BE536193A - - Google Patents

Info

Publication number
BE536193A
BE536193A BE536193DA BE536193A BE 536193 A BE536193 A BE 536193A BE 536193D A BE536193D A BE 536193DA BE 536193 A BE536193 A BE 536193A
Authority
BE
Belgium
Prior art keywords
ceiling
construction
enclosure
joists
compressed air
Prior art date
Application number
Other languages
French (fr)
Publication of BE536193A publication Critical patent/BE536193A/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel

Description

       

   <Desc/Clms Page number 1> 
 



   Le brevet belge déposé le 3 juin   1954,   pour: "Nouveau procédé d'ap- plication de l'air   comprimé   à la construction d'ouvrages souterrains'' concer- ne la construction "in situ" d'une enceinte recouverte par un plafond et ou- verte à sa base, enceinte dans laquelle on envoie de l'air comprimé à une pression suffisante pour évacuer l'eau contenue dans la portion du sol qui se trouve emprisonnée à l'intérieur de ladite enceinte. 



   L'emploi d'air comprimé n'est d'ailleurs nécessaire que si l'on o- père au dessous du niveau de la nappe aquifère. 



   L'enceinte en question communique avec l'extérieur par des installa- tions fixes comportant un ou plusieurs "sas" utilisés: - d'une part, pour l'évacuation des déblais qui remplissent complè- tement l'enceinte au moment où l'on entame les travaux en souterrain, - d'autre part, pour l'introduction dans l'enceinte du béton et des autres éléments entrant dans la constitution de l'ouvrage à construire. 



   A l'intérieur de l'enceinte, un double problème de transport se pose donc, correspondant: - à l'évacuation des déblais vers les installations de communication avec l'extérieur, - à l'amenée au lieu d'emploi des matériaux provenant desdites in- stallations. 



   Les transports en question pourraient s'effectuer par roulement dans le fond de l'excavation , au fur et à mesure du creusement de celle-ci, mais on sait que, dans les travaux en souterrain, le sol est fréquemment en- combré et mal nivelé. 



   De plus la construction   "in   situ" d'ouvrages souterrains est surtout intéressante pour un travail exécuté dans un terrain peu consistant,   où   le roulage se fait difficilement. 



   L'invention consiste à associer le procédé d'application de l'air comprimé suivant le brevet précité avec l'utilisation de monorails suspendus au plafond de l'enceinte qui préexiste au moment où on entame les travaux en souterrain. A ces monorails, on accrochera, au moyen de galets appropriés, des engins de transport roulants, qui seront utilisés pour effectuer tout ou partie des deux catégories de transport ci-dessus décrits. 



   Suivant cette invention, la pose des chemins de roulement destinés à recevoir les engins de transport peut être faite de différentes manières, soit que les monorails soient mis en place avant la confection du toit et suspendus à celui-ci au cours de ladite confection, soit que, dans un premier stade, on se contente de fixer au toit les engins qui serviront ultérieurement à la mise en place des rails. Ceux-ci seront alors posés à l'intérieur de 1' enceinte, au fur et à mesure de l'avancement du travail. 



   Il est décrit ci-après, à titre d'exemple non limitatif, une réali- sation de l'invention qui se rattache à la première de ces deux conceptions. 



   Les figures 1 à 7 montrent les phases successives de la construction. 



   Sur toutes ces figures A désigne les parois verticales, B le talus. 



   Sur la figure 1 on voit en coupe verticale transversale une excava- tion, qui a été descendue dans le sol jusqu'au niveau de la nappe aquifère. 



   Dans le fond de cette excavation, on a construit deux parois verti- cales A parallèles, étanches à l'eau et à l'air comprimé. Le pied des rideaux ainsi constitué est descendu en contrebas des ouvrages à construire. Les deux 

 <Desc/Clms Page number 2> 

 parois A sont réunies l'une à l'autre par deux autres parois transversales verticales d'une construction analogue. Ces dernières, qui peuvent être très éloignées l'une de l'autre, non sont pas représentées sur les dessins. 



   La figure 2 montre la phase suivante du travail. Dans le fond de la fouille, on a disposé un certain nombre de poutrelles C destinées à con- stituer les futurs chemins de roulement accrochés au plafond ou toit de 1' enceinte. Pour faciliter la pose et le réglage desdites poutrelles, on a éventuellement constitué, au préalable, une forme de sable D dans le fond de la fouille. 



   La phase ultérieure du travail, représentée en coupe verticale et en plan,respectivement sur les figures 3 et 4, consiste à noyer dans une nouvelle couche de sable E se superposant à la forme de sable D, les pou- trelles C dont il vient d'être question de telle sorte que le niveau supé- rieur de la couche E soit au niveau de la partie supérieure des poutrelles C, puis à disposer au dessus d'autres poutrelles F jouant le rôle de traver- ses. Celles ci sont liées aux poutrelles C, soit par soudure, soit au moyen de rivets ou de boulons. 



   Il ne reste plus, pour achever l'enceinte, qu'à constituer son pla- fond par les opérations mises en évidence sur les fig. 5 et 6. On y voit des parois de coffrage verticales G, soutenues par des étais H, qui limite- ront latéralement la dalle de béton armé I dans laquelle seront enrobées à la fois la partie supérieure des parois latérales A (sur la figure   5   on a supposé que les armatures a contenues dans ces parois avaient été dégagées et retournées) et les poutrelles F constituant traverses. 



   S'il n'est pas nécessaire que la face inférieure de la dalle I soit parfaitement lisse, celle-ci peut être coulée directement sur la forme de sable D-E. 



   Les traverses sont d'autant plus rapprochées que les charges que l'on désire suspendre aux rails de roulement sont plus importantes. 



   L'enceinte étant achevée, on peut remblayer la fouille et, s'il y a lieu, reconstituer le revêtement du sol. 



   Il reste à exécuter les travaux en souterrain selon le procédé dé- crit dans le brevet belge du 3 Juin 1954 sus-visé. 



   Sur la figure 7, qui est une coupe verticale transversale, on voit une benne preneuse K remplie de déblais et suspendue à un charriot L, qui est accroché à l'une des poutrelles C. 



   Le fait que celles-ci sont enrobées de sable facilite leur dégage- ment au fur et à mesure que l'exécution des déblais laisse échapper le sable vers l'intérieur. 



   Au front d'attaque, les machines à terrassement peuvent d'ailleurs elles aussi être suspendues aux poutrelles. 



   Le transport des déblàis au moyen d'engins suspendus aux poutrelles peut s'effectuer sur toute la distance séparant le front d'attaque des instal- lations de communication avec l'extérieur ou seulement sur une partie de cette distance si, dans la portion terminée de l'ouvrage, on préfère utiliser des engins reposant sur le sol tels que des tapis ou roulant sur celui-ci. 



   Les poutrelles peuvent également être utilisées pour la circulation, sur tout ou partie de la distance comprise entre les installations de commu- nication avec l'extérieur et le chantier de bétonnage, des engins qui servent à approvisionner ledit chantier, soit en béton, soit en matériaux constitu- 

 <Desc/Clms Page number 3> 

 tifs du béton. Elles peuvent enfin être utilisées pour supporter - soit à demeure, soit seulement lorsqu'un déplacement est nécessaire - les coffra- ges ou les engins utilisés pour le bétonnage. 



   Si leur pose a été soignée, les poutrelles constituent un excellent repère pour la mise en place précise des coffrages . 



   Les poutrelles pourront être détachées ou séparées des traverses auxquelles elles sont suspendues, elles pourront dans d'autres cas être con- servées en vue d'être utilisées au cours de l'exploitation de   l'ouvrage.   



   A titre de variante, on pourrait se contenter d'incorporer au pla- fond au moment de sa confection les supports nécessaires à la fixation des poutrelles, celles-ci étant ultérieurement amenées en place et fixées au plafond au fur et à mesure de l'avancement des travaux de terrassement. 



   Il est naturellement loisible, sans sortir du cadre de l'invention, de réaliser d'autres variantes de ce mode de transport.



   <Desc / Clms Page number 1>
 



   The Belgian patent filed on June 3, 1954, for: "New process for the application of compressed air to the construction of underground works" concerns the construction "in situ" of an enclosure covered by a ceiling and open at its base, an enclosure into which compressed air is sent at a pressure sufficient to evacuate the water contained in the portion of the ground which is trapped inside said enclosure.



   The use of compressed air is moreover necessary only if one o- fers below the level of the aquifer.



   The enclosure in question communicates with the outside through fixed installations comprising one or more "airlocks" used: - on the one hand, for the evacuation of the spoil which completely fills the enclosure when the work begins underground, - on the other hand, for the introduction into the enclosure of concrete and other elements entering into the constitution of the work to be built.



   Inside the enclosure, a double transport problem therefore arises, corresponding to: - the evacuation of the excavated material to the facilities for communication with the outside, - the delivery to the place of use of the materials from of said installations.



   The transports in question could be carried out in shifts in the bottom of the excavation, as the excavation progresses, but it is known that, in underground work, the soil is frequently clogged up and poorly. leveled.



   In addition, the "in situ" construction of underground structures is especially advantageous for work carried out in loose terrain, where rolling is difficult.



   The invention consists in combining the method of applying compressed air according to the aforementioned patent with the use of monorails suspended from the ceiling of the enclosure which pre-exists at the time when the underground work is started. To these monorails, we will hang, by means of appropriate rollers, rolling transport vehicles, which will be used to perform all or part of the two categories of transport described above.



   According to this invention, the installation of the tracks intended to receive the transport vehicles can be done in different ways, either that the monorails are put in place before the making of the roof and suspended from it during said making, or that, in a first stage, one is satisfied to fix to the roof the machines which will be used later for the installation of the rails. These will then be placed inside the enclosure, as the work progresses.



   An embodiment of the invention which relates to the first of these two designs is described below by way of nonlimiting example.



   Figures 1 to 7 show the successive phases of construction.



   In all these figures A denotes the vertical walls, B the slope.



   In FIG. 1 we see in transverse vertical section an excavation, which has been lowered into the ground to the level of the aquifer.



   At the bottom of this excavation, two parallel vertical walls A have been built, tight against water and compressed air. The foot of the curtains thus formed is lowered below the structures to be constructed. Both

 <Desc / Clms Page number 2>

 walls A are joined to one another by two other vertical transverse walls of a similar construction. The latter, which can be very far from each other, are not shown in the drawings.



   Figure 2 shows the next phase of labor. At the bottom of the excavation, a number of C-beams have been placed, intended to constitute the future tracks attached to the ceiling or roof of the enclosure. To facilitate the installation and adjustment of said beams, optionally, a form of sand D has been formed beforehand in the bottom of the excavation.



   The subsequent phase of the work, shown in vertical section and in plan, respectively in Figures 3 and 4, consists in drowning in a new layer of sand E superimposed on the form of sand D, the trash C from which it comes from 'be questioned so that the upper level of the layer E is at the level of the upper part of the beams C, then to place above other beams F playing the role of sleepers. These are linked to the C-joists, either by welding or by means of rivets or bolts.



   In order to complete the enclosure, all that remains is to constitute its ceiling by the operations shown in FIGS. 5 and 6. We see there vertical formwork walls G, supported by props H, which will laterally limit the reinforced concrete slab I in which both the upper part of the side walls A will be embedded (in figure 5 it was assumed that the reinforcements a contained in these walls had been released and turned over) and the beams F constituting sleepers.



   If it is not necessary for the underside of the slab I to be perfectly smooth, it can be poured directly onto the sand form D-E.



   The sleepers are all the closer as the loads that one wishes to suspend from the running rails are greater.



   Once the enclosure is complete, the excavation can be backfilled and, if necessary, the floor covering can be reconstructed.



   It remains to carry out the work underground according to the process described in the Belgian patent of June 3, 1954 referred to above.



   In figure 7, which is a transverse vertical section, we see a clamshell K filled with spoil and suspended from a cart L, which is hooked to one of the beams C.



   The fact that these are coated with sand facilitates their release as the execution of the cuttings lets the sand escape into the interior.



   At the attack front, earthmoving machines can also be suspended from the joists.



   The transport of the cuttings by means of machinery suspended from the joists can be carried out over the entire distance separating the leading front from the installations of communication with the outside or only over part of this distance if, in the completed portion of the work, it is preferred to use devices resting on the ground such as carpets or running on it.



   The beams can also be used for the circulation, over all or part of the distance between the communication installations with the exterior and the concreting site, of the machines which are used to supply said site, either with concrete or with concrete. constituent materials

 <Desc / Clms Page number 3>

 tifs of concrete. Finally, they can be used to support - either permanently or only when movement is necessary - the boxes or the machines used for concreting.



   If their installation has been neat, the joists constitute an excellent reference point for the precise installation of the formwork.



   The joists can be detached or separated from the sleepers to which they are suspended; in other cases, they can be kept for use during the operation of the structure.



   As a variant, one could be satisfied with incorporating into the ceiling at the time of its making the supports necessary for fixing the joists, the latter being subsequently brought into place and fixed to the ceiling as the installation progresses. progress of earthworks.



   It is naturally permissible, without departing from the scope of the invention, to produce other variants of this mode of transport.


    

Claims (1)

RESUME. ABSTRACT. Mode de transport dans la construction d'ouvrages souterrains et moyens propres à le réaliser caractérisé par la combinaison du procédé d'ap- plication de l'air comprimé suivant le brevet belge déposé le 3 Juin 1954 - pour : "Nouveau procédé d'application de l'air comprimé à la construction d'ouvrages souterrains" et l'utilisation d'engins de transport roulants accrochés à des monorails fixés au plafond de l'enceinte. Mode of transport in the construction of underground works and means suitable for carrying it out characterized by the combination of the compressed air application process according to the Belgian patent filed on June 3, 1954 - for: "New application process from compressed air to the construction of underground works "and the use of rolling transport vehicles attached to monorails fixed to the ceiling of the enclosure. Les poutrelles destinées à servir de chemins de roulement aux engins de transport sont mises en place avant l'exécution du plafond de l'enceinte puis enrobées de sable et solidarisées avec les traverses du plafond de sor- te qu'après construction de ce plafond elles se trouvent dégagées au fur et à mesure de l'exécution des déblais par l'écoulement du sable à l'intérieur, Au lieu de poutrelles destinées à servir de chemin de roulement, on peut ne mettre en place que les supports nécessaires à leur fixation, les poutrelles étant fixées aux dits supports au fur et à mesure de l'avancement du travail de terrassement. The beams intended to serve as runways for transport vehicles are put in place before the construction of the enclosure ceiling, then coated with sand and secured to the cross members of the end ceiling until after construction of this ceiling they are released as the excavation progresses by the flow of sand inside, Instead of joists intended to serve as a track, it is possible to put in place only the supports necessary for their fixing, the joists being fixed to said supports as the earthwork progresses.
BE536193D BE536193A (en)

Publications (1)

Publication Number Publication Date
BE536193A true BE536193A (en)

Family

ID=166968

Family Applications (1)

Application Number Title Priority Date Filing Date
BE536193D BE536193A (en)

Country Status (1)

Country Link
BE (1) BE536193A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4648743A (en) * 1984-11-26 1987-03-10 Gerhard Sauer Method of producing a subterranean structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4648743A (en) * 1984-11-26 1987-03-10 Gerhard Sauer Method of producing a subterranean structure

Similar Documents

Publication Publication Date Title
EP0102340B1 (en) Method of making reinforced concrete constructions such as subways, road tunnels and the like; prefabricated concrete elements for making such constructions
EP2649242B1 (en) Method for building structures, particularly passages under operating railways or the like.
CH642416A5 (en) METHOD OF CONSTRUCTING UNDERGROUND WORKS WITH VERTICAL WALLS, DEVICE FOR EXECUTING THE METHOD AND UNDERGROUND WORK.
CA1302111C (en) Process and apparatus for making a rigid load-bearing slab
FR2537180A1 (en) CONSTRUCTION BRIDGE BUILT IN STABILIZED LAND
CN106759463A (en) A kind of hypogee and its construction method
EP0560660B1 (en) Multistorey underground garages and construction method thereof
WO2000001904A1 (en) Mobile horizontal platform for prefabrication on building site and for successively placing masonry parts
BE536193A (en)
EP0242497B1 (en) Tunnel construction process
FR3006701A1 (en) METHOD AND DEVICE FOR MANUFACTURING BANCH WALLS USING A REUSABLE FORMWORK AND COMPRISING AT LEAST ONE ADJUSTED FRAME
EP0192004B1 (en) Process and apparatus for installing a structure such as a prefabricated bridge
CH434335A (en) Method of construction of a passage under track and installation for the implementation of this method
FR2824851A1 (en) PREFABRICATED BRIDGE SUPPORT
EP0423105B1 (en) Prefabricated structural element to be used as a cellar
FR2634236A1 (en) METHOD FOR REPAIRING A FOUNDATION COMPRISING DETERIORATED PILE HEADS, ESPECIALLY WOOD PILES
FR2727447A1 (en) Construction of tunnel under embankment in soft soils or areas prone to flooding
EP0418162B1 (en) Process for constructing structures, in particular railway underpasses
FR2839990A1 (en) Prefabricated Civil engineering structure for installing passage under rail track comprises portico with upper crosspiece connecting two vertical abutments extended by additional spans supported by cover plate on talus ridge
BE894650R (en) Reinforced concrete construction underground - has frames dropped into excavations with positioning detents ensuring continuity
FR2472074A1 (en) Reinforcement for open excavations - provides temporary side protection from rocks using vertical plates permitting introduction of tubular coffer pieces
FR2959253A1 (en) MOLDED WALL WITH PREFABRICATED FACING
FR2869052A1 (en) Non prefabricated safety engineering structure i.e. safety bridge, has reinforced concrete and parallelepiped deck slab that is cast directly, in functional position, in temporary support on ground which is prepared consequently
JP2693028B2 (en) Construction method of human hole in middle of pipeline
BE864136A (en) METHOD AND DEVICE FOR CONSTRUCTION IN THE SOIL OF VERTICAL WALLS FROM AN UNDERGROUND DUCT