CA2019776A1 - Procedure for making a liquid-tight wall in the ground and wall thus made - Google Patents

Procedure for making a liquid-tight wall in the ground and wall thus made

Info

Publication number
CA2019776A1
CA2019776A1 CA 2019776 CA2019776A CA2019776A1 CA 2019776 A1 CA2019776 A1 CA 2019776A1 CA 2019776 CA2019776 CA 2019776 CA 2019776 A CA2019776 A CA 2019776A CA 2019776 A1 CA2019776 A1 CA 2019776A1
Authority
CA
Canada
Prior art keywords
trench
joining
length
construction
auxiliary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
CA 2019776
Other languages
French (fr)
Inventor
Alexander Verstraeten
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Funderingstechnieken Verstraeten BV
Original Assignee
Funderingstechnieken Verstraeten BV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Funderingstechnieken Verstraeten BV filed Critical Funderingstechnieken Verstraeten BV
Publication of CA2019776A1 publication Critical patent/CA2019776A1/en
Abandoned legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/185Bulkheads or similar walls made solely of concrete in situ with flexible joint members between sections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • E02D19/185Joints between sheets constituting the sealing aprons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/182Bulkheads or similar walls made solely of concrete in situ using formworks to separate sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

ABSTRACT OF THE DISCLOSURE:

There is disclosed a procedure for making and a construction of a liquid-tight wall in the ground, according to which procedure and construction a trench is made in the ground, the trench is filled with cement, at least a length of sealing foil and at least an auxiliary construction for holding one side of the length in the trench are let down vertically and the auxiliary construction is later removed again from the trench. The procedure is simple to carry out and can also be used for great depths of the wall.

Description

2~1g77fi Procedure for makiny a liquid-tlght wall in the ground and wall thus made.
_____________________________________________~_____________ The invention relates to a procedure for making a liquid-tight wall in the ground, according to which procedure a trench is made in the ground, the trench is filled with cement, at least a length of sealing foil and at least an a ~ iliary construction for holding one side of t]le lenyth in the trench are let down vertically and the auxiliary construction is later removed again from the trench.

Procedures for making a liquid-tight wall are known whereby a sheet piling section is placed in a trench filled with bentonite cement prior to hardening or stiffening. These procedures are very difficult to apply with great depths. A large crane must be utilized for installing the sheet piling sections and often a vibrator rnust be utilizecl in order to overcome the friction of the overlappiny edges of the sections. The utilization of this known procedure is therefore very expensive.

That is why procedures were devised of the type referred to here whereby use is made of lengths of sealing foil in ulace of piling sections.

A procedure of this type is known from EP-A-O 292 765.
According to the procedure described in this patent application lengths of a plastic foil are placed one next to the other in a trench filled with bentonite. The vertically overlapping edges of these lengths are held in 2~77~

an auxiliary constructlon which is pumped out after placing the lengths. In the pumped out hollow auxiliary construction a welding apparatus i~ then introduced and with this the overlapping edges are welded to each other.
Through the necessity of pumping out the auxiliary construction and welding the edges to each other this known procedure is relatively laborious.

The purpose of the invention is to remedy these disadvantages and to provide a procedure for making a liquid-tight wall in the ground which is very simple and can also be easily utilized for great depths of the wall.

For this purpose a first trench of a wall part, called panel is dug and this is filled with cement, two auxiliary constructions are installed in this first trench, one at each extremity of the trench, with a slot provided with a seal over their height and on their sides facing each other and a length of sealing foil is lowered between these auxiliary constructions and a joining construction down on both edges thereof so that the length is connected by its edges to the auxiliary construction, in each auxiliary construction a joining part of the ~oining construction is present and the slots in the sides of the auxiliary constructlons are sealed, a second trench for a second panel is dug at a distance which is almost equal to the width of the length of sealing foil and this trench is filled with cement, two auxiliary constructions are installed therein in the manner described above with a length of sealing foil between them which is connected to these auxiliary constructions by auxiliary constructions of which a joininc~ part extends into the a~Kiliary constructions, subsequently an intermediate trench, which is filled with cement, is dug between the two trenches and thus between two auxiliary constructions, after sufficient hardening or stiffening of hardellable or stiffenable cement in the first and the second trench the two 2~:~977~
auxiliary constructions are removed from these trenches and finally in the ~llereby enlarqed intermediate trench, filled with cement, for a third panel a third length of sealing foil is installed with joining edges on its edges which work together with the joining parts of the lengths in the first and second trench after which, in as far as necessary, the wall is made further by forming a following panel each time at a distance of a panel at the extremity of the trench, in the manner described above for a first or second panel, and subsequently forming an intermediate panel between the two panels in the same manner as the third panel.

In a preferably applied embodiment of the invention the joining construction of the lengths in a first and a second trench is a separate joining element in relation to the length, which joining e]ement is installed with a joining part in an auxiliary construction and has a joining edge on its opposite edge which works together wlth a joining edge on an edge of the length.

It is desirable to install the joining element together with the corresponding auxiliary construction in the trench.

The joinir~g edge of a length of sealiny foil can be formed by a folded over edge which rorms a sleeve and a relatively stiff tube which is installed in this sleeve.

Suitably a rollable foil is utilized which is unwound from a drum in the trench, which foil is provided with Weigllts.

The invention also relates to a wall manufactured according to one of the preceding embodiments.

In order to show better the characteristics according to 20:~77 ~
the present invention, some preferred embodiments of a procedure for makiny a liquid-tight wall ln the ground and of a wall thus n~de according to the invention are described hereafter, as examples without any restrictive character, with reference to the enclosed drawings, in which:

Figures 1 through 8 are schematically Maintained horizontal cross-sectional representation of a wall during successive steps of its manufacture according to the procedure of the invention;
figure 9 represents a part from the cross-section ~: from figure 2 drawn on larger scale;
figure 10 represents a part of the cross-section from figuxe 3, also drawn on laxger scale;
figure 11 represents a part of the crass-section from figure 8, also drawn on larger scale;
: figure 12 is a detail from figure 10 drawn on still ::~ larger scale, and represented during a phase of the manufacture;
figure 13 represents the detail from figure 12 but in a later phase;
figure 14 represents a vertical cross-section of a :~ : trench after the installatlon of the auxiliary constructions but prior to the installation of a sealing foil;
figure 15 represents a vertical cross-section of a trench analogue to that from figure 14 but relating to a following phase of the procedure, namely during the installation of a sealing foil;
figure 16 represents a longitudinal vertical cross-section of a trench during the application of the procedure namely during the installation of a sealing foil in a trench.

In the various figures the same reference numbers relate ~ .:, .:

to the same elements. 2 ~ ~ ~ 7 7 ~3 For making a watertight wall 1 in the ground 2 the following will be effected accordiny to the invention.

A first trench 3 with a length of 3 to 8 meters and a width of 0.3 to 1.2 meters is dug with a trencher or trench excavator. During or immediately after the digging the trench 3 is filled with ~entonite 4 or a mixture of bentonite and cement. The condition as represented in figure 1 is obtained.

At both extremities of the trench 3 an auxiliary construction 5 is let down vertically into the ground.
This auxiliary construction 5 can consists of one element with a length of 12 to 16 meters or, if the trench 3 is dee~er consist of several elements placed abGve each other, as represented in figures 14 and 15.

As especially appears from figures 9 and 10 in which a cross-section of an auxiliary construction is represented, each auxiliary construction S contains a hollow tubular base 6 to which protruding sleeves 7 cvnnect on one side between whicl- a slot ~ is formed. Two compressed air hoses 10, which form seals, are glued in semicircular notches 9 in the two sleeves 7 on the extremity of the slot 8.

The width of the base 6 is of course equal to the width of the trench 3. The two auxiliary constructions 5 are so placed in the trench 3 that the slots 8 are directed with their open extremity toward each other. If the auxiliary construction 5 consists of several elements not only the base 6 and the sleeve 7 of the elements located above each other are connected to each other b-lt also the compressed air hoses 10 of these elements.

Before the two auxiliary construction 5 are let down into 2~1 ~77 ~
the trench 3, a joining construction 11 is coupled to each auxiliary construction 5 which, as especially appears from figures 9 anc1 10 consiqts of a st:lff metal strip 12 with a gutter-shaped ~oining element with C-shaped cross-section 13 respectively 14 on both edges. The two join~ng elements 13 and 14 consist of round tubes which are cut open on the side away from the strip 12. One of the joining elements 13 extends into the slot 8 of the auxiliary construction 5. The compressed air hoses 10 of the auxiliary construction 5 are inflated so that not only the ~lot 8 is sealed but also the joining construction 11 is fixed to the auxiliary construction 5.

As soon as the two auxiliary constructions 5 are fixed with the joining constructions 11 in the slot 3, a length of a supple foil of plastic such as polyethylene with high density starts to he lowered. As especially appears from figures 15 and 16, the foil is unwound from a drwn 16 mounted on a vehicle 17. In order to facilitate the lowerinq the bottom of the lenyth 15 is weighted with elements 18 of metal or concrete. The two edges of the length 15 are folded over and so attached to each other by means of sewing, gluing or fusing together, that a sleeve 19 is formed into which a perforated tube 20 is slid.
This tube 20 is made of plastic, relatively stiff but still supple enough to be able to be wound up on the drum 16. The diameter of the perforated tube 20 is smaller than the inside diameter of the joining elements 13 and 14. The length 15 has such a width that the two sleeves 19 with a perforated tube 20 therein formed on their edyes can slide into the joining elements 14 located outside the two joining constructions 11 as is represented in detail in figure 12. The tube 20 sits with some play in the joining element 14 but cannot get out of this joining element sideways because its diameter is greater than the slot in the joining element.

. .
:, .

-. ~.
- . .. ~ :. :~... . : ., . - ,: .-, 2~19~7~
As soon as the length 15 has reached the bottom of the trench, the foil is cut off above the ground and the upper extremity of the length 15 rests on the bottom. The vehicle 17 with the drum 16 can now be removed.

Subsequently the joining connection is further finished by in~ecting a swelling and stiffening liquid 21 such as a polyurethane mixture into the perforated tube 20. This liquid fills the entire inner space of the sleeve 19 through the perforations of the tube 20 and with that, especlally during the swelling, presses the sleeve 19 against the internal wall of the ~oining element 14 as represented in figure 13. After the swelling and stiffening of the liquid 21 the connection between the length 15 and the ~oining construction 11 is watertight.

If the length 15 was installed in a mixture of bentonite and cement, then this mixture is allowed to harden or stiffen and then the first panel 22 is ready. If the slot 3 was only filled with bentonite 4 or a tixotropic liquid, then after the installation of the length 15 this liquid is replaced by another cement 23 which hardens or stiffens. After the hardening or stiffening the first panel 22 and the condition represented in figure 2 is obtained.

In entirely the same manner as described above a second panels 22 is made at a distance from the first panel 22 that is somewhat smaller than the width of a length 15.
The manufacture of the second panel 22 is therefore also started with the digging of a trench 3 as represented in figure 3. After that 2 auxiliary constructions 5 are installed in this trench each of which is provided with a ~oining construction 11. Finally a length 15 of foil is installed between the ~oining constructions 11 after which either the original cement is allowed to harden or stiffen in the trench 3 if this was hardenable or stiffenable, or this original cement is replaced by new cement 23 which is , . ~

- 8 - ~977fi hardel1able or stiffenable which is then allowed to harden or stiffen The corldition represented in figure 4 with two cvmpletely formed panels 22 i9 obtalned.

After the cement of the two panels 22 is sufficiently stiffened and hardened, a third trench 24 is dug out between the two formed panels 22 and in fact between the two neighboring auxiliary constructions 5 of these panels as represented in figure 5. This intermediate trench 24 is immediately filled with bentonite 4.

The inter~diate panel 25 of the wall 1 is now formed in this intermediate trench as follows.

First of all the pressure is let out of the compressed air hoses IO of the two auxillary cons~ructions 5 on both sides of the intermediate trench 24 and these auxiliary constructions 5 are removed as represented in figure 7. A
lengthened intermediate trench 24 is now obtained into which the joining elements 13 extend, which were located in the last mentioned auxiliary constructions 5.

Into the intermediate trench 24 a length 15 is installed with edges formed by the sleeves 19 in which sits a perforated tube 20, in the joining elements 13 of the two aforementioned joining constructions. After filliny these sleeves 19 with a dilatable and stiffenable liquid 21 such as a polyurethane mixture, a watertight connection of this intermediate length 15 and the two joining constructions 11 is obtained.

After the replacement of the bentonite 4 by a stiffenable or hardenable rnixture 23 and the stiffening and hardening of this mixture, an intermediate panel 25 is obtained as represented in figure 7 and therefore a uninterrupted wall 1 in which a seal is continuously present, namely a seal formed by three lengths 15 and joining constructions 11 ,:
: ` ~

- 9 - 20~7~

situated between the lengtl1s.

On both sides of the wall 1 as represented in figure 7 this wall can now be further constructed as desired whereby therefore each time a following panel 22 is made in the above mentioned manner at a distance from the last panel and thereafter an intermediate panel 25 is made between these two panels 22.

In a variant of the above describtid embodirnent a length 15 of plastic foil is not used but a length of a metal foil.
The metal foil must be sufficiently pliable in order to be able to be rollecl up. The edges o~ the lengtl1 are then no~ forrned by sleeves but just folded over edyes of the metal foil. Because these edc3es have sufficiently stiffness the perforated tube 20 can be oMitted.

In another variant of the above described embodiment, an additional non-perforated supple tube is installed in the perforated tube 20 which at the bottorn ends under the tube 2G. During the lowering of the length 15 bentonite is pumped throuyl1 this additional tube which blows clean the inside of the correspQnding joining element 13 or 14 in which the sleeve 19 is installed and thereby facilitates the lowering. As soon as the lenyth 15 has reached the bottom of the trench 3 or the intermediate trench 24, this additlonal tube is withdrawn from the ground under simultaneous injection of the swelling liquid 21 which fills the perforated tube 20 and fills the corresponding sleeve 19 through the perforations.

In yet another variant of the above described embodiment no se~arate joining constructions 11 are used which are brought into the ground with the auxiliary constructions 5. The lenc~th 15 must then be provided with a joining construction on both sides which is identical to the part of the above described joinint3 constructiorl 11 that 20~977B

extends lnto an auxiliary construction 5. The jolning construction is then relatively supple since it must be capable of being rolled onto the drum 16.

Whatever the embodiment is, the procedure can be applied with relatively light cranes. The procedure can be utilized to any depth and on the spot welding is not necessary. The lengths 15 of foil can be taken relatively wide so that the number of connections between the lengths can be limited to a minimum.

The foil utilized fvr the length 15 is relatively inexpensive and, once it is in the ground in a hard or stiffened cement this foil is protected for ever and it can fulfill its watertight function.

The procedure is very fast and inexpensive.

The present invention is in no way restricted to the embodiments described above and shown in the figures, but such watertight walls can be implemented in different forms and dimensions and also the parts utillzed in the procedure can take different forms and dimensions, without departing from the scope of the present invention.

, . ,, - : ..
. . : .

Claims (14)

1. Procedure for making a liquid-tight wall (1) in the ground (2), according to which procedure a trench (3) is made in the ground, the trench (3) is filled with cement (4), at least a length ( 15 ) of sealing foil and at least an auxiliary construction (5) for holding one side of the length (15) in the trench (3) are let down vertically, and the auxiliary construction (5) is later removed again from the trench (3) characterized in that first a trench (3) is dug in order to make a wall part, called panel (22) and filled with cement (4), two auxiliary constructions (5) are installed in this first trench (3) one at each extremity of the trench (3) with a slot (8) provided with a seal (10) over their height and on their sides facing each other and a length (15) of sealing foil is lowered between these auxiliary constructions (5) and a joining construction (11) lowered onto both edges thereof so that the length (15) is connected by its edges to the auxiliary construction (5), in each auxiliary construction (5) a joining part (14) of the joining construction (11) is present and the slots (8) in the sides of the auxiliary constructions (5) are sealed, a second trench (3) for a second panel (22) is dug at a distance which is almost equal to the width of the length (15) of sealing foil and is filled with cement (4), two auxiliary constructions (5) are installed therein in the manner described above with a length (15) of sealing foil between them which is connected to these auxiliary constructions (5) by joining constructions (11) of which a joining part (14) extends into the auxiliary constructions (5), subsequently an intermediate trench (24) which is filled with cement (4) is dug between the two trenches (3) and thus between two auxiliary constructions (5), after sufficient hardening or stiffening of hardenable or stiffenable cement (4 or 23) in the first and the second trench (3) the two auxiliary constructions (5) are removed from these trenches (3) and finally in the thereby enlarged intermediate trench (24), filled with cement (4), for a third panel (25) a third length (15) of sealing foil is installed with joining edges (19, 20) on its edges which work together with the joining parts (14) of the lengths (15) in the first and second trench (3) after which, in as far as necessary, the wall is made further by forming a following panel (22) each time at a distance of a panel (22) at the extremity of the trench (3), in the manner described above for a first or second panel (22), and subsequently forming an intermediate panel (25) between the two panels (22) in the same manner as a third panel (25).
2. Procedure according to claim 1, characterized in that the joining construction (11) of the lengths (15) is a separate joining element in a first and a second trench (3) in relation to the length (15), which joining element is installed with a joining part (14) in an auxiliary construction (5) and has a joining edge (13) on its edge lying opposite which works together with a joining edge (19, 20) on an edge of the length (15).
3. Procedure according to claim 2, characterized in that the joining construction (11) is installed in the trench (3) together with the corresponding auxiliary construction (5).
4. Procedure according to one of the claims 2 and 3, characterized in that the joining edge (19, 20) of the length (15) in the first and second trench is equal to the joining edge (19, 20) of the length which is installed in the third trench.
5. Procedure according to one of the claims 2 through 4, characterized in that the joining edge (19, 20) of a length (15) of sealing foil is formed by a folded over edge which forms a sleeve (19) and a relatively stiff tube (9) installed therein.
6. Procedure according to one of the claims 2 through 5, characterized in that the joining edge (19, 20) of a length (15) is sealed in a joining edge (13) of a joining construction (11) after the installation by means of a dilatable and hardenable liquid (21).
7. Procedure according to the claims 5 and 6 characterized in that as tube (20) in a sleeve forming edge (19) of a length (15) a perforated tube is utilized and the dilatable hardenable liquid (21) is injected through this perforated tube.
8. Procedure according to one of the claims 5 and 7, characterized in that in order to facilitate the lowering of the length (15) into the tube (19) of a joining edge (19, 20) of the length (15) an additional tube is installed along which a lubricating liquid is squirted for cleaning the joining edge (13) of the joining construction (11) into which the joining edge (19, 20) of the length (11) must be brought.
9. Procedure according to one of the claims 2 through 8, characterized in that as joining construction (11) an element is utilized consisting of a relatively stiff strip (12) which carries a gutter-shaped joining element (13 and 14) on both edges which has the shape of a tube which is cut open on the side away from the strip (12) and through which the joining edge (19, 20) of a length (15) can not get out sideways.
10. Procedure according to one of the preceding claims, characterized in that as length (15) a length of rollable foil is utilized which is unwound from a drum (16), which foil is provided with weighting elements (18) in order to facilitate the lowering into a trench (3 or 24).
11. Procedure according to one of the preceding claims, characterized in that as auxiliary construction (5) an element is utilized that has a base (6), two protruding parts (7) standing thereon between which a slot (8) is formed for a joining construction (11) while the seal (10 ) is formed by two compressed air hoses (10) which are installed in notches (9) in the protruding parts (7), in the slot (8).
12. Procedure according to one of the preceding claims, characterized in that the trench (3 or 24) is first filled with bentonite or analogue liquid and after the installation of a length (15) in this trench (3 or 24) this liquid is replaced by a stiffenable or hardenable liquid (23).
13 . Procedure according to claim 1, characterized in that in the first and the second trench (3) a length (15) of foil is installed which is provided with the auxiliary construction (5) on its edges, which auxiliary construction (5) is brought with a joining part into an auxiliary construction (5) which joining part then after the digging of an intermediate trench (24) and the removal of the auxiliary construction (5) is made to work together with a joining edge (19, 20) of the length (15) which is installed in the intermediate trench for the formation of the third panel (25).
14. Wall manufactured according to the procedure according to one of the preceding claims.
CA 2019776 1989-06-30 1990-06-26 Procedure for making a liquid-tight wall in the ground and wall thus made Abandoned CA2019776A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NL8901669 1989-06-30
NL8901669A NL8901669A (en) 1989-06-30 1989-06-30 METHOD FOR MANUFACTURING A LIQUID-CLOSING WALL IN THE GROUND AND WALL MADE THEREFORE

Publications (1)

Publication Number Publication Date
CA2019776A1 true CA2019776A1 (en) 1990-12-31

Family

ID=19854941

Family Applications (1)

Application Number Title Priority Date Filing Date
CA 2019776 Abandoned CA2019776A1 (en) 1989-06-30 1990-06-26 Procedure for making a liquid-tight wall in the ground and wall thus made

Country Status (5)

Country Link
EP (1) EP0411682B1 (en)
BE (1) BE1003594A6 (en)
CA (1) CA2019776A1 (en)
DE (1) DE69001654T2 (en)
NL (1) NL8901669A (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4229941C2 (en) * 1992-09-08 1995-10-12 Bilfinger Berger Bau Process for the production of a sealing wall
DE9217609U1 (en) * 1992-12-23 1993-04-08 Bilfinger + Berger Bauaktiengesellschaft, 6800 Mannheim, De
FR2708946B1 (en) * 1993-08-11 1995-12-08 Spie Fondations Method for installing a seal between two panels of a diaphragm wall and device for implementing this method.
FR2747703B1 (en) * 1996-04-19 1999-05-07 Soc D Gestion De Brevets MOLDED WALL WITH CONTINUOUS REINFORCEMENT, METHOD FOR PRODUCING SUCH A MOLDED WALL IN THE GROUND, AND FORMWORK FOR MAKING SUCH A MOLDED WALL
GB2325262B (en) 1997-05-12 2001-05-02 Kvaerner Cementation Found Ltd Hydrophilic waterbar for diaphragm wall joints
DE102008039988A1 (en) 2008-08-27 2010-03-04 Matthias König Applying colmation layers in river banks and onto lake bed of water bodies in combination with inlake treatment of acidic and/or potentially acidic water, by applying and/or introducing lime- and dolomite products on and/or into water body
GB201112136D0 (en) 2011-07-14 2011-08-31 Coupland John W Diaphragm wall apparatus and methods
GB201706643D0 (en) 2017-04-26 2017-06-07 Ccmj Systems Ltd Diaphragm walls
GB2571097B (en) 2018-02-15 2021-08-25 Ccmj Systems Ltd Shear key former apparatus and method(s)
CN109626076A (en) * 2018-12-21 2019-04-16 四川正升环保科技有限公司 The vertical lower film machine of mobile antiseepage film
CN110130405B (en) * 2019-05-28 2020-12-04 中铁一局集团有限公司 Waterproof construction method for underground structure staged construction structural joint
CN114411695A (en) * 2022-01-24 2022-04-29 梁军 Construction method and connection structure of underground cast-in-place continuous wall

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3430790C2 (en) * 1984-08-22 1986-08-14 Ed. Züblin AG, 7000 Stuttgart Device for connecting drainage layers in diaphragm walls and method for using the device
DE3430791A1 (en) * 1984-08-22 1986-03-06 Ed. Züblin AG, 7000 Stuttgart Method of connecting sheeting sections in trench-wall-like sealing walls and apparatus for carrying out the method
DE3432706A1 (en) * 1984-09-06 1986-03-13 Ed. Züblin AG, 7000 Stuttgart Method for the subsequent placement of an additional seal in trench walls and device for carrying out the method
US4741644A (en) * 1985-04-11 1988-05-03 Finic, B.V. Environmental cut-off and drain
DE3727202A1 (en) * 1987-08-14 1989-03-02 Held & Francke Bau Ag Method of constructing sealing trench walls

Also Published As

Publication number Publication date
BE1003594A6 (en) 1992-04-28
NL8901669A (en) 1991-01-16
DE69001654D1 (en) 1993-06-24
DE69001654T2 (en) 1993-09-02
EP0411682B1 (en) 1993-05-19
EP0411682A1 (en) 1991-02-06

Similar Documents

Publication Publication Date Title
EP0135584B1 (en) Environmental cut-off for deep excavations
CA2019776A1 (en) Procedure for making a liquid-tight wall in the ground and wall thus made
JPS6122698B2 (en)
KR100923078B1 (en) Cofferdam Construction Method using Sheet File and Wale and Construction Method For Underwater Structure using the Cofferdam
US4582453A (en) Method and apparatus for in situ forming underground panelized concrete walls with improved joint structure
KR102249942B1 (en) Waling filler for CIP
US4459063A (en) Building construction
GB2136861A (en) Process for the construction of insulated sites in particular for the discharge of polluant products or the formation of impervious barricades or barriers, and works thereby constructed
KR101960489B1 (en) Underground column wall construction method using waterstop rubber and underground column wall therewith
CN1193675A (en) Underground walls for cast-in-situ concrete piles and constructioning process therefor
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
RU2262572C2 (en) Method for permanent sheet pile connection
JPH09268583A (en) Structural steel embedded half precast concrete member and construction method of underground structure using the same member
KR200363400Y1 (en) Frame to draw out H beam
JPS583091B2 (en) Construction method for underground column walls
EP0610992B1 (en) Method for providing a sheet pile wall in the ground and a prefabricated wall element for carrying out such method
JPS6011179B2 (en) Construction method of underground wall
JPS63277319A (en) Setting of friction pile
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPH05132930A (en) Developing method of foundation pile with drain layer
KR101835828B1 (en) Complex Steel Pipe Structure for Underground Wall and the Construction Method Using the Same
CN214784012U (en) Take braced system work well waterproof construction
JPS60181497A (en) Drilling method and apparatus for covering pipeline wall by water impermeable film
CN218713291U (en) Open caisson type inverse water collecting well system in comprehensive pipe gallery
JP3603272B2 (en) Underground continuous wall construction method and steel cage with outer shell

Legal Events

Date Code Title Description
FZDE Dead