WO2021103192A1 - Supporting structure for preventing roadway surrounding rock from transferring heat - Google Patents

Supporting structure for preventing roadway surrounding rock from transferring heat Download PDF

Info

Publication number
WO2021103192A1
WO2021103192A1 PCT/CN2019/125573 CN2019125573W WO2021103192A1 WO 2021103192 A1 WO2021103192 A1 WO 2021103192A1 CN 2019125573 W CN2019125573 W CN 2019125573W WO 2021103192 A1 WO2021103192 A1 WO 2021103192A1
Authority
WO
WIPO (PCT)
Prior art keywords
layer
roadway
polyurethane foam
rigid polyurethane
grid cloth
Prior art date
Application number
PCT/CN2019/125573
Other languages
French (fr)
Chinese (zh)
Inventor
郭忠平
何程乾
张延旭
张福玉
冷超
Original Assignee
山东科技大学
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 山东科技大学 filed Critical 山东科技大学
Publication of WO2021103192A1 publication Critical patent/WO2021103192A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Definitions

  • the utility model relates to the technical field of roadway support, in particular to a support structure that prevents heat transfer from the surrounding rock of the roadway.
  • the cooling of the mine insulation material is an active cooling method by adding low thermal conductivity materials around the roadway to prevent the heat from the surrounding rock of the roadway from being released to the inside of the roadway.
  • the research and application of thermal insulation materials in construction technology and aerospace industry have been very extensive. New thermal insulation materials are used in mines affected by heat damage. By adding thermal insulation materials on the wall of the roadway, the deep heat source of the roadway can be isolated and the surrounding rock can be prevented from radiating heat. Achieve active cooling effect and save cooling cost.
  • the utility model In order to control the deformation of the surrounding rock of the roadway and prevent the heat from the surrounding rock of the roadway from being transferred into the roadway, the utility model provides a supporting structure for preventing the heat transfer of the surrounding rock of the roadway.
  • the specific technical scheme is as follows.
  • a supporting structure for preventing heat transfer to the surrounding rock of a roadway comprising supporting bolts and a shotcrete concrete layer.
  • the supporting bolts are arranged in the roadway, and the bolting and shotcreting concrete layer is arranged close to the surrounding rock of the roadway; it is characterized in that it also includes hard A polyurethane foam layer and a grid cloth mortar layer, the hard polyurethane foam layer is fixed on the anchor shotcrete layer, and the grid cloth mortar layer is arranged on the hard polyurethane foam layer; the cross-sectional shape and the roadway of the anchor shot concrete layer
  • the cross-section shape is the same, the anchor shotcrete layer is a solid structure and the surface is flat, the rigid polyurethane foam layer is evenly and evenly covered on the anchor shotcrete layer, the grid cloth mortar layer includes grid cloth and mortar, and the grid cloth is exposed through the anchor rod
  • the ends are hung on the rigid polyurethane foam layer, and the mortar wraps the grid cloth and is consolidated on the rigid polyurethane foam layer.
  • the thickness of the anchor shotcrete layer is less than 20 mm
  • the thickness of the rigid polyurethane foam layer is greater than 30 mm
  • the thickness of the grid cloth mortar layer is 1.5-3 mm.
  • the cross section of the roadway is rectangular, trapezoidal, semicircular arch, arc arch, oval or circular.
  • barbs are provided on the grid cloth.
  • the beneficial effect of the utility model is that the stability of the overall support structure of the roadway is ensured by the reasonable arrangement of the supporting bolts and the bolt shotcrete layer, the rigid polyurethane foam layer is arranged to prevent the heat transfer of the surrounding rock of the roadway, and the hard High-quality polyurethane foam has the advantages of convenient construction and good heat insulation performance; and considering the deformation of the surrounding rock of the roadway, the installation of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the installation of a grid cloth mortar layer can protect The rigid polyurethane foam layer improves the overall thermal insulation and stability of the structure.
  • Figure 1 is a schematic diagram of the supporting structure to prevent heat transfer to the surrounding rock of the roadway;
  • Figure 2 is a schematic diagram of the grid cloth structure
  • Figure 3 is a schematic diagram of the barb structure
  • Figure 4 is a schematic diagram of the supporting process of the insulated roadway
  • a supporting structure to prevent heat transfer to the surrounding rock of a roadway includes a supporting bolt and a shotcrete concrete layer.
  • a supporting bolt 1 is set on the roadway, and a shotcrete bolt 2 is set close to the surrounding rock of the roadway.
  • the rigid polyurethane foam layer 3 and the grid cloth mortar layer 4, the rigid polyurethane foam layer 3 is fixed on the anchor shotcrete layer 2, and the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3.
  • the thickness of the anchor shotcrete layer 2 is less than 20mm
  • the thickness of the rigid polyurethane foam layer 3 is greater than 30mm
  • the thickness of the grid cloth mortar layer 4 is 1.5-3mm.
  • the cross-sectional shape of the shotcrete layer 2 is the same as that of the roadway, and the shotcrete layer 2 has a solid structure and has a flat surface.
  • the anchor shotcrete layer 2 includes a first concrete layer and a second concrete layer.
  • the first concrete layer is formed by spraying concrete in the roadway.
  • the thickness of the first concrete layer is less than 8cm.
  • the second concrete layer is sprayed.
  • the thickness of the second concrete layer is greater than 10 cm.
  • the rigid polyurethane foam layer is evenly and evenly covered on the anchor shotcrete layer.
  • the grid cloth mortar layer includes grid cloth 9 and mortar. The grid cloth 9 is hung on the rigid polyurethane foam layer through the exposed end of the anchor rod. The wrapping grid cloth is fixed on the rigid polyurethane foam layer.
  • the roadway section can be rectangular, trapezoidal, semi-circular arch, arc arch, ellipse or circle and other irregular shapes.
  • Barbs are provided on the grid cloth, so that it is convenient for the grid cloth to be hung in the place where the anchor distance is large, and the grid cloth mortar layer and the rigid polyurethane foam layer are closely attached to facilitate the spraying of the mortar; the structure of the barb 8 Specifically, a pointed head 5, a connecting rod 6 and a fin plate 7 are provided, 3-4 fin plates 7 are arranged in a cone shape around the pointed head 5, and the rear end of the barb 8 is sleeved and fixed on the mesh cloth 9 in a ring shape.
  • the barb is made of plastic material to reduce costs.
  • the specific construction of the support structure is to spray concrete on the roadway wall for the first time to level the roadway wall; then drill holes and install bolts for support, using high-strength bolts, nuts and pallets. Control the deformation of the surrounding rock and maintain the stability of the rock formation. After the concrete has hardened to a certain extent, spray rigid polyurethane foam using on-site spraying. Use a high-pressure spray gun to spray the mixture on the wall surface, try to ensure that the thickness is uniform, and there should be no thickness less than 30mm. Use a spatula to remove the excessively thick areas, and use rigid polyurethane foam to make up the excessively thin areas.
  • the wind power during construction should not be greater than level 3, and the relative humidity of the air should be less than 70%, which can avoid the problems of environmental pollution caused by foam splashing during spraying and high material waste rate.
  • the rigid polyurethane foam is cooled and cured, it is hung with a grid cloth to spray polymer cement mortar to improve the durability of the material.
  • the rigid polyurethane foam layer is set to prevent the heat transfer of the surrounding rock of the roadway.
  • the rigid polyurethane foam is used for convenient construction and thermal insulation performance. Good advantages. And considering the deformation of the surrounding rock of the roadway, the setting of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the setting of a grid cloth mortar layer can protect the rigid polyurethane foam layer and improve the overall thermal insulation of the structure And stability.
  • the insulated roadway includes the supporting bolt 1, the shotcrete concrete layer 2, the hard polyurethane foam layer 3 and the grid cloth mortar layer 4.
  • the anchor shotcrete layer 2 is set close to the surrounding rock of the roadway, and the 3 layers of hard polyurethane foam are fixed in On the anchor shotcrete layer 2, the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3.
  • the concrete structure includes supporting bolts and shotcrete concrete layer. Support bolts 1 are set in the roadway, and shotcrete concrete layer 2 is set close to the surrounding rock of the roadway. It also includes a rigid polyurethane foam layer 3 and a grid cloth mortar layer 4.
  • the rigid polyurethane foam layer 3 is fixed on the anchor shotcrete layer, and the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3.
  • the thickness of the anchor shotcrete layer 2 is less than 20mm
  • the thickness of the rigid polyurethane foam layer 3 is greater than 30mm
  • the thickness of the grid cloth mortar layer 4 is 1.5-3mm.
  • the cross-sectional shape of the shotcrete layer 2 is the same as that of the roadway, and the shotcrete layer 2 has a solid structure and has a flat surface.
  • the anchor shotcrete layer includes a first concrete layer and a second concrete layer.
  • the first concrete layer is formed by spraying concrete in the roadway.
  • the thickness of the first concrete layer is less than 8cm.
  • the second concrete layer is sprayed.
  • the thickness of the second concrete layer is greater than 10cm.
  • the rigid polyurethane foam layer 3 is evenly and evenly covered on the anchor shotcrete layer.
  • the grid cloth mortar layer 4 includes grid cloth and mortar. The grid cloth is hung on the rigid polyurethane foam layer through the exposed end of the anchor rod.
  • the wrapping mesh cloth is consolidated on the rigid polyurethane foam layer, and the mesh cloth adopts medium alkali or alkali-free glass fiber mesh cloth.
  • the roadway section can be rectangular, trapezoidal, semi-circular arch, arc arch, ellipse or circle and other irregular shapes.
  • Barbs are provided on the grid cloth, so that it is convenient to hang the grid cloth in the place where the anchor distance is large, and to ensure that the grid cloth mortar layer and the rigid polyurethane foam layer are close together to facilitate the spraying of the mortar; the structure of the barb is specific It is provided with a pointed head, a connecting rod and a fin plate, and 3-4 fin plates are arranged in a cone shape around the pointed head. The rear end of the barb is sleeved and fixed on the intersection of the grid cloth in a ring shape. Plastic material production reduces costs.
  • a method for supporting an insulated roadway is disclosed, and the supporting steps include:
  • Step 1 Spray concrete on the wall of the newly excavated roadway to level the wall of the roadway to form the first concrete layer; the thickness of the first concrete layer is less than 8cm.
  • For the newly excavated and formed high-temperature roadway carry out bolt and shotcrete support and level the roadway wall to control the deformation of the surrounding rock and maintain the stability of the rock formation.
  • Step 2 Construct bolt drilling on the flat roadway wall, install bolts, pallets and nuts, support the roadway, and control the deformation of the surrounding rock of the roadway.
  • Anchor cables can also be set to strengthen the support of the roadway.
  • Step 3 Spray the concrete again to form an anchor spray concrete layer.
  • spray hard polyurethane foam to form a hard polyurethane foam layer.
  • the thickness of the second concrete layer formed by spraying concrete again is greater than 10cm
  • the thickness of the first concrete layer and the second concrete layer combined to form the anchor shotcrete layer is less than or equal to 20cm.
  • the spraying of rigid polyurethane foam uses the on-site spraying method. Specifically, the rigid polyurethane foam is sprayed on the surface of the wall with a high-pressure spray gun, and the spraying is repeated to ensure uniform thickness.
  • the wind power in the tunnel during construction is less than 3, and the relative humidity of the air is less than 70%. , It can avoid the problems of easy splashing of foam during spraying to cause environmental pollution and high material waste rate; the thickness of the rigid polyurethane foam layer is greater than 30mm.
  • Step 4 Check whether the rigid polyurethane foam is evenly sprayed.
  • the thickness is greater than or equal to 30cm.
  • the locations where the thickness is greater than 33cm are removed with a shovel.
  • the locations that are too thin and less than 27cm are filled with rigid polyurethane foam.
  • the preparation method of rigid polyurethane foam is to use polyether resin and isocyanic acid as the main raw materials to add into the material mixer at a ratio of 1:1 and mix, and use the carbon dioxide generated in the reaction as the blowing agent. After a period of time, The rigid polyurethane foam can be obtained. It can be sprayed directly on the building interface, and after about 30 minutes of reaction cooling and finalization, it completely adheres to the building interface.
  • Step 5 After the rigid polyurethane foam is cooled and cured, a grid cloth is hung, and then polymer cement mortar is sprayed on the grid cloth, and the cement mortar is solidified to form a grid cloth mortar layer.
  • the thickness of the grid cloth mortar layer is 1.5-3mm.
  • the main components of polymer cement mortar are cement, aggregates and organic polymers that can disperse water. After these proportions are added to the water, they can be used after stirring.
  • the construction process of the insulated roadway support method is convenient and efficient, and cost-saving.
  • the first concrete layer is constructed first to ensure the surface of the surrounding rock of the roadway is smooth, and it is also convenient to set the anchor bolts and cables, which ensures the accurate setting of the bolts and the flatness of the pallets. , Improve the supporting effect; the second concrete spray layer re-spraying ensures the effectiveness of the anchor spray concrete layer, and the sequential spraying of the first spray layer and the second spray layer can improve the construction efficiency, and the anchor spray concrete layer can harden faster ;
  • the construction of the rigid polyurethane foam layer is more convenient, and the price is low, energy saving and environmental protection.
  • the rigid polyurethane foam will not break and damage its thermal insulation performance, and has excellent impact resistance; it is more convenient to hang the grid cloth and the grid cloth mortar Layer layout.
  • the selection of rigid polyurethane foam is obtained through comparison of similar structures.
  • the comparison of rigid polyurethane foam, polystyrene material and polystyrene The composition structure of styrene EPS is combined with the heat transfer characteristics of tunnel support in deep mines.
  • rigid polyurethane foam with a thickness of 25mm can achieve 50% thermal insulation and low cost, making it an ideal thermal insulation material.
  • the construction of the rigid polyurethane foam layer is more convenient, and the price is low, energy saving and environmental protection.
  • the rigid polyurethane foam will not break and damage its thermal insulation performance, and has excellent impact resistance; it is more convenient to hang the grid cloth and the grid cloth mortar Layer layout.
  • Rigid polyurethane foam is one of the materials with the lowest thermal conductivity among all thermal insulation materials.
  • the thermal insulation effect of 50mm thick rigid polyurethane foam is equivalent to 90mm thick mineral wool, 100mm thick cork, 130mm thick fiberboard, and 280mm thick. Wood board or 760mm thick concrete, which allows it to effectively preserve heat and maintain a low temperature environment.
  • Rigid polyurethane foam has high compressive strength and shear strength, and can effectively bond with various widely used surface materials. These materials can increase the inherent strength of rigid polyurethane foam and make it usable as a semi-structural sheet. Rigid polyurethane foam will not rupture and damage its thermal insulation performance, and has excellent impact resistance.
  • the thermal insulation material rigid polyurethane foam can also be used under extreme conditions of -70°C-+130°C, which makes the supporting system have the advantages of anti-aging and moisture resistance, simple construction and mature construction technology as support.
  • Rigid polyurethane foam is green and safe.
  • Rigid polyurethane foam does not contain toxic chemical raw materials, is safe and has no toxic side effects to the human body, and the raw materials can be recycled, low price, energy saving and environmental protection.
  • the supporting bolts and the shotcrete concrete layer are set reasonably to ensure the stability of the overall support structure of the roadway.
  • the rigid polyurethane foam layer is set to prevent the heat transfer of the surrounding rock of the roadway.
  • the rigid polyurethane foam is used for convenient construction and isolation. Advantages of good thermal performance. And considering the deformation of the surrounding rock of the roadway, the setting of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the setting of a grid cloth mortar layer can protect the rigid polyurethane foam layer and improve the overall thermal insulation of the structure And stability.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Disclosed is a supporting structure for preventing roadway surrounding rock from transferring heat, relating to the technical field of roadway supporting. The supporting structure comprises supporting anchor rods (1), an anchoring and shotcreting concrete layer (2), a rigid polyurethane foam layer (3) and a gridding cloth mortar layer (4), wherein the supporting anchor rods (1) are arranged on a roadway, the anchoring and shotcreting concrete layer (2) is tightly attached to roadway surrounding rock, the rigid polyurethane foam layer (3) is arranged on the anchoring and shotcreting concrete layer (2) in a pressing manner, the gridding cloth mortar layer (4) is arranged on the rigid polyurethane foam layer (3), the section shape of the anchoring and shotcreting concrete layer (2) is the same as that of the roadway, the anchoring and shotcreting concrete layer (2) is of a solid structure and is smooth in terms of surface, the rigid polyurethane foam layer (3) evenly and smoothly covers the anchoring and shotcreting concrete layer (2), the gridding cloth mortar layer (4) comprises gridding cloth (9) and mortar, the gridding cloth (9) is hung on the rigid polyurethane foam layer (3) via an exposed end of the anchor rod, and the mortar is wrapped around the gridding cloth (9) and cured on the rigid polyurethane foam layer (3). The supporting structure can control deformation of roadway surrounding rock and also prevent heat of the roadway surrounding rock from being transmitted into the roadway.

Description

一种阻止巷道围岩传热的支护结构Supporting structure for preventing heat transfer in surrounding rock of roadway 技术领域Technical field
本实用新型涉及巷道支护技术领域,尤其是一种阻止巷道围岩传热的支护结构。The utility model relates to the technical field of roadway support, in particular to a support structure that prevents heat transfer from the surrounding rock of the roadway.
背景技术Background technique
随着经济的快速发展,能源需求大量增加,煤炭资源被大量的开采;随着矿井开采深度不断加大,矿井热害问题越来越严重,治理矿井热害影响着许多矿山企业的可持续发展。目前,对矿井热害的处理以加大通风量、制冷降温和制冰降温的被动降温方式为主。矿井隔热材料降温是通过在巷道周围添加低热导率材料,阻止巷道围岩热量向巷道内部释放的一种主动降温方法。隔热材料在建筑技术和航天工业方面的研究和应用已经非常广泛,隔热新材料应用于受热害影响的矿井,通过在巷道壁面附加隔热材料,隔离巷道深度热源、阻止围岩放热,达到主动降温效果,节约降温成本。With the rapid development of the economy, the demand for energy has increased greatly, and coal resources have been exploited in a large amount; with the continuous increase in the depth of mine mining, the problem of mine thermal damage has become more and more serious. The management of mine thermal damage affects the sustainable development of many mining enterprises . At present, the treatment of mine thermal hazards is mainly based on passive cooling methods such as increasing ventilation, cooling and ice making. The cooling of the mine insulation material is an active cooling method by adding low thermal conductivity materials around the roadway to prevent the heat from the surrounding rock of the roadway from being released to the inside of the roadway. The research and application of thermal insulation materials in construction technology and aerospace industry have been very extensive. New thermal insulation materials are used in mines affected by heat damage. By adding thermal insulation materials on the wall of the roadway, the deep heat source of the roadway can be isolated and the surrounding rock can be prevented from radiating heat. Achieve active cooling effect and save cooling cost.
然而由于矿井开采中存在危险性,并且施工不便,需要合理的设置巷道支护结构,通过构建隔热材料层来阻止巷道围岩传热,并且避免影响巷道围岩的支护结构的稳定性,需要对现有的支护结构做进一步的改进。However, due to the dangers in mine mining and the inconvenience of construction, it is necessary to set up a reasonable roadway support structure. By building a layer of thermal insulation material to prevent the heat transfer of the surrounding rock of the roadway, and to avoid affecting the stability of the support structure of the surrounding rock of the roadway. The existing supporting structure needs to be further improved.
发明概述Summary of the invention
技术问题technical problem
问题的解决方案The solution to the problem
技术解决方案Technical solutions
为了控制巷道围岩变形,并且阻止巷道围岩热量向巷道内传递,本实用新型提供了一种阻止巷道围岩传热的支护结构,具体技术方案如下。In order to control the deformation of the surrounding rock of the roadway and prevent the heat from the surrounding rock of the roadway from being transferred into the roadway, the utility model provides a supporting structure for preventing the heat transfer of the surrounding rock of the roadway. The specific technical scheme is as follows.
一种阻止巷道围岩传热的支护结构,包括支护锚杆和锚喷混凝土层,巷道设置支护锚杆,紧贴巷道围岩设置锚喷混凝土层;其特征在于,还包括硬质聚氨酯泡沫层和网格布砂浆层,所述硬质聚氨酯泡沫层固定在锚喷混凝土层上,网格布砂浆层设置在硬质聚氨酯泡沫层上;所述锚喷混凝土层的断面形状和巷道断 面形状相同,锚喷混凝土层为实心结构并且表面平整,硬质聚氨酯泡沫层均匀平整的覆盖在锚喷混凝土层上,网格布砂浆层包括网格布和砂浆,网格布通过锚杆外露端挂设在硬质聚氨酯泡沫层上,砂浆包裹网格布固结在硬质聚氨酯泡沫层上。A supporting structure for preventing heat transfer to the surrounding rock of a roadway, comprising supporting bolts and a shotcrete concrete layer. The supporting bolts are arranged in the roadway, and the bolting and shotcreting concrete layer is arranged close to the surrounding rock of the roadway; it is characterized in that it also includes hard A polyurethane foam layer and a grid cloth mortar layer, the hard polyurethane foam layer is fixed on the anchor shotcrete layer, and the grid cloth mortar layer is arranged on the hard polyurethane foam layer; the cross-sectional shape and the roadway of the anchor shot concrete layer The cross-section shape is the same, the anchor shotcrete layer is a solid structure and the surface is flat, the rigid polyurethane foam layer is evenly and evenly covered on the anchor shotcrete layer, the grid cloth mortar layer includes grid cloth and mortar, and the grid cloth is exposed through the anchor rod The ends are hung on the rigid polyurethane foam layer, and the mortar wraps the grid cloth and is consolidated on the rigid polyurethane foam layer.
优选的是,锚喷混凝土层厚度小于20mm,所述硬质聚氨酯泡沫层厚度大于30mm,所述网格布砂浆层厚度为1.5-3mm。Preferably, the thickness of the anchor shotcrete layer is less than 20 mm, the thickness of the rigid polyurethane foam layer is greater than 30 mm, and the thickness of the grid cloth mortar layer is 1.5-3 mm.
优选的是,巷道断面呈矩形、梯形、半圆拱形、圆弧拱形、椭圆形或圆形。Preferably, the cross section of the roadway is rectangular, trapezoidal, semicircular arch, arc arch, oval or circular.
优选的是,网格布上设置有钩刺。Preferably, barbs are provided on the grid cloth.
发明的有益效果The beneficial effects of the invention
有益效果Beneficial effect
本实用新型的有益效果是,通过合理的设置支护锚杆和锚喷混凝土层,保证了巷道整体支护结构的稳定性,设置硬质聚氨酯泡沫层来阻止巷道围岩热传递,利用了硬质聚氨酯泡沫施工方便,隔热性能好的优点;并且考虑到巷道围岩的变形情况,设置硬质聚氨酯泡沫层可以保证支护结构的抗剪、抗压性能;设置网格布砂浆层可以保护硬质聚氨酯泡沫层并提升结构整体的隔热性和稳定性。The beneficial effect of the utility model is that the stability of the overall support structure of the roadway is ensured by the reasonable arrangement of the supporting bolts and the bolt shotcrete layer, the rigid polyurethane foam layer is arranged to prevent the heat transfer of the surrounding rock of the roadway, and the hard High-quality polyurethane foam has the advantages of convenient construction and good heat insulation performance; and considering the deformation of the surrounding rock of the roadway, the installation of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the installation of a grid cloth mortar layer can protect The rigid polyurethane foam layer improves the overall thermal insulation and stability of the structure.
对附图的简要说明Brief description of the drawings
附图说明Description of the drawings
图1是阻止巷道围岩传热的支护结构示意图;Figure 1 is a schematic diagram of the supporting structure to prevent heat transfer to the surrounding rock of the roadway;
图2是网格布结构示意图;Figure 2 is a schematic diagram of the grid cloth structure;
图3是钩刺结构示意图;Figure 3 is a schematic diagram of the barb structure;
图4是隔热巷道支护流程示意图;Figure 4 is a schematic diagram of the supporting process of the insulated roadway;
图中:1-支护锚杆;2-锚喷混凝土层;3-硬质聚氨酯泡沫层;4-网格布砂浆层;5-尖头;6-连杆;7-翅板;8-钩刺;9-网格布。In the picture: 1- supporting anchor rod; 2- anchor shotcrete layer; 3- rigid polyurethane foam layer; 4- mesh cloth mortar layer; 5- pointed end; 6-connecting rod; 7- fin plate; 8- Barb; 9-grid.
发明实施例Invention embodiment
本发明的实施方式Embodiments of the present invention
结合图1至图4所示,本实用新型提供的一种阻止巷道围岩传热的支护结构具体实施方式如下。With reference to Figures 1 to 4, the specific implementation of a supporting structure for preventing heat transfer from surrounding rocks of a roadway provided by the present invention is as follows.
实施例1Example 1
一种阻止巷道围岩传热的支护结构,具体的结构包括支护锚杆和锚喷混凝土层,巷道设置支护锚杆1,紧贴巷道围岩设置锚喷混凝土层2,还包括硬质聚氨酯泡沫层3和网格布砂浆层4,硬质聚氨酯泡沫层3固定在锚喷混凝土层2上,网格布砂浆层4设置在硬质聚氨酯泡沫层3上。其中,锚喷混凝土层2厚度小于20mm,硬质聚氨酯泡沫层3厚度大于30mm,网格布砂浆层4厚度为1.5-3mm。A supporting structure to prevent heat transfer to the surrounding rock of a roadway. The specific structure includes a supporting bolt and a shotcrete concrete layer. A supporting bolt 1 is set on the roadway, and a shotcrete bolt 2 is set close to the surrounding rock of the roadway. The rigid polyurethane foam layer 3 and the grid cloth mortar layer 4, the rigid polyurethane foam layer 3 is fixed on the anchor shotcrete layer 2, and the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3. Among them, the thickness of the anchor shotcrete layer 2 is less than 20mm, the thickness of the rigid polyurethane foam layer 3 is greater than 30mm, and the thickness of the grid cloth mortar layer 4 is 1.5-3mm.
锚喷混凝土层2的断面形状和巷道断面形状相同,锚喷混凝土层2为实心结构并且表面平整。其中锚喷混凝土层2包括第一混凝土层和第二混凝土层,先在巷道内喷射混凝土形成第一混凝土层,第一混凝土层厚度小于8cm,第一混凝土层凝固后再喷射第二混凝土层,第二混凝土层的厚度大于10cm。硬质聚氨酯泡沫层均匀平整的覆盖在锚喷混凝土层上,网格布砂浆层包括网格布9和砂浆,网格布9通过锚杆外露端挂设在硬质聚氨酯泡沫层之上,砂浆包裹网格布固结在硬质聚氨酯泡沫层上。The cross-sectional shape of the shotcrete layer 2 is the same as that of the roadway, and the shotcrete layer 2 has a solid structure and has a flat surface. The anchor shotcrete layer 2 includes a first concrete layer and a second concrete layer. The first concrete layer is formed by spraying concrete in the roadway. The thickness of the first concrete layer is less than 8cm. After the first concrete layer is solidified, the second concrete layer is sprayed. The thickness of the second concrete layer is greater than 10 cm. The rigid polyurethane foam layer is evenly and evenly covered on the anchor shotcrete layer. The grid cloth mortar layer includes grid cloth 9 and mortar. The grid cloth 9 is hung on the rigid polyurethane foam layer through the exposed end of the anchor rod. The wrapping grid cloth is fixed on the rigid polyurethane foam layer.
另外,巷道断面可以呈矩形、梯形、半圆拱形、圆弧拱形、椭圆形或圆形等不规则形状。网格布上设置有钩刺,从而方便锚杆间距较大的地方挂设网格布,并保证网格布砂浆层和硬质聚氨酯泡沫层紧贴在一起方便喷射砂浆;钩刺8的结构具体为,设置有尖头5、连杆6和翅板7,围绕尖头5呈锥形设置有3-4个翅板7,钩刺8的后端呈环形套设固定在网格布9的交叉点上,钩刺用塑料材质制作降低成本。In addition, the roadway section can be rectangular, trapezoidal, semi-circular arch, arc arch, ellipse or circle and other irregular shapes. Barbs are provided on the grid cloth, so that it is convenient for the grid cloth to be hung in the place where the anchor distance is large, and the grid cloth mortar layer and the rigid polyurethane foam layer are closely attached to facilitate the spraying of the mortar; the structure of the barb 8 Specifically, a pointed head 5, a connecting rod 6 and a fin plate 7 are provided, 3-4 fin plates 7 are arranged in a cone shape around the pointed head 5, and the rear end of the barb 8 is sleeved and fixed on the mesh cloth 9 in a ring shape. The barb is made of plastic material to reduce costs.
支护结构的施工具体是,首先在巷道壁面第一次喷射混凝土,平整巷道壁面;然后钻孔并安装锚杆进行支护,使用高强度的锚杆、螺母以及托盘。控制围岩变形、维持岩层稳定。混凝土硬化一定程度后喷涂硬质聚氨酯泡沫,采用现场喷涂法。使用高压喷枪将混合料喷涂在墙体表面,尽量保证厚度均匀,不能有厚度小于30mm的地方,将过厚处使用铲刀清除,过薄处用硬质聚氨酯泡沫塑料补上。受环境影响,施工时风力不得大于3级,空气相对湿度应小于70%,可以避免喷涂时泡沫易飞溅造成环境污染,材料浪费率高的问题。待硬质聚氨酯泡沫塑料冷却熟化后挂上网格布喷射聚合物水泥砂浆提高材料的耐用程度。The specific construction of the support structure is to spray concrete on the roadway wall for the first time to level the roadway wall; then drill holes and install bolts for support, using high-strength bolts, nuts and pallets. Control the deformation of the surrounding rock and maintain the stability of the rock formation. After the concrete has hardened to a certain extent, spray rigid polyurethane foam using on-site spraying. Use a high-pressure spray gun to spray the mixture on the wall surface, try to ensure that the thickness is uniform, and there should be no thickness less than 30mm. Use a spatula to remove the excessively thick areas, and use rigid polyurethane foam to make up the excessively thin areas. Affected by the environment, the wind power during construction should not be greater than level 3, and the relative humidity of the air should be less than 70%, which can avoid the problems of environmental pollution caused by foam splashing during spraying and high material waste rate. After the rigid polyurethane foam is cooled and cured, it is hung with a grid cloth to spray polymer cement mortar to improve the durability of the material.
合理的设置支护锚杆和锚喷混凝土层,保证了巷道整体支护结构的稳定性,设 置硬质聚氨酯泡沫层来阻止巷道围岩热传递,利用了硬质聚氨酯泡沫施工方便,隔热性能好的优点。并且考虑到巷道围岩的变形情况,设置硬质聚氨酯泡沫层可以保证支护结构的抗剪、抗压性能;设置网格布砂浆层可以保护硬质聚氨酯泡沫层并提升结构整体的隔热性和稳定性。Reasonable setting of supporting bolts and shotcrete concrete layer ensures the stability of the overall support structure of the roadway. The rigid polyurethane foam layer is set to prevent the heat transfer of the surrounding rock of the roadway. The rigid polyurethane foam is used for convenient construction and thermal insulation performance. Good advantages. And considering the deformation of the surrounding rock of the roadway, the setting of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the setting of a grid cloth mortar layer can protect the rigid polyurethane foam layer and improve the overall thermal insulation of the structure And stability.
实施例2Example 2
为了进一步的说明该巷道支护结构的有益效果,对该结构的构筑方法进行说明。In order to further illustrate the beneficial effects of the roadway support structure, the construction method of the structure will be described.
隔热巷道包括支护锚杆1、锚喷混凝土层2、硬质聚氨酯泡沫层3和网格布砂浆层4,紧贴巷道围岩设置锚喷混凝土层2,硬质聚氨酯泡沫3层固定在锚喷混凝土层2上,网格布砂浆层4设置在硬质聚氨酯泡沫层3上。具体的结构包括支护锚杆和锚喷混凝土层,巷道设置支护锚杆1,紧贴巷道围岩设置锚喷混凝土层2,还包括硬质聚氨酯泡沫层3和网格布砂浆层4,硬质聚氨酯泡沫层3固定在锚喷混凝土层上,网格布砂浆层4设置在硬质聚氨酯泡沫层3上。其中,锚喷混凝土层2厚度小于20mm,硬质聚氨酯泡沫层3厚度大于30mm,网格布砂浆层4厚度为1.5-3mm。The insulated roadway includes the supporting bolt 1, the shotcrete concrete layer 2, the hard polyurethane foam layer 3 and the grid cloth mortar layer 4. The anchor shotcrete layer 2 is set close to the surrounding rock of the roadway, and the 3 layers of hard polyurethane foam are fixed in On the anchor shotcrete layer 2, the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3. The concrete structure includes supporting bolts and shotcrete concrete layer. Support bolts 1 are set in the roadway, and shotcrete concrete layer 2 is set close to the surrounding rock of the roadway. It also includes a rigid polyurethane foam layer 3 and a grid cloth mortar layer 4. The rigid polyurethane foam layer 3 is fixed on the anchor shotcrete layer, and the grid cloth mortar layer 4 is arranged on the rigid polyurethane foam layer 3. Among them, the thickness of the anchor shotcrete layer 2 is less than 20mm, the thickness of the rigid polyurethane foam layer 3 is greater than 30mm, and the thickness of the grid cloth mortar layer 4 is 1.5-3mm.
锚喷混凝土层2的断面形状和巷道断面形状相同,锚喷混凝土层2为实心结构并且表面平整。其中锚喷混凝土层包括第一混凝土层和第二混凝土层,先在巷道内喷射混凝土形成第一混凝土层,第一混凝土层厚度小于8cm,第一混凝土层凝固后再喷射第二混凝土层,第二混凝土层的厚度大于10cm。硬质聚氨酯泡沫层3均匀平整的覆盖在锚喷混凝土层上,网格布砂浆层4包括网格布和砂浆,网格布通过锚杆外露端挂设在硬质聚氨酯泡沫层之上,砂浆包裹网格布固结在硬质聚氨酯泡沫层上,网格布采用中碱或无碱玻璃纤维网格布。另外,巷道断面可以呈矩形、梯形、半圆拱形、圆弧拱形、椭圆形或圆形等不规则形状。网格布上设置有钩刺,从而方便锚杆间距较大的地方挂设网格布,并保证网格布砂浆层和硬质聚氨酯泡沫层紧贴在一起方便喷射砂浆;钩刺的结构具体为,设置有尖头、连杆和翅板,围绕尖头呈锥形设置有3-4个翅板,钩刺的后端呈环形套设固定在网格布的交叉点上,钩刺用塑料材质制作降低成本。The cross-sectional shape of the shotcrete layer 2 is the same as that of the roadway, and the shotcrete layer 2 has a solid structure and has a flat surface. The anchor shotcrete layer includes a first concrete layer and a second concrete layer. The first concrete layer is formed by spraying concrete in the roadway. The thickness of the first concrete layer is less than 8cm. After the first concrete layer is solidified, the second concrete layer is sprayed. The thickness of the second concrete layer is greater than 10cm. The rigid polyurethane foam layer 3 is evenly and evenly covered on the anchor shotcrete layer. The grid cloth mortar layer 4 includes grid cloth and mortar. The grid cloth is hung on the rigid polyurethane foam layer through the exposed end of the anchor rod. The wrapping mesh cloth is consolidated on the rigid polyurethane foam layer, and the mesh cloth adopts medium alkali or alkali-free glass fiber mesh cloth. In addition, the roadway section can be rectangular, trapezoidal, semi-circular arch, arc arch, ellipse or circle and other irregular shapes. Barbs are provided on the grid cloth, so that it is convenient to hang the grid cloth in the place where the anchor distance is large, and to ensure that the grid cloth mortar layer and the rigid polyurethane foam layer are close together to facilitate the spraying of the mortar; the structure of the barb is specific It is provided with a pointed head, a connecting rod and a fin plate, and 3-4 fin plates are arranged in a cone shape around the pointed head. The rear end of the barb is sleeved and fixed on the intersection of the grid cloth in a ring shape. Plastic material production reduces costs.
公开了一种隔热巷道支护方法,其支护步骤包括:A method for supporting an insulated roadway is disclosed, and the supporting steps include:
步骤一.在新开挖的巷道壁面喷射混凝土,平整巷道壁面,形成第一混凝土层;其中第一混凝土层的厚度小于8cm。对于新开挖成型后的高温巷道进行锚喷支护并平整巷道壁面控制围岩变形、维持岩层稳定。Step 1. Spray concrete on the wall of the newly excavated roadway to level the wall of the roadway to form the first concrete layer; the thickness of the first concrete layer is less than 8cm. For the newly excavated and formed high-temperature roadway, carry out bolt and shotcrete support and level the roadway wall to control the deformation of the surrounding rock and maintain the stability of the rock formation.
步骤二.在平整的巷道壁面施工锚杆钻孔,安装锚杆、托盘和螺母,对巷道进行支护,控制巷道围岩变形。其中锚杆参数为直径Φ=25mm,每根长2m,间距800mm,排距800mm;还可以设置锚索加强对巷道的支护。Step 2. Construct bolt drilling on the flat roadway wall, install bolts, pallets and nuts, support the roadway, and control the deformation of the surrounding rock of the roadway. Among them, the bolt parameters are diameter Φ=25mm, each length is 2m, the spacing is 800mm, and the row spacing is 800mm. Anchor cables can also be set to strengthen the support of the roadway.
步骤三.再次喷射混凝土,形成锚喷混凝土层,混凝土硬化后喷涂硬质聚氨酯泡沫,形成硬质聚氨酯泡沫层。其中再次喷射混凝土形成第二混凝土层厚度大于10cm,第一混凝土层和第二混凝土层组合形成锚喷混凝土层厚度小于等于20cm。喷涂硬质聚氨酯泡沫使用现场喷涂法,具体是使用高压喷枪将硬质聚氨酯泡沫喷涂在墙体表面,重复喷涂,保证厚度均匀,施工时巷道内通风的风力小于3级,空气相对湿度小于70%,可以避免喷涂时泡沫易飞溅造成环境污染,材料浪费率高的问题;硬质聚氨酯泡沫层厚度大于30mm。 Step 3. Spray the concrete again to form an anchor spray concrete layer. After the concrete is hardened, spray hard polyurethane foam to form a hard polyurethane foam layer. Wherein, the thickness of the second concrete layer formed by spraying concrete again is greater than 10cm, and the thickness of the first concrete layer and the second concrete layer combined to form the anchor shotcrete layer is less than or equal to 20cm. The spraying of rigid polyurethane foam uses the on-site spraying method. Specifically, the rigid polyurethane foam is sprayed on the surface of the wall with a high-pressure spray gun, and the spraying is repeated to ensure uniform thickness. The wind power in the tunnel during construction is less than 3, and the relative humidity of the air is less than 70%. , It can avoid the problems of easy splashing of foam during spraying to cause environmental pollution and high material waste rate; the thickness of the rigid polyurethane foam layer is greater than 30mm.
步骤四.检查硬质聚氨酯泡沫喷涂是否均匀,其厚度大于或等于30cm,厚度大于33cm的位置用铲刀清除,过薄厚度小于27cm位置用硬质聚氨酯泡沫补齐。硬质聚氨脂泡沫塑料的制备方法是采用聚醚树脂和异氰酸为主要原料按1∶1比例加入物料混合器混匀混合,以反应中生成的二氧化碳为发泡剂,一段时间后,便可得到硬质聚氨酯泡沫塑料。既可直接喷涂于建筑界面上,经过约30min的反应冷却定型,完全黏附在建筑界面上。Step 4. Check whether the rigid polyurethane foam is evenly sprayed. The thickness is greater than or equal to 30cm. The locations where the thickness is greater than 33cm are removed with a shovel. The locations that are too thin and less than 27cm are filled with rigid polyurethane foam. The preparation method of rigid polyurethane foam is to use polyether resin and isocyanic acid as the main raw materials to add into the material mixer at a ratio of 1:1 and mix, and use the carbon dioxide generated in the reaction as the blowing agent. After a period of time, The rigid polyurethane foam can be obtained. It can be sprayed directly on the building interface, and after about 30 minutes of reaction cooling and finalization, it completely adheres to the building interface.
步骤五.硬质聚氨酯泡沫塑料冷却熟化后挂设网格布,然后在网格布上喷射聚合物水泥砂浆,水泥砂浆凝固后形成网格布砂浆层。网格布砂浆层厚度为1.5-3mm。聚合物水泥砂浆主要组成材料是水泥、骨料以及可以分散水的有机聚合物,将这些配比之后加入到水中搅拌即可使用。具体是混凝土硬化一定程度后喷涂硬质聚氨酯泡沫,发泡后形成隔热层,阻止高温向巷道传播;待硬质聚氨酯泡沫塑料冷却熟化后挂网格布喷射聚合物水泥砂浆,最终形成具有隔热功能的支护系统。 Step 5. After the rigid polyurethane foam is cooled and cured, a grid cloth is hung, and then polymer cement mortar is sprayed on the grid cloth, and the cement mortar is solidified to form a grid cloth mortar layer. The thickness of the grid cloth mortar layer is 1.5-3mm. The main components of polymer cement mortar are cement, aggregates and organic polymers that can disperse water. After these proportions are added to the water, they can be used after stirring. Specifically, after the concrete is hardened to a certain extent, rigid polyurethane foam is sprayed to form an insulating layer after foaming to prevent the high temperature from spreading to the roadway; after the rigid polyurethane foam is cooled and cured, the polymer cement mortar is sprayed on a grid cloth, and finally a barrier is formed. Thermal support system.
隔热巷道支护方法的施工工艺方便高效、成本节约,先构筑第一混凝土层,从而保证巷道围岩的表面平整,也方便设置锚杆锚索,保证了锚杆的准确设置和 托盘的平整,提升支护效果;第二混凝土喷层复喷保证了锚喷混凝土层的有效性,并且第一喷层和第二喷层的先后喷射可以提升施工效率,锚喷混凝土层可以更快的硬化;硬质聚氨酯泡沫层的施工更加方便,并且价格低廉、节能环保,硬质聚氨酯泡沫不会发生破裂而损害其保温性能,具备优秀的抗冲击性能;挂设网格布更方便网格布砂浆层的布置。The construction process of the insulated roadway support method is convenient and efficient, and cost-saving. The first concrete layer is constructed first to ensure the surface of the surrounding rock of the roadway is smooth, and it is also convenient to set the anchor bolts and cables, which ensures the accurate setting of the bolts and the flatness of the pallets. , Improve the supporting effect; the second concrete spray layer re-spraying ensures the effectiveness of the anchor spray concrete layer, and the sequential spraying of the first spray layer and the second spray layer can improve the construction efficiency, and the anchor spray concrete layer can harden faster ; The construction of the rigid polyurethane foam layer is more convenient, and the price is low, energy saving and environmental protection. The rigid polyurethane foam will not break and damage its thermal insulation performance, and has excellent impact resistance; it is more convenient to hang the grid cloth and the grid cloth mortar Layer layout.
其中硬质聚氨酯泡沫的选取是通过同类结构对比而得到的,为了选择合适的隔热材料形成隔热结构,将热害阻止在井巷外围,通过对比硬质聚氨酯泡沫、聚苯乙烯材料和聚苯乙烯EPS的组成结构,结合到深部矿井的巷道支护的传热特点。对比如表1所示,25mm厚度的硬质聚氨酯泡沫就可达到隔热保温50%的效果,且成本较低,是非常理想的隔热材料。并且硬质聚氨酯泡沫层的施工更加方便,并且价格低廉、节能环保,硬质聚氨酯泡沫不会发生破裂而损害其保温性能,具备优秀的抗冲击性能;挂设网格布更方便网格布砂浆层的布置。Among them, the selection of rigid polyurethane foam is obtained through comparison of similar structures. In order to select suitable thermal insulation materials to form a thermal insulation structure and prevent thermal damage from the periphery of the shaft, the comparison of rigid polyurethane foam, polystyrene material and polystyrene The composition structure of styrene EPS is combined with the heat transfer characteristics of tunnel support in deep mines. For example, as shown in Table 1, rigid polyurethane foam with a thickness of 25mm can achieve 50% thermal insulation and low cost, making it an ideal thermal insulation material. Moreover, the construction of the rigid polyurethane foam layer is more convenient, and the price is low, energy saving and environmental protection. The rigid polyurethane foam will not break and damage its thermal insulation performance, and has excellent impact resistance; it is more convenient to hang the grid cloth and the grid cloth mortar Layer layout.
表1Table 1
Figure PCTCN2019125573-appb-000001
Figure PCTCN2019125573-appb-000001
硬质聚氨酯泡沫是所有隔热材料中具有最低导热性的材料之一,50mm厚的硬质聚氨酯泡沫塑料的保温效果相当于90mm厚的矿棉、100mm厚的软木、130mm厚纤维板、280mm厚的木板或760mm厚的混凝土,这使其可以有效的保存热量维持低温环境。硬质聚氨酯泡沫具备高强度的压缩强度和剪切强度,可有效的与各种广为使用表面材料粘结,这些材料可增加硬质聚氨酯泡沫的固有强度,使其可作为半结构板材使用,硬质聚氨酯泡沫也不会发生破裂而损害其保温性能,具备优秀的抗冲击性能。保温隔热材料硬质聚氨酯泡沫还可以在-70℃-+130℃极端条件下使用,使得支护系统具有耐老化、抗潮等优点,施工简便且有成熟的施工技术作为支撑。硬质聚氨酯泡沫具有绿色安全性,硬质聚氨脂泡沫塑 料不含有毒化学原料,对人体安全无毒副作用,且原材料可循环使用,价格低廉、节能环保。Rigid polyurethane foam is one of the materials with the lowest thermal conductivity among all thermal insulation materials. The thermal insulation effect of 50mm thick rigid polyurethane foam is equivalent to 90mm thick mineral wool, 100mm thick cork, 130mm thick fiberboard, and 280mm thick. Wood board or 760mm thick concrete, which allows it to effectively preserve heat and maintain a low temperature environment. Rigid polyurethane foam has high compressive strength and shear strength, and can effectively bond with various widely used surface materials. These materials can increase the inherent strength of rigid polyurethane foam and make it usable as a semi-structural sheet. Rigid polyurethane foam will not rupture and damage its thermal insulation performance, and has excellent impact resistance. The thermal insulation material rigid polyurethane foam can also be used under extreme conditions of -70℃-+130℃, which makes the supporting system have the advantages of anti-aging and moisture resistance, simple construction and mature construction technology as support. Rigid polyurethane foam is green and safe. Rigid polyurethane foam does not contain toxic chemical raw materials, is safe and has no toxic side effects to the human body, and the raw materials can be recycled, low price, energy saving and environmental protection.
本方法合理的设置支护锚杆和锚喷混凝土层,保证了巷道整体支护结构的稳定性,设置硬质聚氨酯泡沫层来阻止巷道围岩热传递,利用了硬质聚氨酯泡沫施工方便,隔热性能好的优点。并且考虑到巷道围岩的变形情况,设置硬质聚氨酯泡沫层可以保证支护结构的抗剪、抗压性能;设置网格布砂浆层可以保护硬质聚氨酯泡沫层并提升结构整体的隔热性和稳定性。In this method, the supporting bolts and the shotcrete concrete layer are set reasonably to ensure the stability of the overall support structure of the roadway. The rigid polyurethane foam layer is set to prevent the heat transfer of the surrounding rock of the roadway. The rigid polyurethane foam is used for convenient construction and isolation. Advantages of good thermal performance. And considering the deformation of the surrounding rock of the roadway, the setting of a rigid polyurethane foam layer can ensure the shear resistance and compression performance of the supporting structure; the setting of a grid cloth mortar layer can protect the rigid polyurethane foam layer and improve the overall thermal insulation of the structure And stability.
当然,上述说明并非是对本实用新型的限制,本实用新型也并不仅限于上述举例,本技术领域的技术人员在本实用新型的实质范围内所做出的变化、改型、添加或替换,也应属于本实用新型的保护范围。Of course, the above description is not a limitation of the present utility model, and the present utility model is not limited to the above examples. Changes, modifications, additions or substitutions made by those skilled in the art within the essential scope of the utility model are also It should belong to the protection scope of the utility model.

Claims (4)

  1. 一种阻止巷道围岩传热的支护结构,包括支护锚杆和锚喷混凝土层,巷道设置支护锚杆,紧贴巷道围岩设置锚喷混凝土层;其特征在于,还包括硬质聚氨酯泡沫层和网格布砂浆层,所述硬质聚氨酯泡沫层固定在锚喷混凝土层上,网格布砂浆层设置在硬质聚氨酯泡沫层上;所述锚喷混凝土层的断面形状和巷道断面形状相同,锚喷混凝土层为实心结构并且表面平整,硬质聚氨酯泡沫层均匀平整的覆盖在锚喷混凝土层上,网格布砂浆层包括网格布和砂浆,网格布通过锚杆外露端挂设在硬质聚氨酯泡沫层上,砂浆包裹网格布固结在硬质聚氨酯泡沫层上。A supporting structure for preventing heat transfer to the surrounding rock of a roadway, comprising supporting bolts and a shotcrete concrete layer. The supporting bolts are arranged in the roadway, and the bolting and shotcreting concrete layer is arranged close to the surrounding rock of the roadway; it is characterized in that it also includes hard A polyurethane foam layer and a grid cloth mortar layer, the hard polyurethane foam layer is fixed on the anchor shotcrete layer, and the grid cloth mortar layer is arranged on the hard polyurethane foam layer; the cross-sectional shape and the roadway of the anchor shot concrete layer The cross-section shape is the same, the anchor shotcrete layer is a solid structure and the surface is flat, the rigid polyurethane foam layer is evenly and evenly covered on the anchor shotcrete layer, the grid cloth mortar layer includes grid cloth and mortar, and the grid cloth is exposed through the anchor rod The ends are hung on the rigid polyurethane foam layer, and the mortar wraps the grid cloth and is consolidated on the rigid polyurethane foam layer.
  2. 根据权利要求1所述的一种阻止巷道围岩传热的支护结构,其特征在于,所述锚喷混凝土层厚度小于20mm,所述硬质聚氨酯泡沫层厚度大于30mm,所述网格布砂浆层厚度为1.5-3mm。The supporting structure for preventing heat transfer to the surrounding rock of a roadway according to claim 1, wherein the thickness of the bolted shotcrete layer is less than 20mm, the thickness of the rigid polyurethane foam layer is greater than 30mm, and the grid cloth The thickness of the mortar layer is 1.5-3mm.
  3. 根据权利要求1所述的一种阻止巷道围岩传热的支护结构,其特征在于,所述巷道断面呈矩形、梯形、半圆拱形、圆弧拱形、椭圆形或圆形。The supporting structure for preventing heat transfer to surrounding rocks of a roadway according to claim 1, wherein the cross section of the roadway is rectangular, trapezoidal, semi-circular arch, arc arch, oval or circular.
  4. 根据权利要求1至3任意一项所述的一种阻止巷道围岩传热的支护结构,其特征在于,所述网格布上设置有钩刺。According to any one of claims 1 to 3, a supporting structure for preventing heat transfer in surrounding rocks of a roadway, characterized in that barbs are provided on the grid cloth.
PCT/CN2019/125573 2019-11-29 2019-12-16 Supporting structure for preventing roadway surrounding rock from transferring heat WO2021103192A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201922096082.5U CN211081909U (en) 2019-11-29 2019-11-29 Supporting structure for preventing heat transfer of surrounding rock of roadway
CN201922096082.5 2019-11-29

Publications (1)

Publication Number Publication Date
WO2021103192A1 true WO2021103192A1 (en) 2021-06-03

Family

ID=71629102

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2019/125573 WO2021103192A1 (en) 2019-11-29 2019-12-16 Supporting structure for preventing roadway surrounding rock from transferring heat

Country Status (2)

Country Link
CN (1) CN211081909U (en)
WO (1) WO2021103192A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153362B (en) * 2020-12-30 2022-08-26 中铁隧道集团三处有限公司 Construction method of high-temperature tunnel supporting structure under high ground stress
CN113107526B (en) * 2021-04-24 2023-05-16 淮北市平远软岩支护工程技术有限公司 Anti-impact ground pressure supporting method suitable for forming roadway

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006291690A (en) * 2005-03-17 2006-10-26 Shimizu Corp Lining concrete curing equipment
JP2010248758A (en) * 2009-04-14 2010-11-04 Taisei Corp Hollow pipe body and tunnel construction method using the same
CN101975073A (en) * 2009-09-30 2011-02-16 王晓利 Retractable concrete arch and anchor rod combined support system and construction method
CN201810321U (en) * 2010-06-28 2011-04-27 中铁二十局集团有限公司 Composite heat insulation lining structure of plateau frozen earth tunnel
CN204386622U (en) * 2014-12-31 2015-06-10 长安大学 A kind of tunnel is far from wall type insulation construction
CN205100993U (en) * 2015-08-07 2016-03-23 云南迪庆有色金属有限责任公司 Ore removal level drift section supporting construction
CN106703884A (en) * 2017-01-13 2017-05-24 中南大学 Cooling method for thermal insulating layer on wall surface of high-temperature hard rock roadway of deep well
CN106988769A (en) * 2017-06-02 2017-07-28 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure and its construction method
CN107762538A (en) * 2017-12-08 2018-03-06 承德路桥建设总公司 A kind of tunnel-liner heat-insulating method and its heat insulation and preservation device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006291690A (en) * 2005-03-17 2006-10-26 Shimizu Corp Lining concrete curing equipment
JP2010248758A (en) * 2009-04-14 2010-11-04 Taisei Corp Hollow pipe body and tunnel construction method using the same
CN101975073A (en) * 2009-09-30 2011-02-16 王晓利 Retractable concrete arch and anchor rod combined support system and construction method
CN201810321U (en) * 2010-06-28 2011-04-27 中铁二十局集团有限公司 Composite heat insulation lining structure of plateau frozen earth tunnel
CN204386622U (en) * 2014-12-31 2015-06-10 长安大学 A kind of tunnel is far from wall type insulation construction
CN205100993U (en) * 2015-08-07 2016-03-23 云南迪庆有色金属有限责任公司 Ore removal level drift section supporting construction
CN106703884A (en) * 2017-01-13 2017-05-24 中南大学 Cooling method for thermal insulating layer on wall surface of high-temperature hard rock roadway of deep well
CN106988769A (en) * 2017-06-02 2017-07-28 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure and its construction method
CN107762538A (en) * 2017-12-08 2018-03-06 承德路桥建设总公司 A kind of tunnel-liner heat-insulating method and its heat insulation and preservation device

Also Published As

Publication number Publication date
CN211081909U (en) 2020-07-24

Similar Documents

Publication Publication Date Title
WO2021103192A1 (en) Supporting structure for preventing roadway surrounding rock from transferring heat
CN203361380U (en) Ultra-thin efficient composite heat preservation template of permanent cast-in-place concrete
CN102850034A (en) Chlorine magnesium cement compound foaming insulation board and preparation method thereof
CN104529345B (en) Nano-pearl rock heat insulating mortar and preparation method thereof
CN102173717B (en) Production method of high-strength light environment-friendly insulation fire-proof plate
CN203430021U (en) Split-free polyurethane composite heat insulation template for pouring concrete
CN201190339Y (en) Insulation structure for outer wall of building
CN102966201B (en) Nanoscale efficient heat-insulated wall plate and construction method thereof
CN213773995U (en) Heat-preservation building structure
CN208455848U (en) A kind of two-sided steel wire embeds the prefabricated assembled wall of insulation board
CN101372413A (en) Light ceramsite concrete and preparation thereof
CN206034902U (en) Compound incubation outer wall -in -place mould
CN101775861B (en) Cast in situs construction method for light heat-insulation integral wall of energy-saving construction house and light heat-insulation wall material
CN208415678U (en) Active low energy consumption precast concrete truss structure wall
CN207017573U (en) Composite heat preserving external wall
CN206887982U (en) A kind of solar energy high temperature fused salt storage tank basis heat insulation structural
CN207686079U (en) Active multiple fireproof heat insulating external wall structure
CN211736144U (en) Green environment-friendly fireproof energy-saving building wallboard
CN107460968A (en) Sandwich heat preservation in-line combined wall and the practice with lead pipe coarse sand energy-dissipating and shock-absorbing key
CN203401772U (en) Thick-plaster fireproof mortar phenolic resin plate
CN209975765U (en) Steel wire mesh A-grade fireproof vacuum insulation panel heat preservation system
CN203174899U (en) Slope finding and heat preservation integrated roof building construction
CN113153362B (en) Construction method of high-temperature tunnel supporting structure under high ground stress
CN203569726U (en) Bearing-type cast-in-place insulating layer outer wall
CN206308844U (en) Embedded twigs of the chaste tree drawknot foam block loam wall

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19954689

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 19954689

Country of ref document: EP

Kind code of ref document: A1