AU2023226534A1 - Pre-grouting treatment method for water hazards in shaft construction - Google Patents

Pre-grouting treatment method for water hazards in shaft construction Download PDF

Info

Publication number
AU2023226534A1
AU2023226534A1 AU2023226534A AU2023226534A AU2023226534A1 AU 2023226534 A1 AU2023226534 A1 AU 2023226534A1 AU 2023226534 A AU2023226534 A AU 2023226534A AU 2023226534 A AU2023226534 A AU 2023226534A AU 2023226534 A1 AU2023226534 A1 AU 2023226534A1
Authority
AU
Australia
Prior art keywords
shaft
grouting
holes
treatment
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
AU2023226534A
Inventor
Jidong CHENG
Longbo GAO
Junhua HOU
Rongyi LIU
Wenmao LV
Ziwei QIAN
Lei Wang
Xianshuai WU
Nengcheng YU
Dong Zhang
Hengxin ZHOU
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Publication of AU2023226534A1 publication Critical patent/AU2023226534A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

A pre-grouting treatment method for water hazards in shaft construction, the method mainly comprising the steps of: performing surveying and setting out to obtain the plane position and downhole position of a shaft; analyzing geological data of the shaft to determine a zone of a lower section of the shaft that needs a grouting treatment; constructing an annular surrounding roadway (1) in the lower section of the shaft; constructing grouting drill holes (2) upwards in the lower section of the shaft to perform a pre-grouting treatment on an aquifer; after the grouting treatment on the lower section of the shaft is completed, performing a filling treatment on the annular surrounding roadway (1); normally excavating the shaft downwards to penetrate the treated aquifer in the lower section; and finally completing the construction of the shaft. The method is suitable for operating conditions in which there has been a roadway around the bottom of a shaft, the shaft is at a great depth, and an aquifer is mainly located in a bottomhole section. By means of the method, the upper-section excavation and lower-section water hazard pre-treatment of a shaft can be performed synchronously and operated in parallel, thereby reducing the time consumed by conventional grouting-from-the surface and pre-grouting-from-the-working-face, and thus saving on the overall shaft construction time.

Description

PRE-GROUTING TREATMENT METHOD FOR WATER HAZARDS IN SHAFT CONSTRUCTION TECHNICAL FIELD
[0001] The present invention relates to the field of an underground hazards treatment in a coal mine, and specifically to a pre-grouting treatment method for water hazards in a shaft construction.
BACKGROUND
[0002] The shaft is utilized in the shaft mine to establish the connection between the upper section and the lower section of the mine, which is the throat of the mine. The current shaft sinking methods comprise a freezing method, a caisson method, a drilling method and a common method. When the common method is utilized in shaft construction, the aquifer water hazards that the shaft requires to penetrate can be treated by the pre-grouting method, or a method of excavation and masonry with water in a shaft disclosed in Chinese patent CN112746849B can also be utilized for water hazard prevention and control.
[ 0003] At present, there are two common pre-grouting treatment methods for water hazards in the shaft constructions: the ground pre-grouting method and the working face pre-grouting method. After the shaft construction is completed, the residual leakage point of the shaft wall can be treated by back-wall grouting. The ground pre-grouting is mainly used for the strata with numerous aquifers and large spans. By constructing multiple boreholes on the ground before the shaft construction to the lowest aquifer, each aquifer is controlled by segmented grouting, and the shaft is excavated after the grouting is completed. The working face pre-grouting means that after the shaft is excavated to a certain distance from the aquifer, the excavation is terminated, and a plurality of grouting holes are constructed on the working surface to carry out the grouting, and the shaft is excavated again after the grouting is completed. In addition, a grouting method is also proposed in a process of a multi-working face parallel operation on a ground pre-grouting of a shaft disclosed by the Chinese patent CN103233699A, in which first section of the grouting still occupies the shaft construction time, and the effective engineering amount of the second and third sections of the ground grouting drilling is little and the cost is high. At present, a lot of shaft construction time is occupied by the commonly used shaft grouting methods.
SUMMARY
[0004] In view of the above technical deficiencies, the objectives of the present invention are to provide a pre-grouting treatment method for water hazards in a shaft construction, which controls a pre-grouting treatment on an aquifer at the bottom section of the shaft by constructing grouting drill holes upwards at the bottom of the shaft. In the method, the normal excavation of the upper section of the shaft during the process of grouting is not affected, the synchronization of grouting and shaft excavation is truly implemented, and the progress of the shaft construction is not affected.
[ 0005] In order to solve the above technical problems, the technical solutions adopted by the present invention are as follows.
[ 0006] Provided in the present invention is a pre-grouting treatment method for water hazards in a shaft construction. The method includes the following steps.
[ 0007] In Step 1, a center point of a shaft on the ground is surveyed and set out, a position of a bottom of the shaft is surveyed and set out.
[ 0008] In Step 2, geological data for the shaft are analyzed to determine a zone of the lower section of the shaft that requires a grouting treatment.
[ 0009] In Step 3, an upper section of the shaft is constructed normally, a connecting roadway towards the bottom of the shaft is constructed, the annular surrounding roadway is constructed around the bottom of the shaft and a temporary drainage system is established.
[0010] In Step 4, the aquifer in the lower part of the shaft is treated by pre-grouting by drilling the hole upward in the annular surrounding roadway.
[0011] In Step 5, after the pre-grouting treatment at the lower section of the shaft is completed, a filling treatment on the annular surrounding roadway is performed, the shaft is excavated downwards normally to penetrate the treated aquifer at the lower section of the shaft.
[0012] In Step 6, the shaft is excavated downwards normally to a designed depth position of the shaft, the relevant support works are completed, a connection between the bottom of the shaft and downhole roadways is established, and a construction of the shaft is completed.
[0013] Preferably, in Step 3, connecting roadway is constructed at the bottom of the shaft through original downhole roadways, and the annular surrounding roadway is constructed around the bottom of the shaft.
[ 0014] Preferably, in Step 3, the annular surrounding roadway is 6 m to 8 m away from an outer wall of the shaft with a height of 4 m high and a width of 3 m, is capable of accommodating an underground tunnel drilling rig for operation.
[ 0015] Preferably, in Step 4, a plurality of equispaced grouting drill holes are arranged vertically upward by taking the annular surrounding roadway constructed around the shaft as a drilling field, depths of the grouting drill holes reach an uppermost aquifer, and grouting operations are performed through the grouting drill holes.
[ 0016] Preferably, in Step 4, a construction method of the grouting drill holes is as follows: firstly, the plurality of grouting drill holes are constructed uniformly, and then checking supplementary-grouting holes are constructed complementally in intervals between adjacent grouting drill holes.
[ 0017] When no water flows out of the checking-supplementary-grouting holes, it indicates that an expected grouting effect is reached, and then the grouting is terminated.
[ 0018] When water remains flowing out of the checking-supplementary-grouting holes, the grouting for the checking-supplementary-grouting holes is completed, subsequently, a second round of checking-supplementary-grouting holes are constructed in the intervals between the constructed grouting drill holes, in this way, until no water flows out of the checking supplementary-grouting holes, an effective curtain of the grouting is formed, and an expected effect of the grouting is formed.
[ 0019] The beneficial effects of the present invention are as follows. the present invention is suitable for the operating conditions in which there is a roadway around the bottom of the shaft, the shaft depth is at a great depth, and an aquifer is mainly located at the bottom of the shaft, which can implement the synchronization and parallel operation of the upper section excavation and the lower section water hazard pre-treatment of the shaft, thereby reducing the time consumed by conventional grouting from the surface and pre-grouting from the working face, and thus saving on the overall shaft construction time.
BRIEF DESCRIPTION OF THE DRAWINGS
[0020] In order to explain the technical solutions in the embodiments of the present invention or the prior art more clearly, the following is a brief introduction on the drawings required to be used in the descriptions of the embodiments or the prior arts. It is obvious that the drawings described below are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative efforts.
[ 0021] FIG. 1 illustrates a structural schematic diagram of a pre-grouting treatment method for water hazards in a shaft construction provided in the embodiments of the present invention.
[ 0022] FIG. 2 illustrates a schematic diagram of a formation of a waterproof curtain provided in the embodiments of the present invention.
[ 0023] Brief descriptions on the numerals of the drawings are as follows.
[ 0024] 1. Annular surrounding roadway; 2. Grouting drill hole; 3. Waterproof curtain.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[ 0025] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. It will be apparent that the described embodiments are merely one part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without any creative efforts shall fall within the protection scope of the present invention.
[ 0026] As illustrated in FIGS. 1 to 2, provided is a pre-grouting treatment method for water hazards in a shaft construction. The method includes the following steps.
[ 0027] 1. The survey and set-out of the plane position and the downhole position of the shaft:. according to the design drawings of the shaft, the center point on the ground of the shaft is surveyed and set out, the position for the bottom of the shaft is surveyed and set out.
[ 0028] 2. The analysis of the geological data for the shaft to determine the zone of the lower section that requires the grouting treatment: the data for the shaft are collected, sort out and analyzed to determine such as the location, structure and thickness of the aquifer that requires to be treated in the lower-section of the shaft.
[0029] 3. The normal construction at the upper-section of the shaft and the excavation of the annular surrounding roadway grouted at the lower-section: the excavation of the upper-section of the shaft is carried out, and the connecting roadway (the roadway is not wasted, even if other shaft construction methods are used, this roadway will also be constructed in the later stage) are constructed simultaneously through the original downhole roadways, and the annular surrounding roadway is constructed around the bottom of the shaft. The roadway is 6 m to -8 m away from the outer wall of the shaft with the height of 4 m and the width of 3 m, which can accommodate an underground tunnel drilling rig for operation.
[ 0030] At the same time, the temporary drainage system is constructed or pipelines are laid downhole to discharge the water flew out from the grouting drill holes 2 in the later stage in the annular surrounding roadway 1.
[ 0031] 4. The normal construction at the upper-section of the shaft, the pre-grouting treatment on an aquifer at the lower section of the shaft by constructing grouting drill holes upwards: the upper-section of the shaft is continued to be excavated normally, and the grouting operation of the aquifer at the lower section is performed simultaneously, grouting drill holes 2 are arranged upward vertically by taking the annular surrounding roadway 1 constructed around the shaft as a drilling field, the depths of the grouting drill holes 2 reach an uppermost aquifer, and the grouting operations are performed through the grouting drill holes 2.
[ 0032] The opened positions of the grouting drill holes 2 are located in the annular surrounding roadway 1, the grouting drill holes 2 are arranged equidistantly, and the construction is carried out by selecting holes at intervals. Firstly, 24 grouting drill holes are constructed uniformly, and then the checking-supplementary-grouting holes are constructed complementally in intervals between 4 adjacent grouting drill holes 2. When no water flows out of the checking-supplementary-grouting holes, it indicates that an expected grouting effect is reached, and then the grouting is terminated.
[ 0033] When water remains flowing out of the checking-supplementary-grouting holes, the grouting for the checking-supplementary-grouting holes is completed, subsequently, a second round of checking-supplementary-grouting holes are constructed in the intervals between constructed grouting drill holes 2, in this way, until no water flows out of the checking supplementary-grouting holes, an effective curtain 3 of grouting is formed, and an expected effect of grouting is formed.
[0034] 5. After the pre-grouting treatment at the lower-section of the shaft is completed, a filling treatment is performed on the annular surrounding roadway, the shaft is excavated downwards normally to penetrate the treated aquifer at the lower section. Since the aquifer is treated in advance, no water hazards accidents will be caused, and dry shafts can be basically drilled.
[ 0035] 6. The completion of the shaft construction: the shaft is excavated downwards normally to a designed depth position of the shaft, the relevant support works are completed, a connection between the bottom of the shaft and downhole roadways is established, and a construction of the shaft is completed.
[ 0036] Compared with the conventional ground grouting method, this method saves a large amount of useless drilling in the upper-section, saves the time and cost of water hazards treatments, and reduces the difficulties and risks of the control in the conventional over-loose interval of drilling. Compared with the S-hole type ground pre-grouting proposed by a process of a multi-working face parallel operation on a ground pre-grouting of a shaft in Chinese patent CN103233699A, this method saves the extension footage of the shaft and reduces the cost. Compared with the pre-grouting of the working face, the present invention does not require to terminate the excavation, that is, it does not require to terminate the shaft excavation specifically for water hazards treatments. In addition, the space of the working face in the shaft in the prior art is relative small, only one drilling equipment can be generally accommodated, and the overall drilling speed is slow, while the present invention is capable of operating a plurality of devices at the same time, saving the overall construction time of the shaft greatly.
[ 0037] It will be apparent to those skilled in the art that various changes and variants can be made in the present invention without departing from the spirit and scope of the present invention. In this way, provided that these modifications and variations of the present invention are within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (5)

CLAIMS What is claimed is:
1. A pre-grouting treatment method for water hazards in a shaft construction, comprising following steps:
Step 1, surveying and setting out a center point of a shaft on a ground, surveying and setting out a position of a bottom of the shaft;
Step 2, analyzing geological data for the shaft to determine a zone of a lower-section of the shaft that requires a grouting treatment;
Step 3, normally constructing at an upper-section of the shaft, constructing an annular surrounding roadway (1) at the bottom of the shaft and establishing a temporary drainage system;
Step 4, treating, by pre-grouting and drilling holes (2) upward, the aquifer in the lower part of the shaft;
Step 5, performing, after the pre-grouting treatment on the lower-section of the shaft is completed, a filling treatment on the annular surrounding roadway (1), normally excavating the shaft downwards to penetrate a treated aquifer at the lower section of the shaft.
Step 6, normally excavating the shaft downwards to a designed depth position of the shaft, completing relevant support works, establishing a connection between the bottom of the shaft and downhole roadways, and completing a construction of the shaft.
2. The pre-grouting treatment method for the water hazards in the shaft construction according to claim 1, wherein in Step 3, connecting roadway are constructed at the bottom of the shaft and the annular surrounding roadway (1) is constructed around the bottom of the shaft through original downhole roadways.
3. The pre-grouting treatment method for the water hazards in the shaft construction according to claim 2, wherein in Step 3, the annular surrounding roadway (1) is 6 m to 8 m away from an outer wall of the shaft with a height of 4 m and a width of 3 m, is capable of accommodating an underground tunnel drilling rig for operation.
4. The pre-grouting treatment method for the water hazards in the shaft construction according to claim 3, wherein in Step 4, a plurality of equispaced grouting drill holes (2) are arranged vertically upward by taking the annular surrounding roadway (1) constructed around the shaft as a drilling field, depths of the grouting drill holes (2) reach an uppermost aquifer, and grouting operations are performed through the grouting drill holes (2).
5. The pre-grouting treatment method for the water hazards in the shaft construction according to claim 4, wherein in Step 4, a construction method of the grouting drill holes (2) is: uniformly constructing the plurality of grouting drill holes (2), and then complementally constructing checking-supplementary-grouting holes in intervals between adjacent grouting drill holes (2);
indicating, when no water flows out of the checking-supplementary-grouting holes, that an expected grouting effect is reached, and then terminating the grouting; and
when water remains flowing out of the checking-supplementary-grouting holes, the grouting for the checking-supplementary-grouting holes, subsequently, constructing a second round of checking-supplementary-grouting holes in the intervals between the constructed grouting drill holes (2), processing in this way until no water flows out of the checking-supplementary grouting holes, forming an effective curtain (3) of the grouting, and achieving an expected effect of the grouting.
AU2023226534A 2022-02-25 2023-02-17 Pre-grouting treatment method for water hazards in shaft construction Pending AU2023226534A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN202210178346.5 2022-02-25
CN202210178346.5A CN114635697B (en) 2022-02-25 2022-02-25 Pre-grouting treatment method for water damage of shaft well construction
PCT/CN2023/076732 WO2023160471A1 (en) 2022-02-25 2023-02-17 Pre-grouting treatment method for water hazards in shaft construction

Publications (1)

Publication Number Publication Date
AU2023226534A1 true AU2023226534A1 (en) 2024-05-09

Family

ID=81948084

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2023226534A Pending AU2023226534A1 (en) 2022-02-25 2023-02-17 Pre-grouting treatment method for water hazards in shaft construction

Country Status (3)

Country Link
CN (1) CN114635697B (en)
AU (1) AU2023226534A1 (en)
WO (1) WO2023160471A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114320303A (en) * 2021-12-09 2022-04-12 中国铁建大桥工程局集团有限公司 Method for excavating vertical shaft flood discharge tunnel body support
CN114635697B (en) * 2022-02-25 2023-01-24 中国矿业大学 Pre-grouting treatment method for water damage of shaft well construction
CN115030727B (en) * 2022-06-20 2023-04-07 长沙矿山研究院有限责任公司 Method for treating harm of local water spraying in well shaft with installed equipment
CN115324592A (en) * 2022-07-26 2022-11-11 陕西延长石油矿业有限责任公司 Dynamic monitoring and dynamic response control method for aquifer for well construction
CN117780354B (en) * 2024-02-28 2024-05-14 安徽建筑大学 Method for reinforcing bottom of shaft of coal mine vertical shaft to be built by thick loose layer thin bedrock by sparse-filling

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4458945A (en) * 1981-10-01 1984-07-10 Ayler Maynard F Oil recovery mining method and apparatus
US5842518A (en) * 1997-10-14 1998-12-01 Soybel; Joshua Richard Method for drilling a well in unconsolidated and/or abnormally pressured formations
CN102518470B (en) * 2011-12-27 2014-07-09 陕西彬长矿业集团有限公司 Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN105134125B (en) * 2015-08-26 2018-09-11 北京中煤矿山工程有限公司 Annular space bottom end construction technology for plugging after gas vertical wall
CN105545330A (en) * 2016-02-26 2016-05-04 河北钢铁集团矿业有限公司 Water prevention and control process in construction of metallurgical underground mining ore pass fragmenting system
CN109026010B (en) * 2018-08-13 2019-10-01 中煤能源研究院有限责任公司 A kind of mine seepage well slip casting type sinking shaft construction method
CN109854249A (en) * 2019-03-04 2019-06-07 中煤第五建设有限公司 It is a kind of for extra deep shaft formation pre processing around the lane Jing Huan method
CN111365002B (en) * 2020-03-30 2021-07-30 北京中煤矿山工程有限公司 Ground pre-grouting method for small-section high wellbore in complex stratum
CN112746849B (en) * 2020-12-11 2022-02-18 中国矿业大学 Shaft water-carrying digging and building method
CN114635697B (en) * 2022-02-25 2023-01-24 中国矿业大学 Pre-grouting treatment method for water damage of shaft well construction

Also Published As

Publication number Publication date
CN114635697B (en) 2023-01-24
WO2023160471A1 (en) 2023-08-31
CN114635697A (en) 2022-06-17

Similar Documents

Publication Publication Date Title
AU2023226534A1 (en) Pre-grouting treatment method for water hazards in shaft construction
CA2614569C (en) Method of increasing reservoir permeability
CN103835651B (en) A kind of single hole directional drilling local slip casting mine shaft rising boring technique
CN103835648B (en) One improves rock stratum performance mine shaft rising boring technique by surface grout injection
CN111206933A (en) Tunnel construction method for traversing karst water-rich section
CN111594258A (en) Technical method for quickly extracting gas to reach standard by using broken soft low-permeability outburst coal seam instead of roadway through holes
CN101915072B (en) Method for extracting coal bed gas in stable mining region by ground well drilling
CN111140279B (en) Method for preventing and treating old empty water on thick coal seam under condition of repeated mining caused by small kiln damage to layering
CN111255463B (en) Hard top plate comb-shaped long drilling segmented fracturing roadway deformation source treatment method
CN109611146B (en) Separation layer water drainage grouting method
CN103867229A (en) Coal mine large-mining-depth and next-group coal exploitation water control comprehensive treatment method
CN104975868A (en) Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling
CN106089291A (en) A kind of collaborative extraction is caving the old dead zone of formula and the method for lower coal seam coal bed gas
CN108412453A (en) A kind of coal mining water controls system and construction method altogether with gas
CN105804754A (en) Coal uncovering method for mining shaft with coal seam as main water-bearing layer
CN103742188A (en) Coal mine pump drainage gas well and drilling method thereof
CN113107589B (en) Advanced pre-drainage method for coal seam roof aquifer ground
JP7292772B2 (en) External expansion pipe construction method for drilling in the mining zone
CN110778317A (en) Construction method for ground grouting filling drilling structure in caving zone in mining process
CN117988845A (en) Grouting modification and reinforcement method for zone of soft rock breaking zone of underground coal mine
RU2382166C1 (en) Method of drilling-in
CN114635748B (en) Method for preventing and controlling water damage of shaft sinking
CN114278372B (en) Diversion arrangement method for underground directional drilling area of huge thick water-rich layer
CN114575844A (en) Roadway roof segmented pressure relief and reinforcement control method based on double-roadway excavation
CN111236310B (en) Construction method of connecting channel of existing underground structure in weak water-rich stratum