CN100410455C - Strong rammer treatment high-water content foundation soil auxiliary construction process - Google Patents
Strong rammer treatment high-water content foundation soil auxiliary construction process Download PDFInfo
- Publication number
- CN100410455C CN100410455C CNB2006101158728A CN200610115872A CN100410455C CN 100410455 C CN100410455 C CN 100410455C CN B2006101158728 A CNB2006101158728 A CN B2006101158728A CN 200610115872 A CN200610115872 A CN 200610115872A CN 100410455 C CN100410455 C CN 100410455C
- Authority
- CN
- China
- Prior art keywords
- foundation soil
- water content
- quicklime
- construction process
- auxiliary construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The present invention relates to an auxiliary construction process for treating foundation soil with high water content by utilizing dynamic consolidation method. It is characterized by that in the high water-content foundation soil interior firstly the quicklime or other water-absorbing material can be used, and made into the uniformly-distributed lime-soil piles or lime-soil piers, then the dynamic consolidation process can be made.
Description
Affiliated technical field
The present invention relates to a kind of processing method, especially to high-moisture silty clay Measures for Making Ground and Foundation method to building lot.
Background technology
The processing method of building lot, according to different building requirements and ground soil property characteristics many kinds are arranged, strong ram be a kind of weight hold high ram method for processing foundation, by improving the soil compactness, reducing compressibility of Soil, increase substantially foundation capability, because cost is low, speed is fast, is called as the method for processing foundation of getting twice the result with half the effort.Yet on many foundation soil water content soil with high, dynamic compaction but is restricted, and reason is often to cause foundation soil to become " spongy soil " after strong the rammer, has to adopt the higher piling method of cost.
Summary of the invention
The present invention is exactly the auxiliary construction process at a kind of strong rammer treatment high-water content foundation soil of the shortcoming design of prior art, after adopting this technology, can use the Treatment by Dynamic Compaction ground on the ground of high-moisture, technology is easy to be reliable, reduce cost, accelerate the duration.
The technical solution adopted for the present invention to solve the technical problems is: the auxiliary construction process that designs a kind of strong rammer treatment high-water content foundation soil: make equally distributed ash stake or grey pier with quicklime or other absorbent material earlier in the high-moisture foundation soil, and then ram by force.With the ash stake that quicklime is made, be that to make a call to a diameter earlier in the high-moisture foundation soil be 180~400 millimeters, the degree of depth is 1~5 meter stake hole, tamps quicklime then in the stake hole, the interval in a hole be generally 0.7~1.5 meter uniform.And with the grey pier that quicklime is made, then be that to make a call to a diameter earlier in the high-moisture foundation soil be 0.5~1 meter, the degree of depth is generally 1~2 meter pier hole, tamps quicklime then in the pier hole, the interval in pier hole be generally 2~3 meters uniform.
The invention has the beneficial effects as follows,, expanded the accommodation of strong rammer Ground Treatment because the strong absorptive of quicklime when treated high-moisture ground rams by force again, the situation that foundation soil becomes " spongy soil " can not occur again.
The specific embodiment
One. near on the saturated silty clay foundation soil, 300 millimeters of diameters are suppressed at 1 meter at every interval earlier in water content, and quicklime is tamped in dark 3 meters stake hole then in the stake hole, ram by force again.Characteristic value of foundation bearing capacity after the processing is 180KPa.
Two. having on the saturated silty clay foundation soil of five meters saturated yielding soil layers, 2 meters at every interval, earlier ramming out the degree of depth with the hammer ram of 0.6 meter of diameter is 1 meter Dun Keng, tamps quicklime then in pier is cheated, and rams by force again.Characteristic value of foundation bearing capacity after the processing is 200KPa.
Claims (3)
1. the auxiliary construction process of a strong rammer treatment high-water content foundation soil is characterized in that: make equally distributed ash stake or grey pier with quicklime earlier in the high-moisture foundation soil, and then ram by force.
2. the auxiliary construction process of strong rammer treatment high-water content foundation soil as claimed in claim 1, it is characterized in that: with the ash stake of quicklime making, be that earlier to make a call to a diameter in the high-moisture foundation soil be 180~400 millimeters, the degree of depth is 1~5 meter stake hole, in the stake hole, tamp quicklime then, the stake hole be spaced apart 0.7~1.5 meter uniform.
3. the auxiliary construction process of strong rammer treatment high-water content foundation soil as claimed in claim 1, it is characterized in that: with the grey pier of quicklime making, be that earlier to make a call to a diameter in the high-moisture foundation soil be 0.5~1 meter, the degree of depth is 1~2 meter pier hole, in the pier hole, tamp quicklime then, the pier hole be spaced apart 2~3 meters uniform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006101158728A CN100410455C (en) | 2006-08-14 | 2006-08-14 | Strong rammer treatment high-water content foundation soil auxiliary construction process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006101158728A CN100410455C (en) | 2006-08-14 | 2006-08-14 | Strong rammer treatment high-water content foundation soil auxiliary construction process |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1932168A CN1932168A (en) | 2007-03-21 |
CN100410455C true CN100410455C (en) | 2008-08-13 |
Family
ID=37878183
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006101158728A Expired - Fee Related CN100410455C (en) | 2006-08-14 | 2006-08-14 | Strong rammer treatment high-water content foundation soil auxiliary construction process |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100410455C (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101560760B (en) * | 2009-05-22 | 2010-11-10 | 中冶京唐建设有限公司 | Construction method for fast concreting and dredging and filling ultra-fine earth foundation |
CN102359101A (en) * | 2011-07-28 | 2012-02-22 | 江苏建筑职业技术学院 | Foundation treatment method for collapsible soil |
CN102635044B (en) * | 2012-04-27 | 2014-07-09 | 滦南交通建设开发公司 | Treating method of dynamic compacter for excavation roadbed |
CN111140199A (en) * | 2019-12-25 | 2020-05-12 | 北京正和恒基滨水生态环境治理股份有限公司 | Shaft plugging method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57158415A (en) * | 1981-03-24 | 1982-09-30 | Yokoyama Kiso Kogyo Kk | Method of improving construction for soft ground |
JPS5876608A (en) * | 1981-10-30 | 1983-05-09 | Wakachiku Kensetsu Kk | Method of amending soft ground using quicklime |
CN1093766A (en) * | 1993-04-14 | 1994-10-19 | 广州市经济技术开发区管理委员会 | Soft-clay lime deep-layer consolidation method |
CN1326033A (en) * | 2000-05-25 | 2001-12-12 | 关伟伯 | Soil compacting method and its special machine and tool |
-
2006
- 2006-08-14 CN CNB2006101158728A patent/CN100410455C/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS57158415A (en) * | 1981-03-24 | 1982-09-30 | Yokoyama Kiso Kogyo Kk | Method of improving construction for soft ground |
JPS5876608A (en) * | 1981-10-30 | 1983-05-09 | Wakachiku Kensetsu Kk | Method of amending soft ground using quicklime |
CN1093766A (en) * | 1993-04-14 | 1994-10-19 | 广州市经济技术开发区管理委员会 | Soft-clay lime deep-layer consolidation method |
CN1326033A (en) * | 2000-05-25 | 2001-12-12 | 关伟伯 | Soil compacting method and its special machine and tool |
Also Published As
Publication number | Publication date |
---|---|
CN1932168A (en) | 2007-03-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101591904B (en) | Method for strengthening composite pile foundation by prepressing drainage and following grouting for drainage body | |
CN104131555B (en) | A kind of outsourcing water penetration concrete reinforced pipe crushed stone grouting pile and construction method thereof | |
CN100359100C (en) | Method for treating soft foundition by fast 'high vacuum impacting dense, pile base' compound method | |
CN101220589B (en) | Soil engineering bag and method for dynamically squeezing and synthetically reinforcing soft groundwork | |
CN103233454A (en) | Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation | |
CN100410455C (en) | Strong rammer treatment high-water content foundation soil auxiliary construction process | |
CN102251512A (en) | Construction method for compacting high loess-filled embankment by combining vibration roller compaction with dynamic compaction | |
CN101736738A (en) | Pressure resistance and pull-out resistance grouted gravel pile | |
CN100427687C (en) | Slope support method by compacting soil-lime to form cushion solid | |
CN101899838B (en) | Bottom-grouting-enlarged small-diameter prestressed tubular pile composite foundation construction method | |
CN101660307A (en) | Treatment method of collapsible loess foundation | |
CN100535256C (en) | Strong ramming semi-replacement construction technique | |
CN100572688C (en) | The method of consolidating soft soil ground foundation by dynamic pre drainage consolidation | |
CN101634139B (en) | Dynamic compaction method for backfill foundation with drainage layer | |
CN201436323U (en) | Drainage structure of dynamic compaction foundation | |
CN101736730A (en) | Mixed reinforcement method of high-fill sand foundation | |
CN109667260A (en) | A kind of reinforcement system and its construction method based on soft foundation discharge fixing | |
CN102605761A (en) | Layering and humidifying construction method of foundation soil mass sand well | |
CN107313468A (en) | A kind of seepage proof curtain for releasing collapsible loess foundation settlement by soaking is with level every infiltration level structure and method | |
CN111535306B (en) | Microbial curing method and irrigation and drainage device suitable for marine soft soil foundation | |
CN204530685U (en) | A kind of cement-soil stiff composite pile | |
CN201981530U (en) | Down hole deep dynamic compaction pile in collapsible loess area | |
CN106337409A (en) | Method for treating peat soil foundation through preloading in combination with salt piles | |
CN112144338A (en) | Roadbed construction method of peat soil foundation | |
CN207092156U (en) | A kind of seepage proof curtain for releasing collapsible loess foundation settlement by soaking is with level every infiltration level structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20080813 Termination date: 20160814 |