WO2022254704A1 - 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体 - Google Patents

基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体 Download PDF

Info

Publication number
WO2022254704A1
WO2022254704A1 PCT/JP2021/021406 JP2021021406W WO2022254704A1 WO 2022254704 A1 WO2022254704 A1 WO 2022254704A1 JP 2021021406 W JP2021021406 W JP 2021021406W WO 2022254704 A1 WO2022254704 A1 WO 2022254704A1
Authority
WO
WIPO (PCT)
Prior art keywords
work
additional
board production
equipment
board
Prior art date
Application number
PCT/JP2021/021406
Other languages
English (en)
French (fr)
Inventor
裕昭 片井
Original Assignee
ヤマハ発動機株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ヤマハ発動機株式会社 filed Critical ヤマハ発動機株式会社
Priority to PCT/JP2021/021406 priority Critical patent/WO2022254704A1/ja
Publication of WO2022254704A1 publication Critical patent/WO2022254704A1/ja

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing

Definitions

  • the present invention relates to technology for managing the execution of work for the production of component-mounted boards, which are boards on which components are mounted.
  • the present invention has been made in view of the above-mentioned problems, and it is an object of the present invention to enable efficient operation of a production site by appropriately responding to an accelerated progress of work for the production of component-mounted boards. do.
  • a board production management apparatus comprises: a plan acquisition unit for acquiring a work execution plan indicating a plan for executing a predetermined work for producing a component-mounted board, which is a board on which components are mounted; a work instruction unit for instructing execution of the additional work when it is determined that additional work different from the predetermined work can be executed based on the result of confirming whether or not progress is made with respect to the work execution plan.
  • a board production management method includes a step of acquiring a work execution plan indicating a plan for executing a predetermined work for producing a component-mounted board, which is a board on which components are mounted, and and if it is determined that an additional work different from the predetermined work can be executed based on the result of confirming whether or not progress is made with respect to the plan, the step of instructing execution of the additional work.
  • a board production management program includes steps of acquiring a work execution plan indicating a plan for executing a predetermined work for producing a component-mounted board, which is a board on which components are mounted, and When it is determined that an additional work different from the predetermined work can be performed based on the result of confirming whether or not progress is made with respect to the plan, instructing the execution of the additional work to be performed by the computer.
  • a recording medium records the above board production management program so that it can be read by a computer.
  • the predetermined work includes equipment work performed by the board production equipment for mounting components on the board
  • the work execution plan includes an equipment work execution plan indicating a plan for performing the equipment work by the board production equipment
  • the additional work includes additional equipment work that is different from equipment work
  • the work instruction department confirms whether the progress of the equipment work is progressing according to the equipment work execution plan.
  • the board production management apparatus may be configured to instruct the board production equipment to execute the additional equipment work.
  • the work instruction unit determines that the additional equipment work can be performed based on the result of the equipment work progress confirmation, the work instruction unit instructs the board production equipment to perform the additional equipment work after completing the equipment work.
  • a management device may be configured. With such a configuration, the board production equipment can perform the additional equipment work after surely completing the equipment work that should be originally performed.
  • equipment work is component mounting work for mounting components on a predetermined number of substrates.
  • the specific content of equipment work can be considered in various ways.
  • the additional equipment work may be work for performing maintenance on the substrate production equipment, or may be work performed to educate workers about maintenance or operation of the substrate production equipment.
  • the predetermined work includes an auxiliary work that assists the board production equipment for mounting components on the board
  • the work execution plan includes an auxiliary work execution plan that indicates a plan for executing the auxiliary work by the work subject in charge of the auxiliary work.
  • the additional work includes additional auxiliary work different from the auxiliary work
  • the work instruction unit confirms whether the progress of the auxiliary work is progressing with respect to the auxiliary work execution plan
  • the board production management apparatus may be configured to instruct the work subject to perform the additional auxiliary work when it is determined that the additional auxiliary work can be executed.
  • the work subject can be caused to perform the additional auxiliary work, thereby improving the operating rate of the work subject.
  • the work instruction unit determines that the additional auxiliary work can be executed based on the result of the auxiliary work progress confirmation
  • the work instruction unit instructs the work subject to execute the additional auxiliary work after completing the auxiliary work.
  • the auxiliary work is the work of supplying components to the board production equipment.
  • the additional auxiliary work may be a work of collecting waste discharged from the board production equipment, or may be a work of preparing parts to be replenished to the board production equipment.
  • the specific content of the work subject can be considered in various ways.
  • the subject of work may be a worker or a robot.
  • FIG. 1 is a block diagram showing an example of a board production system according to the present invention
  • FIG. The front view which shows a solder printer typically.
  • the top view which shows a component mounting machine typically.
  • FIG. 2 is a block diagram showing an example of the configuration of a server computer; 4 is a flowchart showing an example of work management executed by a server computer; 6 is a flowchart showing an example of assignment of additional work executed in the work management of FIG. 5; 6 is a timing chart schematically showing an example in which the work management of FIG. 5 is applied to component mounting work; 6 is a timing chart schematically showing an example in which the work management of FIG. 5 is applied to mounting setup work; FIG.
  • FIG. 1 is a block diagram showing an example of a board production system according to the present invention.
  • the board production system 1 manages a board production line 11 for producing a component-mounted board, which is a board B (FIGS. 2 and 3) on which a component E (FIG. 3) is mounted, and the production of the component-mounted board by the board production line 11.
  • a server computer 9 is provided.
  • This board production line 11 includes a solder printer 2 , a print inspection machine 3 , a component mounting machine 4 , a mounting inspection machine 5 , a reflow furnace 6 and a board inspection machine 7 .
  • a solder printing machine 2 prints solder on the substrate B, and a print inspection machine 3 inspects the printing state of the solder by the solder printing machine 2.
  • the component mounter 4 places the component E on the solder of the board B which has been inspected for the solder printing state by the print inspection device 3, and the mounting inspection device 5 inspects the placement state of the component E by the component mounter 4. do.
  • the reflow furnace 6 melts the solder printed on the board B by heating the board B, which has been inspected for the component mounting state by the mounting inspection machine 5, and the board inspection machine 7 heats the board heated by the reflow furnace 6.
  • the mounting state of component E in B is inspected.
  • the board production system 1 thus produces component-mounted boards (board production).
  • the substrate B can be transported to the devices 2 to 7 by a transport robot such as a conveyor or an AGV (Automated Guided Vehicle), or by an operator OP.
  • a board B determined to be defective by the inspection of the print inspection machine 3 is not transported to the component mounting machine 4, and a board B determined to be defective by the inspection of the mounting inspection machine 5 is not transported to the mounting inspection machine 5.
  • the board production system 1 includes a solder storage 12 for storing solder printed on the board B by the print inspection machine 3 and a component storage 13 for storing the components E mounted on the board B by the component mounter 4.
  • a solder storage 12 for storing solder printed on the board B by the print inspection machine 3
  • a component storage 13 for storing the components E mounted on the board B by the component mounter 4.
  • parts storage 13 parts supply reels with tapes for storing parts E wound around are stored in a plurality of pockets.
  • the parts E stored on the tape are chip parts such as integrated circuits, transistors, and capacitors.
  • the delivery or receipt of solder or components E to or from the solder storage 12 or parts storage 13 is performed by an operator OP.
  • a workbench 14 that can be used by the operator OP for work is provided.
  • the server computer 9 communicates with the solder printer 2, the print inspection machine 3, the component mounting machine 4, the mounting inspection machine 5, the reflow furnace 6, the board inspection machine 7, the solder storage 12, and the component storage 13. Communication between the server computer 9 and these devices 2-7, 12, 13 can be by wire or wirelessly. Further, the server computer 9 wirelessly communicates with the mobile terminal 8 carried by the operator OP.
  • the mobile terminal 8 is a computer such as a tablet computer that can be carried by the operator OP, and has a touch panel display, a wireless communication function, and the like. Therefore, the mobile terminal 8 can display information received from the server computer 9 by the wireless communication function on the touch panel display, and can transmit information input to the touch panel display by the operator OP to the server computer 9 .
  • Fig. 2 is a front view schematically showing a solder printing machine.
  • XYZ orthogonal coordinate axes are shown as appropriate, with the Z direction being the vertical direction and the X and Y directions being the horizontal directions.
  • the solder printing machine 2 prints solder on the lands of the substrate B using a mask M through which pattern holes provided corresponding to the lands of the substrate B penetrate.
  • This solder printer 2 includes a mask holding unit 21 holding a mask M, a substrate holding unit 23 arranged below the mask M, and a squeegee unit 29 arranged above the mask M.
  • the solder printing machine 2 slides the squeegee 291 of the squeegee unit 29 on the upper surface of the mask M in the X direction while causing the substrate B to face the mask M from below by the substrate holding unit 23 .
  • the supplied solder is printed on the upper surface of the substrate B through the pattern holes of the mask M (printing process).
  • the substrate holding unit 23 is arranged below the mask M held by the mask holding unit 2 and aligns the substrate B with respect to the mask M.
  • the substrate holding unit 23 includes a pair of conveyors 24 for transporting the substrate B, a substrate holding section 25 for holding the substrate B received from the conveyor 24, and a flat movable table 26 for supporting the conveyor 24 and the substrate holding section 25.
  • a pair of conveyors 24 are arranged parallel to the Y direction while being spaced apart in the X direction, and support both ends of the substrate B in the X direction from below on their upper surfaces. Then, each conveyor 24 conveys the board B in the Y direction, and the board B is carried into or out of the solder printing machine 2 .
  • the substrate holding unit 25 has a flat plate-shaped elevating table 251 and a slide support 252 that can slide in the Z direction with respect to the movable table 26 , and the elevating table 251 is supported by the upper end of the slide support 252 .
  • a plurality of backup pins 253 erected in the Z direction are arranged on the upper surface of the lifting table 251 at intervals in the X and Y directions. As the slide column 252 moves up and down, the backup pin 253 moves up and down together with the lift table 251 . For example, when the substrate B is carried in by the conveyor 24 , the upper end of each backup pin 253 is positioned below the upper surface of the conveyor 24 .
  • the substrate holding section 25 also has a pair of clamp plates 254 arranged above the pair of conveyors 24 with a gap in the X direction.
  • the upper surface of each clamp plate 254 is a plane parallel to the X direction and the Y direction and positioned at the same height. At least one of these clamp plates 254 is movable in the X direction.
  • the substrate holding unit 23 has a table driving mechanism 27 that drives the movable table 26.
  • the table driving mechanism 27 includes an X-axis table 271, a Y-axis table 272 attached to the upper surface of the X-axis table 271, an R-axis table 273 attached to the upper surface of the Y-axis table 272, and a and a ball screw 274 for moving the movable table 26 up and down.
  • the table driving mechanism 27 drives the X-axis table 271 in the X direction, drives the Y-axis table 272 in the Y direction, and rotates the R-axis table 273 in the R direction (rotating direction about an axis parallel to the Z direction).
  • the table drive mechanism 27 can drive the conveyor 24 and the substrate holder 25 arranged on the movable table 26 in the X, Y, Z, and R directions.
  • the table driving mechanism 27 adjusts the position of the substrate B clamped by the clamp plate 254 in the X, Y, and R directions, while adjusting the position in the Z direction. rise to This brings the top surfaces of clamp plate 254 and substrate B into contact with the bottom surface of mask M, respectively.
  • the squeegee unit 29 adjusts the rotation angle of the squeegee 291 to bring the squeegee 291 into contact with the upper surface of the mask M at a predetermined angle (attack angle), and press the squeegee 291 against the mask M with a predetermined pressure (printing pressure). press. From this state, the squeegee unit 29 moves the squeegee 291 in the X direction at a predetermined speed (squeegee speed) to print solder on the lands of the substrate B through the pattern holes of the mask M.
  • squeegee speed predetermined speed
  • FIG. 3 is a plan view schematically showing a component mounter.
  • the mounter 4 includes a pair of conveyors 41 arranged in parallel in the Y direction. Then, the component mounter 4 mounts the component E on the board B that has been carried into the mounting processing position (the position of the board B in FIG. 3) from the upstream side in the Y direction (board transport direction) by the conveyor 41.
  • the board B (component-mounted board B) on which the mounting is completed is carried out by the conveyor 41 from the mounting processing position to the downstream side in the Y direction.
  • the component mounter 4 is provided with a pair of X-axis rails 421 parallel to the X-direction, an X-axis ball screw 422 parallel to the X-direction, and an X-axis motor 423 (servo motor) for rotating the X-axis ball screw 422 .
  • a Y-axis rail 424 parallel to the Y-direction is fixed to a nut of an X-axis ball screw 422 while being supported by a pair of X-axis rails 421 so as to be movable in the X-direction.
  • a Y-axis ball screw 425 parallel to the Y-direction and a Y-axis motor 426 (servo motor) for rotating the Y-axis ball screw 425 are attached to the Y-axis rail 424 . It is fixed to the nut of the Y-axis ball screw 425 while being supported so as to be movable in the Y direction. Therefore, the X-axis motor 423 rotates the X-axis ball screw 422 to move the head unit 43 in the X direction, and the Y-axis motor 426 rotates the Y-axis ball screw 425 to move the head unit 43 in the Y direction. .
  • the head unit 43 has a so-called rotary type mounting head 431 .
  • the mounting head 431 has a plurality of (eight) nozzles 432 circumferentially arranged at equal angular intervals around the rotation axis, and the plurality of nozzles 432 are rotatable around the rotation axis.
  • two component supply units 44 are arranged in the X direction on each side of the pair of conveyors 41 in the Y direction.
  • a plurality of tape feeders 441 are detachably attached to each component supply section 44 so as to be aligned in the Y direction.
  • the tape feeder 441 extends in the X direction and has a component supply point 442 at the leading end on the conveyor 41 side in the X direction.
  • a component supply reel is arranged for each tape feeder 441, and the tape feeder 441 is loaded with a tape pulled out from the component supply reel. Then, the tape feeder 441 intermittently feeds the tape in the X direction toward the conveyor 41 side. As a result, the components E in the tape are sent out in the X direction (feed direction) and sequentially supplied to the component supply locations 442 of the tape feeder 441 .
  • the mounting head 431 picks up and places the component E with each nozzle 432 .
  • the mounting head 431 moves above the tape feeder 441 and brings the nozzle 432 into contact with the component E supplied to the component supply location 442 by the tape feeder 441 .
  • the mounting head 431 causes the nozzle 432 to generate a predetermined negative pressure, thereby sucking (picking up) the component E with the nozzle 432 .
  • the mounting head 431 moves above the board B at the mounting processing position at a predetermined transfer speed to mount the component E on the board B.
  • FIG. In this way, the component mounter 4 performs the mounting process of picking up the component E and mounting it on the board B.
  • a tape collection box 443 is provided for each component supply section 44 . Empty tapes (ejections) discharged from the tape feeders 441 of the corresponding component supply units 44 are discarded in the tape collection boxes 443 .
  • the component mounter 4 appropriately executes auto-calibration for automatically calibrating the position of the head unit 43 .
  • the position of the head unit 43 may be displaced due to the extension of the X-axis ball screw 422 or the Y-axis ball screw 425 due to the heat generated by driving the head unit 43 .
  • the mounter 4 has a camera 45 attached to the head unit 43 and a plurality of reference marks 451 indicating reference positions. Then, the mounter 4 moves the head unit 43 so that the camera 45 faces the reference mark 451 from above, and adjusts the position of the camera 45 with respect to the reference mark 451 based on the result of capturing the reference mark 451 with the camera 45 . get.
  • the mounter 4 corrects the position of the head unit 43 based on the positional deviation of the head unit 43 calculated from the result of executing this operation for each reference mark 451 .
  • the solder printing machine 2 prints solder (printing process)
  • the component mounting machine 4 mounts the component E (mounting process)
  • the reflow furnace 6 melts the solder (reflow process).
  • the board B (component-mounted board) on which the component E is mounted is produced.
  • the board inspection machine 7 inspects the quality of component mounting on the board B produced in this way (board inspection).
  • the operation of such board production system 1 is managed by the server computer 9 .
  • FIG. 4 is a block diagram showing an example of the configuration of a server computer.
  • the server computer 9 includes a calculation unit 91 , a storage unit 92 , a UI (User Interface) 93 and a communication unit 94 .
  • the calculation unit 91 is a processor having a calculation function
  • the storage unit 92 is a storage device such as an HDD (Hard Disk Drive) or an SSD (Solid State Drive).
  • the UI 93 also includes input devices such as a keyboard or mouse and output devices such as a display and speakers. It should be noted that the input device and output device of the UI 93 do not necessarily have to be configured separately, and they may be configured integrally with a touch panel display.
  • the communication unit 94 communicates with each of the devices 2, 3, 4, 5, 6, and 7 of the board production line 11 and each of the storages 12 and 13 by wire or wirelessly (in FIG. 4, A component mounter 4 is shown as a representative of these), and wirelessly communicates with a portable terminal 8 carried by the operator OP.
  • a storage unit 92 stores a board production management program 15 for managing board production on the board production line 11 .
  • This board production management program 15 is provided in a state recorded in a recording medium 16 such as a USB (Universal Serial Bus) memory or an optical disk, and the server computer 9 stores the board production management program 15 read from the recording medium 16.
  • a recording medium 16 such as a USB (Universal Serial Bus) memory or an optical disk
  • the server computer 9 stores the board production management program 15 read from the recording medium 16.
  • Store in section 92 Store in section 92 .
  • the example of the mode of providing the board production management program 15 is not limited to this, and the board production management program 15 may be provided to the server computer 9 by downloading it from an external computer storage device to the server computer 9, for example.
  • the arithmetic unit 91 executes the board production management program 15 to generate a production plan acquisition unit 911 , an execution plan creation unit 912 , a predicted result comparison unit 913 and a work instruction update unit 914 . Operations of these functional units 911, 912, 913, and 914 will be described later.
  • the common floor information includes worker information Ifa, inventory information Ifb, and line information Ifc.
  • the worker information Ifa indicates the information of the worker OP (for example, the mobile terminal 8 to be formed, etc.) who performs the work in the board production system 1 .
  • This worker information Ifa is acquired based on the input operation of the worker OP to the UI 93, for example.
  • Inventory information Ifb includes solder inventory information regarding the type and amount of solder stored in solder storage 12 and parts inventory information regarding the type and amount of parts E stored in parts storage 13 .
  • the server computer 9 acquires the solder inventory information by receiving the solder inventory information from the solder storage 12 via the communication unit 94, and receives the parts inventory information from the parts storage 13 via the communication unit 94. By doing so, parts inventory information is acquired.
  • the line information Ifc is information about each device 2, 3, 4, 5, 6, 7 of the board production line 11. For example, the type and number of squeegees 291 that can be used in the solder printer 2, The type and number of tape feeders 441 that can be used are shown.
  • the server computer 9 acquires the line information Ifc based on the communication with the corresponding device or the operator OP's input operation to the UI 93 .
  • the control information includes the board production plan Pp, work execution plan Po, work progress information Ip, and additional work candidate list Lo.
  • the board production plan Pp indicates the type and number of component-mounted boards to be produced by the board production line 11 .
  • This board production plan Pp indicates production of a single type or a plurality of types of component-mounted boards, and is created and stored in the storage unit 92 by an input operation to the UI 93 by the operator OP, for example.
  • the work execution plan Po is created by the execution plan creation unit 912 based on the board production plan Pp acquired by the production plan acquisition unit 911 from the storage unit 92 .
  • the work execution plan Po indicates a work plan to be executed by the board production line 11 and the operator OP in order to produce component-mounted boards according to the board production plan Pp. include.
  • the machine work execution plan Po1 is a start/end schedule of machine work to be executed by each device 2, 3, 4, 5, 6, 7 of the board production line 11 for producing component-mounted boards according to the board production plan Pp. Indicates the time, etc.
  • the machine work is solder printing work handled by the solder printer 2 and component mounting work handled by the component mounter 4 .
  • the solder printing work is the work of printing solder on a predetermined number of boards B corresponding to the same type
  • the component mounting work is the work of mounting parts E on the predetermined number of boards B corresponding to the same type.
  • a solder printing execution plan indicating the execution plan of the solder printing work and a component mounting execution plan indicating the execution plan of the component mounting work are each created as the machine work execution plan Po1.
  • the board production plan Pp indicates production of a plurality of types of component-mounted boards
  • a solder printing execution plan and a component mounting execution plan can be created as the machine work execution plan Po1 for each type of component-mounted boards.
  • the calculation unit 91 controls the solder printing machine 2 based on a solder printing execution plan (machine work execution plan Po1) indicating the solder printing work, thereby causing the solder printing machine 2 to execute the solder printing work.
  • a solder printing execution plan machine work execution plan Po1
  • the computing unit 91 transmits an operation command C1 (printing command) indicating an operation procedure required for executing the solder printing work to the solder printer 2 through the communication unit 94, and the solder printer 2 receives The solder printing work is executed by executing the operation according to the operation command C1.
  • the control mode for causing the solder printing machine 2 to perform the solder printing work is not limited to this.
  • the solder printing execution plan may be transmitted from the board raw server computer 9 to the solder printing machine 2, and the solder printing machine 2 may create and execute an operation procedure required for executing the solder printing work.
  • the computing unit 91 controls the component mounter 4 based on the component mounting execution plan (machine work execution plan Po1) indicating the component mounting work, thereby causing the component mounting machine 4 to execute the component mounting work.
  • the computing unit 91 transmits an operation command C1 (mounting command) indicating the operation procedure required for executing the component mounting work to the component mounter 4 through the communication unit 94, and the component mounter 4 receives the command C1 (mounting command).
  • the component mounting work is executed by executing the operation according to the operation command C1.
  • the control mode for causing the component mounter 4 to perform component mounting work is not limited to this.
  • the component mounting execution plan may be transmitted from the server computer 9 to the component mounter 4, and the component mounter 4 may create and execute an operation procedure required for component mounting work.
  • the manual work execution plan Po2 indicates the start/end scheduled times of the manual work to be executed by the operator OP for the production of the component-mounted boards according to the board production plan Pp.
  • ⁇ Print setup work for setting the squeegee 291 and solder to the solder printing machine 2 to start the solder printing work
  • ⁇ Solder supply work for supplying solder to the solder printing machine 2 from the solder storage 12
  • a mounting setup work for setting the tape feeder 441 loaded with the component E to the component mounter 4, a component replenishment work for replenishing the component E from the component storage 13 to the component mounter 4, and the like.
  • the calculation unit 91 transmits the operation command C2 to the mobile terminal 8 of the operator OP in order to execute the various manual work execution plans Po2.
  • the calculation unit 91 issues an operation command C2 that instructs the solder to be set in the solder printing machine 2 and the squeegee 291 based on the solder inventory amount indicated by the inventory information Ifb, the type of the squeegee 291 indicated by the line information Ifc, and the like. to the mobile terminal 8. Accordingly, the operator OP can perform the print setup work according to the operation command C2 received by the mobile terminal 8. FIG. Further, the calculation unit 91 transmits an operation command C2 instructing the execution of the solder replenishment work to the mobile terminal 8 according to the consumption of solder accompanying the execution of the solder printing work by the solder printing machine 2 .
  • the operator OP can perform the solder replenishment work according to the operation command C2 received by the portable terminal 8.
  • the calculation unit 91 identifies the mobile terminal 8 of the worker OP who is in charge of the work indicated by the operation command C2 based on the worker information Ifa, and transmits the operation command C2 to the mobile terminal 8 .
  • the calculation unit 91 instructs the component E and the tape feeder 441 to be set in the mounter 4 based on the inventory amount of the component E indicated by the inventory information Ifb, the type of the tape feeder 441 indicated by the line information Ifc, and the like. to the mobile terminal 8. Accordingly, the operator OP can perform the mounting preparation work according to the operation command C2 received by the mobile terminal 8.
  • the calculation unit 91 transmits an operation command C2 instructing execution of component replenishment work to the portable terminal 8 according to the consumption of the components E accompanying the execution of the component mounting work by the component mounter 4 . Thereby, the operator OP can perform the parts replenishment work according to the operation command C2 received by the mobile terminal 8 .
  • the calculation unit 91 identifies the mobile terminal 8 of the worker OP who is in charge of the work indicated by the operation command C2 based on the worker information Ifa, and transmits the operation command C2 to the mobile terminal 8 .
  • the work progress information Ip includes machine progress information Ip1 and manual progress information Ip2.
  • the machine progress information Ip1 is information indicating the progress of machine work executed by each of the devices 2, 3, 4, 5, 6, and 7 in the substrate production line 11. , 6 and 7 and stored in the storage unit 92 .
  • the progress of the solder printing work (the start time of the solder printing work, the number of printed boards B, the end time of the solder printing work, etc.) is acquired as machine progress information Ip1, and the parts are mounted.
  • the progress of the component mounting work (the start time of the component mounting work, the number of boards B on which the component E has been mounted, the end time of the component mounting work, etc.) is obtained as machine progress information Ip1.
  • the manual progress information Ip2 is information indicating the progress of the manual work performed by the operator OP.
  • the operator OP inputs the start time and end time of the print setup work, solder replenishment work, mounting setup work, or component replenishment work into the portable terminal 8 , and the portable terminal 8 transmits this to the communication unit 94 .
  • the additional work candidate list Lo indicates in list form candidates for work (additional machine work) that can be additionally performed by the board production line 11 and candidates for work (additional manual work) that can be additionally performed by the operator OP.
  • Candidates for work (additional machine work) that can be additionally performed by the board production line 11 are: ⁇ Automatic maintenance work automatically executed by the solder printing machine 2 or the component mounter 4 (for example, the above autocalibration, etc.) ⁇ Maintenance education work for teaching the operator OP manual maintenance work for the solder printer 2 or the component mounter 4 ⁇ Operation education work for teaching the operator OP how to operate the solder printer 2 or the component mounter 4 mentioned.
  • Candidates for work that can be additionally performed by the operator OP are: ⁇ Recovering tape discarded in the tape recovery box 443 ⁇ Preparing the component E and the tape feeder 441 to be set in the workbench 14 for the component mounting work scheduled to be executed next to the component mounting work being executed Preparatory work, component preparation work for preparing the component E to be supplied next to the component mounter 4 on the workbench 14, support work for another operator OP whose work is delayed, and the like.
  • FIG. 5 is a flowchart showing an example of work management executed by the server computer
  • FIG. 6 is a flowchart showing an example of allocation of additional work executed in the work management of FIG.
  • the flow charts of both figures are executed by calculation of the calculation unit 91 based on the board production management program 15.
  • FIG. The flowchart is executed in parallel for both the machine work indicated by the machine work execution plan Po1 and the manual work indicated by the manual work execution plan Po2.
  • the case of executing the manual work execution plan Po2 will be explained.
  • step S101 the execution plan creation unit 912 acquires the machine work execution plan Po1 and saves it in the storage unit 92. Specifically, as described above, the execution plan creation unit 912 obtains the machine work execution plan Po1 by calculating it from the board production plan Pp. In step S ⁇ b>102 , the prediction result comparison unit 913 acquires the machine progress information Ip ⁇ b>1 from the solder printer 2 , the component mounter 4 , etc., and stores it in the storage unit 92 .
  • the predicted actual result comparison unit 913 compares the machine work execution plan Po1 and the machine progress information Ip1 (step S103), and determines whether the progress of the machine work indicated by the machine progress information Ip1 has progressed with respect to the machine work execution plan Po1. It is determined whether or not there is (step S104). For example, when the solder printing work by the solder printing machine 2 is targeted, the estimated completion time of the solder printing work indicated by the solder printing execution plan and the progress (actual result) of the solder printing work being executed by the solder printing machine 2 By comparing with the estimated completion time of the solder printing work (estimated completion time), it is possible to determine whether the solder printing work is progressing.
  • the estimated completion time of the component mounting work indicated by the component mounting execution plan and the progress (actual result) of the component mounting work being executed by the component mounter 4 By comparing with the estimated completion time of the component mounting work (estimated completion time), it is possible to determine whether the component mounting work is progressing.
  • step S105 the work instruction updating unit 914 performs the assignment of the additional work shown in FIG.
  • step S201 the time (advance time) during which the machine work indicated by the machine progress information Ip1 is advanced relative to the machine work execution plan Po1 is acquired. This preceding time can be obtained, for example, by subtracting the estimated completion time from the expected completion time.
  • step S202 one additional machine work among additional machine work candidates indicated by the additional work candidate list Lo is assigned as work to be executed after completion of the machine work indicated by the machine work execution plan Po1.
  • step S203 the time required for the assigned additional machine work (additional work time) is calculated. Then, in step S204, it is determined whether or not the one additional machine work can be executed based on the comparison between the preceding time acquired in step S201 and the additional work time calculated in step S203. If the preceding time is equal to or longer than the additional work time, it is determined that the one additional machine work can be executed (YES), and it is decided to execute the one additional machine work (step S205). An additional machine work execution plan for executing the one additional machine work after completion of the machine work indicated by Po1 is created (step S206).
  • step S206 the execution command for instructing the execution of the additional machine work based on the additional machine work execution plan is issued to the corresponding one of the devices 2 to 7 at an appropriate timing (for example, during execution or at the completion of the immediately preceding machine work). Sent to equipment (additional machine work instructions). This causes additional machine work to be performed by the device in question.
  • step S206 it returns to the flowchart of FIG. 5 and progresses to step S106.
  • step S206 determines whether or not additional machine work candidates exist in the additional work candidate list Lo in addition to the candidates already assigned in step S202. Then, if there is another additional machine work candidate ("YES" in step S207), the process returns to step S202, and steps S202 to S204 are executed for the other additional machine work. On the other hand, if there is no candidate for additional machine work (“NO” in step S207), the process returns to the flowchart of FIG. 5 and proceeds to step S106.
  • step S104 when it is determined in step S104 that the estimated completion time of the machine work is the same as or later than the expected completion time, it is determined that the progress of the machine work indicated by the machine progress information Ip1 has not progressed with respect to the machine work execution plan Po1. A determination is made (NO), and the process proceeds to step S106.
  • step S106 it is determined whether or not to end the board production plan Pp. Specifically, if all the machine work execution plans Po1 required to execute the board production plan Pp have not been completed, it is determined “NO” in step S106, and the process returns to step S101. On the other hand, when all machine work execution plans Po1 required for execution of the board production plan Pp are completed, it is determined “YES” in step S106, and the flow chart of FIG. 5 ends.
  • step S ⁇ b>101 the execution plan creation unit 912 acquires the manual work execution plan Po ⁇ b>2 and stores it in the storage unit 92 . Specifically, as described above, the execution plan creation unit 912 acquires the manual work execution plan Po2 by calculating it from the board production plan Pp. In step S ⁇ b>102 , the prediction result comparison unit 913 acquires the manual progress information Ip ⁇ b>2 from the mobile terminal 8 and stores it in the storage unit 92 .
  • the predicted result comparison unit 913 compares the manual work execution plan Po2 and the manual progress information Ip2 (step S103), and determines whether the progress of the manual work indicated by the manual progress information Ip2 has progressed with respect to the manual work execution plan Po2. It is determined whether or not there is (step S104). Specifically, the progress of the manual work is determined by comparing the scheduled start time of the manual work indicated by the manual work execution plan Po2 and the start time (actual start time) of the manual work indicated by the manual progress information Ip2. I can judge.
  • step S105 the work instruction updating unit 914 performs the assignment of the additional work shown in FIG.
  • step S201 the time (preceding time) during which the manual work indicated by the manual progress information Ip2 is progressing with respect to the manual work execution plan Po2 is acquired.
  • This preceding time can be obtained, for example, by subtracting the actual start time from the scheduled start time.
  • step S202 one additional manual work among the additional manual work candidates indicated by the additional work candidate list Lo is assigned as work to be executed after completion of the manual work indicated by the manual work execution plan Po2.
  • step S203 the time required for the assigned additional manual work (additional work time) is calculated. Then, in step S204, it is determined whether or not the one additional manual work can be executed based on the comparison between the preceding time acquired in step S201 and the additional work time calculated in step S203. If the preceding time is equal to or longer than the additional work time, it is determined that the one additional manual work can be executed (YES), and it is decided to execute the one additional manual work (step S205), and the manual work execution plan is executed. After completion of the manual work indicated by Po2, an additional manual work execution plan for executing the one additional manual work is created (step S206).
  • an execution command instructing to execute the additional manual work based on the additional manual work execution plan is sent to the mobile terminal 8 at an appropriate timing (for example, during execution or completion of the previous manual work).
  • the operator OP carrying the portable terminal 8 executes the additional manual work (additional manual work execution instruction).
  • step S206 it returns to the flowchart of FIG. 5 and progresses to step S106.
  • step S207 it is determined whether or not additional manual work candidates exist in the additional work candidate list Lo in addition to the candidates already assigned in step S202. Then, if there is another additional manual work candidate ("YES" in step S207), the process returns to step S202, and steps S202 to S204 are executed for the other additional manual work. On the other hand, if there is no candidate for additional manual work ("NO" in step S207), the process returns to the flowchart of FIG. 5 and proceeds to step S106.
  • step S104 when it is determined in step S104 that the estimated completion time of the manual work is the same as or later than the expected completion time, it is determined that the progress of the manual work indicated by the manual progress information Ip2 has not progressed with respect to the manual work execution plan Po2. A determination is made (NO), and the process proceeds to step S106.
  • step S106 it is determined whether or not to end the board production plan Pp. Specifically, if all the manual work execution plans Po2 required to execute the board production plan Pp have not been completed, it is determined “NO” in step S106, and the process returns to step S101. On the other hand, when all manual work execution plans Po2 required for execution of the board production plan Pp are completed, it is determined “YES” in step S106, and the flow chart of FIG. 5 ends.
  • FIG. 7 is a timing chart schematically showing an example of applying the work management of FIG. 5 to component mounting work.
  • the "Plan" column of FIG. 7 there is a machine work execution plan Po1 indicating that the component mounting work will be performed at times ⁇ 1 to ⁇ 2, and a machine work execution plan Po1 that indicates that the component mounting work will be performed at times ⁇ 3 to ⁇ 4. It is shown.
  • the time required for auto-calibration is the time ⁇ 2 less than the preceding time ⁇ 1.
  • FIG. 8 is a timing chart schematically showing an example of applying the work management of FIG. 5 to the mounting setup work.
  • the manual work execution plan Po2 indicating that the mounting preparation work is to be performed at times ⁇ 1 to ⁇ 2
  • the manual work execution plan Po2 indicating that the mounting preparation work is to be performed at times ⁇ 3 to ⁇ 4. It is shown.
  • the time required for collecting the tape is the time ⁇ 2 that is less than the preceding time ⁇ 1.
  • the tape collection is to be executed after the completion of the mounting preparation work at times ⁇ 5 to ⁇ 6.
  • the progress of machine work (equipment work) such as solder printing work or component mounting work executed by the board production line 11 (board production equipment) for mounting component E on board B is determined by the solder printing execution plan or the component mounting execution plan.
  • Steps S103 and S104 equipment work progress confirmation) for confirming whether or not the machine work execution plan Po1 is advanced are executed by the predicted actual result comparison unit 913 (work instruction unit).
  • the work instruction update unit 914 determines that the additional machine work (additional equipment work) can be executed ("YES" in step S204). Execution is instructed to the board production line 11 (additional machine work execution instruction).
  • step S204 the work instruction update unit 914 (work instruction unit) determines that the additional machine work can be executed based on the results of steps S103 and S104 (equipment work progress confirmation) ("YES" in step S204), the operation shown in FIG. After completing the machine work (component mounting work) as described above, the board production line 11 (the component mounter 4 thereof) is instructed to perform additional machine work (auto-calibration). With such a configuration, the board production line 11 can perform the additional machine work after surely completing the machine work that should be originally performed.
  • Step S ⁇ b>103 and S ⁇ b>104 confirmation of auxiliary work progress for confirming whether or not are executed by the prediction result comparison unit 913 (work instruction unit).
  • the work instruction update unit 914 determines that the additional manual work (additional auxiliary work) can be executed ("YES" in step S204).
  • Instruct workers to perform (Additional Manual Work Execution Instructions).
  • step S204 the work instruction update unit 914 (work instruction unit) determines that the additional manual work can be executed based on the results of steps S103 and S104 (confirmation of auxiliary work progress) ("YES" in step S204), the operation shown in FIG. After the manual work (mounting setup work) is completed, the operator is instructed to perform the additional manual work (tape collection) using the portable terminal 8 . With such a configuration, the worker can perform the additional manual work after surely completing the manual work that should be originally performed.
  • the server computer 9 corresponds to an example of the "board production management apparatus" of the present invention
  • the execution plan creation unit 912 corresponds to an example of the "plan acquisition unit” of the present invention
  • the comparison unit 913 and the work instruction update unit 914 cooperate to function as an example of the "work instruction unit” of the present invention
  • the board production line 11 corresponds to an example of the "board production equipment” of the present invention
  • board production management and board production management.
  • the program 15 corresponds to an example of the "board production management program” of the present invention
  • the recording medium 16 corresponds to an example of the "recording medium” of the present invention
  • the operator OP corresponds to an example of the "operation subject" of the present invention.
  • the machine work execution plan Po1 and the manual work execution plan Po2 each correspond to an example of the "work execution plan" of the present invention, and the machine work execution plan Po1 corresponds to an example of the "equipment work execution plan” of the present invention.
  • the manual work execution plan Po2 corresponds to an example of the "auxiliary work execution plan” of the present invention.
  • the present invention is not limited to the above embodiments, and various modifications can be made to the above without departing from the spirit of the present invention.
  • the method of acquiring the additional work time in step S203 is not specifically described. Therefore, the additional work time can be obtained in various ways. For example, a table that associates additional work with the additional work time required for the additional work may be stored in the storage unit 92, and the additional work time may be obtained based on the table. Alternatively, the additional work time required for the additional work may be calculated based on the result of simulating the execution of the additional work by the server computer 9 .
  • the candidates included in the additional work candidate list Lo are not limited to the above examples.
  • the additional task candidate list Lo may include nozzle cleaning as an additional manual task.
  • the configuration of the substrate production line 11 may be changed as appropriate.
  • the board production line 11 it is not always necessary for the board production line 11 to have a device other than the component mounter 4 (for example, the solder printer 2 or the board inspection machine 7).
  • the work management of FIG. 5 is applied to both the machine work by the board production line 11 and the manual work by the operator OP. However, the work management of FIG. 5 may be applied to only one of machine work and manual work.
  • the work subject that performs manual work and additional manual work is not limited to the operator OP, and may be a robot such as an unmanned guided vehicle.
  • Substrate production line (substrate production equipment) 15... Substrate production control program 16... Recording medium 9... Server computer (substrate production control device) 912 ... Execution plan creation unit (plan acquisition unit) 913 ... Prediction result comparison unit (work instruction unit) 914 ... Work instruction update unit (work instruction unit) OP: Worker (main subject of work) Po1... Machine work execution plan (work execution plan, equipment work execution plan) Po2: manual work execution plan (work execution plan, auxiliary work execution plan)

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Primary Health Care (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • General Health & Medical Sciences (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Health & Medical Sciences (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Automation & Control Theory (AREA)
  • Supply And Installment Of Electrical Components (AREA)

Abstract

所定作業(マシン作業、マニュアル作業)の進捗が作業実行計画(マシン作業実行計画Po1、マニュアル作業実行計画Po2)に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行が指示される(図5、図6)。これによって、部品実装基板の生産のための作業の進捗が早まった場合に的確に対応して、生産現場を効率的に稼働させることが可能となる。

Description

基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体
 この発明は、部品が実装された基板である部品実装基板の生産のための作業の実行を管理する技術に関する。
 従来、半田印刷機、部品実装機およびリフロー機に対して順番に基板を搬送して、部品が実装された基板である部品実装基板を所定の生産計画に従って生産する基板生産ラインが知られている。かかる基板生産ラインでは、半田印刷機への半田の補給や、部品実装機への部品の補給といった作業を、作業者が実行する。このような作業者による作業の進捗は状況によって遅れる場合がある。これに対して、特許文献1では、生産管理装置が作業者の作業の進捗を監視して、作業の進捗が遅れている場合には生産計画を再作成する。
特開2020-160638号公報
 ところで、部品実装基板の生産のためには、基板生産設備(基板生産ライン)および作業者のそれぞれが種々の作業を実行する。かかる作業の進捗は、特許文献1で指摘されているように遅れる場合がある一方、早まる場合もある。後者の場合、作業を終えた基板生産設備あるいは作業者が待機することとなり、生産現場の効率的な稼働の観点から改善の余地がある。
 この発明は上記課題に鑑みなされたものであり、部品実装基板の生産のための作業の進捗が早まった場合に的確に対応して、生産現場の効率的な稼働を可能とすることを目的とする。
 本発明に係る基板生産管理装置は、部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する計画取得部と、所定作業の進捗が作業実行計画に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行を指示する作業指示部とを備える。
 本発明に係る基板生産管理方法は、部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する工程と、所定作業の進捗が作業実行計画に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行を指示する工程とを備える。
 本発明に係る基板生産管理プログラムは、部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する工程と、所定作業の進捗が作業実行計画に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行を指示する工程とを、コンピュータに実行させる。
 本発明に係る記録媒体は、上記の基板生産管理プログラムを、コンピュータによって読み出し可能に記録する。
 このように構成された本発明(基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体)では、所定作業の進捗が作業実行計画に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行が指示される。これによって、部品実装基板の生産のための作業の進捗が早まった場合に的確に対応して、生産現場を効率的に稼働させることが可能となる。
 また、所定作業は、基板に部品を実装する基板生産設備により実行される設備作業を含み、作業実行計画は、基板生産設備によって設備作業を実行する計画を示す設備作業実行計画を含み、追加作業は、設備作業とは異なる追加設備作業を含み、作業指示部は、設備作業の進捗が設備作業実行計画に対して進んでいるか否かを確認する設備作業進捗確認の結果に基づき、追加設備作業を実行できると判断すると、追加設備作業の実行を基板生産設備に指示するように、基板生産管理装置を構成してもよい。かかる構成では、基板生産設備による設備作業の進捗が進んでいる場合には、基板生産設備に追加設備作業を実行させて、基板生産設備の稼働率を向上させることができる。
 また、作業指示部は、設備作業進捗確認の結果に基づき追加設備作業を実行できると判断すると、設備作業を完了した後に追加設備作業を実行するように基板生産設備に指示するように、基板生産管理装置を構成してもよい。かかる構成では、基板生産設備は、本来実行すべき設備作業を確実に完了してから、追加設備作業を実行することができる。
 なお、設備作業の具体的な内容は種々考えられる。例えば、設備作業は、所定枚数の基板に部品を実装する部品実装作業である。
 また、設備作業の具体的な内容は種々考えられる。例えば、追加設備作業は、基板生産設備に対してメンテナンスを行う作業であってもよいし、基板生産設備のメンテナンスあるいはオペレーションを作業者に教育するために実行する作業であってもよい。
 また、所定作業は、基板へ部品を実装する基板生産設備を補助する補助作業を含み、作業実行計画は、補助作業を担当する作業主体によって補助作業を実行する計画を示す補助作業実行計画を含み、追加作業は、補助作業とは異なる追加補助作業を含み、作業指示部は、補助作業の進捗が補助作業実行計画に対して進んでいるか否かを確認する補助作業進捗確認の結果に基づき、追加補助作業を実行できると判断すると、追加補助作業の実行を作業主体に指示するように、基板生産管理装置を構成してもよい。作業主体による補助作業の進捗が進んでいる場合には、作業主体に追加補助作業を実行させて、作業主体の稼働率を向上させることができる。
 また、作業指示部は、補助作業進捗確認の結果に基づき追加補助作業を実行できると判断すると、補助作業を完了した後に追加補助作業を実行するように作業主体に指示するように、基板生産管理装置を構成してもよい。かかる構成では、作業主体は、本来実行すべき補助作業を確実に完了してから、追加補助作業を実行することができる。
 また、補助作業の具体的な内容は種々考えられる。例えば、補助作業は、基板生産設備に部品を補給する作業である。
 また、追加補助作業の具体的内容は種々考えられる。例えば、追加補助作業は、基板生産設備から排出される排出物を回収する作業であってもよいし、基板生産設備に補給予定の部品を準備する作業であってもよい。
 また、作業主体の具体的内容は種々考えられる。例えば、作業主体は、作業者であってもよいし、ロボットであってもよい。
 本発明によれば、部品実装基板の生産のための作業の進捗が早まった場合に的確に対応して、生産現場の効率的な稼働を可能とすることが可能となる。
本発明に係る基板生産システムの一例を示すブロック図。 半田印刷機を模式的に示す正面図。 部品実装機を模式的に示す平面図。 サーバコンピュータの構成の一例を示すブロック図。 サーバコンピュータが実行する作業管理の一例を示すフローチャート。 図5の作業管理で実行される追加作業の割り当ての一例を示すフローチャート。 部品実装作業に対して図5の作業管理を適用した一例を模式的示すタイミングチャート。 実装段取り作業に対して図5の作業管理を適用した一例を模式的示すタイミングチャート。
 図1は本発明に係る基板生産システムの一例を示すブロック図である。基板生産システム1は部品E(図3)が実装された基板B(図2、図3)である部品実装基板を生産する基板生産ライン11と、基板生産ライン11による部品実装基板の生産を管理するサーバコンピュータ9を備える。この基板生産ライン11は、半田印刷機2、印刷検査機3、部品実装機4、実装検査機5、リフロー炉6および基板検査機7を備える。半田印刷機2は基板Bに半田を印刷し、印刷検査機3は半田印刷機2による半田の印刷状態を検査する。部品実装機4は印刷検査機3による半田印刷状態の検査を受けた基板Bの半田に対して部品Eを載置し、実装検査機5は部品実装機4による部品Eの載置状態を検査する。リフロー炉6は実装検査機5による部品載置状態の検査を受けた基板Bを加熱することで基板Bに印刷された半田を溶融させ、基板検査機7はリフロー炉6による加熱を受けた基板Bにおける部品Eの実装状態を検査する。基板生産システム1は、このようにして、部品実装基板を生産する(基板生産)。
 なお、装置2~7に対する基板Bの搬送は、コンベアあるいはAGV(Automated Guided Vehicle)といった搬送ロボットや、作業者OPによって行うことができる。また、印刷検査機3の検査で不良と判定された基板Bは部品実装機4に搬送されず、実装検査機5の検査で不良と判定された基板Bは実装検査機5に搬送されない。
 さらに、基板生産システム1は、印刷検査機3で基板Bに印刷される半田を保管する半田保管庫12や、部品実装機4で基板Bに実装される部品Eを保管する部品保管庫13を備える。この部品保管庫13では、複数のポケットに部品Eを収納するテープが巻き付けられた部品供給リールが保管される。テープに収納される部品Eは、例えば集積回路、トランジスタ、コンデンサ等のチップ部品である。これら半田保管庫12あるいは部品保管庫13に対する半田あるいは部品Eの出庫あるいは入庫は、作業者OPによって実行される。また、基板生産システム1では、作業者OPが作業に利用できる作業台14が設けられている。
 サーバコンピュータ9は、半田印刷機2、印刷検査機3、部品実装機4、実装検査機5、リフロー炉6、基板検査機7、半田保管庫12および部品保管庫13と通信を行う。サーバコンピュータ9とこれらの装置2~7、12、13との通信は、有線あるいは無線によって行うことができる。さらに、サーバコンピュータ9は、作業者OPが携帯する携帯端末8と無線によって通信を行う。この携帯端末8は、例えばタブレットコンピュータ等の作業者OPが携帯できるコンピュータであり、タッチパネルディスプレイおよび無線通信機能等を有する。したがって、携帯端末8は、無線通信機能によってサーバコンピュータ9から受信した情報をタッチパネルディスプレイに表示したり、作業者OPによってタッチパネルディスプレイに入力された情報をサーバコンピュータ9に送信したりできる。
 図2は半田印刷機を模式的に示す正面図である。図2および以下の図では、Z方向を鉛直方向とし、X方向およびY方向を水平方向とするXYZ直交座標軸を適宜示す。半田印刷機2は、基板Bのランドに対応して設けられたパターン孔が貫通するマスクMを用いて基板Bのランドに半田を印刷する。この半田印刷機2は、マスクMを保持するマスク保持ユニット21と、マスクMの下方に配置された基板保持ユニット23と、マスクMの上方に配置されたスキージユニット29とを備える。そして、半田印刷機2は、基板保持ユニット23により基板BをマスクMに下方から対向させつつスキージユニット29のスキージ291をマスクMの上面にX方向へ摺動させることで、マスクMの上面に供給された半田を、マスクMのパターン孔を介して基板Bの上面に印刷する(印刷処理)。
 基板保持ユニット23は、マスク保持ユニット2に保持されたマスクMの下方に配置され、マスクMに対して基板Bの位置を合わせる。この基板保持ユニット23は、基板Bを搬送する一対のコンベア24と、コンベア24から受け取った基板Bを保持する基板保持部25と、コンベア24および基板保持部25を支持する平板形状の可動テーブル26とを有する。
 一対のコンベア24はX方向に間隔を空けつつY方向に平行に配置されており、それぞれの上面で基板BのX方向の両端を下方から支持する。そして、各コンベア24がY方向に基板Bを搬送して、半田印刷機2に対する基板Bの搬入あるいは搬出を実行する。
 基板保持部25は、平板形状の昇降テーブル251と、可動テーブル26に対してZ方向にスライド可能なスライド支柱252とを有し、昇降テーブル251がスライド支柱252の上端に支持されている。また、昇降テーブル251の上面にはZ方向に立設された複数のバックアップピン253がX方向およびY方向に間隔を空けて並ぶ。そして、スライド支柱252が昇降することで、昇降テーブル251とともにバックアップピン253が昇降する。例えばコンベア24の基板Bの搬入時は、各バックアップピン253の上端がコンベア24の上面より下方に位置する。そして、コンベア24がバックアップピン253の直上に基板Bを搬入すると、バックアップピン253が上昇して、バックアップピン253の上端がコンベア24の上面より上方へ突出する。これによって、コンベア24の上面から各バックアップピン253の上端へ基板Bが受け渡される。
 また、基板保持部25は、一対のコンベア24の上方でX方向に間隔を空けて配置された一対のクランププレート254を有する。各クランププレート254の上面はX方向およびY方向に平行な平面であり、同じ高さに位置する。これらクランププレート254のうち少なくとも一方は、X方向に可動である。
 そして、バックアップピン253上の基板Bが一対のクランププレート254の間にまで上昇して、可動のクランププレート254がX方向に移動することで、これらクランププレート254の間隔が狭まって、基板Bがこれらクランププレート254によりX方向(水平方向)からクランプされる。
 さらに、基板保持ユニット23は、可動テーブル26を駆動するテーブル駆動機構27を有する。このテーブル駆動機構27は、X軸テーブル271と、X軸テーブル271の上面に取り付けられたY軸テーブル272と、Y軸テーブル272の上面に取り付けられたR軸テーブル273と、R軸テーブル273に対して可動テーブル26を昇降させるボールネジ274とを有する。このテーブル駆動機構27は、X軸テーブル271をX方向に駆動し、Y軸テーブル272をY方向へ駆動し、R軸テーブル273をR方向(Z方向に平行な軸を中心とする回転方向)に駆動し、ボールネジ274を回転させることで可動テーブル26をZ方向に駆動する。つまり、テーブル駆動機構27は、可動テーブル26に配置されたコンベア24および基板保持部25をX、Y、Z、R方向に駆動することができる。例えば搬入された基板BをマスクMに対して位置決めする際には、テーブル駆動機構27は、クランププレート254にクランプされた基板Bの位置を、X・Y・R方向に調整しつつ、Z方向へ上昇させる。これによって、クランププレート254および基板Bそれぞれの上面がマスクMの下面に接触する。
 スキージユニット29は、スキージ291の回転角度を調整することでスキージ291を所定の角度(アタック角度)でマスクMの上面に当接させるとともに、所定の圧力(印圧)でスキージ291をマスクMに押圧する。この状態から、スキージユニット29は、スキージ291を所定の速度(スキージ速度)でスキージ291をX方向に移動させることで、マスクMのパターン孔を介して半田を基板Bのランドに印刷する。
 図3は部品実装機を模式的に示す平面図である。図3に示すように、部品実装機4は、Y方向へ並列に配置された一対のコンベア41を備える。そして、部品実装機4は、コンベア41によりY方向(基板搬送方向)の上流側から実装処理位置(図3の基板Bの位置)に搬入した基板Bに対して部品Eを実装し、部品Eの実装を完了した基板B(部品実装基板B)をコンベア41により実装処理位置からY方向の下流側へ搬出する。
 この部品実装機4では、X方向に平行な一対のX軸レール421と、X方向に平行なX軸ボールネジ422と、X軸ボールネジ422を回転駆動するX軸モータ423(サーボモータ)とが設けられ、Y方向に平行なY軸レール424が一対のX軸レール421にX方向に移動可能に支持された状態でX軸ボールネジ422のナットに固定されている。Y軸レール424には、Y方向に平行なY軸ボールネジ425と、Y軸ボールネジ425を回転駆動するY軸モータ426(サーボモータ)とが取り付けられており、ヘッドユニット43がY軸レール424にY方向に移動可能に支持された状態でY軸ボールネジ425のナットに固定されている。したがって、X軸モータ423によりX軸ボールネジ422を回転させてヘッドユニット43をX方向に移動させ、Y軸モータ426によりY軸ボールネジ425を回転させてヘッドユニット43をY方向に移動させることができる。
 ヘッドユニット43は、いわゆるロータリ型の実装ヘッド431を有する。つまり、実装ヘッド431は、回転軸を中心に円周状に等角度間隔で配列された複数(8個)のノズル432を有し、複数のノズル432は回転軸を中心に回転可能である。
 図3に示すように、一対のコンベア41のY方向の両側それぞれでは、2つの部品供給部44がX方向に並んでいる。各部品供給部44に対しては、複数のテープフィーダ441がY方向に並んで着脱可能に装着されている。テープフィーダ441はX方向に延設されており、X方向におけるコンベア41側の先端部に部品供給箇所442を有する。そして、部品供給リールが各テープフィーダ441に対して配置され、テープフィーダ441には、部品供給リールから引き出されたテープが装填されている。そして、テープフィーダ441は、テープをコンベア41側へ向けてX方向に間欠的に送り出す。これによって、テープ内の部品EがX方向(フィード方向)に送り出されて、テープフィーダ441の部品供給箇所442に順番に供給される。
 そして、実装ヘッド431は、各ノズル432により部品Eの吸着・載置を行う。具体的には、実装ヘッド431はテープフィーダ441の上方へ移動して、テープフィーダ441により部品供給箇所442に供給された部品Eにノズル432を当接させる。そして、実装ヘッド431は、所定の負圧をノズル432に発生させることで、ノズル432により部品Eを吸着(ピックアップ)する。実装ヘッド431はこうして部品Eを保持した状態で、実装処理位置の基板Bの上方に所定の移載速度で移動して基板Bに部品Eを載置する。こうして、部品Eを吸着して基板Bに載置する実装処理が部品実装機4により実行される。
 また、部品実装機4では、各部品供給部44に対してテープ回収ボックス443が設けられている。テープ回収ボックス443には、対応する部品供給部44のテープフィーダ441から排出された空のテープ(排出物)が廃棄される。
 また、部品実装機4は、ヘッドユニット43の位置を自動的に較正するオートキャリブレーションを適宜実行する。つまり、ヘッドユニット43の駆動に伴う発熱によってX軸ボールネジ422あるいはY軸ボールネジ425が伸長したために、ヘッドユニット43の位置にずれが生じる場合がある。これに対して、部品実装機4は、ヘッドユニット43に取り付けられたカメラ45と、基準となる位置を示す複数の基準マーク451とを有する。そして、部品実装機4は、ヘッドユニット43を移動させることでカメラ45を基準マーク451に上方から対向させつつ、カメラ45で基準マーク451を撮像した結果に基づき基準マーク451に対するカメラ45の位置を取得する。部品実装機4は、この動作を各基準マーク451に対して実行した結果から算出したヘッドユニット43の位置ずれに基づき、ヘッドユニット43の位置を補正する。
 このように、基板生産システム1では、半田印刷機2による半田の印刷(印刷処理)と、部品実装機4による部品Eの実装(実装処理)と、リフロー炉6による半田の溶融(リフロー処理)とを経て、部品Eが実装された基板B(部品実装基板)が生産される。こうして生産された基板Bに対する部品実装の良否は、基板検査機7によって検査される(基板検査)。このような基板生産システム1での動作は、サーバコンピュータ9によって管理される。
 図4はサーバコンピュータの構成の一例を示すブロック図である。このサーバコンピュータ9は、演算部91、記憶部92、UI(User Interface)93および通信部94を備える。演算部91は、演算機能を有するプロセッサであり、記憶部92はHDD(Hard Disk Drive)あるいはSSD(Solid State Drive)等で構成された記憶装置である。また、UI93は、キーボードあるいはマウス等の入力機器とディスプレイやスピーカ等の出力機器を備える。なお、UI93の入力機器と出力機器とを別体で構成する必要は必ずしもなく、タッチパネルディスプレイによってこれらを一体的に構成してもよい。また、通信部94は、上述の通り、基板生産ライン11の各装置2、3、4、5、6、7および各保管庫12、13と有線あるいは無線で通信を行うとともに(図4では、これらを代表して部品実装機4が示される)、作業者OPに携帯される携帯端末8と無線で通信を行う。
 記憶部92には、基板生産ライン11での基板生産を管理するための基板生産管理プログラム15が保存されている。この基板生産管理プログラム15は、例えばUSB(Universal Serial Bus)メモリあるいは光ディスク等の記録媒体16に記録された状態で提供され、サーバコンピュータ9は、記録媒体16から読み出した基板生産管理プログラム15を記憶部92に保存する。なお、基板生産管理プログラム15の提供態様の例はこれに限られず、例えば外部のコンピュータの記憶装置からサーバコンピュータ9へのダウンロードによって、基板生産管理プログラム15をサーバコンピュータ9に提供してもよい。サーバコンピュータ9では、演算部91が基板生産管理プログラム15を実行することで、生産計画取得部911、実行計画作成部912、予測実績比較部913および作業指示更新部914を生成する。これらの機能部911、912、913、914の動作は後述する。
 さらに、記憶部92では、基板生産システム1の全体で共通するフロア共通情報と、基板生産システム1で実行される各制御で利用される制御情報とが保存されている。フロア共通情報には、作業者情報Ifa、在庫情報Ifbおよびライン情報Ifcが含まれる。作業者情報Ifaは、基板生産システム1で作業を行う作業者OPの情報(例えば、形態する携帯端末8等)を示す。この作業者情報Ifaは、例えばUI93に対する作業者OPの入力操作に基づき取得される。在庫情報Ifbは、半田保管庫12に保管される半田の種類および量に関する半田在庫情報と、部品保管庫13に保管される部品Eの種類および量に関する部品在庫情報とを含む。サーバコンピュータ9は、通信部94を介して半田在庫情報を半田保管庫12より受信することで、半田在庫情報を取得するとともに、通信部94を介して部品在庫情報を部品保管庫13より受信することで、部品在庫情報を取得する。ライン情報Ifcは、基板生産ライン11の各装置2、3、4、5、6、7に関する情報であり、例えば、半田印刷機2で使用できるスキージ291の種類および本数や、部品実装機4で使用できるテープフィーダ441の種類および本数等を示す。サーバコンピュータ9は、該当の装置との通信あるいはUI93に対する作業者OPの入力操作に基づき、ライン情報Ifcを取得する。
 制御情報には、基板生産計画Pp、作業実行計画Po、作業進捗情報Ipおよび追加作業候補リストLoが含まれる。基板生産計画Ppは、基板生産ライン11によって生産する部品実装基板の種類および枚数を示す。この基板生産計画Ppは、単一種類あるいは複数種類の部品実装基板の生産を示し、例えば、作業者OPによるUI93への入力操作によって作成されて記憶部92に保存される。
 作業実行計画Poは、生産計画取得部911が記憶部92から取得した基板生産計画Ppに基づき、実行計画作成部912によって作成される。この作業実行計画Poは、基板生産計画Ppに従って部品実装基板を生産するために、基板生産ライン11および作業者OPが実行すべき作業計画を示し、マシン作業実行計画Po1およびマニュアル作業実行計画Po2を含む。
 マシン作業実行計画Po1は、基板生産計画Ppに従った部品実装基板の生産のために基板生産ライン11の各装置2、3、4、5、6、7により実行するマシン作業の開始・終了予定時刻等を示す。例えばマシン作業は、半田印刷機2よって担当される半田印刷作業や、部品実装機4によって担当される部品実装作業である。半田印刷作業は、同一種類に対応する所定枚数の基板Bへ半田を印刷する作業であり、部品実装作業は、同一種類に対応する所定枚数の基板Bへ部品Eを実装する作業である。つまり、半田印刷作業の実行計画を示す半田印刷実行計画や、部品実装作業の実行計画を示す部品実装実行計画のそれぞれがマシン作業実行計画Po1として作成される。基板生産計画Ppが複数種類の部品実装基板の生産を示す場合には、部品実装基板の種類毎に半田印刷実行計画および部品実装実行計画のそれぞれをマシン作業実行計画Po1として作成することができる。
 演算部91は、半田印刷作業を示す半田印刷実行計画(マシン作業実行計画Po1)に基づき半田印刷機2を制御することで、半田印刷機2に半田印刷作業を実行させる。例えば、演算部91は、半田印刷作業を実行するために必要となる動作の手順を示す動作指令C1(印刷指令)を通信部94によって半田印刷機2に送信し、半田印刷機2は受信した動作指令C1に従って動作を実行することで、半田印刷作業を実行する。なお、半田印刷機2に半田印刷作業を実行させる制御態様はこれに限られない。例えば、半田印刷実行計画を基板生サーバコンピュータ9から半田印刷機2に送信して、半田印刷機2が半田印刷作業の実行に要する動作手順を作成して、これを実行してもよい。
 また、演算部91は、部品実装作業を示す部品実装実行計画(マシン作業実行計画Po1)に基づき部品実装機4を制御することで、部品実装機4に部品実装作業を実行させる。例えば、演算部91は、部品実装作業を実行するために必要となる動作の手順を示す動作指令C1(実装指令)を通信部94により部品実装機4に送信し、部品実装機4は受信した動作指令C1に従って動作を実行することで、部品実装作業を実行する。なお、部品実装機4に部品実装作業を実行させる制御態様はこれに限られない。例えば、部品実装実行計画をサーバコンピュータ9から部品実装機4に送信して、部品実装機4が部品実装作業の実行に要する動作手順を作成して、これを実行してもよい。
 マニュアル作業実行計画Po2は、基板生産計画Ppに従って部品実装基板の生産のために作業者OPにより実行するマニュアル作業の開始・終了予定時刻等を示す。マニュアル作業としては、
・半田印刷作業の開始のために、スキージ291や半田を半田印刷機2にセットする印刷段取り作業
・半田保管庫12から半田印刷機2に半田を補給する半田補給作業
・部品実装作業の開始のために、部品Eを装填したテープフィーダ441を部品実装機4にセットする実装段取り作業
・部品保管庫13から部品実装機4に部品Eを補給する部品補給作業
等が挙げられる。そして、演算部91は、上記各種のマニュアル作業実行計画Po2を実行させるために、動作指令C2を作業者OPの携帯端末8に送信する。
 例えば、演算部91は、在庫情報Ifbにより示される半田の在庫量や、ライン情報Ifcにより示されるスキージ291の種類等に基づき、半田印刷機2にセットする半田およびスキージ291を指示する動作指令C2を携帯端末8に送信する。これによって、作業者OPは、携帯端末8が受信した動作指令C2に従って、印刷段取り作業を実行できる。また、演算部91は、半田印刷機2による半田印刷作業の実行に伴う半田の消費に応じて、半田補給作業の実行を指示する動作指令C2を携帯端末8に送信する。これによって、作業者OPは、携帯端末8が受信した動作指令C2に従って、半田補給作業を実行できる。この際、演算部91は、動作指令C2が示す作業を担当する作業者OPの携帯端末8を作業者情報Ifaに基づき特定して、当該携帯端末8に動作指令C2を送信する。
 また、演算部91は、在庫情報Ifbにより示される部品Eの在庫量や、ライン情報Ifcにより示されるテープフィーダ441の種類等に基づき、部品実装機4にセットする部品Eおよびテープフィーダ441を指示する動作指令C2を携帯端末8に送信する。これによって、作業者OPは、携帯端末8が受信した動作指令C2に従って、実装段取り作業を実行できる。また、演算部91は、部品実装機4による部品実装作業の実行に伴う部品Eの消費に応じて、部品補給作業の実行を指示する動作指令C2を携帯端末8に送信する。これによって、作業者OPは、携帯端末8が受信した動作指令C2に従って、部品補給作業を実行できる。この際、演算部91は、動作指令C2が示す作業を担当する作業者OPの携帯端末8を作業者情報Ifaに基づき特定して、当該携帯端末8に動作指令C2を送信する。
 作業進捗情報Ipは、マシン進捗情報Ip1およびマニュアル進捗情報Ip2を含む。マシン進捗情報Ip1は、基板生産ライン11の各装置2、3、4、5、6、7が実行するマシン作業の進捗を示す情報であり、通信部94が各装置2、3、4、5、6、7から受信して、記憶部92に保存する。例えば、半田印刷機2からは、半田印刷作業の進捗(半田印刷作業の開始時刻、印刷が完了した基板Bの枚数あるいは半田印刷作業の終了時刻等)がマシン進捗情報Ip1として取得され、部品実装機4からは、部品実装作業の進捗(部品実装作業の開始時刻、部品Eの実装が完了した基板Bの枚数あるいは部品実装作業の終了時刻等)がマシン進捗情報Ip1として取得される。
 マニュアル進捗情報Ip2は、作業者OPが実行するマニュアル作業の進捗を示す情報であり、通信部94が携帯端末8から受信して、記憶部92に保存する。つまり、作業者OPは、印刷段取り作業、半田補給作業、実装段取り作業あるいは部品補給作業の開始時刻や終了時刻を携帯端末8に入力して、携帯端末8はこれを通信部94に送信する。
 追加作業候補リストLoは、基板生産ライン11により追加的に実行できる作業(追加マシン作業)の候補や、作業者OPにより追加的に実行できる作業(追加マニュアル作業)の候補をリスト形式で示す。基板生産ライン11により追加的に実行できる作業(追加マシン作業)の候補としては、
・半田印刷機2あるいは部品実装機4等が自動的に実行するオートメンテナンス作業(例えば、上記のオートキャリブレーション等)
・半田印刷機2あるいは部品実装機4へのマニュアルメンテナンス作業を作業者OPに教示するメンテナンス教育作業
・半田印刷機2あるいは部品実装機4の操作方法を作業者OPに教示するオペレーション教育作業
等が挙げられる。作業者OPにより追加的に実行できる作業(追加マニュアル作業)の候補としては、
・テープ回収ボックス443に廃棄されたテープの回収作業
・実行中の部品実装作業の次に実行予定の部品実装作業に対する実装段取り作業でセットする部品Eやテープフィーダ441を作業台14に準備する段取り準備作業
・部品実装機4に次に補給予定の部品Eを作業台14に準備する部品準備作業
・作業に遅延が生じている他の作業者OPの支援作業
等が挙げられる。
 図5はサーバコンピュータが実行する作業管理の一例を示すフローチャートであり、図6は図5の作業管理で実行される追加作業の割り当ての一例を示すフローチャートである。両図のフローチャートは、基板生産管理プログラム15に基づく演算部91の演算によって実行される。また、同フローチャートは、マシン作業実行計画Po1が示すマシン作業およびマニュアル作業実行計画Po2が示すマニュアル作業の両方に対して並行して実行される。ここでは、マシン作業実行計画Po1に実行する場合を説明した後に、マニュアル作業実行計画Po2に実行する場合を説明する。
 ステップS101では、実行計画作成部912は、マシン作業実行計画Po1を取得して、記憶部92に保存する。具体的には、上述の通り、実行計画作成部912は基板生産計画Ppからマシン作業実行計画Po1を算出することで、これを取得する。ステップS102では、予測実績比較部913が、半田印刷機2および部品実装機4等からマシン進捗情報Ip1を取得して、記憶部92に保存する。
 そして、予測実績比較部913は、マシン作業実行計画Po1とマシン進捗情報Ip1とを比較して(ステップS103)、マシン作業実行計画Po1に対してマシン進捗情報Ip1が示すマシン作業の進捗が進んでいるか否かを判断する(ステップS104)。例えば、半田印刷機2での半田印刷作業を対象とする場合、半田印刷実行計画が示す半田印刷作業の完了予定時刻と、半田印刷機2により実行中の当該半田印刷作業の進捗(実績)から推定される当該半田印刷作業の完了時刻(完了推定時刻)との比較によって、半田印刷作業の進捗が進んでいるかを判断できる。あるいは、部品実装機4での部品実装作業を対象とする場合、部品実装実行計画が示す部品実装作業の完了予定時刻と、部品実装機4により実行中の当該部品実装作業の進捗(実績)から推定される当該部品実装作業の完了時刻(完了推定時刻)との比較によって、部品実装作業の進捗が進んでいるかを判断できる。
 例えばマシン作業の完了推定時刻が完了予定時刻より早いと判断されると、マシン作業実行計画Po1に対して、マシン進捗情報Ip1が示すマシン作業の進捗が進んでいると判断されて(ステップS104で「YES」)、ステップS105が実行される。ステップS105では、図6の追加作業の割り当てが作業指示更新部914によって実行される。
 ステップS201では、マシン進捗情報Ip1が示すマシン作業がマシン作業実行計画Po1に対して進んでいる時間(先行時間)が取得される。この先行時間は、例えば、完了予定時刻から完了推定時刻を減算することで取得できる。ステップS202では、追加作業候補リストLoが示す追加マシン作業の候補のうちの一の追加マシン作業が、マシン作業実行計画Po1が示すマシン作業の完了後に実行する作業として割り当てられる。
 ステップS203では、割り当てられた一の追加マシン作業に要する時間(追加作業時間)が算出される。そして、ステップS204では、ステップS201で取得した先行時間とステップS203で算出した追加作業時間との比較に基づき、当該一の追加マシン作業を実行可能かが判断される。先行時間が追加作業時間以上である場合には、当該一の追加マシン作業が実行可能(YES)と判断されて、当該一の追加マシン作業を実行すると決定し(ステップS205)、マシン作業実行計画Po1が示すマシン作業の完了後に当該一の追加マシン作業を実行する追加マシン作業実行計画が作成される(ステップS206)。また、追加マシン作業実行計画に基づき追加マシン作業を実行するように指示する実行指令は、適宜のタイミング(例えば、直前のマシン作業の実行中あるいは完了時)に装置2~7のうちの該当の装置に送信される(追加マシン作業実行指示)。これによって、該当の装置により、追加マシン作業が実行される。なお、ステップS206の後は、図5のフローチャートに戻ってステップS106に進む。
 一方、先行時間が追加作業時間未満である場合には、ステップS206において当該一の追加マシン作業が実行不能(NO)と判断されて、ステップS207に進む。ステップS207では、追加作業候補リストLoのうち、ステップS202で割当済みの候補の他に、追加マシン作業の候補が存在するかが判断される。そして、他の追加マシン作業の候補が存在する場合(ステップS207で「YES」の場合)には、ステップS202に戻って、他の追加マシン作業について、ステップS202~S204が実行される。一方、他の追加マシン作業の候補が存在しない場合(ステップS207で「NO」の場合)には、図5のフローチャートに戻ってステップS106に進む。
 また、ステップS104で、マシン作業の完了推定時刻が完了予定時刻と同じあるいは遅いと判断されると、マシン作業実行計画Po1に対して、マシン進捗情報Ip1が示すマシン作業の進捗が進んでいないと判断されて(NO)、ステップS106に進む。
 ステップS106では、基板生産計画Ppを終了するか否かが判断される。具体的には、基板生産計画Ppの実行に必要となる全てのマシン作業実行計画Po1が完了していない場合には、ステップS106で「NO」と判断されて、ステップS101に戻る。一方、基板生産計画Ppの実行に必要となる全てのマシン作業実行計画Po1が完了した場合には、ステップS106で「YES」と判断されて、図5のフローチャートが終了する。
 次にマニュアル作業実行計画Po2に実行する場合を説明する。ステップS101では、実行計画作成部912は、マニュアル作業実行計画Po2を取得して、記憶部92に保存する。具体的には、上述の通り、実行計画作成部912は基板生産計画Ppからマニュアル作業実行計画Po2を算出することで、これを取得する。ステップS102では、予測実績比較部913が、携帯端末8からマニュアル進捗情報Ip2を取得して、記憶部92に保存する。
 そして、予測実績比較部913は、マニュアル作業実行計画Po2とマニュアル進捗情報Ip2とを比較して(ステップS103)、マニュアル作業実行計画Po2に対してマニュアル進捗情報Ip2が示すマニュアル作業の進捗が進んでいるか否かを判断する(ステップS104)。具体的には、マニュアル作業実行計画Po2が示すマニュアル作業の開始予定時刻と、マニュアル進捗情報Ip2が示すマニュアル作業の開始時刻(開始実績時刻)との比較によって、マニュアル作業の進捗が進んでいるかを判断できる。
 例えばマニュアル作業の開始実績時刻が開始予定時刻より早いと判断されると、マニュアル作業実行計画Po2に対して、マニュアル進捗情報Ip2が示すマニュアル作業の進捗が進んでいると判断されて(ステップS104で「YES」)、ステップS105が実行される。ステップS105では、図6の追加作業の割り当てが作業指示更新部914によって実行される。
 ステップS201では、マニュアル進捗情報Ip2が示すマニュアル作業がマニュアル作業実行計画Po2に対して進んでいる時間(先行時間)が取得される。この先行時間は、例えば、開始予定時刻から開始実績時刻を減算することで取得できる。ステップS202では、追加作業候補リストLoが示す追加マニュアル作業の候補のうちの一の追加マニュアル作業が、マニュアル作業実行計画Po2が示すマニュアル作業の完了後に実行する作業として割り当てられる。
 ステップS203では、割り当てられた一の追加マニュアル作業に要する時間(追加作業時間)が算出される。そして、ステップS204では、ステップS201で取得した先行時間とステップS203で算出した追加作業時間との比較に基づき、当該一の追加マニュアル作業を実行可能かが判断される。先行時間が追加作業時間以上である場合には、当該一の追加マニュアル作業が実行可能(YES)と判断されて、当該一の追加マニュアル作業を実行すると決定し(ステップS205)、マニュアル作業実行計画Po2が示すマニュアル作業の完了後に当該一の追加マニュアル作業を実行する追加マニュアル作業実行計画が作成される(ステップS206)。また、追加マニュアル作業実行計画に基づき追加マニュアル作業を実行するように指示する実行指令は、適宜のタイミング(例えば、直前のマニュアル作業の実行中あるいは完了時)に携帯端末8に送信される。これによって、携帯端末8を携帯する作業者OPによって、追加マニュアル作業が実行される(追加マニュアル作業実行指示)。なお、ステップS206の後は、図5のフローチャートに戻ってステップS106に進む。
 一方、先行時間が追加作業時間未満である場合には、当該一の追加マニュアル作業が実行不能(NO)と判断されて、ステップS207に進む。ステップS207では、追加作業候補リストLoのうち、ステップS202で割当済みの候補の他に、追加マニュアル作業の候補が存在するかが判断される。そして、他の追加マニュアル作業の候補が存在する場合(ステップS207で「YES」の場合)には、ステップS202に戻って、他の追加マニュアル作業について、ステップS202~S204が実行される。一方、他の追加マニュアル作業の候補が存在しない場合(ステップS207で「NO」の場合)には、図5のフローチャートに戻ってステップS106に進む。
 また、ステップS104で、マニュアル作業の完了推定時刻が完了予定時刻と同じあるいは遅いと判断されると、マニュアル作業実行計画Po2に対して、マニュアル進捗情報Ip2が示すマニュアル作業の進捗が進んでいないと判断されて(NO)、ステップS106に進む。
 ステップS106では、基板生産計画Ppを終了するか否かが判断される。具体的には、基板生産計画Ppの実行に必要となる全てのマニュアル作業実行計画Po2が完了していない場合には、ステップS106で「NO」と判断されて、ステップS101に戻る。一方、基板生産計画Ppの実行に必要となる全てのマニュアル作業実行計画Po2が完了した場合には、ステップS106で「YES」と判断されて、図5のフローチャートが終了する。
 図7は部品実装作業に対して図5の作業管理を適用した一例を模式的示すタイミングチャートである。図7の「計画」の欄では、時刻α1~α2に部品実装作業を実行することを示すマシン作業実行計画Po1と、時刻α3~α4に部品実装作業を実行することを示すマシン作業実行計画Po1が示されている。
 図7の「進捗」の欄では、時刻α1~α2で実行予定であった部品実装作業が時刻α1より早い時刻α5に開始されたために、この部品実装作業は、時刻α2より早い時刻α6に完了すると推定される。その結果、マシン作業実行計画Po1に対してマシン進捗情報Ip1が示す進捗は、先行時間Δα1だけ進んでいる。
 これに対して、図7の「追加」の欄に示すように、オートキャリブレーションに要する時間(追加作業時間)は、先行時間Δα1以下の時間Δα2である。その結果、時刻α5~α6の部品実装作業の完了後にオートキャリブレーション(追加作業)を実行すると決定される。
 図8は実装段取り作業に対して図5の作業管理を適用した一例を模式的示すタイミングチャートである。図8の「計画」の欄では、時刻β1~β2に実装段取り作業を実行することを示すマニュアル作業実行計画Po2と、時刻β3~β4に実装段取り作業を実行することを示すマニュアル作業実行計画Po2が示されている。
 図8の「進捗」の欄では、時刻β1~β2で実行予定であった実装段取り作業が時刻β1より早い時刻β5に開始されたために、この実装段取り作業は、時刻β2より早い時刻β6に完了すると推定される。その結果、マニュアル作業実行計画Po2に対してマニュアル進捗情報Ip2が示す進捗は、先行時間Δβ1だけ進んでいる。
 これに対して、図8の「追加」の欄に示すように、テープ回収に要する時間(追加作業時間)は、先行時間Δβ1以下の時間Δβ2である。その結果、時刻β5~β6の実装段取り作業の完了後にテープ回収(追加作業)を実行すると決定される。
 以上に説明する実施形態では、所定作業(マシン作業、マニュアル作業)の進捗が作業実行計画(マシン作業実行計画Po1、マニュアル作業実行計画Po2)に対して進んでいるか否かを確認した結果に基づき、所定作業とは異なる追加作業を実行できると判断すると、追加作業の実行が指示される(図5、図6)。これによって、部品実装基板の生産のための作業の進捗が早まった場合に的確に対応して、生産現場を効率的に稼働させることが可能となる。
 特に、基板Bに部品Eを実装する基板生産ライン11(基板生産設備)により実行される半田印刷作業あるいは部品実装作業といったマシン作業(設備作業)の進捗が、半田印刷実行計画あるいは部品実装実行計画といったマシン作業実行計画Po1に対して進んでいるか否かを確認するステップS103、S104(設備作業進捗確認)が予測実績比較部913(作業指示部)によって実行される。そして、作業指示更新部914(作業指示部)は、ステップS103、S104の結果に基づき、追加マシン作業(追加設備作業)を実行できると判断すると(ステップS204で「YES」)、追加マシン作業の実行を基板生産ライン11に指示する(追加マシン作業実行指示)。かかる構成では、基板生産ライン11によるマシン作業の進捗が進んでいる場合には、基板生産ライン11に追加マシン作業を実行させて、基板生産ライン11の稼働率を向上させることができる。
 また、作業指示更新部914(作業指示部)は、ステップS103、S104(設備作業進捗確認)の結果に基づき追加マシン作業を実行できると判断すると(ステップS204で「YES」)、図7に示すようにマシン作業(部品実装作業)を完了した後に追加マシン作業(オートキャリブレーション)を実行するように基板生産ライン11(の部品実装機4)に指示する。かかる構成では、基板生産ライン11は、本来実行すべきマシン作業を確実に完了してから、追加マシン作業を実行することができる。
 また、作業者(作業主体)により実行される印刷段取り作業、半田補給作業、実装段取り作業あるいは部品補給作業といったマニュアル作業(補助作業)の進捗が、マニュアル作業実行計画Po2に対して進んでいるか否かを確認するステップS103、S104(補助作業進捗確認)が予測実績比較部913(作業指示部)によって実行される。そして、作業指示更新部914(作業指示部)は、ステップS103、S104の結果に基づき、追加マニュアル作業(追加補助作業)を実行できると判断すると(ステップS204で「YES」)、追加マニュアル作業の実行を作業者に指示する(追加マニュアル作業実行指示)。かかる構成では、作業者によるマニュアル作業の進捗が進んでいる場合には、作業者に追加マニュアル作業を実行させて、作業者の稼働率を向上させることができる。
 また、作業指示更新部914(作業指示部)は、ステップS103、S104(補助作業進捗確認)の結果に基づき追加マニュアル作業を実行できると判断すると(ステップS204で「YES」)、図8に示すようにマニュアル作業(実装段取り作業)を完了した後に追加マニュアル作業(テープ回収)を実行するように、携帯端末8を用いて作業者に指示する。かかる構成では、作業者は、本来実行すべきマニュアル作業を確実に完了してから、追加マニュアル作業を実行することができる。
 このように上記の実施形態では、サーバコンピュータ9が本発明の「基板生産管理装置」の一例に相当し、実行計画作成部912が本発明の「計画取得部」の一例に相当し、予測実績比較部913および作業指示更新部914が協働して本発明の「作業指示部」の一例として機能し、基板生産ライン11が本発明の「基板生産設備」の一例に相当し、基板生産管理プログラム15が本発明の「基板生産管理プログラム」の一例に相当し、記録媒体16が本発明の「記録媒体」の一例に相当し、作業者OPが本発明の「作業主体」の一例に相当し、マシン作業実行計画Po1およびマニュアル作業実行計画Po2のそれぞれが本発明の「作業実行計画」の一例に相当し、マシン作業実行計画Po1が本発明の「設備作業実行計画」の一例に相当し、マニュアル作業実行計画Po2が本発明の「補助作業実行計画」の一例に相当する。
 なお、本発明は上記実施形態に限定されるものではなく、その趣旨を逸脱しない限りにおいて上述したものに対して種々の変更を加えることが可能である。例えばステップS203での追加作業時間の取得方法は、特に具体的に説明していない。そこで、追加作業時間を種々の態様で取得することができる。例えば、追加作業と、当該追加作業に要する追加作業時間とを対応付けたテーブルを記憶部92に記憶しておき、当該テーブルに基づいて追加作業時間を求めてもよい。あるいは、追加作業の実行をサーバコンピュータ9によりシミュレーションした結果に基づき、当該追加作業に要する追加作業時間を算出してもよい。
 また、追加作業候補リストLoに含まれる候補は、上記の例に限られない。例えば、部品実装機4がノズル432を洗浄するノズル洗浄をオートメンテナンス作業として実行する場合には、追加作業候補リストLoは、ノズル洗浄を追加マニュアル作業として含んでもよい。
 また、基板生産ライン11の構成を適宜変更してもよい。例えば、部品実装機4以外の装置(例えば、半田印刷機2あるいは基板検査機7)を基板生産ライン11が具備することは必ずしも必要ない。
 また、基板生産ライン11によるマシン作業および作業者OPによるマニュアル作業の両方に対して、図5の作業管理を適用している。しかしながら、マシン作業およびマニュアル作業のいずれか一方のみに対して、図5の作業管理を適用してもよい。
 また、マニュアル作業および追加マニュアル作業を実行する作業主体は、作業者OPに限られず、無人搬送車等のロボットでもよい。
 11…基板生産ライン(基板生産設備)
 15…基板生産管理プログラム
 16…記録媒体
 9…サーバコンピュータ(基板生産管理装置)
 912…実行計画作成部(計画取得部)
 913…予測実績比較部(作業指示部)
 914…作業指示更新部(作業指示部)
 OP…作業者(作業主体)
 Po1…マシン作業実行計画(作業実行計画、設備作業実行計画)
 Po2…マニュアル作業実行計画(作業実行計画、補助作業実行計画)
 
 

Claims (16)

  1.  部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する計画取得部と、
     前記所定作業の進捗が前記作業実行計画に対して進んでいるか否かを確認した結果に基づき、前記所定作業とは異なる追加作業を実行できると判断すると、前記追加作業の実行を指示する作業指示部と
    を備える基板生産管理装置。
  2.  前記所定作業は、前記基板に部品を実装する基板生産設備により実行される設備作業を含み、
     前記作業実行計画は、前記基板生産設備によって前記設備作業を実行する計画を示す設備作業実行計画を含み、
     前記追加作業は、前記設備作業とは異なる追加設備作業を含み、
     前記作業指示部は、前記設備作業の進捗が前記設備作業実行計画に対して進んでいるか否かを確認する設備作業進捗確認の結果に基づき、前記追加設備作業を実行できると判断すると、前記追加設備作業の実行を前記基板生産設備に指示する請求項1に記載の基板生産管理装置。
  3.  前記作業指示部は、前記設備作業進捗確認の結果に基づき前記追加設備作業を実行できると判断すると、前記設備作業を完了した後に前記追加設備作業を実行するように前記基板生産設備に指示する請求項2に記載の基板生産管理装置。
  4.  前記設備作業は、所定枚数の基板に部品を実装する部品実装作業である請求項2または3に記載の基板生産管理装置。
  5.  前記追加設備作業は、前記基板生産設備に対してメンテナンスを行う作業である請求項2ないし4のいずれか一項に記載の基板生産管理装置。
  6.  前記追加設備作業は、前記基板生産設備のメンテナンスあるいはオペレーションを作業者に教育するために実行する作業である請求項2ないし5のいずれか一項に記載の基板生産管理装置。
  7.  前記所定作業は、前記基板へ部品を実装する基板生産設備を補助する補助作業を含み、
     前記作業実行計画は、前記補助作業を担当する作業主体によって前記補助作業を実行する計画を示す補助作業実行計画を含み、
     前記追加作業は、前記補助作業とは異なる追加補助作業を含み、
     前記作業指示部は、前記補助作業の進捗が前記補助作業実行計画に対して進んでいるか否かを確認する補助作業進捗確認の結果に基づき、前記追加補助作業を実行できると判断すると、前記追加補助作業の実行を前記作業主体に指示する請求項1ないし6のいずれか一項に記載の基板生産管理装置。
  8.  前記作業指示部は、前記補助作業進捗確認の結果に基づき前記追加補助作業を実行できると判断すると、前記補助作業を完了した後に前記追加補助作業を実行するように前記作業主体に指示する請求項7に記載の基板生産管理装置。
  9.  前記補助作業は、前記基板生産設備に部品を補給する作業である請求項7または8に記載の基板生産管理装置。
  10.  前記追加補助作業は、前記基板生産設備から排出される排出物を回収する作業である請求項7ないし9のいずれか一項に記載の基板生産管理装置。
  11.  前記追加補助作業は、前記基板生産設備に補給予定の部品を準備する作業である請求項7ないし10のいずれか一項に記載の基板生産管理装置。
  12.  前記作業主体は、作業者である請求項7ないし11のいずれか一項に記載の基板生産管理装置。
  13.  前記作業主体は、ロボットである請求項7ないし11のいずれか一項に記載の基板生産管理装置。
  14.  部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する工程と、
     前記所定作業の進捗が前記作業実行計画に対して進んでいるか否かを確認した結果に基づき、前記所定作業とは異なる追加作業を実行できると判断すると、前記追加作業の実行を指示する工程と
    を備える基板生産管理方法。
  15.  部品が実装された基板である部品実装基板の生産のための所定作業を実行する計画を示す作業実行計画を取得する工程と、
     前記所定作業の進捗が前記作業実行計画に対して進んでいるか否かを確認した結果に基づき、前記所定作業とは異なる追加作業を実行できると判断すると、前記追加作業の実行を指示する工程と
    を、コンピュータに実行させる基板生産管理プログラム。
  16.  請求項15に記載の基板生産管理プログラムを、コンピュータによって読み出し可能に記録する記録媒体。
     
PCT/JP2021/021406 2021-06-04 2021-06-04 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体 WO2022254704A1 (ja)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/JP2021/021406 WO2022254704A1 (ja) 2021-06-04 2021-06-04 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2021/021406 WO2022254704A1 (ja) 2021-06-04 2021-06-04 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体

Publications (1)

Publication Number Publication Date
WO2022254704A1 true WO2022254704A1 (ja) 2022-12-08

Family

ID=84322991

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2021/021406 WO2022254704A1 (ja) 2021-06-04 2021-06-04 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体

Country Status (1)

Country Link
WO (1) WO2022254704A1 (ja)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006076768A (ja) * 2004-09-13 2006-03-23 Toyota Industries Corp 作業管理システム及び作業管理方法
JP2017117332A (ja) * 2015-12-25 2017-06-29 ファナック株式会社 製造セルの作業の遅れを修正する製造管理装置
JP2020160638A (ja) * 2019-03-26 2020-10-01 パナソニックIpマネジメント株式会社 生産管理装置および生産計画作成方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006076768A (ja) * 2004-09-13 2006-03-23 Toyota Industries Corp 作業管理システム及び作業管理方法
JP2017117332A (ja) * 2015-12-25 2017-06-29 ファナック株式会社 製造セルの作業の遅れを修正する製造管理装置
JP2020160638A (ja) * 2019-03-26 2020-10-01 パナソニックIpマネジメント株式会社 生産管理装置および生産計画作成方法

Similar Documents

Publication Publication Date Title
US10893641B2 (en) Group determination method and group determination apparatus
US10775775B2 (en) Preparation operation determination system, method, and apparatus
JP6945721B2 (ja) 実装関連装置及び実装システム
US10520930B2 (en) Component mounting system and progress display system of set-up work
JPWO2015166538A1 (ja) 管理装置
EP3226669A1 (en) Tool exchange assistance system and tool exchange assistance method for component mounting line
JP7126045B2 (ja) 計画管理方法および計画管理装置
TW202110657A (zh) 焊膏珠回收系統及方法
US7543259B2 (en) Method and device for deciding support portion position in a backup device
US10845783B2 (en) Component mounting system, worker allocation system, and worker allocation method
US11009860B2 (en) Preparation schedule creating method and preparation schedule creating apparatus
JP7029597B2 (ja) 生産計画作成方法および生産計画作成装置
WO2022254704A1 (ja) 基板生産管理装置、基板生産管理方法、基板生産管理プログラムおよび記録媒体
JP2010135775A (ja) 電子部品の装着方法、電子部品装着装置、電子部品装着装置の電子部品装着順序決定方法及び電子部品装着装置の装着データ作成方法
JP2023054189A (ja) 基板作業システム
JP7012198B2 (ja) 部品実装システムおよび段取り作業管理システムならびに段取り作業管理方法
JP6837198B2 (ja) 設備構成作成支援システムおよび設備構成作成支援方法
JP6982741B2 (ja) 設備構成作成支援システムおよび設備構成作成支援方法
JP7149452B2 (ja) 部品実装システムおよび管理方法
WO2022215312A1 (ja) メンテナンス支援システムおよびメンテナンス支援方法ならびにメンテナンス支援プログラム
JP7083966B2 (ja) 部品実装管理装置、部品実装管理方法、部品実装管理プログラム、記録媒体
JP7431927B2 (ja) 部品実装システム
JP7153822B2 (ja) セットアップ支援装置
WO2022118453A1 (ja) データ管理システム
JP2012199319A (ja) 電子部品装着装置

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21943344

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE