WO2024084771A1 - 管路工事管理システム、管理サーバ、管路工事管理方法及び管路工事管理プログラム - Google Patents
管路工事管理システム、管理サーバ、管路工事管理方法及び管路工事管理プログラム Download PDFInfo
- Publication number
- WO2024084771A1 WO2024084771A1 PCT/JP2023/027660 JP2023027660W WO2024084771A1 WO 2024084771 A1 WO2024084771 A1 WO 2024084771A1 JP 2023027660 W JP2023027660 W JP 2023027660W WO 2024084771 A1 WO2024084771 A1 WO 2024084771A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- construction
- information
- management
- performance
- pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06313—Resource planning in a project environment
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0639—Performance analysis of employees; Performance analysis of enterprise or organisation operations
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Definitions
- the present invention relates to a pipeline construction management system, a management server, a pipeline construction management method, and a pipeline construction management program for managing pipeline construction.
- waterworks are required to record the details of construction work as it progresses.
- the content that needs to be recorded varies depending on the waterworks that commission the work.
- Waterworks are also required to prepare and submit documents in a format specified by each waterworks.
- the shape, dimensions, etc. of the portion of the work that has been completed among the areas where construction is planned are measured and recorded in accordance with specified standards.
- the difference between the recorded measurement values and the design values of the work is recorded (hereinafter referred to as "completed form management").
- a completed form management table of a specified format is created that lists these design values, the measurement values, and the differences between the measurement values and the design values.
- the person in charge would generally hand-record measurements taken at the construction site on a paper management sheet.
- the person in charge would transcribing the measurements recorded on the paper management sheet into a spreadsheet or similar software on a computer in the office, etc., using a keyboard or similar.
- Patent Document 1 proposes that on-site inspection information required for construction management be entered via a mobile device, and the entered information be collected on a server to assist in the creation of a completed form management sheet.
- each stage of construction requires photo management.
- the number of photos that need to be managed during construction is very large.
- photo management takes a lot of time. For example, it took a lot of time for the person in charge to link the management location of the construction site with the photos taken at that location.
- the person in charge would take photos of blackboards with handwritten details of the construction work written on them, along with the on-site construction status. As a result, taking photos for photo management took a lot of time.
- Patent documents 2 and 3 therefore propose creating a blackboard electronically and generating a photographic image with an electronic blackboard.
- Patent Documents 1 to 3 in as-built management or photo management, documents are created that link the construction plan and the actual construction results.
- Pipeline construction projects involve multiple processes. Furthermore, in the pipeline construction projects, multiple documents must be prepared for each of the multiple processes. Therefore, in the pipeline construction projects, many documents must be prepared.
- the object of the present invention is to realize a pipeline construction management system that can efficiently process data on construction plans and data on construction results, and can more efficiently manage construction results.
- the pipeline construction management system is a system for managing pipeline construction.
- the pipeline construction management system has a management server and a performance acquisition terminal capable of communicating with the management server and acquiring data on construction performance corresponding to management items for managing performance in the pipeline construction as performance information.
- the management server has a construction plan information generation unit that links information on the construction plan of the pipeline that is the subject of the pipeline construction to the management items to generate construction plan information, and a construction management information generation unit that links the performance information acquired by the performance acquisition terminal to the construction plan information to generate construction management information (first configuration).
- the management server generates construction plan information in which information about the construction plan is linked to the management items that manage the results.
- the performance acquisition terminal also acquires data on the construction performance corresponding to the management items as performance information.
- the management server links the performance information to the construction plan information to generate construction management information.
- the construction management information generation unit links the construction plan information and the performance information to the management position that is the object of management in the pipeline, and generates the construction management information (second configuration).
- the management server further includes a work information management list generation unit that creates data for a list of performance information acquired during a specified construction period based on the construction management information (third configuration).
- the management server further includes a document creation unit that creates documents in which the performance information is linked to each management location according to a specified format based on the construction management information (fourth configuration).
- the construction plan information includes design values for the earthwork of the pipeline construction.
- the data on the construction performance are actual measurement values corresponding to the design values.
- the construction management information generation unit calculates the difference between the design values and the actual measurement values included in the performance information acquired by the performance acquisition terminal, and links the design values, the actual measurement values, and the difference to the management positions to generate the construction management information (fifth configuration).
- the management item is a photograph.
- the performance acquisition terminal acquires photographed photograph data as performance information.
- the construction management information generation unit links the photographed photograph data by the performance acquisition terminal to the management location and generates the construction management information (sixth configuration).
- the management server further includes an electronic whiteboard creation unit that creates an electronic whiteboard to be added to the photo data based on the construction plan information.
- the construction management information generation unit links the photo data to which the electronic whiteboard has been added to the management location, and generates the construction management information (seventh configuration).
- the management server can easily create an electronic whiteboard to be added to the photo data. Therefore, image data in which the electronic whiteboard has been added to the photo data can be easily created. Therefore, image data to which an electronic whiteboard has been added can be efficiently managed.
- the construction plan information, the performance information, and the construction management information are each linked to the work scope of the pipeline construction work (eighth configuration).
- pipeline construction can be planned and managed for each work area. Therefore, even if a change in the plan occurs, the plan can be easily changed and calculation processing can be performed according to the work area.
- the construction plan information is linked to work schedule information, which is information about the schedule of work in the work scope
- the performance acquisition terminal acquires the construction plan information from the management server, while acquiring performance information that corresponds to the construction plan information and is linked to the work scope and the work schedule information, and then outputs the performance information to the management server, and the management server modifies the construction plan information based on the performance information output from the performance acquisition terminal (ninth configuration).
- the construction plan information can be easily revised by using performance information linked to the work scope.
- the pipeline construction plan can be easily changed according to the work scope.
- the management server manages pipeline construction work.
- the management server has a construction plan information generation unit that generates construction plan information by linking information related to the construction plan of the pipeline that is the subject of the pipeline construction work to management items that manage the results of the pipeline construction work, a communication unit capable of communicating with a performance acquisition terminal that acquires data related to the construction results corresponding to the management items as performance information, and a construction management information generation unit that receives the performance information from the performance acquisition terminal, links the received performance information to the construction plan information, and generates construction management information (tenth configuration).
- the management server generates the construction plan information in which information related to the construction plan is linked to the management items.
- the management server also links the performance information acquired by the performance acquisition terminal to the construction plan information to generate construction management information.
- the construction management information generation unit links the construction plan information and the performance information to the management position that is the object of management in the pipeline, and generates the construction management information (eleventh configuration).
- a document creation unit is further provided that creates documents in which the performance information is linked to each of the management locations based on the construction management information in a predetermined format (twelfth configuration).
- the pipeline construction management method has a track record acquisition terminal and a management server, and controls a pipeline construction management system that manages pipeline construction.
- the pipeline construction management method includes a construction plan information generation step in which the management server links information on the construction plan of the pipeline that is the subject of the pipeline construction to a management item to generate construction plan information, a construction plan information transmission step in which the management server transmits the construction plan information to the track record acquisition terminal, a track record information acquisition step in which the track record acquisition terminal acquires data on the construction track record corresponding to the management item in the pipeline construction as track record information, a track record information reception step in which the management server receives the track record information from the track record acquisition terminal, and a construction management information generation step in which the management server links the track record information received from the track record acquisition terminal to the construction plan information to generate construction management information (13th configuration).
- the management server generates the construction plan information in which information related to the construction plan is linked to the management items.
- the performance acquisition terminal also acquires data on the construction performance corresponding to the management item as performance information.
- the management server links the performance information acquired by the performance acquisition terminal to the construction plan information to generate construction management information.
- the management server links the construction plan information and the performance information to the management position that is the object of management in the pipeline, and generates the construction management information (fourteenth configuration).
- the management server further has a document creation process for creating documents in which the performance information is linked to each management location based on the construction management information, in accordance with a predetermined format (fifteenth configuration).
- a pipeline construction management program has a track record acquisition terminal and a management server, and controls a pipeline construction management system that manages pipeline construction.
- the pipeline construction management program causes the management server to execute a construction plan information generation process that links information about the construction plan of the pipeline that is the subject of the pipeline construction to a management item and generates construction plan information, a construction plan information transmission process that transmits the construction plan information to the track record acquisition terminal, a track record information reception process that receives track record information from the track record acquisition terminal that has acquired track record information including data about construction results corresponding to the management item in the pipeline construction, and a construction management information generation process that links the track record information received from the track record acquisition terminal to the construction plan information and generates construction management information (16th configuration).
- the management server generates the construction plan information in which information related to the construction plan is linked to the management items.
- the management server also links the performance information acquired by the performance acquisition terminal to the construction plan information to generate construction management information.
- the construction management information generation process includes a process in which the management server links the construction plan information and the performance information to a management position that is the subject of management in the pipeline, and generates the construction management information (17th configuration).
- the management server is further made to execute a submission document creation process for creating documents in which the performance information is linked to each management location based on the construction management information in a predetermined format (18th configuration).
- the management server of the pipeline construction management system has a construction plan information generation unit that links information about the construction plan of the pipeline that is the subject of pipeline construction to management items to generate construction plan information, and a construction management information generation unit that links performance information acquired by the performance acquisition terminal to the construction plan information to generate construction management information.
- FIG. 1 is a functional block diagram showing a schematic configuration of a water pipe construction management system according to a first embodiment of the present invention.
- FIG. 2 is a functional block diagram showing a schematic configuration of a management server, a construction planning terminal, and a performance acquisition terminal included in the water pipe construction management system.
- FIG. 3 is a diagram for explaining the width of an excavation trench and the soil covering at a location where a water pipe is to be buried.
- FIG. 4 is a diagram illustrating the type and thickness of the pavement or roadbed of a road.
- FIG. 5 is a diagram for explaining a method for setting the start point and end point of a pipe of a water pipe that is the subject of water pipe construction work.
- FIG. 1 is a functional block diagram showing a schematic configuration of a water pipe construction management system according to a first embodiment of the present invention.
- FIG. 2 is a functional block diagram showing a schematic configuration of a management server, a construction planning terminal, and a performance acquisition terminal included in the water pipe construction
- FIG. 6 is a diagram for explaining a method for setting the management position of a pipeline in water pipe construction work.
- FIG. 7 is a flow diagram showing the process flow of a water pipe construction management method for controlling a water pipe construction management system that manages water pipe construction.
- FIG. 8 is a functional block diagram showing a schematic configuration of a water pipe construction management system according to the second embodiment of the present invention.
- FIG. 9 is a diagram showing a template of a completed form management table, which is an example of construction plan information.
- FIG. 10 is a diagram showing a completed form management table, which is an example of a document to be submitted.
- FIG. 11 is a functional block diagram showing a schematic configuration of a water pipe construction management system according to the third embodiment of the present invention.
- FIG. 12 is a diagram for explaining a method for setting a management position of a pipeline in photograph management.
- FIG. 13 is a diagram showing an example of an electronic whiteboard.
- FIG. 14 is a diagram illustrating an example of a work information management list.
- FIG. 15 is a diagram showing an example of a monitor image of the result acquisition terminal when a photograph is taken.
- FIG. 16 is a diagram showing a monitor image to which an electronic whiteboard has been added.
- FIG. 17 is a functional block diagram showing a schematic configuration of a water pipe construction management system according to the fourth embodiment of the present invention.
- FIG. 18 is a diagram showing a schematic diagram of section map data.
- FIG. 19 is a diagram illustrating the construction plan information.
- FIG. 20 is a diagram showing a schematic diagram of a correction process for construction plan information.
- FIG. 1 is a functional block diagram showing a schematic configuration of a water pipe construction management system (pipe construction management system) 1 according to a first embodiment of the present invention.
- the water pipe construction management system 1 is a system for managing the results of water pipe construction (pipe construction).
- the water pipe construction refers to construction work for burying water pipes, etc. underground.
- the water pipe construction includes not only construction work for burying new water pipes, etc. underground, but also construction work for updating water pipes, etc. buried underground.
- the water pipes, etc. include not only water pipes, but also parts necessary for constructing a pipeline, such as valves.
- the water pipe construction management system 1 has a management server 3, a construction planning terminal 5, and a performance acquisition terminal 7.
- the management server 3 and the construction planning terminal 5 are connected to each other so that they can communicate with each other via a network such as the Internet.
- the management server 3 and the performance acquisition terminal 7 are connected to each other so that they can communicate with each other via a network such as the Internet.
- the management server 3 is a server device that has a database that stores various data for managing water pipe construction work, and provides the function of processing the data.
- the construction planning terminal 5 is a front-end terminal for creating information related to the construction plan for the water pipe pipeline that is the subject of the water pipe construction work.
- the user of the construction planning terminal 5 is the planner U1 in charge of creating the construction plan.
- the construction planning terminal 5 is used by the user, planner U1, to create the construction plan.
- the construction planning terminal 5 can be realized, for example, by a personal computer or a tablet terminal.
- the construction planning terminal 5 accesses the management server 3 by wired or wireless communication, and performs an operation to link information related to the construction plan for the water pipe pipeline that is the subject of the water pipe construction work to a management item that manages the results of the water pipe construction work.
- the result acquisition terminal 7 acquires data on the construction results corresponding to the management items as result information.
- the user of the result acquisition terminal 7 is the on-site person in charge of the water pipe construction U2.
- the result acquisition terminal 7 is used by the user, the on-site person in charge U2, to input the result information.
- the result acquisition terminal 7 can be realized by, for example, a notebook PC, a tablet terminal, or a mobile terminal such as a smartphone. Since the result acquisition terminal 7 is used on-site, it is preferable that it is capable of wireless communication, but wired communication may also be used.
- FIG. 2 is a functional block diagram showing a schematic configuration of the management server 3, construction planning terminal 5, and result acquisition terminal 7 included in the water pipe construction management system 1.
- the management server 3 has a communication unit 31, a memory unit 32, and a control unit 33.
- the communication unit 31 is a network interface for connecting to a wired or wireless network and communicating.
- the memory unit 32 stores the programs executed by the control unit 33 and the data used by the programs. Details of the data stored in the memory unit 32 will be described later.
- the control unit 33 executes various functions in the management server 3 by executing programs. Details of the control unit 33 will be described later.
- the construction planning terminal 5 has a communication function with the management server 3.
- the construction planning terminal 5 can realize various functions by executing various processes such as local programs.
- the construction planning terminal 5 can store local programs and various data used in the programs.
- the construction planning terminal 5 has an operation input unit (not shown) that allows input operations by the user, the planner U1.
- the construction planning terminal 5 executes various processes such as programs based on the input operation contents.
- the construction planning terminal 5 may have a display unit, or may be configured to be able to output display data to another display unit.
- the construction planning terminal 5 also transmits the input operation details to the management server 3. Depending on the operation details, the management server 3 executes various applications.
- the construction planning terminal 5 has CAD software or the like installed as a local program, and can edit information related to the construction plan.
- the construction planning terminal 5 can synchronize the edited information related to the construction plan with the data stored in the memory unit 32 of the management server 3 by communicating with the management server 3 via a network.
- the result obtaining terminal 7 includes a communication unit 71 , a storage unit 72 , a control unit 73 , and a touch panel unit 74 .
- the communication unit 71 is a network interface for connecting to a mobile phone communication network or a wireless network or a wired network based on wireless communication standards, etc., to perform communication.
- the storage unit 72 stores various data including programs executed by the control unit 73 and data used in the programs. Details of the data stored in the storage unit 72 will be described later.
- the control unit 73 executes various functions in the performance acquisition terminal 7 by executing programs.
- the touch panel unit 74 accepts touch input by the user of the result acquisition terminal 7, while displaying various screens to the user.
- the result acquisition terminal 7 executes various processes based on the operation content accepted by the touch panel unit 74.
- the result acquisition terminal 7 also transmits the operation content accepted by the touch panel unit 74 to the management server 3.
- the control unit 33 of the management server 3 has a construction plan information generating unit 51 , an information transmitting unit 54 , a construction management information generating unit 55 , and a submission document creating unit 56 .
- the construction plan information generating unit 51 links information 320 about the construction plan of the water pipe pipeline that is the subject of the water pipe work to management items to generate construction plan information 327.
- the construction plan information generating unit 51 also links the management items to management positions that are the objects to be managed in the pipeline.
- the information 320 relating to the construction plan includes, for example, design information 3201, earthwork information 3202, obstacle information 3203, construction project information 3204, site information 3205, ground information 3206, and process information 3207.
- the design information 3201 is information related to the design of the pipeline.
- the design information 3201 includes information related to the water pipes used in the water pipe construction work, such as the diameter, length, type (straight pipe, irregular pipe, cut pipe, etc.), number, and arrangement.
- the design information 3201 is, for example, information obtained from a pipeline diagram of the water pipe.
- the design information 3201 includes information related to the designed pipeline (hereinafter referred to as the "designed pipeline").
- the design information 3201 is created, for example, based on the operation contents in the construction planning terminal 5.
- the earthwork information 3202 is information about earthwork for water pipe construction. The following is a more specific description with reference to FIG. 3 and FIG. 4.
- FIG. 3 is a diagram for explaining the excavation trench width and earth covering at the location where the water pipe 91 is buried.
- FIG. 4 is a diagram for explaining the type of pavement or roadbed of the road and its thickness.
- the earthwork information 3202 includes the excavation trench width W 1 at the location where the water pipe 91 is buried, the excavation depth H 1 , and the earth covering H 2 for the water pipe 91.
- the earthwork information 3202 also includes the types L1, L2, and L3 of the pavement or roadbed before and after burial, and the thicknesses T1, T2, and T3 for each type.
- the types may indicate the structure of the layer above the roadbed in the structure of the road R.
- type L1 is the surface layer
- type L2 is the upper roadbed
- type L3 is the lower roadbed.
- the earthwork information 3202 also includes standard values of information about the design dimensions of these earthworks.
- the standard value is a value indicating the allowable range of error for the design dimensions.
- the earthwork information 3202 may further include information on the characteristics of the road structure and the retaining portions.
- the obstacle information 3203 includes information on underground obstacles (underground structures such as cross pipes, other underground buried objects, etc.) at the location where the water pipe is to be buried. Note that the obstacle information 3203 may further include information related to at least one of the road structure, soil quality, and groundwater.
- the construction project information 3204 includes information related to the water pipe construction project.
- the construction project information 3204 may include, for example, identification information for identifying the water pipe construction project, the location of the construction, the name of the water pipe construction project, the type of work, a schematic diagram, or an order number, etc.
- the site information 3205 includes information related to site conditions.
- the information related to site conditions includes at least one of the following information: available work time, available personnel, type and number of work machines to be used, whether parallel work can be performed, whether parallel use of work machines can be performed, transportation time for soil or water pipes, etc., whether test excavation is performed, etc.
- Ground information 3206 includes information related to the ground at the location where the water pipe is to be buried. Specifically, ground information 3206 includes information related to the surrounding area and information related to road conditions.
- the above-ground surroundings-related information includes information about the environment near the location where the water pipe construction work will be carried out.
- the information about the environment near the location where the water pipe construction work will be carried out includes information about whether there are any facilities that are regularly used by surrounding residents in the area facing the construction site or in the surrounding areas. Such facilities include homes, stores, parking lots, etc.
- the information about the environment near the location where the water pipe construction work will be carried out includes information about whether the construction site is in the city or in the suburbs.
- the road condition-related information includes traffic information at the location where the water pipe construction work is being carried out, and, if the location where the water pipe construction work is being carried out is a road, information on the width and number of lanes of that road.
- Process information 3207 is information regarding the construction schedule for the target pipeline.
- the management items are items for which the performance of the water pipe construction work is managed.
- the management items include, for example, items that are listed in the submitted documents.
- the construction plan information generating unit 51 links information 320 relating to the construction plan to the management items and the management positions, for example, as described below.
- Figure 5 is a diagram explaining a method for setting the start point P1 and end point P2 of the design pipe TP of the water pipe PL that is the subject of water pipe construction work.
- Figure 6 is a diagram explaining a method for setting the management position of the pipe in water pipe construction work.
- the construction plan information generating unit 51 sets the start point P1 and end point P2 of the design pipe TP of the water pipe PL that is the subject of the water pipe construction work in response to the user's operation on the construction plan terminal 5.
- the construction plan information generating unit 51 sets the management positions A0, ..., A9+10.0 for the design pipeline TP.
- the management positions that are the basic measurement points are assigned an identification number, for example, "A" plus a number.
- Management positions A0, A1, ..., A9, etc. correspond to basic measurement points.
- the predetermined interval M is, for example, 50 m. Therefore, the basic measurement points do not necessarily coincide with the joints between water pipes.
- the additional measurement points set at the singular points are assigned to bypass piping sections, such as overpasses.
- the overpasses are sections where piping is routed around underground obstacles such as cross pipes 92 at locations where the obstacles are present underground.
- the bypass piping sections also include overpasses that route piping around underground obstacles and twisted sections that route piping by bending the pipeline horizontally.
- the additional measurement points set at the singular points include locations where the earthwork cross section changes. Even if the end point is located at a position other than the basic measurement point, actual measurements at the end point are required.
- the additional measurement points are identified by their planimetric distance from the base measurement point. For this reason, the management positions that are the additional measurement points are assigned identification numbers, for example, "A,” "the number of the reference base measurement point,” and "the planimetric distance from the base measurement point.”
- management position A5+20.0 is an additional measurement point at the bridging section.
- management position A9+10.0 is an additional measurement point at the end point. Additional measurement points can be set manually or automatically, separate from the base measurement points.
- each management location is linked to an earthwork section B1 to B4.
- an earthwork section means a section that has the same earthwork information. In other words, the same earthwork information is applied within the same earthwork section.
- the construction plan information generating unit 51 generates construction plan information 327 by linking information 320 related to the construction plan of the water pipe pipeline that is the subject of the water pipe construction work to the management items and the management location.
- the management items and the management location may be linked to identification information for identifying the water pipe construction work case or the construction name of the water pipe construction work.
- the construction plan information 327 may include identification information for identifying the water pipe construction work case or the construction name of the water pipe construction work.
- the construction plan information generating unit 51 stores the created construction plan information 327 in the storage unit 32.
- the information transmission unit 54 transmits the construction plan information 327 generated by the construction plan information generation unit 51 to the performance acquisition terminal 7.
- the information transmission unit 54 may also transmit the construction management information 328 generated by the construction management information generation unit 55 (described later) to the performance acquisition terminal 7.
- the construction management information generating unit 55 links the performance information 722 acquired by the performance acquisition terminal 7 to the construction plan information 327 to generate the construction management information 328.
- the construction management information generating unit 55 stores the generated construction management information 328 in the storage unit 32.
- the submission document creation unit 56 creates documents in a predetermined format in which the performance information 722 is linked to each management location based on the construction management information 328 generated by the construction management information generation unit 55.
- the submission document creation unit 56 stores the created submission document data 329 in the storage unit 32.
- the water pipe construction management system 1 is a system for managing water pipe construction.
- the water pipe construction management system 1 has a management server 3 and a performance acquisition terminal 7 that can communicate with the management server 3 and acquires data on construction performance corresponding to management items for managing performance in water pipe construction as performance information 722.
- the management server 3 has a construction plan information generating unit 51 that links information 320 about the construction plan of the designed pipeline TP of the water pipe PL that is the target of the water pipe construction work to the management items to generate construction plan information 327, and a construction management information generating unit 55 that links the performance information 722 acquired by the performance acquisition terminal 7 to the construction plan information 327 to generate construction management information 328.
- the management server 3 generates construction plan information 327 that links the information 320 related to the construction plan to the management items.
- the performance acquisition terminal 7 also acquires data on the construction performance corresponding to the management item as performance information 722.
- the performance information 722 may include identification information for identifying the water pipe construction project or the construction name of the water pipe construction project.
- the management server 3 links the performance information 722 to the construction plan information 327 to generate construction management information 328.
- the management server 3 may link the performance information 722 and the construction plan information 327 via identification information for identifying the water pipe construction project or the construction name of the water pipe construction project.
- the construction management information 328 may also include identification information for identifying the water pipe construction project or the construction name of the water pipe construction project.
- the construction management information generating unit 55 of the management server 3 links the construction plan information 327 and the performance information 722 acquired by the performance acquisition terminal 7 to the management position that is the object of management in the pipeline, and generates the construction management information 328.
- the management server 3 further includes a submission document creation unit 56 that creates documents in a predetermined format in which the performance information 722 is linked to each of the management locations based on the construction management information 328.
- FIG. 7 is a flow diagram showing the flow of processing of a water pipe construction management method (pipe construction management method) for controlling the water pipe construction management system 1 that manages water pipe construction.
- the management server 3 links information 320 related to the construction plan for the water pipe pipeline that is the subject of the water pipe work to the management items, and generates construction plan information 327 (construction plan information generation process) (step S11).
- the management server 3 may execute step S11 in response to a request from the construction plan terminal 5.
- the management server 3 transmits the construction plan information 327 to the performance acquisition terminal 7 (construction plan information transmission process) (step S12).
- the performance acquisition terminal 7 acquires data on the construction performance corresponding to the management item in the water pipe construction as performance information 722 (performance information acquisition process) (step S21).
- the management server 3 receives the performance information 722 from the performance acquisition terminal 7 (performance information receiving process) (step S13).
- the performance information 722 is associated with the corresponding management item and transmitted from the performance acquisition terminal 7 to the management server 3.
- the management server 3 links the performance information 722 received from the performance acquisition terminal 7 to the construction plan information 327 to generate construction management information 328 (construction management information generation process) (step S14).
- the management server 3 creates documents in a predetermined format for each management location based on the construction management information 328 (document creation process) (step S15).
- the above water pipe construction management method allows efficient data processing of construction plan data and construction performance data, making it possible to more efficiently manage construction performance. It also allows efficient organization of the vast amount of data in the construction plan information 327 and performance information 722, and makes it easy to compare the construction plan information 327 and performance information 722 at each management location. It also reduces the workload involved in creating documents for each management location based on the construction management information 328.
- the water pipe construction management program may be a program that causes the management server 3 constituting a part of the water pipe construction management system 1 to execute steps S11 to S15 shown in Fig. 7. By executing this program by the management server 3, the water pipe construction management system 1 and the water pipe construction management method according to the present embodiment can be realized.
- the water pipe construction business support system control program has a performance acquisition terminal 7 and a management server 3, and is a program for controlling the water pipe construction management system 1 that manages water pipe construction.
- the water pipe construction management program causes the management server 3 to execute a construction plan information generation process that links information 320 related to the construction plan of the water pipe pipeline that is the subject of the water pipe construction to a management item to generate construction plan information 327, a construction plan information transmission process that transmits the construction plan information 327 to the track record acquisition terminal 7, a performance information reception process that receives performance information 722 from the track record acquisition terminal 7 that has acquired performance information 722 including data related to the construction results corresponding to the management item in the water pipe construction, and a construction management information generation process that links the performance information 722 received from the track record acquisition terminal 7 to the construction plan information 327 to generate construction management information 328.
- the construction management information generation process includes a process in which the management server 3 links the construction plan information 327 and performance information 722 to the management position that is the object of management in the pipeline, and generates the construction management information 328.
- the water pipe construction management program also causes the management server 3 to execute a submission document creation process that creates documents in a predetermined format for each management location based on the construction management information 328.
- the above water pipe construction management program allows efficient data processing of construction plan data and construction performance data, making it possible to more efficiently manage construction performance. It also allows efficient organization of the vast amount of data in the construction plan information 327 and performance information 722, and makes it easy to compare the construction plan information 327 and performance information 722 at each management location. It also reduces the workload involved in creating documents for each management location based on the construction management information 328.
- FIG. 8 is a functional block diagram showing a schematic configuration of a water pipe construction management system 11 according to the second embodiment of the present invention.
- the water pipe construction management system 11 according to the second embodiment is a system that performs as-built management.
- the water pipe construction management system 11 differs from the water pipe construction management system 1 according to the first embodiment in that it manages the management items required for as-built management.
- performance information which is data on construction performance corresponding to the management items, includes, for example, actual measured values relative to the design values of the pipeline.
- the performance acquisition terminal 7 acquires actual measured value information 723 as the performance information.
- the storage unit 72 of the result acquisition terminal 7 stores actual value information 723 that constitutes a part of the result information.
- the actual value information 723 is, for example, information on actual values measured on-site, and is input to the result acquisition terminal 7 by the touch panel unit 74.
- the result acquisition terminal 7 transmits the actual value information 723 to the management server 3.
- the storage unit 32 of the management server 3 stores construction plan information 627 , construction management information 628 , and submitted document data 629 .
- the control unit 33 of the management server 3 also has a construction plan information generation unit 151, an information transmission unit 154, a construction management information generation unit 155, and a submission document creation unit 156.
- the construction plan information generating unit 151 links information 320 about the construction plan of the water pipe pipeline that is the subject of the water pipe construction work to the management items and management positions required in the completed form management, and generates construction plan information 627.
- the management items include various dimensions in water pipe construction.
- the management items may be set for each type of work. Examples of types of work in water pipe construction include piping earthwork, pipe installation work, roadbed work, and paving work. The type of work is set manually or automatically for each management position.
- the management items include, for example, the excavation trench width and excavation depth at the location where the water pipe is buried.
- the management items include the type of pavement or roadbed and its thickness.
- the management positions for completed form management are as described in embodiment 1. That is, the management positions for completed form management include basic measurement points set at predetermined intervals, bypass piping sections such as overpasses, points where the earthwork cross section changes, and additional measurement points set at singular points such as the end point P2.
- the construction plan information 627 generated by the construction plan information generation unit 151 is linked to identification information for identifying the water pipe construction project or the construction name of the water pipe construction project.
- the construction plan information 627 includes design values related to the earthwork of the water pipe construction project.
- FIG. 9 is a diagram showing a template of a completed form management table, which is an example of the construction plan information 627.
- the construction plan information 627 includes a template of a completed form management table as shown in FIG. 9.
- the completed form management table shown in FIG. 9 is a form for which the type of work is piping earthwork.
- the list TBL1 included in the completed form management table includes the excavation trench width W1 and excavation depth H1 as the management items.
- the list TBL1 also lists the design values of the excavation trench width W1 and excavation depth H1 linked to the management position No. A0, A1, A2, etc.
- the top of the list TBL1 also lists the lower limit standard value of the excavation trench width W1 -30 mm and the upper limit standard value of the excavation depth H1 +100 mm and the lower limit standard value -50 mm.
- the date, actual measurement value, and difference corresponding to the management position No. A0, A1, A2, etc. are blank when the actual measurement value has not been measured.
- the information transmission unit 154 transmits the construction plan information 627, including the completed form management table, to the result acquisition terminal 7.
- the information transmission unit 154 may also synchronize the construction management information 628 generated by the construction management information generation unit 155, which will be described later, with the result acquisition terminal 7.
- the construction management information generating unit 155 links the actual measurement values included in the actual measurement information 723 acquired by the performance acquisition terminal 7 to the construction plan information 627, and generates the construction management information 628.
- FIG. 10 is a diagram showing a completed form management table, which is an example of a document to be submitted.
- the construction management information 628 includes a completed form management table having a list TBL2 in which at least some of the actual results values are listed, as shown in FIG. 10.
- the construction management information generating unit 155 calculates the difference between the design value included in the construction plan information 627 and the actual measurement value acquired by the performance acquisition terminal 7.
- the construction management information generating unit 155 also links the design value, the actual measurement value, and the difference to the management position, and generates a completed form management table, which is an example of the construction management information 628.
- the submission document creation unit 156 creates a completed form management table in which design values and actual measured values are linked for each management position according to a specified format, based on the construction management information 628 generated by the construction management information generation unit 155.
- the construction plan information 627 includes design values related to the earthwork of the water pipe construction. Furthermore, the data related to the construction performance includes actual measurement values corresponding to the design values. Furthermore, the construction management information generating unit 155 calculates the difference between the design values and the actual measurement values included in the performance information acquired by the performance acquisition terminal 7, and links the design values, the actual measurement values, and the difference to the management position to generate the construction management information 628.
- design values, actual measured values, and the difference between the design values and the actual measured values for earthwork in water pipe construction can be linked to the management location and managed as construction management information 628.
- FIG. 11 is a functional block diagram showing a schematic configuration of a water pipe construction management system 12 according to the third embodiment of the present invention.
- the water pipe construction management system 12 according to the third embodiment is a system that manages photographs.
- the water pipe construction management system 12 differs from the water pipe construction management system 11 according to the second embodiment in that photographs are managed as management items.
- the management items are, for example, photographs that are required to be taken at the location where the water pipe is to be buried or near the site.
- the performance information which is data related to the construction performance corresponding to the management item, includes photo data taken at the site.
- the performance acquisition terminal 7 acquires the photo data 724 as the performance information.
- the memory unit 72 of the performance acquisition terminal 7 differs from the memory unit 72 of the performance acquisition terminal 7 according to the second embodiment in that it further stores photo data 724 constituting part of the performance information, an electronic whiteboard 725, and a work information management list 726.
- the track record acquisition terminal 7 has a photographing unit 75 for taking pictures.
- the track record acquisition terminal 7 executes photographing with the photographing unit 75 in response to, for example, a user operation received by the touch panel unit 74.
- the control unit 73 of the track record acquisition terminal 7 generates photo data 724 to which an electronic whiteboard 725 has been added.
- the control unit 73 of the track record acquisition terminal 7 stores the generated photo data 724 in the storage unit 72. A method of adding the electronic whiteboard 725 to the photo data 724 will be described in detail later.
- the track record acquisition terminal 7 sends the generated photo data 724 to the management server 3.
- the control unit 33 of the management server 3 has a construction plan information generation unit 251, an electronic whiteboard creation unit 252, an information transmission unit 254, a construction management information generation unit 255, a submission document creation unit 256, and a work information management list generation unit 257.
- the construction plan information generating unit 251 links information 320 about the construction plan for the water pipe pipeline that is the subject of the water pipe construction work to the management items and management positions required in photo management, and generates construction plan information 927.
- the water utility determines the photography items to be managed, as well as the locations and content of the photography for said photography items.
- certain attachments may be required depending on the photography items. For example, the following photography locations, content, and photography items are determined:
- the photographed items may include the work content at the management location linked to the photographed items. Note that there may be multiple work contents for one management location.
- photos of gate valves, etc. are required.
- photos of retaining walls, etc. are required.
- photos of water supply pipe switching work are required. That is, the photographed items may include the equipment at the management location linked to the photographed items.
- FIG. 12 is a diagram explaining a method for setting the management positions of a pipeline in photo management.
- the construction plan information generating unit 251 sets management positions A0, ..., A9+10.0, C1 to C9 as photography locations for a designed pipeline TP whose start and end points have been set.
- the management positions A0, ..., A9+10.0, indicated by open and closed circles, include the basic and additional measurement points mentioned above.
- the closed circles A3, A6, and A9 represent measurement points every 150 m from the starting point.
- the open circles A0, A1, A2, A4, A5, A5+20.0, A7, A8, and A9+10.0 represent measurement points other than those every 150 m.
- the open circles A3, A6, and A9 require the taking of photos before work begins, after completion, status photos, photos of the finished product, and quality control photos.
- the open circles A0, A1, A2, ... require the taking of photos before work begins, after completion, and photos of the finished product.
- Triangle marks C3 and C7 indicate the locations where the special-shaped pipes are placed. For this reason, photos of the finished product are required to be taken at triangle marks C3 and C7.
- the open squares C1, C4, and C8 indicate the locations of the check valves. For this reason, photographs of the valves and plugs are required at the open squares C1, C4, and C8.
- the stars C2 and C5 indicate retaining earth. For this reason, at the stars C2 and C5, you are required to take photographs of the temporary structures.
- Black square marks C6 and C9 indicate the locations where water supply pipe switching work will be performed. For this reason, at black square marks C6 and C9, photographs of the water supply pipe switching work are required to be taken.
- the construction plan information generating unit 251 links the information 320 about the construction plan of the water pipe pipeline that is the subject of the water pipe construction work to the photographed items and the managed location to generate the construction plan information 927.
- the photographed items include the work content or equipment at the managed location.
- the electronic whiteboard creation unit 252 creates an electronic whiteboard 952 to be added to the photo data 724 based on the construction plan information 927. Whether or not an electronic whiteboard 952 is to be added is also set for each photo requested at each management position. The electronic whiteboard creation unit 252 creates the electronic whiteboard 952 depending on whether or not an electronic whiteboard 952 is to be added.
- FIG. 13 is a diagram showing an example of an electronic whiteboard.
- the electronic whiteboard E1 includes the work name E11, the type of work E12, the date of photography E13, the management location E14, the design dimensions E15, the measured dimensions E16, the instruction number E17, and a schematic diagram E18.
- the electronic whiteboard creation unit 252 sets the photography date E13 based on the process information included in the construction plan information 927. Furthermore, when it is necessary to set dimensions, the electronic whiteboard creation unit 252 sets the design dimensions E15 based on the design information included in the construction plan information 927. The actual dimensions E16 can be set after the actual measurement value information 723 including actual measurements is acquired by the result acquisition terminal 7. Furthermore, the electronic whiteboard creation unit 252 sets the work name E11, work type E12, and command number E17 based on the information 320 relating to the construction plan included in the construction plan information 927.
- the electronic whiteboard creation unit 252 stores the electronic whiteboard 952 created as described above in the memory unit 32.
- the information transmission unit 254 transmits the construction plan information 927 generated by the construction plan information generation unit 251 and the electronic whiteboard image of the electronic whiteboard 952 created by the electronic whiteboard creation unit 252 to the result acquisition terminal 7.
- the information transmission unit 254 may also synchronize the construction management information 928 created by the construction management information generation unit 255 described later with the result acquisition terminal 7.
- the information transmission unit 254 also synchronizes the work information management list 953 created by the work information management list generation unit 257 described later with the work information management list 726 stored in the memory unit 72 of the result acquisition terminal 7.
- the construction management information generating unit 255 links the photo data 724 acquired by the result acquisition terminal 7 to the construction plan information 927, and generates the construction management information 928. More specifically, the construction management information generating unit 255 acquires the result information including the photo data 724 from the result acquisition terminal 7, and links the photo data 724 to which the electronic whiteboard 725 has been added to the management position, and generates the construction management information 928.
- the management server can easily create an electronic whiteboard image to be added to the photo data 724.
- the submitted document creation unit 256 creates a construction photo ledger in which photographs are linked as management items for each management location according to a specified format, based on the construction management information 928 generated by the construction management information generation unit 255.
- the submitted document creation unit 256 stores the created construction photo ledger in the memory unit 32 as submitted document data 929.
- the work information management list generating unit 257 creates a work information management list 953, which is data of a list of actual performance information 722 acquired during a specified construction period, based on the construction management information 928.
- the specified construction period includes the construction period of a major process on a daily basis to a monthly or annual basis.
- the work information management list generating unit 257 also creates a work information management list 953 for each management location.
- the work information management list generating unit 257 determines whether a photograph that is actual performance information has already been taken at the management location, based on the construction management information 928. If a photograph that is actual performance information has already been taken at the management location, the work information management list generating unit 257 sets a completion flag indicating that the photograph has been taken.
- FIG. 14 is a diagram showing an example of the work information management list 953.
- three electronic whiteboards E21, E22, and E23 have been created at the management position No. 2. Since a photograph has already been acquired for the electronic whiteboard E21, the work information management list generation unit 257 sets a completion flag E211 for the electronic whiteboard E21.
- Fig. 15 is a diagram showing an example of a monitor image of the result acquisition terminal 7 when a photo is taken.
- Fig. 16 is a diagram showing a monitor image to which an electronic whiteboard E3 has been added.
- the performance acquisition terminal 7 stores the work information management list 726 received from the management server 3 in the memory unit 72.
- the result acquisition terminal 7 displays the contents of the work information management list 726 on the touch panel unit 74.
- the result acquisition terminal 7 accepts the selection of an electronic whiteboard from the user.
- the electronic whiteboard E21 displays each of the electronic whiteboards E21 to E23 in thumbnail format on the touch panel unit 74.
- the result acquisition terminal 7 displays the remaining electronic whiteboards E22 and E23 in a selectable state on the touch panel unit 74.
- the result acquisition terminal 7 captures an image using the photographing unit 75.
- a monitor image F1 as shown in FIG. 15 is obtained by the camera constituting the photographing unit 75.
- the control unit 73 of the result acquisition terminal 7 superimposes an electronic whiteboard image E231 of the electronic whiteboard E23 on the monitor image F1 as shown in FIG. 16, and displays it on the touch panel unit 74.
- the position at which the electronic whiteboard image E231 is superimposed on the monitor image F1 may be set to the top left of the monitor image F1 as an initial setting, for example, or the position may be changeable in response to a user operation.
- the photograph is completed when the user performs a shutter operation.
- the control unit 73 of the result acquisition terminal 7 stores in the memory unit 72 the photo data 724 in which the electronic whiteboard image is superimposed on the photographed image.
- the control unit 73 of the result acquisition terminal 7 stores in the memory unit 72 the photo data 724 to which the electronic whiteboard E23 has been added.
- the management item is a photograph.
- the result acquisition terminal 7 acquires the photographed photograph data 724 as result information.
- the construction management information generation unit 255 links the photographed photograph data 724 by the result acquisition terminal 7 to the management location, and generates the construction management information 928.
- FIG. 17 is a functional block diagram showing a schematic configuration of a water pipe construction management system 13 according to the fourth embodiment of the present invention.
- the water pipe construction management system 13 according to the fourth embodiment differs from the water pipe construction management system 11 according to the second embodiment in that the construction plan information 627 and the construction management information 628 are linked to the work scope.
- the information 320 relating to the construction plan stored in the memory unit 32 of the management server 3 further includes business entity information 3208.
- the business entity information 3208 includes information relating to the identification ID of the water utility.
- the information relating to the identification ID of the water utility includes, for example, a code uniquely assigned to each water utility and the name of the water utility.
- the business entity information 3208 is linked to construction project information 3204.
- the water pipe construction project in the construction project information 3204 is linked to the identification ID of the water utility that ordered the water pipe construction project.
- the construction plan information generating unit 151 links the information 320 on the construction plan of the water pipe pipeline that is the target of the water pipe construction work to the management items and management positions required in the completed form management for each predetermined section of the designed pipeline included in the design information 3201, and generates the construction plan information 627. Specifically, the construction plan information generating unit 151 reads the information 320 on the construction plan from the storage unit 32 for each predetermined section of the designed pipeline included in the design information 3201, and generates the construction plan information 627. As a result, the construction plan information 627 is generated for each of the predetermined sections.
- the specified section is, for example, a section included in one piece of drawing data for the designed pipeline.
- drawing data relating to the specified section in the designed pipeline is referred to as section drawing data.
- the designed pipeline includes at least one piece of section drawing data.
- the specified section may be a section other than that included in the one piece of drawing data, so long as it is a predetermined section in the designed pipeline.
- the section drawing data is linked to the water pipe construction work indicated in the construction project information 3204.
- the section drawing data is linked to the business entity information 3208 linked to the construction project information 3204.
- the section drawing data includes construction section data for at least one construction section.
- the construction section data is data for each construction section in the section drawing data.
- the construction section is a unit for managing water pipe construction work. For multiple construction sections, for example, different water pipe construction contractors may carry out the water pipe construction work, construction schedules may overlap, and different performance acquisition terminals may be assigned to acquire construction performance information as described below.
- the work section data includes work range data relating to at least one work range.
- the work range data is data for each work range in the work section data.
- the work range is the smallest unit for managing water pipe work.
- the work range may be determined based on the work schedule, or may be determined according to the work content. For example, the work range may be the work range for one day when the construction plan information is created, or may be the work range determined when the design information or the construction plan information is created.
- FIG. 18 is a diagram showing a schematic of section drawing data.
- FIG. 18 shows an example in which design information 3201 includes three section drawing data DD11, DD12, and DD13 as the section drawing data.
- FIG. 18 shows an example of section drawing data DD11.
- Section drawing data DD11 includes construction section data for two construction sections K1 and K2.
- Construction section K1 includes three work areas K11, K12, and K13.
- Construction section K2 includes two work areas K21 and K22.
- AA0 to AA5 indicate management positions
- P1 indicates the start point of the design pipeline TP
- P2 indicates the end point of the design pipeline TP.
- the construction plan information generating unit 151 generates the construction plan information for each work area using the design information and the attribute data. Specifically, the construction plan information generating unit 151 generates the construction plan information 627 using information on the design pipeline included in the design information 3201 and various information (3201-3208) included in the information on the construction plan 320. The construction plan information 627 is generated in association with the work area. The construction plan information 627 associated with the work area is also associated with the construction section including the work area. The construction plan information 627 associated with the work area is also associated with the section drawing data including data on the work area and the construction section. The construction plan information 627 associated with the work area is also associated with the construction schedule included in the process information 3207. In other words, the construction plan information 627 is associated with the work schedule information, which is information on the schedule of work in the work area associated with the construction plan information 627.
- FIG. 19 is a diagram showing a schematic of the construction plan information 627 generated by the construction plan information generating unit 151.
- the construction plan information 627 is generated by the construction plan information generating unit 151 for each of the section drawing data DD11, DD12, and DD13.
- the construction plan information generated based on the section drawing data DD11 includes construction plan information generated based on the construction sections K1 and K2.
- the construction plan information generated based on the construction section K1 includes construction plan information generated based on the work areas K11, K12, and K13.
- the construction plan information generated based on the construction section K2 includes construction plan information generated based on the work areas K21 and K22.
- the construction plan information 627 generated by the construction plan information generation unit 151 is stored in the storage unit 32.
- the construction plan information 627 may be stored in the storage unit 32 for each section drawing data, for each construction section, or for each work range.
- FIG. 19 shows an example in which the construction plan information is stored in the storage unit 32 for each section drawing data.
- the information transmission unit 154 outputs the construction plan information 627 generated by the construction plan information generation unit 151 and stored in the storage unit 32 to the track record acquisition terminal 7 described later. Specifically, the information transmission unit 154 links the construction plan information 627 to the work range, reads it from the storage unit 32, and outputs the read construction plan information 627 to the track record acquisition terminal 7 via the communication unit 31. In the example shown in FIG. 19, on work day: N, the information transmission unit 154 reads the construction plan information linked to the work ranges KK11, KK12, and KK13 on and after the construction schedule N from the storage unit 32, and transmits the read construction plan information 627 to the track record acquisition terminal 7. The information transmission unit 154 may transmit only the construction plan information linked to the work range KK11 of the construction schedule N, which is the day of the work day N, to the track record acquisition terminal 7.
- the construction management information generation unit 155 acquires the performance information acquired by the performance acquisition terminal 7 and linked to the work scope via the communication unit 31.
- the construction management information generation unit 155 links the performance information acquired from the performance acquisition terminal 7 to the construction plan information 627 to generate construction management information 628.
- the construction management information generation unit 55 stores the generated construction management information 628 in the memory unit 32.
- the memory unit 32 stores the construction plan information 627 and the construction management information 628, each linked to the work scope.
- the submitted document preparation unit 156 may create submitted document data 629 using construction plan information 627 and construction management information 628, at least one of which is linked to the construction section. In this case, the submitted document preparation unit 156 may create submitted document data 629 using construction plan information 627 or construction management information 628 linked to the work scope. In addition, the submitted document preparation unit 156 may create a daily report based on the performance information for the construction schedule N as a submitted document in accordance with the construction management information 628. The submitted document preparation unit 156 may create submitted documents for a work section or construction section for any period in response to a request from the construction plan terminal 5.
- control unit 33 further includes a construction plan information correction unit 157.
- the construction plan information correction unit 157 corrects the construction plan information 627 based on the performance information output from the performance acquisition terminal 7. Details of the construction plan information correction unit 157 will be described later.
- the result acquisition terminal 7 acquires water pipe construction result information 722 according to the construction plan information acquired from the management server 3 as described above. Specifically, the result acquisition terminal 7 acquires the result information 722 corresponding to the construction plan information 721 linked to the work scope according to an input from a site worker or an output from a detection device such as a sensor. The result information 722 may be linked with information on the work date of the work scope in addition to the actual measurement value information 723. The result acquisition terminal 7 may be configured by the construction plan terminal 5.
- the performance acquisition terminal 7 acquires construction plan information 721 linked to the work scope from the management server 3, and also acquires performance information 722 that corresponds to the construction plan information 721 and is linked to the work scope and work date, and then outputs the performance information 722 to the management server 3.
- the construction plan information correction unit 157 corrects the construction plan information 627 based on the construction management information 628 stored in the storage unit 32. In other words, the construction plan information correction unit 157 corrects the construction plan information 627 based on the performance information transmitted from the performance acquisition terminal 7. For example, when the performance information in the construction management information 628 indicates that the construction is progressing faster than the schedule planned in the construction plan information 627 or indicates that the construction is delayed, the construction plan information correction unit 157 corrects the construction plan information 627 using the construction management information 628. In this case, the construction plan information correction unit 157 corrects the construction plan information 627 using the construction management information 628 stored in the storage unit 32 and linked to the work scope.
- Figure 20 is a diagram that illustrates the correction process of the construction plan information 627 by the construction plan information correction unit 157.
- the following describes a case where the performance information in the construction management information 628 indicates that the construction is progressing faster than planned in the construction plan information 627.
- the construction plan information 721 linked to the work ranges shown in FIG. 19 is scheduled for work on construction schedule N, and the construction plan information 721 linked to the work range K12 is scheduled for work on construction schedule N+1.
- the performance acquisition terminal 7 acquires performance information 722 corresponding to the construction plan information 721 linked to the work ranges K11 and K12 among the construction plan information 721 linked to the work ranges shown in FIG. 19.
- the performance information 722 corresponding to the construction plan information 721 linked to the work ranges K11 and K12 is linked to the work day N. Therefore, this means that the work in the work range K12 was completed on the construction schedule N, which is earlier than the scheduled construction schedule N+1.
- the performance acquisition terminal 7 outputs the performance information 722 linked to the work ranges K11 and K12 to the management server 3.
- the construction plan information correction unit 157 corrects the construction plan information 627 based on the performance information 722 transmitted from the performance acquisition terminal 7. Specifically, as described above, in the planned work range K12, the work was completed on the construction schedule N, which is earlier than the construction schedule N+1, so the construction plan information correction unit 157 updates the construction schedule of the construction plan information 721 linked to the work range K12 to N based on the performance information 722 linked to the work range K12. Furthermore, the construction plan information correction unit 157 advances the construction schedule of the construction plan information 627 linked to the work range K13 of the construction schedule N+2 to N+1.
- construction plan information correction unit 157 may set a flag indicating that the work has been completed in the construction plan information 721 linked to the work range K12, rather than changing the construction schedule of the construction plan information 721 linked to the work range K12 in which the work was completed earlier than planned.
- the following describes a case where the performance information in the construction management information 628 indicates that the construction is behind schedule as planned in the construction plan information 627.
- the construction plan information correction unit 157 may postpone the construction schedule for the incomplete work scope.
- the construction plan information correction unit 157 corrects the construction schedule in the construction plan information 627 linked to work range K13 to N+1. That is, the construction plan information correction unit 157 corrects the construction schedule in work range K11 to the "next day" after the originally scheduled N. In response to this, the construction plan information correction unit 157 further sets the construction schedules in the construction plan information 627 linked to work ranges K12 and K13 from construction schedule N+1 onwards by one day each. That is, the construction schedules of the incomplete work ranges may be postponed in order.
- the construction plan information correction unit 157 may postpone the construction schedule for work area K11 to another day after N. In other words, the order of the incomplete work areas may be changed to postpone the construction schedule. If this affects the construction schedule for the subsequent work areas K12 and K13, the construction plan information correction unit 157 will revise the construction schedule for work area K12 and K13.
- the construction plan information correction unit 157 advances or postpones the construction schedule of the construction plan information 627 using the construction management information 628 as performance information linked to the work scope. In other words, the construction plan information correction unit 157 corrects the construction plan information 627 using the construction management information 628.
- the construction plan information 627 can be easily modified by modifying the construction plan information 627 using the construction management information 628 as actual performance information linked to the work scope.
- the plan for the water pipe construction work can be easily changed according to the work scope.
- the water pipe construction management system 1 is a system that manages water pipe construction. Furthermore, the management server 3 manages water pipe construction.
- the configuration of each of the above embodiments can also be used to manage pipeline construction for sewage systems, agricultural water, and the like, in addition to water supply (tap water).
- the configuration of each of the above embodiments can be realized as a pipeline construction management system, a pipeline construction management method that controls the pipeline construction management system, and a pipeline construction management program.
- the management server is a server that manages pipeline construction.
- the completed form management table does not include a schematic diagram.
- the completed form management table may also include a schematic diagram.
- the memory unit of the management server, the plan creation terminal, or the performance acquisition terminal can be realized by, for example, a storage device such as a volatile or non-volatile RAM (Read Only Memory) or ROM (Random Access Memory).
- the memory unit can be realized by, for example, an internal or external storage device or removable media.
- Specific examples of the memory unit include cache memory and main storage device.
- specific examples of the memory unit include auxiliary storage devices such as an SSD (Solid State Drive) or HDD (Hard Disk).
- control unit of the management server, the plan creation terminal, or the performance acquisition terminal realizes various functions by executing programs using a calculation device such as a CPU (Central Processing Unit) or an MPU (Micro Processing Unit).
- a calculation device such as a CPU (Central Processing Unit) or an MPU (Micro Processing Unit).
- some or all of the various functions realized by the control unit may be realized in hardware using a dedicated processor or calculation circuit.
- the program may be stored in a computer-readable storage medium that is capable of being stored not temporarily but substantially.
- the storage medium may be included in the storage unit of the management server, the plan creation terminal, or the performance acquisition terminal.
- the program may be supplied to the management server, the plan creation terminal, or the performance acquisition terminal via a wired or wireless transmission medium.
- the management server may be realized by one or more computer devices.
- the water pipe construction management systems 1, 11, 12, and 13 have a construction plan terminal 5 used by the planner U1 and a performance acquisition terminal 7 used by the site worker U2.
- the water pipe construction management systems may further have a water utility terminal used by the water utility.
- the water utility terminal may be able to access a management server and refer to various data such as construction plan information, construction management information, or submitted document data.
- the construction management information generating unit 55, 155, 255 links the construction plan information 327, 627, 927 and the performance information to the management position of the pipeline that is the object of management, to generate the construction management information 328, 628, 928.
- the construction management information generating unit does not have to link the construction plan information and the performance information to the management position of the pipeline that is the object of management.
- the construction management information generating unit may link the construction plan information and the performance information to map information.
- the management server 3 has a submission document preparation unit 56, 156, 256.
- the document preparation unit may be omitted.
- the performance acquisition terminal 7 has a touch panel unit 74.
- the performance acquisition terminal may have a display device and an input device that are different from the touch panel unit.
- the result acquisition terminal 7 adds the electronic whiteboard 725 to the photo data 724.
- the management server 3 may also add the electronic whiteboard 725 to the photo data 724.
- the result acquisition terminal 7 acquires image data on which an electronic whiteboard image is not superimposed as photo data.
- the result acquisition terminal 7 transmits the image data and the electronic whiteboard corresponding to the image data to the management server 3.
- the management server 3 adds the electronic whiteboard to the photo data.
- the electronic whiteboard creation unit 252 creates an electronic whiteboard 952 to be added to the photo data 724 based on the construction plan information 927.
- the electronic whiteboard creation unit may be omitted.
- the work information management list generation unit 257 creates a work information management list 953, which is data of a list of performance information 722 acquired during a specified construction period, based on the construction management information 928.
- the work information management list generation unit may be omitted.
- management positions AA0 and AA3 are located at both ends of the construction section K1.
- management positions are located at both ends of each work section.
- a management position may be located midway through a work section.
- a work section may include multiple management positions.
- the construction plan information and the construction management information are each linked to the work scope.
- the construction plan information may be linked to a parameter other than the work scope.
- the construction management information may be linked to a parameter other than the work scope.
- the management server 3 has the construction plan information correction unit 157.
- the management server in other embodiments may have the construction plan information correction unit.
- a device other than the management server may have the construction plan information correction unit.
- the construction plan information 627 is generated by the management server 3 for each of the specified sections.
- the management server may generate the construction plan information for each of the specified sections.
- the present invention can be used in pipeline construction management systems that manage pipeline construction.
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Life Sciences & Earth Sciences (AREA)
- Biodiversity & Conservation Biology (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Priority Applications (5)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202380073641.7A CN120077402A (zh) | 2022-10-18 | 2023-07-27 | 管路工程管理系统、管理服务器、管路工程管理方法及管路工程管理程序 |
| EP23879424.2A EP4607442A4 (en) | 2022-10-18 | 2023-07-27 | Conduit construction management system, management server, conduit construction management method, and conduit construction management program |
| JP2024551233A JPWO2024084771A1 (https=) | 2022-10-18 | 2023-07-27 | |
| TW112128655A TW202418160A (zh) | 2022-10-18 | 2023-07-31 | 管路工程管理系統、管理伺服器、管路工程管理方法及管路工程管理程式 |
| US19/182,866 US20250245760A1 (en) | 2022-10-18 | 2025-04-18 | Conduit construction management system, management server, conduit construction management method, and conduit construction management program |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP2022166821 | 2022-10-18 | ||
| JP2022-166821 | 2022-10-18 |
Related Child Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| US19/182,866 Continuation US20250245760A1 (en) | 2022-10-18 | 2025-04-18 | Conduit construction management system, management server, conduit construction management method, and conduit construction management program |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| WO2024084771A1 true WO2024084771A1 (ja) | 2024-04-25 |
Family
ID=90737406
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| PCT/JP2023/027660 Ceased WO2024084771A1 (ja) | 2022-10-18 | 2023-07-27 | 管路工事管理システム、管理サーバ、管路工事管理方法及び管路工事管理プログラム |
Country Status (6)
| Country | Link |
|---|---|
| US (1) | US20250245760A1 (https=) |
| EP (1) | EP4607442A4 (https=) |
| JP (1) | JPWO2024084771A1 (https=) |
| CN (1) | CN120077402A (https=) |
| TW (1) | TW202418160A (https=) |
| WO (1) | WO2024084771A1 (https=) |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008225862A (ja) | 2007-03-13 | 2008-09-25 | Element System Kk | 電子黒板付き工事写真撮像及び工事管理台帳自動作成システム並びにこれに使用するプログラム |
| JP2014098956A (ja) * | 2012-11-13 | 2014-05-29 | Yks Corporation Co Ltd | 水道工事日報作成装置、水道工事日報作成装置の制御方法、水道工事日報作成装置プログラム及び記録媒体 |
| JP2016189199A (ja) | 2011-10-31 | 2016-11-04 | 株式会社リコー | 管理システム |
| JP2017102935A (ja) | 2016-12-20 | 2017-06-08 | 株式会社建設システム | プログラム、携帯端末、情報処理方法、及び、情報処理システム |
| JP2021165920A (ja) * | 2020-04-07 | 2021-10-14 | 株式会社クボタ | 施工管理書類作成装置、施工管理書類作成方法、配管施工図作成装置及び配管施工図作成方法 |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5557718B2 (ja) * | 2010-12-08 | 2014-07-23 | 株式会社クボタ | 配管施工管理システム、携帯端末及び施工情報管理サーバ |
| JP6542597B2 (ja) * | 2015-06-23 | 2019-07-10 | 株式会社クボタ | 施工管理情報収集装置、管路竣工図作成システム、施工管理情報収集方法、工事日報生成方法及び工事日報 |
| US11386364B1 (en) * | 2019-10-24 | 2022-07-12 | Eci Software Solutions, Inc. | Construction project information and document access system |
-
2023
- 2023-07-27 EP EP23879424.2A patent/EP4607442A4/en active Pending
- 2023-07-27 JP JP2024551233A patent/JPWO2024084771A1/ja active Pending
- 2023-07-27 CN CN202380073641.7A patent/CN120077402A/zh active Pending
- 2023-07-27 WO PCT/JP2023/027660 patent/WO2024084771A1/ja not_active Ceased
- 2023-07-31 TW TW112128655A patent/TW202418160A/zh unknown
-
2025
- 2025-04-18 US US19/182,866 patent/US20250245760A1/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2008225862A (ja) | 2007-03-13 | 2008-09-25 | Element System Kk | 電子黒板付き工事写真撮像及び工事管理台帳自動作成システム並びにこれに使用するプログラム |
| JP2016189199A (ja) | 2011-10-31 | 2016-11-04 | 株式会社リコー | 管理システム |
| JP2014098956A (ja) * | 2012-11-13 | 2014-05-29 | Yks Corporation Co Ltd | 水道工事日報作成装置、水道工事日報作成装置の制御方法、水道工事日報作成装置プログラム及び記録媒体 |
| JP2017102935A (ja) | 2016-12-20 | 2017-06-08 | 株式会社建設システム | プログラム、携帯端末、情報処理方法、及び、情報処理システム |
| JP2021165920A (ja) * | 2020-04-07 | 2021-10-14 | 株式会社クボタ | 施工管理書類作成装置、施工管理書類作成方法、配管施工図作成装置及び配管施工図作成方法 |
Non-Patent Citations (1)
| Title |
|---|
| See also references of EP4607442A4 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN120077402A (zh) | 2025-05-30 |
| EP4607442A4 (en) | 2026-03-04 |
| JPWO2024084771A1 (https=) | 2024-04-25 |
| EP4607442A1 (en) | 2025-08-27 |
| US20250245760A1 (en) | 2025-07-31 |
| TW202418160A (zh) | 2024-05-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CA2750923C (en) | Systems, methods and apparatus relating to generation, transmission, access and storage of virtual white line (vwl) images and data for excavation projects | |
| US20150310360A1 (en) | Systems and methods for advanced sanitary sewer infrastructure management | |
| US10671650B2 (en) | System and method for integration and correlation of GIS data | |
| JP2017215878A (ja) | 工事情報管理システム | |
| WO2012162736A1 (en) | Construction management system and method | |
| JP2001325310A (ja) | 下水道敷設設計支援システム及び記録媒体 | |
| WO2024084771A1 (ja) | 管路工事管理システム、管理サーバ、管路工事管理方法及び管路工事管理プログラム | |
| JP2001222521A (ja) | 書類作成システム及び記録媒体 | |
| JP2984262B1 (ja) | 地中線支援システム | |
| US20150186894A1 (en) | Locate ticket management | |
| JP2024088574A (ja) | 管路工事管理装置、管路工事管理システム、管路工事管理方法及び管路工事管理プログラム | |
| JP2024092932A (ja) | 電子黒板管理装置、電子黒板管理システム、電子黒板管理方法及び電子黒板管理プログラム | |
| Erdélyi et al. | Building information modelling of industrial plants | |
| JP2020042531A (ja) | 固定資産管理システム | |
| JP2004295628A (ja) | インフラストラクチャに対する工事支援システム | |
| JP2006048281A (ja) | 設計図面作成システム及び積算システム及び工事管理システム | |
| JP2003296404A (ja) | 工事に伴う地図更新のシステムとその更新方法並びに地図更新サービス提供方法 | |
| CN113378258B (zh) | 一种长输管道三维设计方法 | |
| JP2003082853A (ja) | 書類作成支援プログラム、書類作成支援方法および提出書類管理装置 | |
| Persson | Surveying in the Construction Industry-A study of surveying and machine guidance systems in excavators on ground construction projects | |
| JP2001324053A (ja) | ガス管路埋設業務支援システム及び記録媒体 | |
| Reeder et al. | 3D engineered models for highway construction: the Iowa experience. | |
| Spangler et al. | Record Package Guidance: Best Practices | |
| JP2025068876A (ja) | 管路工事の工程計画作成装置、工程計画作成システム、工程計画作成方法及び工程計画を作成するためのプログラム | |
| JP2024150311A (ja) | 写真管理台帳作成システム、写真管理台帳作成方法及び写真管理台帳作成システム制御用プログラム |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| 121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 23879424 Country of ref document: EP Kind code of ref document: A1 |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2024551233 Country of ref document: JP Ref document number: 202380073641.7 Country of ref document: CN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 202517042791 Country of ref document: IN |
|
| WWE | Wipo information: entry into national phase |
Ref document number: 2023879424 Country of ref document: EP |
|
| NENP | Non-entry into the national phase |
Ref country code: DE |
|
| WWP | Wipo information: published in national office |
Ref document number: 202517042791 Country of ref document: IN |
|
| ENP | Entry into the national phase |
Ref document number: 2023879424 Country of ref document: EP Effective date: 20250519 |
|
| WWP | Wipo information: published in national office |
Ref document number: 202380073641.7 Country of ref document: CN |
|
| WWP | Wipo information: published in national office |
Ref document number: 2023879424 Country of ref document: EP |