AU2014289638B2 - Loading system and method for loading a freight car with bulk material - Google Patents

Loading system and method for loading a freight car with bulk material Download PDF

Info

Publication number
AU2014289638B2
AU2014289638B2 AU2014289638A AU2014289638A AU2014289638B2 AU 2014289638 B2 AU2014289638 B2 AU 2014289638B2 AU 2014289638 A AU2014289638 A AU 2014289638A AU 2014289638 A AU2014289638 A AU 2014289638A AU 2014289638 B2 AU2014289638 B2 AU 2014289638B2
Authority
AU
Australia
Prior art keywords
freight car
outlet opening
bulk material
loading
total weight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
AU2014289638A
Other versions
AU2014289638A1 (en
Inventor
Peter Groll
Ralph Muller
Viktor RAIS
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sandvik Rock Processing Australia Pty Ltd
Original Assignee
Sandvik Rock Processing Australia Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sandvik Rock Processing Australia Pty Ltd filed Critical Sandvik Rock Processing Australia Pty Ltd
Publication of AU2014289638A1 publication Critical patent/AU2014289638A1/en
Assigned to SCHENCK PROCESS EUROPE GMBH reassignment SCHENCK PROCESS EUROPE GMBH Alteration of Name(s) of Applicant(s) under S113 Assignors: SCHENCK PROCESS GMBH
Application granted granted Critical
Publication of AU2014289638B2 publication Critical patent/AU2014289638B2/en
Assigned to SCHENCK PROCESS EUROPE GMBH reassignment SCHENCK PROCESS EUROPE GMBH Request for Assignment Assignors: SCHENCK PROCESS EUROPE GMBH
Assigned to SCHENCK PROCESS AUSTRALIA PTY LIMITED reassignment SCHENCK PROCESS AUSTRALIA PTY LIMITED Request for Assignment Assignors: SCHENCK PROCESS EUROPE GMBH
Assigned to SANDVIK ROCK PROCESSING AUSTRALIA PTY LIMITED reassignment SANDVIK ROCK PROCESSING AUSTRALIA PTY LIMITED Request to Amend Deed and Register Assignors: SCHENCK PROCESS AUSTRALIA PTY LIMITED
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01GWEIGHING
    • G01G19/00Weighing apparatus or methods adapted for special purposes not provided for in the preceding groups
    • G01G19/02Weighing apparatus or methods adapted for special purposes not provided for in the preceding groups for weighing wheeled or rolling bodies, e.g. vehicles
    • G01G19/04Weighing apparatus or methods adapted for special purposes not provided for in the preceding groups for weighing wheeled or rolling bodies, e.g. vehicles for weighing railway vehicles

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Loading Or Unloading Of Vehicles (AREA)

Abstract

The invention relates to a loading system for loading at least one freight car (1) of a train with bulk material, comprising a closable outlet opening (51) for metering the bulk material, which outlet opening is arranged on a dispensing device (5) of a bulk material reservoir, wherein the freight car (5) can be moved under the outlet opening (51) on rails (6) and at least one measuring device (2) having an evaluating device (3) is arranged in order to detect wheel loads, axle loads, bogie loads, and/or the total weight of the freight car (1). According to the invention, the measuring device (2) comprises, per rail (6), at least two measuring segments (21, 22, 21a, 22a) arranged one after the other in a direction of travel of the train, wherein at least one of the measuring segments (21, 21a) lies below the outlet opening (51) or in the action region of the bulk material falling through the outlet opening (51).

Description

2014289638 23 Dec 2015
Loading System and Method for Loading a Freight Car with Bulk Material Field of the Invention
The present invention concerns a loading system for loading freight cars of a train with bulk material and a method for loading freight cars of a train with bulk material.
Background of the Invention
Loading systems for loading vehicles, and specifically cars of freight trains, with bulk material exist. Typically, the train with the freight cars travels below the outlet opening of a bulk material container or below the outlet opening of a dispensing device or a loading chute. There, the flap or slide for opening or closing the outlet opening is opened by the operating personnel, and the bulk material falls into the cargo space of the freight car due to gravity. During the loading process, the permissible total weight of a freight car or the permissible axle load should not be exceeded on the one hand, but on the other hand the load capacity of the freight car should be fully utilized. Nonetheless, freight cars often are unevenly loaded or fall below or above the permissible total weight.
An arrangement of sensors for determining the forces exerted by an object on a rail is disclosed in EP 1 607 726 B1, wherein the sensors form a measurement zone from which two virtual subsections or measurement subsections can in turn be constructed by means of an analysis device. In this design, the signals of the virtual measurement subsections are combined with the aid of the analysis device in such a manner that the force exerted by the object moving on the rail can be represented.
In addition, a loading system for freight cars is disclosed in EP 0 367 570 A2 in which a weighing device for the empty freight cars is provided ahead of a first loading device, and a weighing device for the partially loaded freight cars is provided after the first loading device. After a partially loaded freight car has been weighed, a computing unit determines the difference between the empty and partially loaded freight car, and then, -1 - 2014289638 23 Dec 2015 based on a stored control value, determines the bulk material quantity that must still be added for optimal filling of the freight car. Next, using this information, the bulk material quantity that is lacking is additionally dispensed through a weighing hopper and a second loading device.
Because of the infrastructure required for this loading system, the system is correspondingly resource-intensive, and also requires that the loading process must be carried out in two stages. Consequently, a desirable outcome of the present invention is to improve a loading system for bulk material. A desirable outcome of the loading system according to the invention is to optimally utilize the capacity of each individual freight car, and to reduce the time of the loading process to a minimum.
The above discussion of background art is included to explain the context of the present invention. It is not to be taken as an admission that any of the documents or other material referred to was published, known or part of the common general knowledge in Australia at the priority date of any one of the claims of this specification.
Summary of the Invention
Accordingly, in one aspect, the present invention provides a loading system for loading at least one freight car of a train with bulk material, - having, located at a dispensing device of a bulk material reservoir, a closable outlet opening for dispensing the bulk material, - wherein the freight car can be moved on rails below the outlet opening, and - in order to determine wheel loads, axle loads, truck loads, and/or the total weight of the freight car, at least one measurement device having an analysis device is provided, - the measurement device includes at least two measuring sections arranged one behind the other in the train’s direction of travel for each rail, - wherein at least one of the measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening. -2- 2014289638 23 Dec 2015
In another aspect, the present invention provides method for loading at least one freight car of a train with bulk material, wherein the bulk material is delivered to the freight car from a bulk material reservoir through a closable outlet opening, having the steps: - moving the freight car into the region of a measurement device having an analysis device and at least two measuring sections arranged one behind the other in the train’s direction of travel, wherein at least one of the measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening, - analyzing the output signals of the measuring sections in order to determine the exerted wheel loads, axle loads, truck loads, or the total weight of the freight car at least at one position x1 or at least at one time t1 of a loading process, - determining an actual value of the wheel load, axle load, truck load, or total weight of the freight car at the position x1 or at the time t1, - comparing a target value of the wheel load, axle load, truck load, or total weight of the freight car with the actual value determined, - displaying or outputting a signal for adjustment of the outlet opening as a function of the target/actual comparison.
Embodiments of the invention provide a loading system for optimized loading of at least one freight car of a train with bulk material. The bulk material is taken from a dispensing device of a bulk material reservoir, preferably a bulk material container or hopper, that has at its outlet a closable and adjustable outlet opening for dispensing the bulk material. Typically, a flap or slide that can be operated manually by operating personnel or by means of an electric actuator is provided for closing and adjusting the outlet opening. Located below the outlet opening are rails on which the freight car can be moved so that the bulk material falling from the outlet opening arrives in the loading opening of the freight car. To determine wheel loads, axle loads, or truck loads, and/or the total weight of the freight car, at least one measurement device having an analysis device is provided, which includes at least two measuring sections arranged one behind -3- 2014289638 23 Dec 2015 the other in the train’s direction of travel for each rail. At least one of these measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening. In advantageous fashion, the measuring sections have a defined distance from one another. To achieve an optimal loading process, at the end of which the actual total weight of the freight car corresponds to the desired values or the maximum permissible values, it is unimportant in the loading system according to the invention whether the freight car travels at a uniform speed during the loading process, whether it temporarily comes to a stop during the loading process, or even whether it rolls back in the opposite direction. These influences can be sensed by means of the measuring sections and processed by the analysis unit. A wide variety of design embodiments can be used for the measuring sections here. Firstly, it is possible to use classical railroad track scales or weighbridges that comprise a platform supported on weight sensors and to which the rails are in turn fastened. For precise sensing of the force acting on the railroad track scale and to avoid force shunting, rail breaks are typically provided before and after the measuring section defined by the railroad track scale in this design. In this context, weight sensors are fundamentally understood to mean all sensors, force transducers, and pressure transducers in which an analysis of the electrical (voltage) signals permits determination of the force acting on the sensor. For determining compressive, tensile, and/or shear forces, different requirements must be placed on the type and installation of the weight sensors depending on the direction of force.
Accordingly, an arrangement of multiple weighing sleepers in combination with one rail break each or with one transverse force sensor each to define the beginning and end of a measuring section, such as are described in EP1121573B1, to which reference is made here, are also possible as a measurement device or measuring section. In contrast to the implementation of the measuring section using weighing sleepers, in which the sensors are located underneath the rail or in the sleeper body, measuring sections are also possible in which the sensors are located directly on the rail or in the rail web. - 4 - 2014289638 23 Dec 2015
Furthermore, weighbeams, weighbeams in rail form, and special weighbeams or measuring rails, such as are disclosed in WO2012045422A1, to which reference is likewise made here, also come into consideration as another embodiment for a measuring section.
The enumeration of possible embodiments is not exhaustive, however. Nonetheless, what is important for achieving an optimal loading process is that the measuring sections, and thus the output signals received from the measuring sections, can be analyzed independently of one another. In this way an accurate determination of the loads of the freight car at the relevant position and an accurate assignment of the detected loads to the individual wheels or axles of the freight car can take place. The idea behind this is to determine the present loading state at each position of the freight car to be loaded - whether it is measured directly by means of a “virtual measuring section that travels with the vehicle” or is predicted/interpolated/extrapolated from individual measuring sections. A curve of position (x-axis) and loading (y-axis) is produced in this way.
One advantageous embodiment of the loading system according to the invention additionally provides that the at least two measuring sections are subsections of a virtual measuring section. For these measuring sections, only embodiments in which the beginning and end of the measuring section or subsections are defined by sensors come into consideration. In this context, the arrangement of the sensors in the virtual measuring section permits a simulation of multiple measuring sections separated from one another, and consequently an analysis of the rail section located between each pair of sensors without effects from force shunts / distorting influences from loads of the wheels of adjacent freight cars.
Based on the premise that information is stored in the analysis unit about every individual freight car of a train regarding its freight car type, truck spacing and axle spacing, and also its tare weight and permissible total weight, a comparison between -5- 2014289638 23 Dec 2015 the applicable target value and the actual value determined at the relevant position can be created using the actual values obtained with the aid of the output signals from the sensors of the measuring section for the wheel load, axle load, truck load, or total weight of a freight car at the positions in the loading system defined by the measuring sections. When the target value and actual value for the total weight are compared, it becomes clear to a possible operator of the outlet opening whether the outlet opening must be opened because the current volume flow is insufficient to achieve an optimal loading, or whether the reverse is true. This information can be made clear to the operator by a comparison of the target and actual values or else through simple visual or audible signals.
One advantageous embodiment of the loading system according to the invention provides for the first measuring section of the two measuring sections to be located ahead of the region of action of the bulk material falling through the outlet opening. The tare weight of the freight car can be ascertained therewith. If the tare weight should be greater than the stored, theoretical tare weight on account of deposit build-ups or the like, this circumstance can be taken into account during the loading process.
According to another embodiment of the loading system, an additional measuring section for the measurement device can be located after the region of action of the bulk material falling through the outlet opening. This ensures that the total weight can be precisely determined after the conclusion of the loading process.
An enhancement of the loading system according to the invention provides that a control unit for controlling or adjusting the closable outlet opening is additionally arranged. Accordingly, the output signals of the analysis device serve as input signals for the control unit. By means of the control unit, therefore, controlled variables are derived as a function of the target/actual comparison for the loading, and the control mechanism of the flap or the slide is set in motion to open or close the outlet opening. - 6 - 2014289638 23 Dec 2015
If different car types are used in one train, it is also advantageous for a device for detecting and identifying railroad car types to be located ahead of the measuring sections in the loading system. Included among the systems that can be used here are railroad car identification systems (so-called tag readers), light barriers, cameras, axle counting systems, and a railroad track scale by which means the axle spacings of a freight car can be determined in addition to the tare weight.
In order to attain the aforementioned object, a method for optimized loading of at least one freight car of a train with bulk material is also provided, wherein the bulk material is delivered to the freight car from a bulk material reservoir through a closable outlet opening. In this method, the freight car is first moved into the region of a measurement device that comprises an analysis device and at least two measuring sections arranged one behind the other in the train’s direction of travel. The measuring sections of the measurement device are arranged here such that at least one of these measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening.
Then, the analysis of the output signals of the measuring sections is carried out by means of the analysis device in order to determine the exerted wheel loads, axle loads, truck loads, or the total weight of a freight car, during a loading process. Next, an actual value of the wheel load, axle load, truck load, or total weight of the freight car is determined at least at one position x1 of the measurement device or at least at one time t1 of the loading process. This process can be repeated at any desired positions or at any desired times. By means of a subsequent comparison of a target value of the wheel load, axle load, truck load, or total weight of the freight car with the actual value determined, it is then possible to ascertain whether the loading process must be modified or whether it can be continued with the given size of the outlet opening. Lastly, the display or output of a signal for adjustment of the outlet opening takes place as a function of the target/actual comparison. With the display, a possible operator of the outlet opening is thus given the opportunity during the loading process to influence the process currently taking place. -7- 2014289638 23 Dec 2015
Advantageously, however, the adjustment of the outlet opening is controlled automatically as a function of the target/actual comparison of the wheel load, axle load, truck load, or total freight car weight. Closed-loop control of the loading process is made possible in this way.
An enhancement of the method according to the invention for optimized loading of a freight car with bulk material additionally provides that a projection or a prediction of a total weight to be expected and/or of a mass distribution to be expected in the freight car for the end of the loading process can be determined at least at one arbitrary position x1 of the freight car on the measurement device or at least at one arbitrary time t1 of the loading process, and can be displayed or output.
The following substantial advantages over prior art systems are among those achieved with the loading system according to the invention and the method according to the invention: By means of the actual values determined of the loads exerted on the measurement device, a modification of the size of the outlet opening, and hence a modification at the material being loaded, can be undertaken even while the loading process is taking place in order to achieve an optimum total weight of the freight car being loaded. The loading method and the loading process can thus be optimized. The invention can even be employed in the case of fluctuating bulk material densities, or for different bulk materials in the same loading system, with no need to make any adjustment to the method or the device.
Brief Description of the Figures
The invention is described in detail below on the basis of exemplary embodiments.
Fig. 1 accordingly shows a schematic representation of a loading system according to the invention -8- 2014289638 23 Dec 2015
Fig. 2 shows another loading system according to the invention with modified measuring sections, likewise in a schematic representation
Fig. 3 shows a line chart to illustrate a loading process in which a curve of the actual value of the total weight is compared to an optimum curve of the total weight of a freight car.
Detailed Description
The loading system according to the invention shown schematically in Fig. 1 comprises a dispensing device 5 of a reservoir of bulk material, for example coal or iron ore, by which means the bulk material can be conveyed continuously into open freight cars 1 of a train. For the purpose of illustration, however, only two freight cars 1 of a train, without the associated locomotive, are shown in Fig. 1. The direction of travel of the train or of the freight cars 1 is indicated by an arrow at the level of the cars. Customary freight cars for transporting bulk material are open, unroofed freight cars. Accordingly, loading or filling with bulk material preferably takes place from above. The freight cars 1 shown have running gears with four axles 11, 12, 13, 14, wherein two axles 11, 12 are located on a front truck and two axles 13, 14 are located on a rear truck in each case. The number of axles or trucks of a freight car is of no consequence for the invention, however, since all wheels, axles, and trucks can be taken into account.
The freight cars 1 can travel on rails 6 into the region of the dispensing device 5. Oftentimes the bulk material is stored in a bulk material container or hopper that has a loading chute at its outlet or lower end. The bulk material container is customarily located on a platform or substructure (not shown), which is suitable for the passage of a train on account of its clear height.
The dispensing device 5, the bulk material container, or the loading chute through which the bulk material falls downward due to gravity, has a closable outlet opening 51 for volumetrically dispensing the bulk material. In order to close the outlet opening 51, a flap or a slide may be provided that can be moved mechanically so that the size of the - 9 - 2014289638 23 Dec 2015 outlet opening 51 is modifiable and adjustable. Accordingly, the closable outlet opening 51 is opened during the loading process for a freight car 1, and is closed upon conclusion of the loading, when a change of freight cars takes place beneath the outlet opening 51.
In the exemplary embodiment shown in Fig. 1, a measurement device 2 is arranged at the height of the rails 6 for sensing the wheel loads, axle loads, truck loads, or the total weight of a freight car 1. Conventional, standard sleepers, to which the rails 6 are attached, are accordingly provided as the support points 7 for the rails 6. For each stretch of track, the measurement device 2 shown includes four measuring sections 23, 22, 21,24 in succession that are arranged a distance y apart from one another. In the present case, the distance between the measuring sections 23, 22, 21, 24 is selected such that it corresponds to the axle spacing of two wheel axles 11, 12 of a truck. The measuring sections 23, 22, 21,24 shown can be composed of standard rails, for example, with prefabricated sensors attached in or to the rail web thereof at the start and at the end of the measuring section. Preferably, sensors are used here that are inserted, in screw or dowel form or in the form of so-called measuring eyes, into a provided bore in the neutral fiber of the rail web, transversely to the longitudinal direction of the rails, and are secured. The measurement signals that result from the loads from individual wheels acting on the measuring sections 23, 22, 21, 24 can be analyzed very exactly without interfering effects from adjacent wheels on the same rail 6. By means of an analysis device 3, the wheel loads, axle loads, truck loads, or the total weight of the freight car 1 are then determined at multiple defined positions on the measurement device 2 from the measurement signals.
If the train is traveling in the specified direction of travel, the wheel axle 11 of the unladen freight car 1 can first be sensed by the measuring section 23. During continued travel in the unladen state, the wheel axle 11 then reaches the measuring section 22, while the wheel axle 12 is simultaneously located on the measuring section 23, etc. -10- 2014289638 23 Dec 2015
This means that the tare weight of the freight car 1 as well as the partially loaded states and the total weight of the freight car 1 after conclusion of the loading process can be determined by means of the measurement device 2, regardless of whether the car is traveling, rolling backward, or standing still during the loading process.
In the present example, a control unit is additionally provided for controlling the closable outlet opening 51. The control unit is connected to the analysis device 3 in such a way that the output signals of the analysis device 3 serve as input signals for the control unit 4.
As is evident from Fig. 3, the signals determined through the measurement device 2 and the analysis device 3 can be represented in graphical form as a curve. The positions a and b of the loading system are plotted on the x-axis 8 of the graph, and the mass of the freight car is plotted in [t] on the y-axis 9. Accordingly, the actual value 101 of the total weight of the freight car 1 is shown at specific positions of the loading system or at a specific point in time of the loading process. In the representation of all values determined for a freight car 1, a steadily rising value for the total weight typically results with an opened outlet opening.
Since a value for the optimal total weight 100 and values for an optimal loading process of each freight car type are likewise stored in the analysis device 3, the difference 102 between the two values can be determined and displayed for each position. From the comparison of the two values, a corresponding signal can therefore be sent to the control unit 4 for each position. Depending on whether the actual value 101 of the total weight at the relevant position is above or below the optimal total weight 100, the quantity of the closable outlet opening 51 is either reduced or increased.
It is evident from Fig. 3, for example, that a deviation of the actual value 101 from the optimal total weight 100 was already present at loading position b, and this deviation continued to the end of the loading process. With the use of a loading system according to the invention in one of the exemplary embodiments, the closable outlet opening 51 -11 - 2014289638 16 Feb 2017
It is evident from Fig. 3, for example, that a deviation of the actual value 101 from the optimal total weight 100 was already present at loading position b, and this deviation continued to the end of the loading process. With the use of a loading system according to the invention in one of the exemplary embodiments, the closable outlet opening 51 would automatically have been operated in the case of such a curve in order to increase the loading quantity as early as at position b.
Fig. 2 shows another embodiment of a loading system according to the invention. In contrast to the first exemplary embodiment from Fig. 1, measuring sections 23a, 22a, 21a, 24a, which make use of weighbridges, are employed here. They include a platform or concrete plate supported on weight sensors, to which the rails 6 are in turn fastened. The use and analysis of the signals obtained through these measuring sections 23a, 22a, 21a, 24a take place in the same way as in the previously described variants, however.
Throughout the description and claims of this specification, the word “comprise” and variations of the word, such as “comprising” and “comprises”, is not intended to exclude other additives, components, integers or steps. -12- 2014289638 23 Dec 2015
List of reference numbers 1 freight car 11, 12, 13, 14 freight car axle 2 measurement device 21, 21a measuring section 22, 22a measuring section 23, 23a measuring section 24, 24a measuring section 3 analysis device 4 control unit 5 dispensing device of a bulk material reservoir 51 closable outlet opening 6 rail 7 support point, sleeper 8 x axis: freight car position on measurement device of loading system 9 y axis: mass in [t] 100 optimal total freight car weight 101 actual value of total freight car weight 102 difference between optimal value and actual value of total freight car weight -13 -

Claims (13)

  1. The claims defining the invention are as follows:
    1. Loading system for loading at least one freight car of a train with bulk material, - having, located at a dispensing device of a bulk material reservoir, a closable outlet opening for dispensing the bulk material, - wherein the freight car can be moved on rails below the outlet opening, and - in order to determine wheel loads, axle loads, truck loads, and/or the total weight of the freight car, at least one measurement device having an analysis device is provided, - the measurement device includes at least two measuring sections arranged one behind the other in the train’s direction of travel for each rail, - wherein at least one of the measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening.
  2. 2. Loading system according to claim 1, wherein the measuring sections can be analyzed independently of one another by the analysis device.
  3. 3. Loading system according to claim 1 or 2, wherein the measuring sections are subsections of a virtual measuring section.
  4. 4. Loading system according to one of the preceding claims, wherein the first of the two measuring sections of the measurement device is located ahead - in the direction of travel - of the region of action of the bulk material falling through the outlet opening.
  5. 5. Loading system according to one of the preceding claims, wherein an additional measuring section for the measurement device is located after the region of action of the bulk material falling through the outlet opening.
  6. 6. Loading system according to one of the preceding claims, wherein a control unit for controlling or adjusting the closable outlet opening is provided.
  7. 7. Loading system according to claim 6, wherein the output signals of the analysis device are provided as input signals for the control unit.
  8. 8. Loading system according to one of the preceding claims, wherein a device for detecting and identifying railroad car types is located ahead of the measuring sections.
  9. 9. Loading system according to claim 8, wherein a railroad car identification system, a light barrier, a camera, an axle counting system, or a railroad track scale by which means the axle spacings of a freight car are determined in addition to the tare weight, is provided for the purpose of detecting railroad car types.
  10. 10. Method for loading at least one freight car of a train with bulk material, wherein the bulk material is delivered to the freight car from a bulk material reservoir through a closable outlet opening, having the steps: - moving the freight car into the region of a measurement device having an analysis device and at least two measuring sections arranged one behind the other in the train’s direction of travel, wherein at least one of the measuring sections is located below the outlet opening or in the region of action of the bulk material falling through the outlet opening, - analyzing the output signals of the measuring sections in order to determine the exerted wheel loads, axle loads, truck loads, or the total weight of the freight car at least at one position x1 or at least at one time t1 of a loading process, - determining an actual value of the wheel load, axle load, truck load, or total weight of the freight car at the position x1 or at the time t1, - comparing a target value of the wheel load, axle load, truck load, or total weight of the freight car with the actual value determined, - displaying or outputting a signal for adjustment of the outlet opening as a function of the target/actual comparison.
  11. 11. Method according to claim 10, wherein the adjustment of the outlet opening is controlled automatically as a function of the target/actual comparison of the wheel load, axle load, truck load, or total freight car weight.
  12. 12. Method according to one of claims 10 or 11, wherein the steps - analyzing the output signals of the measuring sections in order to determine the exerted wheel loads, axle loads, truck loads, or the total weight of the freight car, - determining an actual value of the wheel load, axle load, truck load, or total weight of the freight car, - comparing a target value of the wheel load, axle load, truck load, or total weight of the freight car with the actual value determined, - displaying or outputting a signal for adjustment of the outlet opening as a function of the target/actual comparison, are repeated at as many positions xn as desired or at as many points in time tn as desired of a loading process.
  13. 13. Method according to one of claims 10 to 12, wherein a total weight to be expected and/or a total weight distribution to be expected in the freight car for the end of the loading process is determined at the position x1, xn of the measurement device or at the time t1, tn of the loading process, and is displayed or output.
AU2014289638A 2013-07-11 2014-06-27 Loading system and method for loading a freight car with bulk material Active AU2014289638B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
DE102013011606.6A DE102013011606B4 (en) 2013-07-11 2013-07-11 Loading system and method for loading a wagon with bulk goods
DE102013011606.6 2013-07-11
PCT/EP2014/001768 WO2015003776A1 (en) 2013-07-11 2014-06-27 Loading system and method for loading a freight car with bulk material

Publications (2)

Publication Number Publication Date
AU2014289638A1 AU2014289638A1 (en) 2016-01-21
AU2014289638B2 true AU2014289638B2 (en) 2017-05-25

Family

ID=51136415

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2014289638A Active AU2014289638B2 (en) 2013-07-11 2014-06-27 Loading system and method for loading a freight car with bulk material

Country Status (6)

Country Link
CN (1) CN105264345B (en)
AU (1) AU2014289638B2 (en)
BR (1) BR112015028406B1 (en)
DE (1) DE102013011606B4 (en)
WO (1) WO2015003776A1 (en)
ZA (1) ZA201507883B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2018214111B1 (en) * 2017-05-26 2018-10-18 Der-Chang John Lee atf Ikhthus Trust Train load-out arrangement

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102015207688A1 (en) 2015-04-27 2016-10-27 Siemens Aktiengesellschaft Control method, control device and loading system for the automatic loading of a transport container with bulk material
CN107643117B (en) * 2016-07-22 2021-05-18 Zf 腓德烈斯哈芬股份公司 Loading profile
WO2018209385A1 (en) * 2017-05-17 2018-11-22 Technological Resources Pty. Limited A train loading system
CN107902444A (en) * 2017-12-18 2018-04-13 襄阳航生石化环保设备有限公司 A kind of quantifying and loading device and quantifying and loading method
CN108408435A (en) * 2018-04-27 2018-08-17 朱新平 The system realized and automatically process the super short weight of entrucking is synchronized in railway entrucking process
CA3099175C (en) 2018-06-04 2023-05-23 Indurad Gmbh System for manipulating the load in bulk rail trains and method for operating such a system
CN110118591A (en) * 2019-05-10 2019-08-13 北京沄汇智能科技有限公司 Micro-weighing control method, device, storage medium and computer equipment
CN110081822A (en) * 2019-06-04 2019-08-02 圆通全球集运有限公司 A kind of mobile device of the measurement charging ratio based on laser sensor
DE102019214156A1 (en) * 2019-09-17 2021-03-18 Hüttlin Gmbh Method for dosing a target component

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2150298A (en) * 1983-11-24 1985-06-26 Central Electr Generat Board Method and apparatus for weighing rail wagons
US6075212A (en) * 1998-09-11 2000-06-13 General Chemical Corporation Method of weighing railroad cars without uncoupling them

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT6309B (en) 1900-04-28 1901-12-27 Adolf Munkacs
US4094367A (en) 1977-02-16 1978-06-13 Railweight, Inc. System for single draft weighing of cars coupled in motion
US4401175A (en) 1979-05-21 1983-08-30 Mangood Corporation System for weighing railroad cars in motion during loading
CA1137525A (en) 1979-05-21 1982-12-14 Jack R. Caldicott System for weighing railroad cars in motion during loading
US4445581A (en) 1982-09-07 1984-05-01 Mangood Corporation System for loading railroad cars
US4659274A (en) * 1984-11-13 1987-04-21 Accutrol Incorporated Computer controlled load-out system
US4904154A (en) 1988-11-03 1990-02-27 Kerr-Mcgee Coal Corporation Loading system for railroad cars
DE19848119A1 (en) 1998-10-20 2000-05-25 Pfister Waagen Gmbh Track scale
ATE445829T1 (en) 2004-06-18 2009-10-15 Tamtron Systems Oy METHOD AND DEVICE FOR MEASURING CHARACTERISTICS OF A VEHICLE MOVING ON RAILS
CN201488797U (en) * 2009-12-04 2010-05-26 杜福厚 Sleeper bearing type rail weighbridge structure
DE102010047234B8 (en) 2010-10-04 2015-12-24 Schenck Process Gmbh Weighing module for measuring wheel contact forces
CN102706421A (en) * 2012-06-04 2012-10-03 杭州钱江称重技术有限公司 High-precision intelligent foundation-pit-free rail weighing device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2150298A (en) * 1983-11-24 1985-06-26 Central Electr Generat Board Method and apparatus for weighing rail wagons
US6075212A (en) * 1998-09-11 2000-06-13 General Chemical Corporation Method of weighing railroad cars without uncoupling them

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2018214111B1 (en) * 2017-05-26 2018-10-18 Der-Chang John Lee atf Ikhthus Trust Train load-out arrangement
WO2018213869A1 (en) * 2017-05-26 2018-11-29 Der-Chang John Lee atf Ikhthus Trust Train load-out arrangement

Also Published As

Publication number Publication date
ZA201507883B (en) 2019-11-27
BR112015028406A2 (en) 2017-07-25
WO2015003776A1 (en) 2015-01-15
BR112015028406B1 (en) 2022-02-01
CN105264345B (en) 2018-10-12
AU2014289638A1 (en) 2016-01-21
DE102013011606A1 (en) 2015-01-15
CN105264345A (en) 2016-01-20
DE102013011606B4 (en) 2022-06-23

Similar Documents

Publication Publication Date Title
AU2014289638B2 (en) Loading system and method for loading a freight car with bulk material
CN110817485B (en) Anti-unbalance-loading system and method for throwing type unloading of railway loading station
US4460308A (en) Method for loading coal into railroad cars
CA1111798A (en) Multi-car train loading station
EP2773927B1 (en) Method for weighing a vehicle, and measuring system and measuring arrangement therefor
CN113291867A (en) Railway open wagon rapid constant-volume loading system and method
CN109250532B (en) Bulk material loading method and system based on single feed opening and related device
CN108675011A (en) A kind of entrucking building entrucking metering method and entrucking building
US20200079601A1 (en) Train Load-Out Arrangement
US4445581A (en) System for loading railroad cars
WO2015161995A1 (en) Determination of the mass of a metallic melt
CN204588163U (en) Based on the rapid automobile quantifying and loading system that existing silo is transformed
AU2018426926C1 (en) System for manipulating the load in bulk rail trains and method for operating such a system
RU2615707C2 (en) System and method of weighing couple railway wagons in motion
CN203069253U (en) Front static rail weighbridges for double-dumping car dumper
CN209296120U (en) Multi-channel quantitative entrucking track scale
CN206142481U (en) Developments track scale secondary quick loading system of compensation formula ration that weighs
FI111158B (en) A method for maximizing the loading capacity of single wagons and trains in bulk loading
AU2015342731B2 (en) A train loading system
CN109084874A (en) A kind of molten iron quantitative loading system and molten iron quantitative loading method
EP0019479B1 (en) System for weighing freight cars in motion during loading
US4401175A (en) System for weighing railroad cars in motion during loading
RU2784784C1 (en) Method and device for determining the location of the center of gravity of a loaded railway car
RU2098775C1 (en) Method metering loose cargoes while loading cars
CN109405947A (en) Multi-channel quantitative entrucking track scale and its metering method

Legal Events

Date Code Title Description
HB Alteration of name in register

Owner name: SCHENCK PROCESS EUROPE GMBH

Free format text: FORMER NAME(S): SCHENCK PROCESS GMBH

FGA Letters patent sealed or granted (standard patent)
PC Assignment registered

Owner name: SCHENCK PROCESS EUROPE GMBH

Free format text: FORMER OWNER(S): SCHENCK PROCESS EUROPE GMBH

PC Assignment registered

Owner name: SCHENCK PROCESS AUSTRALIA PTY LIMITED

Free format text: FORMER OWNER(S): SCHENCK PROCESS EUROPE GMBH

HB Alteration of name in register

Owner name: SANDVIK ROCK PROCESSING AUSTRALIA PTY LIMITED

Free format text: FORMER NAME(S): SCHENCK PROCESS AUSTRALIA PTY LIMITED