CH155702A - Process for the renewal of railways and device for implementing this process. - Google Patents

Process for the renewal of railways and device for implementing this process.

Info

Publication number
CH155702A
CH155702A CH155702DA CH155702A CH 155702 A CH155702 A CH 155702A CH 155702D A CH155702D A CH 155702DA CH 155702 A CH155702 A CH 155702A
Authority
CH
Switzerland
Prior art keywords
track
section
rails
service
transport
Prior art date
Application number
Other languages
French (fr)
Inventor
Collet Les Fils D Albert
Loiseau Rene
Original Assignee
Albert Collet Fils D
Loiseau Rene
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Albert Collet Fils D, Loiseau Rene filed Critical Albert Collet Fils D
Publication of CH155702A publication Critical patent/CH155702A/en

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

  

  Procédé pour le renouvellement des voies ferrées et dispositif pour la mise en     oeuvre     de ce procédé.    Pour renouveler le matériel de voies, on  procède habituellement de la manière sui  vante  Les     matériaux    neufs, rails, traverses, pe  tit     matériel    non assemblés,     destinés    à rempla  cer les matériaux usagés en service, sont dis  tribués au préalable le long de la ligne à re  nouveler.

   Dans les     intervalles    de temps com  pris entre les passages de trains, on enlève  des tronçons de voie usagés., on les remplace  par des tronçons de voie neufs, l'assemblage  étant fait sur place; Tes rails et le petit ma  tériel usagés sont mis sur les accotements et  les traverses sont mises sur les talus.  



  Ce procédé ne permet pas d'aller     vite;    en  tre deux     passages    de trains il n'est générale  ment possible de remplacer qu'une faible lon  gueur     de    voie. Le transport des matériaux le  long de la voie est également une opération  coûteuse; les     accotements    sont     encombrés    par  les matériaux neufs avant l'exécution du tra-         vail    et par les matériaux usagés lorsque  ceux-ci ont été remplacés par les matériaux  neufs.  



       Le    procédé qui fait partie de la présente       invention    a pour     objet    de remédier à. ces di  vers inconvénients; il consiste à amener les  voies assemblées par grandes     longueurs,    les  rails étant     tirefonnés    sur les traverses, à l'en  droit où l'un doit faire la pose, en utilisant  pour le transport à     pied-d'oeuvre    les rails       existants,    et à enlever par grandes longueurs  la voie à remplacer, .en utilisant les rails  existants pour évacuer cette voie.  



  L'invention comprend également un dis  positif pour la mise en     aeuvre    du procédé, ca  ractérisé par le fait qu'il comporte un moyen  de transport des tronçons de voie à. poser et  à déposer sur la voie     existante,    ainsi que des  rails     auxiliaires    amovibles disposés de part et       d'autrL,    de la voie principale et sur lesquels on  fait rouler un appareil destiné à la dépose du  tronçon usagé et à la pose du tronçon neuf.

        La     fig.    1 est un schéma permettant de  comprendre le principe du procédé suivant  l'invention;       Les        fig.    2 e     -t    3 représentent en coupe et en  élévation latérale une forme d'exécution  d'une partie du dispositif pour la     anise    en       #uvre    du procédé., sous forme d'un galet pou  vant être employé pour le transport du tron  çon de voie assemblé;

    Les     fig.    4, 5 illustrent, au moyen d'un  plan et d'une coupe transversale verticale,  une forme d'exécution du procédé pour trans  porter le tronçon de voie neuf depuis le chan  tier jusque sur la     voie    à réparer, de manière  qu'il n'y ait plus qu'à le pousser sur cette voie  pour l'amener à     pied-d'#uvre;     La     fig.    6 représente un détail des barres  de translation;

    La     fig.    7 représente un mode d'exécution  d'un appareil appelé     diplory,    destiné à effec  tuer la. pose du tronçon de voie, cet     appareil     faisant partie d'un dispositif pour la mise en       #uvre    du     procédé;     La     fig.    8     représente    un     diploiy        utilisé    au  transport de la voie de     service;

       Les     fig.    8 et 10 représentent, respective  ment en coupe perpendiculairement aux rails  et en vue latérale, une variante du moyen de  transport faisant partie du dispositif pour la  mise en     #uvre    du procédé, dans laquelle le  tronçon de rail est fixé sur des galets munis  de traverses auxiliaires, en position de trans  port;  Les     fig.    11 et 12     représentent.,    respecti  vement dans des vues qui correspondent aux  précédentes, un     diplory    perfectionné à dis  positif de levage par treuil et à traverses  guidées verticalement par des glissières por  tées par les galets de roulement.  



  Enfin, la     fig.    13 représente l'emploi d'un       diplory    de type ordinaire aménagé pour la  pose, la, dépose et le     transport    de la voie de       service.     



  Pour mettre en     ceuvre    le procédé suivant  la présente invention, on peut procéder, par  exemple, de la manière suivante: On remplace  en une seule     opération    un tronçon de voie    <I>C D</I>     (fig.    1) de la ligne A B à renouveler,  ce tronçon ayant une longueur de 150 mè  tres, par exemple.<I>'A</I> -et<I>B</I> étant les gares re  liées par la voie à renouveler, l'assemblage du  tronçon .à poser est fait, par exemple en A,  tandis que le. tronçon usagé     -est    évacué sur la.  gare B pour y être démonté.

   Une voie de  service provisoire E E',<I>F F,</I> placée comme  le montre la. figure relativement      < à.    la. partie  <I>C D</I> à remplacer, sert, de voie de roulement  à un appareil appelé     diplory    qui     sert    à faire  la pose et la. dépose des tronçons de voie.

   Le  schéma des opérations est le suivant: le tron  çon de voie neuf est. amené par roulement sur  la voie principale (par exemple au moyen des  galets qui seront décrits plus loin) dans la  région H C, en amont de la partie à     réfection-          ner.    Le tronçon usagé<I>C D</I> séparé de la voie  principale est suspendu aux éléments du     di-          plory,    soulevé de la<B>,</B> hauteur voulue, trans  porté par le diplory dans la région<I>D I,</I> en  aval de la partie à réfectionner, puis mis  en position de roulement sur la voie princi  pale allant vers B (par exemple muni de  galets de support roulant sur cette voie). Il  est alors séparé du     diplory,    puis transporté  vers B sur la voie principale.

   Le     diplory    est  ensuite ramené vers A jusque dans la posi  tion dans laquelle le tronçon neuf qui se  trouve en H C peut lui être suspendu. Lors  que     cette    suspension est réalisée, le tronçon  de voie neuf, libéré de ses organes de roule  ment, qui serviront pour l'évacuation d'un  tronçon usagé suivant, est transporté en<I>C D</I>  par le     diplory;    mais il est alors mis en place  et raccordé à la voie existante.  



  Le     diplory    est agencé de telle manière  que, en rapprochant ses roues, il puisse rouler  sur la voie principale et transporter ses pro  pres rails de service. Il suffira donc, pour  remplacer le tronçon en<I>D I,</I> par exemple,  de transporter au moyen du     diplory    les voies  de service vers B de la longueur du tron  çon DI.  



  Pour porter le tronçon de voie neuf pen  dant son transport entre la gare A où se  trouve le chantier d'assemblage et la région  H C dans laquelle il sera accroché au di-           plory    et pour     supporter    le     tronçon    de voie  usagé dans -son transport vers la gare B,  on peut utiliser des galets tels que repré  sentés dans les     fig.    2 et 3. Le galet propre  ment dit 1 est monté sur l'axe 2, des roule  ments à billes 3 étant interposés entre le ga  let et son axe. Cet axe supporte l'étrier 4  prolongé par le pivot 5 monté de manière à  pouvoir tourner dans une embase 6.

   Cette  embase est accrochée au rail. d'un côté par la  partie en forme de crochet 7, d'autre part,  par l'intermédiaire de la barre $ munie d'un  rebord 9 qui, lorsqu'on le pousse longitudi  nalement, vient, d'une part, par son rebord  9, prendre appui sur la semelle du rail,  d'autre part, par la face opposée sur la sur  face intérieure du rebord 10 formé sur l'em  base 6.  



  L'écartement des deux bords 7 et 10 étant  plus grand d'un côté de l'embase que de l'au  tre côté de cette embase, en enfonçant la  barre 8 à partir du côté de plus grand écar  tement des deux bords, on obtient un     ser-          .age    énergique de l'embase sur la semelle  du rail. Le galet comporte un dispositif de  verrouillage qui permet de le bloquer dans  quatre positions à 90   l'une de l'autre par  rapport au rail qu'il porte; dans deux de ces  positions, son axe est perpendiculaire au rail;  dans les deux autres positions, il est parallèle        < i    celui-ci.

   Ce dispositif se compose d'une col  lerette 11 fixée sur l'étrier de support du ga  let, présentant quatre logements dont trois,  1,2, 13, 14 sont figurés sur le dessin, le qua  trième étant du côté opposé au logement 13.  Un verrou 15 tourillonné en 16 sur l'embase  6 est, dans la position de repos, engagé dans  l'un de ces logements, de sorte qu'il bloque  l'étrier relativement     ià    son embase. Pour mo  difier l'orientation du galet, il suffit de dé  gager le verrou en le soulevant de la hauteur  voulue.

   On voit que, en fixant un nombre  de galets suffisant de ce genre sous les rails  d'un tronçon de voie assemblés sur leurs tra  verses, l'ensemble constituera un véritable  châssis roulant que l'on pourra facilement  placer sur la voie existante de manière à  l'amener à     pied-d'ceuvre,       Généralement, le montage du tronçon de  rail aura lieu sur un chantier situé en dehors  de la voie principale. Il faudra donc trans  porter ce tronçon de manière à l'amener sur  la voie principale dans la position voulue  pour qu'il puisse être transporté sur cette  voie. Le tronçon T     (fig.    4) sera monté sur  des paires de galets g     g1,    g' g'1, g"     g"1,    etc.,  dont les axes seront orientés parallèlement  aux rails du 'tronçon T.

   On disposera     trans-          versalement    à la voie T des tronçons de rails  ou des barres de translation<I>r, r', r",</I> etc.,  l'écartement des tronçons<I>r, r'</I> étant, par  exemple, le même que celui des paires de ga  lets<I>g</I>     g1,   <I>g'</I>     g'i,   <I>g"</I>     9'1.    La position relative  de l'un de ces rails r par rapport à la voie       principale    est représentée sur la     fig.    5 ; la       figA    est une vue analogue dans le cas d'une  barre.  



  On commencera par monter le     tronçon     de voie muni de ses galets sur les tronçons  de rails<I>r,</I>     r',   <I>r",</I> etc., dans la position indi  quée dans la     fig.    4. On poussera. ensuite ce  tronçon de voie jusqu'à ce que les rails qui le  composent viennent     jà    l'aplomb des rails de  la voie principale. Lorsqu'ils seront dans  cette position, l'ensemble constitué par le  tronçon de voie et des galets supports sera  soulevé à l'aide de vérins de la hauteur suf  fisante pour que l'on puisse enlever facile  ment les rails r, 7', r", etc.

   Cet enlèvement  étant fait, on fera. tourner de 90   les galets  supports dans le sens     convenable,        c'est-à.-          dire    de sorte que l'ensemble du tronçon et de  ses galets supports constitue un ensemble qui  puisse rouler sur la voie principale. Il suffira  alors d'abaisser le tronçon de voie à l'aide  des vérins, jusqu'à ce que les galets viennent  reposer sur les rails de la voie principale.  



  On a indiqué au début de la description  que, lorsque l'ensemble constitué par le tron  çon de voie supporté par les galets a. été  amené dans la région H C, il faut avec le       diplory,    d'une part, faire la dépose du tron  çon usagé, d'autre part, effectuer la pose du  tronçon neuf. Le     diplory    représenté en     fig.    7  comprend une série d'éléments     constitués    cha-           cun    par une traverse 21 montée sur des ga  lets de roulements 22, munis de chapes 23; des  vérins 24 sont interposés entre la chape 23  et la traverse 21. On peut donc, à l'aide de  ces vérins, compenser la différence de ni  veau des deux rails de la voie de service.

   Ces  vérins ont aussi pour objet le soulèvement de  la traverse lorsque cela est nécessaire. L'écar  tement des galets 22 peut être modifié de ma  nière qu'ils puissent, ou bien reposer sur les  rails de service, pour la pose et la dépose, ou  bien reposer sur la voie principale pour le  transport des rails de service.

   Pour la dépose  du tronçon de voie usagé, le     diplory    étant  amené à l'aplomb de ce tronçon, celui-ci est  séparé du reste de la voie; les rails usagés,  assemblés sur leurs traverses, sont     supendus     aux traverses 2,1 du     diplory,    puis ces traver  ses sont soulevées à l'aide des vérins jusqu'à  ce que le tronçon usagé soit à une hauteur  suffisante au-dessus de la voie pour que,  après le montage des galets sur ce tronçon  usagé, ceux-ci soient à un niveau plus élevé  que la voie elle-même.

   La fixation des galets  pourra avoir lieu soit avant, soit après le dé  placement du     diplory    qui a pour but d'ame  ner le     tronçon    de voie usagé dans la région  <I>D I.</I> Le tronçon de voie muni de ses galets  étant amené dans la région<I>D I,</I> il suffira de  l'abaisser suffisamment pour que les galets  supports du tronçon reposent sur les rails de  la voie principale. Le tronçon usagé sera alors  séparé du     diplory.    On ramènera le     diplory     en arrière jusque dans la région H C et la  pose du tronçon neuf en<I>C D</I> se fera. à l'aide  du     diplory    par une série     d'opérations    exacte  ment inverses de celles qui viennent d'Être  décrites.  



  La     fig.    8 représente une variante du     di-          plory,    figuré en position de transport.     Il    re  pose par ses galets sur la voie principale,  tandis que les rails de la voie de service sont  suspendus aux engins de levage 26 montés  sur les côtés du     diplory.     



  Les     fig.    9 et 10 représentent une va  riante du moyen de transport du     tronçon    de  voie, dans laquelle le galet de roulement 1    est monté dans les joues 41 qui sont fixées  sur les traverses auxiliaires porte-galet 40  au moyen des équerres 42. La fixation des  traverses 40 sur chaque rail du tronçon à.  transporter a lieu au moyen de dispositifs  comprenant chacun deux leviers 43, 44 dont  l'un 43 est articulé en 45 sur la traverse,  et dont l'autre 44, qui a la forme coudée in  diquée, est articulé en 46 avec le levier 43.  L'extrémité 47 du levier 44 est en forme de  fourche à deux branches. Un levier 48, arti  culé en 49 sur la traverse, porte une bague  50, et un écrou de serrage 51.

   Le montage de  la traverse auxiliaire 40 a lieu de la manière  suivante: lorsqu'elle a été mise relativement  au rail dans la position voulue, on rabat le  levier 44 sur le champignon du rail dans la  position représentée en     fig.    9, on relève le  levier 48 que l'on amène entre les deux bran  ches de la fourche 47, la bague étant placée  sur les deux branches et on serre l'écrou 51.  Le     démontage    se fait en sens inverse.

   Les ga  lets sont fixés de préférence sur la traverse  au moyen de tout dispositif de fixation ra  pide qui les rende facilement     démontables.     L'emploi des traverses a pour objet de pou  voir     placer    facilement les galets à     l'écarte-          ment    voulu, et en particulier de remédier à  la différence     d'écartement    qui peut     exister     éventuellement entre les rails du     tronçon    à  poser et les rails sur lesquels ils reposent.

      Les     fig.    11 et 12 représentent une va  riante du     diplory,    dans laquelle les galets  22 du     diplory    sont à. double boudin pour em  pêcher leur déraillement dans le     cas    d'un dé  placement accidentel de la voie de     service.     Les engins de levage 25 et 26 se composent  d'un treuil commandé par vis sans fin et roue  dentée     hélicoïdale        5\2,    5'3 sur lequel s'enroule  le     câble    54 portant à. sa partie inférieure le  crochet 34.  



  La traverse 21, composée des deux fers en  <B>U</B> 21a et 21b convenablement     entretoisés,    re  pose sur le plateau 24' du vérin 24. Elle est  guidée latéralement par des glissières 55, 56  portées par la chape des galets de roulement.      L'utilité de ces glissières est de guider les  traverses 21, de manière que leur axe de sy  métrie reste constamment vertical lorsqu'on  les soulève au moyen des vérins.  



  Pour le transport des voies de service, on  peut, au lieu du     diplory    spécial décrit, uti  liser un     diplory    ordinaire dont les galets sont       à.    l'écartement de la voie à poser ou à rem  placer. A cet effet, on peut procéder de la  manière suivante: Sur chaque traverse du     di-          plory    60 (fi-. 13) montée sur les galets 61  placés à l'écartement de la voie en cours de  remplacement, on assemble, à l'aide de bri  des, une traverse 62 qui surplombe largement  de part et d'autre les traverses de la voie en  cours de remplacement.

   Les     lève-rails    2.6 qui  servent à la pose, à la dépose et au transport  de la voie de service, et qui ont été précédem  ment décrits, sont montés sur cette traverse  62 à raison d'un à chaque extrémité. La pose  et la dépose de la voie de service se fait de  la manière décrite plus haut. Il va sans dire  que les procédés     décrits    sont donnés expressé  ment à     titre    d'exemples.



  Method for renewing railway tracks and device for implementing this method. To renew track material, the following procedure is usually carried out. re new.

   In the time intervals between train passes, used track sections are removed, replaced by new track sections, assembly being done on site; Your used rails and small equipment are put on the shoulders and sleepers are put on the slopes.



  This process does not allow you to go quickly; between two train passages it is generally possible to replace only a short length of track. Transporting materials along the track is also an expensive operation; the shoulders are encumbered by new materials before the work is performed and by used materials when these have been replaced by new materials.



       The object of the method which forms part of the present invention is to remedy. these various disadvantages; it consists in bringing the assembled tracks in great lengths, the rails being pulled on the sleepers, to the right where one must do the laying, using the existing rails for transport on foot, and in remove by great lengths the track to be replaced, .using the existing rails to evacuate this track.



  The invention also comprises a positive device for the implementation of the method, ca ractérisé in that it comprises a means of transporting sections of track to. pose and deposit on the existing track, as well as removable auxiliary rails arranged on either side of the main track and on which is rolled a device intended for the removal of the used section and the installation of the new section.

        Fig. 1 is a diagram making it possible to understand the principle of the process according to the invention; Figs. 2 and 3 show in section and in side elevation an embodiment of part of the device for carrying out the process., In the form of a roller that can be used for transporting the section of assembled track;

    Figs. 4, 5 illustrate, by means of a plan and a vertical cross section, one embodiment of the method for transporting the new section of track from the site to the track to be repaired, so that it you just have to push him on this path to get him to work; Fig. 6 shows a detail of the translation bars;

    Fig. 7 represents an embodiment of an apparatus called diplory, intended to effect the. laying of the track section, this apparatus forming part of a device for implementing the method; Fig. 8 represents a diploiy used to transport the service road;

       Figs. 8 and 10 show, respectively in section perpendicular to the rails and in side view, a variant of the transport means forming part of the device for carrying out the process, in which the rail section is fixed on rollers provided with sleepers auxiliaries, in transport position; Figs. 11 and 12 represent., Respectively in views which correspond to the preceding ones, an improved diplory with a positive lifting device by means of a winch and cross members guided vertically by slides carried by the running rollers.



  Finally, fig. 13 represents the use of a diplory of ordinary type fitted out for the installation, the removal and the transport of the service road.



  To implement the method according to the present invention, one can proceed, for example, in the following way: A section of track <I> CD </I> (fig. 1) of line AB is replaced in a single operation. to renew, this section having a length of 150 meters, for example. <I> 'A </I> -and <I> B </I> being the stations re linked by the track to be renewed, the assembly of the section. to be laid is done, for example at A, while the. used section -is evacuated on the. station B to be dismantled there.

   A provisional service road E E ', <I> F F, </I> placed as shown in the. figure relatively <to. the. part <I> C D </I> to replace, serves as a running track for a device called diplory which is used to pose and. removal of track sections.

   The diagram of operations is as follows: the new section of track is. brought by rolling on the main track (for example by means of the rollers which will be described later) in the region H C, upstream of the part to be repaired. The used section <I> CD </I> separated from the main track is suspended from the components of the brochure, lifted from the desired <B>, </B> height, transported by the diplory in the region <I> DI, </I> downstream of the part to be repaired, then put into rolling position on the main track going towards B (for example fitted with support rollers rolling on this track). It is then separated from the diplory, then transported to B on the main track.

   The diplory is then brought back to A until it reaches the position in which the new section which is at H C can be suspended from it. When this suspension is carried out, the section of new track, freed from its running gear, which will be used for the evacuation of a next used section, is transported in <I> C D </I> by the diplory; but it is then put in place and connected to the existing track.



  The diplory is arranged in such a way that, by bringing its wheels closer together, it can roll on the main track and carry its own service rails. It will therefore suffice, to replace the section in <I> D I, </I> for example, to transport by means of diplory the service tracks to B of the length of section DI.



  To carry the new section of track during its transport between station A where the assembly site is located and the HC region in which it will be attached to the brochure and to support the section of track used in its transport to the station B, you can use rollers as shown in fig. 2 and 3. The actual roller 1 is mounted on the axis 2, ball bearings 3 being interposed between the ga let and its axis. This axis supports the caliper 4 extended by the pivot 5 mounted so as to be able to rotate in a base 6.

   This base is hooked to the rail. on one side by the hook-shaped part 7, on the other hand, by means of the bar $ provided with a flange 9 which, when pushed lengthwise, comes, on the one hand, by its flange 9, rest on the sole of the rail, on the other hand, by the opposite face on the inner face of the flange 10 formed on the base 6.



  The spacing of the two edges 7 and 10 being greater on one side of the base than on the other side of this base, by pushing in the bar 8 from the side with the greatest separation of the two edges, we obtains an energetic clamping of the base on the base of the rail. The roller comprises a locking device which allows it to be locked in four positions at 90 to each other with respect to the rail which it carries; in two of these positions, its axis is perpendicular to the rail; in the other two positions, it is parallel to this one.

   This device consists of a collar 11 fixed to the ga let support bracket, having four housings of which three, 1, 2, 13, 14 are shown in the drawing, the fourth being on the side opposite the housing 13 A latch 15 journalled at 16 on the base 6 is, in the rest position, engaged in one of these housings, so that it locks the stirrup relative to its base. To change the orientation of the roller, simply release the lock by raising it to the desired height.

   It can be seen that, by fixing a sufficient number of rollers of this type under the rails of a section of track assembled on their sleepers, the whole will constitute a real rolling frame that can easily be placed on the existing track in such a way. to bring it to the job, Generally, the assembly of the rail section will take place on a site located outside the main track. This section will therefore have to be transported so as to bring it onto the main track in the desired position so that it can be transported on this track. Section T (fig. 4) will be mounted on pairs of rollers g g1, g 'g'1, g "g" 1, etc., the axes of which will be oriented parallel to the rails of section T.

   Sections of rails or translation bars <I> r, r ', r ", </I> etc. will be placed crosswise to track T, the spacing of the sections <I> r, r' </ I> being, for example, the same as that of the pairs of ga lets <I> g </I> g1, <I> g '</I> g'i, <I> g "</I> 9' 1. The relative position of one of these rails r with respect to the main track is shown in FIG. 5; figA is a similar view in the case of a bar.



  We will start by mounting the section of track fitted with its rollers on the sections of rails <I> r, </I> r ', <I> r ", </I> etc., in the position indicated in fig. 4. This section of track will then be pushed until the rails which compose it come directly above the rails of the main track. When they are in this position, the assembly formed by the section of track and the supporting rollers will be lifted using jacks of sufficient height so that the rails r, 7 ', r ", etc. can be easily removed.

   This removal being done, we will do. turn the support rollers by 90 in the correct direction, that is to say so that the whole of the section and its support rollers constitutes an assembly which can roll on the main track. It will then be sufficient to lower the section of track using the jacks, until the rollers come to rest on the rails of the main track.



  It was indicated at the beginning of the description that, when the assembly constituted by the section of track supported by the rollers a. been brought to the H C region, it is necessary with the diplory, on the one hand, to remove the used section, on the other hand, to install the new section. The diplory represented in fig. 7 comprises a series of elements each consisting of a cross member 21 mounted on rolling balls 22, provided with yokes 23; jacks 24 are interposed between the yoke 23 and the cross member 21. It is therefore possible, using these jacks, to compensate for the difference in level of the two rails of the service track.

   The purpose of these jacks is also to lift the cross member when necessary. The spacing of the rollers 22 can be modified so that they can either rest on the service rails for laying and removal, or else rest on the main track for transporting the service rails.

   For the removal of the used section of track, the diplory being brought in line with this section, it is separated from the rest of the track; the used rails, assembled on their sleepers, are suspended on the diplory sleepers 2,1, then these rails are raised using the jacks until the used section is at a sufficient height above the track so that, after mounting the rollers on this used section, they are at a higher level than the track itself.

   The fixing of the rollers can take place either before or after the displacement of the diplory whose aim is to bring the section of track used in the <I> D I. </I> region. The section of track fitted with its rollers being brought into the <I> DI region, </I> it will suffice to lower it sufficiently so that the support rollers of the section rest on the rails of the main track. The used section will then be separated from the diplory. We will bring the diplory back to the region H C and the installation of the new section in <I> C D </I> will be done. with the aid of diplory by a series of operations exactly the opposite of those which have just been described.



  Fig. 8 represents a variant of the brochure, shown in the transport position. It rests by its rollers on the main track, while the rails of the service track are suspended from the lifting devices 26 mounted on the sides of the diplory.



  Figs. 9 and 10 represent a variant of the means of transport of the section of track, in which the rolling roller 1 is mounted in the cheeks 41 which are fixed to the auxiliary roller carrier cross members 40 by means of the brackets 42. The fixing of the cross members 40 on each rail from section to. transport takes place by means of devices each comprising two levers 43, 44, one of which 43 is articulated at 45 on the cross member, and the other 44, which has the indicated bent shape, is articulated at 46 with the lever 43 The end 47 of the lever 44 is in the form of a fork with two branches. A lever 48, articulated at 49 on the cross member, carries a ring 50, and a tightening nut 51.

   The assembly of the auxiliary cross member 40 takes place as follows: when it has been placed relative to the rail in the desired position, the lever 44 is folded on the head of the rail in the position shown in FIG. 9, the lever 48 is raised which is brought between the two branches of the fork 47, the ring being placed on the two branches and the nut 51 is tightened. Disassembly is carried out in reverse order.

   The gaets are preferably fixed on the cross member by means of any quick fixing device which makes them easily removable. The purpose of the use of sleepers is to easily place the rollers at the desired spacing, and in particular to remedy the difference in spacing which may possibly exist between the rails of the section to be laid and the rails on which they rest.

      Figs. 11 and 12 represent a variant of the diplory, in which the rollers 22 of the diplory are at. double flange to prevent their derailment in the event of an accidental displacement of the service road. The lifting devices 25 and 26 consist of a winch controlled by an endless screw and helical toothed wheel 5 \ 2, 5'3 on which is wound the cable 54 carrying to. its lower part the hook 34.



  The cross member 21, made up of two suitably braced <B> U </B> bars 21a and 21b, rests on the plate 24 'of the jack 24. It is guided laterally by slides 55, 56 carried by the yoke of the rollers bearing. The usefulness of these slides is to guide the sleepers 21, so that their symmetry axis remains constantly vertical when they are lifted by means of the jacks.



  For the transport of the service tracks, one can, instead of the described special diplory, use an ordinary diplory whose rollers are at. the gauge of the track to be laid or replaced. To this end, we can proceed as follows: On each cross member of the di- plory 60 (fig. 13) mounted on the rollers 61 placed at the spacing of the track being replaced, we assemble, at the using bri des, a crosspiece 62 which largely overhangs on either side the ties of the track being replaced.

   The lift rails 2.6 which are used for laying, removing and transporting the service track, and which have been previously described, are mounted on this cross member 62 at the rate of one at each end. The installation and removal of the service track is carried out in the manner described above. It goes without saying that the methods described are given expressly by way of example.

 

Claims (1)

REVENDICATIONS I Procédé pour le renouvellement des voies ferrées, caractérisé par le fait qu'on amène les voies assemblées par grandes longueurs, les rails étant tirefonnés sur les traverses, à l'endroit où doit se faire la pose, en utilisant pour le transport les rails existants, et que l'on enlève par grandes longueurs la voie à remplacer, en utilisant pour évacuer cette voie, les rails existants. II Dispositif pour la mise en oeuvre du pro cédé suivant la revendication I, CLAIMS I Process for the renewal of the railway tracks, characterized by the fact that the assembled tracks are brought in long lengths, the rails being pulled on the sleepers, at the place where the laying is to be done, using for transport the existing rails, and that the track to be replaced is removed in great lengths, using the existing rails to evacuate this track. II Device for the implementation of the process according to claim I, caractérisé par le fait qu'il comporte un moyen de transport des tronçons de voie à poser et à déposer sur la voie existante, ainsi que des rails auxiliaires amovibles disposés de part et d'autre de la voie principale sur lesquels roule un appareil destiné à la dé pose du tronçon usagé et à la, pose du tronçon neuf. characterized by the fact that it comprises a means of transporting the sections of track to be laid and to be deposited on the existing track, as well as removable auxiliary rails arranged on either side of the main track on which a device intended to run runs the removal of the used section and the installation of the new section. SOUS-REVENDICATIONS 1 Procédé suivant la revendication I, carac térisé par le fait que la dépose et la pose étant effectuées au moyen d'un appareil roulant sur une voie de service dont les rails sont placés de part et d'autre de la voie normale, l'appareil même qui a ef fectué la dépose du tronçon à remplacer et sa mise en place sur la voie aval, est ra mené à l'amont de la partie à réfectionner, afin de prendre et de poser le tronçon de remplacement sur la partie à réfectionner. 2 Procédé suivant la revendication I et la sous-revendication 1, SUB-CLAIMS 1 A method according to claim I, charac terized in that the removal and installation being carried out by means of a rolling device on a service track, the rails of which are placed on either side of the normal track , the same device which removed the section to be replaced and its installation on the downstream track, is brought upstream of the part to be repaired, in order to take and place the replacement section on the part to repair. 2 A method according to claim I and sub-claim 1, caractérisé en" ce qu'on munit le tronçon neuf et celui à. éva cuer, d'un moyen de transport tel que ces tronçons peuvent avoir un déplacement transversal par rapport à la. voie, en plus des déplacements longitudinaux et verti caux dus à l'appareil de pose et de dépose. 3 Procédé suivant la revendication I et la sous-revendication 1, caractérisé par le fait qu'un moyen de transport, ayant amené le tronçon de remplacement en amont du tronçon à réfectionner, est éva cué par l'aval de cet emplacement. characterized in "that the new section and that to be evacuated are provided with a means of transport such that these sections can have a transverse displacement with respect to the track, in addition to the longitudinal and vertical displacements due to the installation and removal apparatus. 3 A method according to claim I and sub-claim 1, characterized in that a transport means, having brought the replacement section upstream of the section to be repaired, is evacuated by downstream from this location. 4 Dispositif suivant la revendication II, ca ractérisé par le fait que le moyen de trans port, destiné à transporter les tronçons de voie, comporte une série de trains de roues, les roues (1) de chaque paire étant réunies par un dispositif rigide (40) comportant des organes (43 à 49) pour la fixation ra pide du tronçon de remplacement ou du tronçon à remplacer. 4 Device according to claim II, ca ractérisé in that the transport means, for transporting the track sections, comprises a series of wheel sets, the wheels (1) of each pair being joined by a rigid device ( 40) comprising members (43 to 49) for the rapid fixing of the replacement section or of the section to be replaced. 5 Dispositif suivant la revendication II, ca- ractérisé par le fait que l'appareil de pose et de dépose est constitué par un portique bas monté sur des galets de roulement sus ceptibles de circuler sur les rails de service et comportant entre chaque galet (22) et la traverse (221) du portique un vérin (24) permettant de maintenir la traverse hori zontale quand les rails de service sont à des niveaux différents. 5 Device according to claim II, charac- terized in that the fitting and removal apparatus consists of a low gantry mounted on running rollers capable of running on the service rails and comprising between each roller (22 ) and the cross member (221) of the gantry a jack (24) making it possible to keep the horizontal cross member when the service rails are at different levels. 6 Dispositif suivant la revendication II et la sous-revendication 5, caractérisé par le fait que les galets (22) peuvent se déplacer le long de la traverse (21) du portique, de façon à permettre au portique de se déplacer soit sur les rails de service, soit sur la voie normale pour transporter les rails de ser vice. 6 Device according to claim II and sub-claim 5, characterized in that the rollers (22) can move along the cross member (21) of the gantry, so as to allow the gantry to move either on the rails or on the normal track for transporting the service rails.
CH155702D 1929-11-30 1930-11-17 Process for the renewal of railways and device for implementing this process. CH155702A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR155702X 1929-11-30

Publications (1)

Publication Number Publication Date
CH155702A true CH155702A (en) 1932-07-15

Family

ID=8876127

Family Applications (1)

Application Number Title Priority Date Filing Date
CH155702D CH155702A (en) 1929-11-30 1930-11-17 Process for the renewal of railways and device for implementing this process.

Country Status (1)

Country Link
CH (1) CH155702A (en)

Similar Documents

Publication Publication Date Title
JP2008074141A (en) Truck for tracks and ladder type tie transporting device
FR2627522A1 (en) DEVICE FOR PRINTING RESPECTIVELY A TRACTION OR A PUSH ON RAILS, IN ORDER TO LONGITUDINALLY OFFSET RAILS OF RAISED RAILWAYS
FR2476708A1 (en) MOBILE ASSEMBLY FOR CLEANING THE RAILWAY BALLAST LAYER AND CLEANING METHOD USING SUCH AN ASSEMBLY
WO2012072901A1 (en) Method for constructing a railway track
EP3368718A1 (en) System and method for transporting a railway switch
CH155702A (en) Process for the renewal of railways and device for implementing this process.
EP0108168A1 (en) Track installation replacement method and train for carrying out the method
EP0160898B1 (en) Handling apparatus for assembled railway switches or crossings
BE375010A (en)
FR2535359A1 (en) Method for the replacement of railway lines and handling frame for implementing the same
EP2671698B1 (en) Bench for manufacturing girders by extrusion
EP0773153B1 (en) Mobile platform for surmounting height deviations
CH680865A5 (en)
FR2546925A1 (en) Multi-chassis rail track laying and dismantling machine
FR2698281A1 (en) Turf system on support, which is removable for storage - has steel plate supporting soil on which grass grows,with plate being raised by hydraulic jacks and moved on wheels
EP0467001A1 (en) Train for laying new tracks and method for their laying using such a train
EP3795448B1 (en) Device for lifting and transferring a railway vehicle off a railway track, and associated lifting and transfer method
EP0182958B1 (en) Track-handling apparatus for a railroad track section
EP0283391B1 (en) Method for the realisation of concrete structures such as bridge decks, and arrangement for its application
US1300255A (en) Track-laying machine.
FR2473599A1 (en) Manual tomb slab lifting hoist - has mobile lifting chassis running on removable rails
FR2845701A1 (en) Railway track laying procedure consists of making up track sections with temporary rails and permanent sleepers and replacing rails after laying
CH657650A5 (en) Apparatus for handling a railway gear panel
CH398663A (en) Equipment for laying sleepers on the ballast bed of a railway track
FR2467539A1 (en) Plant raising and handling frame - has roller mounted plant containers travelling on spindles acting as rails, to discharge point