BE893989A - Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid - Google Patents

Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid Download PDF

Info

Publication number
BE893989A
BE893989A BE0/208718A BE208718A BE893989A BE 893989 A BE893989 A BE 893989A BE 0/208718 A BE0/208718 A BE 0/208718A BE 208718 A BE208718 A BE 208718A BE 893989 A BE893989 A BE 893989A
Authority
BE
Belgium
Prior art keywords
frame
concrete
frames
prefabricated
reinforcements
Prior art date
Application number
BE0/208718A
Other languages
French (fr)
Original Assignee
Dynamique Du Batiment Dynabat
S P R L Ets E Ronveaux
Entpr S Louis De Waele S A
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dynamique Du Batiment Dynabat, S P R L Ets E Ronveaux, Entpr S Louis De Waele S A filed Critical Dynamique Du Batiment Dynabat
Priority to BE0/208718A priority Critical patent/BE893989A/en
Publication of BE893989A publication Critical patent/BE893989A/en
Priority to EP83870074A priority patent/EP0102340B1/en
Priority to DE8383870074T priority patent/DE3378135D1/en
Priority to AT83870074T priority patent/ATE37586T1/en
Priority to CA000433410A priority patent/CA1217349A/en
Priority to BR8304095A priority patent/BR8304095A/en
Priority to US06/518,752 priority patent/US4697955A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The method of constructing road tunnels, underground stations etc., uses sections of rectangular concrete tubing (1) with an external steel reinforcing mat (8) installed in an open trench. Wet concrete can then be poured over the sides and top before applying a covering layer. The walls of the prefabricated sections are thinner than usual, but after installation with the reinforcement and concrete covering, the whole has adequate strength. The interior surfaces (2) are smooth, and the outside surfaces are rough, to assist keying. In one form, the sides and top are supported by a thick plinth which extends sideways beyond the side walls. The reinforcement mat is then embedded in the projecting plinth portions. Additional internal central supports can be included.

Description

       

  Procédé de réalisation d'ouvrages en béton armé tels que galeries souterraines, tunnels routiers, etc. ; éléments en béton préfabriqués pour la réalisation de tels

  
ouvrage s . 

  
La présente invention se rapporte à la réalisation d'ouvrages en béton armé tels que galeries souterraines, tunnels routiers, tunnels pour métros, pertuis, bâtiments préfabriqués, etc. à l'aide d'éléments préfabriqués.

  
L'exécution de ces ouvrages à l'aide d'éléments préfabriqués donne lieu à une difficulté étant donné que d'une manière générale, d'une part,le poids des éléments est très important, et que d'autre part, l'encombrement de ces éléments rend difficile, voire impossible, le transport par convoi routier.

  
Le but de la présente invention est de remédier à cette difficulté, d'alléger au maximum

  
et de réduire les dimensions extérieures de ces éléments préfabriqués tout en conservant un parachèvement intérieur aussi proche que possible du parachèvement final et de permettre ainsi l'exécution du procédé dans des conditions particulièrement économiques.

  
En vue de la réalisation de ce but, le procédé objet de l'invention est caractérisé essentiellement en ce que l'on utilise en les juxtaposant des éléments de construction préfabriqués (appelés

  
 <EMI ID=1.1> 

  
dans un état se rapprochant le plus possible de l'état parachevé tandis que la face extérieure comporte des aspérités exécutées afin de permettre une collaboration ultérieure avec un béton d'apport qui est coulé de manière à enrober des armatures extérieures en acier rendues solidaires de l'élément ("prêcadre") en réalisant ainsi un cadre monolithique fini dont la résistance est nettement supérieure à celle du précadre initialement mis en place.

  
Dans la mise en pratique du procède, les armatures extérieures sont rendues solidaires de l'élément préfabriqué ("précadre") avant la mise en place de l'élément préfabriqué.

  
Une particularité essentielle de l'invention est l'élément en béton armé préfabriqué,en lui-même, dénommé "précadre", caractérisé en ce qu'il est constitué par un cadre dont la surface intérieure est en substance lisse se rapprochant le plus possible de l'état prévu

  
de parachèvement tandis que la face extérieure est munie

  
 <EMI ID=2.1> 

  
boration avec un béton d'apport, cet élément ("précadre") étant muni d'armatures extérieures rendues solidaires

  
 <EMI ID=3.1> 

  
Ci-après on décrira plus en détail en se référant aux dessins annexés, ces éléments préfabriqués ainsi que le mode d'exécution du procédé.

  
Sur les dessins ci-joints :

  
les figures 1, 2, 3 sont des vues en perspective montrant différentes réalisations de l'élément dit "précadre" ;

  
les figures 4 et 5 sont des vues illustrant la mise en place des éléments dans une fouille ; la figure 6 est relative à une variante d'élément "précadre" ;

  
les figures 7 et 8 montrent comment peut s'effectuer l'assemblage entre les "précadres" ; la figure 9 est une vue plus détaillée relative à la réalisation du "précadre".

  
L'élément "précadre" est un bloc creux

  
1 réalisé avec des parois en béton armé les plus minces possibles, c'est-à-dire dans la pratique de 5 à 15 cm d'épaisseur (figure 1).

  
La face intérieure 2 du précadre 1 est coulée généralement lisse autour d'un moule et de toute manière présente un aspect aussi proche que possible de l'aspect fini souhaité.

  
Par contre, la face extérieure est réalisée en béton rugueux soit sans coffrage extérieur, soit avec un coffrage comportant des irrégularités ou des empreintes aboutissant à créer une surface non lisse comportant des rugosités 3 (figures 1 et 9) .

  
En outre, la face extérieure (figure 9) comporte des armatures d'attente 4 et/ou des douilles d'ancrage 5 avec tiges filetées 9 et/ou des plaques métalliques 6 avec des doguets 7 et des cavaliers 10 ce qui permet de mettre en place après durcissement du béton et décoffrage du béton préfabriqué des armatures périphériques 8 qui seront fixées sur les armatures d'attente 4, sur les tiges filetées 9 ou sur les cavaliers 10.

  
Cette dernière opération peut être réalisée dans l'usine de préfabrication ou sur le chantier, avant la mise en oeuvre des éléments.

  
Etant donné que ces éléments sont destinés à être poses sur le sol nivelé 11 (figure 4), en surface du terrain ou dans une fouille 12 (figure 4), le futur radier 13 du "précadre" peut être réalisé dans son épaisseur définitive alors que les autres parois sont exécutées en faible épaisseur comme expliqué ci-dessus (figure 2) .

  
Le radier 13 comporte alors desexcroissances
14 à l'extérieur des parois verticales avec des armatures verticales 15 ancrées dans ces mêmes excroissances (figure 2).

  
Ceci permet d'éviter le bétonnage ultérieur entre la partie horizontale inférieure 16 du "précadre" (figure 5) et le niveau 11 du terrain, bétonnage qui peut éventuellement être rendu assez difficile si l'épaisseur complémentaire à bétonner est faible.

  
Par contre un "précadre" réalisé comme représenté à la figure 2 pèsera plus lourd et sera plus encombrant qu'un élément semblable suivant la figure 1.

  
Ce sont finalement des considérations de poids, de facilité de bétonnage et de mise en oeuvre qui guideront le choix entre ces deux types de "précadres"

  
Lorsque la portée horizontale de la toiture du "précadre" devient trop grande pour être franchie par une dalle de 5 à 15 cm d'épaisseur par exemple,

  
des étais provisoires 17 peuvent être prévus pour réduire cette portée (figure 2).

  
Ces étançons 17 seront maintenus en place pendant l'exécution du béton d'apport extérieur 18
(figure S) et ne seront enlevés qu'après durcissement de ce même béton jusqu'à ce qu'il ait atteint une résistance suffisante.

  
La figure 3 montre un "prêcadre" 1 comportant des éléments de finition intérieurs 19, en l'occurrence des éléments de quais pour une station de métro, les garde-corps de sécurité et les revêtements de parachèvement sur les sols, murs et plafonds. La figure 5 montre comme un "précadre" 1 peut être mis en place dans une fouille 12 comportant une paroi verticale blindée 20, par des palplanches
21 par exemple et une autre paroi 22 en talus assez raide compte tenu de la cohésion du terrain.

  
Dans une telle exécution : à l'aide d'une grue avec un palonnier 23 , le "précadre" 1 est mis en place au fond de la fouille 12. Il est réglé sur

  
quatre vérins 24 posés sur le fond de la fouille qui permettent d'assurer la mise en place du "précadre"  avec toute la précision requise.

  
 <EMI ID=4.1> 

  
réglé, des calages en bois, béton ou acier sont mis en place et coincés entre le "précadre" et le niveau d'assise sur le sol en permettant ainsi d'enlever et de récupérer les vérins de réglage.

  
Le bétonnage de seconde phase 18 (figure 5) est alors entrepris en noyant ces éléments de calage dans la masse de béton.

  
Les vérins provisoires peuvent être remplacés par des vérins-sacs perdus qui sont injectés d'un coulis de ciment pour assurer le réglage correct du "précadre" ; ces vérins ne nécessitent plus des dispositifs de calage et sont noyés dans la masse de béton , coulée sur le chantier à l'extérieur du "précadre".

  
Suivant la figure 5, ce béton de seconde phase sera coulé en dessous du précadre, de part et d'autre de celui-ci et au-dessus de celui-ci.

  
La figure 4 montre un "précadre" conforme à la figure 2 mis en place au fond d'une fouille 12 comportant un talus assez raide 22 et un autre talus 25

  
à faible pente.

  
Lorsque le talus 22 est raide, voire vertical

  
(20), le béton de seconde phase 18 sera mis en oeuvre entre ce talus et le "précadre".

  
Du côté du talus à faible pente 25, pour éviter de mettre en oeuvre des quantités de béton trop importantes, un coffrage vertical 26 (figure 4) est mis en place avec des appuis sur le talus. Ce coffrage 26 est récupérable après durcissement du béton.

  
Les figures 1 à 5 montrent des "précadres" de forme rectangulaire.

  
Il est bien entendu toutefois que ces "précadres" peuvent être d'une forme généralement quelconque comportant notamment des parties arrondies
(figure 6).

  
La figure 6 montre un élément de prëcadre typique pour la réalisation d'abris souterrains, de tunnels ou de stations de métro.

  
Les différents "précadres" sont mis en oeuvre sur le terrain 11 préalablement nivelé et sont juxtaposes de manière à réaliser l'ouvrage dans son ensemble.

  
Pour réaliser l'étanchéité éventuelle et la continuité entre les éléments, suivant l'invention il

  
est prévu de réaliser le bétonnage 18 de seconde phase

  
à cheval sur le joint 28 avec une armature éventuelle

  
de recouvrement 29 conformément à ce que montre la figure 7.

  
Chacun des deux "précadres" voisins peut comporter des armatures en attente 29 qui se recouvrent lors de la mise en oeuvre comme le montre la figure 8.

  
L'étanchéité éventuelle requise entre ces éléments est réalisée par des joints 30 périphériques

  
en matière compressible placés entre les "précadres" complétés éventuellement par deux rainures périphériques inversées 31 (figure 7) ou qui s'emboîtent (figure 8).

  
Dans le cas de la figure 7, cette rainure

  
31 est injectée d'un coulis de ciment 33 après réglage des éléments et durcissement du béton de seconde phase 18.

  
Dans le cas de la figure 8, ces rainures et excroissances agissent comme un tenon et une mortaise assurant un réglage automatiquement correct entre le nouvel élément mis en place et celui, en amont, qui est déjà réglé.

  
L'assemblage entre les éléments juxtaposés peut également se faire par des boulons 34 reliant des cornières métalliques 35 ancrées dans chacun des éléments juxtaposés.

  
Le béton d'apport peu\. être un béton classique composé de sable, gravier, ciment et eau ou un matériau spécial par exemple un matériau isotrope durcissable tel qu'un mélange de bentonite, de ciment et

  
d'eau.

  
Le matériau d'apport peut aussi comporter des fibres, résistant à la traction, en acier, verre, amiante ou autre matériau. 

REVENDICATIONS

  
1. Procédé de réalisation d'ouvrages en béton armé tels que tunnels routiers, galeries souterraines, tunnels pour métros, pertuis, bâtiments et autres ouvrages du même genre, caractérisé en ce que l'on utilise enles juxtaposant, des éléments de construction préfabriqués (appelés "précadres") en forme de blocs creux (1) dont la surface intérieure (2) est lisse

  
et dans un état se rapprochant le plus possible de l'état parachevé tandis que la face extérieure comporte des aspérités ou rugosités (3) exécutées afin de permettre une collaboration ultérieure avec un béton d'apport extérieur (18) qui est coulé de manière à enrober des armatures extérieures (8) en acier rendues solidaires

  
de l'élément ("précadre ") en réalisant ainsi un cadre monolithique fini dont la résistance est nettement supérieure à celle du précadre initialement mis en place.



  Method of making reinforced concrete structures such as underground galleries, road tunnels, etc. ; precast concrete elements for the realization of such

  
works .

  
The present invention relates to the production of reinforced concrete structures such as underground galleries, road tunnels, metro tunnels, trenches, prefabricated buildings, etc. using prefabricated elements.

  
The execution of these works using prefabricated elements gives rise to a difficulty given that in general, on the one hand, the weight of the elements is very important, and that on the other hand, the the size of these elements makes it difficult, if not impossible, to transport by road convoy.

  
The purpose of the present invention is to remedy this difficulty, to lighten as much as possible

  
and to reduce the external dimensions of these prefabricated elements while maintaining an internal finish as close as possible to the final finish and thus allow the execution of the process under particularly economical conditions.

  
With a view to achieving this aim, the process which is the subject of the invention is essentially characterized in that prefabricated building elements (called

  
 <EMI ID = 1.1>

  
in a state as close as possible to the finished state while the outer face has rough edges executed in order to allow a later collaboration with a filler concrete which is poured so as to coat external steel reinforcements made integral with the 'element ("preadframe") thereby achieving a finished monolithic frame whose resistance is significantly greater than that of the pre-frame initially put in place.

  
In putting the process into practice, the external reinforcements are made integral with the prefabricated element ("pre-frame") before the installation of the prefabricated element.

  
An essential feature of the invention is the precast reinforced concrete element, in itself, called "pre-frame", characterized in that it is constituted by a frame whose inner surface is substantially smooth as close as possible expected state

  
finishing while the outer face is provided

  
 <EMI ID = 2.1>

  
boration with filler concrete, this element ("pre-frame") being provided with external reinforcements made integral

  
 <EMI ID = 3.1>

  
Below we will describe in more detail with reference to the accompanying drawings, these prefabricated elements as well as the mode of execution of the method.

  
On the attached drawings:

  
Figures 1, 2, 3 are perspective views showing different embodiments of the element called "pre-frame";

  
Figures 4 and 5 are views illustrating the placement of the elements in a search; Figure 6 relates to a variant element "precadre";

  
Figures 7 and 8 show how can be done the assembly between the "pre-frames"; Figure 9 is a more detailed view relating to the realization of the "frame".

  
The element "pre-frame" is a hollow block

  
1 made with the thinnest reinforced concrete walls possible, that is to say in practice 5 to 15 cm thick (Figure 1).

  
The inner face 2 of the pre-frame 1 is cast generally smooth around a mold and in any case has an appearance as close as possible to the desired finished appearance.

  
On the other hand, the external face is made of rough concrete either without external formwork, or with a formwork comprising irregularities or indentations leading to creating a non-smooth surface comprising roughness 3 (Figures 1 and 9).

  
In addition, the external face (FIG. 9) has waiting reinforcements 4 and / or anchor sockets 5 with threaded rods 9 and / or metal plates 6 with doguets 7 and jumpers 10 which makes it possible to place in place after hardening of the concrete and stripping of the precast concrete of the peripheral reinforcements 8 which will be fixed on the waiting reinforcements 4, on the threaded rods 9 or on the jumpers 10.

  
This last operation can be carried out in the prefabrication plant or on the site, before the elements are implemented.

  
Since these elements are intended to be placed on the leveled ground 11 (figure 4), on the surface of the ground or in an excavation 12 (figure 4), the future slab 13 of the "precadre" can be made in its final thickness then that the other walls are made in thin thickness as explained above (Figure 2).

  
The raft 13 then has growths
14 outside the vertical walls with vertical reinforcements 15 anchored in these same protuberances (Figure 2).

  
This makes it possible to avoid subsequent concreting between the lower horizontal part 16 of the "pre-frame" (FIG. 5) and the level 11 of the ground, concreting which can possibly be made quite difficult if the additional thickness to be concreted is small.

  
On the other hand, a "frame" produced as shown in FIG. 2 will weigh heavier and will be more bulky than a similar element according to FIG. 1.

  
It is ultimately considerations of weight, ease of concreting and implementation that will guide the choice between these two types of "pre-frames"

  
When the horizontal span of the "precadre" roof becomes too large to be crossed by a slab 5 to 15 cm thick, for example,

  
provisional stays 17 can be provided to reduce this range (Figure 2).

  
These props 17 will be held in place during the execution of the external filler concrete 18
(Figure S) and will only be removed after hardening of the same concrete until it has reached sufficient strength.

  
FIG. 3 shows a "pre-frame" 1 comprising interior finishing elements 19, in this case platform elements for a metro station, security railings and finishing coatings on floors, walls and ceilings. FIG. 5 shows how a "pre-frame" 1 can be put in place in a dig 12 comprising an armored vertical wall 20, by sheet piles
21 for example and another wall 22 with a fairly steep slope taking into account the cohesion of the terrain.

  
In such an execution: using a crane with a lifting beam 23, the "pre-frame" 1 is placed at the bottom of the excavation 12. It is set to

  
four cylinders 24 placed on the bottom of the excavation which ensure the establishment of the "frame" with all the required precision.

  
 <EMI ID = 4.1>

  
adjusted, wooden, concrete or steel wedges are put in place and wedged between the "front frame" and the level of the seat on the ground, thus making it possible to remove and recover the adjustment cylinders.

  
The second phase concreting 18 (Figure 5) is then undertaken by drowning these wedging elements in the mass of concrete.

  
The temporary jacks can be replaced by lost bag jacks which are injected with a cement grout to ensure the correct setting of the "pre-frame"; these jacks no longer require wedging devices and are embedded in the mass of concrete, poured on the site outside the "frame".

  
According to FIG. 5, this second phase concrete will be poured below the pre-frame, on either side of it and above it.

  
FIG. 4 shows a "pre-frame" in accordance with FIG. 2 placed at the bottom of an excavation 12 comprising a fairly steep slope 22 and another slope 25

  
with a slight slope.

  
When the slope 22 is steep, even vertical

  
(20), the second phase concrete 18 will be used between this embankment and the "precadre".

  
On the side of the slope with a slight slope 25, to avoid using excessive quantities of concrete, a vertical formwork 26 (FIG. 4) is put in place with supports on the slope. This formwork 26 is recoverable after hardening of the concrete.

  
Figures 1 to 5 show "frames" of rectangular shape.

  
It is understood, however, that these "pre-frames" may be of any general shape, including in particular rounded parts.
(figure 6).

  
Figure 6 shows a typical pre-frame element for the construction of underground shelters, tunnels or metro stations.

  
The different "pre-frames" are implemented on the ground 11 previously leveled and are juxtaposed so as to produce the structure as a whole.

  
To achieve the possible seal and continuity between the elements, according to the invention there

  
second phase concreting 18 is planned

  
straddling joint 28 with a possible reinforcement

  
cover 29 in accordance with what FIG. 7 shows.

  
Each of the two neighboring "pre-frames" may include waiting reinforcements 29 which overlap during implementation as shown in FIG. 8.

  
Any sealing required between these elements is achieved by peripheral seals 30

  
in compressible material placed between the "pre-frames" possibly supplemented by two inverted peripheral grooves 31 (FIG. 7) or which fit together (FIG. 8).

  
In the case of FIG. 7, this groove

  
31 is injected with a cement grout 33 after adjustment of the elements and hardening of the second phase concrete 18.

  
In the case of FIG. 8, these grooves and protrusions act like a tenon and a mortise ensuring an automatically correct adjustment between the new element put in place and that, upstream, which is already adjusted.

  
The assembly between the juxtaposed elements can also be done by bolts 34 connecting metal angles 35 anchored in each of the juxtaposed elements.

  
Filler concrete little \. be a conventional concrete composed of sand, gravel, cement and water or a special material for example an isotropic hardening material such as a mixture of bentonite, cement and

  
of water.

  
The filler material may also include fibers, tensile strength, steel, glass, asbestos or other material.

CLAIMS

  
1. Method for making reinforced concrete structures such as road tunnels, underground galleries, metro tunnels, sluices, buildings and other similar structures, characterized in that prefabricated construction elements are used in juxtaposition ( called "pre-frames") in the form of hollow blocks (1) whose interior surface (2) is smooth

  
and in a state as close as possible to the finished state while the outer face has roughness or roughness (3) executed to allow subsequent collaboration with an external filler concrete (18) which is poured so as coat steel external frames (8) made integral

  
of the element ("pre-frame"), thereby producing a finished monolithic frame whose resistance is much higher than that of the pre-frame initially put in place.


    

Claims (1)

2. Procédé suivant la revendication 1, caractérisé en ce que les armatures extérieures (8) sont rendues solidaires de l'élément préfabriqué ("précadre") avant la mise en place de l'élément préfabriqué. 2. Method according to claim 1, characterized in that the external reinforcements (8) are made integral with the prefabricated element ("pre-frame") before the establishment of the prefabricated element. 3. Elément en béton armé préfabriqué,caractérisé en ce qu'il est constitué par un cadre dont la surface intérieure (2) est en substance lisse se rapprochant le plus possible de l'état prévu de parachèvement tandis que la face extérieure est munie d'une rugosité (3) choisie de manière à permettre une collaboration avec un béton d'apport (18), cet élément ("prëcadre") étant muni d'armatures extérieures (8) rendues solidaires de l'élément ("précadre") avant 3. Prefabricated reinforced concrete element, characterized in that it is constituted by a frame, the internal surface (2) of which is substantially smooth, as close as possible to the intended state of completion while the external face is provided with '' a roughness (3) chosen so as to allow collaboration with a filler concrete (18), this element ("pre-frame") being provided with external reinforcements (8) made integral with the element ("pre-frame") before sa mise en place. its implementation. 4. Elément en béton armé préfabriqué suivant la revendication 3, caractérisé en ce qu'il est réalisé avec des parois les plus minces possibles <EMI ID=5.1> 4. Precast reinforced concrete element according to claim 3, characterized in that it is produced with the thinnest possible walls <EMI ID = 5.1> 5. Elément en béton armé préfabriqué suivant la revendication 3, caractérisé en ce que la face extérieure de l'élément comporte des armatures d'attente 5. Prefabricated reinforced concrete element according to claim 3, characterized in that the external face of the element comprises waiting reinforcements (4) et/ou des douilles d'ancrage (5) avec tiges filetées (4) and / or anchor sleeves (5) with threaded rods (9) et/ou des plaques métalliques (6) avec des doguets (9) and / or metal plates (6) with doguets (7) et des cavaliers (10), ce qui permet de mettre (7) and jumpers (10), which allows you to put en place, après durcissement et décoffrage du béton préfabriqué, des armatures périphériques (8) qui in place, after hardening and formwork of the precast concrete, peripheral reinforcements (8) which seront fixées sur les armatures d'attente (4), sur les tiges filetées (9) ou sur les cavaliers (10), cette dernière opération pouvant se faire dans l'usine de préfabrication ou sur le chantier avant la mise en oeuvre des éléments. will be fixed on the waiting frames (4), on the threaded rods (9) or on the jumpers (10), this last operation can be done in the prefabrication factory or on the site before the implementation of the elements . 6. Elément en béton préfabriqué suivant 6. Prefabricated concrete element according to la revendication 3, caractérisé en ce que, comme les <EMI ID=6.1> claim 3, characterized in that, like the <EMI ID = 6.1> le sol nivelé en surface du terrain ou dans une fouille, le radier (13) du précadre peut être réalisé dans son épaisseur définitive alors que les autres parois sont exécutées en faible épaisseur, ce radier donnant alors lieu à des excroissances (14) à l'extérieur des parties verticales avec des armatures verticales (15) ancrées dans ces excroissances. the ground leveled on the surface of the ground or in an excavation, the raft (13) of the pre-frame can be made in its final thickness while the other walls are made in thin thickness, this raft then giving rise to outgrowths (14) at the exterior of the vertical parts with vertical frames (15) anchored in these protuberances. 7. Elément en béton préfabriqué suivant 7. Prefabricated concrete element according to la revendication 3, caractérisé en ce que le précadre peut comprendre des étais provisoires (17), lorsque claim 3, characterized in that the pre-frame may include temporary stays (17), when la portée horizontale de la toiture du précadre est trop grande. the horizontal span of the roof of the pre-frame is too large. 8. Elément en béton préfabriqué suivant la revendication 3, caractérisé en ce que le précadre 8. Precast concrete element according to claim 3, characterized in that the pre-frame peut comporter des éléments de finition intérieurs may have interior finishers (19) par exemple des éléments de quais dans une station de métro, des garde-corps de sécurité, des revêtements de parachèvement sur les quais, murs et plafonds. 9. Procédé suivant la revendication 1, caractérisé en ce que le sol est préalablement nivelé, dans une fouille ouverte, blindée ou sous boue thixotropique, qu'un "précadre" selon l'une quelconque des revendications 3 à 8 est ensuite mis en oeuvre sur quatre vérins de réglage (24) prenant appui sur le niveau d'assise du sol, que ces vérins sont réglés pour mettre (19) for example platform elements in a metro station, security railings, coverings on platforms, walls and ceilings. 9. Method according to claim 1, characterized in that the soil is previously leveled, in an open excavation, armored or under thixotropic mud, that a "pre-frame" according to any one of claims 3 to 8 is then implemented on four adjustment cylinders (24) bearing on the ground level of the ground, that these cylinders are adjusted to put <EMI ID=7.1>  <EMI ID = 7.1> de calage en bois, béton ou acier sont ensuite coincés entre la partie inférieure du précadre et le niveau wedging in wood, concrete or steel are then wedged between the lower part of the pre-frame and the level du sol permettant l'enlèvement et la récupération soil for removal and recovery des vérins tout en maintenant le "précadre" dans sa position correcte, qu'ensuite un béton d'apport (18) est coulé sur le chantier en prenant appui d'une part sur cylinders while maintaining the "frame" in its correct position, then a filler concrete (18) is poured on the site by taking support on the one hand on le "précadre" et d'autre part sur les talus environnants ou sur des éléments de coffrages extérieurs. the "pre-frame" and on the other hand on the surrounding slopes or on external formwork elements. 10. Procédé selon la revendication 9, caractérisé en ce que les vérins provisoires sont remplacés par des vérins-sacs perdus qui sont injectés d'un coulis de ciment pour assurer le réglage correct 10. Method according to claim 9, characterized in that the temporary jacks are replaced by lost bag jacks which are injected with a cement grout to ensure the correct adjustment du "précadre", que ces vérins ne nécessitent plus les dispositifs de calage et qu'ils sont noyés dans la masse de béton coulée sur le chantier à l'extérieur "pre-frame", that these cylinders no longer require wedging devices and that they are embedded in the mass of concrete poured on the site outside du précadre. of the frame. 11. Procédé selon les revendications 1, 2, 11. Method according to claims 1, 2, 9 et 10, caractérisé en ce que des joints d'étanchéité périphériques (30) en matière compressible sont prévus entre les différents "précadres" pour assurer leur étanchéité ultérieure après mise en oeuvre, ces "prêcadres" étant éventuellement complétés par des rainures périphériques inversées (31) ou qui s'emboîtent (figure 8). 9 and 10, characterized in that peripheral seals (30) in compressible material are provided between the different "pre-frames" to ensure their subsequent sealing after implementation, these "pre-frames" being optionally supplemented by inverted peripheral grooves (31) or which fit together (figure 8). 12. Procédé de construction selon l'une quelconque des revendications 1, 2, 9, 10, 11, caractérisé en ce que des rainures sont conçues dans la péri-phêrie des faces en contact de deux "précadres" et 12. Construction method according to any one of claims 1, 2, 9, 10, 11, characterized in that grooves are designed in the periphery of the contacting faces of two "pre-frames" and que ces rainures sont injectées d'un coulis de ciment that these grooves are injected with a cement grout (33) après réglage définitif et durcissement du béton d'apport. (33) after final adjustment and hardening of the filler concrete. 13. Procédé suivant l'une quelconque des revendications 1, 2, 9 à 12, caractérisé en ce que la continuité entre les précadres successifs est réalisée par boulonnage, accrochage, post-contrainte ou bétonnage complémentaire à cheval sur le joint (figures 7 et 8) . 13. Method according to any one of claims 1, 2, 9 to 12, characterized in that the continuity between the successive pre-frames is achieved by bolting, hanging, post-stressing or additional concreting straddling the joint (Figures 7 and 8). 14. Procédé de construction suivant l'une quelconque des revendications 1, 2, 9 à 13, caractérisé en ce que le matériau d'apport coulé à l'extérieur 14. Construction method according to any one of claims 1, 2, 9 to 13, characterized in that the filler material poured outside des "précadres" est un béton classique ou un matériau isotrope durcissable tel qu'un mélange de bentonite, "pre-frames" is a conventional concrete or an isotropic hardening material such as a bentonite mixture, de ciment et d'eau. cement and water. 15. Procédé suivant l'une quelconque des revendications 1, 2, 9 à 14, caractérisé en ce que le matériau d'apport comporte des fibres, résistant à la traction, en acier, verre, amiante ou matériau similaire. 15. Method according to any one of claims 1, 2, 9 to 14, characterized in that the filler material comprises fibers, tensile resistant, steel, glass, asbestos or similar material.
BE0/208718A 1982-07-30 1982-07-30 Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid BE893989A (en)

Priority Applications (7)

Application Number Priority Date Filing Date Title
BE0/208718A BE893989A (en) 1982-07-30 1982-07-30 Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid
EP83870074A EP0102340B1 (en) 1982-07-30 1983-07-27 Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions
DE8383870074T DE3378135D1 (en) 1982-07-30 1983-07-27 Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions
AT83870074T ATE37586T1 (en) 1982-07-30 1983-07-27 PROCESSES FOR MANUFACTURING REINFORCED CONCRETE STRUCTURES SUCH AS UNDERGROUND PATHWAYS, ROAD TUNNELS, ETC; PREFABRICATED CONCRETE ELEMENTS FOR THE MANUFACTURE OF SUCH BUILDINGS.
CA000433410A CA1217349A (en) 1982-07-30 1983-07-28 Engineering of reinforced concrete structures, such as tunnels, underpasses and the like, and precast concrete elements used in said engineering processes
BR8304095A BR8304095A (en) 1982-07-30 1983-07-29 PROCESS FOR CARRYING OUT ARMED CONCRETE WORKS AS IN TRAFFIC TUNNELS, UNDERGROUND GALLERIES, METER TUNNELS AND PREFABRICATED CONCRETE ELEMENT
US06/518,752 US4697955A (en) 1982-07-30 1983-07-29 Method of constructing reinforced concrete works such as underground galleries, road tunnels, et cetera; pre-fabricated contrete elements for constructing such works

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
BE0/208718A BE893989A (en) 1982-07-30 1982-07-30 Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid

Publications (1)

Publication Number Publication Date
BE893989A true BE893989A (en) 1983-01-31

Family

ID=3843549

Family Applications (1)

Application Number Title Priority Date Filing Date
BE0/208718A BE893989A (en) 1982-07-30 1982-07-30 Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid

Country Status (1)

Country Link
BE (1) BE893989A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061709A (en) * 2010-12-15 2011-05-18 河海大学 Engineering machinery construction channel in debris flow state alluvial soil area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061709A (en) * 2010-12-15 2011-05-18 河海大学 Engineering machinery construction channel in debris flow state alluvial soil area

Similar Documents

Publication Publication Date Title
EP0102340B1 (en) Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions
EP0185065B1 (en) Method for making a rigid slab able to support a building
CA1319261C (en) Cellular structures for retaining wall
WO1983001823A1 (en) Method for obtaining hollow structures, such as conduits, silos or shelters and structures obtained by such method
KR101005780B1 (en) Underground constructure form system for preventing concretes of underground slab and girder from crack
EP0089861B1 (en) Method of reinforcing arches or similar constructions
EP0244890B1 (en) Process for producing hollow structures such as ducts, silos, or shelters, and structures obtained by this process
FR2903437A1 (en) Prefabricated element for forming e.g. reinforced concrete wall e.g. bridge pillar, has metallic beam extending along longitudinal direction and comprising lower head beam drowned in plate extending between two spaced lateral sides
FR2687711A1 (en) Method for constructing a building, such as an underground shelter, by assembly of prefabricated elements
BE893989A (en) Prefabricated concrete road tunnel - is made of thin walled sections in open cutting with wet concrete poured over reinforcing grid
EP0042024B1 (en) Method of producing at the site and without formwork masonry partition walls in reinforced concrete
FR2939817A1 (en) Prefabricated elementary block for constructing e.g. outer insulating wall of building, has connection elements connecting reinforcement structures to fix inner bearing wall and outer protective shell to maintain constant transversal gap
BE1004988A4 (en) SET OF ELEMENTS FOR erect WALLS OF A HOUSE.
EP0784128B1 (en) Process for the manufacturing of a half timbered panel, panel obtained by the process and construction comprising at least one such panel
FR2959253A1 (en) MOLDED WALL WITH PREFABRICATED FACING
JP3108565B2 (en) Assembly blocks for underground structures
EP0423105A1 (en) Prefabricated structural element to be used as a cellar
FR2535373A1 (en) Construction of a swimming pool made from reinforced concrete by prefabrication.
FR2467923A2 (en) Tied industrialised building frame - is formed by slab edge grooves and ducts with column reinforcement in slab at duct
BE541742A (en)
FR2744471A1 (en) Prefabricated hollow brick modules for cladding, load bearing walls, acoustic insulation, low walls and other construction
JP2023001683A (en) Construction method of underground structure and underground structure as well as precast concrete side wall or intermediate wall/column therefor
EP1045091B1 (en) Construction element reinforcement method
JPH1121860A (en) Construction method for wall-form concrete structure
EP1248890B1 (en) Method for constructing a building

Legal Events

Date Code Title Description
RE Patent lapsed

Owner name: DYNAMIQUE DU BATIMENT DYNABAT S.A.

Effective date: 19970731

Owner name: S.P.R.L. ETS E. RONVEAUX

Effective date: 19970731

Owner name: LES ENTREPRISES LOUIS DE WAELE S.A.

Effective date: 19970731