CH670124A5 - - Google Patents

Download PDF

Info

Publication number
CH670124A5
CH670124A5 CH199888A CH199888A CH670124A5 CH 670124 A5 CH670124 A5 CH 670124A5 CH 199888 A CH199888 A CH 199888A CH 199888 A CH199888 A CH 199888A CH 670124 A5 CH670124 A5 CH 670124A5
Authority
CH
Switzerland
Prior art keywords
sleeve
pile system
sleeve pile
piles
cone
Prior art date
Application number
CH199888A
Other languages
German (de)
Inventor
Norbert Sint
Original Assignee
Universale Grundbau Ges Mbh
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Universale Grundbau Ges Mbh filed Critical Universale Grundbau Ges Mbh
Publication of CH670124A5 publication Critical patent/CH670124A5/de

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

BESCHREIBUNG Die Erfindung betrifft ein auf Druck und bzw. oder Zug belastbares Hülsenpfahlsystem, das aus einzelnen Hülsenpfählen besteht, die durch Kupplungsstücke verbunden sind, wobei der unterste Hülsenpfahl eine Rammspitze trägt. DESCRIPTION The invention relates to a tubular pile system which can be subjected to pressure and / or tensile stress and which consists of individual tubular piles which are connected by coupling pieces, the lowest tubular pile carrying a ram tip.

Durch die AT-PS 260 807 ist ein Hülsenpfahlsystem dieser Art bekanntgeworden, bei welchem jeder Hülsenpfahl an seinen beiden Enden mit einem Nippelstück verbunden ist, wobei beim Zusammenstecken der Hülsenpfähle die ineinandergreifenden Nippelstücke durch eine Hammerkopfschraube und eine Mutter miteinander verbunden werden. Diese Verbindungsart ist umständlich und arbeitsaufwendig. From AT-PS 260 807 a sleeve pile system of this type has become known, in which each sleeve pile is connected at both ends to a nipple piece, the interlocking nipple pieces being connected to one another by a hammer head screw and a nut when the sleeve piles are plugged together. This type of connection is cumbersome and labor intensive.

Aufgabe der Erfindung ist die Schaffung eines Hülsen-pfahlsystems, bei welchem die Hülsenpfähle untereinander und die Rammspitze mit dem untersten Hülsenpfahl in einfacher und rascher Weise verbunden werden können. The object of the invention is to provide a tube pile system in which the tube piles can be connected to one another and the ram tip to the bottom tube pile in a simple and rapid manner.

Diese Aufgabe wird erfindungsgemäss dadurch gelöst, dass das Kupplungsstück als Doppelkonus mit einem mittigen Flansch ausgebildet ist, der zwei Anschlagflächen bildet, und dass die Rammspitze auf der dem Hülsenpfahl zugewandten Seite aussen als Konus mit einer Anschlagfläche ausgebildet ist. This object is achieved according to the invention in that the coupling piece is designed as a double cone with a central flange which forms two stop faces, and in that the ram tip on the outside facing the sleeve pile is designed as a cone with a stop face.

Weitere Einzelheiten der Erfindung werden nachfolgend anhand der Zeichnung erläutert. Es zeigen Further details of the invention are explained below with reference to the drawing. Show it

Fig. 1 ein Kupplungsstück gemäss der Erfindung mit angesetzten Hülsenpfählen vor dem Rammen im Querschnitt, 1 is a cross-section of a coupling piece according to the invention with attached piles before ramming,

Fig. 2 das Kupplungsstück nach Fig. 1 nach dem Rammen, 2 the coupling piece according to FIG. 1 after ramming,

Fig. 3 bis 5 verschiedene Ausführungsbeispiele von Rammspitzen gemäss der Erfindung im Querschnitt, und Fig. 3 to 5 different embodiments of ram tips according to the invention in cross section, and

Fig. 6 bis 15 praktische Anwendungsbeispiele des erfin-dungsgemässenHülsenpfahlsystems. 6 to 15 practical application examples of the sleeve pile system according to the invention.

Das Kupplungsstück nach Fig. 1 und 2 ist aussen als Doppelkonus 2 mit einem mittigen Flansch 3 ausgebildet, so dass zwei Anschlagflächen 4 für die Enden der Hülsenpfähle 6 entstehen. Die Innenwand 5 ist vorzugsweise zylindrisch. Der maximale Durchmesser des Doppelkonus 5 ist um 5 bis 10%, vorzugsweise 7,5% grösser als der Innendurchmesser der Hülsenpfähle 6, der am Ende der Hülsenpfähle beim Rammen bis auf den maximalen Durchmesser des Doppelkonus 2 aufgeweitet wird (siehe Fig. 2), wobei es durch den hohen Druck an den Übergangsflächen zwischen Doppelkonus 2 und den Hülsenpfählen 6 zu einem Reibungsschluss kommt, bzw. eine Kaltpressschweissung eintreten kann. Das Verhältnis des maximalen Durchmessers des Doppelkonus 2 zur Länge des Kupplungsstückes 1 beträgt 1:1 bis 1:2, vor- -zugsweise 1:1,5. Die Steigung des Doppelkonus 2 beträgt 1:20 bis 1:40, vorzugsweise 1:30. 1 and 2 is formed on the outside as a double cone 2 with a central flange 3, so that two stop surfaces 4 are formed for the ends of the sleeve piles 6. The inner wall 5 is preferably cylindrical. The maximum diameter of the double cone 5 is 5 to 10%, preferably 7.5% larger than the inner diameter of the sleeve piles 6, which is expanded at the end of the sleeve piles during ramming to the maximum diameter of the double cone 2 (see FIG. 2), the high pressure at the transition surfaces between the double cone 2 and the sleeve posts 6 leads to a frictional connection, or a cold pressure welding can occur. The ratio of the maximum diameter of the double cone 2 to the length of the coupling piece 1 is 1: 1 to 1: 2, preferably 1: 1.5. The slope of the double cone 2 is 1:20 to 1:40, preferably 1:30.

Als Material für die Herstellung der Hülsenpfähle 6 und des Kupplungsstückes 1 dient vorzugsweise Stahl (Stahlguss oder Temperguss). Es können aber auch Metall und deren Legierungen, sowie Kunststoffe, gegebenenfalls faserverstärkt oder mit metallischen Einlagen, wie Ringe od. dgl., verwendet werden. Steel (cast steel or malleable cast iron) is preferably used as the material for the production of the sleeve piles 6 and the coupling piece 1. However, it is also possible to use metal and its alloys, as well as plastics, optionally fiber-reinforced or with metallic inserts such as rings or the like.

Auch eine Kombination der genannten Materialien untereinander kann zur Herstellung verwendet werden. Zum Schutz gegen Korrosion in aggressiven Böden kann die Aussenseite der aus Stahl gefertigten Hülsenpfähle 6 mit einem hochabriebfesten Kunststoff, z.B. gefülltes Epoxidharz, beschichtet werden. A combination of the materials mentioned with one another can also be used for the production. To protect against corrosion in aggressive soils, the outside of the steel piles 6 made of steel can be coated with a highly abrasion-resistant plastic, e.g. filled epoxy resin.

Die Rammspitzen 7a, 7b, 7c nach Fig. 3 bis 5 weisen aussen einen Konus 8 und eine Anschlagfläche 9 auf. Die Dimensionen des Konus 8 sind die gleichen wie die des Doppelkonus 2 nach Fig. 1 und 2. Es können auch die gleichen genannten Materialien zur Herstellung verwendet werden. Die Rammspitze 7a, nach Fig. 3 hat eine kegelförmige, spitze Unterseite und eignet sich für dichtgelagerte Böden, die Rammspitze 7b nach Fig. 4 hat eine flache Unterseite und wird bei locker gelagerten Böden eingesetzt. Die Rammspitze 7c nach Fig. 5 hat ebenfalls eine flache Unterseite, die mit einem vorstehenden Injektionskopf 10 versehen ist, dessen Austrittsöffnungen mit einem Kunststoffstöpsel 11 ver-schliessbar sind. Das Injektionsgut wird über einen an die Rammspitze 7c anschraubbaren Schlauch 12 zugeführt. The ram tips 7a, 7b, 7c according to FIGS. 3 to 5 have a cone 8 and a stop surface 9 on the outside. The dimensions of the cone 8 are the same as those of the double cone 2 according to FIGS. 1 and 2. The same materials mentioned can also be used for the production. The ram tip 7a, according to FIG. 3, has a conical, pointed underside and is suitable for densely mounted floors, the ram tip 7b according to FIG. 4 has a flat underside and is used for loosely mounted floors. The ram tip 7c according to FIG. 5 also has a flat underside, which is provided with a projecting injection head 10, the outlet openings of which can be closed with a plastic plug 11. The injection material is supplied via a hose 12 which can be screwed onto the ram tip 7c.

Die Konusflächen des Kupplungsstückes 1 und der Rammspitzen 7a bis 7c können aufgerauht oder mit Rillen versehen sein, um die Reibung zu erhöhen. The conical surfaces of the coupling piece 1 and the ram tips 7a to 7c can be roughened or provided with grooves in order to increase the friction.

Fig. 6 zeigt die Verbindung dreier Hülsenpfähle 6 mit zwei Kupplungsstücken 1 und den Einsatz einer Rammspitze 7c, wobei die Schläuche 12 mit Schraub- oder Steckverbindungen 13 verbunden werden. Das Injektionsgut 14 (Zement oder Kunststoff) zum Verfestigen des Untergrundes im Aufstandsbereich des untersten Hülsenpfahls wird nach dem Rammen über die Schläuche 12 injiziert, wobei dabei die Kunststoffstöpsel 11 herausgepresst werden. 6 shows the connection of three sleeve piles 6 with two coupling pieces 1 and the use of a ram tip 7c, the hoses 12 being connected with screw or plug connections 13. The material to be injected 14 (cement or plastic) for solidifying the subsurface in the contact area of the lowermost tube pile is injected via the hoses 12 after ramming, the plastic plugs 11 being pressed out in the process.

Falls der unterste Hülsenpfahl die Belastung nicht nur If the bottom sleeve pile not only the load

2 2nd

5 5

10 10th

15 15

20 20th

25 25th

30 30th

35 35

40 40

45 45

50 50

55 55

60 60

es it

670124 670124

über die Spitze abträgt, sondern über einen Teil seines Mantels, wird in diesem Bereich in die Beschichtung aus Kunststoff Quarzsand eingebettet, um eine rauhere Oberfläche und damit eine höhere Tragfähigkeit des Mantels zu erreichen. abrading over the tip, but over part of its jacket, is embedded in the coating of plastic quartz sand in this area in order to achieve a rougher surface and thus a higher load-bearing capacity of the jacket.

Nach dem Rammen der Hülsenpfähle 6 werden diese mit einem Mörtelbeton (B 225, K 5, GK 0/4) gefüllt. After the piles 6 have been rammed, they are filled with a mortar concrete (B 225, K 5, GK 0/4).

Die Fig. 7 bis 12 zeigen jeweils im Aufriss und Grundriss die Verbindung des obersten Hülsenpfahls mit einem Fundament für Neubauten. Zuerst wird der Pfahl auf die für die Belastung notwendige Tiefe gerammt. Anschliessend wird die statisch notwendige Länge des obersten Hülsenpfahls 6 in das Fundament 15 eingebunden (Fig. 7 und 8). 7 to 12 each show in elevation and plan the connection of the uppermost tube pile with a foundation for new buildings. First the pile is rammed to the depth necessary for the load. The statically necessary length of the uppermost sleeve pile 6 is then integrated into the foundation 15 (FIGS. 7 and 8).

Im Falle einer Durchstanzgefahr des Fundaments wird ein Träger 16 (z.B. U-Profil) nach Fig. 9 und 10, oder eine runde Platte nach Fig. 11 und 12 auf dem oberen Ende des Hülsenpfahls 6, z.B. durch Schweissen befestigt. In the event of a risk of the foundation being punched through, a support 16 (e.g. U-profile) according to FIGS. 9 and 10, or a round plate according to FIGS. 11 and 12 is placed on the upper end of the sleeve pile 6, e.g. attached by welding.

Fig. 13 zeigt das Unterfangen eines vorhandenen Bauteils, wie Fundament 15, Bodenplatte, Mauern etc., mittels eines Kernbohrgerätes wird zuerst ein Loch gebohrt, dessen Durchmesser ca. 20 mm grösser, als der des Hülsenpfahls 6 ist. Anschliessend wird der Hülsenpfahl 6 auf die erforderliche Tiefe gerammt. Die Verbindung zwischen dem Hülsenpfahl 6 und dem Bauteil wird mittels einer Füllung 16 aus Kunstharzmörtel hergestellt. 13 shows the undertaking of an existing component, such as foundation 15, base plate, walls, etc., using a core drilling machine, a hole is first drilled, the diameter of which is approximately 20 mm larger than that of the sleeve pile 6. The sleeve pile 6 is then rammed to the required depth. The connection between the sleeve pile 6 and the component is made by means of a filling 16 made of synthetic resin mortar.

Fig. 14 und 15 zeigen das Heben von Altbauten bzw. deren s Fundament 15, Bodenplatten etc. Hier wird, wie nach Fig. 13 beschrieben, zuerst ein Loch durch das zu hebende Fundament 15 gebohrt, durch welches der Pfahl gerammt wird. Die Oberkante des obersten Hülsenpfahls 6 wird auf der Höhe H der zukünftig gewünschten Fundamentoberkante abge-10 schnitten. Anschliessend werden in das Fundament je Pfahl zwei Löcher 17' gebohrt, in welche Zuganker 18 eingeklebt werden. Diese werden mit einem Träger 19 so verbunden, dass auf dem Pfahlkopf ein Hebezug (Presse, Spindel od. dgl.) 20 Platz hat, welches das Fundament auf die gewünschte 15 Höhe H anhebt (Fig. 15). Dies kann sowohl an einzelnen Stellen oder an mehreren Stellen des Fundamentes 15 bei gleichzeitiger, synchroner Anhebung erfolgen. Nach dem Hebevorgang wird der Hohlraum zwischen dem Hülsenpfahl 6 und dem Fundament mit einer Füllung 16' aus schnell 20 erhärtendem Zement oder Kunststoff vergossen oder ver-presst. 14 and 15 show the lifting of old buildings or their foundation 15, floor slabs etc. Here, as described in accordance with FIG. 13, a hole is first drilled through the foundation 15 to be lifted, through which the pile is rammed. The upper edge of the uppermost tube pile 6 is cut off at the height H of the future desired upper edge of the foundation. Then two holes 17 'are drilled into the foundation for each pile, into which tie rods 18 are glued. These are connected to a carrier 19 in such a way that there is space for a hoist (press, spindle or the like) 20 on the pile head, which raises the foundation to the desired height 15 (FIG. 15). This can take place both at individual points or at several points on the foundation 15 with simultaneous, synchronous lifting. After the lifting process, the cavity between the tube pile 6 and the foundation is poured or pressed with a filling 16 'made of quick-setting cement or plastic.

B B

4 Blatt Zeichnungen 4 sheets of drawings

Claims (11)

670124 PATENTANSPRÜCHE670124 PATENT CLAIMS 1. Hülsenpfahlsystem, welches auf Druck und bzw., oder Zug belastbar ist, und aus einzelnen Hülsenpfählen besteht, die durch Kupplungsstücke verbunden sind, wobei der unterste Hülsenpfahl eine Rammspitze trägt, dadurch gekennzeichnet, dass das Kupplungsstück (1) aussen als Doppelkonus (2) mit einem mittigen Flansch (3) ausgebildet ist, der zwei Anschlagflächen (4) bildet, und dass die Rammspitze (7a bis 7c) auf der dem Hülsenpfahl (6) zugewandten Seite aussen als Konus (8) mit einer Anschlagfläche (9) ausgebildet ist. 1. sleeve pile system, which can be subjected to pressure and / or tension, and consists of individual sleeve piles which are connected by coupling pieces, the lowest sleeve pile carrying a ram tip, characterized in that the coupling piece (1) on the outside as a double cone (2 ) is formed with a central flange (3), which forms two stop surfaces (4), and that the ram tip (7a to 7c) on the outside facing the sleeve pile (6) is designed as a cone (8) with a stop surface (9) is. 2. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass der maximale Durchmesser des Doppelkonus (2) und des Konus (8) um 5 bis 10%, vorzugsweise 7,5% grösser als der Innendurchmesser der Hülsenpfähle (6) ist. 2. sleeve pile system according to claim 1, characterized in that the maximum diameter of the double cone (2) and the cone (8) is 5 to 10%, preferably 7.5% larger than the inner diameter of the sleeve piles (6). 3. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass das Verhältnis des maximalen Durchmessers des Doppelkonus (2) zur Länge des Kupplungsstücks (1) 1:1 bis 1:2, vorzugsweise 1:1,5 beträgt. 3. sleeve pile system according to claim 1, characterized in that the ratio of the maximum diameter of the double cone (2) to the length of the coupling piece (1) is 1: 1 to 1: 2, preferably 1: 1.5. 4. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass die Steigung des Doppelkonus (2) und des Konus (8) 1:20 bis 1:40, vorzugsweise 1:30 beträgt. 4. sleeve pile system according to claim 1, characterized in that the slope of the double cone (2) and the cone (8) is 1:20 to 1:40, preferably 1:30. 5. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass das Kupplungsstück (1), die Rammspitze (7a bis 7c) und die Hülsenpfähle (6) aus Stahl- oder Temperguss hergestellt sind. 5. sleeve pile system according to claim 1, characterized in that the coupling piece (1), the ram tip (7a to 7c) and the sleeve piles (6) are made of cast steel or malleable cast iron. 6. Hülsenpfahlsystem nach Anspruch 5, dadurch gekennzeichnet, dass die Aussenseite der Hülsenpfähle (6) mit einem hochabriebfesten Kunststoff beschichtet ist. 6. sleeve pile system according to claim 5, characterized in that the outside of the sleeve piles (6) is coated with a highly abrasion-resistant plastic. 7. Hülsenpfahlsystem nach Anspruch 6, dadurch gekennzeichnet, dass in die Beschichtung aus Kunststoff Quarzsand eingebettet ist. 7. sleeve pile system according to claim 6, characterized in that in the coating of plastic quartz sand is embedded. 8. Hülsenpfahlsystem nach Anspruch 5, dadurch gekennzeichnet, dass die Konusflächen des Kupplungsstücks (1) und der Rammspitze (7a bis 7c) aufgerauht oder mit Rillen versehen sind. 8. sleeve pile system according to claim 5, characterized in that the conical surfaces of the coupling piece (1) and the ram tip (7a to 7c) are roughened or provided with grooves. 9. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass die Rammspitze (7a) eine kegelförmige, spitze Unterseite aufweist (Fig. 3). 9. sleeve pile system according to claim 1, characterized in that the ram tip (7a) has a conical, pointed underside (Fig. 3). 10. Hülsenpfahlsystem nach Anspruch 1, dadurch gekennzeichnet, dass die Rammspitze (7b) eine flache Unterseite aufweist (Fig. 4). 10. sleeve pile system according to claim 1, characterized in that the ram tip (7b) has a flat underside (Fig. 4). 11. Hülsenpfahlsystem nach Anspruch 10, dadurch gekennzeichnet, dass die flache Unterseite mit einem vorstehenden Injektionskopf (10) versehen ist (Fig. 5). 11. sleeve pile system according to claim 10, characterized in that the flat underside is provided with a projecting injection head (10) (Fig. 5).
CH199888A 1987-07-10 1988-05-27 CH670124A5 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT174487A AT388011B (en) 1987-07-10 1987-07-10 SLEEVE PILE SYSTEM

Publications (1)

Publication Number Publication Date
CH670124A5 true CH670124A5 (en) 1989-05-12

Family

ID=3520076

Family Applications (1)

Application Number Title Priority Date Filing Date
CH199888A CH670124A5 (en) 1987-07-10 1988-05-27

Country Status (3)

Country Link
AT (1) AT388011B (en)
CH (1) CH670124A5 (en)
DE (1) DE3817963A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116791555A (en) * 2023-08-29 2023-09-22 西南石油大学 Drilling platform pile shoe structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE506910C2 (en) * 1996-07-02 1998-03-02 Peterson F O & Soener Pile joints as well as the procedure for making this pile joint
AT3740U3 (en) * 2000-03-22 2001-07-25 Gk Construction Bau Ges M B H STEEL PITCHING PILE

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1051427A (en) * 1912-01-18 1913-01-28 Frank Mccluskey Joint for tubular piling.
US2864241A (en) * 1955-12-20 1958-12-16 Fiore Driving points for piles
DE1246638B (en) * 1965-06-30 1967-08-10 Celler Maschf Geb Connection for sheet metal pipes, especially for well construction and pile foundations
DE1911697C3 (en) * 1969-03-03 1974-03-21 6600 Saarbruecken Detachable connection for drill pipes used in bored pile manufacture
JPS5321202B2 (en) * 1974-10-04 1978-07-01
DE2949938A1 (en) * 1979-12-12 1981-06-19 Brown, Boveri & Cie Ag, 6800 Mannheim Foundation pile for building - has injection outlets above flat transverse component near bottom end
DE3121602A1 (en) * 1981-05-30 1982-12-23 Erwaeta Bohrtechnik GmbH, 2300 Kiel Sleeve connection for the ends of in each case two lengths of pipe

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116791555A (en) * 2023-08-29 2023-09-22 西南石油大学 Drilling platform pile shoe structure
CN116791555B (en) * 2023-08-29 2023-11-17 西南石油大学 Drilling platform pile shoe structure

Also Published As

Publication number Publication date
AT388011B (en) 1989-04-25
ATA174487A (en) 1988-09-15
DE3817963A1 (en) 1989-01-19

Similar Documents

Publication Publication Date Title
EP1591596B1 (en) Embedded dowel
DE2318842A1 (en) DEVICE AND METHOD FOR THE FORMATION OF PILLARS IN THE SOIL
DE2141474A1 (en) Method of coating a wall surface
WO2012059093A2 (en) Ramming tool
DE1625383C3 (en) Fastening bolts
DE7631480U1 (en) REFRACTORY CEMENT BLOCK
CH670124A5 (en)
EP1706653A1 (en) Anchoring arrangement and use of an anchor rod
DE69938438T2 (en) A CONCRETE ELEMENTS AND PILLAR METHOD EMBEDDED IN CONCRETE
EP3161226B1 (en) Anchor dowel
EP0088825A2 (en) Transporting anchor for prefabricated concrete elements
AT785U1 (en) PILE
AT380502B (en) METHOD AND DEVICE FOR WIDING RUNWAY PANELS, BRIDGE ROADWAYS OR THE LIKE.
DE102006023799A1 (en) DEvice for manufacturing foundation elements, particularly ring shaped in-situ pile and pile barrier with reduced concrete quantity, comprises double wall drilling pipe with internal wall and outer wall
DE4023695C2 (en) Device for laying sewer pipes consisting of pipes, in particular sewer pipes
DE1634273A1 (en) Ground anchor and process for its manufacture
DE102005017598A1 (en) Tie anchor, for mounting machines/brackets at floors/walls or building structures at foundations, has a spreading anchor at the base of the drilling attached to an upper threaded plug by a cord/cable
CH690727A5 (en) Sleeve-shaped anchoring element to embed in Betongiessmasse.
DE2403473A1 (en) Concrete tubular pile - with steel tube reinforcement with bottom closed end and side wings
DE2906797A1 (en) Reinforced concrete girder construction - involves retainer anchor fixing at stress member ends before concreting
EP2896750B1 (en) Device and method for anchoring a building structure
DE2105432A1 (en) Process for the production of a pre-stressed concrete tubular pile or an in-situ concrete pile with a pre-stressed outer zone as well as facilities for carrying out the process
CH439133A (en) Process for producing a pile in the ground and concrete pile for carrying out the process
AT15636U1 (en) INCLUDED IN A SUB-BACKGROUND SYSTEM
DE1784515C2 (en) Reinforcement of precast concrete elements by means of one or more anchor rods embedded in the same

Legal Events

Date Code Title Description
PL Patent ceased