Prior art keywords
pile
concrete
lining
sheaths
mixed
Prior art date
Application number
Other languages
French (fr)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Publication of BE720112A publication Critical patent/BE720112A/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

  

   <Desc/Clms Page number 1> 
 



  "   Procède   de fabrication d'un pieu de fonçage mixte et dispositif pour sa mise en oeuvre" 
La présente invention se rapporte à un procédé de fabrication d'un pieu de fonoage mixte comprenant une semelle et un corps plus petit, rattanché   oelle-oi,   se composant   d'aoier   ou de béton armé   d'acier   et susceptible de présenter à son extrémité supérieure un bourrelet d'ar- rêt pour le trou du pieu, le béton de garniture étant in- troduit autour de ce   corps.   



   Il existe une série complète de pieux de   fonça.   
 EMI1.1 
 se mixtes, dans lesquels la oemelle ;;ler(1).lemnt pieu est plus grande de tous côtés que le corps de   colu@@@si et   où la gaina de béton de garniture défoncée libremen par la semelle du pieu   en%   remplie progressivement de   @@ut en   bas pondant le fonçage ou progressivement de brai   ou haut   après le foncage, au moyen de tubes d'alimentation prévus   expressément   dans ce but. 

 <Desc/Clms Page number 2> 

 



   Les semelles de ces pieux, ainsi que les tubes limentation pour le remplissage de la gaine de béton de garniture à l'aide de lait de ciment, sont très coû-   teux.   Le remplissage parfait des gaines de béton de garni- ture est fréquemment défectueux lorsque par suite des   vi.   brations du fonçage, des détériorations se produisent sur les tubes d'alimentation, lesquelles bouchent ces derniers ou provoquent un émiettement du sol dans le trou de fonça- ge en cas de terres mouvantes. 



   Le problème posé par la présente invention con-   siste à   éliminer ces inconvénients et à réaliser un pieu de fonçage mixte à l'aide duquel un bouohage des tubes d'alimentation pour le béton de garniture est évité dans la zone du corps du pieu. 



   Oe problème est résolu conformément à l'inven- tion, en ce sens que des gaines de béton de garniture se développant parallèlement à l'axe longitudinal du pieu sont formées et que le béton de garniture est introduit par coulée de haut en bas dans l'une des gaines pendant le fonçage et est ramené de bas en haut dans l'autre gai- ne. 



   Dans la présente invention, on part donc du fait que la force portante des pieux de foncage mixtes est relativement faible en général h proximité de la sur- face du sol et qu'élis atteint un maximum uu voisinage du corps du pieu. Il en résulte qu'en utilisant des corps de pieux légèrement plue grands, mais des   semelles     beau-   coup plus petites qua selles des pieux connus, on parvient à une force portante identique ou même plus grande que celle obtenue précédemment aveo les pieux connus, 
Dès lors, les semelles des pieux sont conçues de telle sorte qu'elles ne saillent pas trop largement au- delà du profil du corps de pieu* 

 <Desc/Clms Page number 3> 

 
En outre, dans la présente invention, le profil de la semelle du pieu saille, au moins en deux endroits,

   non au-delà du profil du corps de pieu ou tout au moins de plus grandes parties de   ce corps.   De préférence,   ces   parties de semelles de pieu ne saillant pas au-delà du profil du corps sont maintenues petites. Il en résulte, dans les pieux conformes à l'invention, que le corps n'est      pas muni d'une gaine de béton enoerolante sur sa longueur entière. On obtient ainsi au moins deux coquilles de béton de garniture qui ne sont en général reliée l'une à l'autre qu'à un seul endroit à proximité du corps de pieu, 
La gaine de garniture se subdivise, autour du corps de pieu, en deux coquilles séparées au moins.

   Par conséquent, il est possible, au cours du fonçage, de pres- ser le béton de garniture vers le bas, jusqu'à la semelle de pieu approximativement, par l'une des deux gaines au moins, de l'introduire également dans la seconde gaine par une liaison existant à proximité de lasemelle de pieu entre les deux gaines et de le refouler ensuite vers le haut par la seconde gaine jusqu'à la surface du sol. Dès lors, une gaine au moins est remplie en continu et pro- gressivement par une coulée de haut en bas pendant le foncage et l'autre gaine est comblée par le refoulement de bas en haut. 



   Ce système de remplissage est exempt de tubes sur la longueur entière du pieu, Une simple étanchéité entre le corps du pieu et la paroi de terre d'une gaine est exclusivement nécessaire à proximité de la surface du sol, le béton de garniture étant amené dans l'une des deux gaines par l'intermédiaire de cette étanchéité. Le remplis- sage précis de la gaine est garanti lorsque le béton de garniture, introduit sur l'une des faces du pieu, est refoulé vers le haut en continu et   progressivement   avec le fonçage sur l'autre face du pieu jusqu'à la surface du sol 

 <Desc/Clms Page number 4> 

 et qu'une petite quantité de béton-déborde constamment sur   celle-ci.   Ce prooédé peut être   contrôlé   visuellement. 



   Le   procède   déorit ci-avant peut être mis en oeuvre avec plein succès conformément à l'invention en   utilisant   des pieux dont le corps n'est pas rétréci par rapport à la semelle de pieu sur des distances plus lon- gues ou plus courtes,   o'est-à-dire   des pieux qui présen- tent des colleta. 



   Dans ces pieux, il doit être garanti qu'un con- duit pour la coulée vers le bas d'un béton de garniture soit prévu d'un coté dans le collet sur la partie non   ré-   trécie du corps de pieu et qu'un conduit similaire soit formé librement sur l'autre face du collet pour le refou- lement vers le haut du béton de garniture. 



   A la place de l'appareil de remplissage usuel, il peut également être utilisé un simple dispositif de remplissage, où la pression désirée est déterminée   simple..   ment par un levage ou un abaissement de ce dispositif au- dessus de la surface du sol. 



   Des dispositifs de retenue, transmettant des fractions de charge absorbées par le béton de garniture directement au corps de pieu, peuvent être prévue sur   ce   dernier. 



   D'autres particularités de l'invention se déga- gent de la   description   ci-après réalisée à l'aide des exem. ples de réalisation représentés aux dessina annexée dans lesquels! la figure 1 est un pieu de fonçage mixte en vue latérale; la figure 2 est une coupe d'un pieu de fonçage mixte comprenant de très petites gaines de béton de garni- ture; la figure 3 est une coupe d'un pieu de fonçage mixte équipé de gaines de béton de garniture plus larges, 

 <Desc/Clms Page number 5> 

 la figure   4   est une coupe d'un pieu de fonçage mixte dont le corps est rond; la figure 5 est une coupe d'un pieu de fonçage mixte dont le corps su compose d'un profilé on forme de palplanche; la figure 6 est une coupe d'un pieu de fonçage mixte doté d'un corps à section transversale en forme de double T ;

   la figure 7 est une vue en perspective d'un pieu de fonçage mixte équipé d'un corps à section transversale en double T et d'une aile inférieure et supérieure. 



   Le mode opératoire du   prédé   conforme à l'in- vention est le suivant : le pieu représenté à la figure 1 comprend une semelle 1 et un corps 2 ainsi qu'un renforce- ment inférieur 3 et un renforcement supérieur 4 du corps      de pieu. Sur la longueur entière du corps 2, on a prévu une nervure de corps 5 qui se prolonge vers le bas jus- qu'à proximité de la semelle 1 et qui, dans le présent exemple,   saille   avec un tranchant au-delà du profil de la semelle. Une nervure similaire 5, pratiquée sur la face opposée du corps de pieu 2, correspond à la première .nervure précitée. Des conduits 6 et 7 sont pratiques sur l'une des faces du pieu dans les deux renforcements 3 et 4 et des conduits 8 et 9, disposés sur l'autre face du pieu, correspondent également aux conduits cités en premier lieu.

   Lorsque le pieu est enfoncé, la gaine de garniture 10 défoncée librement par la semelle sur l'une des faces du pieu est remplie de béton en continu par coulée de haut en bas progressivement avec le fonçage, une partie du béton étant pressée dans la gaine de garniture 13 sur l'au- tre face du pieu par l'ouverture 12 comprise entre la se- melle 1 et la nervure 5 du corps de pieu 2. Lorsque le ren- 

 <Desc/Clms Page number 6> 

 forcement 3 du corps 2 pénètre dans le sol au cours du fonçage, le béton de garniture est refoulé intérieurement dans la gaine 10 par le conduit 6 du renforcement 3 et est forcé ensuite vers le haut dans la gaine 13 par l'ouvertu- re 12.

   Ce béton est ensuite ramené en partie à la surface de la terre par le conduit 8 du renforcement   3.'Le   procédé de remplissage de la gaine 11 comprise entre les deux ren- forcements 3 et 4 sur l'une des faces du pieu et de l'au- tre gaine 14 sur l'autre face du pieu est similaire à celui   prédécrit.   Si, au cours du fonçage, le renforcement supérieur 4 pénètre dans le sol, le béton de garniture est pressé vers le bas dans la gaine 11 par le conduit 7 et dans la gaine 10 par le conduit 6 et est ensuite refoulé vers le haut dans la gaine 13 par l'ouverture 12 et dans la gaine 14 par la conduit 8. Il parvient finalement à la surface du sol par le oonduit 9. 



   Les figures 2,3, 4,5 et 6 représentent des coupes de différents exemples de réalisation de profils de corps et de semelles de pieux. La figure 2 montre un profil de corps de pieu 18 qui saille au-delà du profil de semelle 42, ainsi qu'un profil de corps 19 qui est à fleur du profil de semelle 42. Ces deux profils de corps 18 et 
19 correspondent aux profils 20et   21   prévus sur l'autre faoe du pieu. Le béton de garniture peut être pressé vers le bas par l'intermédiaire d" conduit 22 compris entre la terre et le corps de pieu, formé librement par la semelle 42 et limité par les profils de corps 18 et 19. Ce béton peut être forcé vers le haut par la gaine entière restante 45. La même disposition est reproduite à la figure 3. La gaine 44 est interrompue par les profils de corps 23,24 et 25.

   Si on supprime le profil 25, le béton de garniture descend sur l'une des faces de la gaine 44 et remonte sur l'autre face de cette faine 44. En revanche, si on supprime le profil 23, le béton de garniture   dépend   par le conduit 26 et remontepar la gaine 44 restante, enrôlant la preo- 

 <Desc/Clms Page number 7> 

 que totalité du corps de pieu. La figure 4 montre que le procédé peut être mis en oeuvre également pour des corps de pieux ronds, lorsque la terre 28 contacte à deux en- droit le profil rond 27 du corps de pieu. On obtient ainsi la gaine 29 qui peut être remplie de   bdton   par une coulée de haut en bas, et la   gaina 30   qui peut être comblée par une remontée du béton.

   La figure 5 représente un profilé en forme de palplanche 31 qui présente, d'une part, de minces semelles 32 et 33 et d'autre part, une large semelle 34. Les raocords 35 et 36 du palplanche sont si- tués à l'extérieur du corps et divisent ainsi la gaine en deux coquilles, A la figure 6, on a représenté un coprs de fonçage   37,   dans lequel la gaine 39 est remplie par l'intermédiaire de la gaine 38 et la gaine 41 par la gaine 40. La figure 7 représente finalement un profilé 46 à sec- tion transversale en forme de double T, comprenant une aile inférieure 47 aveo des semelles 48, ainsi qu'une aile supérieure 49 dotée d'un renforcement 50 et d'une conduite 51 pour le béton de garniture.

   En outre, on a reproduit l'armature en béton 52 et les ouvertures 53 servant au passage du béton de garniture et permettant la coulée vers le bas de celui-ci dans l'une des gaines et la remontée du béton dans l'autre gaine. 



  REVENDICATIONS 

**ATTENTION** fin du champ DESC peut contenir debut de CLMS **.



   <Desc / Clms Page number 1>
 



  "Method of manufacturing a mixed driving pile and device for its implementation"
The present invention relates to a method of manufacturing a mixed fonoage pile comprising a sole and a smaller body, joined together oelle-oi, consisting of aoier or steel reinforced concrete and capable of having at its end at the top, a stop bead for the hole in the pile, the concrete filling being introduced around this body.



   There is a complete set of shank piles.
 EMI1.1
 mixed, in which the oemelle ;; ler (1) .lemnt pile is larger on all sides than the body of colu @@@ if and where the sheath of concrete of filling broken free by the sole of the pile in% gradually filled from @@ ut at the bottom laying the sinking or gradually of pitch or high after sinking, by means of feed tubes provided expressly for this purpose.

 <Desc / Clms Page number 2>

 



   The footings of these piles, as well as the feed tubes for filling the concrete lining sheath with cement milk, are very expensive. The perfect filling of concrete lining ducts is frequently defective when, as a result of vi. When driving, damage occurs to the feed pipes, which clogs them or causes the soil to crumble in the sinking hole in the event of shifting soil.



   The problem posed by the present invention consists in eliminating these drawbacks and in providing a mixed jacking pile by means of which plugging of the feed pipes for the filling concrete is avoided in the area of the pile body.



   This problem is solved according to the invention, in that sheaths of concrete lining extending parallel to the longitudinal axis of the pile are formed and the lining concrete is poured from top to bottom into the pile. 'one of the ducts during driving and is brought back upwards in the other duct.



   In the present invention, therefore, it is assumed that the load-bearing force of the mixed driving piles is relatively low in general near the surface of the ground and that they reach a maximum in the vicinity of the body of the pile. As a result, by using slightly larger pile bodies, but much smaller footings than known piles, the same or even greater load bearing capacity is achieved than that previously obtained with known piles.
Therefore, the footings of the piles are designed so that they do not protrude too widely beyond the profile of the pile body *

 <Desc / Clms Page number 3>

 
In addition, in the present invention, the profile of the base of the pile protrudes, at least in two places,

   not beyond the profile of the stake body or at least larger parts of that body. Preferably, those stake flange portions not protruding beyond the profile of the body are kept small. As a result, in the piles according to the invention, the body is not provided with an enoerolante concrete sheath over its entire length. In this way, at least two concrete lining shells are obtained which are generally only connected to one another in one place near the pile body,
The packing sleeve is subdivided around the pile body into at least two separate shells.

   Consequently, it is possible, during the driving process, to press the filling concrete downwards to the pile base approximately, by at least one of the two sheaths, to introduce it also into the pile. second sheath by a link existing near the pile sole between the two sheaths and then push it back upwards through the second sheath to the ground surface. Consequently, at least one sheath is filled continuously and progressively by pouring from top to bottom during sinking and the other sheath is filled by the discharge from bottom to top.



   This filling system is free of tubes over the entire length of the pile. A simple seal between the body of the pile and the earth wall of a sheath is exclusively necessary near the surface of the soil, the filling concrete being brought into one of the two sheaths via this seal. The precise filling of the sheath is guaranteed when the filling concrete, introduced on one side of the pile, is driven upwards continuously and gradually with the driving on the other side of the pile to the surface. of the ground

 <Desc / Clms Page number 4>

 and that a small amount of concrete constantly spills over it. This process can be checked visually.



   The process described above can be carried out with full success in accordance with the invention by using piles the body of which is not constricted with respect to the pile base over longer or shorter distances, or 'that is to say, stakes which present colleta.



   In these piles it must be ensured that a pipe for the downward pouring of a filling concrete is provided on one side in the collar on the unshrunk part of the pile body and that a similar conduit is formed loosely on the other side of the collar for upward discharge of the filling concrete.



   Instead of the usual filling apparatus, a simple filling device can also be used, where the desired pressure is determined simply by raising or lowering this device above the ground surface.



   Retainers, transmitting load fractions absorbed by the filling concrete directly to the pile body, may be provided on the latter.



   Other particularities of the invention emerge from the description below produced with the aid of Examples. ples of realization represented in the attached drawings in which! Figure 1 is a mixed jacking pile in side view; Figure 2 is a sectional view of a mixed jacking pile comprising very small sheaths of concrete lining; Figure 3 is a sectional view of a mixed jacking pile fitted with larger concrete lining sheaths,

 <Desc / Clms Page number 5>

 FIG. 4 is a section through a mixed driving pile, the body of which is round; FIG. 5 is a section through a mixed sinking pile, the body of which consists of a section formed into a sheet pile; Fig. 6 is a sectional view of a combination jacking pile having a double T-shaped cross-section body;

   Figure 7 is a perspective view of a mixed sinking pile equipped with a double T cross section body and a lower and upper wing.



   The operating mode of the predecessor according to the invention is as follows: the pile shown in FIG. 1 comprises a sole 1 and a body 2 as well as a lower reinforcement 3 and an upper reinforcement 4 of the pile body. Over the entire length of the body 2, a body rib 5 is provided which extends downwardly to the vicinity of the sole 1 and which, in the present example, protrudes with a cutting edge beyond the profile of the sole. A similar rib 5, made on the opposite face of the pile body 2, corresponds to the aforementioned first rib. Ducts 6 and 7 are practical on one side of the pile in the two reinforcements 3 and 4 and pipes 8 and 9, arranged on the other side of the pile, also correspond to the pipes mentioned first.

   When the pile is driven in, the lining sleeve 10 freely broken by the flange on one of the faces of the pile is filled with concrete continuously by pouring up and down gradually with the driving, part of the concrete being pressed into the sleeve of packing 13 on the other side of the pile through the opening 12 between the sole 1 and the rib 5 of the pile body 2. When the

 <Desc / Clms Page number 6>

 forcing 3 of body 2 penetrates into the ground during sinking, the lining concrete is pushed back internally into the sheath 10 through the duct 6 of the reinforcement 3 and is then forced upwards into the sheath 13 through the opening 12 .

   This concrete is then brought back in part to the surface of the earth through the pipe 8 of the reinforcement 3. 'The process for filling the sheath 11 between the two reinforcements 3 and 4 on one of the faces of the pile and of the other sheath 14 on the other face of the pile is similar to that described above. If, during driving, the upper reinforcement 4 penetrates the ground, the filling concrete is pressed downwards into the sheath 11 through the duct 7 and into the sheath 10 through the duct 6 and is then forced upwards into the sheath 13 through the opening 12 and in the sheath 14 through the conduit 8. It finally reaches the surface of the ground through the oonduit 9.



   Figures 2, 3, 4, 5 and 6 show cross sections of various embodiments of body profiles and pile flanges. Figure 2 shows a pile body profile 18 which protrudes beyond the sole profile 42, as well as a body profile 19 which is flush with the sole profile 42. These two body profiles 18 and
19 correspond to the profiles 20 and 21 provided on the other faoe of the pile. The filling concrete can be pressed down through conduit 22 between the earth and the pile body, freely formed by the flange 42 and limited by the body profiles 18 and 19. This concrete can be forced. up by the remaining entire sheath 45. The same arrangement is reproduced in Figure 3. The sheath 44 is interrupted by the body profiles 23, 24 and 25.

   If the profile 25 is removed, the filling concrete descends on one of the faces of the sheath 44 and rises on the other face of this sheath 44. On the other hand, if the profile 23 is removed, the filling concrete depends on conduit 26 and reassembled through the remaining sheath 44, enrolling the pre-

 <Desc / Clms Page number 7>

 that whole stake body. FIG. 4 shows that the method can also be implemented for round pile bodies, when the earth 28 contacts the round profile 27 of the pile body at two places. This gives the sheath 29 which can be filled with concrete by pouring from top to bottom, and the sheath 30 which can be filled by lifting the concrete.

   FIG. 5 shows a section in the form of a sheet pile 31 which has, on the one hand, thin flanges 32 and 33 and, on the other hand, a wide flange 34. The edges 35 and 36 of the sheet pile are located at the bottom. exterior of the body and thus divide the sheath into two shells, In Figure 6, there is shown a sinking body 37, in which the sheath 39 is filled by means of the sheath 38 and the sheath 41 by the sheath 40. FIG. 7 finally shows a profile 46 with a cross section in the shape of a double T, comprising a lower wing 47 with flanges 48, as well as an upper wing 49 provided with a reinforcement 50 and a duct 51 for the concrete topping.

   In addition, the concrete reinforcement 52 and the openings 53 used for the passage of the filling concrete and allowing the pouring down of the latter in one of the ducts and the rise of the concrete in the other duct were reproduced. .



  CLAIMS

** ATTENTION ** end of DESC field can contain start of CLMS **.

 

Claims (1)

1, Procédé de fabrication d'un pieu de fonçage mixte oomprenant une semelle et un corps plus petit ratta- ché à celle-ci, se composant d'acier ou de béton armé d'aoier et susceptible de présenter à non extrémité supé- rieure un bourrelet d'arrt pour le trou du pieu, un béton de garniture étant introduit autour de ce corps, oaracté- risé en ce que des gaines de béton de garniture ne déve- loppant parallèlement à l'axe longitudinal du pieu sont formé et en ce que le béton de garniture est introduit par <Desc/Clms Page number 8> ooulée de haut en bas dans l'une des gaines de béton de garniture pendant le fonçage et est ramené de bas en haut dans l'autre gaine. 1, A method of manufacturing a mixed jacking pile comprising a sole and a smaller body attached thereto, consisting of steel or reinforced concrete from aoier and capable of having at an upper end a stop bead for the hole of the pile, a lining concrete being introduced around this body, characterized in that sheaths of lining concrete not developing parallel to the longitudinal axis of the pile are formed and in what the filling concrete is introduced by <Desc / Clms Page number 8> o flowed from top to bottom in one of the concrete lining ducts during driving and is brought from bottom to top in the other duct. 2. Dispositif pour la mise en .oeuvre du procédé suivant la revendication 1, caractérise en ce que des nervures triangulaires (5) ou d'une autre forme, qui prirent dans le sol par l'intermédiaire d'une section transversale de la semelle de pieu (1), sont disposées de part et d'autre du corps de pieu (2), parallèlement à son axe longitudinal. 2. Device for implementing the method according to claim 1, characterized in that triangular ribs (5) or of another shape, which took in the ground via a cross section of the sole pile (1), are arranged on either side of the pile body (2), parallel to its longitudinal axis. 3. Dispositif pour la mise en oeuvre du procède suivant la revendication 1, caractérisé en ce que les gaines degarniture (10 et 13) forgea par les nervures (5) sont reliées l'une à l'autre au-dessus du corps de pieu (1). 3. Device for carrying out the process according to claim 1, characterized in that the sheaths (10 and 13) forged by the ribs (5) are connected to each other above the pile body (1). 4. Dispositif pour la mise en oeuvre du procédé suivant la revendication 1 , caractérisé en ce que le corps de pieu (2) présente un renforcement (3) qui sépare les gaines de garniture (10, 13) des gaines de garniture (11,14) et dans lequel des conduits (6,8) sont pratiqués sur chaque faoe du pieu. 4. Device for implementing the method according to claim 1, characterized in that the pile body (2) has a reinforcement (3) which separates the lining sheaths (10, 13) from the lining sheaths (11, 14) and in which conduits (6,8) are made on each faoe of the stake. 5. Dispositif pour la mise en oeuvre du procé- dé suivant la revendication 1, caractérisé en ce que le corps de pieu (2) est doté de dispositifs de retenue (15, 16) pour l'armature (17) du béton de garniture. 5. Device for carrying out the method according to claim 1, characterized in that the pile body (2) is provided with retaining devices (15, 16) for the reinforcement (17) of the filling concrete. . 6. Procédé de fabrication d'un pieu de foncage mixte suivant la revendication 1, caractérisé en ce que la pression pour l'introduction du béon de garniture dans les gaines est réglée par un positionnement plue élevé ou plus bas du dispositif de remplissage. 6. A method of manufacturing a mixed ramming pile according to claim 1, characterized in that the pressure for the introduction of the packing beon into the sheaths is regulated by a higher or lower positioning of the filling device. 7, Procédé de fabrication d'un pieu de fonçage mixte suivant la revendication 1, caractérisé en ce que le béton de garniture est introduit dans les gaines au moyen d'air comprimé. <Desc/Clms Page number 9> 7, A method of manufacturing a mixed jacking pile according to claim 1, characterized in that the lining concrete is introduced into the ducts by means of compressed air. <Desc / Clms Page number 9> 8. Procédé de fabrication d'un pieu de fonçage mixte suivant la revendication 1. caractérisé en ce que le béton de garniture est introduit sous pression dans les gaines au moyen d'une pompe à béton. 8. A method of manufacturing a mixed jacking pile according to claim 1. characterized in that the lining concrete is introduced under pressure into the ducts by means of a concrete pump.
BE720112D 1968-08-29 1968-08-29 BE720112A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
BE720112 1968-08-29

Publications (1)

Publication Number Publication Date
BE720112A true BE720112A (en) 1969-02-03

Family

ID=3853447

Family Applications (1)

Application Number Title Priority Date Filing Date
BE720112D BE720112A (en) 1968-08-29 1968-08-29

Country Status (1)

Country Link
BE (1) BE720112A (en)

Similar Documents

Publication Publication Date Title
FR2513304A1 (en) TOOL FOR DRILLING IN THE SOIL OF HOLES WITH REINFORCED WALLS AND METHOD FOR DRILLING SUCH HOLES
US6698976B1 (en) Grouting pipe equipment and method of grouting using the same for an underground water well
BE720112A (en)
JP5840891B2 (en) Removal method of retaining members
FR2473091A1 (en) Mechanically stripped end shutter for underground concrete walls - has inflatable tubes forcing shutter free of set concrete and forming shaped face for next section
BE898139A (en) Method and apparatus for achieving piles concreted in situ and having a wider basis.
FR2610652A1 (en) PROCESS FOR REINFORCING A PITCHED TUBULAR PIEU, PIEU OBTAINED BY THIS METHOD, DEVICE FOR CARRYING OUT THE METHOD
EP1441076A1 (en) Injectable micropile
EP0305259B1 (en) Process for retaining lateral walls of deep excavations
EP0847462B1 (en) Novel draining wall, method for producing same and element implementated thereby
EP0034520B1 (en) Mining excavating process using the bord and pillar method
FR2504168A1 (en) Drill for forming annular foundation cavities - comprises tube carrying external helical cutting edge and central concrete feed tube
EP0142528A1 (en) Process and equipment for manufacturing in-situ concrete monolithic piles with non-uniform section.
JP4312135B2 (en) Steel pipe sheet pile placing method
WO2000040808A1 (en) Method and device for forming a foundation pipe pile in the ground
BE876763A (en) METHOD AND DEVICE FOR SUPPORTING A BUILDING FROM AN UNDERGROUND GALLERY.
BE551549A (en)
BE1006194A5 (en) Drilling device and process for the formation of piles or the like
EP3320147B1 (en) Method for constructing a foundation including a step of cutting-of
FR2600686A1 (en) Improvements to reinforced concrete screw piles, by adding anchoring teeth
EP0887479A1 (en) Prefabricated manhole for connection and inspection of sewer pipes and process for installing such a manhole
FR2502208A1 (en) Ground stabilisation and strengthening procedure - has grout injection rods acting as ground anchors forced into ground by vibrating percussion hammer
NL1025577C2 (en) In situ foundation pile formation, lubricating agent is applied to outside of pipe used to cast concrete
BE546120A (en)
FR2634804A1 (en) Method of inserting a prefabricated post in a very deep bore and post for the use of this method.