WO2021196657A1 - Novel fabricated anchorage structure serving as both dewatering well and support, and construction method - Google Patents

Novel fabricated anchorage structure serving as both dewatering well and support, and construction method Download PDF

Info

Publication number
WO2021196657A1
WO2021196657A1 PCT/CN2020/130264 CN2020130264W WO2021196657A1 WO 2021196657 A1 WO2021196657 A1 WO 2021196657A1 CN 2020130264 W CN2020130264 W CN 2020130264W WO 2021196657 A1 WO2021196657 A1 WO 2021196657A1
Authority
WO
WIPO (PCT)
Prior art keywords
foundation pit
adjacent
segments
dewatering well
segment
Prior art date
Application number
PCT/CN2020/130264
Other languages
French (fr)
Chinese (zh)
Inventor
武科
郑扬
孙杰
韩宇聪
罗浩天
Original Assignee
山东大学
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 山东大学 filed Critical 山东大学
Publication of WO2021196657A1 publication Critical patent/WO2021196657A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0001Rubbers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0023Slurry
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Definitions

  • the technical field of the geotechnical engineering of the present invention is specifically a novel assembly type anchoring structure and construction method that also serves as a dewatering well and a support.
  • the well point method needs to drill first, and at the same time, it is necessary to use a protective tube to protect the orifice. When lifting the drilling, it should be carried out slowly to prevent the orifice from collapsing and clogging. Secondly, it is necessary to place the well pipe, backfill the stone and wash the hole. It is more complicated and cumbersome, and it is easy to cause project delays.
  • foundation pit support such as soil nail wall, underground continuous wall, cast-in-place pile support and so on.
  • the underground diaphragm wall has high rigidity and good water-stop effect, so it is the strongest supporting form in the supporting structure, but it has higher requirements on the construction site, and special equipment is required during the construction process.
  • the temperature and humidity of the construction can easily lead to the cracking of the wall, which can not achieve the water-stop effect, so it is often treated with a water-stop curtain. This is the shortcoming of the prior art.
  • the technical problem to be solved by the present invention is to address the shortcomings of the prior art.
  • the present invention proposes a new type of prefabricated anchoring structure and construction method that also serves as a dewatering well and a support, which is used in a foundation pit dewatering and support system.
  • the construction and anchoring support method of the prefabricated building can not only play the role of well-point method for precipitation, but also play the role of water interception, seepage prevention, load bearing and water retaining as a new type of underground continuous wall, and overcome the temperature Limitation and disposal of waste mud.
  • a new type of prefabricated anchoring structure that doubles as a dewatering well and a support includes a plurality of prefabricated general segments assembled in sequence, and the general segment is reserved in the front and rear directions
  • Anchor rod groove after assembling adjacent common segments, an anchor hole can be formed.
  • the anchor rod is driven into the foundation pit wall in the anchor rod hole to form the anchor rod support, and the bolt is installed in the bolt hole to connect the adjacent common pipe segments in the left and right directions;
  • the lower end of the pumping steel pipe extends into the water layer, and the upper end of the pumping steel pipe is connected to the water collection header, and the water collection header is connected to a pump;
  • an elastic sealing gasket is arranged between adjacent general-purpose segments in the up and down direction. Elastic sealing gaskets are arranged between adjacent general-purpose tube segments in the left-right direction.
  • the cross section of the universal tube segment is a right-angled trapezoidal structure, the slopes of two adjacent universal tube segments in the left and right direction are spliced into a universal tube segment group, and two adjacent groups of universal tube segment groups are adjacent in the up and down direction.
  • the staggered setting of the splicing seams effectively ensures the stability of the general segment assembly.
  • a filter screen is provided at the lower end of the water pumping steel pipe, and the upper end of the water pumping steel pipe is connected to the water collecting header through a rubber tube.
  • the filter screen can play a filtering role, and the rubber tube is arranged to facilitate the connection of the pumping steel pipe and the water collecting main pipe.
  • the rubber tube ensures good air tightness between the pumping steel pipe and the water collecting main pipe.
  • the height of the universal segment is 3m, the upper short side is 2m, the lower short side is 3m, and the thickness is 1.2m.
  • the diameter of the bolt hole is 120mm, and the diameter of the dewatering well is 300mm.
  • the outer diameter of the steel pipe is 300mm.
  • the outer diameter of the pumping steel pipe is the same as the diameter of the dewatering well hole, which effectively ensures the stability of the pumping steel pipe installed in the dewatering well hole. Only one clamp is required to be installed on the pumping steel pipe. The clamp is located at the highest position.
  • the upper end of the pipe segment can effectively locate the pumping steel pipe.
  • the outer diameter of the pumping steel pipe is generally smaller than the diameter of the dewatering well hole.
  • the concrete slurry is poured between the outer wall and the dewatering well hole, so that it is not convenient to place pumping steel pipes in the dewatering well hole multiple times, and it is difficult to meet the demand for multiple dewatering.
  • the concrete slurry is poured into the hole of the dewatering well to form a pouring pile, which further ensures the stability of the connection of the universal segment.
  • the upper end surface, the lower end surface, the left end surface and the right end surface of the universal tube piece are provided with a sealing groove, and the elastic sealing gasket is arranged in the sealing groove.
  • a new type of construction method of a prefabricated anchoring structure that doubles as a dewatering well and a support includes the following steps:
  • the trenching machine excavates with grab buckets in different trench sections and batches according to the foundation pit line measured on the ground and the geological conditions of the site.
  • the machine excavates the trough section between the two holes to make it through, and completes the excavation of the trough section.
  • the construction personnel need to carry out the cement slurry surface treatment, and the cement slurry is mixed in the high-speed mixer. , The material is charged strictly according to the construction mix ratio.
  • a filter screen is provided at the lower end of the water pumping steel pipe, and the upper end of the water pumping steel pipe is connected to the water collecting header through a rubber tube.
  • the cross section of the universal tube segment is a right-angled trapezoidal structure
  • the cross section of the universal tube segment is a right-angled trapezoidal structure
  • the inclined surfaces of two adjacent universal tube segments in the left-right direction are spliced into a universal tube segment group,
  • the splicing seams between adjacent two sets of general segment groups are arranged staggered in the up and down direction.
  • Prefabrication of general-purpose segments in the factory omits on-site engineering measures such as drilling of dewatering wells, clearing holes, and backfilling sand, which greatly shortens the construction period and reduces engineering costs. It is suitable for a variety of weak formations and shallow The geological conditions such as buried stratum and low groundwater level are adjustable.
  • Figure 1 is a front view of a new type of prefabricated anchoring structure that doubles as a dewatering well and support;
  • Figure 2 is a top view of the new fabricated anchoring structure that doubles as a dewatering well and support.
  • Figure 3 is a side view of the new assembled anchoring structure that doubles as a dewatering well and support.
  • Figure 4 is the overall effect diagram of the new fabricated anchoring structure that doubles as a dewatering well and support.
  • Figure 5 is a new type of bolt diagram of the assembled anchoring structure that doubles as a dewatering well and support.
  • a new type of prefabricated anchoring structure that doubles as a dewatering well and a support includes a plurality of prefabricated general segments 1 assembled in sequence.
  • the general segment 1 is reserved with bolt grooves 1.1 in the front and rear directions. After assembling, adjacent general-purpose segments 1 can form bolt holes 9.
  • the general-purpose segment 1 is reserved with bolt holes in the left and right directions, and the general segment 1 is reserved with dewatering well holes 1.2 in the up and down direction.
  • the cross section of the universal tube piece 1 is a right-angled trapezoidal structure, and the inclined surfaces of two adjacent two universal tube pieces 1 in the left and right direction are spliced into a universal tube piece group.
  • the stitching seams between 2 are staggered.
  • the lower end of the pumping steel pipe 3 is provided with a filter screen 4, and the upper end of the pumping steel pipe 3 is connected to the water collecting header through a rubber tube 5.
  • the height of the universal segment 1 is 3m, the upper short side is 2m, the lower short side is 3m, and the thickness is 1.2m.
  • the diameter of the bolt hole 9 is 120mm, and the diameter of the dewatering well hole 1.2 is 300mm.
  • the outer diameter of the steel pipe 3 is 300 mm.
  • the upper end surface, the lower end surface, the left end surface and the right end surface of the universal tube piece 1 are provided with sealing grooves, and the elastic sealing gasket 8 is arranged in the sealing groove.
  • a new type of construction method of a prefabricated anchoring structure that doubles as a dewatering well and a support includes the following steps:
  • the anchor rod 7 is inserted so that the anchor rod 7 extends into the wall of the foundation pit; in order to ensure the safety of the construction site and prevent the collapse of the general segment 1, the hoisting machine needs to be hoisted until the construction personnel connect the bolts firmly and drive the anchor rod 7 into In the wall of the foundation pit;
  • step (2) the trenching machine excavates different trench sections and batches with grab buckets according to the foundation pit line measured on the ground and on-site geological conditions, and the rotary drilling rig excavates in turn After the two guide holes, the excavator digs the groove section between the two holes to make it through, and completes the excavation of the groove section. After the excavation of each section of the groove section is completed, the construction personnel need to carry out the cement slurry surface treatment. The mixing is carried out in a high-speed mixer, and the materials are charged in strict accordance with the construction mix ratio.
  • the grout surface treatment is performed and the general segment 1 is installed.
  • the lower end of the pumping steel pipe 3 is provided with a filter screen 4, and the upper end of the pumping steel pipe 3 is connected to the water collecting header through a rubber tube 5.
  • the cross section of the universal tube segment 1 is a right-angle trapezoidal structure
  • the cross-section of the universal tube segment 1 is a right-angle trapezoidal structure
  • the bevels of two adjacent universal tube segments 1 in the left-right direction are spliced into a universal tube segment group.
  • the splicing seams 2 between the adjacent two sets of general segment groups in the up and down direction are arranged in a staggered manner.
  • this embodiment has the following advantages:
  • Prefabricated general segment 1 in the factory omitted the on-site engineering measures such as drilling, clearing, and sand backfilling of dewatering wells, which greatly shortened the construction period and reduced the engineering cost. It is suitable for a variety of weak formations, The geological conditions such as shallow stratum and low groundwater level are adjustable.
  • dewatering well hole 1.2 reserved on the general segment 1, a pumping steel pipe 3 is installed as a vacuum dewatering well, which not only has good airtightness of the dewatering well, but also omits drilling, clearing and backfilling. A series of measures to shorten the construction period and reduce costs.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A novel fabricated anchorage structure serving as both a dewatering well and a support, and a construction method, relating to the technical field of geotechnical engineering. The fabricated anchorage structure comprises a plurality of prefabricated general purpose tube segments (1) which are assembled in sequence; anchor rod notches (1.1) are reserved on the general purpose tube segments (1) in the front-back direction; anchor rod holes (9) can be formed after the adjacent general purpose tube segments (1) are assembled; bolt holes are reserved on the general purpose tube segments (1) in the left-right direction; dewatering well holes (1.2) are reserved on the general purpose tube segments (1) in the up-down direction; anchor rods (7) are driven into the wall of a foundation pit from the anchor rod holes (9) to form an anchor rod support, and bolts are mounted in the bolt holes to connect the adjacent general purpose tube segments (1) in the left-right direction; water pumping steel tubes (3) penetrate through the dewatering well holes (1.2); the lower ends of the water pumping steel tubes (3) stretch into a water layer, and the upper ends of the water pumping steel tubes (3) are connected to a water collecting main pipe; the water collecting main pipe is connected to a water pump; elastic sealing pads (8) are provided between the adjacent general purpose tube segments (1) in the up-down direction, and elastic sealing pads (8) are provided between the adjacent general purpose tube segments (1) in the left-right direction.

Description

一种新型兼作降水井与支护的装配式锚固结构及施工方法A new type of prefabricated anchoring structure that doubles as dewatering well and support and construction method 技术领域Technical field
本发明岩土工程的技术领域,具体的是一种新型兼作降水井与支护的装配式锚固结构及施工方法。The technical field of the geotechnical engineering of the present invention is specifically a novel assembly type anchoring structure and construction method that also serves as a dewatering well and a support.
背景技术Background technique
在基坑开挖前,预先在基坑的四周根据计算开挖一定数量的降水井,利用抽水泵在开挖前不断的抽取地下水,使地下水位降低到基坑以下,促使土体固结,提高地基强度。但井点法降水需要首先进行钻孔,同时需要应用护筒对孔口进行保护并且提钻的时候要缓慢进行,防止孔口坍塌与堵塞,其次要放置井管、回填石料以及洗孔,工艺较复杂繁琐,容易造成工程延误。Before the excavation of the foundation pit, a certain number of dewatering wells are excavated in advance based on calculations around the foundation pit, and the groundwater is continuously pumped by the pump before excavation, so that the groundwater level is lowered below the foundation pit, and the soil is consolidated. Improve the strength of the foundation. However, the well point method needs to drill first, and at the same time, it is necessary to use a protective tube to protect the orifice. When lifting the drilling, it should be carried out slowly to prevent the orifice from collapsing and clogging. Secondly, it is necessary to place the well pipe, backfill the stone and wash the hole. It is more complicated and cumbersome, and it is easy to cause project delays.
基坑支护有多种形式,例如土钉墙、地下连续墙、灌注桩支护等。地下连续墙因具有刚度大,止水效果好,因此作为支护结构中最强的支护形式,但对施工场地要求较高,施工过程中要求专用设备,并且浇筑过后的钢筋混凝土墙受现场施工的温湿度影响,极易导致墙体的开裂,从而无法达到止水的效果,因此常常配合止水帷幕进行处理。这就是现有技术中的不足之处。There are many forms of foundation pit support, such as soil nail wall, underground continuous wall, cast-in-place pile support and so on. The underground diaphragm wall has high rigidity and good water-stop effect, so it is the strongest supporting form in the supporting structure, but it has higher requirements on the construction site, and special equipment is required during the construction process. The temperature and humidity of the construction can easily lead to the cracking of the wall, which can not achieve the water-stop effect, so it is often treated with a water-stop curtain. This is the shortcoming of the prior art.
发明内容Summary of the invention
本发明所要解决的技术问题,就是针对现有技术所存在的不足,本发明提出了一种新型兼作降水井与支护的装配式锚固结构及施工方法,用于基坑降水与支护体系中,借助于装配式建筑的施工与锚固支护方法,既能发挥井点法降水的作用,又能作为一种新型地下连续墙发挥截水、防渗、承重、挡水的作用,克服受温度限制和废泥浆处理的问题。The technical problem to be solved by the present invention is to address the shortcomings of the prior art. The present invention proposes a new type of prefabricated anchoring structure and construction method that also serves as a dewatering well and a support, which is used in a foundation pit dewatering and support system. With the help of the construction and anchoring support method of the prefabricated building, it can not only play the role of well-point method for precipitation, but also play the role of water interception, seepage prevention, load bearing and water retaining as a new type of underground continuous wall, and overcome the temperature Limitation and disposal of waste mud.
本方案是通过如下技术措施来实现的:一种新型兼作降水井与支护的装配式锚固结构,包括多个依次拼装的预制的通用管片,所述通用管片在前后方向上预留有锚杆槽,相邻的通用管片拼装后可形成锚杆孔,所述通用管片在左右方向上预留有螺栓孔,所述通用管片在上下方向上预留有降水井孔,从锚杆孔内将锚杆打入基坑壁上形成锚杆支护,从螺栓孔内安装螺栓将左右方向相邻的通用管片连接;在降水井孔内可贯穿设置有抽水钢管,所述抽水钢管的下端伸入水层,所述抽水钢管的上端与集水总管连接,所述集水总管连接有抽水泵;在上下方向上相邻的通用管片之间设置有弹性密封垫,在左右方向上相邻的通用管片之间设置有弹性密封垫。This solution is achieved through the following technical measures: a new type of prefabricated anchoring structure that doubles as a dewatering well and a support includes a plurality of prefabricated general segments assembled in sequence, and the general segment is reserved in the front and rear directions Anchor rod groove, after assembling adjacent common segments, an anchor hole can be formed. The anchor rod is driven into the foundation pit wall in the anchor rod hole to form the anchor rod support, and the bolt is installed in the bolt hole to connect the adjacent common pipe segments in the left and right directions; The lower end of the pumping steel pipe extends into the water layer, and the upper end of the pumping steel pipe is connected to the water collection header, and the water collection header is connected to a pump; an elastic sealing gasket is arranged between adjacent general-purpose segments in the up and down direction. Elastic sealing gaskets are arranged between adjacent general-purpose tube segments in the left-right direction.
优选的,所述通用管片的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组的拼接 缝交错设置,有效的保证了通用管片拼装的稳定性。Preferably, the cross section of the universal tube segment is a right-angled trapezoidal structure, the slopes of two adjacent universal tube segments in the left and right direction are spliced into a universal tube segment group, and two adjacent groups of universal tube segment groups are adjacent in the up and down direction. The staggered setting of the splicing seams effectively ensures the stability of the general segment assembly.
优选的,所述抽水钢管的下端设置有滤网,所述抽水钢管的上端通过橡胶管与集水总管连接。设置有滤网能够起到过滤作用,设置橡胶管方便抽水钢管与集水总管的连接,橡胶管保证抽水钢管与集水总管之间良好的气密性。Preferably, a filter screen is provided at the lower end of the water pumping steel pipe, and the upper end of the water pumping steel pipe is connected to the water collecting header through a rubber tube. The filter screen can play a filtering role, and the rubber tube is arranged to facilitate the connection of the pumping steel pipe and the water collecting main pipe. The rubber tube ensures good air tightness between the pumping steel pipe and the water collecting main pipe.
优选的,所述通用管片的高度为3m,上短边为2m,下短边为3m,厚度为1.2m,所述锚杆孔的直径为120mm,降水井孔直径为300mm,所述抽水钢管的外直径为300mm。所述抽水钢管的外直径与降水井孔的直径相同,有效的保证了抽水钢管安装在降水井孔的稳定性,只需要在抽水钢管上安装一个卡箍,所述卡箍位于位置最上的通用管片的上端,就能将抽水钢管有效的定位,常规设计中,所述抽水钢管的外直径一般会小于降水井孔的直径,为保证抽水钢管不在降水井孔内晃动,需要在抽水钢管的外壁与降水井孔之间浇筑混凝土浆,这样就不便于多次向降水井孔内放置抽水钢管,不好满足多次降水的需求。Preferably, the height of the universal segment is 3m, the upper short side is 2m, the lower short side is 3m, and the thickness is 1.2m. The diameter of the bolt hole is 120mm, and the diameter of the dewatering well is 300mm. The outer diameter of the steel pipe is 300mm. The outer diameter of the pumping steel pipe is the same as the diameter of the dewatering well hole, which effectively ensures the stability of the pumping steel pipe installed in the dewatering well hole. Only one clamp is required to be installed on the pumping steel pipe. The clamp is located at the highest position. The upper end of the pipe segment can effectively locate the pumping steel pipe. In conventional designs, the outer diameter of the pumping steel pipe is generally smaller than the diameter of the dewatering well hole. The concrete slurry is poured between the outer wall and the dewatering well hole, so that it is not convenient to place pumping steel pipes in the dewatering well hole multiple times, and it is difficult to meet the demand for multiple dewatering.
优选的,当锚固结构拼装完成后,向降水井孔内浇筑混凝土浆形成浇筑桩,进一步保证了通用管片连接的稳定性。Preferably, after the assembling of the anchoring structure is completed, the concrete slurry is poured into the hole of the dewatering well to form a pouring pile, which further ensures the stability of the connection of the universal segment.
优选的,所述通用管片的上端面、下端面、左端面以及右端面上均设置有密封槽,所述弹性密封垫设置在密封槽内。Preferably, the upper end surface, the lower end surface, the left end surface and the right end surface of the universal tube piece are provided with a sealing groove, and the elastic sealing gasket is arranged in the sealing groove.
一种新型兼作降水井与支护的装配式锚固结构的施工方法:包括以下步骤:A new type of construction method of a prefabricated anchoring structure that doubles as a dewatering well and a support: It includes the following steps:
(1)工厂预制通用管片,并将其运输至施工现场;(1) The factory prefabricates general-purpose segments and transports them to the construction site;
(2)根据施工图开挖基坑,为了保证施工质量,提前在平整的场地上进行测量并标注欲开挖的基坑线,将基坑内泥浆清理完毕,保证基坑壁的平整;(2) Excavate the foundation pit according to the construction drawings. In order to ensure the quality of the construction, carry out the measurement in advance on the flat site and mark the line of the foundation pit to be excavated, clean the mud in the foundation pit, and ensure the flatness of the foundation pit wall;
(3)使用吊装机将通用管片放置在基坑内并紧贴基坑壁竖向放置,相邻的通用管片之间放置弹性密封垫,相邻的通用管片之间对接形成锚杆孔,在左右方向上相邻的通用管片通过螺栓固定连接,在上下方向上将相邻的通用管片的降水井孔对齐,在前后方向上从锚杆孔内打入锚杆使得锚杆伸入基坑壁内;(3) Use the hoisting machine to place the universal pipe segments in the foundation pit and close to the wall of the foundation pit vertically. Place elastic gaskets between adjacent universal pipe segments, and connect adjacent universal pipe segments to form anchor rod holes. , Adjacent universal pipe segments in the left and right direction are fixedly connected by bolts, the dewatering well holes of the adjacent universal pipe segments are aligned in the up and down direction, and the anchor rod is driven into the anchor rod hole in the front and rear direction to make the anchor rod extend Into the wall of the foundation pit;
(4)将抽水钢管放入降水井孔并进行固定,所述抽水钢管的下端伸入水层,所述抽水钢管的上方与集水总管连接,启动与集水总管连接的抽水泵进行井点降水;(4) Put the pumping steel pipe into the dewatering well hole and fix it, the lower end of the pumping steel pipe extends into the water layer, and the upper part of the pumping steel pipe is connected with the water collection main pipe, and the water pump connected with the water collection main pipe is started to perform the well point precipitation;
(5)当通过井点降水达到下一次开挖基坑的安全高度后,将抽水钢管抽出,根据施工图纸预开挖基坑深度,向下依次安装通用管片,相邻的通用管片之间放置弹性密封垫,相邻的通用管片拼接形成锚杆孔,在左右方向上相邻的通用管片通过螺栓固定连接,在上下方向上将相邻的降水井孔对齐,在前后方向上从锚杆孔内打入锚杆使得锚杆深入基坑壁内,根据基坑的开挖深度,合理选择向下安装通用管片的片数;(5) When the safety height for the next excavation of the foundation pit is reached by dewatering through the well point, the pumped steel pipe is drawn out, the depth of the foundation pit is pre-excavated according to the construction drawings, and the general-purpose segments are installed in sequence downwards. One of the adjacent general-purpose segments Place elastic sealing gaskets between them, and the adjacent common pipe segments are spliced to form anchor rod holes. The adjacent common pipe segments in the left and right directions are fixedly connected by bolts, and the adjacent dewatering well holes are aligned in the up and down direction, Drive the anchor rod from the anchor rod hole to make the anchor rod go deep into the wall of the foundation pit. According to the excavation depth of the foundation pit, reasonably select the number of pieces of general-purpose segment to be installed downward;
(6)根据基坑的开挖深度,合理安排井点降水的次数,重复步骤(4)和步骤(5)直至形成基坑的地下连续墙;(6) According to the excavation depth of the foundation pit, reasonably arrange the number of well point precipitation, repeat steps (4) and (5) until the underground continuous wall of the foundation pit is formed;
(7)最后向降水井孔内浇筑混凝土浆形成浇筑桩。(7) Finally, pour concrete slurry into the dewatering well hole to form a pouring pile.
优选的,在步骤(2)中,挖槽机械根据地面测量的基坑线与现场地质条件,分不同槽段分批次抓斗开挖,旋挖钻机依次开挖两个导向孔后,挖掘机开挖两孔之间的槽段使之贯通,完成该槽段的开挖,在每段槽段开挖完成后,施工人员需要进行水泥浆抹面处理,水泥浆的搅拌在高速搅拌机内进行,严格按照施工配合比进行投料,水泥-水玻璃双液注浆参数为:水玻璃模数M=2.8~3.1,水玻璃溶液浓度Be′=35~40,水泥浆水灰比为0.75:1~1.0:1,水泥浆与水玻璃的体积比为1:0.5~1:1.0,槽段开挖完成后进行水泥浆抹面处理后进行通用管片的安装。Preferably, in step (2), the trenching machine excavates with grab buckets in different trench sections and batches according to the foundation pit line measured on the ground and the geological conditions of the site. The machine excavates the trough section between the two holes to make it through, and completes the excavation of the trough section. After the excavation of each section of the trough section is completed, the construction personnel need to carry out the cement slurry surface treatment, and the cement slurry is mixed in the high-speed mixer. , The material is charged strictly according to the construction mix ratio. The cement-water glass double-liquid grouting parameters are: water glass modulus M=2.8~3.1, water glass solution concentration Be′=35~40, cement slurry water-cement ratio is 0.75:1 ~1.0:1, the volume ratio of cement slurry to water glass is 1:0.5~1:1.0. After the excavation of the groove section is completed, the grout is applied to the surface and then the general segment is installed.
优选的,所述抽水钢管的下端设置有滤网,所述抽水钢管的上端通过橡胶管与集水总管连接。Preferably, a filter screen is provided at the lower end of the water pumping steel pipe, and the upper end of the water pumping steel pipe is connected to the water collecting header through a rubber tube.
优选的,所述通用管片的截面为直角梯形结构,所述通用管片的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组之间的拼接缝交错设置。Preferably, the cross section of the universal tube segment is a right-angled trapezoidal structure, the cross section of the universal tube segment is a right-angled trapezoidal structure, and the inclined surfaces of two adjacent universal tube segments in the left-right direction are spliced into a universal tube segment group, The splicing seams between adjacent two sets of general segment groups are arranged staggered in the up and down direction.
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
(1)加工方面:在工厂预制通用管片省略了现场进行降水井钻孔、清孔、回填砂料等工程措施,大大缩短了施工工期、减少了工程成本,适应于多种软弱地层、浅埋地层、地下水位较低等地质条件,具有可调节性。(1) In terms of processing: Prefabrication of general-purpose segments in the factory omits on-site engineering measures such as drilling of dewatering wells, clearing holes, and backfilling sand, which greatly shortens the construction period and reduces engineering costs. It is suitable for a variety of weak formations and shallow The geological conditions such as buried stratum and low groundwater level are adjustable.
(2)降水井方面:在通用管片上预留的降水井孔内贯穿设置抽水钢管作为真空降水井,不仅降水井的气密性良好,而且省略了钻孔、清孔、回填等一系列措施,缩短工期,降低成本。(2) In terms of dewatering wells: pumping steel pipes are installed as vacuum dewatering wells through the dewatering well holes reserved on the general segment. Not only the air tightness of the dewatering wells is good, but also a series of measures such as drilling, clearing and backfilling are omitted. , Shorten the construction period and reduce costs.
(3)基坑支护方面:锚固结构装配完成后,可在通用管片上预留的降水井孔内注入混凝土浆,从而形成灌注桩,进一步增强了通用管片连接的稳定性。(3) Foundation pit support: After the anchoring structure is assembled, concrete slurry can be injected into the dewatering well hole reserved on the general segment to form a cast-in-place pile, which further enhances the stability of the connection of the universal segment.
(4)施工方面:在施工过程中,可分多次降水、分多次开挖、分多次向下安装通用管片,在开挖的过程中,可通过锚杆支撑位置在上的通用管片。(4) Construction: In the construction process, it can be divided into multiple precipitations, multiple excavations, and multiple downward installation of general-purpose segments. During the excavation process, the anchor rod can be used to support the general purpose of the position. Tube piece.
由此可见,本发明与现有技术相比,具有突出的实质性特点和显著的进步,其实施的有益效果也是显而易见的。It can be seen that, compared with the prior art, the present invention has outstanding substantive features and significant progress, and the beneficial effects of its implementation are also obvious.
附图说明Description of the drawings
为了更清楚地说明本发明的技术方案,下面将对描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to explain the technical solution of the present invention more clearly, the following will briefly introduce the drawings that need to be used in the description. Obviously, the drawings in the following description are only some embodiments of the present invention. As far as personnel are concerned, they can also obtain other drawings based on these drawings without creative work.
图1为本新型兼作降水井与支护的装配式锚固结构的正视图;Figure 1 is a front view of a new type of prefabricated anchoring structure that doubles as a dewatering well and support;
图2为本新型兼作降水井与支护的装配式锚固结构的俯视图。Figure 2 is a top view of the new fabricated anchoring structure that doubles as a dewatering well and support.
图3为本新型兼作降水井与支护的装配式锚固结构的侧视图。Figure 3 is a side view of the new assembled anchoring structure that doubles as a dewatering well and support.
图4为本新型兼作降水井与支护的装配式锚固结构整体效果图。Figure 4 is the overall effect diagram of the new fabricated anchoring structure that doubles as a dewatering well and support.
图5为本新型兼作降水井与支护的装配式锚固结构的锚杆图。Figure 5 is a new type of bolt diagram of the assembled anchoring structure that doubles as a dewatering well and support.
图中:1-通用管片,1.1-锚杆槽,1.2-降水井孔,2-拼接缝,3-抽水钢管,4-滤网,5-橡胶管,6-承压板,7-锚杆,8-弹性密封垫,9-锚杆孔。In the picture: 1-universal segment, 1.1-anchor groove, 1.2-dewatering well hole, 2-splicing joint, 3-pumping steel pipe, 4-filter mesh, 5-rubber tube, 6-pressure plate, 7- Anchor rod, 8-elastic gasket, 9-bolt hole.
具体实施方式Detailed ways
为使得本发明的发明目的、特征、优点能够更加的明显和易懂,下面将运用具体的实施例及附图,对本发明保护的技术方案进行清楚、完整地描述,显然,下面所描述的实施例仅仅是本发明一部分实施例,而非全部的实施例。基于本专利中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本专利保护的范围。In order to make the objectives, features, and advantages of the present invention more obvious and understandable, specific embodiments and drawings will be used below to clearly and completely describe the technical solutions protected by the present invention. Obviously, the implementation described below The examples are only a part of the embodiments of the present invention, not all the embodiments. Based on the embodiments in this patent, all other embodiments obtained by a person of ordinary skill in the art without creative work shall fall within the scope of protection of this patent.
实施例1Example 1
如图所示,一种新型兼作降水井与支护的装配式锚固结构,包括多个依次拼装的预制的通用管片1,所述通用管片1在前后方向上预留有锚杆槽1.1,相邻的通用管片1拼装后可形成锚杆孔9,所述通用管片1在左右方向上预留有螺栓孔,所述通用管片1在上下方向上预留有降水井孔1.2,从锚杆孔9内将锚杆7打入基坑壁上形成锚杆支护,在螺栓孔内安装螺栓将左右方向相邻的通用管片1连接,在降水井孔1.2内可贯穿设置有抽水钢管3,所述抽水钢管3的下端伸入水层,所述抽水钢管3的上端与集水总管连接,所述集水总管连接有抽水泵,在上下方向上相邻的通用管片1之间设置有弹性密封垫8,在左右方向上相邻的通用管片1之间设置有弹性密封垫8,所述弹性密封垫8为三元乙丙橡胶垫。As shown in the figure, a new type of prefabricated anchoring structure that doubles as a dewatering well and a support includes a plurality of prefabricated general segments 1 assembled in sequence. The general segment 1 is reserved with bolt grooves 1.1 in the front and rear directions. After assembling, adjacent general-purpose segments 1 can form bolt holes 9. The general-purpose segment 1 is reserved with bolt holes in the left and right directions, and the general segment 1 is reserved with dewatering well holes 1.2 in the up and down direction. , Drive the anchor rod 7 into the foundation pit wall from the anchor rod hole 9 to form the anchor rod support, install the bolt in the bolt hole to connect the adjacent common pipe segments 1 in the left and right directions, and can be installed through the dewatering well hole 1.2 There is a pumping steel pipe 3, the lower end of the pumping steel pipe 3 extends into the water layer, the upper end of the pumping steel pipe 3 is connected with a water collection header, the water collection header is connected with a water pump, and the general-purpose tube segments adjacent in the up and down direction An elastic sealing gasket 8 is arranged between 1 and an elastic sealing gasket 8 is arranged between adjacent general-purpose tube pieces 1 in the left-right direction. The elastic sealing gasket 8 is an EPDM rubber gasket.
所述通用管片1的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片1的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组之间的拼接缝2交错设置。The cross section of the universal tube piece 1 is a right-angled trapezoidal structure, and the inclined surfaces of two adjacent two universal tube pieces 1 in the left and right direction are spliced into a universal tube piece group. The stitching seams between 2 are staggered.
所述抽水钢管3的下端设置有滤网4,所述抽水钢管3的上端通过橡胶管5与集水总管连接。The lower end of the pumping steel pipe 3 is provided with a filter screen 4, and the upper end of the pumping steel pipe 3 is connected to the water collecting header through a rubber tube 5.
所述通用管片1的高度为3m,上短边为2m,下短边为3m,厚度为1.2m,所述锚杆孔9的直径为120mm,降水井孔1.2直径为300mm,所述抽水钢管3的外直径为300mm。The height of the universal segment 1 is 3m, the upper short side is 2m, the lower short side is 3m, and the thickness is 1.2m. The diameter of the bolt hole 9 is 120mm, and the diameter of the dewatering well hole 1.2 is 300mm. The outer diameter of the steel pipe 3 is 300 mm.
当锚固结构拼装完成后,向降水井孔1.2内浇筑混凝土浆形成浇筑桩。After the anchoring structure is assembled, pour concrete slurry into the dewatering well hole 1.2 to form a pouring pile.
所述通用管片1的上端面、下端面、左端面以及右端面上均设置有密封槽, 所述弹性密封垫8设置在密封槽内。The upper end surface, the lower end surface, the left end surface and the right end surface of the universal tube piece 1 are provided with sealing grooves, and the elastic sealing gasket 8 is arranged in the sealing groove.
实施例2Example 2
一种新型兼作降水井与支护的装配式锚固结构的施工方法:包括以下步骤:A new type of construction method of a prefabricated anchoring structure that doubles as a dewatering well and a support: It includes the following steps:
(1)工厂预制通用管片1,并将其运输至施工现场;(1) The factory prefabricates general segment 1 and transports it to the construction site;
(2)根据施工图开挖基坑,为了保证施工质量,提前在平整的场地上进行测量并标注欲开挖的基坑线,将基坑内泥浆清理完毕,保证基坑壁的平整;(2) Excavate the foundation pit according to the construction drawings. In order to ensure the quality of the construction, carry out the measurement in advance on the flat site and mark the line of the foundation pit to be excavated, clean the mud in the foundation pit, and ensure the flatness of the foundation pit wall;
(3)使用吊装机将通用管片1放置在基坑内并紧贴基坑壁竖向放置,相邻的通用管片1之间放置弹性密封垫8,相邻的通用管片1拼接形成锚杆孔9,在左右方向上相邻的通用管片1通过螺栓固定连接,在上下方向上将相邻的通用管片1的降水井孔1.2对齐,在前后方向上从锚杆孔9内打入锚杆7使得锚杆7伸入基坑壁内;为保证施工现场的安全,防止通用管片1的倒塌,吊装机需一直进行吊装直到施工人员将螺栓连接牢固,将锚杆7打入基坑壁内;(3) Use the hoisting machine to place the universal segment 1 in the foundation pit and place it close to the wall of the foundation pit vertically. Place an elastic gasket 8 between the adjacent universal segments 1, and the adjacent universal segments 1 are spliced to form an anchor The rod hole 9 is fixedly connected by bolts to the adjacent universal tube segments 1 in the left and right direction. The dewatering well holes 1.2 of the adjacent universal tube segments 1 are aligned in the up and down direction, and the anchor rod hole 9 is drilled in the front and back direction. The anchor rod 7 is inserted so that the anchor rod 7 extends into the wall of the foundation pit; in order to ensure the safety of the construction site and prevent the collapse of the general segment 1, the hoisting machine needs to be hoisted until the construction personnel connect the bolts firmly and drive the anchor rod 7 into In the wall of the foundation pit;
(4)将抽水钢管3放入降水井孔1.2并进行固定,所述抽水钢管3的下端伸入水层,所述抽水钢管3的上方与集水总管连接,启动与集水总管连接的抽水泵进行井点降水;(4) Put the pumping steel pipe 3 into the dewatering well hole 1.2 and fix it. The lower end of the pumping steel pipe 3 extends into the water layer. Water pump for well point precipitation;
(5)当通过井点降水达到下一次开挖基坑的安全高度后,将抽水钢管3抽出,根据施工图纸预开挖基坑深度,向下依次安装通用管片1,相邻的通用管片1之间放置弹性密封垫8,相邻的通用管片1之间对接形成锚杆孔9,在左右方向上相邻的通用管片1通过螺栓固定连接,在上下方向上将相邻的降水井孔1.2对齐,在前后方向上从锚杆孔9内打入锚杆7使得锚杆7深入基坑壁内,根据基坑的开挖深度,合理选择向下安装通用管片1的片数;(5) When the safety height of the next excavation of the foundation pit is reached through the well point, the pumping steel pipe 3 is drawn out, and the depth of the foundation pit is pre-excavated according to the construction drawings. An elastic gasket 8 is placed between the sheets 1, and the adjacent general-purpose tube sheets 1 are butt-connected to form an anchor rod hole 9. The adjacent general-purpose tube sheets 1 are fixedly connected by bolts in the vertical direction Align the hole 1.2 of the dewatering well, and drive the anchor rod 7 from the anchor rod hole 9 in the front and back direction to make the anchor rod 7 penetrate into the wall of the foundation pit. According to the excavation depth of the foundation pit, choose the piece of universal segment 1 to be installed downward. number;
(6)根据基坑的开挖深度,合理安排井点降水的次数,重复步骤(4)和步骤(5)直至形成基坑的地下连续墙;(6) According to the excavation depth of the foundation pit, reasonably arrange the number of well point precipitation, repeat steps (4) and (5) until the underground continuous wall of the foundation pit is formed;
(7)最后向降水井孔1.2内浇筑混凝土浆形成浇筑桩。(7) Finally, pour concrete slurry into the dewatering well hole 1.2 to form a pouring pile.
实施例3Example 3
与实施例2的不同之处在于:在步骤(2)中,挖槽机械根据地面测量的基坑线与现场地质条件,分不同槽段分批次抓斗开挖,旋挖钻机依次开挖两个导向孔后,挖掘机开挖两孔之间的槽段使之贯通,完成该槽段的开挖,在每段槽段开挖完成后,施工人员需要进行水泥浆抹面处理,水泥浆的搅拌在高速搅拌机内进行,严格按照施工配合比进行投料,水泥-水玻璃双液注浆参数为:水玻璃模数M=2.8~3.1,水玻璃溶液浓度Be′=35~40,水泥浆水灰比为0.75:1~1.0:1,水泥浆与水玻璃的体积比为1:0.5~1:1.0,槽段开挖完成后进行水泥浆抹面处理后进行通用管片1的安装。优选的,水玻璃模数M=2.8,水玻璃溶液浓度Be′=35,水泥浆 水灰比为0.75:1,水泥浆与水玻璃的体积比为1:0.5。The difference from Example 2 is that in step (2), the trenching machine excavates different trench sections and batches with grab buckets according to the foundation pit line measured on the ground and on-site geological conditions, and the rotary drilling rig excavates in turn After the two guide holes, the excavator digs the groove section between the two holes to make it through, and completes the excavation of the groove section. After the excavation of each section of the groove section is completed, the construction personnel need to carry out the cement slurry surface treatment. The mixing is carried out in a high-speed mixer, and the materials are charged in strict accordance with the construction mix ratio. The cement-water glass two-fluid grouting parameters are: water glass modulus M=2.8~3.1, water glass solution concentration Be′=35~40, cement slurry The water-cement ratio is 0.75:1~1.0:1, and the volume ratio of cement slurry to water glass is 1:0.5~1:1.0. After the excavation of the trough section is completed, the grout surface treatment is performed and the general segment 1 is installed. Preferably, the water glass modulus M=2.8, the water glass solution concentration Be'=35, the cement slurry water cement ratio is 0.75:1, and the volume ratio of cement slurry to water glass is 1:0.5.
所述抽水钢管3的下端设置有滤网4,所述抽水钢管3的上端通过橡胶管5与集水总管连接。所述通用管片1的截面为直角梯形结构,所述通用管片1的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片1的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组之间的拼接缝2交错设置。The lower end of the pumping steel pipe 3 is provided with a filter screen 4, and the upper end of the pumping steel pipe 3 is connected to the water collecting header through a rubber tube 5. The cross section of the universal tube segment 1 is a right-angle trapezoidal structure, the cross-section of the universal tube segment 1 is a right-angle trapezoidal structure, and the bevels of two adjacent universal tube segments 1 in the left-right direction are spliced into a universal tube segment group. The splicing seams 2 between the adjacent two sets of general segment groups in the up and down direction are arranged in a staggered manner.
与现有技术相比,本实施例有以下优势:Compared with the prior art, this embodiment has the following advantages:
(1)加工方面:在工厂预制通用管片1省略了现场进行降水井钻孔、清孔、回填砂料等工程措施,大大缩短了施工工期、减少了工程成本,适应于多种软弱地层、浅埋地层、地下水位较低等地质条件,具有可调节性。(1) In terms of processing: Prefabricated general segment 1 in the factory omitted the on-site engineering measures such as drilling, clearing, and sand backfilling of dewatering wells, which greatly shortened the construction period and reduced the engineering cost. It is suitable for a variety of weak formations, The geological conditions such as shallow stratum and low groundwater level are adjustable.
(2)降水井方面:在通用管片1上预留的降水井孔1.2内贯穿设置抽水钢管3作为真空降水井,不仅降水井的气密性良好,而且省略了钻孔、清孔、回填等一系列措施,缩短工期,降低成本。(2) In terms of dewatering wells: In the dewatering well hole 1.2 reserved on the general segment 1, a pumping steel pipe 3 is installed as a vacuum dewatering well, which not only has good airtightness of the dewatering well, but also omits drilling, clearing and backfilling. A series of measures to shorten the construction period and reduce costs.
(3)基坑支护方面:锚固结构装配完成后,可在通用管片1上预留的降水井孔1.2内注入混凝土浆,从而形成灌注桩,进一步增强了通用管片1连接的稳定性。(3) Foundation pit support: After the anchoring structure is assembled, concrete slurry can be injected into the dewatering well hole 1.2 reserved on the general segment 1 to form a cast-in-place pile, which further enhances the stability of the connection of the general segment 1 .
(4)施工方面:在施工过程中,可分多次降水、分多次开挖、分多次向下安装通用管片1,在开挖的过程中,可通过锚杆7支撑位置在上的通用管片1。(4) Construction: During the construction process, it can be divided into multiple precipitations, multiple excavations, and multiple downward installation of the general segment 1. During the excavation process, the anchor rod 7 can be used to support the upper position. The universal tube piece 1.
本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参考即可。The various embodiments in this specification are described in a progressive manner. Each embodiment focuses on the differences from other embodiments, and the same or similar parts between the various embodiments can be referred to each other.
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点、创造性的特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown in this text, but should conform to the widest scope consistent with the principles, novel features, and creative features disclosed in this text.

Claims (10)

  1. 一种新型兼作降水井与支护的装配式锚固结构,其特征是:包括多个依次拼装的预制的通用管片,所述通用管片在前后方向上预留有锚杆槽,相邻的通用管片拼装后可形成锚杆孔,所述通用管片在左右方向上预留有螺栓孔,所述通用管片在上下方向上预留有降水井孔,从锚杆孔内将锚杆打入基坑壁上形成锚杆支护,从螺栓孔内安装螺栓将左右方向相邻的通用管片连接;在降水井孔内可贯穿设置有抽水钢管,所述抽水钢管的下端伸入水层,所述抽水钢管的上端与集水总管连接,所述集水总管连接有抽水泵;在上下方向上相邻的通用管片之间设置有弹性密封垫,在左右方向上相邻的通用管片之间设置有弹性密封垫。A new type of prefabricated anchoring structure that doubles as a dewatering well and a support is characterized in that it includes a plurality of prefabricated general segments assembled in sequence, and the general segment is reserved with anchor grooves in the front and rear directions, and adjacent Anchor rod holes can be formed after assembly of the universal segment, the universal segment is reserved with bolt holes in the left and right directions, and the universal segment is reserved with dewatering well holes in the up and down direction. Driven into the wall of the foundation pit to form anchor rod support, install bolts from the bolt holes to connect the adjacent common pipe segments in the left and right directions; pumping steel pipes can be installed through the dewatering well holes, and the lower end of the pumping steel pipes is inserted into the water Layer, the upper end of the water pumping steel pipe is connected with the water collecting main pipe, and the water collecting main pipe is connected with a water pump; an elastic sealing gasket is arranged between the adjacent common pipe segments in the up and down direction, and the adjacent common pipe in the left and right directions An elastic sealing gasket is arranged between the tube segments.
  2. 根据权利要求1所述的新型兼作降水井与支护的装配式锚固结构,其特征是:所述通用管片的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组的拼接缝交错设置。The new fabricated anchoring structure for both dewatering wells and support according to claim 1, characterized in that: the cross section of the general segment is a right-angle trapezoidal structure, and two adjacent general segments are arranged in the left and right directions. The inclined planes of the two groups are spliced into a common segment group, and the splicing seams of two adjacent groups of the common segment group are arranged in a staggered manner in the up and down direction.
  3. 根据权利要求1所述的新型兼作降水井与支护的装配式锚固结构,其特征是:所述抽水钢管的下端设置有滤网,所述抽水钢管的上端通过橡胶管与集水总管连接。The new fabricated anchoring structure for both dewatering wells and support according to claim 1, characterized in that: the lower end of the pumping steel pipe is provided with a filter screen, and the upper end of the pumping steel pipe is connected to the header pipe through a rubber pipe.
  4. 根据权利要求2所述的新型兼作降水井与支护的装配式锚固结构,其特征是:所述通用管片的高度为3m,上短边为2m,下短边为3m,厚度为1.2m,所述锚杆孔的直径为120mm,降水井孔直径为300mm,所述抽水钢管的外直径为300mm。The new fabricated anchoring structure for both dewatering wells and support according to claim 2, characterized in that: the height of the general segment is 3m, the upper short side is 2m, the lower short side is 3m, and the thickness is 1.2m The diameter of the bolt hole is 120mm, the diameter of the dewatering well hole is 300mm, and the outer diameter of the pumping steel pipe is 300mm.
  5. 根据权利要求1所述的新型兼作降水井与支护的装配式锚固结构,其特征是:当锚固结构拼装完成后,向降水井孔内浇筑混凝土浆形成浇筑桩。According to claim 1, the new fabricated anchoring structure for both dewatering well and support is characterized in that: after the anchoring structure is assembled, concrete slurry is poured into the dewatering well hole to form a pouring pile.
  6. 根据权利要求2所述的新型兼作降水井与支护的装配式锚固结构,其特征是:所述通用管片的上端面、下端面、左端面以及右端面上均设置有密封槽,所述弹性密封垫设置在密封槽内。The new fabricated anchoring structure for both dewatering wells and support according to claim 2, characterized in that: the upper end surface, the lower end surface, the left end surface and the right end surface of the universal segment are all provided with sealing grooves, the The elastic sealing gasket is arranged in the sealing groove.
  7. 一种新型兼作降水井与支护的装配式锚固结构的施工方法:其特征是:包括以下步骤:A new type of construction method of a prefabricated anchoring structure that doubles as a dewatering well and a support: It is characterized in that it includes the following steps:
    (1)工厂预制通用管片,并将其运输至施工现场;(1) The factory prefabricates general-purpose segments and transports them to the construction site;
    (2)根据施工图开挖基坑,为了保证施工质量,提前在平整的场地上进行测量并标注欲开挖的基坑线,将基坑内泥浆清理完毕,保证基坑壁的平整;(2) Excavate the foundation pit according to the construction drawings. In order to ensure the quality of the construction, carry out the measurement in advance on the flat site and mark the line of the foundation pit to be excavated, clean the mud in the foundation pit, and ensure the flatness of the foundation pit wall;
    (3)使用吊装机将通用管片放置在基坑内并紧贴基坑壁竖向放置,相邻的通用管片之间放置弹性密封垫,相邻的通用管片之间对接形成锚杆孔,在左右方向上相邻的通用管片通过螺栓固定连接,在上下方向上将相邻的通用管片的降水 井孔对齐,在前后方向上从锚杆孔内打入锚杆使得锚杆伸入基坑壁内;(3) Use the hoisting machine to place the universal pipe segments in the foundation pit and close to the wall of the foundation pit vertically. Place elastic gaskets between adjacent universal pipe segments, and connect adjacent universal pipe segments to form anchor rod holes. , Adjacent universal pipe segments in the left and right direction are fixedly connected by bolts, the dewatering well holes of the adjacent universal pipe segments are aligned in the up and down direction, and the anchor rod is driven into the anchor rod hole in the front and rear direction to make the anchor rod extend Into the wall of the foundation pit;
    (4)将抽水钢管放入降水井孔并进行固定,所述抽水钢管的下端伸入水层,所述抽水钢管的上方与集水总管连接,启动与集水总管连接的抽水泵进行井点降水;(4) Put the pumping steel pipe into the dewatering well hole and fix it, the lower end of the pumping steel pipe extends into the water layer, and the upper part of the pumping steel pipe is connected with the water collection main pipe, and the water pump connected with the water collection main pipe is started to perform the well point precipitation;
    (5)当通过井点降水达到下一次开挖基坑的安全高度后,将抽水钢管抽出,根据施工图纸预开挖基坑深度,向下依次安装通用管片,相邻的通用管片之间放置弹性密封垫,相邻的通用管片拼接形成锚杆孔,在左右方向上相邻的通用管片通过螺栓固定连接,在上下方向上将相邻的降水井孔对齐,在前后方向上从锚杆孔内打入锚杆使得锚杆深入基坑壁内,根据基坑的开挖深度,合理选择向下安装通用管片的片数;(5) When the safety height for the next excavation of the foundation pit is reached by dewatering through the well point, the pumped steel pipe is drawn out, the depth of the foundation pit is pre-excavated according to the construction drawings, and the general-purpose segments are installed in sequence downwards. One of the adjacent general-purpose segments Place elastic sealing gaskets between them, and the adjacent common pipe segments are spliced to form anchor rod holes. The adjacent common pipe segments in the left and right directions are fixedly connected by bolts, and the adjacent dewatering well holes are aligned in the up and down direction, Drive the anchor rod from the anchor rod hole to make the anchor rod go deep into the wall of the foundation pit. According to the excavation depth of the foundation pit, reasonably select the number of pieces of general-purpose segment to be installed downward;
    (6)根据基坑的开挖深度,合理安排井点降水的次数,重复步骤(4)和步骤(5)直至形成基坑的地下连续墙;(6) According to the excavation depth of the foundation pit, reasonably arrange the number of well point precipitation, repeat steps (4) and (5) until the underground continuous wall of the foundation pit is formed;
    (7)最后向降水井孔内浇筑混凝土浆形成浇筑桩。(7) Finally, pour concrete slurry into the dewatering well hole to form a pouring pile.
  8. 根据权利要求7所述的新型兼作降水井与支护的装配式锚固结构的施工方法,其特征是:在步骤(2)中,挖槽机械根据地面测量的基坑线与现场地质条件,分不同槽段分批次抓斗开挖,旋挖钻机依次开挖两个导向孔后,挖掘机开挖两孔之间的槽段使之贯通,完成该槽段的开挖,在每段槽段开挖完成后,施工人员需要进行水泥浆抹面处理,水泥浆的搅拌在高速搅拌机内进行,严格按照施工配合比进行投料,水泥-水玻璃双液注浆参数为:水玻璃模数M=2.8~3.1,水玻璃溶液浓度Be′=35~40,水泥浆水灰比为0.75:1~1.0:1,水泥浆与水玻璃的体积比为1:0.5~1:1.0,槽段开挖完成后进行水泥浆抹面处理后进行通用管片的安装。The construction method of a new type of prefabricated anchoring structure that doubles as a dewatering well and a support according to claim 7, characterized in that: in step (2), the trenching machine is divided according to the foundation pit line measured on the ground and the geological conditions of the site. Different groove sections are excavated in batches with grab buckets. After the rotary drilling rig digs two pilot holes in turn, the excavator digs the groove section between the two holes to make it through to complete the excavation of the groove section. After the excavation of the section is completed, the construction personnel need to carry out the cement slurry surface treatment. The cement slurry is stirred in a high-speed mixer, and the materials are charged in strict accordance with the construction ratio. The cement-water glass double-liquid grouting parameter is: water glass modulus M = 2.8~3.1, the concentration of water glass solution Be'=35~40, the water-cement ratio of cement slurry is 0.75:1~1.0:1, the volume ratio of cement slurry and water glass is 1:0.5~1:1.0, the excavation of the trench section After the completion of the cement grout surface treatment, the general-purpose segment is installed.
  9. 根据权利要求7所述的新型兼作降水井与支护的装配式锚固结构的施工方法,其特征是:所述抽水钢管的下端设置有滤网,所述抽水钢管的上端通过橡胶管与集水总管连接。The construction method of a new type of assembly anchoring structure that doubles as a dewatering well and a support according to claim 7, characterized in that: the lower end of the pumping steel pipe is provided with a filter screen, and the upper end of the pumping steel pipe is connected to the water collecting pipe through a rubber pipe. Header connection.
  10. 根据权利要求7所述的新型兼作降水井与支护的装配式锚固结构的施工方法,其特征是:所述通用管片的截面为直角梯形结构,所述通用管片的截面为直角梯形结构,在左右方向上两个相邻的两个通用管片的斜面拼接为通用管片组,在上下方向上相邻两组通用管片组之间的拼接缝交错设置。The construction method of a novel assembly anchoring structure that also serves as a dewatering well and a support according to claim 7, wherein the cross section of the general segment is a right-angle trapezoidal structure, and the cross-section of the universal segment is a right-angle trapezoidal structure , In the left and right directions, the bevels of two adjacent general tube segments are spliced into a general tube segment group, and the splicing seams between the two adjacent groups of general tube segment groups in the up and down direction are arranged in a staggered manner.
PCT/CN2020/130264 2020-04-03 2020-11-20 Novel fabricated anchorage structure serving as both dewatering well and support, and construction method WO2021196657A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202010260894.3A CN111350202A (en) 2020-04-03 2020-04-03 Novel assembly type anchoring structure capable of being used as dewatering well and support and construction method
CN202010260894.3 2020-04-03

Publications (1)

Publication Number Publication Date
WO2021196657A1 true WO2021196657A1 (en) 2021-10-07

Family

ID=71194802

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/130264 WO2021196657A1 (en) 2020-04-03 2020-11-20 Novel fabricated anchorage structure serving as both dewatering well and support, and construction method

Country Status (2)

Country Link
CN (1) CN111350202A (en)
WO (1) WO2021196657A1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114293573A (en) * 2022-01-19 2022-04-08 中国长江三峡集团有限公司 Drainable anti-slide pile and construction method thereof
CN114351718A (en) * 2022-01-11 2022-04-15 吉林大学 Subway station construction foundation pit supporting and stabilizing device
CN114411787A (en) * 2022-02-10 2022-04-29 中铁广州工程局集团有限公司 Well point dewatering method for steel cofferdam in water
CN114606930A (en) * 2022-03-29 2022-06-10 中天建设集团有限公司 Assembly type recyclable underground continuous wall and construction method thereof
CN114908856A (en) * 2022-06-14 2022-08-16 中交(广州)建设有限公司 Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof
CN115110538A (en) * 2022-06-01 2022-09-27 中国一冶集团有限公司 Light well point and steel sleeve box combined dewatering support construction method
CN115182369A (en) * 2022-07-29 2022-10-14 中交(南京)建设有限公司 Dewatering well structure and pile foundation construction method reconstructed by utilizing dewatering well
CN115787693A (en) * 2022-12-07 2023-03-14 兰州理工大学 Water stopping method for water gushing in deep foundation pit under riverside slow-dip interbed
CN116290282A (en) * 2023-04-23 2023-06-23 中铁一局集团市政环保工程有限公司 Construction method for connecting new and old pipelines

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111350202A (en) * 2020-04-03 2020-06-30 山东大学 Novel assembly type anchoring structure capable of being used as dewatering well and support and construction method
CN114606951B (en) * 2022-03-03 2024-01-12 北京大圣智造科技有限公司 Intelligent assembled inverted hanging structure in foundation pit and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106978814A (en) * 2017-05-09 2017-07-25 天津大学 A kind of Fabricated Structure for Support of Excavation
JP2017203255A (en) * 2016-05-09 2017-11-16 藤村ヒューム管株式会社 Panel connector and connected wall formed by the same
CN206971229U (en) * 2017-05-11 2018-02-06 中国建筑第八工程局有限公司 Foundation pit supporting construction with precipitation function
CN109281313A (en) * 2018-09-27 2019-01-29 广州地铁设计研究院股份有限公司 A kind of Prefabricated composite box diaphram wall and its construction method
CN109778836A (en) * 2019-02-15 2019-05-21 中煤江南建设发展有限公司 A kind of prefabricated ground-connecting-wall structure and structure-based construction method
CN209114482U (en) * 2018-10-24 2019-07-16 福建卓越建设工程开发有限公司 A kind of recyclable composite soil nailing wall of assembled flexible surface layer
CN209277165U (en) * 2018-07-19 2019-08-20 天津大学 A kind of detachable lightweight assembled pattern foundation pit supporting structure
CN110409474A (en) * 2019-08-07 2019-11-05 中煤第三建设(集团)有限责任公司 It is placed in the pipe well for lower water of diaphram wall bottom
CN111350202A (en) * 2020-04-03 2020-06-30 山东大学 Novel assembly type anchoring structure capable of being used as dewatering well and support and construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09144016A (en) * 1995-11-28 1997-06-03 Takenaka Komuten Co Ltd Execution method of concrete in underground water leakage section
CN104632250A (en) * 2014-12-17 2015-05-20 北京工业大学 Prefabricated tunnel lining structure of inverted segments for round foundation pit and construction method of prefabricated tunnel lining structure
CN207130741U (en) * 2017-07-03 2018-03-23 袁雪峰 A kind of precast concrete slope protecting components and protective slope structure
CN110295615A (en) * 2019-07-25 2019-10-01 常州工学院 A kind of recyclable and prefabricated slope retaining structure and construction method
CN110939125A (en) * 2019-12-30 2020-03-31 广州地铁设计研究院股份有限公司 Sealing structure of prefabricated underground continuous wall

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017203255A (en) * 2016-05-09 2017-11-16 藤村ヒューム管株式会社 Panel connector and connected wall formed by the same
CN106978814A (en) * 2017-05-09 2017-07-25 天津大学 A kind of Fabricated Structure for Support of Excavation
CN206971229U (en) * 2017-05-11 2018-02-06 中国建筑第八工程局有限公司 Foundation pit supporting construction with precipitation function
CN209277165U (en) * 2018-07-19 2019-08-20 天津大学 A kind of detachable lightweight assembled pattern foundation pit supporting structure
CN109281313A (en) * 2018-09-27 2019-01-29 广州地铁设计研究院股份有限公司 A kind of Prefabricated composite box diaphram wall and its construction method
CN209114482U (en) * 2018-10-24 2019-07-16 福建卓越建设工程开发有限公司 A kind of recyclable composite soil nailing wall of assembled flexible surface layer
CN109778836A (en) * 2019-02-15 2019-05-21 中煤江南建设发展有限公司 A kind of prefabricated ground-connecting-wall structure and structure-based construction method
CN110409474A (en) * 2019-08-07 2019-11-05 中煤第三建设(集团)有限责任公司 It is placed in the pipe well for lower water of diaphram wall bottom
CN111350202A (en) * 2020-04-03 2020-06-30 山东大学 Novel assembly type anchoring structure capable of being used as dewatering well and support and construction method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114351718A (en) * 2022-01-11 2022-04-15 吉林大学 Subway station construction foundation pit supporting and stabilizing device
CN114293573A (en) * 2022-01-19 2022-04-08 中国长江三峡集团有限公司 Drainable anti-slide pile and construction method thereof
CN114293573B (en) * 2022-01-19 2024-02-06 中国长江三峡集团有限公司 Drainage type anti-skid pile and construction method thereof
CN114411787A (en) * 2022-02-10 2022-04-29 中铁广州工程局集团有限公司 Well point dewatering method for steel cofferdam in water
CN114411787B (en) * 2022-02-10 2022-12-02 中铁广州工程局集团有限公司 Well point dewatering method for steel cofferdam in water
CN114606930A (en) * 2022-03-29 2022-06-10 中天建设集团有限公司 Assembly type recyclable underground continuous wall and construction method thereof
CN114606930B (en) * 2022-03-29 2024-04-26 中天建设集团有限公司 Assembled recyclable underground diaphragm wall and construction method thereof
CN115110538A (en) * 2022-06-01 2022-09-27 中国一冶集团有限公司 Light well point and steel sleeve box combined dewatering support construction method
CN114908856A (en) * 2022-06-14 2022-08-16 中交(广州)建设有限公司 Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof
CN115182369A (en) * 2022-07-29 2022-10-14 中交(南京)建设有限公司 Dewatering well structure and pile foundation construction method reconstructed by utilizing dewatering well
CN115787693A (en) * 2022-12-07 2023-03-14 兰州理工大学 Water stopping method for water gushing in deep foundation pit under riverside slow-dip interbed
CN116290282A (en) * 2023-04-23 2023-06-23 中铁一局集团市政环保工程有限公司 Construction method for connecting new and old pipelines

Also Published As

Publication number Publication date
CN111350202A (en) 2020-06-30

Similar Documents

Publication Publication Date Title
WO2021196657A1 (en) Novel fabricated anchorage structure serving as both dewatering well and support, and construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN103590425B (en) A kind of Peaty soft soil stratum subway station construction technology
CN109630127B (en) Construction method of ultra-deep shield vertical shaft for water-rich weak stratum
US4146348A (en) Method for executing impermeable construction joints for diaphragm walls
CN108677926A (en) Coercion underground continuous wall and its construction method
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN112253162A (en) Water-rich sand layer large-diameter jacking pipe group entrance and exit reinforcing structure and construction method
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN214194602U (en) Precipitation structure suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN112609720A (en) Precipitation construction method suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN114541408B (en) Front upper part wind-containing well structure of underground station end well and underpass construction method thereof
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN111379273A (en) Construction method of corrugated steel comprehensive pipe gallery
CN111456091B (en) Pressure sewage pipe diversion method
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN110029673B (en) Anchor cable bored pile structure suitable for deep foundation pit support and support method thereof
CN111254914A (en) Anchoring assembly type underground continuous wall assembly structure and construction method
CN105672328B (en) Slip casting ductule resists the H profile steel foundation pit support device of earth lateral pressure
CN219195988U (en) Turnover formula foundation ditch side slope protector with locking protection that takes off
CN218204422U (en) Foundation pit supporting structure of PRC tubular pile and prestressed anchorage cable combination
CN217651830U (en) A precipitation tubular well for subway station foundation ditch

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20929145

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20929145

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 20929145

Country of ref document: EP

Kind code of ref document: A1

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205 DATED 03.07.2023)

122 Ep: pct application non-entry in european phase

Ref document number: 20929145

Country of ref document: EP

Kind code of ref document: A1