用于等高度简支箱梁、连续箱梁的原位浇筑施工。The mobile formwork can be used for reference in the in-situ pouring construction of simply supported box girders with equal heights and continuous box girders.
梁模合一型移动模架技术特点鲜明,总结如下:The technical characteristics of beam-mold-integrated mobile formwork are distinct, which are summarized as follows:
(1)适应宽墩桥梁施工(1) Adapt to wide pier bridge construction
成功解决了超宽墩身条件下移动模架走行过孔的技术难题。Successfully solved the technical problem of moving the formwork through the hole under the condition of ultra-wide pier body.
(2)梁模合一(2) Combination of beam and mold
梁模结构合二为一的移动模架在国内外尚属首次应用。It is the first application at home and abroad that the beam-formwork structure is combined into one mobile formwork.
(3)低厚度底模及抽屉式开合(3) Low thickness bottom mold and drawer type opening and closing
底模厚度小,水平开合,可充分利用混凝土箱梁和墩顶之间的有限空间。The bottom formwork is small in thickness and can be opened and closed horizontally, which can make full use of the limited space between the concrete box girder and the top of the pier.
(4)无支腿结构,投入减少,工序简化。(4) No outrigger structure, less investment and simplified process.
(5)预设拱度(5) Default camber
主梁设置了上拱,使混凝土梁体线型更好。The main beam is set with an upper arch to make the line shape of the concrete beam better.
(6)模板条件好(6) Template condition is good
模板块面大、接缝少、刚度大、间隙小,漏浆、错台、蜂窝麻面等质量隐患大为降低,成品梁内实外美。The formwork has large surface area, fewer joints, high rigidity, and small gaps, greatly reducing potential quality hazards such as slurry leakage, wrong platform, and honeycomb pockmarks, and the finished beam is solid inside and outside.
(7)刚度大、自重轻(7) High rigidity and light weight
(8)外模板作业少(8) Less external template work
通过操作主梁支承千斤顶即可自动脱模,主梁到达设计位置,则外模同步就位。减少了人工脱模、模板调整等工序。The mold can be automatically demoulded by operating the main beam supporting jack, and the outer mold will be in place synchronously when the main beam reaches the designed position. Reduce manual demoulding, template adjustment and other processes.
(9)作业面开阔(9) The working surface is wide
敞开式作业面,并配置可活动门机,钢筋、内模均可整体吊装,有利于缩短作业周期。The open working surface is equipped with a movable door machine, and the steel bars and inner molds can be hoisted as a whole, which is beneficial to shorten the working cycle.
附图说明Description of drawings
图1移动模架立面图Figure 1 Elevation view of mobile formwork
图2移动模架平面图Figure 2 Plane view of mobile formwork
图3a移动模架墩顶断面图(混凝土浇筑状态)Figure 3a Sectional view of the top of the mobile formwork pier (concrete pouring state)
图3b移动模架墩顶断面图(纵移状态)Figure 3b Sectional view of the pier top of the mobile formwork (in the longitudinal state)
图3c移动模架跨中断面图(混凝土浇筑状态)Figure 3c cross-sectional view of the mobile formwork (concrete pouring state)
图3d移动模架跨中断面图(脱模状态)Figure 3d cross-sectional view of the mobile formwork (demoulding state)
图4移动模架承重主梁断面图Figure 4 Sectional view of the load-bearing main beam of the mobile formwork
图5移动模架主梁连接构造图Figure 5 Mobile formwork main beam connection structure diagram
图6底模结构图Figure 6 Bottom mold structure diagram
图7a~图7d底模开合施工步骤图Figure 7a~Figure 7d Construction steps of bottom formwork opening and closing
图8~图16移动模架施工步骤图Figure 8-16 Construction steps of mobile formwork
图中:1-承重主梁,2-导梁,3-支承装置,4-模板系统,5-底模开合系统,6-纵横移系统,7-辅助结构。In the figure: 1-load-bearing main beam, 2-guide beam, 3-supporting device, 4-formwork system, 5-bottom mold opening and closing system, 6-vertical and lateral movement system, 7-auxiliary structure.
具体实施方式 Detailed ways
对照图1、图2,移动模架由承重主梁1、导梁2、支承装置3、模板系统4、底模开合系统5、纵横移系统6及辅助结构7组成。1 and 2, the mobile formwork is composed of load-bearing
对照图3a,移动模架主梁1通过支承装置3支承在墩顶上。辅助结构7的门吊布置在移动模架的上方。Referring to Fig. 3a, the
对照图3b,移动模架纵移时,底模4通过底模开合系统5水平开启,以避开墩顶的桥梁支座垫石。Referring to Fig. 3b, when the mobile formwork moves vertically, the
对照图3c,箱梁混凝土浇筑时,底模4用吊杆8吊挂在主梁1上;底模开启系统5附着在主梁1的一侧。Referring to Fig. 3c, when the concrete of the box girder is poured, the
对照图3d,脱模时,主梁1连同底模4一起下降,与混凝土箱梁脱离。Referring to Fig. 3d, when demoulding, the
对照图4,主梁1的顶板9及一侧的腹板10根据混凝土箱梁的形状倾斜布置。Referring to Fig. 4, the
对照图5,主梁1各制造节段之间的连接,用作模板面的承重梁1的顶板9及腹板10采用内法兰螺栓连接;其余的采用节点板剪力螺栓连接。Referring to Fig. 5, the connection between the manufacturing segments of the
对照图6,底模4采用低高度的正交异性板,其两侧布置滑道以便向一侧滑移开启。Referring to FIG. 6 , the
对照图7a,将底模开合系统5的液压油缸活塞杆伸出,并与底模4通过滑座连接。Referring to Fig. 7a, the piston rod of the hydraulic cylinder of the bottom mold opening and
对照图7b,将液压油缸的活塞杆缩回,拖动底模4向一侧水平滑移。Referring to Fig. 7b, the piston rod of the hydraulic cylinder is retracted, and the
对照图7c,底模开启至一半时,将液压油缸旋转180°并重新与底模4连接。Referring to Fig. 7c, when the bottom mold is half opened, the hydraulic cylinder is rotated 180° and connected with the
对照图7d,液压油缸顶推,将底模4继续向一侧滑移,直至完全开启。Referring to Fig. 7d, the hydraulic oil cylinder pushes and continues to slide the
对照图8,移动模架各部分结构在支架上安装成整体。With reference to Fig. 8, each part structure of mobile formwork is installed on the support as a whole.
对照图9,绑扎混凝土箱梁的钢筋,穿预应力束,浇筑箱梁混凝土并养护。Referring to Fig. 9, the steel bars of the concrete box girder are bound, the prestressed beams are worn, and the box girder concrete is poured and maintained.
对照图10,张拉混凝土箱梁的预应力束并锚固,灌浆、封锚。Referring to Figure 10, the prestressed beams of the tensioned concrete box girder are anchored, grouted, and anchored.
对照图11,移动模架整体下降脱模,安装纵横移系统6。Referring to Fig. 11, the mobile formwork is lowered and demoulded as a whole, and the longitudinal and
对照图12,启动纵横移系统6,牵引移动模架向前滑移。With reference to Fig. 12, start the longitudinal and
对照图13,移动模架纵移至下一跨施工位置。Referring to Fig. 13, the mobile formwork moves longitudinally to the next span construction position.
对照图14,继续混凝土箱梁的施工直至所有的混凝土箱梁完成。Referring to Figure 14, continue the construction of the concrete box girders until all the concrete box girders are completed.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2007101686102A CN101205702A (en) | 2007-12-05 | 2007-12-05 | Beam and mold combined mobile formwork |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2007101686102A CN101205702A (en) | 2007-12-05 | 2007-12-05 | Beam and mold combined mobile formwork |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN101205702A true CN101205702A (en) | 2008-06-25 |
Family
ID=39566164
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNA2007101686102A Pending CN101205702A (en) | 2007-12-05 | 2007-12-05 | Beam and mold combined mobile formwork |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101205702A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102691270A (en) * | 2012-06-27 | 2012-09-26 | 中铁四局集团机电设备安装有限公司 | Efficient and quick movable mould frame |
| CN104131515A (en) * | 2014-08-20 | 2014-11-05 | 中铁十九局集团第二工程有限公司 | Method for constructing cast-in-place box beam by means of movable formwork |
| CN112695650A (en) * | 2020-12-24 | 2021-04-23 | 保利长大工程有限公司 | Downward movable formwork method construction method for shoal variable-curve wide cast-in-place beam |
| CN113073556A (en) * | 2021-03-19 | 2021-07-06 | 中铁大桥局集团第一工程有限公司 | Descending type beam mold combination movable mold frame and construction method thereof |
| CN114525737A (en) * | 2022-03-03 | 2022-05-24 | 河南大学 | Bridge deck type movable formwork via hole braking system and braking method |
-
2007
- 2007-12-05 CN CNA2007101686102A patent/CN101205702A/en active Pending
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102691270A (en) * | 2012-06-27 | 2012-09-26 | 中铁四局集团机电设备安装有限公司 | Efficient and quick movable mould frame |
| CN104131515A (en) * | 2014-08-20 | 2014-11-05 | 中铁十九局集团第二工程有限公司 | Method for constructing cast-in-place box beam by means of movable formwork |
| CN112695650A (en) * | 2020-12-24 | 2021-04-23 | 保利长大工程有限公司 | Downward movable formwork method construction method for shoal variable-curve wide cast-in-place beam |
| CN113073556A (en) * | 2021-03-19 | 2021-07-06 | 中铁大桥局集团第一工程有限公司 | Descending type beam mold combination movable mold frame and construction method thereof |
| CN113073556B (en) * | 2021-03-19 | 2023-12-22 | 中铁大桥局集团第一工程有限公司 | Construction method of movable formwork of downlink beam formwork combination |
| CN114525737A (en) * | 2022-03-03 | 2022-05-24 | 河南大学 | Bridge deck type movable formwork via hole braking system and braking method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101117791B (en) | Combined mobile formwork base with special-shaped steel box and orthotropic plate bottom formwork and its construction method | |
| CN108442255A (en) | A mobile formwork bridge-building machine and a construction method for a cast-in-place bridge | |
| CN101581073B (en) | Downlink movable mould frame and walking method thereof | |
| CN104594918B (en) | Split integrated underground passage steel mold plate trolley and construction method thereof | |
| CN105155423A (en) | Upward moving type movable formwork for continuous box girder construction | |
| CN106120563A (en) | Cast-in-situ box girder Combined movable mould bases and construction method thereof | |
| CN103498421B (en) | A kind of mobile formwork of constructing for U-shaped water conservancy aqueduct | |
| CN101210419A (en) | Small radius curved concrete box girder construction machine with internal and external girder system and its construction method | |
| CN102140779A (en) | Movable cast-in-situ support and movable construction method of box girder cast-in-situ support | |
| CN204343173U (en) | A kind of Segmental assembling bridge-erecting machine | |
| CN104695335B (en) | Upstroke movable framework steel bar overall binding lifting construction engineering method and constructing device | |
| CN108098982B (en) | Hydraulic retraction internal mold for large-span precast box girder | |
| CN103526697B (en) | Self-propelled movable formwork for construction of double-rectangle water conservancy aqueduct | |
| WO2021031354A1 (en) | Method for movable formwork passing through hole, and device for movable formwork passing through hole | |
| CN205112063U (en) | Integral hydraulic pressure exterior sheathing of precast box girder | |
| CN205243003U (en) | Prefabricated U -shaped segment girder template of stub matching | |
| CN101205702A (en) | Beam and mold combined mobile formwork | |
| CN102225580B (en) | Method for longitudinally moving box girder internal mold | |
| CN202658529U (en) | Device for integrally hoisting and molding prefabricated reinforced bars for fabricating girders of high-speed rails in situ | |
| CN107829374B (en) | Construction Method of Mobile Formwork and Cantilever of Highway Prestressed Concrete Box Girder | |
| CN116219906B (en) | Asymmetric Variable Width Continuous Beam Hanging Formwork Device and Construction Method | |
| CN201132942Y (en) | Beam and mold combined mobile formwork | |
| CN205975365U (en) | Cast -in -situ box girder combined type moving die carrier | |
| CN117513185A (en) | A new type of continuous beam suspension cast-in-place bridge building machine | |
| CN102001127B (en) | Combined box girder hydraulic internal mould |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Open date: 20080625 |