CN100410455C - Strong rammer treatment high-water content foundation soil auxiliary construction process - Google Patents

Strong rammer treatment high-water content foundation soil auxiliary construction process Download PDF

Info

Publication number
CN100410455C
CN100410455C CNB2006101158728A CN200610115872A CN100410455C CN 100410455 C CN100410455 C CN 100410455C CN B2006101158728 A CNB2006101158728 A CN B2006101158728A CN 200610115872 A CN200610115872 A CN 200610115872A CN 100410455 C CN100410455 C CN 100410455C
Authority
CN
China
Prior art keywords
foundation soil
water content
quicklime
construction process
auxiliary construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2006101158728A
Other languages
Chinese (zh)
Other versions
CN1932168A (en
Inventor
毛心焰
程淑蒂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2006101158728A priority Critical patent/CN100410455C/en
Publication of CN1932168A publication Critical patent/CN1932168A/en
Application granted granted Critical
Publication of CN100410455C publication Critical patent/CN100410455C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to an auxiliary construction process for treating foundation soil with high water content by utilizing dynamic consolidation method. It is characterized by that in the high water-content foundation soil interior firstly the quicklime or other water-absorbing material can be used, and made into the uniformly-distributed lime-soil piles or lime-soil piers, then the dynamic consolidation process can be made.

Description

The auxiliary construction process of strong rammer treatment high-water content foundation soil
Affiliated technical field
The present invention relates to a kind of processing method, especially to high-moisture silty clay Measures for Making Ground and Foundation method to building lot.
Background technology
The processing method of building lot, according to different building requirements and ground soil property characteristics many kinds are arranged, strong ram be a kind of weight hold high ram method for processing foundation, by improving the soil compactness, reducing compressibility of Soil, increase substantially foundation capability, because cost is low, speed is fast, is called as the method for processing foundation of getting twice the result with half the effort.Yet on many foundation soil water content soil with high, dynamic compaction but is restricted, and reason is often to cause foundation soil to become " spongy soil " after strong the rammer, has to adopt the higher piling method of cost.
Summary of the invention
The present invention is exactly the auxiliary construction process at a kind of strong rammer treatment high-water content foundation soil of the shortcoming design of prior art, after adopting this technology, can use the Treatment by Dynamic Compaction ground on the ground of high-moisture, technology is easy to be reliable, reduce cost, accelerate the duration.
The technical solution adopted for the present invention to solve the technical problems is: the auxiliary construction process that designs a kind of strong rammer treatment high-water content foundation soil: make equally distributed ash stake or grey pier with quicklime or other absorbent material earlier in the high-moisture foundation soil, and then ram by force.With the ash stake that quicklime is made, be that to make a call to a diameter earlier in the high-moisture foundation soil be 180~400 millimeters, the degree of depth is 1~5 meter stake hole, tamps quicklime then in the stake hole, the interval in a hole be generally 0.7~1.5 meter uniform.And with the grey pier that quicklime is made, then be that to make a call to a diameter earlier in the high-moisture foundation soil be 0.5~1 meter, the degree of depth is generally 1~2 meter pier hole, tamps quicklime then in the pier hole, the interval in pier hole be generally 2~3 meters uniform.
The invention has the beneficial effects as follows,, expanded the accommodation of strong rammer Ground Treatment because the strong absorptive of quicklime when treated high-moisture ground rams by force again, the situation that foundation soil becomes " spongy soil " can not occur again.
The specific embodiment
One. near on the saturated silty clay foundation soil, 300 millimeters of diameters are suppressed at 1 meter at every interval earlier in water content, and quicklime is tamped in dark 3 meters stake hole then in the stake hole, ram by force again.Characteristic value of foundation bearing capacity after the processing is 180KPa.
Two. having on the saturated silty clay foundation soil of five meters saturated yielding soil layers, 2 meters at every interval, earlier ramming out the degree of depth with the hammer ram of 0.6 meter of diameter is 1 meter Dun Keng, tamps quicklime then in pier is cheated, and rams by force again.Characteristic value of foundation bearing capacity after the processing is 200KPa.

Claims (3)

1. the auxiliary construction process of a strong rammer treatment high-water content foundation soil is characterized in that: make equally distributed ash stake or grey pier with quicklime earlier in the high-moisture foundation soil, and then ram by force.
2. the auxiliary construction process of strong rammer treatment high-water content foundation soil as claimed in claim 1, it is characterized in that: with the ash stake of quicklime making, be that earlier to make a call to a diameter in the high-moisture foundation soil be 180~400 millimeters, the degree of depth is 1~5 meter stake hole, in the stake hole, tamp quicklime then, the stake hole be spaced apart 0.7~1.5 meter uniform.
3. the auxiliary construction process of strong rammer treatment high-water content foundation soil as claimed in claim 1, it is characterized in that: with the grey pier of quicklime making, be that earlier to make a call to a diameter in the high-moisture foundation soil be 0.5~1 meter, the degree of depth is 1~2 meter pier hole, in the pier hole, tamp quicklime then, the pier hole be spaced apart 2~3 meters uniform.
CNB2006101158728A 2006-08-14 2006-08-14 Strong rammer treatment high-water content foundation soil auxiliary construction process Expired - Fee Related CN100410455C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006101158728A CN100410455C (en) 2006-08-14 2006-08-14 Strong rammer treatment high-water content foundation soil auxiliary construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006101158728A CN100410455C (en) 2006-08-14 2006-08-14 Strong rammer treatment high-water content foundation soil auxiliary construction process

Publications (2)

Publication Number Publication Date
CN1932168A CN1932168A (en) 2007-03-21
CN100410455C true CN100410455C (en) 2008-08-13

Family

ID=37878183

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006101158728A Expired - Fee Related CN100410455C (en) 2006-08-14 2006-08-14 Strong rammer treatment high-water content foundation soil auxiliary construction process

Country Status (1)

Country Link
CN (1) CN100410455C (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101560760B (en) * 2009-05-22 2010-11-10 中冶京唐建设有限公司 Construction method for fast concreting and dredging and filling ultra-fine earth foundation
CN102359101A (en) * 2011-07-28 2012-02-22 江苏建筑职业技术学院 Foundation treatment method for collapsible soil
CN102635044B (en) * 2012-04-27 2014-07-09 滦南交通建设开发公司 Treating method of dynamic compacter for excavation roadbed
CN111140199A (en) * 2019-12-25 2020-05-12 北京正和恒基滨水生态环境治理股份有限公司 Shaft plugging method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57158415A (en) * 1981-03-24 1982-09-30 Yokoyama Kiso Kogyo Kk Method of improving construction for soft ground
JPS5876608A (en) * 1981-10-30 1983-05-09 Wakachiku Kensetsu Kk Method of amending soft ground using quicklime
CN1093766A (en) * 1993-04-14 1994-10-19 广州市经济技术开发区管理委员会 Soft-clay lime deep-layer consolidation method
CN1326033A (en) * 2000-05-25 2001-12-12 关伟伯 Soil compacting method and its special machine and tool

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57158415A (en) * 1981-03-24 1982-09-30 Yokoyama Kiso Kogyo Kk Method of improving construction for soft ground
JPS5876608A (en) * 1981-10-30 1983-05-09 Wakachiku Kensetsu Kk Method of amending soft ground using quicklime
CN1093766A (en) * 1993-04-14 1994-10-19 广州市经济技术开发区管理委员会 Soft-clay lime deep-layer consolidation method
CN1326033A (en) * 2000-05-25 2001-12-12 关伟伯 Soil compacting method and its special machine and tool

Also Published As

Publication number Publication date
CN1932168A (en) 2007-03-21

Similar Documents

Publication Publication Date Title
CN101591904B (en) Method for strengthening composite pile foundation by prepressing drainage and following grouting for drainage body
CN104131555B (en) A kind of outsourcing water penetration concrete reinforced pipe crushed stone grouting pile and construction method thereof
CN100359100C (en) Method for treating soft foundition by fast 'high vacuum impacting dense, pile base' compound method
CN101220589B (en) Soil engineering bag and method for dynamically squeezing and synthetically reinforcing soft groundwork
CN103233454A (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN100410455C (en) Strong rammer treatment high-water content foundation soil auxiliary construction process
CN102251512A (en) Construction method for compacting high loess-filled embankment by combining vibration roller compaction with dynamic compaction
CN101736738A (en) Pressure resistance and pull-out resistance grouted gravel pile
CN100427687C (en) Slope support method by compacting soil-lime to form cushion solid
CN101899838B (en) Bottom-grouting-enlarged small-diameter prestressed tubular pile composite foundation construction method
CN101660307A (en) Treatment method of collapsible loess foundation
CN100535256C (en) Strong ramming semi-replacement construction technique
CN100572688C (en) The method of consolidating soft soil ground foundation by dynamic pre drainage consolidation
CN101634139B (en) Dynamic compaction method for backfill foundation with drainage layer
CN201436323U (en) Drainage structure of dynamic compaction foundation
CN101736730A (en) Mixed reinforcement method of high-fill sand foundation
CN109667260A (en) A kind of reinforcement system and its construction method based on soft foundation discharge fixing
CN102605761A (en) Layering and humidifying construction method of foundation soil mass sand well
CN107313468A (en) A kind of seepage proof curtain for releasing collapsible loess foundation settlement by soaking is with level every infiltration level structure and method
CN111535306B (en) Microbial curing method and irrigation and drainage device suitable for marine soft soil foundation
CN204530685U (en) A kind of cement-soil stiff composite pile
CN201981530U (en) Down hole deep dynamic compaction pile in collapsible loess area
CN106337409A (en) Method for treating peat soil foundation through preloading in combination with salt piles
CN112144338A (en) Roadbed construction method of peat soil foundation
CN207092156U (en) A kind of seepage proof curtain for releasing collapsible loess foundation settlement by soaking is with level every infiltration level structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080813

Termination date: 20160814