WO2022198842A1 - Hollow-hole burn cut three-time blasting method - Google Patents

Hollow-hole burn cut three-time blasting method Download PDF

Info

Publication number
WO2022198842A1
WO2022198842A1 PCT/CN2021/105888 CN2021105888W WO2022198842A1 WO 2022198842 A1 WO2022198842 A1 WO 2022198842A1 CN 2021105888 W CN2021105888 W CN 2021105888W WO 2022198842 A1 WO2022198842 A1 WO 2022198842A1
Authority
WO
WIPO (PCT)
Prior art keywords
blasting
hole
area
pilot hole
holes
Prior art date
Application number
PCT/CN2021/105888
Other languages
French (fr)
Chinese (zh)
Inventor
王海亮
谷志民
姜世斌
杨波
赵军
李占海
周勇
周明聪
孟祥慧
李建伟
张文明
王振彪
Original Assignee
山东科技大学
中铁二局集团成都新技术爆破工程有限公司
青岛市政空间开发集团有限责任公司
中国交通建设股份有限公司
河北飞瀑环保科技有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 山东科技大学, 中铁二局集团成都新技术爆破工程有限公司, 青岛市政空间开发集团有限责任公司, 中国交通建设股份有限公司, 河北飞瀑环保科技有限公司 filed Critical 山东科技大学
Publication of WO2022198842A1 publication Critical patent/WO2022198842A1/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D1/00Blasting methods or apparatus, e.g. loading or tamping
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Definitions

  • the invention relates to the technical field of engineering blasting, in particular to a three-time blasting method for hollow hole straight-hole cutting.
  • a drilling, loading and transporting machine is usually used in the excavation construction. Due to the structural characteristics of the all-in-one machine equipment during blasting, the all-in-one machine head can only be withdrawn to a position 15m ⁇ 20m away from the excavation face. In order to avoid the damage to the head of the all-in-one machine caused by blasting flying stones, it is necessary to set up multiple protection facilities between the excavation face and the head. The process of building protection facilities increases the construction process and thus increases the construction cost.
  • the split-section method is often used for construction, so that the lower section is detonated first, and then the upper section is detonated. This not only reduces the difficulty of flying stone control caused by the high cutting position of the positive step method, but also solves the roof safety problem caused by the inverted step method.
  • problems in the first blasting technology of the lower section (1) If all blasting tasks of the lower section rocks cannot be completed at one time, for example, the blasting of the lower section is completed in 2 ⁇ 3 times, the collapsed rocks will be scattered in the first blasting.
  • Chinese Patent Publication No. CN102914226 discloses a blasting vibration damping method for hollow hole straight eye diamond cutting.
  • the purpose of the invention is to reduce the impact of blasting vibration on buildings and residents' lives.
  • Chinese Patent Publication No. CN109372509A discloses a method for arranging double-empty rhombus-shaped undercut holes in access filling mining.
  • the purpose of the invention is to improve the utilization rate of blast holes, increase the length of the cycle footage, and reduce the cost of rock drilling and blasting. Reduce the number of cycle operations, shorten the mining time of the approach, and improve the productivity and safety of backfill mining.
  • Chinese Patent Publication No. CN107218043 A discloses a method for excavating a broken surrounding rock cavern.
  • the hole is expanded and excavated, and the explosions are sequentially initiated from the center of the pilot hole to the surrounding holes, and the slag is discharged; finally, the main hole support is completed.
  • the problems of this patent are: (1) During the drilling and blasting excavation process of the pilot hole, the throwing distance and throwing range of the blasting flying stones along the axis of the pilot hole cannot be effectively controlled, and the relative position of the driving face and the pilot hole cannot be effectively controlled. damage to equipment and facilities. (2) The caving rocks from the blasting of the pilot tunnel are scattered on both sides of the blasting section of the pilot tunnel, and the unblasted parts on both sides are filled. Subsequent procedures on both sides of the pilot hole, such as drilling, charging, wiring, detonation, etc., must be carried out after removing these rocks. This greatly reduces the construction efficiency.
  • Chinese Patent Publication No. CN 102758633 B discloses a construction method for a large-section tunnel with good surrounding rock conditions.
  • the method includes: (1) determining a central pilot hole on a section of a predetermined tunnel; Determine the location distribution of the blast holes on the section. (3) Drill a blast hole on the section of the central pilot hole; (4) Fill the blast hole with explosive detonators and detonate in sequence; (5) Exhaust smoke and remove the stone slag; (6) Outside the central pilot hole and inside the tunnel (7) Exhaust smoke and remove stone ballast; (8) Support; (9) Repeat the above steps until the tunnel reaches the predetermined length.
  • This method also fails to effectively control the throwing direction, throwing distance and throwing range of the blasting flying stones in the pilot hole.
  • the number of detonator segments that need to be detonated is larger than that of slant hole cutting.
  • one excavation cycle of a large-section tunnel requires multiple detonations to complete.
  • the purpose of the present invention is to provide a three-time blasting method for hollow hole straight-hole cutting to solve the following problems encountered by the straight-hole cutting blasting method in tunnel excavation: (1) The number of available detonator sections is limited, especially the use of coal mine permits Under the condition of using electric detonator, the problem of too many blasting times of the lower section. (2) Rocks from multiple blasting of the lower section or the first blasting of the pilot tunnel are scattered in the lower part of the working face and on both sides of the blasting section of the pilot tunnel, and the unblasted parts on both sides are buried, resulting in the problem of low construction efficiency.
  • a three-time blasting method for hollow hole straight-hole cutting characterized in that it comprises the following steps:
  • the shovel head of the ballast removal equipment should also be able to enter the hole for ballast removal;
  • the principle of selecting the depth of the super-leading pilot hole is to improve the utilization rate of the full-section blast hole under the premise of pursuing a large footage, and its depth will generally not exceed 5m;
  • pilot hole formed for the first time is in the advanced pilot hole area, it is not a real advanced pilot hole.
  • Hollow holes, reaming holes, auxiliary holes and slot edge holes are drilled on the section of the advanced pilot hole, wherein the reaming slot holes are evenly arranged around the hollow hole, the slot edge holes are arranged on the outline of the pilot hole, and the reaming slot holes are arranged on the outline of the pilot hole.
  • Auxiliary holes are evenly arranged between the hole and the side hole, and the depths of the expanded hole, the auxiliary hole and the side hole are required to be the same and less than the depth of the hollow hole, and the depth of the expanded hole, the auxiliary hole and the side hole is set as T;
  • the footage control principle of the two blasting is: the first blasting maximizes the footage, and the second blasting only needs to blast the remaining residual holes;
  • the surrounding rock conditions of the section are weak surrounding rock conditions
  • the advanced pilot tunnel area is passively supported, and the passive support is A support frame whose shape and size are adapted to the contour of the advanced pilot hole area is placed in the advanced pilot hole area.
  • a ballast stack or a ballast shield is placed between the excavation working face and the equipment to be protected, and the ballast stack or the ballast shield is arranged opposite to the advanced pilot hole area; the height of the ballast stack or the ballast shield is greater than that of the expansion.
  • the maximum distance between the slot and the bottom plate, the width of the ballast stack or the ballast plate is greater than the maximum opening width of the leading pilot hole area.
  • the distance between the ballast stack or the ballast plate and the excavation face is 2.0m to 8.0m.
  • the width of the super-leading hole region is 1.0m-2.0m, and the height is 1.5m-2.0m.
  • the three times of blasting all use 1-5 sections of coal mine allowable electric detonators.
  • the present invention adopts the pilot hole first method of the lower section and the hollow hole straight hole cutting technology.
  • the section size of the pilot hole By controlling the section size of the pilot hole, the number of detonator sections is used less, and the first blasting method of the pilot hole section is completed by one-time detonation method.
  • the advanced excavation of the pilot tunnel solves the problem of low construction efficiency when the lower section is blasted multiple times.
  • the present invention makes full use of the residual blastholes in the pilot hole to carry out the second blasting, so as to achieve the designed blasthole utilization rate and the predetermined driving cycle footage of the pilot hole.
  • the double blasting method of the pilot hole with small section is used to replace the double blasting method of the lower section, which solves the problem of the large amount of detonators and explosives caused by the high number of blasting of the lower section, and creates a good free surface for the blasting of other sections outside the pilot tunnel, which improves the overall The blasthole utilization rate and cycle footage of the section.
  • the present invention controls the throwing direction of the flying stones by means of the side wall of the guide hole, and avoids the equipment that needs to be protected on the working face by selecting the position of the guide hole.
  • the size of the ballast stack or the ballast plate matches the size of the guide hole and the position of the hollow hole, so as to control the throwing distance and throwing range of the flying stones.
  • the cycle footage achieved by the double blasting method of the pilot hole creates a good free surface condition for the third blasting of the full section, ensures the utilization rate of the blasthole and the cycle footage for the full section blasting, and reduces the detonator. and consumption of explosives.
  • the depth of the pilot hole must be increased, which is bound to increase the depth of the pilot hole. It needs to be supported with bolts, etc., which reduces the construction efficiency again.
  • the inventor adopts reverse thinking and only excavates a small-sized pilot hole during the first cycle. Even if a weak rock section is encountered, it is only necessary to push the support frame to passively support the pilot hole, and then put the The pilot hole is blasted twice, creating a good free surface for the blasting of the main blasting area outside the pilot hole, and improving the utilization rate of the full-section blasthole.
  • the blasting utilization rate of the main blasting area can basically reach 100%; Then reduce the first cycle footage of the main blasting area, and actively reserve a pilot hole for the second cycle footage, so that starting from the second cycle, the blasting can be performed according to the normal cycle footage, and there will be no slag coverage after the first cycle pilot hole blasting.
  • the situation at the bottom of the main blasting zone provides a faster way for blasting all sections, with outstanding substantive features and significant progress.
  • Figure 1 is a schematic diagram of the full-section blasthole arrangement
  • Fig. 2 is the layout schematic diagram of the advanced pilot hole area
  • FIG. 3 is a schematic diagram of the excavation process
  • Fig. 4a is a schematic diagram of the arrangement of the ballast stack, and Fig. 4b is a cross-sectional view taken along the line A-A of Fig. 4a;
  • Figure 5 is a schematic diagram of the full-section blasthole arrangement in the embodiment.
  • FIG. 6 is a schematic diagram for passively supporting an advanced pilot hole.
  • 1 ⁇ 5 correspond to 1 ⁇ 5 detonators respectively.
  • FIGS. 1 to 6 a specific embodiment of a three-time blasting method for hollow hole straight-hole undercutting provided by the present invention will be described.
  • the roadway is a straight wall semi-circular arch section
  • the excavation width is 5.40m
  • the height is 3.75m
  • the section area is 15.53m 2 .
  • Its working force is 220ml
  • the explosion speed is 3000m/s
  • the intensity is 0.01m
  • the diameter of the medicine roll is 0.035m
  • the length is 0.40m
  • the mass is 400g/roll.
  • 1 ⁇ 5 sections of coal mine allowable electric detonators are used.
  • the diameter of the empty hole is 0.133m
  • the diameter of the charging hole is 0.042m.
  • the hollow hole 3 with a diameter of d 1 is drilled, the diameter of the expanded slot hole 4 of d 2 , the auxiliary hole 5 in the advanced pilot hole area and the slot edge hole 6, the expanded slot hole 4
  • the maximum distance from the floor is H 2 .
  • Hollow hole 3 is located 0.85m to the right of the centerline of the roadway and 0.9m above the bottom plate; reaming holes 4 are arranged around hollow hole 3, and the circumferential equidistant spacing between adjacent reaming holes 4 is maintained.
  • ballast stack Arrange the ballast stack at 4.0m directly in front of the leading pilot hole area 1 (see Figures 4a and 4b).
  • the peripheral holes 7 and the auxiliary holes 8 in the main blasting area are drilled in the main blasting area, and the auxiliary holes 8 in the main blasting area are arranged around the advanced pilot hole area 1.
  • the spacing between holes and rows of auxiliary holes 8 in the main explosion area is 0.45m and 0.55m, and the spacing between holes of peripheral holes 7 is 0.40m.
  • the positive step method is a construction method in which the tunnel excavation section is divided into two or more excavation working faces according to the height, and the upper excavation working face is ahead of the lower excavation working face by a certain distance.
  • the inverted step method is a construction method in which the tunnel excavation section is divided into two or more excavation working faces according to the height, and the lower excavation working face is ahead of the upper excavation working face by a certain distance.
  • the duplex blasting method of the pilot hole in the construction process of the split-section method in which the pilot hole is advanced and blasted, in view of the low utilization rate of the first blasting blasting hole when the pilot hole is cut with a straight hole, the first blasting in the pilot hole is used.
  • the first blasting in the pilot hole is used.
  • continue to use the original blast hole repeat the charging, connection, and detonation operations in the residual blast hole of the pilot hole section, complete the second blasting, and blast the remaining surrounding rock;
  • the excavation depth can create a better air surface for full-section blasting.
  • This method can effectively improve the utilization rate of the full-section blasting hole and improve the full-section blasting cycle footage. Compared with the lower section duplex blasting method, it can effectively reduce the consumption of detonators and explosives in the second blasting, and improve the safety of blasting operations.

Abstract

Disclosed in the present invention is a hollow-hole burn cut three-time blasting method. In the method, a pilot tunnel is excavated on one side of the centerline of a tunneling section and in a direction where there is no target to be protected on a working face; the pilot tunnel divides the tunneling section into an advanced pilot tunnel region and a main blasting region; the advanced pilot tunnel region is blasted twice, and the main blasting region is then subjected to third blasting; the drilling footage of the third blasting is equal to that of the first blasting of the advanced pilot tunnel; and after one blasting cycle, a reserved pilot tunnel is formed in a new tunneling section, such that starting from a second cycle, blasting can be performed according to a normal cyclic drilling footage, and a situation that rock slag covers the bottom of the main blasting region after the first cyclic pilot tunnel blasting does not occur, thus providing a faster mode for blasting implementation of all sections.

Description

一种中空孔直眼掏槽三次爆破方法A three-time blasting method for hollow hole straight-hole cutting 技术领域technical field
本发明涉及工程爆破技术领域,尤其是一种中空孔直眼掏槽三次爆破方法。The invention relates to the technical field of engineering blasting, in particular to a three-time blasting method for hollow hole straight-hole cutting.
背景技术Background technique
交通隧道、矿山巷道开挖施工过程中,为了提高爆破效率,常需要通过加大掏槽部位的装药量以达到良好的爆破效果。常规的掏槽方式和爆破方法产生的飞石可以抛掷到距离工作面20m~30m的区域,个别飞石甚至能达到40m的区域,爆破飞石可能会破坏掘进工作面附近的掘进设备及支护设施。In the process of excavation of traffic tunnels and mine roadways, in order to improve the blasting efficiency, it is often necessary to increase the amount of charge at the cutting part to achieve a good blasting effect. The flying stones produced by the conventional cutting and blasting methods can be thrown to the area 20m~30m away from the working face, and some flying stones can even reach the area of 40m. facility.
目前,在煤矿岩巷掘进施工中,为提高岩巷开挖钻爆施工的机械化水平,在掘进施工中通常会使用钻、装、运一体机。爆破时因一体机设备结构特点,一体机机头只能撤至距掘进工作面15m~20m的位置。为了避免爆破飞石对一体机机头的破坏,需要在掘进工作面与机头间搭设多重防护设施,搭建防护设施的过程增加了施工工序从而增大了施工成本。At present, in order to improve the mechanization level of drilling and blasting construction of rock roadway excavation in coal mines, a drilling, loading and transporting machine is usually used in the excavation construction. Due to the structural characteristics of the all-in-one machine equipment during blasting, the all-in-one machine head can only be withdrawn to a position 15m~20m away from the excavation face. In order to avoid the damage to the head of the all-in-one machine caused by blasting flying stones, it is necessary to set up multiple protection facilities between the excavation face and the head. The process of building protection facilities increases the construction process and thus increases the construction cost.
在可供使用的雷管段数受限条件下,如煤矿许用电雷管只有5段的情况,常采用分断面法施工,让下断面先行起爆,然后再起爆上断面。这样既降低了正台阶法掏槽部位偏高带来的飞石控制难度,又解决了倒台阶法带来的顶板安全问题。但是,下断面先行起爆技术也存在以下问题:(1)如果不能一次起爆完成下断面岩石的全部爆破任务,如分2~3次完成下断面的爆破,就会出现崩落的岩石散落在先起爆爆破断面的两侧,填埋两侧未爆破部位。必须在清除这些岩石后才能进行下断面两侧的后续工序,如钻孔、装药、连线、起爆等。这样就大大降低了施工效率。(2)如果能够一次起爆完成下断面岩石的全部爆破任务,由于爆破范围覆盖整个下断面,爆破飞石沿着整个下断面向外抛掷,很难对隧道工作面前方的设备进行有效的防护。Under the condition that the number of available detonator sections is limited, such as the case where there are only 5 electric detonators allowed in a coal mine, the split-section method is often used for construction, so that the lower section is detonated first, and then the upper section is detonated. This not only reduces the difficulty of flying stone control caused by the high cutting position of the positive step method, but also solves the roof safety problem caused by the inverted step method. However, there are also the following problems in the first blasting technology of the lower section: (1) If all blasting tasks of the lower section rocks cannot be completed at one time, for example, the blasting of the lower section is completed in 2~3 times, the collapsed rocks will be scattered in the first blasting. On both sides of the blasting section, the unexploded parts on both sides are buried. Subsequent procedures on both sides of the lower section, such as drilling, charging, wiring, detonation, etc., must be carried out after removing these rocks. This greatly reduces the construction efficiency. (2) If all the blasting tasks of the lower section of the rock can be completed at one time, since the blasting range covers the entire lower section, the blasting flying stones are thrown outward along the entire lower section, and it is difficult to effectively protect the equipment in front of the tunnel working face.
另外,由于大断面隧道爆破一次起爆药量大,特别是临空面条件差,无法释放多余的爆炸能量,造成爆破振动难以控制。In addition, due to the large amount of blasting charge in one-time blasting of large-section tunnels, especially the poor air conditions, the excess explosive energy cannot be released, making it difficult to control the blasting vibration.
现有技术中:In the prior art:
期刊论文《水工隧道爆破进洞施工中爆破飞石的防护》(宋彧 ,黑龙江水利科技,2019年08期,第150~152页)公开了一种爆破飞石的防护技术。对场区内不便撤离的大型设备,使用橡胶软垫、棉垫或者厚重树枝等起到缓冲作用的防护用品对其进行遮挡覆盖,从而减小飞石动能,降低飞石弹射对设备的损坏。这种加强覆盖与遮挡的方法属于被动防护,不能完全避免飞石对设备的破坏,防护的工序多且劳动强度大,影响了掘进进度;另外对防护用品承载能力、质量的要求较高,成本增大。The journal paper "Protection of Flying Rocks During Blasting Construction of Hydraulic Tunnels" (Song Yu, Heilongjiang Water Conservancy Science and Technology, 2019-08, pp. 150-152) discloses a protection technology for blasting flying rocks. For large equipment that is inconvenient to evacuate in the field, use rubber pads, cotton pads, or thick branches and other protective equipment to cover it, so as to reduce the kinetic energy of flying stones and reduce the damage to equipment caused by flying stones. This method of strengthening coverage and shielding belongs to passive protection, which cannot completely avoid the damage of flying stones to equipment. There are many protection procedures and labor intensity, which affects the progress of the excavation. In addition, the requirements for the bearing capacity and quality of protective equipment are high, and the cost increase.
中国专利公开号CN102914226公开了一种中空孔直眼菱形掏槽爆破减振方法。使用潜孔钻机在隧道掌子面中间位置钻一个直径为90mm至180mm的中空孔;使用凿岩机打多个炮孔,炮孔包括环绕中空孔展开的掏槽孔、辅助孔、周边孔和底板孔;按照炮孔布置顺序及雷管延期时间起爆炸药。该发明的目的是降低爆破振动对建筑物及居民生活的影响。Chinese Patent Publication No. CN102914226 discloses a blasting vibration damping method for hollow hole straight eye diamond cutting. Use a down-the-hole drilling machine to drill a hollow hole with a diameter of 90mm to 180mm in the middle of the tunnel face; use a rock drill to drill a number of blast holes, including undercut holes, auxiliary holes, peripheral holes and bottom plate holes spread around the hollow hole ; Detonate explosives according to the arrangement sequence of the blastholes and the delay time of the detonator. The purpose of the invention is to reduce the impact of blasting vibration on buildings and residents' lives.
中国专利公开号CN109372509A公开了一种用于进路充填采矿中双空孔菱形掏槽孔的布置方法,该发明的目的是为了提高炮孔利用率,增加循环进尺长度,降低凿岩爆破成本,减少循环作业次数,缩短进路回采时间,提高充填采矿的生产能力和安全性。Chinese Patent Publication No. CN109372509A discloses a method for arranging double-empty rhombus-shaped undercut holes in access filling mining. The purpose of the invention is to improve the utilization rate of blast holes, increase the length of the cycle footage, and reduce the cost of rock drilling and blasting. Reduce the number of cycle operations, shorten the mining time of the approach, and improve the productivity and safety of backfill mining.
中国专利公开号CN107218043 A公开了一种破碎围岩洞室开挖方法,其特征是导洞布置在主洞中部,采用风钻钻爆进行小导洞开挖,首先开挖一个循环进尺;之后进行主洞扩挖,由导洞中心向周边孔方向依次起爆,出渣;最后完成主洞支护。此专利存在的问题有:(1)导洞钻爆开挖过程中,未能对爆破飞石沿导洞轴线方向的抛掷距离及抛掷范围进行有效地控制,对掘进工作面与导洞相对位置的设备、设施造成破坏。(2)导洞爆破崩落的岩石散落在导洞爆破断面两侧,填埋两侧未爆破部位。必须在清除这些岩石后才能进行导洞两侧的后续工序,如钻孔、装药、连线、起爆等。这样就大大降低了施工效率。Chinese Patent Publication No. CN107218043 A discloses a method for excavating a broken surrounding rock cavern. The hole is expanded and excavated, and the explosions are sequentially initiated from the center of the pilot hole to the surrounding holes, and the slag is discharged; finally, the main hole support is completed. The problems of this patent are: (1) During the drilling and blasting excavation process of the pilot hole, the throwing distance and throwing range of the blasting flying stones along the axis of the pilot hole cannot be effectively controlled, and the relative position of the driving face and the pilot hole cannot be effectively controlled. damage to equipment and facilities. (2) The caving rocks from the blasting of the pilot tunnel are scattered on both sides of the blasting section of the pilot tunnel, and the unblasted parts on both sides are filled. Subsequent procedures on both sides of the pilot hole, such as drilling, charging, wiring, detonation, etc., must be carried out after removing these rocks. This greatly reduces the construction efficiency.
中国专利公开号CN 102758633 B中公开了一种围岩情况较好的大断面隧道的施工方法,该方法包括:(1)在预定隧道的断面上确定中心导洞;(2)在中心导洞断面上确定炮孔的位置分布。(3)在中心导洞的断面上,开凿炮孔;(4)在炮孔中填充炸药雷管,依次起爆;(5)排烟并清除石碴;(6)对中心导洞以外、隧道以内的岩石进行爆破,以形成预定的隧道轮廓;(7)排烟并清除石碴;(8)支护;(9)重复上述步骤,直到隧道达到预定长度为止。该方法也未能对导洞爆破飞石的抛掷方向、抛掷距离及抛掷范围进行有效地控制。Chinese Patent Publication No. CN 102758633 B discloses a construction method for a large-section tunnel with good surrounding rock conditions. The method includes: (1) determining a central pilot hole on a section of a predetermined tunnel; Determine the location distribution of the blast holes on the section. (3) Drill a blast hole on the section of the central pilot hole; (4) Fill the blast hole with explosive detonators and detonate in sequence; (5) Exhaust smoke and remove the stone slag; (6) Outside the central pilot hole and inside the tunnel (7) Exhaust smoke and remove stone ballast; (8) Support; (9) Repeat the above steps until the tunnel reaches the predetermined length. This method also fails to effectively control the throwing direction, throwing distance and throwing range of the blasting flying stones in the pilot hole.
       中国专利公开号CN102914226、CN109372509A使用了中空孔直眼掏槽爆破技术。中空孔直眼掏槽的爆破飞石抛掷方向相对确定,与斜眼掏槽相比,对爆破飞石的控制相对容易。该技术存在以下缺点:  Chinese Patent Publication Nos. CN102914226 and CN109372509A use hollow hole straight-hole cutting blasting technology. The throwing direction of the blasting flying stone in the hollow hole straight-hole cutting is relatively determined, and the control of the blasting flying stone is relatively easy compared with the oblique-hole cutting. This technique has the following disadvantages:
(1)随着直眼掏槽炮孔深度的增加,炮孔利用率大幅降低。《带有空孔的直眼掏槽的合理参数》(库图佐夫,陕西煤炭技术,1989年03期,第57~60页)一文指出:“当空孔直径一定时,随着孔深从1.5m增至3.2m,炮孔利用率几乎呈直线降低,炸药消耗量也出现相应增高,而爆破1m3岩石的炮孔长度消耗量也出现相应增长”。特别是对于采用煤矿许用炸药,由于炸药的做功能力和猛度较低,炮孔利用率明显低于普通岩石炸药。本发明人在某煤矿进行的岩石巷道爆破试验表明,对于三级煤矿许用乳化炸药,中空孔直孔掏槽的炮孔利用率一般在60%~75%。(1) With the increase of the depth of the straight-hole cut hole, the utilization rate of the hole is greatly reduced. The article "Reasonable Parameters for Straight-Eye Cutting with Empty Holes" (Kutuzov, Shaanxi Coal Technology, 1989 03, pp. 57~60) pointed out: "When the diameter of the hole is constant, as the hole depth changes from From 1.5m to 3.2m, the utilization rate of the blasthole decreases almost linearly, the consumption of explosives also increases accordingly, and the consumption of blasthole length for blasting 1m3 rock also increases accordingly.” Especially for the use of allowable explosives in coal mines, the utilization rate of blastholes is significantly lower than that of ordinary rock explosives due to the low working power and sharpness of the explosives. The rock roadway blasting test carried out by the inventor in a coal mine shows that for the third-level coal mine permitted emulsion explosive, the blast hole utilization rate of hollow hole straight hole cutting is generally 60% to 75%.
(2)为了解决炮孔利用率低的问题,本发明人尝试采用下断面复式爆破法,以提高全断面的炮孔利用率,提高全断面的爆破循环进尺。但是由于下断面复式爆破法在整个下断面范围内进行,需要在下断面第一轮爆破后所有残留的炮孔中重新装填炸药和雷管,加之最小抵抗线方向不确定,又带来2个以下问题:①爆破飞石不易控制,②炸药用量增加30%左右、雷管用量增加100%。(2) In order to solve the problem of low utilization rate of blast holes, the inventors tried to adopt the lower-section duplex blasting method to improve the utilization rate of blast holes in the full section and increase the blasting cycle footage of the full section. However, since the lower section duplex blasting method is carried out in the entire lower section, it is necessary to refill all remaining blasting holes with explosives and detonators after the first round of blasting of the lower section. In addition, the direction of the minimum resistance line is uncertain, which brings the following two problems. : ① It is difficult to control the blasting of flying stones, ② the amount of explosives is increased by about 30%, and the amount of detonators is increased by 100%.
(3)因为需要从直径较小的中空孔逐层爆扩出槽腔,因此与斜眼掏槽相比,需要起爆的雷管段数较多。雷管段数受限情况下,大断面隧道的一个掘进循环需要多次起爆才能完成。(3) Because the cavity needs to be blasted out layer by layer from a hollow hole with a smaller diameter, the number of detonator segments that need to be detonated is larger than that of slant hole cutting. When the number of detonator segments is limited, one excavation cycle of a large-section tunnel requires multiple detonations to complete.
(4)对于煤矿爆破,可供使用的雷管段数只有5段,爆破效率更低。以某煤矿断面积28m 2的岩巷为例,由于不能一次爆落工作面下部的岩石,第一次起爆爆落的岩石就会覆盖工作面下部和两侧未起爆的炮孔,必须在耙碴、出碴之后才能实施第二炮的爆破作业,严重影响了施工效率。因此,煤矿大断面岩巷掘进爆破很少使用直眼掏槽技术。 (4) For coal mine blasting, the number of available detonator segments is only 5, and the blasting efficiency is lower. Taking a rock roadway with a cross-sectional area of 28m 2 in a coal mine as an example, since the rock at the lower part of the working face cannot be blasted off at one time, the rock dropped by the first blast will cover the lower part of the working face and the unexploded blastholes on both sides. The blasting operation of the second gun can only be carried out after the ballast and the ballast are removed, which seriously affects the construction efficiency. Therefore, the straight-hole cutting technology is rarely used in the excavation and blasting of large-section rock roadways in coal mines.
技术解决方案technical solutions
本发明目的是提供一种中空孔直眼掏槽三次爆破方法,以解决隧道掘进使用直眼掏槽爆破方法遇到的以下问题:(1)可供使用雷管段数受限,特别是使用煤矿许用电雷管条件下,下断面爆破次数过多的问题。(2)下断面多次爆破或导洞首次爆破崩落的岩石散落在工作面下部和导洞爆破断面两侧,填埋两侧未爆破部位,造成施工效率低下的问题。(3)中空孔直眼掏槽炮孔利用率低,由此造成全断面爆破掘进炮孔利用率低、循环进尺小的问题。(4)采用下断面复式爆破法带来的①爆破飞石不宜控制,②炸药、雷管用量激增的问题。(5)导洞爆破沿导洞轴线方向抛掷的飞石破坏工作面附近设备的问题。The purpose of the present invention is to provide a three-time blasting method for hollow hole straight-hole cutting to solve the following problems encountered by the straight-hole cutting blasting method in tunnel excavation: (1) The number of available detonator sections is limited, especially the use of coal mine permits Under the condition of using electric detonator, the problem of too many blasting times of the lower section. (2) Rocks from multiple blasting of the lower section or the first blasting of the pilot tunnel are scattered in the lower part of the working face and on both sides of the blasting section of the pilot tunnel, and the unblasted parts on both sides are buried, resulting in the problem of low construction efficiency. (3) The utilization rate of the hollow hole straight hole cut hole is low, which leads to the problems of low utilization rate of the blast hole and small cycle footage in full-section blasting. (4) The problems caused by the use of the lower-section duplex blasting method are that ① the blasting flying stones cannot be controlled, and ② the amount of explosives and detonators increases rapidly. (5) The problem that the flying stones thrown along the axis of the pilot hole by the blasting of the pilot hole destroy the equipment near the working face.
为了达到上述目的,本发明采取的技术方案是:In order to achieve the above object, the technical scheme adopted by the present invention is:
一种中空孔直眼掏槽三次爆破方法,其特征在于,它包括以下步骤:A three-time blasting method for hollow hole straight-hole cutting, characterized in that it comprises the following steps:
S1. 在掘进断面中心线一侧,且朝向工作面无保护目标的方向开挖一个导洞,导洞将掘进断面划分为超前导洞区和主爆区;S1. Excavate a pilot hole on the side of the centerline of the excavation section and towards the direction of the unprotected target of the working face. The pilot hole divides the excavation section into the advanced pilot hole area and the main explosion area;
超前导洞的高度和宽度原则上越小越好,除满足作业人员、钻臂能进入之外,还应满足除碴设备的铲头能进入洞内除碴;In principle, the smaller the height and width of the advanced pilot hole, the better. In addition to allowing the operator and drill arm to enter, the shovel head of the ballast removal equipment should also be able to enter the hole for ballast removal;
超前导洞的深度选取原则是:在追求大进尺前提下同时提高全断面炮孔利用率,其深度一般不会超过5m;The principle of selecting the depth of the super-leading pilot hole is to improve the utilization rate of the full-section blast hole under the premise of pursuing a large footage, and its depth will generally not exceed 5m;
需要解释的是:首次成形的导洞虽然处在超前导洞区,并不是真正意义上的超前导洞。It should be explained that although the pilot hole formed for the first time is in the advanced pilot hole area, it is not a real advanced pilot hole.
S2. 在超前导洞断面上钻凿中空孔、扩槽孔、辅助孔和槽边孔,其中,扩槽孔围绕中空孔均匀布置,槽边孔在导洞的轮廓线上布置,扩槽孔和槽边孔之间均匀布置辅助孔,要求扩槽孔、辅助孔和槽边孔的深度相同且小于中空孔深度,设扩槽孔、辅助孔和槽边孔的深度为T;S2. Hollow holes, reaming holes, auxiliary holes and slot edge holes are drilled on the section of the advanced pilot hole, wherein the reaming slot holes are evenly arranged around the hollow hole, the slot edge holes are arranged on the outline of the pilot hole, and the reaming slot holes are arranged on the outline of the pilot hole. Auxiliary holes are evenly arranged between the hole and the side hole, and the depths of the expanded hole, the auxiliary hole and the side hole are required to be the same and less than the depth of the hollow hole, and the depth of the expanded hole, the auxiliary hole and the side hole is set as T;
S3. 在超前导洞炮孔内装入炸药和雷管,先进行第一次爆破,第一次爆破完成后清理覆盖在主爆区底部的岩渣;然后在超前导洞进行第二次装药爆破,两次爆破的总进尺为L;S3. Loading explosives and detonators into the blastholes of the advanced pilot hole, first blasting, and cleaning up the slag covering the bottom of the main blasting area after the first blasting; , the total footage of the two blasting is L;
两次爆破的进尺控制原则是:第一次爆破实现进尺最大化,第二次爆破只需将剩余的残孔爆落即可;The footage control principle of the two blasting is: the first blasting maximizes the footage, and the second blasting only needs to blast the remaining residual holes;
需要解释的是:最理想状态是L=T,但在实际中很难做到炮孔利用率达到100%,所以现实中L是小于T的。What needs to be explained is: the ideal state is L=T, but it is difficult to achieve 100% blasthole utilization in practice, so L is less than T in reality.
S4. 在主爆区钻凿周边孔和辅助孔,辅助孔围绕超前导洞区;S4. Drill peripheral holes and auxiliary holes in the main blasting area, and the auxiliary holes surround the advanced pilot hole area;
S5. 在主爆区装填炸药和雷管,按照距离超前导洞区由近及远的顺序完成第一循环的第三次爆破,第三次爆破的进尺等于超前导洞第一次爆破的进尺,第三次爆破后,在掘进断面上主动形成一个超前导洞,该超前导洞的深度等于第二次爆破的循环进尺,至此第一个爆破循环完成,经过第一个循环后,形成了新的超前导洞区和新的主爆区; S5. Load explosives and detonators in the main blasting area, and complete the third blasting of the first cycle in order of distance from the advanced pilot hole area from near to far. The footage of the third blasting is equal to the footage of the first blasting of the advanced pilot hole. After the third blasting, an advanced pilot hole was actively formed on the excavation section. The depth of the advanced pilot hole was equal to the cyclic footage of the second blasting. So far, the first blasting cycle was completed. After the first cycle, a new leading hole was formed. The advanced pilot hole area and the new main explosion area;
S6. 在新的超前导洞区和新的主爆区上分别按照S2和S4所述的方法钻凿炮孔;通常为方便施工,在完成第一循环爆破之后,步骤S2和S4中装药孔的钻凿可同时完成。S6. Drill holes in the new advanced pilot hole area and the new main blasting area respectively according to the methods described in S2 and S4; usually for the convenience of construction, after the first cycle of blasting is completed, charging in steps S2 and S4 The drilling of the holes can be done at the same time.
S7. 按照S3所述的爆破方法对新的超前导洞区进行两次爆破,之后按照S5所述的方法对新的主爆区进行爆破,要求新的主爆区爆破进尺为L;S7. Carry out two blasting of the new advanced pilot hole area according to the blasting method described in S3, and then blast the new main blasting area according to the method described in S5, and require that the blasting footage of the new main blasting area be L;
至此,第二个爆破循环完成,重复第二个爆破循环的爆破方法直至完成所有断面的爆破。So far, the second blasting cycle is completed, and the blasting method of the second blasting cycle is repeated until the blasting of all sections is completed.
优选的,当断面围岩条件为软弱围岩条件时,每次人员在进入超前导洞区工作比如钻孔、装药等时对超前导洞区进行被动支护,所述的被动支护就是将一个形状尺寸与超前导洞区轮廓相适应的支撑架置于超前导洞区内。Preferably, when the surrounding rock conditions of the section are weak surrounding rock conditions, each time a person enters the advanced pilot tunnel area for work such as drilling, charging, etc., the advanced pilot tunnel area is passively supported, and the passive support is A support frame whose shape and size are adapted to the contour of the advanced pilot hole area is placed in the advanced pilot hole area.
优选的,在掘进工作面和需要保护的设备之间放置挡碴堆或者挡碴板,挡碴堆或者挡碴板与超前导洞区相对的布置;挡碴堆或者挡碴板的高度大于扩槽孔与底板之间的最大距离,挡碴堆或者挡碴板的宽度大于超前导洞区的最大开口宽度。较佳的,所述挡碴堆或者挡碴板与掘进工作面之间的距离为2.0m~8.0m。Preferably, a ballast stack or a ballast shield is placed between the excavation working face and the equipment to be protected, and the ballast stack or the ballast shield is arranged opposite to the advanced pilot hole area; the height of the ballast stack or the ballast shield is greater than that of the expansion The maximum distance between the slot and the bottom plate, the width of the ballast stack or the ballast plate is greater than the maximum opening width of the leading pilot hole area. Preferably, the distance between the ballast stack or the ballast plate and the excavation face is 2.0m to 8.0m.
优选的,所述超前导洞区的宽度为1.0m~2.0m,高度为1.5m~2.0m。Preferably, the width of the super-leading hole region is 1.0m-2.0m, and the height is 1.5m-2.0m.
优选的,所述的三次爆破均使用1~5段煤矿许用电雷管。Preferably, the three times of blasting all use 1-5 sections of coal mine allowable electric detonators.
有益效果beneficial effect
本发明的积极效果是:The positive effects of the present invention are:
(1)本发明采用下断面导洞先行方法和中空孔直眼掏槽技术,通过控制导洞断面尺寸,使用较少的雷管段数,一次起爆方法完成导洞断面的第一次爆破。导洞超前掘进解决了下断面多次爆破时,导洞爆破崩落的岩石散落在导洞爆破断面两侧,填埋两侧未爆破部位,造成施工效率低下的问题。(1) The present invention adopts the pilot hole first method of the lower section and the hollow hole straight hole cutting technology. By controlling the section size of the pilot hole, the number of detonator sections is used less, and the first blasting method of the pilot hole section is completed by one-time detonation method. The advanced excavation of the pilot tunnel solves the problem of low construction efficiency when the lower section is blasted multiple times.
(2)本发明在导洞内充分利用残余炮孔实施第二次爆破,达到设计的炮孔利用率和导洞预定的掘进循环进尺。采用小断面的导洞复式爆破法替代下断面复式爆破法,解决了下断面爆破次数多致使雷管和炸药用量大的问题,为导洞外其他断面的爆破创造出良好的自由面,提高了全断面的炮孔利用率和循环进尺。(2) The present invention makes full use of the residual blastholes in the pilot hole to carry out the second blasting, so as to achieve the designed blasthole utilization rate and the predetermined driving cycle footage of the pilot hole. The double blasting method of the pilot hole with small section is used to replace the double blasting method of the lower section, which solves the problem of the large amount of detonators and explosives caused by the high number of blasting of the lower section, and creates a good free surface for the blasting of other sections outside the pilot tunnel, which improves the overall The blasthole utilization rate and cycle footage of the section.
(3)本发明借助导洞侧壁控制了飞石的抛掷方向,通过选择导洞位置避开工作面需要保护的设备。(3) The present invention controls the throwing direction of the flying stones by means of the side wall of the guide hole, and avoids the equipment that needs to be protected on the working face by selecting the position of the guide hole.
(4)通过设置挡碴堆或者挡碴板,使挡碴堆或者挡碴板尺寸与导洞尺寸、中空孔的位置相匹配,控制飞石的抛掷距离和抛掷范围。(4) By setting the ballast stack or the ballast plate, the size of the ballast stack or the ballast plate matches the size of the guide hole and the position of the hollow hole, so as to control the throwing distance and throwing range of the flying stones.
(5)通过导洞复式爆破法两次爆破达到的循环进尺,为全断面的第三次爆破创造出良好的自由面条件,保证了全断面爆破的炮孔利用率和循环进尺,降低了雷管和炸药的消耗量。(5) The cycle footage achieved by the double blasting method of the pilot hole creates a good free surface condition for the third blasting of the full section, ensures the utilization rate of the blasthole and the cycle footage for the full section blasting, and reduces the detonator. and consumption of explosives.
(6)长期以来,在对设有导洞的主爆区爆破时,本领域技术人员往往采取主爆区的循环进尺等于导洞爆破区的循环进尺,这是因为大家都形成了固有思维,认为循环进尺大施工效率就高,岂不知,这样做会带来以下两个缺陷,一是导洞爆破崩落的岩石散落在导洞爆破断面两侧,填埋两侧未爆破部位,需要重复清理导洞爆破崩落的岩石,反而降低了施工效率;二是在进行第二个循环爆破时需要再次开挖导洞,要想不开挖导洞,就得加大导洞深度,导洞深度加大势必需要用锚杆等进行支护,再次降低施工效率。为了提高施工效率,发明人采取逆向思维,仅在初次循环时开挖一个小尺寸的导洞,即便是遇到软弱岩断面,只需将支撑架推进去对导洞进行被动支护,然后将导洞分两次爆破,为导洞外主爆区的爆破创造出良好的自由面,提高了全断面炮孔的利用率,经现场试验,主爆区炮孔利用率基本能达到100%;然后降低主爆区初次循环进尺,为第二循环进尺主动预留导洞,这样从第二个循环开始,就可以按照正常的循环进尺爆破,且不会出现初次循环导洞爆破后岩渣覆盖在主爆区底部的情形,为所有断面的爆破提供了更加快捷的方式,具有突出的实质性特点和显著的进步。(6) For a long time, when blasting the main blasting area with a pilot hole, those skilled in the art often take the cyclic footage of the main blasting area equal to the cyclic footage of the blasting area of the pilot hole. This is because everyone has formed an inherent thinking, It is believed that the construction efficiency is high when the cycle footage is large. Do you not know that this will bring the following two defects. One is that the rock collapsed by the blasting of the pilot tunnel is scattered on both sides of the blasting section of the pilot tunnel, and the unexploded parts on both sides of the reclamation need to be cleaned repeatedly. Blasting the collapsed rock in the pilot hole reduces the construction efficiency. Second, the pilot hole needs to be excavated again during the second cycle of blasting. If the pilot hole is not to be excavated, the depth of the pilot hole must be increased, which is bound to increase the depth of the pilot hole. It needs to be supported with bolts, etc., which reduces the construction efficiency again. In order to improve the construction efficiency, the inventor adopts reverse thinking and only excavates a small-sized pilot hole during the first cycle. Even if a weak rock section is encountered, it is only necessary to push the support frame to passively support the pilot hole, and then put the The pilot hole is blasted twice, creating a good free surface for the blasting of the main blasting area outside the pilot hole, and improving the utilization rate of the full-section blasthole. After field tests, the blasting utilization rate of the main blasting area can basically reach 100%; Then reduce the first cycle footage of the main blasting area, and actively reserve a pilot hole for the second cycle footage, so that starting from the second cycle, the blasting can be performed according to the normal cycle footage, and there will be no slag coverage after the first cycle pilot hole blasting. The situation at the bottom of the main blasting zone provides a faster way for blasting all sections, with outstanding substantive features and significant progress.
附图说明Description of drawings
图1是全断面炮孔布置示意图;Figure 1 is a schematic diagram of the full-section blasthole arrangement;
图2是超前导洞区的布置示意图;Fig. 2 is the layout schematic diagram of the advanced pilot hole area;
图3是掘进过程示意图;Figure 3 is a schematic diagram of the excavation process;
图4a是碴堆布置示意图,图4b是图4a的A-A剖视图;Fig. 4a is a schematic diagram of the arrangement of the ballast stack, and Fig. 4b is a cross-sectional view taken along the line A-A of Fig. 4a;
图5是实施例中全断面炮孔布置示意图。Figure 5 is a schematic diagram of the full-section blasthole arrangement in the embodiment.
图6是用于对超前导洞进行被动支护的示意图。FIG. 6 is a schematic diagram for passively supporting an advanced pilot hole.
图中:1-超前导洞区,2-主爆区,3-中空孔、4-扩槽孔、5-超前导洞区辅助孔,6-槽边孔,7-周边孔,8-主爆区辅助孔,9-支撑架。In the picture: 1-Advanced pilot hole area, 2-Main blast area, 3-Hollow hole, 4-Expanded slot hole, 5-Advanced pilot hole area auxiliary hole, 6-Slot side hole, 7-Peripheral hole, 8-Main hole Auxiliary hole in blast area, 9-support frame.
①~⑤分别对应1~5段雷管。①~⑤ correspond to 1~5 detonators respectively.
本发明的实施方式Embodiments of the present invention
结合图1至图6所示,对本发明提供的一种中空孔直眼掏槽三次爆破方法的具体实施方式进行说明。With reference to FIGS. 1 to 6 , a specific embodiment of a three-time blasting method for hollow hole straight-hole undercutting provided by the present invention will be described.
以某煤矿的辅助运输巷道为例,对一种中空孔直眼掏槽三次爆破方法进行说明。该巷道为直墙半圆拱断面,掘进宽度5.40m、高度3.75m,断面面积15.53m 2。其做功能力为220ml,爆速为3000m/s,猛度为0.01m,药卷直径0.035m,长度0.40m,质量为400g/卷。采用1~5段煤矿许用电雷管。空孔直径0.133m,装药孔直径0.042m。爆破前将钻装运一体机撤至距离掘进工作面15.0m处,在巷道面向工作面的左侧停靠,右侧用于行人、设备通道。 Taking the auxiliary transportation roadway of a coal mine as an example, a three-time blasting method of hollow hole straight-hole cutting is described. The roadway is a straight wall semi-circular arch section, the excavation width is 5.40m, the height is 3.75m, and the section area is 15.53m 2 . Its working force is 220ml, the explosion speed is 3000m/s, the intensity is 0.01m, the diameter of the medicine roll is 0.035m, the length is 0.40m, and the mass is 400g/roll. 1~5 sections of coal mine allowable electric detonators are used. The diameter of the empty hole is 0.133m, and the diameter of the charging hole is 0.042m. Before blasting, the integrated drilling and shipping machine was withdrawn to a distance of 15.0m from the excavation working face, and parked on the left side of the roadway facing the working face, and the right side was used for pedestrians and equipment passages.
具体的施工步骤包括:The specific construction steps include:
S1.在掘进断面朝向工作面无保护目标的一侧开挖一个导洞,将掘进断面划分为超前导洞区1和主爆区2,导洞宽a=1.70m、高h=1.70m。当掘进断面为软弱围岩时,将图6所示的支撑架9推进超前导洞区1对其进行被动支护,以保护作业人员的安全。S1. Excavate a pilot hole on the side of the excavation section facing the unprotected target of the working face, and divide the excavation section into the advanced pilot hole area 1 and the main explosion area 2. The pilot hole width a=1.70m, height h=1.70m. When the excavation section is weak surrounding rock, the support frame 9 shown in FIG. 6 is pushed into the advanced pilot tunnel area 1 for passive support, so as to protect the safety of the operators.
S2.在超前导洞区1上按照附图5钻凿直径为d 1的中空孔3,直径为d 2的扩槽孔4、超前导洞区辅助孔5和槽边孔6,扩槽孔4距地板的最大距离为H 2。装药孔孔深均为T=2.50m,中空孔3一次钻凿深度为20.0m,待中空孔3深度小于装药孔孔深时重新钻凿。中空孔3位于巷道中心线右侧0.85m、底板以上0.9m处;扩槽孔4围绕中空孔3布置,相邻扩槽孔4之间保持环向等间距,根据经验扩槽孔4与中空孔3的圆心距t 1=(1.5~3.0)d 1+0.5d 2=0.22~0.42m,取t 1=0.24m;在超前导洞区1的轮廓线上布置一圈槽边孔6,孔间距为0.45m、0.55m;扩槽孔4和槽边孔6之间布置超前导洞区辅助孔5,孔间距为0.55m。 S2. On the advanced pilot hole area 1, according to accompanying drawing 5, the hollow hole 3 with a diameter of d 1 is drilled, the diameter of the expanded slot hole 4 of d 2 , the auxiliary hole 5 in the advanced pilot hole area and the slot edge hole 6, the expanded slot hole 4 The maximum distance from the floor is H 2 . The hole depth of the charging hole is T=2.50m, and the drilling depth of the hollow hole 3 is 20.0m at one time. When the depth of the hollow hole 3 is less than the hole depth of the charging hole, it is re-drilled. Hollow hole 3 is located 0.85m to the right of the centerline of the roadway and 0.9m above the bottom plate; reaming holes 4 are arranged around hollow hole 3, and the circumferential equidistant spacing between adjacent reaming holes 4 is maintained. The center-to-center distance of hole 3 t 1 =(1.5~3.0)d 1 +0.5d 2 =0.22~0.42m, take t 1 =0.24m; arrange a circle of slot edge holes 6 on the contour line of the leading hole area 1, The hole spacing is 0.45m, 0.55m; the auxiliary hole 5 in the advanced pilot hole area is arranged between the expansion slot hole 4 and the slot edge hole 6, and the hole spacing is 0.55m.
S3.在超前导洞区1正前方4.0m处布置挡碴堆(见图4a和4b),挡碴堆宽度W=1.9m、高度H 1=1.2m。在超前导洞区1炮孔内装入炸药和1~5段雷管,完成第一次爆破;第一循环的第一次爆破炮孔利用率为η 1= 0.7,进尺为L 11T=0.7×2.50m=1.75m; S3. Arrange the ballast stack at 4.0m directly in front of the leading pilot hole area 1 (see Figures 4a and 4b). The width of the ballast stack is W=1.9m and the height H 1 =1.2m. Loading explosives and 1~5 detonators into the first blast hole in the super-leading pilot hole area to complete the first blasting; the first blasting blast hole utilization rate of the first cycle is η 1 = 0.7, and the footage is L 11 T =0.7×2.50m=1.75m;
S4.在超前导洞区1掘进工作面进行第二次爆破,第一循环的第二次爆破的炮孔利用率为η 2= 0.98,进尺为L 22(T-L 1)=0.98×(2.5-1.75)m=0.735m;爆破完成后清除爆落并覆盖在主爆区2底部的岩碴; S4. Carry out the second blasting on the excavation working face in the advanced pilot tunnel area 1. The blasting utilization rate of the second blasting in the first cycle is η 2 = 0.98, and the footage is L 22 (TL 1 )=0.98× (2.5-1.75) m=0.735m; after the blasting is completed, remove the rock slag that has fallen and covered the bottom of the main blasting area 2;
S5. 在主爆区钻凿周边孔7和主爆区辅助孔8,主爆区辅助孔8围绕超前导洞区1布置。主爆区辅助孔8的孔、排间距为0.45m、0.55m,周边孔7孔间距为0.40m。周边孔7和主爆区辅助孔8的深度为T 1=1.85m; S5. The peripheral holes 7 and the auxiliary holes 8 in the main blasting area are drilled in the main blasting area, and the auxiliary holes 8 in the main blasting area are arranged around the advanced pilot hole area 1. The spacing between holes and rows of auxiliary holes 8 in the main explosion area is 0.45m and 0.55m, and the spacing between holes of peripheral holes 7 is 0.40m. The depth of the peripheral hole 7 and the auxiliary hole 8 in the main blast zone is T 1 =1.85m;
S6.在主爆区2装填炸药和1~5段雷管,按照距离超前导洞区由近及远的顺序起爆,完成第一次循环的第三次爆破,第三次爆破的进尺也即第一次循环的爆破进尺等于超前导洞区1第一次爆破进尺L 1=1.75m,炮孔利用率为 =0.95。 S6. Load explosives and detonators 1 to 5 in the main blasting area 2, and detonate in the order from near to far away from the lead hole area, and complete the third blasting of the first cycle. The footage of the third blasting is also the first The blasting footage of one cycle is equal to the first blasting footage L 1 = 1.75m of the leading pilot hole area 1, and the blast hole utilization rate is = 0.95.
这样经过第三次爆破后,在掘进断面上主动形成一个真正意义上的超前导洞,该超前导洞的深度等于第二次爆破的循环进尺L 2;至此第一个循环进尺完成,经过第一个循环后,形成了新的超前导洞区和新的主爆区; In this way, after the third blasting, a truly advanced pilot hole is actively formed on the excavation section, and the depth of the advanced pilot hole is equal to the cyclic footage L 2 of the second blasting; After one cycle, a new leading hole area and a new main explosion area are formed;
S7.在新的超前导洞区按照步骤S2-S4操作实施两次爆破;S7. Carry out two blasting operations in the new advanced pilot hole area according to steps S2-S4;
S8. 在新的主爆区按照S5-S6方案进行爆破,要求爆破进尺为L=L 1+L 2=2.485m;至此,第二个循环进尺完成,重复第二个循环进尺的爆破方法直至完成所有断面的爆破。通常为方便施工,在完成第一循环爆破之后,超前导洞区和主爆区装药孔的钻凿可同时完成。 S8. Carry out blasting in the new main blasting area according to the S5-S6 scheme, and the blasting footage is required to be L=L 1 +L 2 =2.485m; at this point, the second cycle footage is completed, and the blasting method of the second cycle footage is repeated until Complete the blasting of all sections. Usually, for the convenience of construction, after the first cycle of blasting is completed, the drilling of the charging holes in the advanced pilot hole area and the main blasting area can be completed at the same time.
当然,上述说明并非是对本发明的限制,本发明也并不仅限于上述举例,本技术领域的技术人员在本发明的实质范围内所做出的变化、改型、添加或替换,也应属于本发明的保护范围。Of course, the above description is not intended to limit the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by those skilled in the art within the essential scope of the present invention should also belong to the present invention. the scope of protection of the invention.
本说明书涉及的术语的定义:Definitions of terms used in this specification:
(1)槽边孔:在超前导洞区开挖轮廓线上布置的炮孔,与周边孔的作用相同,主要用以形成超前导洞区开挖轮廓。(1) Slot side holes: The blastholes arranged on the excavation outline of the advanced pilot hole area have the same function as the peripheral holes, and are mainly used to form the excavation outline of the advanced pilot hole area.
(2)正台阶法,将隧道开挖断面按高度划分成2个或多个开挖工作面,上部的开挖工作面超前下部开挖工作面一定距离的施工方法。(2) The positive step method is a construction method in which the tunnel excavation section is divided into two or more excavation working faces according to the height, and the upper excavation working face is ahead of the lower excavation working face by a certain distance.
(3)倒台阶法,将隧道开挖断面按高度划分成2个或多个开挖工作面,下部的开挖工作面超前上部开挖工作面一定距离的施工方法。(3) The inverted step method is a construction method in which the tunnel excavation section is divided into two or more excavation working faces according to the height, and the lower excavation working face is ahead of the upper excavation working face by a certain distance.
(4)分断面法,将隧道开挖断面划分成2个或多个爆破断面,通过分次起爆不同断面上的岩石,完成一个掘进循环的施工方法。(4) Split-section method, which divides the tunnel excavation section into two or more blasting sections, and completes a tunneling cycle by blasting rocks on different sections in stages.
(5)下断面复式爆破法,下断面先行爆破的分断面法施工工艺中,针对下断面炮眼利用率低的情况,在下断面第一轮爆破完成之后,继续利用原有的炮孔,在下断面残留炮孔中重复装药、连线、起爆作业,完成第二轮爆破,将残留围岩爆落;从而使下断面达到较深的开挖深度,为上断面爆破创造较好的临空面。这种方法能够有效提高全断面的炮孔利用率,提高全断面的爆破循环进尺。(5) In the construction process of the split-section method in which the lower section is blasted first, in view of the low utilization rate of blastholes in the lower section, after the first round of blasting at the lower section is completed, the original blastholes will continue to be used, and the lower section will be blasted first. Repeated charging, connection, and detonation operations in the residual blastholes, completed the second round of blasting, and blasted the residual surrounding rock; thus, the lower section reached a deeper excavation depth and created a better air surface for blasting at the upper section. . This method can effectively improve the utilization rate of the full-section blasting hole and improve the full-section blasting cycle footage.
(6)导洞复式爆破法,导洞超前掘进爆破的分断面法施工工艺中,针对导洞采用直眼掏槽时第一次爆破炮孔利用率低的情况,在导洞第一次爆破完成之后,继续利用原有的炮孔,在导洞断面残留炮孔中重复装药、连线、起爆作业,完成第二次爆破,将残留围岩爆落;从而使导洞达到较深的开挖深度,为全断面爆破创造较好的临空面。这种方法能够有效提高全断面的炮孔利用率,提高全断面的爆破循环进尺。与下断面复式爆破法相比,可以有效降低第二次爆破的雷管和炸药消耗量,提高爆破作业的安全性。(6) The duplex blasting method of the pilot hole, in the construction process of the split-section method in which the pilot hole is advanced and blasted, in view of the low utilization rate of the first blasting blasting hole when the pilot hole is cut with a straight hole, the first blasting in the pilot hole is used. After the completion, continue to use the original blast hole, repeat the charging, connection, and detonation operations in the residual blast hole of the pilot hole section, complete the second blasting, and blast the remaining surrounding rock; The excavation depth can create a better air surface for full-section blasting. This method can effectively improve the utilization rate of the full-section blasting hole and improve the full-section blasting cycle footage. Compared with the lower section duplex blasting method, it can effectively reduce the consumption of detonators and explosives in the second blasting, and improve the safety of blasting operations.

Claims (7)

  1. 一种中空孔直眼掏槽三次爆破方法,其特征在于,它包括以下步骤:A three-time blasting method for hollow hole straight-hole cutting, characterized in that it comprises the following steps:
    S1. 在掘进断面中心线一侧,且朝向工作面无保护目标的方向开挖一个导洞,导洞将掘进断面划分为超前导洞区和主爆区;S1. Excavate a pilot hole on the side of the centerline of the excavation section and towards the direction of the unprotected target of the working face. The pilot hole divides the excavation section into the advanced pilot hole area and the main explosion area;
    超前导洞区的高度和宽度原则上越小越好,除满足作业人员、钻臂能进入之外,还应满足除碴设备的铲头能进入洞内除碴;In principle, the smaller the height and width of the advanced pilot hole area, the better. In addition to allowing the operator and drill arm to enter, the shovel head of the ballast removal equipment should also be able to enter the hole for ballast removal;
    导洞的深度选取原则是:在追求大进尺前提下同时提高全断面炮孔利用率;The principle of selecting the depth of the pilot hole is to improve the utilization rate of the full-section blasthole on the premise of pursuing a large footage;
    S2. 在导洞断面上钻凿中空孔、扩槽孔、辅助孔和槽边孔,其中,扩槽孔围绕中空孔均匀布置,槽边孔在导洞的轮廓线上布置,扩槽孔和槽边孔之间均匀布置辅助孔,要求扩槽孔、辅助孔和槽边孔的深度相同且小于中空孔深度,设扩槽孔、辅助孔和槽边孔的深度为T;S2. Hollow holes, reaming holes, auxiliary holes and slot edge holes are drilled on the section of the pilot hole, wherein the reaming slot holes are evenly arranged around the hollow hole, the slot edge holes are arranged on the outline of the pilot hole, the reaming slot holes and The auxiliary holes are evenly arranged between the slot side holes. It is required that the depths of the expanded slot holes, the auxiliary holes and the slot side holes are the same and less than the depth of the hollow hole.
    S3. 在导洞炮孔内装入炸药和雷管,先进行第一次爆破,第一次爆破完成后清理覆盖在主爆区底部的岩渣;然后在导洞内进行第二次装药爆破,两次爆破的总进尺为L;S3. Loading explosives and detonators into the blasthole of the pilot hole, first blasting, cleaning up the slag covering the bottom of the main blasting area after the first blasting; then blasting the second charge in the pilot hole, The total footage of the two blasting is L;
    两次爆破的进尺控制原则是:第一次爆破实现进尺最大化,第二次爆破只需将剩余的残孔爆落即可;The footage control principle of the two blasting is: the first blasting maximizes the footage, and the second blasting only needs to blast the remaining residual holes;
    S4. 在主爆区钻凿周边孔和辅助孔,辅助孔围绕导洞区布置;S4. Drill peripheral holes and auxiliary holes in the main blasting area, and the auxiliary holes are arranged around the pilot hole area;
    S5. 在主爆区装填炸药和雷管,按照距离超前导洞区由近及远的顺序起爆,完成第一循环的第三次爆破,第三次爆破的进尺等于导洞第一次爆破的进尺,第三次爆破后,在掘进断面上主动形成一个超前导洞,该超前导洞的深度等于第二次爆破的进尺,至此第一个爆破循环完成,经过第一个循环后,形成了新的超前导洞区和新的主爆区; S5. Load explosives and detonators in the main blasting area, and detonate in the order from near to far away from the leading pilot hole area to complete the third blasting of the first cycle. The footage of the third blasting is equal to the footage of the first blasting of the pilot hole. , After the third blasting, an advanced pilot hole is actively formed on the excavation section. The depth of the advanced pilot hole is equal to the footage of the second blasting. So far, the first blasting cycle is completed. After the first cycle, a new The advanced pilot hole area and the new main explosion area;
    S6. 在新的超前导洞区和新的主爆区上分别按照S2和S4所述的方法钻凿炮孔;S6. Drill holes in the new advanced pilot hole area and the new main blast area respectively according to the methods described in S2 and S4;
    S7. 按照S3所述的爆破方法对新的超前导洞区进行两次爆破,之后按照S5所述的方法对新的主爆区进行爆破,要求新的主爆区爆破进尺为L;S7. Carry out two blasting of the new advanced pilot hole area according to the blasting method described in S3, and then blast the new main blasting area according to the method described in S5, and require that the blasting footage of the new main blasting area be L;
    至此,第二个爆破循环完成,重复第二个爆破循环的爆破方法直至完成所有断面的爆破。So far, the second blasting cycle is completed, and the blasting method of the second blasting cycle is repeated until the blasting of all sections is completed.
  2. 如权利要求1所述的中空孔直眼掏槽三次爆破方法,其特征在于,当断面围岩条件为软弱围岩时,每次在人员进入超前导洞区钻凿炮孔和装填炸药时对超前导洞区进行被动支护;所述的被动支护就是将一个形状尺寸与超前导洞区轮廓相适应的支撑架置于超前导洞区内。The three-time blasting method for hollow hole straight hole undercutting according to claim 1, characterized in that, when the surrounding rock condition of the section is weak surrounding rock, each time when personnel enter the advanced pilot hole area to drill the blast hole and fill the explosive, Passive support is performed in the advanced pilot tunnel area; the passive support is to place a support frame in the advanced pilot tunnel area with a shape and size adapted to the contour of the advanced pilot tunnel area.
  3. 如权利要求1或2所述的中空孔直眼掏槽三次爆破方法,其特征在于,在超前导洞区正前方和被保护的设备之间布置挡碴堆或者挡碴板;挡碴堆或者挡碴板的高度大于扩槽孔与底板之间的最大距离,挡碴堆或者挡碴板的宽度大于超前导洞区的最大开口宽度。The three-time blasting method for hollow hole straight-hole undercutting according to claim 1 or 2, characterized in that a ballast stack or a ballast plate is arranged between the front of the leading pilot hole area and the protected equipment; the ballast stack or The height of the ballast baffle plate is greater than the maximum distance between the expansion slot and the bottom plate, and the width of the ballast baffle stack or the ballast baffle plate is greater than the maximum opening width of the leading pilot hole area.
  4. 如权利要求3所述的中空孔直眼掏槽三次爆破方法,其特征在于,所述挡碴堆或者挡碴板与掘进工作面之间的距离为2.0m~8.0m。The three-time blasting method for hollow hole straight-hole undercutting according to claim 3, characterized in that, the distance between the ballast retaining pile or the ballast retaining plate and the excavation working face is 2.0m-8.0m.
  5. 如权利要求1或2所述的中空孔直眼掏槽三次爆破方法,其特征在于,所述超前导洞区的宽度为1.0m~2.0m,高度为1.5m~2.0m。The three-time blasting method for straight hole undercutting in a hollow hole according to claim 1 or 2, characterized in that, the width of the advanced pilot hole area is 1.0m~2.0m, and the height is 1.5m~2.0m.
  6. 如权利要求1所述的中空孔直眼掏槽三次爆破方法,其特征在于,所述的三次爆破均使用1~5段煤矿许用电雷管。The three-time blasting method for hollow hole straight-hole undercutting according to claim 1, characterized in that, the three times of blasting all use 1-5 sections of coal mine permitted electric detonators.
  7. 如权利要求1所述的中空孔直眼掏槽三次爆破方法,其特征在于,所述的导洞深度不超过5m。The three-time blasting method for hollow hole straight-hole undercutting according to claim 1, wherein the depth of the pilot hole is not more than 5m.
PCT/CN2021/105888 2021-03-24 2021-07-13 Hollow-hole burn cut three-time blasting method WO2022198842A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110311498.3A CN112964143B (en) 2021-03-24 2021-03-24 Three-time blasting method for hollow hole straight-hole cut
CN202110311498.3 2021-03-24

Publications (1)

Publication Number Publication Date
WO2022198842A1 true WO2022198842A1 (en) 2022-09-29

Family

ID=76278317

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/105888 WO2022198842A1 (en) 2021-03-24 2021-07-13 Hollow-hole burn cut three-time blasting method

Country Status (2)

Country Link
CN (1) CN112964143B (en)
WO (1) WO2022198842A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112964143B (en) * 2021-03-24 2021-09-21 山东科技大学 Three-time blasting method for hollow hole straight-hole cut

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009228977A (en) * 2008-03-24 2009-10-08 Toda Constr Co Ltd Blasting construction method
CN102914226A (en) * 2012-11-08 2013-02-06 中国矿业大学(北京) Hollow-hole rhombic parallel cut blasting damping method
CN104564088A (en) * 2014-12-31 2015-04-29 中铁隧道集团有限公司 Construction method for heading double pilot tunnels for releasing high-ground stress rockbrust collapsing force
CN107091092A (en) * 2017-06-08 2017-08-25 宁波市交通规划设计研究院有限公司 The approximate full face tunneling structure of mountain highway tunnel neutrality country rock and method
CN109372509A (en) * 2018-11-16 2019-02-22 西北矿冶研究院 Arrangement method for double-hollow-hole rhombic cut holes in access filling mining
CN110953944A (en) * 2019-11-21 2020-04-03 中交隧道工程局有限公司 Method for rapid tunneling by hole-by-hole detonation of flat guide straight-hole cut of extra-long tunnel
CN211084969U (en) * 2019-05-29 2020-07-24 中交一公局集团有限公司 Two lining protection blasting systems of preceding hole in no well pilot tunnel even arch tunnel
CN112964143A (en) * 2021-03-24 2021-06-15 山东科技大学 Three-time blasting method for hollow hole straight-hole cut

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101148331B1 (en) * 2009-08-24 2012-05-21 서동현 Excavation method for pre-nailed tunneling
CN102435114A (en) * 2011-11-02 2012-05-02 中铁隧道集团有限公司 Explosion vibration control construction method of advance and following expanding excavation method of lower large heading of tunnel
CN103557756B (en) * 2013-11-01 2015-08-05 中铁四局集团有限公司 Pilot heading hole-specifically delayed ignition network in Tunnel Blasting
CN107218043A (en) * 2017-08-27 2017-09-29 中铁二十局集团第六工程有限公司 A kind of breaking surrounding rock cavern excavation method
KR102211018B1 (en) * 2018-09-04 2021-02-01 서동현 Vibration-free rapid excavation method using pilot tunnel in large-scale tunnel
CN109339797B (en) * 2018-09-04 2020-06-19 贵州省公路工程集团有限公司 Extremely-small-clear-distance tunnel exit shock absorption construction method
CN110487138B (en) * 2019-09-16 2022-04-15 中国十九冶集团有限公司 Full-section smooth blasting construction method for high-altitude small-section long steep slope tunnel
CN111397455A (en) * 2020-04-15 2020-07-10 辽宁科技大学 Combined detonation method for accurately controlling blasting effect in tunneling

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009228977A (en) * 2008-03-24 2009-10-08 Toda Constr Co Ltd Blasting construction method
CN102914226A (en) * 2012-11-08 2013-02-06 中国矿业大学(北京) Hollow-hole rhombic parallel cut blasting damping method
CN104564088A (en) * 2014-12-31 2015-04-29 中铁隧道集团有限公司 Construction method for heading double pilot tunnels for releasing high-ground stress rockbrust collapsing force
CN107091092A (en) * 2017-06-08 2017-08-25 宁波市交通规划设计研究院有限公司 The approximate full face tunneling structure of mountain highway tunnel neutrality country rock and method
CN109372509A (en) * 2018-11-16 2019-02-22 西北矿冶研究院 Arrangement method for double-hollow-hole rhombic cut holes in access filling mining
CN211084969U (en) * 2019-05-29 2020-07-24 中交一公局集团有限公司 Two lining protection blasting systems of preceding hole in no well pilot tunnel even arch tunnel
CN110953944A (en) * 2019-11-21 2020-04-03 中交隧道工程局有限公司 Method for rapid tunneling by hole-by-hole detonation of flat guide straight-hole cut of extra-long tunnel
CN112964143A (en) * 2021-03-24 2021-06-15 山东科技大学 Three-time blasting method for hollow hole straight-hole cut

Also Published As

Publication number Publication date
CN112964143A (en) 2021-06-15
CN112964143B (en) 2021-09-21

Similar Documents

Publication Publication Date Title
CN110132084B (en) Tunnel over-under-excavation control method
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
CN103321644A (en) Mechanical mode and control blasting combined tunneling method
CN106225618B (en) A kind of method that semo-infinite rock mass borehole blasting expansion is split
CN104564085B (en) Large section tunnel excavation comprehensive construction method under an ultra shallow underground layering part of city
CN111023930B (en) Tunnel step excavation method
CN108915694A (en) It the step tunneling boring unprotect layer tight-face blasting of tunnel lower layer and repairs the roads and protects logical construction method
WO2022198841A1 (en) Flying-limiting hole drilling and blasting method for controlling flying stones in tunnel blasting
WO2022198842A1 (en) Hollow-hole burn cut three-time blasting method
CN105627850A (en) Method for blasting construction of upper and lower fracture surfaces in IV/V-class surrounding rock through three-arm jumbo drill
CN108590688A (en) A kind of TBM development machines and its tunneling construction method with hydraulic drill rig
CN105065004B (en) A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method
CN112432566A (en) Full-section rapid excavation method for large-section tunnel
CN108050902A (en) A kind of tunnel blasting excavation method
CN111457804A (en) Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface
CN110440648B (en) Excavation method based on local section blasting and heading machine excavation
WO2023103256A1 (en) Deep hole vibration-reduction blasting method based on artificial freezing of weak surrounding rock in deep shaft
CN109341451A (en) A kind of damped blasting of tunnels structure and construction
CN109900175A (en) The low damage blasting method of underground mine tunnelling
CN210570271U (en) Cut hole structure for tunnel blasting tunneling engineering
CN209295800U (en) A kind of damped blasting of tunnels structure
CN105298502B (en) The construction method of rock hole wall large diameter pipeline Blasting Excavation
CN207147332U (en) A kind of Tunnel Blasting steel for shot structure
WO2022198839A1 (en) One-time detonation method for large-section tunnel
CN114251099B (en) Blasting excavation method for cross grotto

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21932456

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21932456

Country of ref document: EP

Kind code of ref document: A1