CN101177933B - 桥梁拱肋吊运及支撑支架一体化施工方法及装置 - Google Patents
桥梁拱肋吊运及支撑支架一体化施工方法及装置 Download PDFInfo
- Publication number
- CN101177933B CN101177933B CN2007102027390A CN200710202739A CN101177933B CN 101177933 B CN101177933 B CN 101177933B CN 2007102027390 A CN2007102027390 A CN 2007102027390A CN 200710202739 A CN200710202739 A CN 200710202739A CN 101177933 B CN101177933 B CN 101177933B
- Authority
- CN
- China
- Prior art keywords
- column
- rib
- assembly unit
- lifting
- arch rib
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 17
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 238000005266 casting Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 2
- 230000010354 integration Effects 0.000 abstract 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 4
- 238000012545 processing Methods 0.000 description 3
- 238000013461 design Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000003028 elevating effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000001802 infusion Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种桥梁拱肋吊运及支撑支架一体化施工方法及装置,在拱肋拼装范围内安装立柱,在立柱上安装支撑牛腿,各段拱肋吊装后就位于牛腿上,在立柱顶部安装吊装横梁,吊装横梁上设置纵移轨道,在纵移轨道上安装天车,天车在吊装横梁上纵向移动,在天车上有横移轨道,横移轨道上设置横向移动的卷扬机,使得卷扬机在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。本发明将吊运和支撑的支架一体化,减少了吊运使用的设备,具有灵活方便、操作简单、工期短的优点,不再通过浮吊或吊车进行吊运,减少了设备和资金的投入,可以用于拱肋拼装以及各种桥梁吊装施工领域。
Description
技术领域
本发明涉及一种桥梁拱肋吊运及支撑支架一体化施工方法及装置,属于桥梁施工技术领域。
背景技术
钢拱桥或钢-混结合结构的桥梁,其钢构件通常是在工厂内加工制作,然后运至拼装现场,在工地进行拼装。现有技术中,拱肋的拼装,是在安装范围内搭设支撑支架,通过水面上的浮吊将运输驳船上的拱肋杆件起吊至拼装位置进行组拼。由于拱肋体积大、重量重,采用浮吊吊运存在一些缺点,浮吊不够灵活,操作复杂,施工时间长。而且如果拱桥的拱肋修建位置水位较浅,或有部分位置处于陆地上,浮吊的起重能力不够满足拱肋起吊、拼装要求,那么还需要增加吊车或龙门吊等陆地上的起吊设备进行吊运,施工更加复杂,加大了设备的投入并延长了拼装时间。
发明内容
本发明的目的在于:提供一种灵活方便、操作简单的桥梁拱肋吊运及支撑支架一体化施工方法及装置,以达到减少拱肋拼装的资金投入和工期。
本发明是这样实现的:桥梁拱肋吊运及支撑支架一体化施工方法,将拱肋支撑支架与吊装支架结合为一体,对拱肋进行吊装和支撑,具体做法是,在拱肋拼装范围内安装立柱,在立柱上安装支撑牛腿,各段拱肋吊装后就位于牛腿上,在立柱顶部安装吊装横梁,吊装横梁上设置纵移轨道,在纵移轨道上安装天车,天车在吊装横梁上纵向移动,在天车上有横移轨道,横移轨道上设置横向移动的卷扬机,使得卷扬机在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。
上述的桥梁拱肋吊运及支撑支架一体化施工方法,具体方法包括下述步骤,
a.在拱肋拼装范围内采用沉桩作为支撑桩;
b.预制桩的桩顶浇注钢筋砼承台,并预埋安装立柱用的底座钢板;
c.用钢管连接,制作成立柱,用浮吊或吊车将立柱安装到钢筋砼承台上,然后在立柱之间连接支撑桁架,对立柱进行纵横向的固定及支撑;
d.在立柱相应标高上安装支撑牛腿,各段拱肋吊装后就位于牛腿上;
e.用钢桁架拼装得到吊装横梁,将吊装横梁安装在立柱上方,在吊装横梁安装纵移轨道;
f.纵移轨道上安装天车,在天车上有横移轨道及卷扬机,使得卷扬机在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。
桥梁拱肋吊运及支撑支架一体化施工装置,它包括设置在拱肋拼装范围内的立柱,在立柱上安装支撑牛腿,在立柱顶部设有吊装横梁,吊装横梁上设有纵移轨道,纵向移动的天车设在纵移轨道上,在天车上设有横移轨道,横移轨道上设置横向移动的卷扬机。
上述的桥梁拱肋吊运及支撑支架一体化施工装置,吊装横梁由贝雷桁架拼装而成。
本发明在拱肋拼装范围内安装立柱,立柱上设置牛腿可以支撑各段拱肋的拼装,在立柱上安装横跨整个拼装范围的拼装横梁,在拼装横梁上设置天车,天车上的卷扬机可以在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。本发明将吊运和支撑的支架一体化,减少了吊运使用的设备,如浮吊、吊车和龙门吊等,能够节约吊运投入资金40~50%。采用的吊运方法更加灵活,拼装的周期也大大缩短,与现有采用浮吊或其他吊具相比,节省工期30~40%。因此同现有技术相比,本发明具有灵活方便、操作简单、工期短的优点,不再通过浮吊或吊车进行吊运,减少了设备和资金的投入,可以用于拱肋拼装以及各种桥梁吊装施工领域。
附图说明
附图1为本发明的结构示意图;
附图2为附图1中天车的A向示意图。
具体实施方式
本发明的实施例:如图1所示,桥梁拱肋的施工现场一部分为陆地,一部分在水上,在拱肋拼装范围内设置立柱1。见图2,立柱1可以排列成2排,将整个拼装范围包括进去,立柱1的数量和间距可根据设计确定,在立柱1的相应标高上安装支撑牛腿11,各段拱肋8吊装后就位于牛腿11上;在立柱1上安装吊装横梁2,吊装横梁2上设有纵移轨道3,天车4安装在纵移轨道3上,在天车4上设有横移轨道5,横移轨道5上设置横向移动的卷扬机6,通过卷扬机6将拱肋8吊运到各个拼装位置。为了更加稳定,在立柱1之间安装有用于纵横向联系及支撑的支撑桁架7。
本发明的具体施工步骤如下:
a.在拱肋拼装范围采用打桩锤沉桩作为支撑桩9,支撑桩9分别打入水底和陆地内,使得支撑桩9顶部保持水平。
b.在支撑桩9的桩顶浇注钢筋砼承台10,并预埋安装立柱1用的底座钢板。
c.采用钢管,按10.0m长节段进行加工制作,钢管接长用法兰盘或焊接连接,在现场逐节接长,制作成立柱1,在水中部分采用浮吊,陆上部分采用吊车安装,将立柱1安装到钢筋砼承台10上,然后在立柱1之间连接支撑桁架7,对立柱1进行纵横向的固定及支撑。支撑桁架7用型钢加工制作,支撑桁架7与钢管立柱1直接进行焊接连接。
d.在立柱1的相应标高上安装支撑牛腿11,各段拱肋8吊装后就位于牛腿11上。
e.用钢桁架拼装得到吊装横梁2,将吊装横梁2安装在立柱1上方,在吊装横梁2安装纵移轨道3。
f.纵移轨道3上安装天车4,在天车4上有横移轨道5及卷扬机6,使得卷扬机6在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋8至各个拼装位置。
Claims (3)
1.一种桥梁拱肋吊运及支撑支架一体化施工方法,其特征在于:将拱肋支撑支架与吊装支架结合为一体,对拱肋进行吊装和支撑,具体做法是,在拱肋拼装范围内安装立柱,在立柱之间连接支撑桁架,在立柱上安装支撑牛腿,各段拱肋吊装后就位于牛腿上,在立柱顶部安装吊装横梁,吊装横梁上设置纵移轨道,在纵移轨道上安装天车,天车在吊装横梁上纵向移动,在天车上有横移轨道,横移轨道上设置横向移动的卷扬机,使得卷扬机在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。
2.根据权利要求1所述的桥梁拱肋吊运及支撑支架一体化施工方法,其特征在于:它包括下述步骤,
a.在拱肋拼装范围内采用沉桩作为支撑桩;
b.预制桩的桩顶浇注钢筋砼承台,并预埋安装立柱用的底座钢板;
c.用钢管连接,制作成立柱,用浮吊或吊车将立柱安装到钢筋砼承台上,然后在立柱之间连接支撑桁架,对立柱进行纵横向的固定及支撑;
d.在立柱相应标高上安装支撑牛腿,各段拱肋吊装后就位于牛腿上;
e.用钢桁架拼装得到吊装横梁,将吊装横梁安装在立柱上方,在吊装横梁安装纵移轨道;
f.纵移轨道上安装天车,在天车上有横移轨道及卷扬机,使得卷扬机在整个拱肋拼装范围纵向、横向移动,方便吊运拱肋至各个拼装位置。
3.一种桥梁拱肋吊运及支撑支架一体化施工装置,它包括设置在拱肋拼装范围内的立柱,其特征在于:在立柱上安装支撑牛腿,在立柱顶部设有吊装横梁,吊装横梁上设有纵移轨道,纵向移动的天车设在纵移轨道上,在天车上设有横移轨道,横移轨道上设置横向移动的卷扬机,在立柱上安装有用于纵横向固定及支撑的支撑桁架。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007102027390A CN101177933B (zh) | 2007-11-28 | 2007-11-28 | 桥梁拱肋吊运及支撑支架一体化施工方法及装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007102027390A CN101177933B (zh) | 2007-11-28 | 2007-11-28 | 桥梁拱肋吊运及支撑支架一体化施工方法及装置 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101177933A CN101177933A (zh) | 2008-05-14 |
CN101177933B true CN101177933B (zh) | 2010-06-16 |
Family
ID=39404335
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2007102027390A Expired - Fee Related CN101177933B (zh) | 2007-11-28 | 2007-11-28 | 桥梁拱肋吊运及支撑支架一体化施工方法及装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101177933B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071646A (zh) * | 2010-12-31 | 2011-05-25 | 中铁大桥局集团第四工程有限公司 | 大吨位箱梁下海系统及施工方法 |
CN107893381A (zh) * | 2017-11-30 | 2018-04-10 | 中铁大桥局集团第二工程有限公司 | 一种双幅悬浇梁挂篮底模系统纵横滑移走行平台 |
CN109610329A (zh) * | 2018-12-18 | 2019-04-12 | 李建鑫 | 一种桥梁拱肋施工用一体化吊运装置 |
CN111335185A (zh) * | 2020-04-07 | 2020-06-26 | 中铁三局集团线桥工程有限公司 | 一种实现高度控制的大吨位箱梁架设施工系统及其架设方法 |
CN112302383A (zh) * | 2020-10-29 | 2021-02-02 | 中国建筑土木建设有限公司 | 一种可调节轻型多功能工业厂房体系及其施工方法 |
CN112520578A (zh) * | 2020-12-01 | 2021-03-19 | 中建八局第四建设有限公司 | 一种大跨度超重钢桁架梁浮船驳运的吊装施工方法 |
CN113235604B (zh) * | 2021-02-05 | 2023-04-07 | 中铁工程机械研究设计院有限公司 | 一种装配式建筑的盖板结构的架设施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2337186Y (zh) * | 1998-06-30 | 1999-09-08 | 曹阳 | 高架路砼桥面板吊装机 |
JP2001059208A (ja) * | 1999-08-23 | 2001-03-06 | Chiyoda Engineering Consultants Co Ltd | 鋼製アーチによる既設橋の補強工法 |
JP2004232296A (ja) * | 2003-01-29 | 2004-08-19 | Ishikawajima Harima Heavy Ind Co Ltd | アーチ橋及びアーチフレーム構造 |
WO2005083181A1 (en) * | 2004-02-27 | 2005-09-09 | Wardrop Engineering Inc. | Pre-cast stay-in-place deck form panel utilizing a pressure arch |
CN201128882Y (zh) * | 2007-11-28 | 2008-10-08 | 贵州省桥梁工程总公司 | 桥梁拱肋吊运及支撑支架一体化施工装置 |
-
2007
- 2007-11-28 CN CN2007102027390A patent/CN101177933B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2337186Y (zh) * | 1998-06-30 | 1999-09-08 | 曹阳 | 高架路砼桥面板吊装机 |
JP2001059208A (ja) * | 1999-08-23 | 2001-03-06 | Chiyoda Engineering Consultants Co Ltd | 鋼製アーチによる既設橋の補強工法 |
JP2004232296A (ja) * | 2003-01-29 | 2004-08-19 | Ishikawajima Harima Heavy Ind Co Ltd | アーチ橋及びアーチフレーム構造 |
WO2005083181A1 (en) * | 2004-02-27 | 2005-09-09 | Wardrop Engineering Inc. | Pre-cast stay-in-place deck form panel utilizing a pressure arch |
CN201128882Y (zh) * | 2007-11-28 | 2008-10-08 | 贵州省桥梁工程总公司 | 桥梁拱肋吊运及支撑支架一体化施工装置 |
Also Published As
Publication number | Publication date |
---|---|
CN101177933A (zh) | 2008-05-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101177933B (zh) | 桥梁拱肋吊运及支撑支架一体化施工方法及装置 | |
CN202245617U (zh) | 一种采用组合式井架组装的电梯井道壁 | |
CN101736699B (zh) | 全支架钢箱梁滑移精确定位方法 | |
CN101549836B (zh) | 封闭厂房内吊装超高超重设备的方法和专用吊具 | |
CN103352428A (zh) | 悬索桥索塔横梁无支架施工方法 | |
CN107178042A (zh) | 一种大跨度倒三角型钢管混凝土拱桥钢拱的施工方法 | |
CN211143305U (zh) | 一种钢结构建筑物 | |
CN103866693A (zh) | 一种钢筋混凝土系杆拱桥拱肋的安装方法及吊装辅桥 | |
CN202658590U (zh) | 整体装配式钻孔平台 | |
CN201560397U (zh) | 用于钢箱梁精确定位安装的全支架 | |
CN104314009B (zh) | 大节段提升机构及使用方法 | |
CN111560837A (zh) | 升降式跨河桥结构及其使用方法 | |
CN102777050B (zh) | 大跨度管桁架屋面梁的组拼胎架 | |
CN201128882Y (zh) | 桥梁拱肋吊运及支撑支架一体化施工装置 | |
CN102372228B (zh) | 大跨度吊车梁平移安装方法 | |
KR101450229B1 (ko) | 거더 거치방법 | |
CN105625732A (zh) | 超高悬挑钢结构桁架无支撑施工方法 | |
CN215925689U (zh) | 一种拱桥钢管拱肋安装支架 | |
CN107217669B (zh) | 拔桩设备及其快速移动方法 | |
CN216515141U (zh) | 一种新悬挑施工爬模装置 | |
CN201943006U (zh) | 辅助不变幅架梁吊机架设钢箱梁用主塔区活动支架 | |
CN202247682U (zh) | 一种遮板安装桥吊 | |
CN210262748U (zh) | 钢箱梁顶推施工悬臂支承结构 | |
CN203923923U (zh) | 高墩钢桁梁架设门式提升站 | |
CN210683047U (zh) | 适用于大型构件的装卸车装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100616 |
|
CF01 | Termination of patent right due to non-payment of annual fee |