BE495379A BE495379DA BE495379A BE 495379 A BE495379 A BE 495379A BE 495379D A BE495379D A BE 495379DA BE 495379 A BE495379 A BE 495379A
Authority
BE
Belgium
Prior art keywords
floor
emi
joists
beams
formwork
Prior art date
Application number
Other languages
French (fr)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Publication of BE495379A publication Critical patent/BE495379A/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/26Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated with filling members between the beams
    • E04B5/261Monolithic filling members
    • E04B5/263Monolithic filling members with a flat lower surface
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Building Environments (AREA)

Description

       

   <EMI ID=1.1> 

ET PLANCHERS OBTENUS A L'AIDE DUDIT PROCEDE.

  
Les procédés de réalisation de planchers connus à ce jour, c'està-dire les procédés utilisant, soit le solivage en bois, soit le béton armé coulé sur place, soit encore des éléments préfabriqués, ont l'inconvénient d'exiger le concours d'un plâtrier pour les enduits en plâtre ou la mise en oeuvre d'un plafond suspendu..

  
Ce concours augmente, dans de notables proportions, le prix du plancher par unité de surface en raison soit des multiples opération&#65533; de fa-. bricati.on en atelier, du transport, de la cassé, lorsque l'on a affaire à

  
un plafond suspendu, soit du boisage et de l'application d'un enduit en plâtre, lorsqu'on a affaire à un plancher à solives. 

  
La présente invention a pour objet un procédé d'établissement

  
de planchers qui consiste, en principe, après avoir mis en place les poutrelles du plancher, à couler in-situ, sur un coffrage horizontal à surface lisse, disposé au-dessous desdites poutrelles et à une certaine distance

  
de celles-ci, la sous-face du plancher constituant le plafond, et à rendre celle-ci solidaire des poutrelles, les autres éléments du plancher étant

  
mis en place après exécution de ladite sous-face. On obtient ainsi directement un plafond fini, dont la face apparente est lisse et parfaitement dressée,, prête à recevoir la peinture si celle-ci est prévue, sans nécessiter, pour son parachèvement, l'intervention de spécialistes. 

  
Selon une caractéristique importante de l'invention, le plafond

  
à sous-face finie ainsi constitué peut être utilisé comme coffrage pour la coulée de la dalle de compression^ généralement par l'intermédiaire d'un matériau de remplissage, garnissant l'intervalle entre les poutrelles précitées.

  
La réalisation d'un plancher selon ce procédé, et notamment le moulage de la sous-face sur les coffrages lisses, peut être effectuée en une seule fois pour toute la surface du plancher lorsque celle-ci n'est pas très importante. Dans le cas le plus fréquent où il s'agit de relativement gran-des surfaces, le moulage est exécuté par fractions successives. Les panneaux de coffrage horizontaux à surface lisse sont, dans ce but, montés sur un échafaudage roulant, qui est déplacé d'une seule pièce pour amener les panneaux à l'emplacement désiré.

  
Dans un mode de mise en oeuvre du procédé selon l'invention, la sous-face précitée est établie en une seule opération et présente une épaisseur suffisante pour venir s'accrocher directement sur les ailes inférieures des poutrelles du plancher. Dans ce cas,, cette sous-face peut être soit en plâtre pur, soit enmortier fin à base d'un liant quelconque.

  
Il est possible également d'utiliser un béton-liquide pour la coulée en une seule opération de la sous-face, sur le coffrage horizontal à surface lisse. Une partie du liant entrant dans la composition de celui-ci descend par ségrégation en r-emplissant les interstices et-forme, en se déposant sur le coffrage, la sous-face lisse finie du plancher.

  
Dans un autre mode de mise en oeuvre du procédé selon l'invention, la sous-face est établie en deux opérations successives : coulée surle coffrage horizontal plan, d'un voile de plâtre pur ou de mortier de plâtre- de relativement faible épaiss.eur formant le plafond proprement dit, puis coulée sur ce voile d'un auget en béton de mâchefer, pouzzolane, ponce ou matériau analogue, dont les bords relevés viennent s'accrocher aux ailes des poutrelles.

  
Cet auget est coulé sur le voile inférieur avant la fin de la prise du plâtre ou du mortier qui constitue celui-ci, prise qui peut, d'ailleurs, être retardée par l'addition d'un produit ralentisseur au matériau utilisé.

  
Il peut être avantageux de noyer dans l'auget précité, des arceaux, soit en métal rendu inoxydable, soit en roseaux ou bois fendu, venant prendre appui sur les ailes inférieures des poutrelles du plancher et qui consolident l'accrochage de la sous-face, dans le cas où l'écartement des poutrelles le nécessite.

  
La sous-face précitée, homogène ou hétérogène, établie comme indiqué ci-dessus par coulée in-situ sur un coffrage plan, peut servir de coffrage pour la coulée de la chape de compression du plancher.

  
Selon une caractéristique de l'invention, il est prévu un isolement thermique et/ou phonique entre le plancher et le plafond proprement

  
dits.

  
Dans un mode d'exécution de cette disposition, il est prévu, pour réaliser cet isolement, entre l'auget précité de la sous-face finie constituant le plafond et la chape de compression qui viendra former la face supérieure

  
du plancher, un garnissage établi à l'aide d'un matériau pulvérulent et foisonnant, de faible densité et possédant un coefficient de conductibilité calorifique le plus faible possible. Ce matériau sera choisi en tenant compte des ressources locales, afin d'abaisser son prix de revient et les frais de transport, et pourra être, par exemple, du mâchefer, du pouzzolane, des co-

  
 <EMI ID=2.1> 

  
maigre à faible dosage de liant.

  
Le garnissage sus-visé peut être déversé directement dans l'auget et remplir, jusqu'à affleurement de l'extrémité supérieure des poutrelles,

  
les caissons délimités latéralement par deux poutrelles successives et dont

  
le fond est constitué par l'auget.

  
Afin d'augmenter encore l'effet d'isolement de ce garnissage, celui-ci, dans un autre mode de réalisation du procédé selon l'invention,ne repose pas directement sur le fond de l'auget mais par l'intermédiaire d'éléments en matériau léger, en forme de voûtins, par exemple, logés entre les poutrelles. On réalise ainsi, entre l'auget et le garnis.sage, un matelas d'air qui améliore l'isolement du plancher, tout en réduisant son poids unitaire.

  
La chape de compression est coulée, en dernier lieu, sur les poutrelles, à la manière habituelle, éventuellement après mise en place d'un quadrillage d'armature sur celles-ci. 

  
Dans le cas où il est prévu un garnissage réalisé comme indiqué ci-dessus, le chape de compression vient, à'sa coulée, reposer sur celui-ci.

  
L'isolement peut être obtenu uniquement grâce à un matelas d'air prévu entre la sous-face et la chape de compression. Le béton est soutenu dans ce cas, pendant la coulée .de la chape de compression, par des panneaux

  
 <EMI ID=3.1> 

  
les d'épaisseur et de hauteur'convenables, coulées en même temps que l'auget dont il a été question plus haut, ou constituées par des éléments rapportés.

  
Ces panneaux-peuvent être en lattes de sapins cannes de roseaux ou tout autre matériau convenable, choisi en fonction. des ressources locales. 

  
Il y a lieu de noter que, dans ce dernier mode particulier de mise en oeuvre du procédé selon l'invention, le garnissage intermédiaire est entièrement supprimé, ce qui permet, outre un allégement sensible de la construction, une économie substantielle de matière-et de main-d'oeuvre, notamment dans les régions où le lattis de sapin ou les claies de roseau peuvent être obtenus en grande quantité et à bon compte.

  
La description qui va suivre, faite en regard des dessins annexés donnés à titre d'exemples non limitatifs, permet de se rendre compte comment le présent procédé peut être mise en oeuvre et comment peut être établi l'appareillage servant à sa réalisation. Dans ces dessins : 

  
 <EMI ID=4.1> 

  
procédé de l'invention; 

  
la figo 2 est un plan d'un des coffrages lisses utilisés;

  
la figo 4 est une élévation d'un échafaudage roulant, supportant le coffrage ci-dessus';. 

  
la figo 3 est un détail du moyen de réglage en hauteur de l'échafaudage; 

  
 <EMI ID=5.1> 

  
en profil, une des phases de l'opération; 

  
la figo 7 représente, en coupe, un plancher à sous-face hétérogène;

  
la fige ,8 est une vue en coupe d'un plancher, à sous-face homogène, comportant un garnissage constitué par des voûtins;

  
 <EMI ID=6.1> 

  
sent brevet, se compose des poutrelles 1, d'un plafond 2 en plâtre ou béton de plâtre, accroché aux ailes inférieures des poutrelles, d'un remplissage 5 de copeaux ignifugés, ou traités au bain de ciment, et d'une chape de com-

  
 <EMI ID=7.1> 

  
més en arceaux et dont les extrémités reposent sur les ailes inférieures des poutrelles. La chape de compression peut être, également, armée par des fers

  
 <EMI ID=8.1> 

  
Les poutrelles utilisées peuvent être des'fers à I de-profil normal, ou encore des poutrelles en béton armé de diverses formes pourvu que lesdites poutrelles soient munies d'ailes ou de saillies à leur partie inférieure. On a représenté,' à titre d'exemple, sur la fig. 1 divers profils de poutrelle dont l'utilisation est possible.

  
Une telle conception confère au plafond obtenu des qualités d'isolation thermique et phonique remarquables en raison des nombreux vides intersticiels provoqués par les copeaux de bois ignifugés, ou matériau analogue foisonnant qui-constitue le garnissage 5. 

  
La présente invention concerne également des dispositifs permettant de mettre en oeuvre le procédé-d'établissement de plancher qui vient d'être décrite 

  
A cette fin, on commence (fig. 5 et 6) par disposer les poutrelles 1 parallèlement les unes aux autres et à l'écartement requis par la charge admise au mètre carré de plancher construit.

  
A l'aide de l'échafaudage roulant réglable en hauteur représenté par la fig. 4, on dispose, sous les poutrelles 1, des coffrages plans 8 horizontaux, à surface bien plane et lisse que l'on fixe les uns aux autres au moyen des boulons 9. Les coffrages 8 peuvent, en outre, être-maintenus, de place en place, par des raidisseurs 10 et des tirants 11, reliant les raidis-

  
 <EMI ID=9.1> 

  
exemple, par-des cornières jumelées. Avant de procéder-au serrage des tirants
11, des cales de bois 12 sont intercalées entre les coffrages plans et les poutrelles.

  
Lorsque les coffrages 8 sont mis en place, on coule une première couche de plâtre, d'une épaisseur de 2 à 4 centimètres environ, en veillant à ce que le plâtre, remplisse bien les intervalles entre- les- coffrages 8 et les sous-faces des poutrelles.

  
Cette première coulée de plâtre doit présenter sur sa face nonapparente une surface rugueuse qui peut-être obtenue en la brossant à l'aida d'un balai de bruyère. Afin d'augmenter sa résistance, on pourra incorporer au plâtre une trame de filasse.

  
On procède ensuite à une deuxième coulée de plâtre qui sera réalisée comme la première, en prenant soin, cependant, de lui donner la forme en auget représentée par la fig. 1, de manière à solidariser le'plafond aux ailes inférieures des poutrelles. Avant la prise du plâtre , on pose dans

  
 <EMI ID=10.1> 

  
Dans cette deuxième coulée et par mesure d'économie, on pourra  remplacer là pouzzolane par du mâchefer trié et lave.

  
Lorsque ces coulées sont terminées, on procède au décoffrage, après avoir desserré les tirants, si ceux-ci ont été prévus. Les coffrages plans 8 se posent alors sur les bastings garnissant la partie supérieure de l'échafaudage roulant qui est, alors, déplacé de façon à amener lesdits coffrages en dessous, de nouvelles travées où les opérations qui viennent d'être décrites sont recommencées jusqu'à la finition complète du plafond.

  
Au fur et à mesure qu'une surface du plafond est coulée, on procède à un léger parachèvement en supprimant les bavures et en bouchant les trous laissés par les tirants. 

  
La deuxième phase de l'opération consiste à étaler, sur la sousface, un matelas composé de copeaux de bois ignifugés ou neutralisés au bain

  
de ciment. La surface du matelas sera façonnée en dos d'âne, comme représenté par la fig. 1, à l'aide d'un gabarit de bois prenant appui sur la partie supérieure des poutrelles. 

  
Lorsque ces matelas seront disposés, on passera à la troisième

  
 <EMI ID=11.1> 

  
des poutrelles et à procéder à Inexécution de la chape de compressiono

  
Le plancher est ainsi terminé sur ses deux faces et est immédiatement utilisable pour la suite de la construction.

  
Les dispositifs utilisés pour mettre, en oeuvre le procédé qui vient d'être décrit consistent en des coffrages plans horizontaux qui peuvent être constitués par un cadre 13 en cornières-, métalliques (fig. 2) recouvert soit d'une tôle, soit de planches bien- dressées-. Des trous 14 servent de passage aux tirants. Les tirants sont de simples tiges filetées à leurs extrémités, coopérant avec des brides spéciales permettant le serrage des raidisseurs. Ces tirants peuvent avoir une de leurs extrémités formée en crochet, destinée à soutenir l'aile de la cornière formant raidisseur. L'é-



   <EMI ID = 1.1>

AND FLOORS OBTAINED USING THE SAID PROCESS.

  
The processes for producing floors known to date, that is to say the processes using either wooden joists, or reinforced concrete poured in place, or even prefabricated elements, have the drawback of requiring the assistance of 'a plasterer for plaster coatings or the implementation of a suspended ceiling.

  
This competition increases, in notable proportions, the price of the floor per unit of surface due either to the multiple operations &#65533; of fa-. bricati.on in the workshop, transport, the broken, when we are dealing with

  
a suspended ceiling, or woodwork and the application of a plaster coating, when dealing with a joist floor.

  
The present invention relates to a method of establishing

  
of floors which consists, in principle, after having placed the joists of the floor, in pouring in-situ, on a horizontal formwork with a smooth surface, placed below said joists and at a certain distance

  
of these, the underside of the floor constituting the ceiling, and to make it integral with the joists, the other elements of the floor being

  
put in place after execution of said soffit. In this way, a finished ceiling is obtained directly, the visible face of which is smooth and perfectly erected, ready to receive the painting if it is planned, without requiring, for its completion, the intervention of specialists.

  
According to an important characteristic of the invention, the ceiling

  
with a finished soffit thus constituted can be used as shuttering for the casting of the compression slab ^ generally by means of a filling material, lining the gap between the aforementioned joists.

  
The production of a floor according to this process, and in particular the molding of the underside on the smooth forms, can be carried out all at once for the entire surface of the floor when the latter is not very large. In the most frequent case where it is a question of relatively large surfaces, the molding is carried out in successive fractions. Horizontal formwork panels with a smooth surface are for this purpose mounted on a rolling scaffold, which is moved in one piece to bring the panels to the desired location.

  
In one embodiment of the method according to the invention, the aforementioned soffit is established in a single operation and has sufficient thickness to be hooked directly onto the lower flanges of the joists of the floor. In this case, this underside can be either pure plaster or fine mortar based on any binder.

  
It is also possible to use liquid concrete for the one-step casting of the soffit on the horizontal formwork with a smooth surface. Part of the binder used in the composition of the latter descends by segregation by filling the interstices and-form, by being deposited on the formwork, the finished smooth underside of the floor.

  
In another embodiment of the method according to the invention, the underside is established in two successive operations: pouring on the flat horizontal formwork, a veil of pure plaster or of plaster mortar of relatively low thickness. eur forming the ceiling itself, then casting on this veil a concrete bucket of clinker, pozzolana, pumice or similar material, the raised edges of which hang on the flanges of the beams.

  
This bucket is poured onto the lower web before the end of the setting of the plaster or the mortar which constitutes the latter, setting which can, moreover, be delayed by the addition of a retarder to the material used.

  
It may be advantageous to embed in the aforementioned trough, arches, either in metal made stainless, or in reeds or split wood, coming to rest on the lower flanges of the joists of the floor and which consolidate the attachment of the underside. , if the spacing of the joists requires it.

  
The aforementioned soffit, homogeneous or heterogeneous, established as indicated above by in-situ casting on a flat formwork, can be used as formwork for the casting of the floor compression screed.

  
According to one characteristic of the invention, there is provided thermal and / or sound insulation between the floor and the ceiling itself.

  
said.

  
In one embodiment of this arrangement, provision is made, in order to achieve this isolation, between the aforementioned trough of the finished underside constituting the ceiling and the compression screed which will form the upper face

  
of the floor, a lining established using a pulverulent and abundant material, of low density and having the lowest possible coefficient of heat conductivity. This material will be chosen taking into account local resources, in order to lower its cost price and transport costs, and could be, for example, clinker, pozzolan, co-

  
 <EMI ID = 2.1>

  
lean at low dosage of binder.

  
The aforementioned packing can be poured directly into the bucket and fill, until flush with the upper end of the joists,

  
the caissons delimited laterally by two successive beams and of which

  
the bottom is formed by the bucket.

  
In order to further increase the insulating effect of this lining, the latter, in another embodiment of the method according to the invention, does not rest directly on the bottom of the trough but through the intermediary of elements in light material, in the form of vaults, for example, housed between the beams. Thus, between the bucket and garnis.sage, an air mattress is produced which improves the insulation of the floor, while reducing its unit weight.

  
The compression screed is cast, lastly, on the joists, in the usual way, possibly after placing a reinforcing grid on them.

  
In the event that a lining produced as indicated above is provided, the compression screed comes, in its casting, to rest thereon.

  
Insulation can only be obtained by means of an air mattress provided between the soffit and the compression screed. The concrete is supported in this case, during the pouring of the compression screed, by panels

  
 <EMI ID = 3.1>

  
the thickness and height 'suitable, cast at the same time as the bucket which was discussed above, or constituted by added elements.

  
These panels can be made from slats of fir cane reeds or any other suitable material, chosen as a function. local resources.

  
It should be noted that, in this last particular embodiment of the method according to the invention, the intermediate lining is entirely eliminated, which allows, in addition to a significant reduction in the construction, a substantial saving in material - and labor-intensive, especially in regions where fir lath or reed trays can be obtained in large quantities and cheaply.

  
The description which will follow, given with reference to the appended drawings given by way of nonlimiting examples, makes it possible to understand how the present method can be implemented and how the equipment used for its realization can be established. In these drawings:

  
 <EMI ID = 4.1>

  
method of the invention;

  
figo 2 is a plan of one of the smooth forms used;

  
Fig. 4 is an elevation of a rolling scaffolding, supporting the above formwork ';.

  
FIG. 3 is a detail of the means for adjusting the height of the scaffolding;

  
 <EMI ID = 5.1>

  
in profile, one of the phases of the operation;

  
FIG. 7 shows, in section, a floor with a heterogeneous underside;

  
the figure, 8 is a sectional view of a floor, with a homogeneous soffit, comprising a lining consisting of vaults;

  
 <EMI ID = 6.1>

  
sent patent, consists of joists 1, a ceiling 2 in plaster or plaster concrete, hung on the lower flanges of the joists, a filling 5 of fireproof chips, or treated with a cement bath, and a screed of com

  
 <EMI ID = 7.1>

  
més in arches and the ends of which rest on the lower flanges of the joists. The compression yoke can also be reinforced with irons

  
 <EMI ID = 8.1>

  
The beams used can be normal profile iron beams, or even reinforced concrete beams of various shapes, provided that said beams are provided with flanges or projections at their lower part. There is shown, by way of example, in FIG. 1 various joist profiles that can be used.

  
Such a design gives the ceiling obtained remarkable thermal and sound insulation qualities due to the numerous interstitial voids caused by the fire-retardant wood chips, or similar abundant material which constitutes the lining 5.

  
The present invention also relates to devices making it possible to implement the floor-setting method which has just been described.

  
To this end, we begin (fig. 5 and 6) by placing the beams 1 parallel to each other and at the spacing required by the load allowed per square meter of floor constructed.

  
Using the height-adjustable rolling scaffolding shown in fig. 4, we have, under the beams 1, horizontal flat formwork 8, with a very flat and smooth surface which is fixed to each other by means of bolts 9. The formwork 8 can, in addition, be maintained, from in place, by stiffeners 10 and tie rods 11, connecting the stiffeners

  
 <EMI ID = 9.1>

  
example, by paired angles. Before tightening the tie rods
11, wooden wedges 12 are interposed between the flat forms and the beams.

  
When the formwork 8 is in place, a first layer of plaster, approximately 2 to 4 centimeters thick, is poured in, making sure that the plaster fully fills the gaps between the forms 8 and the sub- faces of joists.

  
This first plaster cast must have a rough surface on its nonapparent surface which can be obtained by brushing it with the help of a heather broom. In order to increase its resistance, a weft of tow can be incorporated into the plaster.

  
A second plaster cast is then carried out which will be carried out like the first, while taking care, however, to give it the shape of a bucket shown in FIG. 1, so as to secure le'plafond to the lower flanges of the joists. Before setting the plaster, we lay in

  
 <EMI ID = 10.1>

  
In this second casting and for the sake of economy, we can replace the pozzolana with sorted and washed clinker.

  
When these castings are completed, one proceeds to the stripping, after having loosened the tie rods, if these have been provided. The flat formworks 8 are then placed on the bastings lining the upper part of the rolling scaffolding which is then moved so as to bring said formwork below, new spans where the operations which have just been described are repeated until to the complete finish of the ceiling.

  
As a surface of the ceiling is poured, a slight finishing is carried out by removing burrs and filling the holes left by the tie rods.

  
The second phase of the operation consists in spreading, on the subface, a mattress made up of fireproof or neutralized wood chips in the bath.

  
of cement. The surface of the mattress will be shaped like a donkey's back, as shown in fig. 1, using a wooden template resting on the upper part of the joists.

  
When these mattresses are ready, we will move on to the third

  
 <EMI ID = 11.1>

  
joists and proceed with Non-execution of the compression screed

  
The floor is thus finished on both sides and is immediately usable for the rest of the construction.

  
The devices used to implement the method which has just been described consist of horizontal flat formwork which may be constituted by a frame 13 of metal angles (FIG. 2) covered either with a sheet or with planks. well- erected-. Holes 14 serve as passage for the tie rods. The tie rods are simple rods threaded at their ends, cooperating with special flanges allowing the tightening of the stiffeners. These tie rods may have one of their ends formed as a hook, intended to support the flange of the angle iron forming a stiffener. The-


    

Claims (1)

chafaudage roulant utilisé (fig. 4) est composé d'une armature tubulaire montée sur des galets roulants dans des fers à U servant de rails. La plateforme supérieure de cet échafaudage est formée par des bastings reposant dans <EMI ID=12.1> The rolling scaffolding used (fig. 4) consists of a tubular frame mounted on rolling rollers in U-shaped bars serving as rails. The upper platform of this scaffolding is formed by bastings resting in <EMI ID = 12.1> n'est pas né.cessairede prévoir de tirants pour soutenir les coffrages horizontaux pendant la coulée de la sous-face. Pour des écartements normaux de poutrelles, les panneaux de coffrage, montés sur l'échafaudage roulant, suffisent à supporter la sous-face pendant sa coulée; la durée du travail s'en trouve notablement réduite. It is not necessary to provide tie rods to support the horizontal forms during the casting of the soffit. For normal joist spacings, the formwork panels, mounted on the rolling scaffolding, are sufficient to support the soffit during its pouring; working hours are significantly reduced. Le planchez¯ représenté en coupe fig. 7 comporte une sous-face . constituée par deux couches de nature différente. Pour l'établissement de cette sous-face , on opère comme suit : après mise en place des poutrelles 1 du plancher, on coule sur les coffrages plans une couche de plâtre pur ou de mortier de plâtre 15, d'une épaisseur de quelques centimètres, venant affleurer la face inférieure des ailes des poutrelles. Avant la fin de la prise The plankz¯ shown in section fig. 7 has an underside. constituted by two layers of different nature. For the establishment of this soffit, one operates as follows: after installation of the joists 1 of the floor, one pours on the flat formwork a layer of pure plaster or plaster mortar 15, with a thickness of a few centimeters , flush with the underside of the beam flanges. Before the end of the dose de cette couche, on procède à une deuxième coulée d'un béton de mâchefer, pouzzolane ou matériau analogue, constituant un auget 16 dont les bords viennent s'accrocher aux ailes inférieures des poutrelles 1. Des arceaux 3 peuvent être noyés dans cet auget. From this layer, a second casting of a concrete of clinker, pozzolana or similar material, constituting a bucket 16, the edges of which are hooked to the lower flanges of the beams 1. The arches 3 can be embedded in this bucket. Après la prise de la deuxième coulée précitée, on termine le plancher en déversant, dans les caissons compris entre les poutrelles, un matériau After the aforementioned second casting has set, the floor is finished by pouring, into the boxes between the beams, a material <EMI ID=13.1> <EMI ID = 13.1> 5 précité comme coffrage. 5 above as formwork. Dans le mode de réalisation représenté à la fig. 8, la sous-face est constituée par une coulée de béton liquide 17. On vient ensuite poser sur l'auget, dans les caissons délimités par deux poutrelles successives, des voûtins tels que 18 dont la face supérieure affleure les ailes supérieures des poutrelles 1. Un matelas d'air 19 se trouve ainsi ménagé entre- l'auget In the embodiment shown in FIG. 8, the underside is formed by a pour of liquid concrete 17. We then place on the trough, in the boxes delimited by two successive beams, vaults such as 18, the upper face of which is flush with the upper flanges of the beams 1 An air mattress 19 is thus provided between the bucket. <EMI ID=14.1> <EMI ID = 14.1> lisant lesdits voûtins comme coffrages. Un quadrillage- d'armature 20, réuni par des épingles telles que-21 aux fers de mise sous tension 22 des poutrelles, peut être-prévu dans tous les cas. reading said vaults as shuttering. A reinforcement grid 20, joined by pins such as 21 to the tensioning irons 22 of the joists, can be provided in all cases. La figure 9 représente un plancher dont la sous-face constituant le plafond fini est établie en une première phase de la manière précédemment décrite. Le garnissage total ou partiel précédemment prévu est ici supprimé, l'isolement du plancher étant assuré uniquement par le matelas d'air subsistant en fin d'opération entre l'auget et la chape de compression. Pour maintenir cette dernière pendant sa coulée, il est prévu, dans l'exemple représenté, des clayonnages constitués par exemple par des tapis de tiges de roseaux 23 Ces panneaux reposent sur des nervures transversales 24 qui peuvent être coulées en même temps que l'auget 16, ou constitués par des éléments rapportés. FIG. 9 represents a floor, the underside of which constituting the finished ceiling is established in a first phase in the manner previously described. The total or partial lining previously provided is here deleted, the floor insulation being provided only by the air mattress remaining at the end of the operation between the bucket and the compression screed. In order to maintain the latter during its casting, it is provided, in the example shown, for wickerings constituted for example by carpets of reed stems. 23 These panels rest on transverse ribs 24 which can be cast at the same time as the bucket 16, or consist of attached elements. Le tapis 23 formant bouclier perdu peut être constitué par n'importe quel écran susceptible de supporter le poids de la chape de compression avant sa prise. On.peut utiliser, à cet effet, des écrans en lattes- de bois assemblées par une trame de fils de fer, ou tout autre panneau léger et suffisamment rigide, plein ou à claire-voie. The mat 23 forming a lost shield can be formed by any screen capable of supporting the weight of the compression screed before it is set. We can use, for this purpose, wooden slat screens assembled by a frame of iron wires, or any other light and sufficiently rigid panel, solid or slatted. REVENDICATIONS. CLAIMS. <EMI ID=15.1> <EMI ID = 15.1> qui consiste, après avoir mis en place les poutrelles du plancher, à couler in-situ, sur un coffrage horizontal à surface lisse, disposé au-dessous desdites poutrelles, et à une certaine distance de celles-ci, la sous-face- du plancher constituant le plafond, et à rendre celle-ci solidaire des poutrelles, les autres éléments du plancher étant mis en place après exécution de ladite sous-face. <EMI ID=16.1> which consists, after having put in place the joists of the floor, to cast in-situ, on a horizontal formwork with a smooth surface, arranged below said joists, and at a certain distance from them, the underside of the floor constituting the ceiling, and to make it integral with the beams, the other elements of the floor being put in place after execution of said soffit. <EMI ID = 16.1> que le plafond à sous-face finie ainsi constitué est utilisé comme coffrage pour la coulée de la dalle de compression. that the finished soffit ceiling thus formed is used as formwork for the casting of the compression slab. 3. - Procédé selon la revendication 1, caractérisé par le fait que la sous-face précitée est établie en une seule opération et à une épaisseur suffisante pour venir s'accrocher directement sur les ailes inférieures des poutrelles du plancher. 3. - Method according to claim 1, characterized in that the aforementioned soffit is established in a single operation and to a sufficient thickness to come to hang directly on the lower flanges of the joists of the floor. <EMI ID=17.1> <EMI ID = 17.1> ment faible épaisseur, formant le, plafond proprement dit, et la deuxième consistant en la coulée sur ce voile d'un auget dont les bords relevés viennent s'accrocher aux ailes des poutrellés, low thickness, forming the ceiling itself, and the second consisting of the casting on this wall of a bucket whose raised edges come to cling to the flanges of the beams, 5. - Procédé selon l'une quelconque des revendications 1, 3 ou 4, caractérisé par le fait que des arceaux sont noyés dans l'auget afin de consolider l'accrochage de la sous-face aux poutrelles-. 5. - Method according to any one of claims 1, 3 or 4, characterized in that the arches are embedded in the bucket in order to consolidate the attachment of the underside to the beams. 6. - Procédé selon l'une quelconque des revendications 1 à 5, caractérisé par le fait qu'il est prévu un isolement entre la dalle de compression du plancher et la sous-face de celui-ci qui constitue le plafond. 6. - Method according to any one of claims 1 to 5, characterized in that there is provided an insulation between the compression slab of the floor and the underside of the latter which constitutes the ceiling. 7. - Procédé selon la revendication 6, caractérisé par le fait que l'isolement est réalisé à l'aide d'un matériau pulvérulent et foisonnant qui vient remplir entièrement les cavités comprises entre: la face supérieure 7. - Method according to claim 6, characterized in that the isolation is carried out using a pulverulent and abundant material which completely fills the cavities between: the upper face <EMI ID=18.1> <EMI ID = 18.1> fin d'opération sur le plancher. end of operation on the floor. 8. - Procédé selon la revendication 6, caractérisé par le fait que l'isolement est réalisé à L'aide d'un remplissage et d'un matelas d'air. 8. - Method according to claim 6, characterized in that the isolation is carried out using a filling and an air mattress. <EMI ID=19.1> <EMI ID = 19.1> que l'isolement est réalisé uniquement à l'aide d'un matelas d'air.- that the isolation is carried out only using an air mattress. 10.- Procédé selon la revendication 9, caractérisé par des panneaux pleins ou à claire-voie, destinés à soutenir la chape de compression pendant sa coulée et reposant sur des nervures solidaires de la sous-face coulée en premier lieu. 10. A method according to claim 9, characterized by solid or slatted panels intended to support the compression screed during its casting and resting on ribs integral with the soffit cast in the first place. 11.- Dispositif pour la mise en'oeuvre du procédé selon l'une quelconque des revendications 1 à 10, caractérisé par des coffrages plans à surface lisse, reposant sur un échafaudage mobile. 11.- Device for the implementation of the method according to any one of claims 1 to 10, characterized by flat formwork with a smooth surface, resting on a mobile scaffolding. 12.- Dispositif suivant la revendication 11, caractérisé par le fait que les coffrages sont maintenus par des raidisseurs et des tirants prenant appui; sur des sommiers disposés sur les poutrelles constituant l'armature du plancher. 12.- Device according to claim 11, characterized in that the formwork is held by stiffeners and tie rods bearing support; on box springs arranged on the joists constituting the floor reinforcement. 13.- Plancher obtenu par le procédé et à l'aide du dispositif selon l'une quelconque des revendications 1 à 12. 13. A floor obtained by the method and using the device according to any one of claims 1 to 12.
BE495379D 1949-10-26 BE495379A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
FR291706X 1949-10-26
FR240450X 1950-04-24

Publications (1)

Publication Number Publication Date
BE495379A true BE495379A (en)

Family

ID=26214251

Family Applications (1)

Application Number Title Priority Date Filing Date
BE495379D BE495379A (en) 1949-10-26

Country Status (5)

Country Link
BE (1) BE495379A (en)
CH (1) CH287489A (en)
DE (1) DE813767C (en)
FR (1) FR990322A (en)
NL (1) NL153357C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE941448C (en) * 1952-12-16 1956-04-12 Kurt Weber Reinforced concrete rib ceilings to be produced without formwork from prefabricated -shaped ceiling beams, ceiling panels and in-situ concrete ribs between the ceiling panels

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE941448C (en) * 1952-12-16 1956-04-12 Kurt Weber Reinforced concrete rib ceilings to be produced without formwork from prefabricated -shaped ceiling beams, ceiling panels and in-situ concrete ribs between the ceiling panels

Also Published As

Publication number Publication date
CH287489A (en) 1952-12-15
FR990322A (en) 1951-09-20
DE813767C (en) 1951-09-17
NL153357C (en)

Similar Documents

Publication Publication Date Title
CN104060781A (en) Cast-in-situ cranked slab stair without seams at stair sections and construction method
EP0750709A1 (en) Floor, method for making same and building comprising at least one such floor
BE495379A (en)
KR101596637B1 (en) concrete lintel for steel and manufacturing method thereof
CN110725532B (en) Supporting system for small formwork of bare concrete decorative wall and construction process
CN102767284B (en) Semi-prefabricating construction process for concrete thin-wall lower return eave
EP1355013A1 (en) Connection between a floor slab and a wall and insulated building comprising such a connection
CN111042391B (en) Oblique lapping structure for main structure and masonry structure
CN104234315B (en) Three-back-shaped external wall rod structure and construction method thereof
BE1010092A6 (en) Method of manufacturing and assembly of an element construction concrete.
BE458504A (en)
JP3249017B2 (en) Concrete crack prevention method using sheet
FR2743584A1 (en) PROCESS FOR MANUFACTURING A STUDDED PANEL, PANEL OBTAINED BY THIS PROCESS AND CONSTRUCTION INCLUDING AT LEAST ONE SUCH PANEL
FR2472644A1 (en) Reinforced concrete flooring panel - includes corrugated iron sheet to bind upper concrete and lower mortar layers together
FR2515567A1 (en) Method of forming precast concrete wall panel - has polygonal rubble face using soaked elastic foam to mount stones on bed with sand forming recessed joints
CH367311A (en) Construction element and method for its manufacture
FR2678659A1 (en) Method for protection and cladding of a building facade, and corresponding building
FR2530705A1 (en) Structural elements especially for the prefabrication of floors.
CN107217855A (en) A kind of ceramsite concrete light-weight structural wall board construction
CA1036797A (en) Building panels
BE1009726A6 (en) Signs of recovery in lieu of floor tile or yoke.
CN107630559B (en) Pre-tensioning construction device and method for floor slab
CH356898A (en) Reinforced concrete construction element for pavements and partitions
EP1041209B1 (en) Product and procedure for fireproofing
FR2525263A1 (en) Method of constructing prefabricated buildings - comprises casting preliminary flooring slabs which incorporate lifting points allowing installation using cranes