CN100420798C - 一种静力挤压混凝土桩的施工方法 - Google Patents

一种静力挤压混凝土桩的施工方法 Download PDF

Info

Publication number
CN100420798C
CN100420798C CNB2006100254376A CN200610025437A CN100420798C CN 100420798 C CN100420798 C CN 100420798C CN B2006100254376 A CNB2006100254376 A CN B2006100254376A CN 200610025437 A CN200610025437 A CN 200610025437A CN 100420798 C CN100420798 C CN 100420798C
Authority
CN
China
Prior art keywords
outer tube
masonry
concrete
pile
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006100254376A
Other languages
English (en)
Other versions
CN1837505A (zh
Inventor
梁毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006100254376A priority Critical patent/CN100420798C/zh
Publication of CN1837505A publication Critical patent/CN1837505A/zh
Application granted granted Critical
Publication of CN100420798C publication Critical patent/CN100420798C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种静力挤压混凝土桩的施工方法,包括以下步骤:(一)将具有内管、外管的护筒用油压机的静压油缸压至设计深度;(二)提起内管,向外管内填充砖石;(三)压下内管,挤压外管内的砖石;(四)重复步骤(二)、(三)反复挤压砖石,在外管底部周围形成砖石扩大头,达到设计压力时停止挤压,提起内管;(五)在外管内放置钢筋笼,浇注混凝土;(六)用内管顶住混凝土将外管提起,完成混凝土桩制作。这种施工方法噪音低、无震动,成桩后在提起外管过程中的不会发生断桩、缩颈现象,提高了混凝土桩的质量。

Description

一种静力挤压混凝土桩的施工方法
技术领域
本发明涉及土木工程基础加固技术,尤其是混凝土桩的施工方法。
背景技术
现有混凝土桩的施工方法通常采用利用钢丝绳向下拉压护筒和重锤锤击桩孔内填充砖石将护筒沉入地下,反复锤击、填充砖石后,所填充的砖、石沉入桩孔底部形成扩大头,然后放置钢筋笼,浇注混凝土,提起护筒即完成施工。申请号为00106288.3、200310115400.9、200410030741.0的专利文献中公开的混凝土桩施工都使用重锤锤击桩孔内的填充料对护筒底端的地基土体进行密实加固,形成扩大头以满足承载要求。这些施工方法由于都需使用重锤锤击,因此会产生很大的噪音和震动、影响周围人们的工作和休息,而且桩身形成后直接用外力提起护筒,易产生断桩、缩颈等现象。
发明内容
为克服现有混凝土桩的施工方法存在的不足,本发明提供一种静力挤压混凝土桩的施工方法,以油压机静压油缸静压的方法将具有内管和外管的的护筒压入地下,不用重锤锤击,噪音和震动大大降低,利用内管顶住混凝土桩身提起外管,不会在提桩过程中发生断桩、缩颈现象。
本发明提供的一种静力挤压混凝土桩的施工方法的技术方案是这样的:
(一)在桩机(4)就位处,按设计桩长,将具有内管(6)和外管(7)的护筒利用油压机的静压油缸(2)的压力同时压入地基内至设计深度,其中内管(6)上端与连接静压油缸活塞杆(3)的压桩头(5)的底面相接,外管(7)上端的绞耳连接桩机(4)的卷扬机的钢丝绳,内管(6)的下端制成锥形头;
(二)利用桩机(4)的卷扬机将内管(6)提起至外管(7)投料口以上,并从投料口向外管(7)内填充砖石(8);
(三)利用油压机静压油缸(2)的压力压下内管(6),挤压外管(7)内的砖石(8);
(四)重复上述步骤(二)、(三)反复挤压砖石(8),在外管(7)底部周围形成砖石扩大头(9),当压力表上显示压力达到设计值时停业挤压,用卷扬机提起内管(6);
(五)在外管(7)内放置钢筋笼,浇注混凝土;
(六)当混凝土浇至指定标高时,用受到静压油缸(2)向下压力的内管(6)顶住混凝土后利用桩机(4)的卷扬机将外管(7)提起,完成混凝土桩制作。
本发明的有益效果是:以油压机静压油缸静压的方法将具有内管和外管的护筒压入地下,不用重锤锤击,噪音和震动大大降低,不会影响周围人们的工作和休息,混凝土桩身形成后,利用内管顶住桩身提起外管,不会在提管过程中发生断桩、缩颈现象,提高了成桩质量。
附图说明
图1是本发明的各个步骤示意图和实施本发明的设备结构示意图。
在图1中,a.利用油压机油缸静压具有内管、外管的护筒成孔,b.提起内管并在外管中填充砖石,c.用内管反复挤压砖石在外管底部周围形成砖石扩大头,d.提起内管在外管内放置钢筋笼、浇注混凝土,e.在提外管时用内管顶住混凝土,f.提升内管、外管,完成施工;1.桩机架上的滑栓机构,2.静压油缸,3.活塞杆,4.桩机,5.压桩头,6.内管,7.外管,8.砖石,9.砖石扩大头,10.混凝土桩。
具体实施方式
图1所示也是实施本发明的方式,包括以下步骤;
a.在桩机(4)就位处利用油压机静压油缸(2)将内管(6)和外管(7)同时压下至设计深度形成桩孔;b.提起内管(6),在外管(7)中填充砖石(8);c.用内管(6)反复挤压砖石(8)后在外管(7)底部形成砖石扩大头(9),当压力表上显示压力达到设计值时停止挤压;d.用卷扬机提起的内管(6),在外管(7)内放置钢筋笼,浇注混凝土;e.在提外管(7)时用内管(6)顶住混凝土;f.提升内管(6)、外管(7)制成混凝土桩(10),完成施工。

Claims (1)

1. 一种静力挤压混凝土桩的施工方法,其特征在于:
(一)在桩机就位处,按设计桩长,将具有内管和外管的护筒利用油压机的静压油缸的压力同时压入地基内至设计深度,其中内管上端与连接静压油缸活塞杆的压桩头的底面相接,外管上端的绞耳连接桩机的卷扬机的钢丝绳,内管的下端制成锥形头;
(二)利用桩机的卷扬机将内管提起至外管投料口以上,并从投料口向外管内填充砖石;
(三)利用油压机静压油缸的压力压下内管,挤压外管内的砖石;
(四)重复上述步骤(二)、(三)反复挤压砖石,在外管底部周围形成砖石扩大头,当压力表上显示压力达到设计值时停止挤压,用卷扬机提起内管;
(五)在外管内放置钢筋笼,浇注混凝土;
(六)当混凝土浇至指定标高时,用受到静压油缸向下压力的内管顶住混凝土后利用桩机的卷扬机将外管提起,完成混凝土桩制作。
CNB2006100254376A 2006-04-03 2006-04-03 一种静力挤压混凝土桩的施工方法 Expired - Fee Related CN100420798C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100254376A CN100420798C (zh) 2006-04-03 2006-04-03 一种静力挤压混凝土桩的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100254376A CN100420798C (zh) 2006-04-03 2006-04-03 一种静力挤压混凝土桩的施工方法

Publications (2)

Publication Number Publication Date
CN1837505A CN1837505A (zh) 2006-09-27
CN100420798C true CN100420798C (zh) 2008-09-24

Family

ID=37015002

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100254376A Expired - Fee Related CN100420798C (zh) 2006-04-03 2006-04-03 一种静力挤压混凝土桩的施工方法

Country Status (1)

Country Link
CN (1) CN100420798C (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126239B (zh) * 2007-09-14 2010-06-02 张立军 一种混凝土桩基的施工装置及施工工艺
CN104099925A (zh) * 2014-07-25 2014-10-15 王继忠 混凝土桩的施工装置及其施工方法
CN105649074B (zh) * 2016-03-22 2019-09-03 沙焕焕 管桩挤扩砼劲性复合桩及其施工方法
CN109680687B (zh) * 2019-01-17 2021-02-05 江西联保工程咨询有限公司 一种桩台一体成型的施工工艺

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59118924A (ja) * 1982-12-23 1984-07-09 Komatsu Ltd 鋼矢板の圧入方法
JPS59146832A (ja) * 1983-01-15 1984-08-22 アプスレ−・メタルズ・リミテッド タイヤ−組立装置および方法
CN2177045Y (zh) * 1993-12-25 1994-09-14 张俊生 分支承力盘承载桩孔成型机
CN1172194A (zh) * 1996-07-31 1998-02-04 杨文杰 钢筋混凝土夯扩灌注桩成桩工艺及其工具

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59118924A (ja) * 1982-12-23 1984-07-09 Komatsu Ltd 鋼矢板の圧入方法
JPS59146832A (ja) * 1983-01-15 1984-08-22 アプスレ−・メタルズ・リミテッド タイヤ−組立装置および方法
CN2177045Y (zh) * 1993-12-25 1994-09-14 张俊生 分支承力盘承载桩孔成型机
CN1172194A (zh) * 1996-07-31 1998-02-04 杨文杰 钢筋混凝土夯扩灌注桩成桩工艺及其工具

Also Published As

Publication number Publication date
CN1837505A (zh) 2006-09-27

Similar Documents

Publication Publication Date Title
CN102733376B (zh) 复合桩及其施工方法
CN201280720Y (zh) 小直径自平衡根键灌注桩根键顶推装置
CN104074186B (zh) 一种建筑地基中成孔的护筒装置及其施工方法
CN106168027A (zh) 振动锤设备和采用该振动锤设备的振压式桩体施工方法
CN101298772B (zh) 静压沉管扩底混凝土桩的施工方法
CN101831908A (zh) 大直径超深度静压单管沉管夯扩灌注桩施工工艺及设备
CN102733377A (zh) 混凝土桩的施工方法
CN100420798C (zh) 一种静力挤压混凝土桩的施工方法
CN101936004A (zh) 一种预制挤扩桩及其施工方法与施工机械设备
CN104929125A (zh) 一种载体桩的施工设备及其施工方法
CN102635110B (zh) 混凝土桩的施工方法
CN101298771A (zh) 静压沉管扩底混凝土桩施工方法及其静力压桩机
CN201943069U (zh) 一种预制挤扩桩
CN102733379B (zh) 混凝土桩的施工方法
CN109853564A (zh) 一种挤密桩的施工方法及专用內夯管锤
CN112240022A (zh) 一种静压沉管桩的施工方法及施工设备
CN2892969Y (zh) 一种静压桩机的沉管扩底装置
CN2804178Y (zh) 液压静力引孔及挤压桩装置
CN201762705U (zh) 一种预制挤扩桩
CN101016744A (zh) 非挤土沉管灌注桩的施工方法及装置
CN109944238A (zh) 全套管全回转内夯桩施工方法
CN109339044A (zh) 一种混凝土管桩施工设备
CN113187026B (zh) 一体化预制泵站沉井施工方法及加固模具
CN110080314B (zh) 一种减小桩基侧摩阻力的方法
CN101343877A (zh) 钻压灌注混凝土载体桩的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080924

Termination date: 20150403

EXPY Termination of patent right or utility model