Vertical-column hoisting tool, and operating method therefor Download PDF

Info

Publication number
WO2023071385A1
WO2023071385A1 PCT/CN2022/111435 CN2022111435W WO2023071385A1 WO 2023071385 A1 WO2023071385 A1 WO 2023071385A1 CN 2022111435 W CN2022111435 W CN 2022111435W WO 2023071385 A1 WO2023071385 A1 WO 2023071385A1
Authority
WO
WIPO (PCT)
Prior art keywords
lifting
column
component
steel plate
hoisting
Prior art date
Application number
PCT/CN2022/111435
Other languages
French (fr)
Chinese (zh)
Inventor
王帅
刘腾
刘建伟
张华�
周豪
周尚民
刘凯响
Original Assignee
中国电建集团山东电力建设第一工程有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国电建集团山东电力建设第一工程有限公司 filed Critical 中国电建集团山东电力建设第一工程有限公司
Publication of WO2023071385A1 publication Critical patent/WO2023071385A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/62Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
    • B66C1/66Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled for engaging holes, recesses, or abutments on articles specially provided for facilitating handling thereof

Definitions

  • the invention relates to the technical field of lifting and hoisting, in particular to a column hoisting tool and a working method.
  • a scaffold for unhooking at the top of the column Before the column is hoisted, it is necessary to set up a scaffold for unhooking at the top of the column, and lay a ladder from the top of the column to the bottom of the column, that is, a self-locking device for construction personnel to go up and down; use a snap ring to connect the wire rope to the top of the column and lift it. Go up the ladder to the scaffold at the top of the column and remove the snap ring and loose hook.
  • the object of the present invention is to overcome the deficiencies of the prior art and provide a column hoisting tool, which does not require construction personnel to climb to the top of the column to remove hooks, has high work efficiency, and avoids safety risks when climbing ladders.
  • the present invention adopts the following technical solutions:
  • an embodiment of the present invention provides a column lifting tool, including a first part and a second part connected as a whole through a connecting piece, and a third part, the third part and the first part and/or the second part
  • the two parts are fixedly connected, the third part is fixed to one end of the elastic part, the other end of the elastic part is connected to one end of the lifting part, the first part and the second part are provided with openings for the lifting part to pass through, and the other end of the lifting part
  • the first anti-off part passes through, and the first anti-off part is connected with the pull cord.
  • first component and the second component are plate-like structures, and the first component and the second component are arranged in parallel.
  • the first part and the second part are provided with hoisting holes capable of cooperating with snap rings connected with steel wire ropes under the hooks of the hoisting equipment.
  • the lifting hole is provided at one end of the first part and the second part, and the lifting part passes through the first part and the second part through the other end of the first part and the second part.
  • the end of the lifting member used to connect with the elastic member is provided with a second anti-off component, and the second anti-off component is connected to the end of the elastic component.
  • a through hole is provided at the end of the lifting member, and the first anti-off component passes through the lifting member through the through hole.
  • the third part is a rod-shaped structure, including a first rod segment, one end of the first rod segment is fixed to the first part or the second part, and the other end of the first rod segment is perpendicular to one end of the second rod segment connected, the elastic member is connected with the second rod segment.
  • connection hole is provided at the end of the first anti-loosening component, and the first anti-loosening component is connected to the pull cord through the connection hole.
  • the length of the stay rope is greater than the height of the column to be hoisted.
  • the embodiment of the present invention provides a working method of a column hoisting tool: After the lifting piece passes through the first component, the top of the column and the second component, insert the first anti-off component at the end of the lifting piece, and then lift the The lifting device is connected with the lifting device, and the column is hoisted by the lifting device. After the column is hoisted, the pull rope is pulled to make the first anti-off part and the lifting part separate. Under the action of the elastic part, the lifting part and the first part, the second The parts and columns are separated to complete the unhooking.
  • the construction personnel when unhooking, the construction personnel only need to pull the stay rope so that the first anti-detachment part is separated from the lifting part.
  • the hoisted column is separated, and then the hook removal is realized.
  • the staff can pull the rope from the ground to realize the hook removal without climbing. To the top of the column, avoiding the safety risk when climbing the ladder.
  • Fig. 1 is a schematic structural view of a column hoisting tool according to Embodiment 1 of the present invention
  • the first steel plate 2. The second steel plate, 3. The connecting steel plate, 4. Lifting hole, 5. The first rod section, 6. The second rod section, 7. Spring, 8. Lifting parts, 9. The first Two anti-off parts, 10. The first anti-off parts.
  • This embodiment provides a column hoisting tool, as shown in Figure 1, including a first part and a second part.
  • the first part and the second part adopt a plate structure, for the convenience of material collection and processing , the first component adopts the first steel plate 1, the second component adopts the second steel plate 2, the first steel plate 1 and the second steel plate 2 are arranged in parallel, and the first steel plate 1 and the second steel plate 2 are connected by a connecting piece
  • the connector adopts a connecting steel plate 3
  • the connecting steel plate 3 can be provided with one or more pieces.
  • the first steel plate 1 and one side of the connecting steel plate 3 are welded and fixed, and the other side of the connecting steel plate 3 is connected to the second steel plate. 2 welding fixed.
  • the first steel plate 1 and the second steel plate 2 adopt rectangular steel plates or square steel plates or steel plates of other shapes, which can be selected by those skilled in the art according to actual needs. Partially entered on demand.
  • the connecting steel plate 3 is welded and fixed at the middle position between the first steel plate 1 and the second steel plate 2 .
  • the upper part of the first steel plate 1 and the second steel plate 2 is provided with a lifting hole 4, the lifting hole 4 on the first steel plate 1 and the second steel plate 2 is coaxially arranged, and the lifting hole 4 is connected with the wire rope under the hook of the lifting equipment.
  • the snap ring connected with the cable matches, and the snap ring can be connected with the first steel plate 1 and the second steel plate 2 through the lifting hole 4 .
  • the hoisting tool also includes a third component, the third component is fixed to the first steel plate 1 or the third component is fixed to the second steel plate 2 or the third component is fixed to both the first steel plate 1 and the second steel plate 2 .
  • the third component is fixed to the second steel plate 2 .
  • the third part adopts a rod-shaped structure, and for the convenience of obtaining materials, the third part is made of steel bars.
  • the third component is an L-shaped rod-shaped structure formed by bending steel bars at 90°, including a first rod segment 5 and a second rod segment 6, and one end of the first rod segment 5 is connected to the second rod segment.
  • the second steel plate 2 is welded and fixed, and the other end of the second rod section 5 is integrally connected with one end of the second rod section 6 .
  • the third part can also adopt an arc-shaped rod or the third part can adopt a plate-shaped structure, for example, the third part can adopt an L-shaped plate or an arc-shaped plate, and those skilled in the art can set it according to actual needs .
  • the third component is welded at the welding position between the second steel plate 2 and the connecting piece.
  • the second rod section 6 of the third component is connected to one end of the elastic member, and the other end of the elastic member is connected to the lifting member.
  • the elastic member adopts a spring 7 , one end of the spring 7 is fixedly connected to the second rod segment, and the other end of the spring 7 is connected to the lifting member 8 , which can exert elastic force on the lifting member 8 .
  • the lifting member 8 can pass through the hoisting hole at the top of the column, so as to apply a lifting load to the column.
  • Bottoms of the first steel plate 1 and the second steel plate 2 are provided with openings, the openings are matched with the lifting piece 8, and the lifting piece can pass through the first steel plate 1 and the second steel plate 2 through the opening.
  • the lifting member 8 adopts a polished rod or a threaded rod, and one end of the lifting member 8 is provided with a second anti-off part 9, and the second anti-off part adopts a cylindrical structure, and the outer diameter of the cylindrical structure is Larger than the diameter of the opening, the second anti-loosening component 9 can contact the side of the second steel plate 2 welded with the third component, thereby preventing the lifting member 8 from detaching from the second steel plate.
  • the spring 7 is connected with the lifting piece through the second release part 9 .
  • the lifting member 8 adopts a lifting bolt, and the head of the lifting bolt can be used as the second anti-loosening component, and there is no need to additionally weld the second anti-loosening component 9 .
  • the other end of the lifting part 8 is provided with a jack, through which a first anti-off part 10 is passed, and the first anti-off part 10 adopts an anti-off bar, and the length of the anti-off bar is greater than the diameter of the opening , the anti-loosening rod can be in contact with the side of the first steel plate 1 away from the second steel plate 2, thereby preventing the lifting member 8 from detaching from the first steel plate.
  • anti-off rod is provided with connecting hole, and anti-off rod is tied and fixed with one end of stay rope by connecting hole, and the staff pulls stay cord, and anti-off rod can be separated with hoisting part 8.
  • the drawstring is a soft rope.
  • connection position between the spring 7 and the second rod segment 6 is located at the distance between the first steel plate 1 and the second steel plate 2. on the axis of the hole.
  • the length of the stay rope is greater than the height of the column to be hoisted.
  • the first steel plate 1 and the second steel plate 2 are connected through the snap ring connected by the steel wire rope under the hoisting hole 4 hoisting equipment hook of the upper part.
  • the hoisting part of the column Extend into the space between the first steel plate 1 and the second steel plate 2, the hoisting part of the column has a hoisting hole, after passing the lifting part 8 through the second steel plate 2, the hoisting part of the column and the first steel plate 1 in sequence, the lifting part
  • the end of the first steel plate 1 is inserted into the first anti-off component 10, and the first anti-off component 10 and the second anti-off component 9 can prevent the lifting member 8 from detaching from the first steel plate 1 and the second steel plate 2.
  • the construction personnel pull the stay rope on the ground, and pull the first anti-off part 10 out of the lifting part 8 through the stay cord, so that the lifting part 8 is separated from the first anti-off part 10, and under the action of the elastic force of the spring 7
  • the lifting part 8 leaves the hoisting part of the first steel plate 1, the second steel plate 2 and the column through the openings on the first steel plate 1 and the second steel plate 2, and the hook removal is completed.
  • the lifting device can be used to hoist the column The tool is placed in the set position for the next use.
  • the construction personnel only need to pull the pull rope on the ground to complete the hook removal operation.
  • the hook can be removed by pulling the pull rope on the ground, without the need to climb to the top of the column, avoiding the safety risk when climbing the ladder.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Ladders (AREA)

Abstract

The present invention relates to a vertical-column hoisting tool and an operating method therefor. The vertical-column hoisting tool comprises a first component and a second component, which are connected as one by means of a connecting member, and further comprises a third component, wherein the third component is fixedly connected to the first component and/or the second component, the third component is fixed to one end of an elastic member, the other end of the elastic member is connected to one end of a hoisting member, the first component and the second component are provided with openings for the hoisting member to pass therethrough, the other end of the hoisting member passes through a first anti-drop component, and the first anti-drop component is connected to a pull rope. By means of the vertical column hoisting tool of the present invention, the process of unhooking is highly efficient and has a good degree of safety.

Description

一种立柱吊装工具及工作方法A column hoisting tool and working method 技术领域technical field
本发明涉及起重吊装技术领域,具体涉及一种立柱吊装工具及工作方法。The invention relates to the technical field of lifting and hoisting, in particular to a column hoisting tool and a working method.
背景技术Background technique
立柱在吊装前需要在立柱顶端搭设摘钩用脚手架,并自立柱顶端至立柱底部铺设爬梯即自锁器供施工人员上下;用卡环将钢丝绳与立柱顶端连接并起吊,就位后施工人员顺着爬梯到立柱顶端的脚手架上将卡环卸掉松钩。Before the column is hoisted, it is necessary to set up a scaffold for unhooking at the top of the column, and lay a ladder from the top of the column to the bottom of the column, that is, a self-locking device for construction personnel to go up and down; use a snap ring to connect the wire rope to the top of the column and lift it. Go up the ladder to the scaffold at the top of the column and remove the snap ring and loose hook.
技术问题technical problem
发明人发现,传统施工方法吊装立柱时有如下缺点:The inventor found that the traditional construction method has the following disadvantages when hoisting the column:
1.施工前需要提前搭设脚手架、爬梯、自锁器等,耗费人力物力。1. Before construction, it is necessary to set up scaffolding, ladders, self-locking devices, etc. in advance, which consumes manpower and material resources.
2.施工过程中需要施工人员攀爬到立柱顶端,过程中存在安全风险。2. During the construction process, construction personnel need to climb to the top of the column, and there are safety risks in the process.
3.钢梁吊装过程中立柱较多,传统逐一摘钩方法施工时间较长。3. There are many columns in the hoisting process of the steel beam, and the traditional method of unhooking one by one takes a long time.
技术解决方案technical solution
本发明的目的是为克服现有技术的不足,提供了一种立柱吊装工具,无需施工人员爬到立柱顶端进行摘钩,工作效率高,避免了爬梯时的安全风险。The object of the present invention is to overcome the deficiencies of the prior art and provide a column hoisting tool, which does not require construction personnel to climb to the top of the column to remove hooks, has high work efficiency, and avoids safety risks when climbing ladders.
为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
第一方面,本发明的实施例提供了一种立柱吊装工具,包括通过连接件连接为整体的第一部件和第二部件,还包括第三部件,第三部件与第一部件和/或第二部件固定连接,第三部件与弹性件的一端固定,弹性件的另一端与起吊件的一端连接,第一部件及第二部件设有用于起吊件穿过的开孔,起吊件的另一端穿过有第一防脱部件,第一防脱件与拉绳连接。In the first aspect, an embodiment of the present invention provides a column lifting tool, including a first part and a second part connected as a whole through a connecting piece, and a third part, the third part and the first part and/or the second part The two parts are fixedly connected, the third part is fixed to one end of the elastic part, the other end of the elastic part is connected to one end of the lifting part, the first part and the second part are provided with openings for the lifting part to pass through, and the other end of the lifting part The first anti-off part passes through, and the first anti-off part is connected with the pull cord.
可选的,所述第一部件和第二部件为板状结构,且第一部件和第二部件平行设置。Optionally, the first component and the second component are plate-like structures, and the first component and the second component are arranged in parallel.
可选的,所述第一部件和第二部件设置有能够与起吊设备吊钩下钢丝绳索连接的卡环相配合的起吊孔。Optionally, the first part and the second part are provided with hoisting holes capable of cooperating with snap rings connected with steel wire ropes under the hooks of the hoisting equipment.
可选的,所述起吊孔设置在第一部件和第二部件的一端,起吊件通过第一部件和第二部件的另一端穿过第一部件和第二部件。Optionally, the lifting hole is provided at one end of the first part and the second part, and the lifting part passes through the first part and the second part through the other end of the first part and the second part.
可选的,所述起吊件用于与弹性件连接的端部设有第二防脱部件,第二防脱部件与弹性件的端部连接。Optionally, the end of the lifting member used to connect with the elastic member is provided with a second anti-off component, and the second anti-off component is connected to the end of the elastic component.
可选的,所述起吊件端部设有通孔,所述第一防脱部件通过所述通孔穿过起吊件。Optionally, a through hole is provided at the end of the lifting member, and the first anti-off component passes through the lifting member through the through hole.
可选的,所述第三部件为杆状结构,包括第一杆段,第一杆段一端与第一部件或第二部件固定,第一杆段的另一端与第二杆段的一端垂直连接,弹性件与第二杆段连接。Optionally, the third part is a rod-shaped structure, including a first rod segment, one end of the first rod segment is fixed to the first part or the second part, and the other end of the first rod segment is perpendicular to one end of the second rod segment connected, the elastic member is connected with the second rod segment.
可选的,所述第一防脱部件的端部设有连接孔,第一防脱部件通过连接孔与拉绳连接。Optionally, a connection hole is provided at the end of the first anti-loosening component, and the first anti-loosening component is connected to the pull cord through the connection hole.
可选的,所述拉绳的长度大于待吊装的立柱的高度。Optionally, the length of the stay rope is greater than the height of the column to be hoisted.
第二方面,本发明的实施例提供了一种立柱吊装工具的工作方法:起吊件穿过第一部件、立柱顶端及第二部件后,在起吊件端部插入第一防脱部件,将起吊件与起吊设备连接,利用起吊设备对立柱进行吊装,立柱吊装完成后,拉动拉绳,使得第一防脱部件与起吊件脱离,在弹性件的作用下,起吊件与第一部件、第二部件及立柱分离,完成摘钩。In the second aspect, the embodiment of the present invention provides a working method of a column hoisting tool: After the lifting piece passes through the first component, the top of the column and the second component, insert the first anti-off component at the end of the lifting piece, and then lift the The lifting device is connected with the lifting device, and the column is hoisted by the lifting device. After the column is hoisted, the pull rope is pulled to make the first anti-off part and the lifting part separate. Under the action of the elastic part, the lifting part and the first part, the second The parts and columns are separated to complete the unhooking.
有益效果Beneficial effect
本发明的立柱吊装工具,进行摘钩时,只需要施工人员拉动拉绳,使得第一防脱件与起吊件脱离,在弹性件的作用下,起吊件会与第一部件、第二部件及吊装好的立柱分离,进而实现了摘钩,施工时无需搭设脚手架、拉设自锁器等工序,省时省力,施工效果高,而且工作人员从地面拉动拉绳即可实现摘钩,无需爬到立柱顶端,避免了爬梯时的安全风险。In the column hoisting tool of the present invention, when unhooking, the construction personnel only need to pull the stay rope so that the first anti-detachment part is separated from the lifting part. The hoisted column is separated, and then the hook removal is realized. During the construction, there is no need to set up scaffolding, pull the self-locking device and other processes, saving time and effort, and the construction effect is high. In addition, the staff can pull the rope from the ground to realize the hook removal without climbing. To the top of the column, avoiding the safety risk when climbing the ladder.
附图说明Description of drawings
构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的限定。The accompanying drawings constituting a part of the present application are used to provide further understanding of the present application, and the schematic embodiments and descriptions of the present application are used to explain the present application and not to limit the present application.
图1为本发明实施例1立柱吊装工具结构示意图;Fig. 1 is a schematic structural view of a column hoisting tool according to Embodiment 1 of the present invention;
其中,1.第一钢板,2.第二钢板,3.连接钢板,4.起吊孔,5.第一杆段,6.第二杆段,7.弹簧,8.起吊件,9.第二防脱部件,10.第一防脱部件。Among them, 1. The first steel plate, 2. The second steel plate, 3. The connecting steel plate, 4. Lifting hole, 5. The first rod section, 6. The second rod section, 7. Spring, 8. Lifting parts, 9. The first Two anti-off parts, 10. The first anti-off parts.
本发明的最佳实施方式BEST MODE FOR CARRYING OUT THE INVENTION
本实施例提供了一种立柱吊装工具,如图1所示,包括第一部件和第二部件,本实施例中,所述第一部件和第二部件采用板状结构,为了取材和加工方便,所述第一部件采用第一钢板1,所述第二部件采用第二钢板2,第一钢板1和第二钢板2平行设置,所述第一钢板1和第二钢板2通过连接件连接成为一个整体,所述连接件采用连接钢板3,所述连接钢板3可设置一块或多块,第一钢板1与连接钢板3的一侧面焊接固定,连接钢板3的另一侧面与第二钢板2焊接固定。This embodiment provides a column hoisting tool, as shown in Figure 1, including a first part and a second part. In this embodiment, the first part and the second part adopt a plate structure, for the convenience of material collection and processing , the first component adopts the first steel plate 1, the second component adopts the second steel plate 2, the first steel plate 1 and the second steel plate 2 are arranged in parallel, and the first steel plate 1 and the second steel plate 2 are connected by a connecting piece As a whole, the connector adopts a connecting steel plate 3, and the connecting steel plate 3 can be provided with one or more pieces. The first steel plate 1 and one side of the connecting steel plate 3 are welded and fixed, and the other side of the connecting steel plate 3 is connected to the second steel plate. 2 welding fixed.
所述第一钢板1和第二钢板2采用矩形钢板或正方形钢板或其他形状的钢板,本领域技术人员可根据实际需要进行选择,第一钢板1和第二钢板2之间的距离满足立柱吊装部分进入的需求。The first steel plate 1 and the second steel plate 2 adopt rectangular steel plates or square steel plates or steel plates of other shapes, which can be selected by those skilled in the art according to actual needs. Partially entered on demand.
优选的,所述连接钢板3焊接固定在第一钢板1和第二钢板2之间的中部位置。Preferably, the connecting steel plate 3 is welded and fixed at the middle position between the first steel plate 1 and the second steel plate 2 .
所述第一钢板1和第二钢板2的上部设置有起吊孔4,第一钢板1和第二钢板2上的起吊孔4同轴设置,且所述起吊孔4与起吊设备吊钩下钢丝绳索连接的卡环相匹配,所述卡环能够通过起吊孔4与第一钢板1和第二钢板2连接。The upper part of the first steel plate 1 and the second steel plate 2 is provided with a lifting hole 4, the lifting hole 4 on the first steel plate 1 and the second steel plate 2 is coaxially arranged, and the lifting hole 4 is connected with the wire rope under the hook of the lifting equipment. The snap ring connected with the cable matches, and the snap ring can be connected with the first steel plate 1 and the second steel plate 2 through the lifting hole 4 .
所述吊装工具还包括第三部件,所述第三部件与第一钢板1固定或第三部件与第二钢板2固定或第三部件与第一钢板1和第二钢板2均固定。The hoisting tool also includes a third component, the third component is fixed to the first steel plate 1 or the third component is fixed to the second steel plate 2 or the third component is fixed to both the first steel plate 1 and the second steel plate 2 .
本实施例中,所述第三部件与第二钢板2固定。In this embodiment, the third component is fixed to the second steel plate 2 .
所述第三部件采用杆状结构,为了取材方便,所述第三部件采用钢筋制成。The third part adopts a rod-shaped structure, and for the convenience of obtaining materials, the third part is made of steel bars.
本实施例中,所述第三部件为采用钢筋折弯90°后形成的L型杆状结构,包括第一杆段5和第二杆段6,所述第一杆段5的一端与第二钢板2焊接固定,第二杆段5的另一端与第二杆段6的一端一体式连接。In this embodiment, the third component is an L-shaped rod-shaped structure formed by bending steel bars at 90°, including a first rod segment 5 and a second rod segment 6, and one end of the first rod segment 5 is connected to the second rod segment. The second steel plate 2 is welded and fixed, and the other end of the second rod section 5 is integrally connected with one end of the second rod section 6 .
在其他一些实施例中,所述第三部件也可采用弧形杆或者第三部件采用板状结构,例如第三部件采用L型板或弧形板,本领域技术人员可根据实际需要进行设置。In some other embodiments, the third part can also adopt an arc-shaped rod or the third part can adopt a plate-shaped structure, for example, the third part can adopt an L-shaped plate or an arc-shaped plate, and those skilled in the art can set it according to actual needs .
进一步的,为了保证第三部件的承载力需求,所述第三部件焊接在第二钢板2与连接件的焊接位置处。Further, in order to ensure the bearing capacity requirements of the third component, the third component is welded at the welding position between the second steel plate 2 and the connecting piece.
所述第三部件的第二杆段6与弹性件的一端连接,弹性件的另一端与起吊件连接。The second rod section 6 of the third component is connected to one end of the elastic member, and the other end of the elastic member is connected to the lifting member.
本实施例中,所述弹性件采用弹簧7,所述弹簧7一端与第二杆段固定连接,弹簧7的另一端与起吊件8连接,能够对起吊件8施加弹性力。In this embodiment, the elastic member adopts a spring 7 , one end of the spring 7 is fixedly connected to the second rod segment, and the other end of the spring 7 is connected to the lifting member 8 , which can exert elastic force on the lifting member 8 .
所述起吊件8能够穿过立柱顶部的吊装孔,从而对立柱施加起升荷载。The lifting member 8 can pass through the hoisting hole at the top of the column, so as to apply a lifting load to the column.
所述第一钢板1和第二钢板2的底部设置有开孔,所述开孔与起吊件8相匹配,起吊件能够通过开孔穿过第一钢板1和第二钢板2。Bottoms of the first steel plate 1 and the second steel plate 2 are provided with openings, the openings are matched with the lifting piece 8, and the lifting piece can pass through the first steel plate 1 and the second steel plate 2 through the opening.
本实施例中,所述起吊件8采用光杆或螺纹杆,所述起吊件8的一端设置有第二防脱部件9,所述第二防脱部件采用柱形结构,柱形结构的外径大于开孔的直径,第二防脱部件9能够与第二钢板2焊接第三部件的侧面接触,从而防止起吊件8与第二钢板脱离。所述弹簧7通过第二放脱部件9与起吊件连接。In this embodiment, the lifting member 8 adopts a polished rod or a threaded rod, and one end of the lifting member 8 is provided with a second anti-off part 9, and the second anti-off part adopts a cylindrical structure, and the outer diameter of the cylindrical structure is Larger than the diameter of the opening, the second anti-loosening component 9 can contact the side of the second steel plate 2 welded with the third component, thereby preventing the lifting member 8 from detaching from the second steel plate. The spring 7 is connected with the lifting piece through the second release part 9 .
本实施例中,为了取材方便,所述起吊件8采用起吊螺栓,所述起吊螺栓的头部即可作为第二防脱部件,无需再额外焊接第二防脱部件9。In this embodiment, for the convenience of obtaining materials, the lifting member 8 adopts a lifting bolt, and the head of the lifting bolt can be used as the second anti-loosening component, and there is no need to additionally weld the second anti-loosening component 9 .
所述起吊件8的另一端设有插孔,通过插孔穿过有第一防脱部件10,所述第一防脱部件10采用防脱杆,所述防脱杆长度大于开孔的直径,防脱杆能够与第一钢板1的背离第二钢板2的侧面接触,进而防止起吊件8从第一钢板上脱离。The other end of the lifting part 8 is provided with a jack, through which a first anti-off part 10 is passed, and the first anti-off part 10 adopts an anti-off bar, and the length of the anti-off bar is greater than the diameter of the opening , the anti-loosening rod can be in contact with the side of the first steel plate 1 away from the second steel plate 2, thereby preventing the lifting member 8 from detaching from the first steel plate.
所述防脱杆的一端设有连接孔,防脱杆通过连接孔与拉绳的一端绑扎固定,工作人员拉动拉绳,能够将防脱杆与起吊件8分离。优选的,所述拉绳采用软绳。One end of described anti-off rod is provided with connecting hole, and anti-off rod is tied and fixed with one end of stay rope by connecting hole, and the staff pulls stay cord, and anti-off rod can be separated with hoisting part 8. Preferably, the drawstring is a soft rope.
进一步的,为了方便弹簧7将起吊件8拉出至与第一钢板1和第二钢板2分离,所述弹簧7与第二杆段6的连接位置位于第一钢板1和第二钢板2开孔的轴线上。Further, in order to facilitate the spring 7 to pull the lifting member 8 out to separate from the first steel plate 1 and the second steel plate 2, the connection position between the spring 7 and the second rod segment 6 is located at the distance between the first steel plate 1 and the second steel plate 2. on the axis of the hole.
进一步的,为了方便施工人员拉动拉绳,所述拉绳的长度大于待吊装的立柱的高度。Further, in order to facilitate construction personnel to pull the stay rope, the length of the stay rope is greater than the height of the column to be hoisted.
本实施例的立柱吊装工具使用方法为:The usage method of the column hoisting tool of the present embodiment is as follows:
将第一钢板1和第二钢板2通过其上部的起吊孔4起吊设备吊钩下钢丝绳索连接的卡环连接,所述起吊设备采用现有的吊车即可,将待吊装的立柱的吊装部分伸入第一钢板1和第二钢板2之间的空间,立柱的吊装部分具有吊装孔,将起吊件8依次穿过第二钢板2、立柱的吊装部分及第一钢板1后,将起吊件穿出第一钢板1的端部插入第一防脱部件10,通过第一防脱部件10和第二防脱部件9能够防止起吊件8从第一钢板1和第二钢板2上脱离。The first steel plate 1 and the second steel plate 2 are connected through the snap ring connected by the steel wire rope under the hoisting hole 4 hoisting equipment hook of the upper part. Extend into the space between the first steel plate 1 and the second steel plate 2, the hoisting part of the column has a hoisting hole, after passing the lifting part 8 through the second steel plate 2, the hoisting part of the column and the first steel plate 1 in sequence, the lifting part The end of the first steel plate 1 is inserted into the first anti-off component 10, and the first anti-off component 10 and the second anti-off component 9 can prevent the lifting member 8 from detaching from the first steel plate 1 and the second steel plate 2.
此时利用起吊件8对立柱进行支撑,利用起吊设备对立柱进行吊装。Utilize the hoisting part 8 to support the column now, and utilize the hoisting equipment to hoist the column.
当立柱吊装完成后,施工人员在地面拉动拉绳,通过拉绳将第一防脱部件10拉出起吊件8,使得起吊件8与第一防脱部件10分离,在弹簧7的弹性力作用下,起吊件8通过第一钢板1和第二钢板2上的开孔离开第一钢板1和第二钢板2及立柱的吊装部分,完成了摘钩,此时可利用起到设备将立柱吊装工具放置到设定位置以便于下一次使用。After the hoisting of the column is completed, the construction personnel pull the stay rope on the ground, and pull the first anti-off part 10 out of the lifting part 8 through the stay cord, so that the lifting part 8 is separated from the first anti-off part 10, and under the action of the elastic force of the spring 7 Next, the lifting part 8 leaves the hoisting part of the first steel plate 1, the second steel plate 2 and the column through the openings on the first steel plate 1 and the second steel plate 2, and the hook removal is completed. At this time, the lifting device can be used to hoist the column The tool is placed in the set position for the next use.
采用本实施例的吊装工具,只需要施工人员在地面拉动拉绳即可完成摘钩操作,施工时无需搭设脚手架、拉设自锁器等工序,省时省力,施工效果高,而且工作人员从地面拉动拉绳即可实现摘钩,无需爬到立柱顶端,避免了爬梯时的安全风险。With the hoisting tool of this embodiment, the construction personnel only need to pull the pull rope on the ground to complete the hook removal operation. During construction, there is no need to set up scaffolding, pull and set up self-locking devices, etc., which saves time and effort, and the construction effect is high. The hook can be removed by pulling the pull rope on the ground, without the need to climb to the top of the column, avoiding the safety risk when climbing the ladder.
上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Although the specific implementation of the present invention has been described above in conjunction with the accompanying drawings, it does not limit the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art do not need to pay creative work Various modifications or variations that can be made are still within the protection scope of the present invention.

Claims (8)

  1. 一种立柱吊装工具,其特征在于,包括通过连接件连接为整体的第一部件和第二部件,还包括第三部件,第三部件与第一部件和/或第二部件固定连接,第三部件与弹性件的一端固定,弹性件的另一端与起吊件的一端连接,第一部件及第二部件设有用于起吊件穿过的开孔,起吊件的另一端穿过有第一防脱部件,第一防脱件与拉绳连接;所述第一部件和第二部件设置有能够与起吊设备吊钩下钢丝绳索连接的卡环相配合的起吊孔;所述起吊孔设置在第一部件和第二部件的一端,起吊件通过第一部件和第二部件的另一端穿过第一部件和第二部件。A column lifting tool, characterized in that it includes a first part and a second part connected as a whole through a connecting piece, and also includes a third part, the third part is fixedly connected with the first part and/or the second part, and the third part The part is fixed with one end of the elastic part, and the other end of the elastic part is connected with one end of the lifting part. The first part and the second part are provided with openings for the lifting part to pass through, and the other end of the lifting part is passed through with a first anti-off The first part is connected with the pull rope; the first part and the second part are provided with a lifting hole that can be matched with the snap ring connected to the wire rope under the hook of the lifting device; the lifting hole is arranged on the first part and one end of the second part, the lifting part passes through the first part and the second part through the other end of the second part.
  2. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述第一部件和第二部件为板状结构,且第一部件和第二部件平行设置。The column lifting tool according to claim 1, wherein the first part and the second part are plate-shaped structures, and the first part and the second part are arranged in parallel.
  3. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述起吊件用于与弹性件连接的端部设有第二防脱部件,第二防脱部件与弹性件的端部连接。A column hoisting tool according to claim 1, characterized in that, the end of the lifting member used to connect with the elastic member is provided with a second anti-off component, and the second anti-off component is connected to the end of the elastic component .
  4. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述起吊件端部设有通孔,所述第一防脱部件通过所述通孔穿过起吊件。The column lifting tool according to claim 1, wherein a through hole is provided at the end of the lifting member, and the first anti-off component passes through the lifting member through the through hole.
  5. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述第三部件为杆状结构,包括第一杆段,第一杆段一端与第一部件或第二部件固定,第一杆段的另一端与第二杆段的一端垂直连接,弹性件与第二杆段连接。A column lifting tool according to claim 1, wherein the third part is a rod-shaped structure, including a first rod section, one end of the first rod section is fixed to the first part or the second part, and the first The other end of the pole section is vertically connected with one end of the second pole section, and the elastic member is connected with the second pole section.
  6. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述第一防脱部件的端部设有连接孔,第一防脱部件通过连接孔与拉绳连接。The column lifting tool according to claim 1, wherein a connection hole is provided at the end of the first anti-off component, and the first anti-off component is connected to the pull rope through the connection hole.
  7. 如权利要求1所述的一种立柱吊装工具,其特征在于,所述拉绳的长度大于待吊装的立柱的高度。A column hoisting tool according to claim 1, wherein the length of the stay rope is greater than the height of the column to be hoisted.
  8. 一种权利要求1-7任一项所述的立柱吊装工具的工作方法,其特征在于,起吊件穿过第一部件、立柱顶端及第二部件后,在起吊件端部插入第一防脱部件,将起吊件与起吊设备连接,利用起吊设备对立柱进行吊装,立柱吊装完成后,拉动拉绳,使得第一防脱部件与起吊件脱离,在弹性件的作用下,起吊件与第一部件、第二部件及立柱分离,完成摘钩。A working method for a column hoisting tool according to any one of claims 1-7, characterized in that, after the lifting piece passes through the first part, the top of the column and the second part, the first anti-off position is inserted into the end of the lifting piece. Components, connect the lifting piece with the lifting equipment, use the lifting equipment to hoist the column, after the column is hoisted, pull the pull rope, so that the first anti-off part is separated from the lifting piece, under the action of the elastic piece, the lifting piece and the first The component, the second component and the column are separated to complete the unhooking.
PCT/CN2022/111435 2021-11-01 2022-08-10 Vertical-column hoisting tool, and operating method therefor WO2023071385A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202111284008.1 2021-11-01
CN202111284008.1A CN113955632A (en) 2021-11-01 2021-11-01 Upright column hoisting tool and working method

Publications (1)

Publication Number Publication Date
WO2023071385A1 true WO2023071385A1 (en) 2023-05-04

Family

ID=79468686

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/111435 WO2023071385A1 (en) 2021-11-01 2022-08-10 Vertical-column hoisting tool, and operating method therefor

Country Status (2)

Country Link
CN (1) CN113955632A (en)
WO (1) WO2023071385A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113955632A (en) * 2021-11-01 2022-01-21 中国电建集团山东电力建设第一工程有限公司 Upright column hoisting tool and working method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08277090A (en) * 1995-04-06 1996-10-22 Sekisui Chem Co Ltd Hoisting structure of column
CN202744163U (en) * 2012-05-31 2013-02-20 天津二十冶建设有限公司 Semi-automatic unhooking lifting device
CN203392725U (en) * 2013-06-05 2014-01-15 中国石油天然气集团公司 Hoisting shackle for ground operation
CN106744310A (en) * 2017-02-22 2017-05-31 湖北创联重工有限公司 A kind of large-scale steel structure column hanging method
JP2017128409A (en) * 2016-01-19 2017-07-27 日新製鋼株式会社 Suspension device
CN107215765A (en) * 2017-06-15 2017-09-29 中国二十冶集团有限公司 Lift shackle
CN108946445A (en) * 2018-09-28 2018-12-07 中石化重型起重运输工程有限责任公司 A kind of shackle of remote ready removal
CN209957207U (en) * 2019-04-03 2020-01-17 北京城建集团有限责任公司 Unhooking device for hoisting steel structure stand column
CN113955632A (en) * 2021-11-01 2022-01-21 中国电建集团山东电力建设第一工程有限公司 Upright column hoisting tool and working method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN212639704U (en) * 2020-04-14 2021-03-02 江苏省苏中建设集团股份有限公司 Bolt type lifting appliance for columns of single-layer industrial factory building

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08277090A (en) * 1995-04-06 1996-10-22 Sekisui Chem Co Ltd Hoisting structure of column
CN202744163U (en) * 2012-05-31 2013-02-20 天津二十冶建设有限公司 Semi-automatic unhooking lifting device
CN203392725U (en) * 2013-06-05 2014-01-15 中国石油天然气集团公司 Hoisting shackle for ground operation
JP2017128409A (en) * 2016-01-19 2017-07-27 日新製鋼株式会社 Suspension device
CN106744310A (en) * 2017-02-22 2017-05-31 湖北创联重工有限公司 A kind of large-scale steel structure column hanging method
CN107215765A (en) * 2017-06-15 2017-09-29 中国二十冶集团有限公司 Lift shackle
CN108946445A (en) * 2018-09-28 2018-12-07 中石化重型起重运输工程有限责任公司 A kind of shackle of remote ready removal
CN209957207U (en) * 2019-04-03 2020-01-17 北京城建集团有限责任公司 Unhooking device for hoisting steel structure stand column
CN113955632A (en) * 2021-11-01 2022-01-21 中国电建集团山东电力建设第一工程有限公司 Upright column hoisting tool and working method

Also Published As

Publication number Publication date
CN113955632A (en) 2022-01-21

Similar Documents

Publication Publication Date Title
CN102900021B (en) Split mounting type bridge wet joint construction method
WO2023071385A1 (en) Vertical-column hoisting tool, and operating method therefor
CN204675621U (en) A kind of shackle for rapid unhooking in tubing string lifting
CN205693247U (en) Multi-functional transmission rope hanger
CN209957207U (en) Unhooking device for hoisting steel structure stand column
CN207566717U (en) A kind of I-shaped floor steel beam lifting structure
CN202488034U (en) Lifting device for electric transmission line of angle iron tower
CN205527435U (en) Installation and device of dismantling jib loading boom
CN217555572U (en) Combined type hoisting device for I-shaped steel beam
CN115838118A (en) Device convenient to hang jack-up suspender at eminence
CN208964367U (en) A kind of safe and simple vertical support hanging apparatus
CN209835410U (en) Device for quick aerial tripping in steel structure hoisting
CN210973530U (en) Hoisting clamp for grating window
CN109987501A (en) A kind of device threaded off in Quick air in steel structure hoisting and tripping method
CN216588482U (en) Workover rig guy rope safety rope telescopic connection device
CN211813028U (en) Special lifting appliance for spiral steel bar
CN211496553U (en) Steel member hoist and mount anticreep device and hoist device who uses thereof
CN216105529U (en) Semi-automatic pin-disengaging type shackle device
CN213143815U (en) Construction hanging flower basket is restoreed in eaves mouth high altitude that encorbelments of metal roofing
CN210655838U (en) Building block handling fixture device
CN210105273U (en) Electromagnetic valve detacher for anti-falling test
CN203173742U (en) Hydraulic hoister steel strand integral threading mechanism
CN217600182U (en) Box post hoist and mount splint formula hoist
CN212503587U (en) One-hook multi-hoisting device for easy-to-dismount support of section steel beam
CN219449103U (en) Secondary beam lifting device

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22885285

Country of ref document: EP

Kind code of ref document: A1