WO2024037042A1 - Construction method for erecting inter-section whole-section steel truss using girder erection crane - Google Patents

Construction method for erecting inter-section whole-section steel truss using girder erection crane Download PDF

Info

Publication number
WO2024037042A1
WO2024037042A1 PCT/CN2023/091549 CN2023091549W WO2024037042A1 WO 2024037042 A1 WO2024037042 A1 WO 2024037042A1 CN 2023091549 W CN2023091549 W CN 2023091549W WO 2024037042 A1 WO2024037042 A1 WO 2024037042A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel truss
girder
crane
segment
erecting
Prior art date
Application number
PCT/CN2023/091549
Other languages
French (fr)
Chinese (zh)
Inventor
梁辉
朱东明
李桐
夏朝鹃
张延辉
王员根
向华
任华焘
郑奕
杨志明
赵梦春
闵理
李勇刚
高峰
Original Assignee
中铁九桥工程有限公司
中铁高新工业股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁九桥工程有限公司, 中铁高新工业股份有限公司 filed Critical 中铁九桥工程有限公司
Publication of WO2024037042A1 publication Critical patent/WO2024037042A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • E01D21/105Balanced cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Definitions

  • the invention relates to the technical field of bridge construction, and specifically to a construction method for erecting a double-intersection whole-section steel truss beam using a girder erecting crane.
  • the whole-segment hoisting method has the advantages of fewer on-site bolting or welding parts, reliable installation quality, and fast installation speed. It is often used for the installation of steel trusses.
  • the whole-segment hoisting method is usually carried out by a bridge deck crane. Erection.
  • the construction schedule is usually tight and the construction tasks are heavy.
  • it is necessary to adopt Construction is carried out by hoisting double-section whole sections.
  • the weight of the whole-section steel truss beam between double sections is usually more than twice that of the single whole-section steel truss beam.
  • the existing steel truss beams erected by the existing bridge deck crane are generally It uses a single-section whole-segment hoisting method, and its lifting capacity cannot meet the erection needs of double-segment whole-segment steel truss beams.
  • the problem solved by the invention is how to erect the entire section steel truss beam between double sections.
  • the present invention provides a construction method for erecting a double-section full-section steel truss beam using a girder erecting crane, which includes:
  • the steel truss beam segment is installed, the connection between the hoisting mechanism and the steel truss beam segment is released, the overhead crane mechanism is retracted and locked, and the girder erecting crane moves to the next girder erecting position.
  • the moving the girder erecting crane to the girder erecting position, and preparing the girder erection includes:
  • the traveling mechanism of the girder erecting crane drives the girder erecting crane to move to the girder erecting position;
  • the traveling mechanism of the girder erecting crane drives the girder erecting crane to move to the girder erecting position including:
  • the sliding shoe cylinder of the traveling mechanism contracts upward to drive the track beam of the traveling mechanism off the ground;
  • the traveling oil cylinder of the traveling mechanism is connected to the limit hole of the track beam.
  • the contraction of the traveling oil cylinder drives the track beam to move forward.
  • the connection between the traveling oil cylinder and the limit hole is released.
  • the traveling oil cylinder extends Go out to the next limit hole and repeat the above operations until the track beam moves into place;
  • the sliding shoe cylinder extends downward to drive the track beam to touch the ground and receive force
  • the traveling oil cylinder is connected to the limit hole of the track beam.
  • the traveling oil cylinder extends to drive the girder crane to move forward, and the connection between the traveling oil cylinder and the limiting hole is released.
  • the traveling oil cylinder Shrink to the next limiting hole and repeat the above operation until the girder crane moves into place.
  • the overhead crane mechanism includes a large beam and a small beam, the large beam and the small beam are arranged in parallel and are respectively slidingly connected to the frame of the girder crane, and the large beam and the small beam are Used to slide along the length direction of the frame, the hoisting mechanism includes three sets of spreaders arranged in a Z-shaped arrangement. The first set of spreaders is arranged at one end of the large beam, and the second set of spreaders is arranged at one end of the large beam. At the other end of the large beam, a third group of the spreaders is arranged on the small beam.
  • the spreaders include a distribution beam, a lifting point slider and an adjustment oil cylinder. The lifting point slider is connected to all the lifting points through a wire rope.
  • the crane mechanism is movably connected, the distribution beam is slidingly connected to the lifting point slider, one end of the adjustment oil cylinder is connected to the distribution beam, and the other end of the adjustment oil cylinder is connected to the suspension point slider,
  • the distribution beam is used to connect with the steel truss beam segments.
  • the distance between the lifting point slide blocks of the first group of the spreaders, the suspension point slide blocks of the second group of the spreaders and the hanging point slide blocks of the third group of the spreaders is equal to The distance between the large beam and the small beam.
  • the construction method after moving the girder erecting crane to the girder erecting position and preparing the girder erection, and before lowering the hoisting mechanism of the girder erecting crane, the construction method also includes:
  • the construction method Also includes:
  • the adjustment of the longitudinal slope of the steel truss beam segment includes:
  • the construction method when erecting to the closing port, also includes closing the steel truss beam segments with the opposite erected steel truss beams, and closing the steel truss beam segments with the opposite erected steel truss beams.
  • the erected steel truss beams include the lower chords, diagonal bars and upper chords of the steel truss beam segments, wherein the lower chords include the middle truss lower chords and side truss lower chords, which are connected in sequence.
  • the diagonal rods include the diagonal rods of the middle truss and the diagonal rods of the side girders, and the upper chord rods include the upper chord rods of the side girders and the upper chord rods of the middle girders.
  • the present invention has the following beneficial effects:
  • the girder erecting crane In the process of erecting the steel truss beam segment, the girder erecting crane first lifts the steel truss beam segment to the preset height so that the steel truss beam segment is in a suspended state, and then adjusts the posture of the three spreaders of the hoisting mechanism.
  • the center of gravity of the steel truss beam segment and the centroid of the hoisting mechanism are on a vertical line, so that the steel truss beam can be
  • the weight of the segment is evenly distributed on the three spreaders, which can maximize the hoisting capacity of each spreader and improve the lifting capacity of the girder crane, which can meet the requirements for erecting the entire segment steel truss beam between double sections.
  • the steel truss beam segments can maintain a stable rise during the entire hoisting process, and the safety of the steel truss beam segment hoisting is ensured.
  • the crane structure moves the steel truss beam segment to the position where it docks with the erected steel truss beam, the coincidence degree between the rear end face of the steel truss beam segment and the front end face of the erected steel truss beam is higher. high, making docking more convenient.
  • Figure 1 is a schematic structural diagram of a girder crane in an embodiment of the present invention
  • Figure 2 is an enlarged view of position A in Figure 1 according to the embodiment of the present invention.
  • Figure 3 is an enlarged view of B in Figure 1 according to the embodiment of the present invention.
  • Figure 4 is a schematic structural diagram of the girder erecting crane from another perspective according to the embodiment of the present invention.
  • Figure 5 is a schematic structural diagram of the girder erecting crane from another perspective according to the embodiment of the present invention.
  • Figure 6 is a schematic diagram of the state of S100 in the embodiment of the present invention.
  • Figure 7 is a schematic diagram of the state of S200 in the embodiment of the present invention.
  • Figure 8 is a schematic diagram of the states from S300 to S400 in the embodiment of the present invention.
  • Figure 9 is a schematic diagram of the states from S500 to S600 in the embodiment of the present invention.
  • Figure 10 is a schematic diagram of the states from S700 to S800 in the embodiment of the present invention.
  • Figure 11 is a schematic diagram of the state of S800 in the embodiment of the present invention.
  • embodiments of the present invention provide a construction method for erecting a double-section full-section steel truss beam using a girder erecting crane, which includes:
  • the girder crane is composed of a frame 5, a support mechanism, a traveling mechanism 3, an anchoring mechanism 4, a lifting mechanism, a crane mechanism 2 and a hoisting mechanism 1.
  • the frame 5 is composed of a bottom front beam, a lower main beam, a rear anchor beam, an upper front beam, an upper main beam, an upper rear beam, a column, a front support rod, a rear tie rod, and multiple connecting systems using high-strength bolts. Or it is connected by pins.
  • the lower main beam, upper main beam, front support rod and rear tie rod located on the left and right sides respectively form a diamond-shaped left truss and a diamond-shaped right truss.
  • the two sets of lower main beams and upper main beams located in the middle , the front support rod and the rear tie rod respectively form a diamond-shaped left middle truss and a diamond-shaped right middle truss.
  • the beam 200 passes through the cables of the bridge tower.
  • the structural forms of the middle truss and the side truss are similar, except that the cross-section of the rod used in the middle truss is slightly smaller.
  • the traveling mechanism 3 of the girder erecting crane drives the girder erecting crane to move to the girder erecting position;
  • each group of traveling mechanisms 3 includes two sets of front and rear traveling components.
  • Each group of traveling components consists of track beams 31, traveling sliding shoes, traveling cylinders 32 and push supports.
  • the traveling sliding shoe is composed of a connecting seat, a sliding shoe cylinder 33 and a sliding sleeve.
  • the connecting seat is fixedly connected to the frame 5, the sliding sleeve is slidingly connected to the track beam 31, and the sliding shoe cylinder 33 is arranged between the connecting seat and the sliding sleeve. It can telescope up and down.
  • One end of the traveling oil cylinder 32 is detachably connected to the track beam 31 through a push support.
  • the other end of the traveling oil cylinder 32 is connected to the sliding sleeve of the traveling sliding shoe.
  • the track beam 31 is provided with multiple sets of limit holes. 311 is used for detachable connection with the push support.
  • the process of the traveling mechanism 3 driving the girder crane to move is as follows:
  • the sliding shoe cylinder 33 of the traveling mechanism 3 contracts upward to drive the track beam 31 of the traveling mechanism 3 to lift off the ground;
  • the support mechanism consists of a left front outrigger, a middle front outrigger, a right front outrigger and four rear outriggers.
  • the left front outrigger and right front outrigger The legs are respectively set at the left and right ends of the bottom front beam, the middle front leg is set in the middle of the bottom front beam, and is located between the left middle truss and the right middle truss.
  • the four rear legs are evenly distributed along the width direction of the frame 5
  • the left front leg, right front leg and four rear legs all use adjustable screw rigid legs
  • the middle front leg uses constant pressure flexible legs .
  • the support force of the left front outrigger and right front outrigger can be designed to be 1400t
  • the support force of the four rear outriggers can be designed to be 100t
  • the middle front outrigger can be equipped with a 2000t level constant pressure cylinder to control the middle truss support. Reaction force.
  • the support mechanism uses rigid support through the left front outrigger and right front outrigger, and the middle front outrigger uses constant pressure flexible outriggers, which can maintain the pressure on the middle front outrigger as the total reaction under any working conditions.
  • One-third of the force, and the girder crane has a symmetrical structure, so the remaining two-thirds of the total reaction force will be automatically shared evenly by the left front leg and the right front leg. Therefore, the girder crane can be lowered to the maximum extent.
  • the beam crane exerts a local load on the steel truss beam 200 at which it is located, so that the bearing capacity of the steel truss beam 200 at which it is located can be utilized to the maximum extent to erect a steel truss beam segment 100 of greater weight.
  • the width direction of the frame 5 refers to the X-axis direction.
  • the four track beams 31 of the four sets of traveling mechanisms 3 need to be operated synchronously according to the above steps, and the traveling speed needs to be accurately controlled.
  • the rated traveling speed is set to 1m/min.
  • the working level of the traveling mechanism is M4.
  • the sliding shoe cylinder 33 extends downward to drive the track beam 31 to touch the ground and receive force;
  • the length of the sliding shoe cylinder 33 extending downward must be sufficient to make each leg of the support mechanism in an off-the-ground state, and the beam erecting crane is converted from a state supported by the support mechanism to a state supported by the four track beams 31. state.
  • the beam erecting crane itself has a large dead weight, it can be placed at the bottom of the track beam 31 Install a support pad with a larger friction coefficient. After the track beam 31 touches the ground and is stressed, the static friction between the track beam 31 and the erected steel truss beam 200 can be used to ensure that the track is moved when the girder erecting crane is subsequently moved. The beam 31 is in a stationary state, and there is no need to temporarily fix the track beam 31 to the erected steel truss beam 200 by means of bolts or welding.
  • the front leg of the support mechanism is equipped with a flip cylinder and a corresponding connecting rod structure.
  • a flip cylinder When in use, just retract the oil cylinder to realize automatic flip of the front leg, avoiding the anchor of the erected steel truss beam 200 box; and the anchoring tie rod assemblies on the left and right sides of the anchoring mechanism 4 are also equipped with flipping cylinders. Just flip it outward when the machine is moving.
  • the frame 5 of the girder crane has a diamond-shaped structure as a whole, when the front end of the girder crane is hoisting the beam, in order to improve the stability of the girder crane and prevent overturning during the erection of the steel truss segment 100, After the traveling mechanism 3 drives the girder crane to move into place, the following steps need to be implemented:
  • the anchoring mechanism 4 is composed of four sets of bolt-type anchor tie rod assemblies.
  • Each set of anchor tie rod assemblies is composed of screw rods, distribution beams 111, tie plates and other parts.
  • the four sets of anchor tie rod assemblies are respectively arranged on the machine.
  • the rear anchor beam and the anchor ear seat are connected through rear anchor tie rods or bolts.
  • the anchor tie rods of this structure The components are clearly stressed, safe and reliable, and the height of the rear anchor can be easily adjusted.
  • the bottom rear side of the frame 5 of the girder crane is also equipped with a winch unit.
  • the wire rope of the winch unit is connected to the hoisting structure through the crane mechanism 2.
  • the winch unit The hoisting mechanism 1 can be raised or lowered by retracting and releasing the wire rope.
  • the descending process is in an unloaded state.
  • the descending speed of the hoisting mechanism 1 can be controlled between 0 and 3.6m/min. After the hoisting mechanism 1 is lowered in place, it can pass through the hoisting tool 11
  • Structures such as upper mounting booms are connected to the lifting lugs of the steel truss beam segments 100 .
  • centroid of the hoisting mechanism 1 refers to the geometric center of the triangle formed by the lines connecting the geometric centers of each group of hoists 11.
  • the plumb line refers to the straight line in the Z-axis direction.
  • the preset height should not be set too high. It is usually appropriate to hoist the steel truss segments to a suspended state with a certain amount of adjustment space.
  • the bridge is an inclined tower with three cable planes arranged on the main channel of the Yangtze River.
  • the double-segment steel truss girder 200 was rolled onto the ship at the Nantong Rugao manufacturing base, and was transferred by barge to the bottom of the girder crane on the river.
  • the hoisting mechanism 1 After the hoisting mechanism 1 is in place, connect the three sets of spreaders 11 to the steel truss beam segments 100.
  • the hoisting mechanism 1 lifts the steel truss beam segments 100 to a height of 300mm away from the hull. At this time, it can be the steel truss beam segment. 100 and the shaking of the hull provide enough space to ensure that the steel truss beam segment 100 is in a completely suspended state, making it easy to adjust the posture of the spreader 11 and ensuring the safety of the hoisting.
  • the operation of the lifting and hoisting mechanism 1 is opposite to the operation of the above-mentioned lowering and hoisting mechanism 1, which will not be described in detail here.
  • the difference is that the process of the lifting operation is a heavy load state, and the lifting speed should be controlled at 0 to 1.8m/min.
  • the steel truss beam section 100 when the hoisting mechanism 1 lifts the steel truss beam section 100, in order to avoid the steel truss beam section 100 colliding with the erected steel truss beam 200 and ensure the safety of the construction process, the steel truss beam section A certain misalignment needs to be maintained between the rear end face of the section 100 and the front end face of the erected steel truss 200.
  • a double-intersection whole-segment steel section with a length of 28m and a weight of 1800t is erected on the Hutong Yangtze River Bridge.
  • a 200mm misalignment needs to be maintained.
  • the crane mechanism 2 drives it to move along the length direction of the frame 5 through the longitudinal oil cylinder provided on the main beam of the frame 5, thereby hoisting the
  • the mechanism 1 and the steel truss beam segment 100 are translated as a whole to a position where they are docked with the erected steel truss beam 200 .
  • the length direction of the frame 5 refers to the Y-axis direction.
  • the stay cables dropped from the bridge tower can be connected to the anchor boxes on the steel truss girder section 100, and then connected by welding or bolting. Connect and fix it with the erected steel truss beam 200 in other ways, then release the connection between the hoisting mechanism 1 and the steel truss segment, retract the crane mechanism 2 and lock it to move the center of gravity of the girder erecting crane backward. After making preparations You can then walk to the next beam erection position for subsequent beam erection construction.
  • the crane mechanism 2 includes a large beam 21 and a small beam 22.
  • the large beam 21 and the small beam 22 are arranged in parallel and are respectively slidingly connected to the frame 5 of the girder crane, and the large beam 21 and the small beam 22 are arranged in parallel.
  • the beam 22 is used to slide along the length direction of the frame 5.
  • the hoisting mechanism 1 includes three sets of spreaders 11 arranged in a Z-shaped arrangement. The first set of spreaders 11 is arranged at one end of the large beam 21, and the second set of spreaders 11 is arranged at the large beam 21. At the other end of the beam 21, the third group of spreaders 11 is set on the small beam 22.
  • the spreader 11 includes a distribution beam 111, a lifting point slider 112 and an adjustment cylinder 113.
  • the lifting point slider 112 moves with the crane mechanism 2 through a wire rope. connection, the distribution beam 111 is slidingly connected to the lifting point slider 112, one end of the adjustment cylinder 113 is connected to the distribution beam 111, the other end of the adjustment cylinder 113 is connected to the lifting point slider 112, the distribution beam 111 is used to connect with the steel truss beam section 100 connections.
  • the left and right ends of the large cross beam 21 are slidingly connected to the left upper main beam and the right upper main beam of the frame 5 respectively, and the small cross beam 22
  • the left and right ends are slidingly connected to the upper middle main beam on the left and the upper main beam on the right respectively, and a set of longitudinal oil cylinders are provided between the two and the upper main beams carrying their respective parts to drive the large cross beam 21 and the small cross beam 22 longitudinally. shift.
  • the large crossbeam 21 and the small crossbeam 22 are arranged one behind the other.
  • the large crossbeam 21 can be in the front and the small crossbeam 22 can be in the back.
  • the large crossbeam 21 can be arranged in the back and the small crossbeam 22 can be arranged in the front as needed. , there is no restriction here.
  • the small beam 22 can be arranged at the rear, so that the third group of spreaders 11 in the middle can be easily stored in a deeper position in the space between the left middle truss and the right middle truss, making the whole machine more compact.
  • the center of gravity is further back, which is safer.
  • the distribution beam 111 of the spreader 11 is arranged along the length direction of the frame 5, and its front and rear ends are provided with lifting holes.
  • the positions of the lifting holes match the positions of the lifting lugs of the steel truss beam segments 100, and the suspension rods and steel beams can be inserted.
  • the lifting lugs of the truss beam segments 100 are connected.
  • the lifting point slider 112 adopts a frame with a C-shaped cross-section.
  • the distribution beam 111 is provided with slideways and multiple slots along the length direction.
  • the C-shaped frame is set on the distribution beam 111 On the sliding movement, one end of the adjusting cylinder 113 is connected to the distribution beam 111, and the other end of the adjusting cylinder 113 is connected to the C-shaped frame.
  • the upper part of the C-shaped frame is provided with an ear plate that can be hinged with the movable pulley provided on the wire rope.
  • the adjusting cylinder When 113 telescopes it can drive the C-shaped frame to slide on the slide of the distribution beam 111.
  • the C-shaped frame can be locked at a certain slot on the distribution beam 111 through the locking structure.
  • the locking structure can be unlocked, and the adjustment cylinder 113 drives the C-shaped frame to slide on the slide of the distribution beam 111 again.
  • the C-shaped frame in the process of lowering the hoisting mechanism 1, in order to maintain the balance of the distribution beam 111, the C-shaped frame is usually located on the vertical line of the center of gravity of the distribution beam 111. During the hoisting process, The centroid of the hoisting mechanism 1 and the center of gravity of the steel truss beam segment 100 are always on the same vertical line. Therefore, when the position of the C-shaped frame is adjusted, the distribution beam 111 will not tilt.
  • the lifting point of the second group of spreaders 11 located in the middle will deviate from the midpoint of the distribution beam 111 by a certain distance, the load received by each part of the distribution beam 111 is not uniform. Therefore, in order to ensure that the distribution beam 111 For the strength of each part of 111, the end relatively close to the hanging point can be strengthened, and the end relatively far away can be appropriately reduced in weight.
  • the first group of hoists The distance between the lifting point slider 112 of the lifting device 11 and the lifting point slider 112 of the second group of lifting fixtures 11 and the lifting point slider 112 of the third group of lifting fixtures 11 is equal to the distance between the large beam 21 and the small beam 22 .
  • the steel wire ropes connecting the three groups of spreaders 11 are always along the In the direction of the plumb line, when adjusting the hanging point sliders 112 of the three sets of spreaders 11, it is necessary to keep the hanging point sliders 112 of the first set of spreaders 11 and the hanging point sliders 112 of the second set of spreaders 11 in contact with the third set of spreaders 11.
  • the distance between the lifting point slide blocks 112 of the group spreader 11 is equal to the distance between the large beam 21 and the small beam 22 .
  • the distance between the large beam 21 and the small beam 22 is 4050mm, that is to say, the first
  • the distance between the lifting point slider 112 of the first set of spreaders 11 and the second set of spreaders 11 and the third set of spreaders 11 is also 4050mm, where the first set of lifts
  • the lifting point slider 112 of the hoisting tool 11 and the hanging point slider 112 of the second group of hoisting tools 11 allow an adjustment range of 0 to 2080mm on their corresponding distribution beams 111.
  • the hanging point slider 112 of the second group of hoisting tools 11 The allowable adjustment range value on its corresponding distribution beam 111 is 0 to 4010 mm.
  • the three groups of spreaders 11 are lifted synchronously at a preset speed, which refers to the average speed within a preset time.
  • synchronous promotion means starting to improve at the same moment or stopping the promotion at the same moment.
  • the preset speed refers to the average speed within the preset time, not the instant speed at a certain moment. In this way, even at a certain moment The real-time speed of a certain group of spreaders 11 is too fast. As long as the real-time speed can be reduced within a preset time, the dynamic balance of the hoisting mechanism 1 can be maintained, making the operability stronger.
  • the steel truss beam sections to be erected will The greater the possibility of shaking in segment 100, the worse the stability.
  • the shorter the preset time the harder it is to maintain dynamic balance, but the better the stability.
  • the specific settings can be set according to needs. There are no restrictions here.
  • the preset time can be set to 10s, 20s or 30s
  • the preset speed can be set to 0.6m/min, 1.2m/min or 1.8m/min
  • the synchronous lifting accuracy is 50mm.
  • the construction method after moving the girder erecting crane to the girder erecting position, preparing to erect the girder, and before lowering the hoisting mechanism 1 of the girder erecting crane, the construction method also includes:
  • the construction method also includes:
  • adjusting the longitudinal slope of the steel truss segment 100 includes the following steps:
  • the adjustment cylinder 113 of the second group of spreaders 11 in the middle can be adjusted first.
  • the adjustment cylinders 113 of the two sets of spreaders 11 located on both sides try to achieve simultaneous and same-amplitude adjustment.
  • the overall lifting or lowering of the hoisting mechanism 1 aligns the rear end surface of the steel truss beam segment 100 with the front end surface of the erected steel truss beam 200.
  • the steel truss beam segment 100 after adjusting the longitudinal inclination angle of the steel truss beam segment 100, the steel truss beam segment 100 will tilt forward or backward as a whole. Therefore, the rear end surface of the steel truss beam segment 100 will not be in contact with the erected steel beam There will inevitably be a certain height difference on the front end surface of the truss beam 200. At this time, in order to maintain the longitudinal inclination angle of the steel truss beam segment 100, this height difference cannot be adjusted by adjusting the attitude of the hoisting mechanism 1, and the entire body needs to be raised or lowered. The hoisting mechanism 1 is used to eliminate this height difference, thereby making the steel truss segment 100 and the erected steel truss 200 more accurately connected.
  • the construction method also includes closing the steel truss beam section 100 with the opposite erected steel truss beam 200, and connecting the steel truss beam section 100 with the opposite erected steel truss beam.
  • the 200 joints include the lower chords, diagonal bars and upper chords of the steel truss beam segments 100.
  • the lower chords include the middle truss lower chords and the side truss lower chords.
  • the diagonal bars include the middle truss diagonal bars and the side truss lower chords.
  • the side truss diagonal rods and the top chord rods of the side girders include the upper chord rods of the side girders and the upper chord rods of the center girders.
  • the following article takes the erection of a double-intersection whole-segment steel truss beam with a length of 28m and a weight of 1800t on the Hutong Yangtze River Bridge as an example to illustrate the auxiliary span steel truss beam closing construction.
  • the span steel truss beam is closed, the main channel bridge steel truss beam is in the maximum double cantilever state.
  • the auxiliary span steel truss beam closure is constructed in the order of closing the lower chord first, then closing the diagonal beam, and then closing the upper chord.
  • the main truss upper chord and diagonal beam high-bolt construction platform of the Helong section steel truss beam segment 100 can be directly used as a standard segment steel truss beam construction platform and sent to the steel truss girder assembly yard for installation in the factory.
  • the splicing joints between the Z12 ⁇ Z13 steel truss beam segments 100 and the Z14 ⁇ Z15 steel truss beam segments 100 are equipped with belts in a normal "Z" shape under standard section cantilever erection conditions, and the bottom string is pole and slope
  • the splicing plate of the rod is normally placed between Z13 sections, and the upper chord bar is placed between Z14; the lower chord bar and the upper chord bar are spliced at the joint position of the Z12 ⁇ Z13 steel truss beam segment 100 and the Z11 steel truss beam segment 100
  • the plate is normally strapped between the sections of Z12 steel truss beam section 100.
  • the splicing plate shrink strap is flush with the diagonal rod port between the sections of Z12 steel truss beam section 100; the cantilever end steel truss
  • the linear adjustment of the beam is mainly before the auxiliary pier is closed.
  • the linear shape of the steel truss beam can be calculated and analyzed based on the load conditions of the steel truss beam and the tension situation of the stay cables, and the cable force of the stay cables can be controlled to ensure the stability of the auxiliary pier.
  • Helongkou is within 300mm below the design elevation; the top of the auxiliary pier uses two 200t horizontal longitudinal jacks, 12 500t vertical jacks and four 200t horizontal transverse jacks to realize the linear adjustment of the steel trusses on the top of the pier.
  • the construction process of the auxiliary span closing is as follows: the three single sections Z9 to Z11 on the pier top of the auxiliary pier are erected 30cm below the design elevation in advance and are pre-deviated 3m. When it is close to erection to the closing entrance, the auxiliary pier completes the jack debugging and slider in advance Position adjustment, installation of traction and longitudinal movement equipment and lateral limit installation, and linear re-measurement.
  • the cable-stayed cable tower end of the first floor is hung, and the alignment of the steel truss beam at the cantilever end is finely adjusted according to the monitoring instructions (mainly the pressure on the main span side) to prepare for the auxiliary span closing;
  • the Z9 ⁇ Z11 steel truss beam segments on the top of the pier are 100 first Through 2 sets of 200t longitudinal jacks, the main span is moved 2.9m longitudinally, and then through 12 sets of 500t vertical jacks and 4 sets of 200t transverse jacks to adjust the vertical and lateral deviations.
  • the positions and postures of the steel truss beam segments 100 on both sides of the gantry are consistent.
  • the steel truss beam segments 100 on the top of the pier are moved longitudinally by 0.1m as a whole to realize the docking of the lower chord poles.
  • the lower chord poles are docked, they are then docked in sequence by lifting and lowering the Z9 to Z11 steel truss beam segments 100 and normal tension.
  • the diagonal rod and upper chord rod are finally punched, high bolted and welded in sequence; finally, the steel truss section 100 on the top of the pier is jacked vertically, the top slideway and slider of the padstone are removed, and the steel truss beam on the top of the pier is installed.
  • the truss beam is permanently supported, and the integral lifting jack on the pier top is arranged simultaneously.
  • auxiliary span steel truss girder closing bolt hole alignment in order to eliminate the deformation difference of the steel truss beam segments 100 on both sides of the closing opening caused by the steel truss girder's own weight and the position of the girder erecting crane, the bolts need to be The hole deviation is controlled within 1mm to facilitate the insertion of punching nails.
  • the major sections are arranged according to the cantilever erection process of the steel truss beam.
  • the adjustment device A, the adjustment device B/C and the inclined rod can be arranged on both sides of the closing mouth to adjust the bolt hole deviation.
  • chords when the auxiliary span steel truss girder is closed to the closing position, the chords must be closed according to the following procedures: closing the lower chord (first the center truss and then the side truss), closing the diagonal rod (first the center truss and then the side truss), and closing the upper chord (first the center truss and then the side truss). Construction is carried out in the order of side girders, middle girders, and rear girders.
  • the vertical jack on the bracket next to the pier adjusts the steel truss segment 100 at the Z9 ⁇ Z11 position of the pier top, so that the rod end of the lower chord
  • the axis and inclination angle match the axis and inclination angle of the front-end lower chord of the cantilever steel truss beam, and then the longitudinal movement jack is used to push the pier top steel truss beam segment 100 toward the mid-span direction, and then close the lower chord middle truss and side truss.
  • Helong diagonal bar After the lower chord of the steel truss beam is docked, a 5t inverted chain can be set between the diagonal bar and the vertical bar. After adjusting the axis slope of the diagonal bar, the diagonal bar can be connected. The punching nails are arranged in a plum blossom shape. The total number 10% of the number of bolt holes.
  • the counter-pressure vertical adjustment and pull device can be set to match the rod end axis and inclination of the upper chord with the upper chord axis and inclination of the front end of the cantilevered steel truss beam. Eliminate the bolt hole deviation, insert punching nails in sequence to make the side girders and middle girders of the upper chord rod closed. The punching nails are arranged in a plum blossom shape, and the total number is 10% of the number of bolt holes.
  • the railway bridge deck and the upper chord small longitudinal beams can be butt welded.
  • the load conditions of the auxiliary span steel truss beams on the north and south sides are when they are closed. Basically the same, the construction process is similar.
  • the docking sequence of first lowering the chord, then the inclined rod, and then the upper chord is adopted.
  • measures such as jack counter-pressure, diagonal pulling and axial pulling (top-pull) are adopted to solve the problem of large steel sections.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to the technical field of bridge construction, and provides a construction method for erecting an inter-section whole-section steel truss using a girder erection crane, comprising: moving a girder erection crane to a girder erection position, and preparing a girder; lowering a hoisting mechanism of the girder erection crane and connecting same with a steel truss section; lifting the steel truss section to a preset height, and adjusting an attitude of the hoisting mechanism to enable the center of gravity of the steel truss section and the centroid of the hoisting mechanism to be on the same vertical line; lifting the hoisting mechanism to cause the steel truss section to reach an installation height; adjusting an overhead crane mechanism to cause the steel truss girder section to reach a butt joint position with an erected steel truss girder; installing the steel truss girder section, disconnecting the hoisting mechanism from the steel truss girder section, returning the overhead crane mechanism and locking same, and moving the girder erection crane to a next girder erection position. The present invention can satisfy the requirements for erecting an inter-section whole-section steel truss, and a steel truss section and an erected steel truss form a butt joint more conveniently.

Description

一种运用架梁起重机架设双节间整节段钢桁梁的施工方法A construction method using a girder erecting crane to erect the entire section of double-section steel truss beams 技术领域Technical field
本发明涉及桥梁施工技术领域,具体而言,涉及一种运用架梁起重机架设双节间整节段钢桁梁的施工方法。The invention relates to the technical field of bridge construction, and specifically to a construction method for erecting a double-intersection whole-section steel truss beam using a girder erecting crane.
背景技术Background technique
桥梁施工过程中,整节段吊装法具有现场栓接或焊接的部位少、安装质量可靠以及安装速度快等优点,常用于钢桁梁的安装,整节段吊装法通常采用桥面吊机进行架设。During bridge construction, the whole-segment hoisting method has the advantages of fewer on-site bolting or welding parts, reliable installation quality, and fast installation speed. It is often used for the installation of steel trusses. The whole-segment hoisting method is usually carried out by a bridge deck crane. Erection.
在一些节点项目上,为了尽量减少对于例如航道通航等各种交通的影响,通常面临着施工工期紧、施工任务重的情况,为了进一步减少吊装次数以及现场焊接工作量,提高施工质量,需要采用双节整节段吊装的方式进行施工,双节间整节段钢桁梁的重量通常是单节整节段钢桁梁的两倍以上,现有的桥面吊机架设钢桁梁一般都是采用单节整节段吊装的方式,其起重吊装能力不能满足双节间整节段钢桁梁的架设需求。In some node projects, in order to minimize the impact on various traffic such as waterway navigation, the construction schedule is usually tight and the construction tasks are heavy. In order to further reduce the number of hoisting and on-site welding workload and improve the construction quality, it is necessary to adopt Construction is carried out by hoisting double-section whole sections. The weight of the whole-section steel truss beam between double sections is usually more than twice that of the single whole-section steel truss beam. The existing steel truss beams erected by the existing bridge deck crane are generally It uses a single-section whole-segment hoisting method, and its lifting capacity cannot meet the erection needs of double-segment whole-segment steel truss beams.
发明内容Contents of the invention
本发明解决的问题是如何架设双节间整节段钢桁梁。The problem solved by the invention is how to erect the entire section steel truss beam between double sections.
为解决上述问题,本发明提供一种运用架梁起重机架设双节间整节段钢桁梁的施工方法,包括:In order to solve the above problems, the present invention provides a construction method for erecting a double-section full-section steel truss beam using a girder erecting crane, which includes:
将架梁起重机移动至架梁位置,准备架梁;Move the girder erecting crane to the girder erection position and prepare to erect the girder;
下降所述架梁起重机的吊装机构并与钢桁梁节段连接;Lower the hoisting mechanism of the girder crane and connect it to the steel truss segment;
提升所述钢桁梁节段至预设高度,调整所述吊装机构的姿态使所述钢桁梁节段的重心与所述吊装机构的形心在同一条铅垂线上;Lift the steel truss beam segment to a preset height, and adjust the attitude of the hoisting mechanism so that the center of gravity of the steel truss beam segment and the centroid of the hoisting mechanism are on the same vertical line;
提升所述吊装机构使所述钢桁梁节段到达安装高度;Lift the hoisting mechanism to bring the steel truss beam segments to the installation height;
调整所述架梁起重机的天车机构使所述钢桁梁节段到达与已架设的钢桁梁对接的位置; Adjust the overhead crane mechanism of the girder erecting crane so that the steel truss beam segments reach the position of docking with the erected steel truss beam;
安装所述钢桁梁节段,解除所述吊装机构与所述钢桁梁节段的连接,收回所述天车机构并锁定,所述架梁起重机走行至下一个架梁位置。The steel truss beam segment is installed, the connection between the hoisting mechanism and the steel truss beam segment is released, the overhead crane mechanism is retracted and locked, and the girder erecting crane moves to the next girder erecting position.
进一步地,所述将架梁起重机移动至架梁位置,准备架梁包括:Further, the moving the girder erecting crane to the girder erecting position, and preparing the girder erection includes:
所述架梁起重机的走行机构驱动所述架梁起重机移动至所述架梁位置;The traveling mechanism of the girder erecting crane drives the girder erecting crane to move to the girder erecting position;
将所述架梁起重机的锚固机构与已架设的所述钢桁梁锚固。Anchor the anchoring mechanism of the beam erecting crane with the erected steel truss beam.
进一步地,所述架梁起重机的走行机构驱动所述架梁起重机移动至所述架梁位置包括:Further, the traveling mechanism of the girder erecting crane drives the girder erecting crane to move to the girder erecting position including:
所述走行机构的滑靴油缸向上收缩带动所述走行机构的轨道梁离地;The sliding shoe cylinder of the traveling mechanism contracts upward to drive the track beam of the traveling mechanism off the ground;
将所述走行机构的走行油缸与所述轨道梁的限位孔连接,所述走行油缸收缩带动所述轨道梁向前移动,解除所述走行油缸与所述限位孔的连接,所述走行油缸伸出至下一个所述限位孔处,重复上述操作,直至所述轨道梁移动到位;The traveling oil cylinder of the traveling mechanism is connected to the limit hole of the track beam. The contraction of the traveling oil cylinder drives the track beam to move forward. The connection between the traveling oil cylinder and the limit hole is released. The traveling oil cylinder extends Go out to the next limit hole and repeat the above operations until the track beam moves into place;
所述滑靴油缸向下伸出带动所述轨道梁触地并受力;The sliding shoe cylinder extends downward to drive the track beam to touch the ground and receive force;
将所述走行油缸与所述轨道梁的限位孔连接,所述走行油缸伸出带动所述架梁起重机向前移动,解除所述走行油缸与所述限位孔的连接,所述走行油缸收缩至下一个所述限位孔处,重复上述操作,直至所述架梁起重机移动到位。The traveling oil cylinder is connected to the limit hole of the track beam. The traveling oil cylinder extends to drive the girder crane to move forward, and the connection between the traveling oil cylinder and the limiting hole is released. The traveling oil cylinder Shrink to the next limiting hole and repeat the above operation until the girder crane moves into place.
进一步地,所述天车机构包括大横梁和小横梁,所述大横梁和所述小横梁平行设置并分别与所述架梁起重机的机架滑动连接,且所述大横梁和所述小横梁用于沿所述机架的长度方向滑动,所述吊装机构包括品字形布置的三组吊具,第一组所述吊具设置在所述大横梁的一端,第二组所述吊具设置在所述大横梁的另一端,第三组所述吊具设置在所述小横梁上,所述吊具包括分配梁、吊点滑块和调整油缸,所述吊点滑块通过钢丝绳与所述天车机构活动连接,所述分配梁与所述吊点滑块滑动连接,所述调整油缸的一端与所述分配梁连接,所述调整油缸的另一端与所述吊点滑块连接,所述分配梁用于与所述钢桁梁节段连接。Further, the overhead crane mechanism includes a large beam and a small beam, the large beam and the small beam are arranged in parallel and are respectively slidingly connected to the frame of the girder crane, and the large beam and the small beam are Used to slide along the length direction of the frame, the hoisting mechanism includes three sets of spreaders arranged in a Z-shaped arrangement. The first set of spreaders is arranged at one end of the large beam, and the second set of spreaders is arranged at one end of the large beam. At the other end of the large beam, a third group of the spreaders is arranged on the small beam. The spreaders include a distribution beam, a lifting point slider and an adjustment oil cylinder. The lifting point slider is connected to all the lifting points through a wire rope. The crane mechanism is movably connected, the distribution beam is slidingly connected to the lifting point slider, one end of the adjustment oil cylinder is connected to the distribution beam, and the other end of the adjustment oil cylinder is connected to the suspension point slider, The distribution beam is used to connect with the steel truss beam segments.
进一步地,在所述调整所述吊装机构的姿态使所述钢桁梁节段的重心与所述吊装机构的形心在同一条铅垂线上的过程中,于所述机架的长度方向上, 第一组所述吊具的所述吊点滑块以及第二组所述吊具的所述吊点滑块与第三组所述吊具的所述吊点滑块之间的间距等于所述大横梁与所述小横梁之间的间距。Further, during the process of adjusting the posture of the hoisting mechanism so that the center of gravity of the steel truss segment and the centroid of the hoisting mechanism are on the same vertical line, in the length direction of the frame superior, The distance between the lifting point slide blocks of the first group of the spreaders, the suspension point slide blocks of the second group of the spreaders and the hanging point slide blocks of the third group of the spreaders is equal to The distance between the large beam and the small beam.
进一步地,在所述提升所述吊装机构使所述钢桁梁节段到达安装高度的过程中,三组所述吊具以预设速度同步提升。Further, during the process of lifting the hoisting mechanism so that the steel truss beam segments reach the installation height, three groups of the hoisting tools are lifted simultaneously at a preset speed.
进一步地,在所述将架梁起重机移动至架梁位置,准备架梁之后,所述下降所述架梁起重机的吊装机构之前,该施工方法还包括:Further, after moving the girder erecting crane to the girder erecting position and preparing the girder erection, and before lowering the hoisting mechanism of the girder erecting crane, the construction method also includes:
调整所述天车机构,使所述吊装机构正对待架设的所述钢桁梁节段。Adjust the overhead crane mechanism so that the hoisting mechanism is facing the steel truss beam segment to be erected.
进一步地,在所述调整所述架梁起重机的天车机构使所述钢桁梁节段到达与已架设的钢桁梁对接的位置之后,安装所述钢桁梁节段之前,该施工方法还包括:Further, after the crown crane mechanism of the girder erecting crane is adjusted so that the steel truss beam segments reach the position of docking with the erected steel truss beams, and before the steel truss beam segments are installed, the construction method Also includes:
调整所述钢桁梁节段的纵坡。Adjust the longitudinal slope of the steel truss segment.
进一步地,所述调整所述钢桁梁节段的纵坡包括:Further, the adjustment of the longitudinal slope of the steel truss beam segment includes:
调整三组所述吊具的所述调整油缸使所述钢桁梁节段倾斜至预设纵倾角度;Adjust the adjustment cylinders of the three sets of spreaders to tilt the steel truss beam segments to a preset trim angle;
整体提升或下降所述吊装机构使所述钢桁梁节段的后端面与已架设的所述钢桁梁的前端面对齐。Lift or lower the hoisting mechanism as a whole to align the rear end surface of the steel truss beam segment with the front end surface of the erected steel truss beam.
进一步地,当架设至合龙口时,该施工方法还包括将所述钢桁梁节段与对向已架设的所述钢桁梁合龙,所述将所述钢桁梁节段与对向已架设的所述钢桁梁合龙包括依次合龙所述钢桁梁节段的下弦杆、斜杆和上弦杆,其中,合龙所述下弦杆包括依次合龙中桁下弦杆和边桁下弦杆,合龙所述斜杆包括依次合龙中桁斜杆和边桁斜杆,合龙所述上弦杆包括依次合龙边桁上弦杆和中桁上弦杆。Further, when erecting to the closing port, the construction method also includes closing the steel truss beam segments with the opposite erected steel truss beams, and closing the steel truss beam segments with the opposite erected steel truss beams. The erected steel truss beams include the lower chords, diagonal bars and upper chords of the steel truss beam segments, wherein the lower chords include the middle truss lower chords and side truss lower chords, which are connected in sequence. The diagonal rods include the diagonal rods of the middle truss and the diagonal rods of the side girders, and the upper chord rods include the upper chord rods of the side girders and the upper chord rods of the middle girders.
本发明与现有技术相比,具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
架梁起重机在架设钢桁梁节段的过程中,先将钢桁梁节段提升至预设高度使钢桁梁节段处于悬空状态,通过对吊装机构的三个吊具的姿态进行调整使钢桁梁节段的重心与吊装机构的形心在一条铅垂线上,从而能够将钢桁梁 节段的重量均匀分布在三个吊具上,可以最大程度地利用每个吊具的吊装能力,提升架梁起重机的起重能力,能够满足架设双节间整节段钢桁梁的要求。In the process of erecting the steel truss beam segment, the girder erecting crane first lifts the steel truss beam segment to the preset height so that the steel truss beam segment is in a suspended state, and then adjusts the posture of the three spreaders of the hoisting mechanism. The center of gravity of the steel truss beam segment and the centroid of the hoisting mechanism are on a vertical line, so that the steel truss beam can be The weight of the segment is evenly distributed on the three spreaders, which can maximize the hoisting capacity of each spreader and improve the lifting capacity of the girder crane, which can meet the requirements for erecting the entire segment steel truss beam between double sections.
同时,由于钢桁梁节段的重心与吊装机构的形心始终维持在同一条铅垂线上,使得钢桁梁节段在整个吊装过程中能够保持平稳上升,钢桁梁节段吊装的安全性更高,在天车结构将钢桁梁节段移动至与已架设的钢桁梁对接的位置时,钢桁梁节段的后端面与已架设的钢桁梁的前端面的重合度更高,从而使得对接更加方便。At the same time, since the center of gravity of the steel truss beam segments and the centroid of the hoisting mechanism are always maintained on the same vertical line, the steel truss beam segments can maintain a stable rise during the entire hoisting process, and the safety of the steel truss beam segment hoisting is ensured. When the crane structure moves the steel truss beam segment to the position where it docks with the erected steel truss beam, the coincidence degree between the rear end face of the steel truss beam segment and the front end face of the erected steel truss beam is higher. high, making docking more convenient.
附图说明Description of drawings
图1为本发明实施例中架梁起重机的结构示意图;Figure 1 is a schematic structural diagram of a girder crane in an embodiment of the present invention;
图2为本发明实施例图1中A处的放大图;Figure 2 is an enlarged view of position A in Figure 1 according to the embodiment of the present invention;
图3为本发明实施例图1中B处的放大图;Figure 3 is an enlarged view of B in Figure 1 according to the embodiment of the present invention;
图4为本发明实施例中架梁起重机另一视角的结构示意图;Figure 4 is a schematic structural diagram of the girder erecting crane from another perspective according to the embodiment of the present invention;
图5为本发明实施例中架梁起重机又一视角的结构示意图;Figure 5 is a schematic structural diagram of the girder erecting crane from another perspective according to the embodiment of the present invention;
图6为本发明实施例中S100的状态示意图;Figure 6 is a schematic diagram of the state of S100 in the embodiment of the present invention;
图7为本发明实施例中S200的状态示意图;Figure 7 is a schematic diagram of the state of S200 in the embodiment of the present invention;
图8为本发明实施例中S300至S400的状态示意图;Figure 8 is a schematic diagram of the states from S300 to S400 in the embodiment of the present invention;
图9为本发明实施例中S500至S600的状态示意图;Figure 9 is a schematic diagram of the states from S500 to S600 in the embodiment of the present invention;
图10为本发明实施例中S700至S800的状态示意图;Figure 10 is a schematic diagram of the states from S700 to S800 in the embodiment of the present invention;
图11为本发明实施例中S800的状态示意图。Figure 11 is a schematic diagram of the state of S800 in the embodiment of the present invention.
附图标记说明:
1、吊装机构;11、吊具;111、分配梁;112、吊点滑块;113、调整油
缸;2、天车机构;21、大横梁;22、小横梁;3、走行机构;31、轨道梁;311、限位孔;32、走行油缸;33、滑靴油缸;4、锚固机构;5、机架;100、钢桁梁节段;200、钢桁梁。
Explanation of reference symbols:
1. Hoisting mechanism; 11. Spreader; 111. Distribution beam; 112. Lifting point slider; 113. Adjustment cylinder; 2. Crown crane mechanism; 21. Large beam; 22. Small beam; 3. Traveling mechanism; 31. Track beam; 311, limit hole; 32, traveling cylinder; 33, sliding shoe cylinder; 4, anchoring mechanism; 5, frame; 100, steel truss beam segment; 200, steel truss beam.
具体实施方式Detailed ways
为使本发明的上述目的、特征和优点能够更为明显易懂,下面结合附图对本发明的具体实施例做详细的说明。In order to make the above objects, features and advantages of the present invention more obvious and understandable, specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
在本发明的描述中,需要理解的是,附图中“X”的正向代表左方,相应地,“X”的反向代表右方、“Y”的正向代表前方,相应地,“Y”的反向代表后方、“Z”的正向代表上方,相应地,“Z”的反向代表下方,术语“X”、“Y”、“Z”等指示的方位或位置关系为基于说明书附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the forward direction of "X" in the drawings represents the left direction, correspondingly, the reverse direction of "X" represents the right direction, and the forward direction of "Y" represents the front direction. Correspondingly, The reverse direction of "Y" represents the rear, and the forward direction of "Z" represents the top. Correspondingly, the reverse direction of "Z" represents the bottom. The orientation or positional relationship indicated by the terms "X", "Y", "Z", etc. is: The orientations or positional relationships shown in the drawings based on the specification are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot It should be understood as a limitation of the present invention.
术语“第一”、“第二”和“第三”等仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。而且,描述的具体特征、结构、材料或特点可以在任何的一个或多个实施例或示例中以合适的方式结合。The terms “first”, “second”, “third”, etc. are used for descriptive purposes only and shall not be understood as indicating or implying relative importance or implicitly indicating the quantity of indicated technical features. Furthermore, the specific features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
为解决上述问题,本发明的实施例提供一种运用架梁起重机架设双节间整节段钢桁梁的施工方法,包括:In order to solve the above problems, embodiments of the present invention provide a construction method for erecting a double-section full-section steel truss beam using a girder erecting crane, which includes:
S100、将架梁起重机移动至架梁位置,准备架梁;S100. Move the girder erecting crane to the girder erecting position and prepare to erect the girder;
如图1至图5所示,本实施例中,架梁起重机由机架5、支撑机构、走行机构3、锚固机构4、起升机构、天车机构2以及吊装机构1等部分组成。As shown in Figures 1 to 5, in this embodiment, the girder crane is composed of a frame 5, a support mechanism, a traveling mechanism 3, an anchoring mechanism 4, a lifting mechanism, a crane mechanism 2 and a hoisting mechanism 1.
其中,机架5由底前横梁、下主梁、后锚梁、上前横梁、上主梁、上后横梁、立柱、前撑杆、后拉杆以及多个连接系等杆件采用高强度螺栓或销轴连接而成,其中,位于左右两侧的下主梁、上主梁、前撑杆以及后拉杆分别组成菱形左边桁架和菱形右边桁架,位于中间的两套下主梁、上主梁、前撑杆以及后拉杆分别组成菱形左中桁架和菱形右中桁架,左中桁架与右中桁架之间留有一定间距,便于收纳吊装机构1的第二组吊具11以及方便连接钢桁梁200与桥塔的拉索穿过,中桁架与边桁架的结构形式类似,不同之处在于中桁架采用的杆件截面略小。Among them, the frame 5 is composed of a bottom front beam, a lower main beam, a rear anchor beam, an upper front beam, an upper main beam, an upper rear beam, a column, a front support rod, a rear tie rod, and multiple connecting systems using high-strength bolts. Or it is connected by pins. Among them, the lower main beam, upper main beam, front support rod and rear tie rod located on the left and right sides respectively form a diamond-shaped left truss and a diamond-shaped right truss. The two sets of lower main beams and upper main beams located in the middle , the front support rod and the rear tie rod respectively form a diamond-shaped left middle truss and a diamond-shaped right middle truss. There is a certain distance between the left middle truss and the right middle truss to facilitate the storage of the second set of spreaders 11 of the hoisting mechanism 1 and the convenient connection of the steel trusses. The beam 200 passes through the cables of the bridge tower. The structural forms of the middle truss and the side truss are similar, except that the cross-section of the rod used in the middle truss is slightly smaller.
具体地,如图6所示,在将架梁起重机移动至架梁位置,准备架梁的过 程可按以下步骤实施:Specifically, as shown in Figure 6, after moving the girder erecting crane to the girder erecting position, the process of preparing the girder erecting The process can be implemented as follows:
S110、架梁起重机的走行机构3驱动架梁起重机移动至架梁位置;S110. The traveling mechanism 3 of the girder erecting crane drives the girder erecting crane to move to the girder erecting position;
如图1、图2和图4所示,本实施例中,走行机构3设置在机架5的底部,从左至右依次设有四组,分别设置在与机架5的左边桁架、左中桁架、右中桁架以及右边桁架相对应的位置处,每组走行机构3均包括前后两套走行组件,每组走行组件均由轨道梁31、走行滑靴、走行油缸32以及顶推支座组成,其中,走行滑靴由连接座、滑靴油缸33以及滑套组成,连接座与机架5固定连接,滑套与轨道梁31滑动连接,滑靴油缸33设置在连接座与滑套之间并能上下伸缩,走行油缸32的一端通过顶推支座与轨道梁31可拆卸连接,走行油缸32的另一端与走行滑靴的滑套连接,轨道梁31上设有多组限位孔311用于与顶推支座可拆卸连接。As shown in Figure 1, Figure 2 and Figure 4, in this embodiment, the traveling mechanism 3 is arranged at the bottom of the frame 5, and four groups are provided from left to right, which are respectively arranged on the left truss and left side of the frame 5. At the corresponding positions of the middle truss, the middle right truss and the right truss, each group of traveling mechanisms 3 includes two sets of front and rear traveling components. Each group of traveling components consists of track beams 31, traveling sliding shoes, traveling cylinders 32 and push supports. The traveling sliding shoe is composed of a connecting seat, a sliding shoe cylinder 33 and a sliding sleeve. The connecting seat is fixedly connected to the frame 5, the sliding sleeve is slidingly connected to the track beam 31, and the sliding shoe cylinder 33 is arranged between the connecting seat and the sliding sleeve. It can telescope up and down. One end of the traveling oil cylinder 32 is detachably connected to the track beam 31 through a push support. The other end of the traveling oil cylinder 32 is connected to the sliding sleeve of the traveling sliding shoe. The track beam 31 is provided with multiple sets of limit holes. 311 is used for detachable connection with the push support.
具体地,走行机构3驱动架梁起重机移动的过程如下:Specifically, the process of the traveling mechanism 3 driving the girder crane to move is as follows:
S111、走行机构3的滑靴油缸33向上收缩带动走行机构3的轨道梁31离地;S111. The sliding shoe cylinder 33 of the traveling mechanism 3 contracts upward to drive the track beam 31 of the traveling mechanism 3 to lift off the ground;
在此过程中,架梁起重机的机架5需由支撑机构进行支撑,其中,支撑机构由左前支腿、中前支腿、右前支腿和四个后支腿组成,左前支腿和右前支腿分别设置在底前横梁的左右两端,中前支腿设置在底前横梁的中部,并位于左中桁架与右中桁架之间,四个后支腿沿机架5的宽度方向均匀分布在底前横梁与后锚梁之间的底部连接横梁上,其中,左前支腿、右前支腿以及四个后支腿均采用调节螺杆式刚性支腿,中前支腿采用恒压柔性支腿。During this process, the frame 5 of the girder crane needs to be supported by a support mechanism. The support mechanism consists of a left front outrigger, a middle front outrigger, a right front outrigger and four rear outriggers. The left front outrigger and right front outrigger The legs are respectively set at the left and right ends of the bottom front beam, the middle front leg is set in the middle of the bottom front beam, and is located between the left middle truss and the right middle truss. The four rear legs are evenly distributed along the width direction of the frame 5 On the bottom connecting beam between the bottom front beam and the rear anchor beam, the left front leg, right front leg and four rear legs all use adjustable screw rigid legs, and the middle front leg uses constant pressure flexible legs .
示例性地,左前支腿、右前支腿的支撑力可设计为1400t,四个后支腿支撑力可设计为100t,中前支腿可配备一台2000t级的恒压油缸来控制中桁支反力。For example, the support force of the left front outrigger and right front outrigger can be designed to be 1400t, the support force of the four rear outriggers can be designed to be 100t, and the middle front outrigger can be equipped with a 2000t level constant pressure cylinder to control the middle truss support. Reaction force.
需要说明的是,支撑机构通过左前支腿和右前支腿采用刚性支承,中前支腿采用恒压柔性支腿,能够满足在任意工况下均保持中前支腿所承受的压力为总反力的三分之一,而架梁起重机又是左右对称的结构,因此剩下的三分之二的总反力会被左前支腿和右前支腿自动均摊,因此,能够最大限度的降低架梁起重机对所站位的钢桁梁200的局部载荷,从而能够最大限度地利用所站位的钢桁梁200的承载能力架设更大重量的钢桁梁节段100。 It should be noted that the support mechanism uses rigid support through the left front outrigger and right front outrigger, and the middle front outrigger uses constant pressure flexible outriggers, which can maintain the pressure on the middle front outrigger as the total reaction under any working conditions. One-third of the force, and the girder crane has a symmetrical structure, so the remaining two-thirds of the total reaction force will be automatically shared evenly by the left front leg and the right front leg. Therefore, the girder crane can be lowered to the maximum extent. The beam crane exerts a local load on the steel truss beam 200 at which it is located, so that the bearing capacity of the steel truss beam 200 at which it is located can be utilized to the maximum extent to erect a steel truss beam segment 100 of greater weight.
其中,如图1所示,机架5的宽度方向是指X轴方向。As shown in FIG. 1 , the width direction of the frame 5 refers to the X-axis direction.
S112、将走行机构3的走行油缸32与轨道梁31的限位孔311连接,走行油缸32收缩带动轨道梁31向前移动,解除走行油缸32与限位孔311的连接,走行油缸32伸出至下一个限位孔311处,重复上述操作,直至轨道梁31移动到位;S112. Connect the traveling oil cylinder 32 of the traveling mechanism 3 to the limit hole 311 of the track beam 31. The traveling oil cylinder 32 contracts to drive the track beam 31 to move forward. The connection between the traveling oil cylinder 32 and the limit hole 311 is released, and the traveling oil cylinder 32 extends out. Go to the next limit hole 311 and repeat the above operation until the track beam 31 moves into place;
需要说明的是,为了保证走行的稳定和安全,四组走行机构3的四条轨道梁31需按上述步骤同步进行操作,并且走行速度需精确控制,通常情况下,走行额定速度设置为1m/min,走行机构的工作级别为M4。It should be noted that in order to ensure the stability and safety of traveling, the four track beams 31 of the four sets of traveling mechanisms 3 need to be operated synchronously according to the above steps, and the traveling speed needs to be accurately controlled. Normally, the rated traveling speed is set to 1m/min. , the working level of the traveling mechanism is M4.
S113、滑靴油缸33向下伸出带动轨道梁31触地并受力;S113. The sliding shoe cylinder 33 extends downward to drive the track beam 31 to touch the ground and receive force;
需要说明的是,滑靴油缸33向下伸出的长度需足以使支撑机构的各个支腿处于离地状态,架梁起重机由支撑机构进行支撑的状态转换到由四根轨道梁31进行支撑的状态。It should be noted that the length of the sliding shoe cylinder 33 extending downward must be sufficient to make each leg of the support mechanism in an off-the-ground state, and the beam erecting crane is converted from a state supported by the support mechanism to a state supported by the four track beams 31. state.
另外,为了方便移动轨道梁31,无需更多的人工参与,从而节省人工成本,提高施工效率,本实施例中,由于架梁起重机本身具有较大的自重,因此,可在轨道梁31的底部加装摩擦系数较大的支垫,在轨道梁31触地并受力后,利用轨道梁31与已架设的钢桁梁200之间的静摩擦力即可做到在后续移动架梁起重机时轨道梁31处于静止不动的状态,而无需采用螺栓或焊接等方式将轨道梁31临时固定在已架设的钢桁梁200上。In addition, in order to facilitate the movement of the track beam 31 without more manual participation, thereby saving labor costs and improving construction efficiency, in this embodiment, since the beam erecting crane itself has a large dead weight, it can be placed at the bottom of the track beam 31 Install a support pad with a larger friction coefficient. After the track beam 31 touches the ground and is stressed, the static friction between the track beam 31 and the erected steel truss beam 200 can be used to ensure that the track is moved when the girder erecting crane is subsequently moved. The beam 31 is in a stationary state, and there is no need to temporarily fix the track beam 31 to the erected steel truss beam 200 by means of bolts or welding.
S114、将走行油缸32与轨道梁31的限位孔311连接,走行油缸32伸出带动架梁起重机向前移动,解除走行油缸32与限位孔311的连接,走行油缸32收缩至下一个限位孔311处,重复上述操作,直至架梁起重机移动到位。S114. Connect the traveling oil cylinder 32 to the limit hole 311 of the track beam 31. The traveling oil cylinder 32 extends to drive the girder crane to move forward. The connection between the traveling oil cylinder 32 and the limit hole 311 is released. The traveling oil cylinder 32 contracts to the next limit. At position hole 311, repeat the above operation until the girder crane moves into position.
需要说明的是,在向前移动架梁起重机的过程中,由于已架设的钢桁梁200上还设有用于连接桥索的锚箱,为了避免支撑机构以及锚固机构4等与锚箱发生干涉,还需将支撑机构的前支腿以及锚固机构4进行翻转。It should be noted that during the process of moving the girder erecting crane forward, since the erected steel truss 200 is also provided with an anchor box for connecting the bridge cables, in order to avoid interference between the support mechanism and the anchoring mechanism 4 and the anchor box , it is also necessary to turn over the front legs of the support mechanism and the anchoring mechanism 4.
其中,支撑机构的前支腿设置了翻转油缸以及相应的连杆结构,使用时,只需将油缸缩回,则可实现前支腿的自动翻转,避开已架设的钢桁梁200的锚箱;而锚固机构4的左右两侧锚固拉杆组件同样也设置了翻转油缸,在整 机移动时向外翻转即可。Among them, the front leg of the support mechanism is equipped with a flip cylinder and a corresponding connecting rod structure. When in use, just retract the oil cylinder to realize automatic flip of the front leg, avoiding the anchor of the erected steel truss beam 200 box; and the anchoring tie rod assemblies on the left and right sides of the anchoring mechanism 4 are also equipped with flipping cylinders. Just flip it outward when the machine is moving.
进一步地,由于架梁起重机的机架5整体为菱形结构,当架梁起重机的前端吊梁时,为了提高架梁起重机的稳定性,防止在架设钢桁梁节段100的过程中倾覆,在走行机构3驱动架梁起重机移动到位后,还需实施以下步骤:Furthermore, since the frame 5 of the girder crane has a diamond-shaped structure as a whole, when the front end of the girder crane is hoisting the beam, in order to improve the stability of the girder crane and prevent overturning during the erection of the steel truss segment 100, After the traveling mechanism 3 drives the girder crane to move into place, the following steps need to be implemented:
S120、将架梁起重机的锚固机构4与已架设的钢桁梁200锚固。S120. Anchor the anchoring mechanism 4 of the girder erecting crane with the erected steel truss beam 200.
具体地,如图1所示,锚固机构4由四组螺栓式锚固拉杆组件组成,每组锚固拉杆组件均由螺杆、分配梁111以及拉板等部分组成,四组锚固拉杆组件分别设置在机架5的后锚梁底部与左边桁架、左中桁架、右中桁架以及右边桁架相对应的位置处,后锚梁与锚固耳座之间通过后锚拉杆或螺栓连接,此种结构的锚固拉杆组件受力明确,安全可靠,且能够很方便地调节后锚固的高度。Specifically, as shown in Figure 1, the anchoring mechanism 4 is composed of four sets of bolt-type anchor tie rod assemblies. Each set of anchor tie rod assemblies is composed of screw rods, distribution beams 111, tie plates and other parts. The four sets of anchor tie rod assemblies are respectively arranged on the machine. At the positions corresponding to the bottom of the rear anchor beam of frame 5 and the left truss, left middle truss, right middle truss and right truss, the rear anchor beam and the anchor ear seat are connected through rear anchor tie rods or bolts. The anchor tie rods of this structure The components are clearly stressed, safe and reliable, and the height of the rear anchor can be easily adjusted.
S300、下降架梁起重机的吊装机构1并与钢桁梁节段100连接;S300, lower the hoisting mechanism 1 of the girder crane and connect it with the steel truss segment 100;
具体地,如图1、图5、图7和图8所示,架梁起重机的机架5底部后侧还设有卷扬机组,卷扬机组的钢丝绳通过天车机构2与吊装结构连接,卷扬机组通过收放钢丝绳即可对吊装机构1进行提升或下降,下降过程为空载状态,吊装机构1的下降速度可控制在0至3.6m/min,吊装机构1下降到位后可通过在吊具11上安装吊杆等结构与钢桁梁节段100的吊耳连接。Specifically, as shown in Figures 1, 5, 7 and 8, the bottom rear side of the frame 5 of the girder crane is also equipped with a winch unit. The wire rope of the winch unit is connected to the hoisting structure through the crane mechanism 2. The winch unit The hoisting mechanism 1 can be raised or lowered by retracting and releasing the wire rope. The descending process is in an unloaded state. The descending speed of the hoisting mechanism 1 can be controlled between 0 and 3.6m/min. After the hoisting mechanism 1 is lowered in place, it can pass through the hoisting tool 11 Structures such as upper mounting booms are connected to the lifting lugs of the steel truss beam segments 100 .
S400、提升钢桁梁节段100至预设高度,调整吊装机构1的姿态使钢桁梁节段100的重心与吊装机构1的形心在同一条铅垂线上;S400. Lift the steel truss beam segment 100 to the preset height, and adjust the posture of the hoisting mechanism 1 so that the center of gravity of the steel truss beam segment 100 and the centroid of the hoisting mechanism 1 are on the same vertical line;
需要说明的是,吊装机构1的形心是指每组吊具11的几何中心的连线所组成的三角形的几何中心,如图8所示,铅垂线是指Z轴方向所在的直线。It should be noted that the centroid of the hoisting mechanism 1 refers to the geometric center of the triangle formed by the lines connecting the geometric centers of each group of hoists 11. As shown in Figure 8, the plumb line refers to the straight line in the Z-axis direction.
需要说明的是,为了保证吊装安全,预设高度不宜设置过高,通常以将钢桁架节段吊起至悬空状态且具有一定的调整空间为宜。It should be noted that in order to ensure the safety of hoisting, the preset height should not be set too high. It is usually appropriate to hoist the steel truss segments to a suspended state with a certain amount of adjustment space.
示例性地,以在新建上海至南通铁路沪通长江大桥上架设1800t双节间整节段钢桁梁为例进行示例性说明,该桥梁为长江主航道上的双塔三索面布置的斜拉桥,为了不影响长江航道的通航,双节段钢桁梁200在南通如皋制造基地滚装上船,由驳船转运至江面上架梁起重机的下方,在进行吊装时, 吊装机构1到位后将三组吊具11与钢桁梁节段100相连,吊装机构1将钢桁梁节段100提升至脱离船体300mm的高度处,此时,既能为钢桁梁节段100以及船体的晃动提供足够的空间,保证钢桁梁节段100处于完全的悬空状态,方便调整吊具11的姿态,又能保证吊装的安全。As an example, take the erection of an 1800t double-intersection whole-segment steel truss beam on the newly built Shanghai-Nantong Railway Hutong Yangtze River Bridge as an example. The bridge is an inclined tower with three cable planes arranged on the main channel of the Yangtze River. To pull the bridge, in order not to affect the navigation of the Yangtze River waterway, the double-segment steel truss girder 200 was rolled onto the ship at the Nantong Rugao manufacturing base, and was transferred by barge to the bottom of the girder crane on the river. During hoisting, After the hoisting mechanism 1 is in place, connect the three sets of spreaders 11 to the steel truss beam segments 100. The hoisting mechanism 1 lifts the steel truss beam segments 100 to a height of 300mm away from the hull. At this time, it can be the steel truss beam segment. 100 and the shaking of the hull provide enough space to ensure that the steel truss beam segment 100 is in a completely suspended state, making it easy to adjust the posture of the spreader 11 and ensuring the safety of the hoisting.
S500、提升吊装机构1使钢桁梁节段100到达安装高度;S500. Lift the hoisting mechanism 1 so that the steel truss segment 100 reaches the installation height;
具体地,如图9所示,提升吊装机构1的操作与上述下降吊装机构1的操作相反,在此不再赘述,不同之处在于,提升操作的过程为重载状态,提升速度应控制在0至1.8m/min。Specifically, as shown in Figure 9, the operation of the lifting and hoisting mechanism 1 is opposite to the operation of the above-mentioned lowering and hoisting mechanism 1, which will not be described in detail here. The difference is that the process of the lifting operation is a heavy load state, and the lifting speed should be controlled at 0 to 1.8m/min.
S600、调整架梁起重机的天车机构2使钢桁梁节段100到达与已架设的钢桁梁200对接的位置;S600. Adjust the overhead crane mechanism 2 of the girder erecting crane so that the steel truss beam segment 100 reaches the position of docking with the erected steel truss beam 200;
需要说明的是,在吊装机构1提升钢桁梁节段100的过程中,为了避免钢桁梁节段100与已架设的钢桁梁200发生碰撞,保证施工过程的安全性,钢桁梁节段100的后端面与已架设的钢桁梁200的前端面之间需保持一定的错位,示例性地,在沪通长江大桥上架设长度为28m,重量为1800t的双节间整节段钢桁梁时,需保持200mm的错位。It should be noted that when the hoisting mechanism 1 lifts the steel truss beam section 100, in order to avoid the steel truss beam section 100 colliding with the erected steel truss beam 200 and ensure the safety of the construction process, the steel truss beam section A certain misalignment needs to be maintained between the rear end face of the section 100 and the front end face of the erected steel truss 200. For example, a double-intersection whole-segment steel section with a length of 28m and a weight of 1800t is erected on the Hutong Yangtze River Bridge. When installing trusses, a 200mm misalignment needs to be maintained.
具体地,如图1、图5、图9和图10所示,天车机构2通过设置在机架5上主梁上的纵移油缸驱动其沿机架5的长度方向移动,从而将吊装机构1以及钢桁梁节段100整体平移至与已架设的钢桁梁200对接的位置。Specifically, as shown in Figures 1, 5, 9 and 10, the crane mechanism 2 drives it to move along the length direction of the frame 5 through the longitudinal oil cylinder provided on the main beam of the frame 5, thereby hoisting the The mechanism 1 and the steel truss beam segment 100 are translated as a whole to a position where they are docked with the erected steel truss beam 200 .
其中,如图1所示,机架5的长度方向是指Y轴方向。Among them, as shown in Figure 1, the length direction of the frame 5 refers to the Y-axis direction.
S800、安装钢桁梁节段100,解除吊装机构1与钢桁梁节段100的连接,收回天车机构2并锁定,架梁起重机走行至下一个架梁位置,重复上述操作。S800. Install the steel truss beam segment 100, release the connection between the hoisting mechanism 1 and the steel truss beam segment 100, retract the crane mechanism 2 and lock it, move the girder erecting crane to the next girder erecting position, and repeat the above operations.
具体地,如图10和图11所示,钢桁梁节段100到位后,可将从桥塔上放下的拉索与钢桁梁节段100上的锚箱连接,然后采用焊接或螺栓连接等方式将其与已架设的钢桁梁200连接固定,再解除解除吊装机构1与钢桁架节段的连接,收回天车机构2并锁定使架梁起重机的重心后移,做好准备工作后即可走行至下一架梁位置进行后续的架梁施工。Specifically, as shown in Figures 10 and 11, after the steel truss girder section 100 is in place, the stay cables dropped from the bridge tower can be connected to the anchor boxes on the steel truss girder section 100, and then connected by welding or bolting. Connect and fix it with the erected steel truss beam 200 in other ways, then release the connection between the hoisting mechanism 1 and the steel truss segment, retract the crane mechanism 2 and lock it to move the center of gravity of the girder erecting crane backward. After making preparations You can then walk to the next beam erection position for subsequent beam erection construction.
进一步地,天车机构2包括大横梁21和小横梁22,大横梁21和小横梁22平行设置并分别与架梁起重机的机架5滑动连接,且大横梁21和小横 梁22用于沿机架5的长度方向滑动,吊装机构1包括品字形布置的三组吊具11,第一组吊具11设置在大横梁21的一端,第二组吊具11设置在大横梁21的另一端,第三组吊具11设置在小横梁22上,吊具11包括分配梁111、吊点滑块112和调整油缸113,吊点滑块112通过钢丝绳与天车机构2活动连接,分配梁111与吊点滑块112滑动连接,调整油缸113的一端与分配梁111连接,调整油缸113的另一端与吊点滑块112连接,分配梁111用于与钢桁梁节段100连接。Further, the crane mechanism 2 includes a large beam 21 and a small beam 22. The large beam 21 and the small beam 22 are arranged in parallel and are respectively slidingly connected to the frame 5 of the girder crane, and the large beam 21 and the small beam 22 are arranged in parallel. The beam 22 is used to slide along the length direction of the frame 5. The hoisting mechanism 1 includes three sets of spreaders 11 arranged in a Z-shaped arrangement. The first set of spreaders 11 is arranged at one end of the large beam 21, and the second set of spreaders 11 is arranged at the large beam 21. At the other end of the beam 21, the third group of spreaders 11 is set on the small beam 22. The spreader 11 includes a distribution beam 111, a lifting point slider 112 and an adjustment cylinder 113. The lifting point slider 112 moves with the crane mechanism 2 through a wire rope. connection, the distribution beam 111 is slidingly connected to the lifting point slider 112, one end of the adjustment cylinder 113 is connected to the distribution beam 111, the other end of the adjustment cylinder 113 is connected to the lifting point slider 112, the distribution beam 111 is used to connect with the steel truss beam section 100 connections.
如图1、图3、图4和图5所示,本实施例中,大横梁21的左右两端分别与机架5的左侧上主梁以及右侧上主梁滑动连接,小横梁22的左右两端分别与左中上主梁以及右中上主梁滑动连接,并且两者与承载各自的上主梁之间均设有一组纵移油缸用于驱动大横梁21以及小横梁22纵移。As shown in Figures 1, 3, 4 and 5, in this embodiment, the left and right ends of the large cross beam 21 are slidingly connected to the left upper main beam and the right upper main beam of the frame 5 respectively, and the small cross beam 22 The left and right ends are slidingly connected to the upper middle main beam on the left and the upper main beam on the right respectively, and a set of longitudinal oil cylinders are provided between the two and the upper main beams carrying their respective parts to drive the large cross beam 21 and the small cross beam 22 longitudinally. shift.
需要说明的是,大横梁21和小横梁22一前一后布置,既可以大横梁21在前,小横梁22在后,也可根据需要将大横梁21布置在后,小横梁22布置在前,在此不做限制。It should be noted that the large crossbeam 21 and the small crossbeam 22 are arranged one behind the other. The large crossbeam 21 can be in the front and the small crossbeam 22 can be in the back. Alternatively, the large crossbeam 21 can be arranged in the back and the small crossbeam 22 can be arranged in the front as needed. , there is no restriction here.
优选地,本实施例中,可将小横梁22布置在后,这样方便将中间的第三组吊具11收纳在左中桁架以及右中桁架之间的空间更深一些的位置处,使得整机行走时重心更靠后一些,安全性更高。Preferably, in this embodiment, the small beam 22 can be arranged at the rear, so that the third group of spreaders 11 in the middle can be easily stored in a deeper position in the space between the left middle truss and the right middle truss, making the whole machine more compact. When walking, the center of gravity is further back, which is safer.
吊具11的分配梁111沿机架5的长度方向设置,其前后两端设有吊孔,吊孔的位置与钢桁梁节段100的吊耳位置相匹配,可穿设吊杆与钢桁梁节段100的吊耳连接,吊点滑块112采用截面形状为C形的框架,分配梁111上设有滑道和沿长度方向的多个卡槽,C形框架套装在分配梁111的滑动上,调整油缸113的一端与分配梁111的连接,调整油缸113的另一端与C形框架连接,C形框架的上部设有耳板可与设置在钢丝绳上的动滑轮铰接,当调整油缸113伸缩时可带动C形框架在分配梁111的滑道上滑动,当滑动至合适位置时,可通过锁紧结构将C形框架锁定在分配梁111上的某一卡槽的位置处,当需要再次调整吊点位置时,可将锁紧结构解锁,调整油缸113再次带动C形框架在分配梁111的滑道上滑动。The distribution beam 111 of the spreader 11 is arranged along the length direction of the frame 5, and its front and rear ends are provided with lifting holes. The positions of the lifting holes match the positions of the lifting lugs of the steel truss beam segments 100, and the suspension rods and steel beams can be inserted. The lifting lugs of the truss beam segments 100 are connected. The lifting point slider 112 adopts a frame with a C-shaped cross-section. The distribution beam 111 is provided with slideways and multiple slots along the length direction. The C-shaped frame is set on the distribution beam 111 On the sliding movement, one end of the adjusting cylinder 113 is connected to the distribution beam 111, and the other end of the adjusting cylinder 113 is connected to the C-shaped frame. The upper part of the C-shaped frame is provided with an ear plate that can be hinged with the movable pulley provided on the wire rope. When the adjusting cylinder When 113 telescopes, it can drive the C-shaped frame to slide on the slide of the distribution beam 111. When it slides to the appropriate position, the C-shaped frame can be locked at a certain slot on the distribution beam 111 through the locking structure. When needed, When the position of the hanging point is adjusted again, the locking structure can be unlocked, and the adjustment cylinder 113 drives the C-shaped frame to slide on the slide of the distribution beam 111 again.
需要说明的是,在吊装机构1下降的过程中,为了保持分配梁111的平衡,C形框架通常是位于分配梁111的重心铅垂线上,而在吊装过程中,由 于吊装机构1的形心与钢桁梁节段100的重心始终是在同一铅垂线上,因此,在调整C形框架的位置时,分配梁111并不会出现倾斜。It should be noted that in the process of lowering the hoisting mechanism 1, in order to maintain the balance of the distribution beam 111, the C-shaped frame is usually located on the vertical line of the center of gravity of the distribution beam 111. During the hoisting process, The centroid of the hoisting mechanism 1 and the center of gravity of the steel truss beam segment 100 are always on the same vertical line. Therefore, when the position of the C-shaped frame is adjusted, the distribution beam 111 will not tilt.
另外,由于在吊装过程中,位于中间的第二组吊具11的吊点会偏离分配梁111的中点一定距离,分配梁111各个部分收到的载荷并不均匀,因此,为了保证分配梁111各个部分的强度,可将其距离吊点相对较近的一端做加强处理,相对较远的一端适当做减重处理。In addition, since during the hoisting process, the lifting point of the second group of spreaders 11 located in the middle will deviate from the midpoint of the distribution beam 111 by a certain distance, the load received by each part of the distribution beam 111 is not uniform. Therefore, in order to ensure that the distribution beam 111 For the strength of each part of 111, the end relatively close to the hanging point can be strengthened, and the end relatively far away can be appropriately reduced in weight.
进一步地,在调整吊装机构1的姿态使钢桁梁节段100的重心与吊装机构1的形心在同一条铅垂线上的过程中,于机架5的长度方向上,第一组吊具11的吊点滑块112以及第二组吊具11的吊点滑块112与第三组吊具11的吊点滑块112之间的间距等于大横梁21与小横梁22之间的间距。Further, in the process of adjusting the posture of the hoisting mechanism 1 so that the center of gravity of the steel truss segment 100 and the centroid of the hoisting mechanism 1 are on the same vertical line, in the length direction of the frame 5, the first group of hoists The distance between the lifting point slider 112 of the lifting device 11 and the lifting point slider 112 of the second group of lifting fixtures 11 and the lifting point slider 112 of the third group of lifting fixtures 11 is equal to the distance between the large beam 21 and the small beam 22 .
如图1、图3、图5和图7所示,为了尽量扩大三组吊具11的覆盖范围,使得在吊装钢桁梁节段100的过程中,钢桁梁节段100的受力更加均匀,大横梁21和小横梁22通常会间隔一定距离,本实施例中,为了保证三组吊具11在吊装钢桁梁节段100的过程中,连接三组吊具11的钢丝绳始终处于沿铅垂线方向,在调整三组吊具11的吊点滑块112时,需保持第一组吊具11的吊点滑块112以及第二组吊具11的吊点滑块112与第三组吊具11的吊点滑块112之间的间距等于大横梁21与小横梁22之间的间距。As shown in Figures 1, 3, 5 and 7, in order to expand the coverage of the three sets of spreaders 11 as much as possible, during the process of hoisting the steel truss beam section 100, the force of the steel truss beam section 100 will be greater Evenly, the large beam 21 and the small beam 22 are usually spaced apart at a certain distance. In this embodiment, in order to ensure that the three groups of spreaders 11 are hoisting the steel truss segment 100, the steel wire ropes connecting the three groups of spreaders 11 are always along the In the direction of the plumb line, when adjusting the hanging point sliders 112 of the three sets of spreaders 11, it is necessary to keep the hanging point sliders 112 of the first set of spreaders 11 and the hanging point sliders 112 of the second set of spreaders 11 in contact with the third set of spreaders 11. The distance between the lifting point slide blocks 112 of the group spreader 11 is equal to the distance between the large beam 21 and the small beam 22 .
示例性地,在沪通长江大桥上架设长度为28m,重量为1800t的双节间整节段钢桁梁时,大横梁21与小横梁22之间的间距为4050mm,也就是说,第一组吊具11的吊点滑块112以及第二组吊具11的吊点滑块112与第三组吊具11的吊点滑块112之间的间距也为4050mm,其中,第一组吊具11的吊点滑块112以及第二组吊具11的吊点滑块112在其对应的分配梁111上允许调整范围值为0至2080mm,第二组吊具11的吊点滑块112在其对应的分配梁111上允许调整范围值为0至4010mm。For example, when erecting a double-intersection full-segment steel truss beam with a length of 28m and a weight of 1800t on the Hutong Yangtze River Bridge, the distance between the large beam 21 and the small beam 22 is 4050mm, that is to say, the first The distance between the lifting point slider 112 of the first set of spreaders 11 and the second set of spreaders 11 and the third set of spreaders 11 is also 4050mm, where the first set of lifts The lifting point slider 112 of the hoisting tool 11 and the hanging point slider 112 of the second group of hoisting tools 11 allow an adjustment range of 0 to 2080mm on their corresponding distribution beams 111. The hanging point slider 112 of the second group of hoisting tools 11 The allowable adjustment range value on its corresponding distribution beam 111 is 0 to 4010 mm.
进一步地,在提升吊装机构1使钢桁梁节段100到达安装高度的过程中,三组吊具11以预设速度同步提升,预设速度是指预设时间内的平均速度。Furthermore, during the process of lifting the hoisting mechanism 1 to bring the steel truss segment 100 to the installation height, the three groups of spreaders 11 are lifted synchronously at a preset speed, which refers to the average speed within a preset time.
如图9所示,为了提高吊装的安全性,还需要对提升过程进行全流程的监控,保证钢桁梁节段100一直处于平稳的状态,因此,在吊装过程中需要 对三组吊具11的同步性进行精准的控制,本实施例中,通过管控三组吊具11的提升时机以及起升速度的方式进行精准把控。As shown in Figure 9, in order to improve the safety of hoisting, it is necessary to monitor the entire hoisting process to ensure that the steel truss segment 100 is always in a stable state. Therefore, it is necessary to The synchronization of the three groups of spreaders 11 is accurately controlled. In this embodiment, the lifting timing and lifting speed of the three groups of spreaders 11 are controlled accurately.
其中,同步提升是指在相同的时刻开始提升或在相同的时刻停止提升,预设速度是指在预设时间内的平均速度,而不是某一时刻的即时速度,这样,即使在某一时刻其中某一组吊具11的即时速度过快,只要在预设时间内能够将即时速度降下来,也能维持吊装机构1的动态平衡,使得可操作性更强。Among them, synchronous promotion means starting to improve at the same moment or stopping the promotion at the same moment. The preset speed refers to the average speed within the preset time, not the instant speed at a certain moment. In this way, even at a certain moment The real-time speed of a certain group of spreaders 11 is too fast. As long as the real-time speed can be reduced within a preset time, the dynamic balance of the hoisting mechanism 1 can be maintained, making the operability stronger.
需要说明的是,预设时间越长,三组吊具11的即时速度差值允许的范围越大,吊装机构1维持动态平衡越容易,但是在吊装的过程中,待架设的钢桁梁节段100的存在晃动的可能性越大,稳定性越差,预设时间越短,维持动态平衡越不容易,但还稳定性越好,具体可根据需要进行设置,在此不做限制,示例性地,预设时长可设置为10s、20s或30s,预设速度可设置为0.6m/min、1.2m/min或1.8m/min,同步提升精度为50mm。It should be noted that the longer the preset time is, the greater the allowable range of real-time speed differences of the three sets of spreaders 11 is, and the easier it is for the hoisting mechanism 1 to maintain dynamic balance. However, during the hoisting process, the steel truss beam sections to be erected will The greater the possibility of shaking in segment 100, the worse the stability. The shorter the preset time, the harder it is to maintain dynamic balance, but the better the stability. The specific settings can be set according to needs. There are no restrictions here. Example Flexibly, the preset time can be set to 10s, 20s or 30s, the preset speed can be set to 0.6m/min, 1.2m/min or 1.8m/min, and the synchronous lifting accuracy is 50mm.
进一步地,在将架梁起重机移动至架梁位置,准备架梁之后,下降架梁起重机的吊装机构1之前,该施工方法还包括:Further, after moving the girder erecting crane to the girder erecting position, preparing to erect the girder, and before lowering the hoisting mechanism 1 of the girder erecting crane, the construction method also includes:
S200、调整天车机构2,使吊装机构1正对待架设的钢桁梁节段100。S200. Adjust the crane mechanism 2 so that the hoisting mechanism 1 is facing the steel truss segment 100 to be erected.
如图7所示,通常情况下,为了使架梁起重机在走行的过程中重心尽量的靠近后侧,吊装机构1一般都会回收并锁紧,因此,在将架梁起重机移动至架梁位置,准备架梁之后,通常还需要调整天车机构2使其将吊装机构1移动到机架5的前部。As shown in Figure 7, under normal circumstances, in order to keep the center of gravity of the girder erecting crane as close to the rear side as possible during travel, the hoisting mechanism 1 is generally retracted and locked. Therefore, after moving the girder erecting crane to the girder erecting position, After preparing the beams, it is usually necessary to adjust the crane mechanism 2 to move the hoisting mechanism 1 to the front of the frame 5 .
需要说明的是,在首次架梁或停工一段时间后继续施工时,在整机移动到位之后,还需对设备进行整机检查以及调试,使其具备架梁施工要求。It should be noted that when erecting beams for the first time or continuing construction after a period of shutdown, after the entire machine is moved into place, the equipment needs to be inspected and debugged to ensure that it meets the requirements for beam erection.
进一步地,在调整架梁起重机的天车机构2使钢桁梁节段100到达与已架设的钢桁梁200对接的位置之后,安装钢桁梁节段100之前,该施工方法还包括:Further, after adjusting the overhead crane mechanism 2 of the girder crane so that the steel truss beam segment 100 reaches the position of docking with the erected steel truss beam 200, and before installing the steel truss beam segment 100, the construction method also includes:
S700、调整钢桁梁节段100的纵坡。S700. Adjust the longitudinal slope of the steel truss segment 100.
具体地,调整钢桁梁节段100的纵坡包括以下步骤:Specifically, adjusting the longitudinal slope of the steel truss segment 100 includes the following steps:
S710、调整三组吊具11的调整油缸113使钢桁梁节段100倾斜至预设纵倾角度; S710. Adjust the adjustment cylinders 113 of the three sets of spreaders 11 to tilt the steel truss segment 100 to the preset trim angle;
需要说明的是,在调整纵坡的过程中,为了避免钢桁梁节段100在横向上的姿态不受影响,可优先选择调整位于中间的第二组吊具11的调整油缸113,当需要调整位于两侧的两组吊具11的调整油缸113时,应尽量做到同步同幅度调整。It should be noted that during the process of adjusting the longitudinal slope, in order to prevent the lateral attitude of the steel truss beam segment 100 from being affected, the adjustment cylinder 113 of the second group of spreaders 11 in the middle can be adjusted first. When necessary When adjusting the adjustment cylinders 113 of the two sets of spreaders 11 located on both sides, try to achieve simultaneous and same-amplitude adjustment.
S720、整体提升或下降吊装机构1使钢桁梁节段100的后端面与已架设的钢桁梁200的前端面对齐。S720. The overall lifting or lowering of the hoisting mechanism 1 aligns the rear end surface of the steel truss beam segment 100 with the front end surface of the erected steel truss beam 200.
需要说明的是,由于调整完钢桁梁节段100的纵向倾斜角度时,钢桁梁节段100时整体前倾或后倾,因此,钢桁梁节段100的后端面与已架设的钢桁梁200的前端面必然会存在一定的高度差,此时,为了维持钢桁梁节段100的纵向倾斜角度,不能再通过调整吊装机构1的姿态来调整此高度差,需整体提升或下降吊装机构1来消除此高度差,从而使得钢桁梁节段100与已架设的钢桁梁200对接更加精准。It should be noted that after adjusting the longitudinal inclination angle of the steel truss beam segment 100, the steel truss beam segment 100 will tilt forward or backward as a whole. Therefore, the rear end surface of the steel truss beam segment 100 will not be in contact with the erected steel beam There will inevitably be a certain height difference on the front end surface of the truss beam 200. At this time, in order to maintain the longitudinal inclination angle of the steel truss beam segment 100, this height difference cannot be adjusted by adjusting the attitude of the hoisting mechanism 1, and the entire body needs to be raised or lowered. The hoisting mechanism 1 is used to eliminate this height difference, thereby making the steel truss segment 100 and the erected steel truss 200 more accurately connected.
进一步地,当架设至合龙口时,该施工方法还包括将钢桁梁节段100与对向已架设的钢桁梁200合龙,将钢桁梁节段100与对向已架设的钢桁梁200合龙包括依次合龙钢桁梁节段100的下弦杆、斜杆和上弦杆,其中,合龙下弦杆包括依次合龙中桁下弦杆和边桁下弦杆,合龙斜杆包括依次合龙中桁斜杆和边桁斜杆,合龙上弦杆包括依次合龙边桁上弦杆和中桁上弦杆。Further, when erecting to the closing point, the construction method also includes closing the steel truss beam section 100 with the opposite erected steel truss beam 200, and connecting the steel truss beam section 100 with the opposite erected steel truss beam. The 200 joints include the lower chords, diagonal bars and upper chords of the steel truss beam segments 100. The lower chords include the middle truss lower chords and the side truss lower chords. The diagonal bars include the middle truss diagonal bars and the side truss lower chords. The side truss diagonal rods and the top chord rods of the side girders include the upper chord rods of the side girders and the upper chord rods of the center girders.
具体地,为了方便理解,后文以沪通长江大桥上架设长度为28m,重量为1800t的双节间整节段钢桁梁,进行辅助跨钢桁梁合龙施工为例进行示例性说明,辅助跨钢桁梁合龙时主航道桥钢桁梁处于最大双悬臂状态,辅助跨钢桁梁合龙采用先合龙下弦杆,再合龙斜杆,然后合龙上弦杆的顺序进行施工。Specifically, in order to facilitate understanding, the following article takes the erection of a double-intersection whole-segment steel truss beam with a length of 28m and a weight of 1800t on the Hutong Yangtze River Bridge as an example to illustrate the auxiliary span steel truss beam closing construction. When the span steel truss beam is closed, the main channel bridge steel truss beam is in the maximum double cantilever state. The auxiliary span steel truss beam closure is constructed in the order of closing the lower chord first, then closing the diagonal beam, and then closing the upper chord.
为便于进行钢桁梁的合龙施工,需先架设辅助墩搭载合龙施工平台,提前准备合龙段钢桁梁拼接板配带、调整悬臂端钢桁梁的线形、调整的墩顶钢桁梁的线形及合龙口对拉等施工措施所需的设备。In order to facilitate the closing construction of steel truss beams, it is necessary to first set up auxiliary piers to carry the closing construction platform, prepare in advance the splicing plates of the steel truss beams in the closing section, adjust the alignment of the steel truss beams at the cantilever end, and adjust the alignment of the steel truss beams on the top of the piers. And the equipment required for construction measures such as Helongkou pulling.
其中,合龙段钢桁梁节段100的主桁上弦杆以及斜杆高栓施工平台可直接倒用标准节段钢桁梁施工平台,发往钢桁梁总拼场,在厂内进行安装,随钢桁梁整体发运,在Z12~Z13钢桁梁节段100与Z14~Z15钢桁梁节段100的拼接缝位置按标准节悬臂架设工况正常的“Z”字型配带,下弦杆以及斜 杆的拼接板正常配带在Z13节间,上弦杆配带在Z14间;在Z12~Z13钢桁梁节段100与Z11钢桁梁节段100的拼接缝位置下弦杆以及上弦杆的拼接板正常配带在Z12钢桁梁节段100的节间,因斜杆为箱型截面,拼接板缩带在Z12钢桁梁节段100的节间与斜杆端口齐平;悬臂端钢桁梁的线形调整主要在辅助墩合龙前,可根据钢桁梁的载荷工况以及斜拉索的张拉情况对钢桁梁的线形进行计算分析,控制斜拉索的索力从而确保辅助墩的合龙口在设计高程以下300mm以内;辅助墩的墩顶通过2台200t水平纵移千斤顶,12台500t竖向千斤顶以及4台200t水平横向千斤顶来实现墩顶钢桁梁的线形调整。Among them, the main truss upper chord and diagonal beam high-bolt construction platform of the Helong section steel truss beam segment 100 can be directly used as a standard segment steel truss beam construction platform and sent to the steel truss girder assembly yard for installation in the factory. Shipped with the steel truss beam as a whole, the splicing joints between the Z12~Z13 steel truss beam segments 100 and the Z14~Z15 steel truss beam segments 100 are equipped with belts in a normal "Z" shape under standard section cantilever erection conditions, and the bottom string is pole and slope The splicing plate of the rod is normally placed between Z13 sections, and the upper chord bar is placed between Z14; the lower chord bar and the upper chord bar are spliced at the joint position of the Z12 ~ Z13 steel truss beam segment 100 and the Z11 steel truss beam segment 100 The plate is normally strapped between the sections of Z12 steel truss beam section 100. Since the diagonal rod has a box section, the splicing plate shrink strap is flush with the diagonal rod port between the sections of Z12 steel truss beam section 100; the cantilever end steel truss The linear adjustment of the beam is mainly before the auxiliary pier is closed. The linear shape of the steel truss beam can be calculated and analyzed based on the load conditions of the steel truss beam and the tension situation of the stay cables, and the cable force of the stay cables can be controlled to ensure the stability of the auxiliary pier. Helongkou is within 300mm below the design elevation; the top of the auxiliary pier uses two 200t horizontal longitudinal jacks, 12 500t vertical jacks and four 200t horizontal transverse jacks to realize the linear adjustment of the steel trusses on the top of the pier.
辅助跨合龙施工过程如下:辅助墩的墩顶Z9~Z11三个单节段按低于设计高程30cm提前架设完成并预偏3m,接近架设至合龙口时,辅助墩提前完成千斤顶调试、滑块位置调整、牵引纵移设备安装以及横向限位安装,并做线形复测,如果与设计轴线存在偏差则提前调整;主塔墩的双悬臂端架设至距离合龙口4个节间时(例如架设至Z14~Z15/Z71~Z72节段),除严格控制索力以及梁面高程外,还需通过调整索力均匀性等手段重点控制轴线偏位,使轴线偏差往墩顶的Z9~Z11钢桁梁节段100靠拢。The construction process of the auxiliary span closing is as follows: the three single sections Z9 to Z11 on the pier top of the auxiliary pier are erected 30cm below the design elevation in advance and are pre-deviated 3m. When it is close to erection to the closing entrance, the auxiliary pier completes the jack debugging and slider in advance Position adjustment, installation of traction and longitudinal movement equipment and lateral limit installation, and linear re-measurement. If there is a deviation from the design axis, adjust it in advance; when the double cantilever ends of the main tower piers are erected to 4 intervals from Helongkou (for example, erection to the Z14~Z15/Z71~Z72 section), in addition to strictly controlling the cable force and beam surface elevation, it is also necessary to focus on controlling the axis deviation by adjusting the uniformity of the cable force, so that the axis deviation is directed towards the Z9~Z11 steel on the top of the pier. The truss segments 100 are brought together.
S(M)25以及S(M)26层斜拉索挂索张拉完成后,架设Z12~Z13/Z73~Z74钢桁梁节段100,同时进行S(M)27以及S(M)28层斜拉索塔端挂设,根据监控指令(主跨侧压重为主)精调悬臂端钢桁梁的线形,准备进行辅助跨合龙;墩顶的Z9~Z11钢桁梁节段100先通过2台200t纵移千斤顶往主跨纵移2.9m,再通过12台500t竖向千斤顶,4台200t横向千斤顶调整竖向及横向偏差,待合龙口两侧的钢桁梁节段100位置姿态一致后,再将墩顶的钢桁梁节段100整体纵移0.1m,实现下弦杆对接,下弦杆对接后,再通过起落Z9~Z11钢桁梁节段100以及法向对拉等措施依次对接斜杆以及上弦杆,最后依次进行冲钉、高栓及焊接施工;最后竖向千斤顶起顶墩顶的钢桁梁节段100,拆除垫石顶面滑道以及滑块,安装墩顶的钢桁梁永久支座,同步布置墩顶的整体起升千斤顶。After the tensioning of the stay cables on floors S(M)25 and S(M)26 is completed, 100 steel truss beam segments Z12~Z13/Z73~Z74 are erected, and S(M)27 and S(M)28 are carried out at the same time. The cable-stayed cable tower end of the first floor is hung, and the alignment of the steel truss beam at the cantilever end is finely adjusted according to the monitoring instructions (mainly the pressure on the main span side) to prepare for the auxiliary span closing; the Z9 ~ Z11 steel truss beam segments on the top of the pier are 100 first Through 2 sets of 200t longitudinal jacks, the main span is moved 2.9m longitudinally, and then through 12 sets of 500t vertical jacks and 4 sets of 200t transverse jacks to adjust the vertical and lateral deviations. The positions and postures of the steel truss beam segments 100 on both sides of the gantry are consistent. After that, the steel truss beam segments 100 on the top of the pier are moved longitudinally by 0.1m as a whole to realize the docking of the lower chord poles. After the lower chord poles are docked, they are then docked in sequence by lifting and lowering the Z9 to Z11 steel truss beam segments 100 and normal tension. The diagonal rod and upper chord rod are finally punched, high bolted and welded in sequence; finally, the steel truss section 100 on the top of the pier is jacked vertically, the top slideway and slider of the padstone are removed, and the steel truss beam on the top of the pier is installed. The truss beam is permanently supported, and the integral lifting jack on the pier top is arranged simultaneously.
需要说明的是,在辅助跨钢桁梁合龙螺栓孔对位时,为消除因钢桁梁自重及架梁起重机站位引起的合龙口两侧的钢桁梁节段100变形差异,需将栓孔偏差控制在1mm以内以便插打冲钉,按照钢桁梁悬臂架设过程布置的大节 段对位措施,可在合龙口两侧布置调节装置A、调节装置B/C以及斜杆对拉倒链实现栓孔偏差的调整。It should be noted that when auxiliary span steel truss girder closing bolt hole alignment, in order to eliminate the deformation difference of the steel truss beam segments 100 on both sides of the closing opening caused by the steel truss girder's own weight and the position of the girder erecting crane, the bolts need to be The hole deviation is controlled within 1mm to facilitate the insertion of punching nails. The major sections are arranged according to the cantilever erection process of the steel truss beam. For segment alignment measures, the adjustment device A, the adjustment device B/C and the inclined rod can be arranged on both sides of the closing mouth to adjust the bolt hole deviation.
需要说明的是,在辅助跨钢桁梁合龙施工至合龙口位置时,弦杆需按照合龙下弦杆(先中桁后边桁),合龙斜杆(先中桁后边桁),合龙上弦杆(先边桁后中桁)的顺序进行施工。It should be noted that when the auxiliary span steel truss girder is closed to the closing position, the chords must be closed according to the following procedures: closing the lower chord (first the center truss and then the side truss), closing the diagonal rod (first the center truss and then the side truss), and closing the upper chord (first the center truss and then the side truss). Construction is carried out in the order of side girders, middle girders, and rear girders.
具体地,合龙下弦杆:调整边跨侧悬臂段钢桁梁线形,同时墩旁托架上的竖向千斤顶调整墩顶Z9~Z11位置处的钢桁梁节段100,使下弦杆的杆端轴线、倾角与悬臂钢桁梁的前端下弦杆轴线、倾角相匹配,再通过纵移千斤顶将墩顶钢桁梁节段100向跨中方向顶推,依次合龙下弦杆中桁、边桁。Specifically, to close the lower chord: adjust the line shape of the steel truss beam of the side span side cantilever section, and at the same time, the vertical jack on the bracket next to the pier adjusts the steel truss segment 100 at the Z9 ~ Z11 position of the pier top, so that the rod end of the lower chord The axis and inclination angle match the axis and inclination angle of the front-end lower chord of the cantilever steel truss beam, and then the longitudinal movement jack is used to push the pier top steel truss beam segment 100 toward the mid-span direction, and then close the lower chord middle truss and side truss.
其中,根据辅助跨合龙期间升降温对下弦杆对接处内力的影响,考虑合龙冲钉插打过程结构受力安全,要求下弦杆对接时拼接面单侧需打入冲钉15个,腹板拼接需采用416个高栓,即实际施工中需打入10%的冲钉,冲钉均匀布置,且一半需布置在靠近顶底区域。Among them, according to the influence of the temperature rise and fall during the auxiliary span closing on the internal force of the lower chord joint, and considering the structural stress safety during the punching process of the closing punch, it is required that 15 punch nails need to be driven into one side of the splicing surface when the lower chord is connected, and the web splicing 416 high bolts need to be used, that is, 10% of the punching nails need to be driven in during actual construction. The punching nails are evenly arranged, and half of them need to be arranged near the top and bottom areas.
合龙斜杆:钢桁梁的下弦杆对接完毕后,可在斜杆与竖杆间设置5t倒链,调节斜杆的轴线斜率后即可对接斜杆,冲钉插打按照梅花形布置,总数为栓孔数量的10%。Helong diagonal bar: After the lower chord of the steel truss beam is docked, a 5t inverted chain can be set between the diagonal bar and the vertical bar. After adjusting the axis slope of the diagonal bar, the diagonal bar can be connected. The punching nails are arranged in a plum blossom shape. The total number 10% of the number of bolt holes.
合龙上弦杆:钢桁梁的斜杆对接完毕后,可通过设置反压竖向调节及对拉装置使上弦杆的杆端轴线以及倾角与悬臂钢桁梁前端的上弦杆轴线以及倾角相匹配,消除栓孔偏差,依次插打冲钉从而使上弦杆的边桁以及中桁合龙,冲钉插打按照梅花形布置,总数为栓孔数量的10%。Helong upper chord: After the diagonal rods of the steel truss beam are docked, the counter-pressure vertical adjustment and pull device can be set to match the rod end axis and inclination of the upper chord with the upper chord axis and inclination of the front end of the cantilevered steel truss beam. Eliminate the bolt hole deviation, insert punching nails in sequence to make the side girders and middle girders of the upper chord rod closed. The punching nails are arranged in a plum blossom shape, and the total number is 10% of the number of bolt holes.
钢桁梁节段100的下弦杆、斜杆以及上弦杆等主桁对接完毕后,可对铁路桥面板以及上弦小纵梁进行对接焊,南北两岸侧的辅助跨钢桁梁合龙时载荷工况基本一致,施工过程类似。After the main trusses such as the lower chord, diagonal beam and upper chord of the steel truss segment 100 are butt-welded, the railway bridge deck and the upper chord small longitudinal beams can be butt welded. The load conditions of the auxiliary span steel truss beams on the north and south sides are when they are closed. Basically the same, the construction process is similar.
这样,通过计算分析采取先下弦、再斜杆、后上弦的对接顺序,并对接过程中采用千斤顶反压、斜向对拉以及轴向对拉(对顶)等措施,可以解决大节段钢桁梁的空间多杆件对接的难题;针对大节段钢桁梁的整体主动合龙施工,通过合龙口的敏感性分析以及持续观测、主墩顶的纵向调整、辅助墩的墩顶竖向调整、合龙口配重以及纵横向对拉(对顶),掌握 了大悬臂状态下钢桁梁的变形规律,调控合龙口的纵桥向、横桥向、竖向以及竖向转角四个自由度,从而可以实现大节段钢桁梁在大悬臂条件下的精确合龙。In this way, through calculation and analysis, the docking sequence of first lowering the chord, then the inclined rod, and then the upper chord is adopted. During the docking process, measures such as jack counter-pressure, diagonal pulling and axial pulling (top-pull) are adopted to solve the problem of large steel sections. The problem of multi-member docking in the space of truss beams; for the overall active closing construction of large-section steel truss beams, through sensitivity analysis and continuous observation of the closing mouth, longitudinal adjustment of the main pier top, and vertical adjustment of the pier top of the auxiliary pier , Helongkou counterweight and vertical and horizontal pull (top), master The deformation law of steel truss beams under large cantilever conditions is determined, and the four degrees of freedom of the longitudinal bridge direction, transverse bridge direction, vertical direction and vertical angle of Helongkou are controlled, so that the deformation of large-segment steel truss beams under large cantilever conditions can be realized. Accurate closure.
虽然本公开披露如上,但本公开的保护范围并非仅限于此。本领域技术人员在不脱离本公开的精神和范围的前提下,可进行各种变更与修改,这些变更与修改均将落入本申请的保护范围。 Although the present disclosure is disclosed as above, the protection scope of the present disclosure is not limited thereto. Those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present disclosure, and these changes and modifications will fall within the protection scope of the present application.

Claims (10)

  1. 一种运用架梁起重机架设双节间整节段钢桁梁的施工方法,包括:A construction method using a beam erecting crane to erect a double-section full-section steel truss beam, including:
    将架梁起重机移动至架梁位置,准备架梁;Move the girder erecting crane to the girder erection position and prepare to erect the girder;
    下降所述架梁起重机的吊装机构(1)并与钢桁梁节段(100)连接;Lower the hoisting mechanism (1) of the girder crane and connect it to the steel truss segment (100);
    提升所述钢桁梁节段(100)至预设高度,调整所述吊装机构(1)的姿态使所述钢桁梁节段(100)的重心与所述吊装机构(1)的形心在同一条铅垂线上;Lift the steel truss beam segment (100) to a preset height, and adjust the posture of the hoisting mechanism (1) so that the center of gravity of the steel truss beam segment (100) is consistent with the centroid of the hoisting mechanism (1) on the same plumb line;
    提升所述吊装机构(1)使所述钢桁梁节段(100)到达安装高度;Lift the hoisting mechanism (1) so that the steel truss segment (100) reaches the installation height;
    调整所述架梁起重机的天车机构(2)使所述钢桁梁节段(100)到达与已架设的钢桁梁(200)对接的位置;Adjust the overhead crane mechanism (2) of the girder erecting crane so that the steel truss beam segment (100) reaches the position of docking with the erected steel truss beam (200);
    安装所述钢桁梁节段(100),解除所述吊装机构(1)与所述钢桁梁节段(100)的连接,收回所述天车机构(2)并锁定,所述架梁起重机走行至下一个架梁位置。Install the steel truss beam segment (100), release the connection between the hoisting mechanism (1) and the steel truss beam segment (100), retract the overhead crane mechanism (2) and lock it, and the erection beam The crane moves to the next beam erection position.
  2. 根据权利要求1所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,所述将架梁起重机移动至架梁位置,准备架梁包括:The construction method of using a girder erecting crane to erect a double-segment full-section steel truss beam according to claim 1, wherein the moving the girder erecting crane to the girder erecting position and preparing the girder erection includes:
    所述架梁起重机的走行机构(3)驱动所述架梁起重机移动至所述架梁位置;The traveling mechanism (3) of the girder erecting crane drives the girder erecting crane to move to the girder erecting position;
    将所述架梁起重机的锚固机构(4)与已架设的所述钢桁梁(200)锚固。Anchor the anchoring mechanism (4) of the girder erecting crane with the erected steel truss beam (200).
  3. 根据权利要求2所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,所述架梁起重机的走行机构(3)驱动所述架梁起重机移动至所述架梁位置包括:The construction method of erecting a double-intersection whole-segment steel truss beam using a girder erecting crane according to claim 2, wherein the traveling mechanism (3) of the girder erecting crane drives the girder erecting crane to move to the girder erecting crane. Locations include:
    所述走行机构(3)的滑靴油缸(33)向上收缩带动所述走行机构(3)的轨道梁(31)离地;The sliding shoe cylinder (33) of the traveling mechanism (3) contracts upward to drive the track beam (31) of the traveling mechanism (3) to lift off the ground;
    将所述走行机构(3)的走行油缸(32)与所述轨道梁(31)的限位孔(311)连接,所述走行油缸(32)收缩带动所述轨道梁(31)向前移动,解除所述走行油缸(32)与所述限位孔(311)的连接,所述走行油缸(32) 伸出至下一个所述限位孔(311)处,重复上述操作,直至所述轨道梁(31)移动到位;Connect the traveling oil cylinder (32) of the traveling mechanism (3) to the limiting hole (311) of the track beam (31). The traveling oil cylinder (32) contracts to drive the track beam (31) to move forward. , release the connection between the traveling oil cylinder (32) and the limiting hole (311), and the traveling oil cylinder (32) Extend to the next limiting hole (311), and repeat the above operation until the track beam (31) moves into place;
    所述滑靴油缸(33)向下伸出带动所述轨道梁(31)触地并受力;The sliding shoe cylinder (33) extends downward to drive the track beam (31) to touch the ground and receive force;
    将所述走行油缸(32)与所述轨道梁(31)的限位孔(311)连接,所述走行油缸(32)伸出带动所述架梁起重机向前移动,解除所述走行油缸(32)与所述限位孔(311)的连接,所述走行油缸(32)收缩至下一个所述限位孔(311)处,重复上述操作,直至所述架梁起重机移动到位。The traveling oil cylinder (32) is connected to the limit hole (311) of the track beam (31). The traveling oil cylinder (32) extends to drive the beam erecting crane to move forward, and the traveling oil cylinder (32) is released. 32) The connection with the limit hole (311), the traveling oil cylinder (32) shrinks to the next limit hole (311), and the above operation is repeated until the girder crane moves into place.
  4. 根据权利要求1所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,所述天车机构(2)包括大横梁(21)和小横梁(22),所述大横梁(21)和所述小横梁(22)平行设置并分别与所述架梁起重机的机架(5)滑动连接,且所述大横梁(21)和所述小横梁(22)用于沿所述机架(5)的长度方向滑动,所述吊装机构(1)包括品字形布置的三组吊具(11),第一组所述吊具(11)设置在所述大横梁(21)的一端,第二组所述吊具(11)设置在所述大横梁(21)的另一端,第三组所述吊具(11)设置在所述小横梁(22)上,所述吊具(11)包括分配梁(111)、吊点滑块(112)和调整油缸(113),所述吊点滑块(112)通过钢丝绳与所述天车机构(2)活动连接,所述分配梁(111)与所述吊点滑块(112)滑动连接,所述调整油缸(113)的一端与所述分配梁(111)连接,所述调整油缸(113)的另一端与所述吊点滑块(112)连接,所述分配梁(111)用于与所述钢桁梁节段(100)连接。The construction method of using a girder erecting crane to erect a double-intersection whole-segment steel truss beam according to claim 1, wherein the overhead crane mechanism (2) includes a large beam (21) and a small beam (22), and the The large beam (21) and the small beam (22) are arranged in parallel and are slidingly connected to the frame (5) of the girder crane respectively, and the large beam (21) and the small beam (22) are used for Sliding along the length direction of the frame (5), the hoisting mechanism (1) includes three sets of spreaders (11) arranged in a Z-shaped arrangement. The first set of spreaders (11) is arranged on the large beam ( 21), the second set of spreaders (11) is set at the other end of the large beam (21), and the third set of spreaders (11) is set on the small beam (22), so The spreader (11) includes a distribution beam (111), a lifting point slider (112) and an adjustment oil cylinder (113). The lifting point slider (112) is movably connected to the crane mechanism (2) through a wire rope. The distribution beam (111) is slidingly connected to the hanging point slider (112), one end of the adjustment oil cylinder (113) is connected to the distribution beam (111), and the other end of the adjustment oil cylinder (113) is connected to the distribution beam (111). The hanging point slider (112) is connected, and the distribution beam (111) is used to connect with the steel truss beam segment (100).
  5. 根据权利要求4所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,在所述调整所述吊装机构(1)的姿态使所述钢桁梁节段(100)的重心与所述吊装机构(1)的形心在同一条铅垂线上的过程中,于所述机架(5)的长度方向上,第一组所述吊具(11)的所述吊点滑块(112)以及第二组所述吊具(11)的所述吊点滑块(112)与第三组所述吊具(11)的所述吊点滑块(112)之间的间距等于所述大横梁(21)与所述小横梁(22)之间的间距。The construction method of erecting a double-intersection whole-segment steel truss beam using a girder erecting crane according to claim 4, wherein when adjusting the posture of the hoisting mechanism (1), the steel truss beam segment (100 ) and the centroid of the hoisting mechanism (1) are on the same vertical line, in the length direction of the frame (5), all of the first group of the hoisting tools (11) The suspension point slider (112) and the suspension point slider (112) of the second group of the spreader (11) and the suspension point slider (112) of the third group of the spreader (11) The distance between them is equal to the distance between the large beam (21) and the small beam (22).
  6. 根据权利要求4所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,在所述提升所述吊装机构(1)使所述钢桁梁节段(100) 到达安装高度的过程中,三组所述吊具(11)以预设速度同步提升。The construction method for erecting a double-intersection whole-segment steel truss beam using a girder erecting crane according to claim 4, wherein when the hoisting mechanism (1) is lifted, the steel truss beam segment (100) In the process of reaching the installation height, the three groups of spreaders (11) are lifted synchronously at a preset speed.
  7. 根据权利要求1所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,在所述将架梁起重机移动至架梁位置,准备架梁之后,所述下降所述架梁起重机的吊装机构(1)之前,还包括:The construction method for erecting double-intersection whole-segment steel truss beams using a girder erecting crane according to claim 1, wherein, after the girder erecting crane is moved to the girder erecting position and the girder erection is prepared, the lowering of the Before the hoisting mechanism (1) of the girder crane, it also includes:
    调整所述天车机构(2),使所述吊装机构(1)正对待架设的所述钢桁梁节段(100)。Adjust the overhead crane mechanism (2) so that the hoisting mechanism (1) is facing the steel truss segment (100) to be erected.
  8. 根据权利要求4所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,在所述调整所述架梁起重机的天车机构(2)使所述钢桁梁节段(100)到达与已架设的钢桁梁(200)对接的位置之后,安装所述钢桁梁节段(100)之前,还包括:The construction method of using a girder erecting crane to erect a double-section full-section steel truss beam according to claim 4, wherein when adjusting the crown crane mechanism (2) of the girder erecting crane, the steel truss beam section is After the section (100) reaches the position of docking with the erected steel truss beam (200), and before installing the steel truss beam section (100), it also includes:
    调整所述钢桁梁节段(100)的纵坡。Adjust the longitudinal slope of the steel truss segment (100).
  9. 根据权利要求8所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,所述调整所述钢桁梁节段(100)的纵坡包括:The construction method of erecting a double-intersection whole-segment steel truss beam using a girder erecting crane according to claim 8, wherein the adjustment of the longitudinal slope of the steel truss beam section (100) includes:
    调整三组所述吊具(11)的所述调整油缸(113)使所述钢桁梁节段(100)倾斜至预设纵倾角度;Adjust the adjustment cylinders (113) of the three sets of spreaders (11) to tilt the steel truss segment (100) to a preset trim angle;
    整体提升或下降所述吊装机构(1)使所述钢桁梁节段(100)的后端面与已架设的所述钢桁梁(200)的前端面对齐。Lift or lower the hoisting mechanism (1) as a whole to align the rear end surface of the steel truss beam segment (100) with the front end surface of the erected steel truss beam (200).
  10. 根据权利要求1至9中任一项所述的运用架梁起重机架设双节间整节段钢桁梁的施工方法,其中,当架设至合龙口时,还包括将所述钢桁梁节段(100)与对向已架设的所述钢桁梁(200)合龙,所述将所述钢桁梁节段(100)与对向已架设的所述钢桁梁(200)合龙包括依次合龙所述钢桁梁节段(100)的下弦杆、斜杆和上弦杆,其中,合龙所述下弦杆包括依次合龙中桁下弦杆和边桁下弦杆,合龙所述斜杆包括依次合龙中桁斜杆和边桁斜杆,合龙所述上弦杆包括依次合龙边桁上弦杆和中桁上弦杆。 The construction method for erecting a double-intersection whole-segment steel truss beam using a girder erecting crane according to any one of claims 1 to 9, wherein when erecting to the closing port, it also includes erecting the steel truss beam segment (100) is coupled with the steel truss beam (200) that has been erected in the opposite direction. The coupling of the steel truss beam segments (100) with the steel truss beam (200) that has been erected in the opposite direction includes closing in sequence. The lower chord, diagonal rod and upper chord of the steel truss beam segment (100), wherein the lower chord includes the lower chord of the middle truss and the lower chord of the side truss in sequence, and the inclined rod includes the middle truss in sequence. The diagonal rod and the side truss diagonal rod, and the upper chord rod include the upper chord rod of the side truss and the upper chord rod of the middle truss in sequence.
PCT/CN2023/091549 2022-08-15 2023-04-28 Construction method for erecting inter-section whole-section steel truss using girder erection crane WO2024037042A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210974317.XA CN115305835B (en) 2022-08-15 2022-08-15 Construction method for erecting double-section whole-section steel truss girder by using girder erecting crane
CN202210974317.X 2022-08-15

Publications (1)

Publication Number Publication Date
WO2024037042A1 true WO2024037042A1 (en) 2024-02-22

Family

ID=83863452

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/091549 WO2024037042A1 (en) 2022-08-15 2023-04-28 Construction method for erecting inter-section whole-section steel truss using girder erection crane

Country Status (2)

Country Link
CN (1) CN115305835B (en)
WO (1) WO2024037042A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115305835B (en) * 2022-08-15 2023-07-11 中铁九桥工程有限公司 Construction method for erecting double-section whole-section steel truss girder by using girder erecting crane

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012039547A2 (en) * 2010-09-20 2012-03-29 이케이중공업주식회사 Bridge construction crane for installing a girder in a curved section
CN103243659A (en) * 2013-05-21 2013-08-14 中铁八局集团第一工程有限公司 Cantilever hanging bracket and using method thereof
CN104763357A (en) * 2015-03-24 2015-07-08 四川宏华石油设备有限公司 Automatic drilling rig transporting device
KR101609661B1 (en) * 2015-06-09 2016-04-06 박재현 Hollow composite girder for bridge and method of constructing the same
CN111532999A (en) * 2020-04-28 2020-08-14 中铁大桥局集团有限公司 Beam erecting crane and beam erecting method
CN115305835A (en) * 2022-08-15 2022-11-08 中铁九桥工程有限公司 Construction method for erecting double-section whole-section steel truss girder by using girder erection crane

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1900423A (en) * 2006-07-10 2007-01-24 中铁大桥局股份有限公司 Integrate section frame building method for steel truss
CN101508403B (en) * 2009-03-06 2011-05-25 武桥重工集团股份有限公司 Girderr crane using three-point statically indeterminate hoisting system
CN108275574A (en) * 2018-04-16 2018-07-13 四川路桥华东建设有限责任公司 Adaptive steel truss girder center of gravity, mounted angle variation hoisting appliance and construction method
CN113846563B (en) * 2021-09-18 2023-04-07 中铁大桥局集团有限公司 Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012039547A2 (en) * 2010-09-20 2012-03-29 이케이중공업주식회사 Bridge construction crane for installing a girder in a curved section
CN103243659A (en) * 2013-05-21 2013-08-14 中铁八局集团第一工程有限公司 Cantilever hanging bracket and using method thereof
CN104763357A (en) * 2015-03-24 2015-07-08 四川宏华石油设备有限公司 Automatic drilling rig transporting device
KR101609661B1 (en) * 2015-06-09 2016-04-06 박재현 Hollow composite girder for bridge and method of constructing the same
CN111532999A (en) * 2020-04-28 2020-08-14 中铁大桥局集团有限公司 Beam erecting crane and beam erecting method
CN115305835A (en) * 2022-08-15 2022-11-08 中铁九桥工程有限公司 Construction method for erecting double-section whole-section steel truss girder by using girder erection crane

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JUN-TANG LI: "Integral Manufacturing and Erection Techniques for Steel Truss Girder of Main Navigational Channel Bridge of Shanghai-Suzhou-Nantong Changjiang River Bridge", BRIDGE CONSTRUCTION, vol. 50, no. 5, 28 October 2020 (2020-10-28), pages 10 - 15, XP093140811 *
YUN-PING ZHU, TANG YONG; XU JIA-PING: "Erection Schemes for Pier-Top Steel Girder of Main Navigational Channel Bridge of Hutong Changjiang River Bridgeeering", WORLD BRIDGES, vol. 46, no. 1, 28 January 2018 (2018-01-28), pages 1 - 5, XP093140813 *

Also Published As

Publication number Publication date
CN115305835A (en) 2022-11-08
CN115305835B (en) 2023-07-11

Similar Documents

Publication Publication Date Title
WO2022048320A1 (en) Hydraulic self-elevating integrated cable-stayed bridge lifting formwork
CN113882279B (en) Self-walking and adjusting concrete continuous beam cantilever pouring construction equipment and process
CN208815424U (en) A kind of bridge descending hanging basket
CN110004829B (en) Steel arch tower lifting method
CN112030767A (en) Steel tower unilateral climbing type lifting formwork and application to inclined single-column steel cable tower
WO2024037042A1 (en) Construction method for erecting inter-section whole-section steel truss using girder erection crane
CN105714690A (en) Segmental cantilever girder lifter for large span steel and concrete composite beam erection construction
CN109183620A (en) Telescoping bracket, steel box-girder hanging device and hanging method
CN109914265A (en) A kind of erection crane
WO2022184136A1 (en) Assembly-type subway station full-hoisting construction method in pile-anchor retaining structure system
CN207987749U (en) Ride cable-styled erection crane
WO2024087901A1 (en) Cantilever casting and locomotion all-in-one machine
CN110396931B (en) Cable-crossing bridge deck crane of central double-cable-plane cable-stayed bridge and construction method thereof
CN205529915U (en) Ladder type masts type hangs pieces together loop wheel machine
CN111395176A (en) Construction method for lowering and dismantling movable formwork based on convenience
CN116289620A (en) Box girder steel bar part combined type conveying device and method
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN105672136A (en) Erecting construction process for large-span steel-concrete combination beam
CN115613478A (en) Continuous beam cantilever casting method
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
CN212052371U (en) Hanging basket device for variable width concrete box girder suspension casting construction
CN209922694U (en) Lifting appliance
CN217417939U (en) Walking system of large-angle heavy-load climbing frame beam crane
CN219527360U (en) Stable lifting structure for high pier construction

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 23853949

Country of ref document: EP

Kind code of ref document: A1