CN114908856A - Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof - Google Patents
Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof Download PDFInfo
- Publication number
- CN114908856A CN114908856A CN202210670310.9A CN202210670310A CN114908856A CN 114908856 A CN114908856 A CN 114908856A CN 202210670310 A CN202210670310 A CN 202210670310A CN 114908856 A CN114908856 A CN 114908856A
- Authority
- CN
- China
- Prior art keywords
- well
- wall
- construction
- auxiliary
- attached
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 75
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 44
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 26
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 20
- 239000010959 steel Substances 0.000 claims abstract description 20
- 238000012360 testing method Methods 0.000 claims abstract description 7
- 238000009412 basement excavation Methods 0.000 claims abstract description 5
- 238000005553 drilling Methods 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 8
- 230000009194 climbing Effects 0.000 claims description 2
- 238000004891 communication Methods 0.000 claims description 2
- 238000001514 detection method Methods 0.000 claims 1
- 235000020681 well water Nutrition 0.000 claims 1
- 239000002349 well water Substances 0.000 claims 1
- 230000009189 diving Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 239000010865 sewage Substances 0.000 description 2
- 238000011144 upstream manufacturing Methods 0.000 description 2
- 230000000903 blocking effect Effects 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/04—Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Water Supply & Treatment (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Public Health (AREA)
- Hydrology & Water Resources (AREA)
- Health & Medical Sciences (AREA)
- Earth Drilling (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
本发明公开了一种新建管道与现状井室接驳的附井结构及其施工方法,包括以下步骤:施工附井基坑支护结构,根据开挖深度采取放坡或钢板桩支护结构;在现状钢筋混凝土井室待接驳侧面施工附井;根据给排水设计确定的接驳点位置;采用水磨钻分层钻进开孔,最后剩余40‑60mm壁厚待所有施工完成后通水前一次性水下破除;完成所有管道、井室施工及试验检测工作,具备通水条件;向附井内灌水,直至水位与现状钢筋混凝土井室水位一致;潜水员水下破除剩余壁厚部分实现新建管道与现状钢筋混凝土井室的连通。大部分接通工作在附井内干作业条件下进行,极大改善了施工作业条件,施工操作简便和施工安全,施工周期短,施工成本低。
The invention discloses an attached well structure for connecting a new pipeline with an existing well room and a construction method thereof, comprising the following steps: constructing a foundation pit supporting structure attached to the well, and adopting a grading or steel sheet pile supporting structure according to the excavation depth; The attached well is constructed on the side of the existing reinforced concrete well room to be connected; the connection point position is determined according to the water supply and drainage design; the water mill drill is used to drill the opening in layers, and the remaining wall thickness of 40-60mm is to be completed after all construction is completed. Complete the construction and testing of all pipelines and wells, and meet the conditions for water passage; pour water into the attached well until the water level is consistent with the current level of reinforced concrete wells; divers underwater remove the remaining wall thickness to realize the new pipeline and The connection of the existing reinforced concrete well room. Most of the connection work is carried out under dry operation conditions in the attached well, which greatly improves the construction operation conditions, and the construction operation is simple and safe, the construction period is short, and the construction cost is low.
Description
技术领域technical field
本发明涉及市政排水施工技术领域,尤其是涉及一种新建管道与现状井室接驳的附井结构及其施工方法。The invention relates to the technical field of municipal drainage construction, in particular to an attached well structure for connecting a new pipeline with an existing well room and a construction method thereof.
背景技术Background technique
在城市排水管道施工过程中普遍存在新建管道与现状钢筋混凝土井室(含暗渠)接驳的情况,现状钢筋混凝土井室(含暗渠)复杂多样,且位于地下,情况难以探明,这给新建管道与现状钢筋混凝土井室(含暗渠)接驳带来了很大的挑战。During the construction of urban drainage pipelines, it is common for new pipelines to be connected to the existing reinforced concrete wells (including culverts). The connection between the pipeline and the existing reinforced concrete well room (including underdrain) brings great challenges.
目前新建管道与现状钢筋混凝土井室(含暗渠)接驳施工工艺主要有:(1)现状钢筋混凝土井室(含暗渠)上下游进行气囊或砌墙封堵后人工下井凿除;(2)通水条件下潜水员下井水下凿除,如中国专利CN202010053573.6公开的新建污水管与既有污水管接驳施工方法;(3)通水条件下采用水下绳锯切割吊出井室,如中国专利CN201821950675.2公开的大直径地下钢筋混凝土给排水管不停水接驳装置;以上方法具有封堵导流工程量大,对现状排水系统影响大,水下作业时间长,安全风险高等特点。At present, the connection construction technology of the new pipeline and the existing reinforced concrete well room (including the underdrain) mainly includes: (1) the upstream and downstream of the existing reinforced concrete well room (including the underdrain) are artificially cut down after the airbag or wall is blocked; (2) Under water conditions, divers go down the well and dig out underwater, such as the construction method for connecting new sewage pipes and existing sewage pipes disclosed in Chinese patent CN202010053573.6; Chinese patent CN201821950675.2 discloses a large-diameter underground reinforced concrete water supply and drainage pipe non-stop connection device; the above method has the characteristics of large amount of blocking and diversion works, large impact on the existing drainage system, long underwater operation time, and high safety risk. .
发明内容SUMMARY OF THE INVENTION
针对现有技术不足,本发明是提供一种新建管道与现状井室接驳的附井结构及其施工方法,以达到施工操作简便和施工安全的目的。Aiming at the deficiencies of the prior art, the present invention provides a well-attached structure for connecting a new pipeline with an existing well room and a construction method thereof, so as to achieve the purpose of simple and safe construction operation.
为了解决上述技术问题,本发明所采用的技术方案为:In order to solve the above-mentioned technical problems, the technical scheme adopted in the present invention is:
一种新建管道与现状井室接驳的附井结构,所述附井结构设置在新建管道和现状井室之间,所述附井结构包括附井基础和附井井壁以及附井盖板,所述附井井壁设在附井基础上,附井盖板设在附井井壁的顶部,附井井壁的一侧与现状井室的现状井壁相连,现状井壁上设有用于连通现状井室和附井的开孔,附井井壁的另一侧与新建管道的端部相连。An attached well structure for connecting a new pipeline and an existing well room, the attached well structure is arranged between the newly built pipeline and the existing well room, and the attached well structure comprises an attached well foundation, an attached well wall and an attached well cover, The wall of the attached well is arranged on the foundation of the attached well, and the cover plate of the attached well is arranged on the top of the wall of the attached well. The openings of the existing well chamber and the attached well, and the other side of the wall of the attached well is connected to the end of the new pipeline.
所述附井基础上设有附井垫层,附井井壁设在附井垫层上。The attached well foundation is provided with an attached well cushion, and the attached well wall is arranged on the attached well cushion.
所述附井盖板上设有附井井筒,附井井筒的顶部设有与地面相平齐的附井井盖。The attached well cover is provided with an attached wellbore, and the top of the attached wellbore is provided with an attached wellbore that is flush with the ground.
所述现状井壁上设有与附井井壁相连的植筋。The existing well wall is provided with a planting bar which is connected with the attached well wall.
所述附井井壁为一侧开口的方形井壁结构。The wall of the attached well is a square wall structure with one side open.
所述附井井壁和附井井筒的内壁上设有上下对应的爬梯。Up and down corresponding climbing ladders are arranged on the wall of the attached well and the inner wall of the attached wellbore.
一种新建管道与现状井室接驳的附井结构的施工方法,包括以下步骤:A construction method of a well-attached structure for connecting a new pipeline with an existing well room, comprising the following steps:
步骤一:施工附井基坑支护结构,根据开挖深度采取放坡或钢板桩支护结构;Step 1: Build the supporting structure of the foundation pit attached to the well, and adopt the grading or steel sheet pile supporting structure according to the excavation depth;
步骤二:在现状钢筋混凝土井室待接驳侧面施工附井;Step 2: Construction of the attached well on the side of the existing reinforced concrete well room to be connected;
步骤三:根据给排水设计确定的接驳点位置;Step 3: The location of the connection point determined according to the water supply and drainage design;
步骤四:采用水磨钻分层钻进开孔,最后剩余40-60mm壁厚待所有施工完成后通水前一次性水下破除;Step 4: Use a water mill drill to drill into the opening in layers, and finally the remaining 40-60mm wall thickness is to be broken underwater at one time before the water is passed after all constructions are completed;
步骤五:完成所有管道、井室施工及试验检测工作,具备通水条件;Step 5: Complete all pipelines, well room construction and testing and testing, and have water supply conditions;
步骤六:向附井内灌水,直至水位与现状钢筋混凝土井室水位一致;Step 6: Fill the attached well with water until the water level is consistent with the current water level in the reinforced concrete well;
步骤七:潜水员水下破除剩余壁厚部分实现新建管道与现状钢筋混凝土井室的连通。Step 7: Divers break the remaining wall thickness underwater to realize the connection between the new pipeline and the existing reinforced concrete well room.
所述支护结构包括钢板桩和牛腿以及围檩,所述围檩通过牛腿设在钢板桩的内侧,并在钢板桩的顶部设有安全栏杆。The supporting structure includes steel sheet piles, corbels and purlins, the purlins are arranged on the inner side of the steel sheet piles through the corbels, and a safety rail is provided on the top of the steel sheet piles.
本发明与现有技术相比,具有以下优点:Compared with the prior art, the present invention has the following advantages:
该新建管道与现状井室接驳的附井结构及其施工方法设计合理,大部分接通工作在附井内干作业条件下进行,极大改善了施工作业条件,确保了施工作业人员的生命安全,施工质量可见可控,施工操作简便和施工安全,施工周期短,施工成本低。The attached well structure and construction method for the connection between the new pipeline and the existing well room are reasonably designed. Most of the connection work is carried out under dry working conditions in the attached well, which greatly improves the construction operation conditions and ensures the safety of construction workers. , the construction quality is visible and controllable, the construction operation is simple and safe, the construction period is short, and the construction cost is low.
附图说明Description of drawings
下面对本说明书各幅附图所表达的内容及图中的标记作简要说明:Below is a brief description of the content expressed in each of the drawings in this specification and the symbols in the drawings:
图1为本发明附井结构平面示意图。FIG. 1 is a schematic plan view of the structure of the attached well according to the present invention.
图2为沿图1中A-A剖视示意图。FIG. 2 is a schematic cross-sectional view along A-A in FIG. 1 .
图3为沿图1中B-B剖视示意图。FIG. 3 is a schematic cross-sectional view along B-B in FIG. 1 .
图4为本发明开孔放大示意图。FIG. 4 is an enlarged schematic view of the opening of the present invention.
图中:In the picture:
1-附井垫层、2-附井基础、3-附井井壁、4-附井盖板、5-附井井筒、6-附井井盖、7-新建管道、8-现状井壁、9-开孔、10-植筋、11-钢板桩、12-牛腿、13-围檩、14-角撑、15-安全栏杆、16-爬梯、17-流槽。1-Attached well cushion, 2-Attached well foundation, 3-Attached well wall, 4-Attached well cover, 5-Attached well bore, 6-Attached well cover, 7-New pipeline, 8-Existing well wall, 9 - Opening, 10-planting reinforcement, 11-steel sheet pile, 12-corbel, 13-purlin, 14-gusset, 15-safety railing, 16-climbing ladder, 17-runner.
具体实施方式Detailed ways
下面对照附图,通过对实施例的描述,对本发明的具体实施方式作进一步详细的说明。The specific embodiments of the present invention will be described in further detail below through the description of the embodiments with reference to the accompanying drawings.
如图1至图4所示,该新建管道与现状井室接驳的附井结构设置在新建管道和现状井室之间;其附井结构包括附井基础2和附井井壁3以及附井盖板4,附井井壁设在附井基础上,附井盖板设在附井井壁的顶部,附井井壁的一侧与现状井室的现状井壁8相连,现状井壁上设有用于连通现状井室和附井的开孔9,附井井壁的另一侧与新建管道7的端部相连。As shown in Figures 1 to 4, the attached well structure connecting the new pipeline and the existing well room is set between the new pipeline and the existing well room; the attached well structure includes the attached well foundation 2, the attached well wall 3 and the attached well The well cover 4, the wall of the attached well is set on the foundation of the attached well, the cover of the attached well is set on the top of the wall of the attached well, one side of the wall of the attached well is connected to the existing
附井井壁3为一侧开口的方形井壁结构,附井基础上设有附井垫层1,附井井壁设在附井垫层上。The shaft wall 3 of the attached well is a square shaft wall structure with one side opening, and a cushion layer 1 is provided on the foundation of the attached well, and the wall of the attached well is arranged on the cushion layer of the attached well.
附井盖板上设有附井井筒5,附井井筒的顶部设有与地面相平齐的附井井盖6,降低成本,施工简便;并在附井井壁和附井井筒的内壁上设有上下对应的爬梯,便于施工。The attached well cover is provided with an attached well 5, and the top of the attached well is provided with an attached
本发明新建管道与现状井室接驳的附井结构的施工方法,包括以下步骤:The construction method of the attached well structure for connecting the new pipeline and the existing well room of the present invention comprises the following steps:
步骤一:施工附井基坑支护结构,根据开挖深度采取放坡或钢板桩支护结构;Step 1: Build the supporting structure of the foundation pit attached to the well, and adopt the grading or steel sheet pile supporting structure according to the excavation depth;
步骤二:在现状钢筋混凝土井室待接驳侧面施工附井;Step 2: Construction of the attached well on the side of the existing reinforced concrete well room to be connected;
步骤三:根据给排水设计确定的接驳点位置;Step 3: The location of the connection point determined according to the water supply and drainage design;
步骤四:采用水磨钻分层钻进开孔,最后剩余40-60mm壁厚待所有施工完成后通水前一次性水下破除;Step 4: Use a water mill drill to drill into the opening in layers, and finally the remaining 40-60mm wall thickness is to be broken underwater at one time before the water is passed after all constructions are completed;
步骤五:完成所有管道、井室施工及试验检测工作,具备通水条件;Step 5: Complete all pipelines, well room construction and testing and testing, and have water supply conditions;
步骤六:向附井内灌水,直至水位与现状钢筋混凝土井室水位一致;Step 6: Fill the attached well with water until the water level is consistent with the current water level in the reinforced concrete well;
步骤七:潜水员水下破除剩余壁厚部分实现新建管道与现状钢筋混凝土井室的连通。Step 7: Divers break the remaining wall thickness underwater to realize the connection between the new pipeline and the existing reinforced concrete well room.
所述支护结构包括钢板桩11和牛腿12以及围檩13,围檩通过牛腿设在钢板桩的内侧,并在钢板桩的顶部设有安全栏杆15;并在拐角处设有角撑14,结构稳定可靠。The supporting structure includes steel sheet piles 11, corbels 12 and
本发明大部分接通工作在附井内干作业条件下进行,极大改善了施工作业条件,确保了施工作业人员的生命安全,施工质量可见可控,施工操作简便和施工安全,施工周期短,施工成本低。Most of the connection work of the invention is carried out under dry operation conditions in the attached well, which greatly improves the construction operation conditions, ensures the life safety of construction workers, the construction quality is visible and controllable, the construction operation is simple and safe, and the construction period is short. Construction cost is low.
优选具体实例为:Preferred specific examples are:
现状钢筋混凝土井室旁实施接驳用U形附井,U形附井尺寸根据接驳过水断面和施工空间需要合理确定,U形附井与现状钢筋混凝土井室接触面应植筋凿毛确保接缝严密防止漏水。在U形附井内进行现状钢筋混凝土井室(含暗渠)接通操作,采用水磨钻分层对现状井壁进行取孔破除,直至剩余50mm待所有施工完成具备通水条件时一次性凿除,以上施工均在干施工条件下进行,现状钢筋混凝土井室维持正常运行。接着进行附井顶板及地面恢复施工及相应试验检测,上下游管道施工完成具备通水条件后,向附井及起连通的下游管道内注水,直至水位与现状钢筋混凝土井室内水位一致,由潜水员潜水进入附井凿出剩余50mm厚现状井壁,完成新建管道与现状钢筋混凝土井室通水。A U-shaped attached well for connection is implemented next to the existing reinforced concrete well. The size of the U-shaped attached well is reasonably determined according to the cross-section of the connection and the construction space. The contact surface between the U-shaped attached well and the existing reinforced concrete well should be planted with reinforcing bars. Make sure the seams are tight to prevent leaks. In the U-shaped attached well, the current reinforced concrete well room (including the underdrain) is connected, and the existing well wall is drilled by using a water mill in layers, until the remaining 50mm is drilled at one time when all the construction is completed and the water supply conditions are met. The above construction is carried out under dry construction conditions, and the current reinforced concrete well room maintains normal operation. Then carry out the recovery construction of the attached well roof and ground and the corresponding test and inspection. After the upstream and downstream pipelines are completed and the water supply conditions are met, water is injected into the attached well and the connected downstream pipelines until the water level is consistent with the existing indoor water level of the reinforced concrete well. Diving into the attached well to excavate the remaining 50mm thick existing well wall, and complete the water connection between the new pipeline and the existing reinforced concrete well room.
该方案新建附井作为开孔作业面的支护结构也是通水使用状态的永久结构,较常规施工减少了临时支护使用时间和基坑暴露时间,降低了安全风险。现状井壁开孔在附井内干作业条件下进行,采用水磨钻取孔破除工艺,破除断面可见可控,可有效保证施工质量和安全。最终50mm厚井壁破除采用潜水员水下一次性破除通水,较常规施工大大减少了导排水工程量或减少了潜水员水下作业时间,有效保证施工安全。最终50mm破除前各道工序可与其他管井同步施工,该附井及接通施工占用关键工期的时间仅为最终50mm破除的时间,可有效缩短工期,降低成本。In this scheme, the support structure of the newly built attached well as the open-hole working surface is also a permanent structure in the state of water-passing use, which reduces the use time of temporary support and the exposure time of foundation pit compared with conventional construction, and reduces the safety risk. The current wellbore drilling is carried out under dry working conditions in the attached well, and the water mill drilling hole breaking technology is adopted, and the breaking section can be seen and controllable, which can effectively ensure the construction quality and safety. The final 50mm-thick well wall is broken by a diver underwater to break through the water at one time, which greatly reduces the amount of diversion and drainage works or reduces the underwater operation time of the diver compared with conventional construction, effectively ensuring construction safety. Each process before the final 50mm break can be constructed simultaneously with other tube wells. The additional well and connection construction takes up only the critical construction period of the final 50mm break, which can effectively shorten the construction period and reduce costs.
如图2所示,附井结构包括附井垫层、附井基础、附井井壁、附井盖板、附井井筒以及附井井盖;首先按设计及规范要求依次施工基坑支护结构、附井垫层1、附井基础2以及附井井壁3。本实施例中基坑开挖深度为3米,钢板桩采用长度为9米的拉森Ⅳ型钢板桩,围檩13及角撑14采用型钢,牛腿采用钢板焊接在钢板桩上,间距为80cm;附井垫层1采用厚度为100mmC15混凝土,平面尺寸为2300mm×2300mm;附井基础2采用厚度为300mmC30钢筋混凝土,平面尺寸为2200mm×2200mm;附井井壁3采用厚度为250mmC30钢筋混凝土,净空尺寸为1500mm×1500mm;施工附井井壁3时,附井井壁3与现状井壁8之间接触面需进行凿毛处理,并在现状井壁上植筋,如图1所示,植筋采用钢筋,间距为200mm,植筋深度250mm,外露250mm。As shown in Figure 2, the attached well structure includes attached well cushion, attached well foundation, attached well shaft wall, attached well cover, attached well bore and attached well cover; first, the foundation pit supporting structure, Attached well cushion 1, attached well foundation 2 and attached well wall 3. In this example, the excavation depth of the foundation pit is 3 meters, the steel sheet piles are Larsen IV steel sheet piles with a length of 9 meters, the
如图3所示,新建管道与现状钢筋混凝土井室(含暗渠)接驳施工流程包括:施工基坑支护结构及附井井壁3(含植筋及接缝密封处理),附井施工完成后回填并拆除基坑支护结构;水磨钻破除第一层现状井壁;水磨钻破除第二层现状井壁;步骤四:施工爬梯16、流槽17、附井盖板4、附井井筒5及附井井盖6;附井井壁3及新建管道7内注水平压;潜水员水下破除剩余50mm厚现状井壁。As shown in Figure 3, the construction process for the connection between the new pipeline and the existing reinforced concrete well room (including the underdrain) includes: construction of the foundation pit supporting structure and the wall 3 of the attached well (including planting bars and joint sealing treatment), and the construction of the attached well. After completion, backfill and dismantle the foundation pit support structure; water mill drill to remove the existing well wall of the first layer; water mill drill to remove the existing well wall of the second layer; step 4:
水磨钻取芯破除,水磨钻通过膨胀螺丝固定在现状井壁上,为水磨钻钻进提供固定基座和反力。水磨钻钻进深度应严格控制,确保钻进深度一致,破除断面平整,防止钻进过深钻通井壁引起透水事故。作业人员井下作业时,应设专人监视,并在井上准备好应急救援物资和设备,一旦发生突发事故,立即进行救援。The water mill core is broken, and the water mill is fixed on the existing well wall by expansion screws, providing a fixed base and reaction force for the water mill drilling. The drilling depth of the water mill drill should be strictly controlled to ensure that the drilling depth is consistent, the broken section is flat, and the drilling is too deep to prevent water penetration accidents caused by drilling through the well wall. When operators are working underground, special personnel should be set up to monitor them, and emergency rescue materials and equipment should be prepared on the well. In the event of an emergency, rescue immediately.
潜水员水下破除剩余50mm厚现状井壁时,采用水下风镐进行,应选派有经验的专业潜水人员,潜水员下井前应进行安全技术交底,检查潜水装备完好,功能正常。潜水员下井应佩带安全绳、长管呼吸机、通信线缆及话筒,潜水作业严格遵守安全操作规程。When divers break the remaining 50mm thick existing well wall underwater, they should use underwater air picks. Experienced professional divers should be selected. Divers should conduct safety technical disclosure before going down the well, and check that the diving equipment is in good condition and functioning properly. Divers should wear safety ropes, long-tube ventilators, communication cables and microphones when going down the well, and strictly abide by the safety operation rules during diving operations.
本发明具有以下优点:1、施工干作业,最大限度减少水下作业时间:大部分接通工作在附井内干作业条件下进行,极大改善了施工作业条件,最大限度减少了水下作业时间,确保了施工作业人员的生命安全;2、施工质量可见可控:由于干作业施工,整个施工过程可在现场技术质量管理人员的监视下进行,更有利于接驳开孔施工质量的控制,从而提高施工质量;3、施工安全更有保障:由于干作业施工,整个施工过程可在现场安全管理人员的监视下进行,更有利于接驳开孔施工安全的管理,从而有效确保施工安全;4、施工周期短,施工成本低:附井、最终50mm破除前的现状井壁水磨钻取孔破除与管道同时施工,可缩短工期,降低施工成本。The present invention has the following advantages: 1. The construction is dry, and the underwater operation time is minimized: most of the connection work is carried out under the dry operation condition in the attached well, which greatly improves the construction operation conditions and minimizes the underwater operation time. , to ensure the life safety of construction workers; 2. The construction quality is visible and controllable: due to the dry construction, the entire construction process can be carried out under the supervision of the on-site technical quality management personnel, which is more conducive to the control of the construction quality of the connection and opening. Thereby improving the construction quality; 3. Construction safety is more guaranteed: due to dry construction, the entire construction process can be carried out under the supervision of on-site safety management personnel, which is more conducive to the management of connection and opening construction safety, thus effectively ensuring construction safety; 4. The construction period is short and the construction cost is low: the existing well wall water mill drilling hole before the final 50mm is broken and the pipeline is constructed at the same time, which can shorten the construction period and reduce the construction cost.
上述仅为对本发明较佳的实施例说明,上述技术特征可以任意组合形成多个本发明的实施例方案。The above description is only for the description of the preferred embodiments of the present invention, and the above technical features can be combined arbitrarily to form a plurality of embodiments of the present invention.
上面结合附图对本发明进行了示例性描述,显然本发明具体实现并不受上述方式的限制,只要采用了本发明的构思和技术方案进行的各种非实质性的改进,或未经改进将本发明的构思和技术方案直接应用于其它场合的,均在本发明的保护范围之内。The present invention has been exemplarily described above in conjunction with the accompanying drawings. Obviously, the specific implementation of the present invention is not limited by the above manner, as long as various insubstantial improvements made by the concept and technical solutions of the present invention are adopted, or the If the concept and technical solutions of the present invention are directly applied to other occasions, they all fall within the protection scope of the present invention.
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210670310.9A CN114908856A (en) | 2022-06-14 | 2022-06-14 | Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210670310.9A CN114908856A (en) | 2022-06-14 | 2022-06-14 | Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114908856A true CN114908856A (en) | 2022-08-16 |
Family
ID=82770626
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210670310.9A Pending CN114908856A (en) | 2022-06-14 | 2022-06-14 | Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114908856A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150345523A1 (en) * | 2014-06-02 | 2015-12-03 | Momentum Environmental, LLC | Energy dissipator and associated system for use in sumped flow-through manholes |
CN107859145A (en) * | 2017-11-17 | 2018-03-30 | 广州市自来水工程公司 | A kind of drainpipe is plugged into construction method under water |
CN109208737A (en) * | 2018-10-09 | 2019-01-15 | 中铁十局集团城市轨道工程有限公司 | A kind of down-stream pipeline changes move in new pipe is plugged into and former pipe blocks construction method |
CN209339279U (en) * | 2018-08-17 | 2019-09-03 | 中国中元国际工程有限公司 | A kind of hydraulic drop inspection shaft |
CN111236387A (en) * | 2020-01-17 | 2020-06-05 | 中铁十二局集团有限公司 | Construction method for connecting newly-built sewage pipe with existing sewage pipe |
WO2021196657A1 (en) * | 2020-04-03 | 2021-10-07 | 山东大学 | Novel fabricated anchorage structure serving as both dewatering well and support, and construction method |
CN215926053U (en) * | 2021-04-26 | 2022-03-01 | 广西建工第一建筑工程集团有限公司 | In-situ water-supply-and-drainage pipe added connection well device without stopping water |
-
2022
- 2022-06-14 CN CN202210670310.9A patent/CN114908856A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150345523A1 (en) * | 2014-06-02 | 2015-12-03 | Momentum Environmental, LLC | Energy dissipator and associated system for use in sumped flow-through manholes |
CN107859145A (en) * | 2017-11-17 | 2018-03-30 | 广州市自来水工程公司 | A kind of drainpipe is plugged into construction method under water |
CN209339279U (en) * | 2018-08-17 | 2019-09-03 | 中国中元国际工程有限公司 | A kind of hydraulic drop inspection shaft |
CN109208737A (en) * | 2018-10-09 | 2019-01-15 | 中铁十局集团城市轨道工程有限公司 | A kind of down-stream pipeline changes move in new pipe is plugged into and former pipe blocks construction method |
CN111236387A (en) * | 2020-01-17 | 2020-06-05 | 中铁十二局集团有限公司 | Construction method for connecting newly-built sewage pipe with existing sewage pipe |
WO2021196657A1 (en) * | 2020-04-03 | 2021-10-07 | 山东大学 | Novel fabricated anchorage structure serving as both dewatering well and support, and construction method |
CN215926053U (en) * | 2021-04-26 | 2022-03-01 | 广西建工第一建筑工程集团有限公司 | In-situ water-supply-and-drainage pipe added connection well device without stopping water |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021109144A1 (en) | Modular intelligent dado cast-in-place pile and construction process therefor | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN113202173B (en) | Construction method for temporarily replacing cross-foundation-pit concrete pipe with steel pipe in deep foundation pit construction | |
CN112727466A (en) | Construction method for support-free prefabricated assembled type shield tunnel air shaft structure | |
CN110700280B (en) | A diversion device and construction method for foundation pit support construction in narrow areas | |
CN114150749A (en) | A construction method for connecting old and new sewage wells without stopping | |
CN112942441B (en) | Pre-grouting water-stopping construction method for water-rich powder sand stratum | |
CN103215922A (en) | High-pressure high-flow centralized leakage grouting leaking stoppage method | |
CN215105880U (en) | Concrete inverted well suitable for connecting new and old water supply and drainage pipelines | |
CN114908856A (en) | Auxiliary well structure for connecting newly-built pipeline with existing well chamber and construction method thereof | |
CN207080242U (en) | Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel | |
CN110792085A (en) | Pipe-jacking working pit supporting method | |
CN113266362B (en) | A construction method of pipe jacking and cover excavation crossing existing dense anchor cable area | |
CN113914909A (en) | A kind of emergency rescue and blocking structure of tunnel water inrush point and its construction method | |
CN115821961A (en) | Construction method of omnibearing high-pressure rotary spraying deep confined water-stop curtain | |
CN220748266U (en) | Underpass structure of unreserved interface existing operation station | |
CN114439024A (en) | A kind of steel pipe curtain auxiliary pile foundation hole forming construction technology | |
CN215053282U (en) | Pre-grouting water stop structure of water-rich silt stratum suitable for connection construction of underground building | |
CN113175350B (en) | A construction method for wastewater pumping station in water-rich sand layer | |
CN117108303A (en) | Unreserved interface existing operation station downward penetrating structure and construction method | |
CN116220733B (en) | Internal anchoring combined protection technology for lower existing tunnel under top unloading | |
CN114991811B (en) | Structural design and water-proof and drainage method for karst tunnel to pass through underground river section | |
CN119041920B (en) | A tunnel communication channel construction method | |
CN117702791B (en) | Water shutoff system of foundation pit interface of river-crossing tunnel and construction method | |
JP3248656U (en) | Shield excavation passage structure for subway entrances and exits |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220816 |