CN114635697A - Pre-grouting treatment method for water damage of shaft well construction - Google Patents

Pre-grouting treatment method for water damage of shaft well construction Download PDF

Info

Publication number
CN114635697A
CN114635697A CN202210178346.5A CN202210178346A CN114635697A CN 114635697 A CN114635697 A CN 114635697A CN 202210178346 A CN202210178346 A CN 202210178346A CN 114635697 A CN114635697 A CN 114635697A
Authority
CN
China
Prior art keywords
shaft
grouting
roadway
treatment
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210178346.5A
Other languages
Chinese (zh)
Other versions
CN114635697B (en
Inventor
钱自卫
余能成
高龙博
刘荣谊
王磊
吴现帅
张冬
吕文茂
周恒心
程继东
侯俊华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN202210178346.5A priority Critical patent/CN114635697B/en
Publication of CN114635697A publication Critical patent/CN114635697A/en
Application granted granted Critical
Publication of CN114635697B publication Critical patent/CN114635697B/en
Priority to AU2023226534A priority patent/AU2023226534A1/en
Priority to PCT/CN2023/076732 priority patent/WO2023160471A1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage

Abstract

The invention discloses a shaft well construction water damage pre-grouting treatment method which mainly comprises the steps of measuring and releasing a shaft plane position and a downhole position, analyzing shaft geological data to determine a section of a lower section needing grouting treatment, constructing a ring-shaped surrounding tunnel of the lower section of a shaft, constructing a grouting drilling hole upwards in the lower section of the shaft to perform pre-grouting treatment on a water-bearing layer, grouting the ring-shaped surrounding tunnel and filling treatment after the grouting treatment of the lower section of the shaft is finished, normally tunneling the shaft downwards to pass through the lower section treated water-bearing layer and finally completing shaft construction; the invention is suitable for the working condition that the periphery of the bottom of the shaft is provided with a roadway, the depth of the shaft is larger, and the aquifer is mainly positioned in the bottom section of the shaft; the synchronous and parallel operation of the upper-section tunneling of the shaft and the lower-section water damage pre-treatment can be realized, the time delay of conventional ground grouting and working surface pre-grouting is reduced, and the shaft construction time is integrally saved.

Description

Pre-grouting treatment method for water damage during shaft construction
Technical Field
The invention relates to the field of underground disaster treatment of coal mines, in particular to a pre-grouting treatment method for water damage of shaft construction.
Background
The underground mine establishes the up-down connection through the shaft and is the throat key of the mine. The current methods for sinking the shaft include freezing method, open caisson method, drilling method and common method. When a well is built by a common method, the aquifer water damage which the shaft needs to pass through can be treated by adopting a pre-grouting method, and the shaft water-carrying digging and building method disclosed by Chinese patent CN112746849B can also be adopted for water damage prevention and control.
The current common method for treating water damage during well construction by grouting mainly comprises two methods, namely a ground pre-grouting method and a working face pre-grouting method, and the method is characterized in that after a shaft is constructed, the residual water leakage points on the wall of the shaft are treated by grouting after the wall is constructed. The ground pre-grouting mainly aims at the stratum with multiple aquifers and large span, a plurality of drill holes are constructed on the ground before the construction of a shaft to reach the lowest aquifer, each aquifer is controlled through sectional grouting, and the shaft is tunneled after the grouting is finished. And pre-grouting on the working face, namely tunneling the shaft to a certain distance from the aquifer, stopping tunneling, constructing a plurality of grouting drill holes downwards on the working face, grouting, and tunneling the shaft again after grouting. In addition, the shaft ground pre-grouting multi-working-face parallel operation process disclosed in the Chinese patent CN103233699A also provides a grouting mode, the first section of grouting still occupies shaft construction time, and the second section and the third section of ground grouting drilling have small effective engineering quantity and high cost. The current commonly used shaft grouting method occupies a large amount of shaft construction time.
Disclosure of Invention
Aiming at the technical defects, the invention aims to provide a method for treating the water damage in shaft construction by pre-grouting, which is characterized in that a grouting hole is constructed upwards at the bottom of a shaft, and pre-grouting control is carried out on a water-bearing stratum at the bottom section of the shaft.
In order to solve the technical problems, the invention adopts the following technical scheme:
the invention provides a pre-grouting treatment method for water damage of shaft well construction, which comprises the following steps:
s1, measuring the central point of the shaft on the ground and the position of the shaft bottom of the shaft;
s2, analyzing geological data of the shaft, and determining a section of the lower section of the shaft needing grouting treatment;
s3, normally constructing the upper section of the shaft, and constructing the shaft bottom to form an annular surrounding roadway; constructing a connection tunnel at the bottom of a shaft, constructing an annular surrounding tunnel at the periphery of the bottom of the shaft and constructing a temporary drainage system;
s4, pre-grouting treatment is carried out on the aquifer through upward construction grouting drilling at the lower section of the shaft;
s5, after the grouting treatment of the lower section of the shaft is finished, filling treatment is carried out on the annular surrounding roadway at the bottom of the shaft, and the shaft is normally tunneled downwards to penetrate through the treated aquifer at the lower section;
and S6, normally tunneling the shaft downwards to the designed well depth position, completing the related supporting work, establishing the connection between the shaft bottom and the underground roadway, and completing the shaft construction.
Preferably, in step S3, a communication roadway is constructed at the bottom of the shaft through the original underground roadway, and an annular surrounding roadway is constructed at the periphery of the bottom of the shaft.
Preferably, in step S3, the annular round roadway is 6-8m away from the outer wall of the shaft, and the annular round roadway has a height of 4m and a width of 3m, so as to accommodate the operation of the underground tunnel drilling machine.
Preferably, in step S4, a plurality of grouting drill holes are vertically and uniformly distributed upwards through an annular surrounding roadway constructed around the shaft as a drilling site, the depth of each grouting drill hole reaches the uppermost aquifer, and grouting operation is performed through the grouting drill holes.
Preferably, in step S4, the grouting and drilling construction method includes: firstly, uniformly constructing a plurality of grouting drill holes, and then supplementing construction and checking injection supplementing holes in the interval between adjacent grouting drill holes;
if the water does not flow out of the filling holes after checking, indicating that the grouting effect is expected, stopping grouting;
if the water still exists in the grouting holes, after the grouting of the grouting holes is checked, second round of grouting holes are constructed at the interval positions of the constructed grouting drill holes, and therefore the grouting is carried out until no water exists in the grouting holes, an effective curtain is formed by grouting, and the grouting achieves the expected effect.
The invention has the beneficial effects that: the invention is suitable for the working condition that the periphery of the bottom of the shaft is provided with a roadway, the depth of the shaft is larger, and the aquifer is mainly positioned at the bottom section of the shaft; the synchronous and parallel operation of the upper-section tunneling of the shaft and the lower-section water damage pre-treatment can be realized, the time delay of conventional ground grouting and working surface pre-grouting is reduced, and the shaft construction time is integrally saved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a schematic structural diagram of a method for treating water damage by pre-grouting for shaft construction according to an embodiment of the present invention; .
FIG. 2 is a schematic view of the waterproof curtain according to the embodiment of the present invention.
Description of reference numerals:
1. annularly winding the lane; 2. grouting and drilling; 3. a waterproof curtain.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1-2, a method for treating water damage by pre-grouting in shaft construction comprises the following steps:
measuring and releasing the plane position and the underground position of a shaft: measuring the central point of the shaft on the ground and the position of the shaft bottom of the shaft according to a shaft design drawing;
analyzing geological data of the shaft and determining a section needing grouting treatment at the lower section: collecting, sorting and analyzing the data of the shaft, and determining the position, structure, thickness, etc. of the water-bearing layer to be treated in the lower section of the shaft.
Normal construction of the upper section of the shaft and tunneling construction of the lower section of the grouting ring around the roadway 1: the method comprises the steps of normally starting and tunneling a shaft on the ground, synchronously passing through an original underground roadway underground, constructing a connection roadway to the shaft bottom of the shaft (the roadway is not wasted, other well building methods are used immediately, and the roadway is also constructed in the later period), constructing an annular surrounding roadway 1 at the periphery of the shaft bottom, enabling the distance between the roadway and the outer wall of the shaft to be 6-8m, enabling the height of the roadway to be 4m and the width of the roadway to be 3m, and enabling the underground tunnel drilling machine to work.
Meanwhile, a temporary drainage system is constructed underground or a pipeline is laid to discharge water discharged from the annular surrounding roadway 1 in the middle and later stages of the grouting drill hole 2.
Fourthly, normal construction of the upper section of the shaft and pre-grouting treatment of the lower section of the shaft on the aquifer through upward drilling holes: and (3) continuously and normally tunneling the upper section of the shaft, synchronously grouting the aquifer at the lower section, taking the annular surrounding roadway 1 constructed at the periphery of the shaft as a drilling site, vertically arranging grouting drill holes 2 upwards, enabling the depth of each grouting drill hole 2 to reach the uppermost aquifer, and performing grouting operation through the grouting drill holes 2.
The open holes of the grouting drill holes 2 are positioned in the annular surrounding roadway 1 and are arranged at equal intervals, the interval hole selection construction is adopted, 24 grouting drill holes are uniformly constructed, then the interval supplementary construction of 4 grouting drill holes 2 is carried out, the supplementary grouting holes are checked, if the supplementary grouting holes are checked to have no water, the grouting effect is expected, and the grouting is stopped;
if the water still exists in the grouting hole, after the grouting of the grouting hole is checked, a second round of grouting hole is constructed at the interval position of the constructed grouting drill hole 2, and the grouting is carried out until no water exists in the grouting hole, so that an effective waterproof curtain 3 is formed, and the expected effect is achieved.
Fifthly, finishing the lower-section grouting treatment, and filling and treating the ring-shaped surrounding roadway 1 at the bottom of the well; the shaft is normally tunneled downwards to pass through the lower section of the managed aquifer, and the aquifer is managed in advance, so that water damage accidents can not happen, and the well can be basically driped.
Completing the construction of the shaft: and (4) normally tunneling the shaft downwards to the designed well depth position, completing related supporting work, establishing a connection between the shaft bottom and the underground roadway, and completing shaft construction.
Compared with the conventional ground grouting method, the method saves a large amount of useless drilling wells at the upper section, saves the time and cost for water damage treatment, and reduces the control difficulty and risk of drilling the conventional loose interval; compared with the S-shaped hole type ground pre-grouting provided by the shaft ground pre-grouting multi-working-surface parallel operation process disclosed by the Chinese patent CN103233699A, the extending footage of a shaft sinking is saved, and the cost is reduced; compared with the working face pre-grouting, the method does not need to stop tunneling, namely specially stopping shaft tunneling for water damage treatment; in addition, in the prior art, the space of a working surface in the shaft is small, only one drilling device can be contained, the integral drilling speed is low, and the invention can simultaneously operate a plurality of devices, thereby greatly saving the integral construction time of the shaft.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (5)

1. A pre-grouting treatment method for water damage of shaft well construction is characterized by comprising the following steps:
s1, measuring the central point of the shaft on the ground and the position of the shaft bottom of the shaft;
s2, analyzing geological data of the shaft, and determining a section of the lower section of the shaft needing grouting treatment;
s3, normally constructing the upper section of the shaft, constructing the shaft bottom and circularly surrounding the roadway (1) and constructing a temporary drainage system;
s4, pre-grouting treatment is carried out on the aquifer through the upward construction grouting drill hole (2) at the lower section of the shaft;
s5, after the grouting treatment of the lower section of the shaft is finished, filling treatment is carried out on the annular surrounding roadway (1) at the bottom of the shaft, and the shaft is normally tunneled downwards to pass through the treated aquifer at the lower section;
and S6, normally tunneling the shaft downwards to the designed well depth position, completing the related supporting work, establishing the connection between the shaft bottom and the underground roadway, and completing the shaft construction.
2. The method for treating the water damage caused by the shaft construction according to claim 1, wherein in step S3, a communication roadway is constructed at the bottom of the shaft through an original underground roadway, and a circular surrounding roadway (1) is constructed at the periphery of the bottom of the shaft.
3. The method for treating the water damage caused by shaft well construction according to claim 2, wherein in step S3, the ring-shaped surrounding roadway (1) is 6-8m away from the outer wall of the shaft, and the ring-shaped surrounding roadway (1) has a height of 4m and a width of 3m and can accommodate the operation of a drilling machine of a downhole gallery.
4. The method for treating the water disaster caused by the shaft construction according to the claim 3, wherein in the step S4, a plurality of grouting drill holes (2) are vertically and uniformly distributed upwards by taking a ring-shaped surrounding roadway (1) constructed on the periphery of the shaft as a drilling field, the depth of each grouting drill hole (2) reaches the top aquifer, and grouting operation is carried out through the grouting drill holes (2).
5. The method for treating the water damage in the shaft construction according to claim 4, wherein in step S4, the construction method of the grouting drill hole (2) comprises the following steps: uniformly constructing a plurality of grouting drill holes (2), and then supplementing construction and checking injection supplementing holes in the interval between adjacent grouting drill holes (2);
if the water does not flow out of the filling holes after checking, indicating that the grouting effect is expected, stopping grouting;
if the water still exists in the grouting holes, after the grouting of the grouting holes is checked, second round of grouting holes are constructed at the interval positions of the constructed grouting drill holes (2) so as to carry out grouting until no water exists in the grouting holes, an effective curtain (3) is formed by grouting, and the expected effect is achieved by grouting.
CN202210178346.5A 2022-02-25 2022-02-25 Pre-grouting treatment method for water damage of shaft well construction Active CN114635697B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN202210178346.5A CN114635697B (en) 2022-02-25 2022-02-25 Pre-grouting treatment method for water damage of shaft well construction
AU2023226534A AU2023226534A1 (en) 2022-02-25 2023-02-17 Pre-grouting treatment method for water hazards in shaft construction
PCT/CN2023/076732 WO2023160471A1 (en) 2022-02-25 2023-02-17 Pre-grouting treatment method for water hazards in shaft construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210178346.5A CN114635697B (en) 2022-02-25 2022-02-25 Pre-grouting treatment method for water damage of shaft well construction

Publications (2)

Publication Number Publication Date
CN114635697A true CN114635697A (en) 2022-06-17
CN114635697B CN114635697B (en) 2023-01-24

Family

ID=81948084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210178346.5A Active CN114635697B (en) 2022-02-25 2022-02-25 Pre-grouting treatment method for water damage of shaft well construction

Country Status (3)

Country Link
CN (1) CN114635697B (en)
AU (1) AU2023226534A1 (en)
WO (1) WO2023160471A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030727A (en) * 2022-06-20 2022-09-09 长沙矿山研究院有限责任公司 Method for treating harm of local water spraying in well shaft with installed equipment
WO2023160471A1 (en) * 2022-02-25 2023-08-31 中国矿业大学 Pre-grouting treatment method for water hazards in shaft construction

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114320303A (en) * 2021-12-09 2022-04-12 中国铁建大桥工程局集团有限公司 Method for excavating vertical shaft flood discharge tunnel body support

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4458945A (en) * 1981-10-01 1984-07-10 Ayler Maynard F Oil recovery mining method and apparatus
CN102518470A (en) * 2011-12-27 2012-06-27 陕西彬长矿业集团有限公司 Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN105134125A (en) * 2015-08-26 2015-12-09 北京中煤矿山工程有限公司 Construction process for blocking bottom end of annular space behind gas vertical well wall
CN105545330A (en) * 2016-02-26 2016-05-04 河北钢铁集团矿业有限公司 Water prevention and control process in construction of metallurgical underground mining ore pass fragmenting system
CN109854249A (en) * 2019-03-04 2019-06-07 中煤第五建设有限公司 It is a kind of for extra deep shaft formation pre processing around the lane Jing Huan method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5842518A (en) * 1997-10-14 1998-12-01 Soybel; Joshua Richard Method for drilling a well in unconsolidated and/or abnormally pressured formations
CN109026010B (en) * 2018-08-13 2019-10-01 中煤能源研究院有限责任公司 A kind of mine seepage well slip casting type sinking shaft construction method
CN111365002B (en) * 2020-03-30 2021-07-30 北京中煤矿山工程有限公司 Ground pre-grouting method for small-section high wellbore in complex stratum
CN112746849B (en) * 2020-12-11 2022-02-18 中国矿业大学 Shaft water-carrying digging and building method
CN114635697B (en) * 2022-02-25 2023-01-24 中国矿业大学 Pre-grouting treatment method for water damage of shaft well construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4458945A (en) * 1981-10-01 1984-07-10 Ayler Maynard F Oil recovery mining method and apparatus
CN102518470A (en) * 2011-12-27 2012-06-27 陕西彬长矿业集团有限公司 Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN105134125A (en) * 2015-08-26 2015-12-09 北京中煤矿山工程有限公司 Construction process for blocking bottom end of annular space behind gas vertical well wall
CN105545330A (en) * 2016-02-26 2016-05-04 河北钢铁集团矿业有限公司 Water prevention and control process in construction of metallurgical underground mining ore pass fragmenting system
CN109854249A (en) * 2019-03-04 2019-06-07 中煤第五建设有限公司 It is a kind of for extra deep shaft formation pre processing around the lane Jing Huan method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
薛建坤等: "环状隔离体技术在塔然高勒煤矿主井冻结孔涌水封堵中的应用*", 《现代矿业》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2023160471A1 (en) * 2022-02-25 2023-08-31 中国矿业大学 Pre-grouting treatment method for water hazards in shaft construction
CN115030727A (en) * 2022-06-20 2022-09-09 长沙矿山研究院有限责任公司 Method for treating harm of local water spraying in well shaft with installed equipment

Also Published As

Publication number Publication date
AU2023226534A1 (en) 2024-05-09
CN114635697B (en) 2023-01-24
WO2023160471A1 (en) 2023-08-31

Similar Documents

Publication Publication Date Title
CN114635697B (en) Pre-grouting treatment method for water damage of shaft well construction
CN103924975B (en) A kind of for the water-retaining method in coal mining process
CN103835648B (en) One improves rock stratum performance mine shaft rising boring technique by surface grout injection
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN108825264A (en) A kind of curtain-grouting method in the closely horizontal burnt rock water-bearing layer of shallow embedding
CN103643918A (en) Method for searching for and preventing mine water seepage of Ordovician limestone mine field
CN113404534B (en) Method for preventing rock burst by staged fracturing of L-shaped ground horizontal well
CN109611146B (en) Separation layer water drainage grouting method
CN114837663B (en) Construction method for improving recovery rate of fault waterproof coal pillar through ground pre-grouting
CN112012785B (en) Method for extracting pressure-relief gas by utilizing L-shaped drilling in overburden rock isolation grouting filling process
CN105804754A (en) Coal uncovering method for mining shaft with coal seam as main water-bearing layer
CN102926392A (en) Foundation pit dewatering system and construction method thereof
CN110067597A (en) A kind of mine angle of depression negative pressure visits the method for putting old dead zone ponding
CN108678753A (en) Reverse-slope tunnel construction method
CN110778317A (en) Construction method for ground grouting filling drilling structure in caving zone in mining process
CN111794259B (en) Method for preventing underground diaphragm wall from collapsing groove of neighboring existing building of high underground water level area
CN108798625B (en) Mine and mine construction method
CN113107589B (en) Advanced pre-drainage method for coal seam roof aquifer ground
CN103291307B (en) A kind of rich water rockhole Dewatering by leading level method
CN115045688A (en) Method for treating gushing water of high-buried-depth tunnel by adopting blocking-before-draining method
CN203475453U (en) Deeply-buried type bearing platform curtain structure of bridge
CN114687796A (en) System for comprehensively treating roof old air water
CN113323722A (en) Water burst treatment method for extra-long tunnel
CN103711136B (en) The construction technology of bridge deep embeded type cushion cap curtain structure
CN111894671B (en) Ground water pumping hole pumping and draining method aiming at working face top plate separation layer water damage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant