WO2019218236A1 - Procédé de construction de système de plafond suspendu - Google Patents

Procédé de construction de système de plafond suspendu Download PDF

Info

Publication number
WO2019218236A1
WO2019218236A1 PCT/CN2018/087005 CN2018087005W WO2019218236A1 WO 2019218236 A1 WO2019218236 A1 WO 2019218236A1 CN 2018087005 W CN2018087005 W CN 2018087005W WO 2019218236 A1 WO2019218236 A1 WO 2019218236A1
Authority
WO
WIPO (PCT)
Prior art keywords
ceiling
dragon skeleton
groove
panel
water pipe
Prior art date
Application number
PCT/CN2018/087005
Other languages
English (en)
Chinese (zh)
Inventor
杨泓斌
李缙
陈祥祥
颜旺龙
刘博�
Original Assignee
增城市碧桂园物业发展有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 增城市碧桂园物业发展有限公司 filed Critical 增城市碧桂园物业发展有限公司
Priority to CN201880000559.0A priority Critical patent/CN112154241A/zh
Priority to PCT/CN2018/087005 priority patent/WO2019218236A1/fr
Publication of WO2019218236A1 publication Critical patent/WO2019218236A1/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F19/00Other details of constructional parts for finishing work on buildings
    • E04F19/02Borders; Finishing strips, e.g. beadings; Light coves
    • E04F19/04Borders; Finishing strips, e.g. beadings; Light coves for use between floor or ceiling and wall, e.g. skirtings
    • CCHEMISTRY; METALLURGY
    • C08ORGANIC MACROMOLECULAR COMPOUNDS; THEIR PREPARATION OR CHEMICAL WORKING-UP; COMPOSITIONS BASED THEREON
    • C08LCOMPOSITIONS OF MACROMOLECULAR COMPOUNDS
    • C08L27/00Compositions of homopolymers or copolymers of compounds having one or more unsaturated aliphatic radicals, each having only one carbon-to-carbon double bond, and at least one being terminated by a halogen; Compositions of derivatives of such polymers
    • C08L27/02Compositions of homopolymers or copolymers of compounds having one or more unsaturated aliphatic radicals, each having only one carbon-to-carbon double bond, and at least one being terminated by a halogen; Compositions of derivatives of such polymers not modified by chemical after-treatment
    • C08L27/04Compositions of homopolymers or copolymers of compounds having one or more unsaturated aliphatic radicals, each having only one carbon-to-carbon double bond, and at least one being terminated by a halogen; Compositions of derivatives of such polymers not modified by chemical after-treatment containing chlorine atoms
    • C08L27/06Homopolymers or copolymers of vinyl chloride
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/04Protective tubing or conduits, e.g. cable ladders or cable troughs

Definitions

  • the invention belongs to the technical field of construction, and in particular relates to a construction method of a ceiling system.
  • the traditional hydropower pre-buried method needs to destroy the main structure during maintenance, and the maintenance is difficult, the cost is high, and the maintenance efficiency is low. At the same time, a large amount of construction waste and noise pollution are generated during maintenance, which will greatly affect the downstairs users. Because the main structure is damaged, it is not conducive to the modification of the internal decoration, the cost of repairing and the time-consuming is long.
  • the pipeline adopts the pre-buried mode, the pipeline and the main structure are integrated, and the pipeline and the structure main body are inconvenient to be separated, which is not conducive to the modification of the later household type. Meet the needs of residents' diverse and flexible.
  • Ceiling ceiling in the current home decoration can be divided into kitchen and bathroom ceiling, living room bedroom ceiling, corridor ceiling and other types, according to the material can be divided into gypsum ceiling, plastic ceiling, glass ceiling, metal ceiling Ceiling and so on.
  • the function of the ceiling is from the beginning of the ugly development to the current beauty, sound insulation and many other functions, such as today's flower ceiling line is simple and smooth, beautiful in appearance, elegant in color, and has bronze, gold, red, blue, milk white, etc. Color; the specification is exactly the same as the width of the house, and it is seamlessly connected with marble, aluminum alloy doors and windows, etc. It is elegant and gorgeous, and it is a perfect addition to the quiet living room environment.
  • the existing ceilings do not have water pipes and wiring functions. At the same time, there are no related processes and methods.
  • the technical problem to be solved by the present invention is to provide a construction method for a ceiling system, which aims to solve the problem that the water pipe and the electric wire are buried in the main structure of the house in the prior art, thereby damaging the main structure when the pipeline is repaired.
  • a construction method of a ceiling system comprising:
  • the dragon skeleton includes a first sub-dragon skeleton and a dragon skeleton crossbar, and the first sub-dragon skeleton has an L-shaped cross section in a vertical direction,
  • the bottom end of the ceiling side panel is provided with an upwardly bent hook-shaped card member, and the end of the ceiling bottom plate away from the wall panel is provided with a downwardly bent hook-shaped card member;
  • the groove width of the wire groove is smaller than the inner width of the groove, and the groove wall has elasticity, and the groove wall edge of the wire groove
  • the length of the strong electric wire is provided with a plurality of intervals
  • the first sub-dragon skeleton is assembled at a corner of the wall panel and the floor panel, and one end of the L-shaped is fixedly connected with the floor panel, and the other end is fixedly connected with the wall panel, and the wiring component with the electric wire is installed at the first position.
  • the water pipe installation member is installed on the wall plate between the first sub-dragon skeleton and the dragon skeleton cross bar, the water pipe is embedded in the water pipe installation member, and the ceiling side plate is installed on the first sub-dragon skeleton.
  • the side of the ceiling floor is adjacent to the wall panel and is connected to the dragon skeleton crossbar, and the end of the wall panel is bent away from the bent hook-shaped card member and the upwardly bent hook-shaped card at the bottom end of the ceiling panel.
  • the components are snapped together, and the lighting device is installed between the ceiling side panel and the shielding member of the ceiling panel.
  • the electric wire is a strong electric wire.
  • the preparation of the dragon skeleton, the ceiling floor and the ceiling side panel comprises the following steps:
  • a metal mold matching the shape of the dragon skeleton, the ceiling bottom plate and the ceiling side plate is prepared in advance, and then the dragon skeleton, the ceiling plate and the ceiling side plate are injection molded by using a plastic material in combination with the metal mold.
  • the preparation of the dragon skeleton, the ceiling floor and the ceiling side panel comprises the following steps:
  • the plate-shaped profile is cut to obtain a dragon skeleton, a ceiling plate and a ceiling side plate.
  • the ceiling bottom plate and the ceiling side plate are made of PVC foamed wood plastic material, and the PVC foamed wood plastic material is produced by processing the following weight ratio raw materials: polyvinyl chloride (PVC): 100 parts; lignified plant fiber: 15-20 parts; active light calcium: 10-20 parts; zinc-calcium composite stabilizer: 7-10 parts, compound type foaming agent: 1-3 parts, lubricant OPE wax: 1.5-2 parts; composite lubricant: 0.5-1 part, foaming regulator: 3-8 parts.
  • PVC polyvinyl chloride
  • the present invention has the beneficial effects that the construction method of the ceiling system of the present invention installs the water pipe installation component on the wall panel in the ceiling of the ceiling, and installs the wiring component on the bottom of the first sub-dragon skeleton.
  • the utility model overcomes the problem that the water pipe and the electric wire are buried in the main structure of the house in the prior art, realizes the separation of the support body and the filler body, and reduces the difficulty and cost of the maintenance of the water pipe wire.
  • the present invention can see the electric wires and the water pipes after the ceiling plate is removed, and the water pipes and the wires can be repaired in one step, thereby improving the efficiency of maintenance.
  • the water pipe, the line and the main structure adopt a separate design to provide more space for interior installation and equipment renewal.
  • the water pipes, lines and equipment can be updated without destroying the main structure, which greatly saves the cost of later maintenance and modification. It greatly reduces the construction waste and noise pollution generated during the later maintenance and renovation, and reduces the damage to the natural environment. Reducing the impact on the downstairs users during maintenance can greatly improve the satisfaction of the occupants.
  • the occupants can modify the unit according to the needs of each individual to maximize the satisfaction of residential use requirements.
  • FIG. 1 is a flow chart of a construction method of a ceiling system according to an embodiment of the present invention
  • FIG. 2 is a schematic structural view of a ceiling ceiling system corresponding to the construction method of FIG. 1;
  • FIG. 3 is a schematic structural view of the high-voltage wiring member of FIG. 2.
  • a construction method of a ceiling system for a ceiling includes the following steps:
  • the dragon skeleton 1 includes a first sub-dragon skeleton 11 and a dragon skeleton crossbar 12, and the first sub-dragon skeleton 11 has an L-shaped cross section in the vertical direction, and the bottom end of the ceiling side panel 3 is provided with an upwardly bent hook.
  • a card member 31, the end of the ceiling plate 2 away from the wall plate is provided with a downwardly bent hook-shaped card member 21;
  • the method for preparing the dragon skeleton 1, the ceiling bottom plate 2 and the ceiling side panel 3 can adopt the following two methods, wherein the method 1: preparing the dragon skeleton 1, the ceiling bottom plate 2 and the ceiling side plate 3 in advance. The metal mold of the shape is matched, and then the plastic skeleton is combined with the metal mold to mold the dragon skeleton 1, the ceiling bottom plate 2 and the ceiling side plate 3. Method 2: Cutting the plate-shaped profile to obtain a dragon skeleton 1, a ceiling bottom plate 2 and a ceiling side plate 3.
  • the groove wall 61 of the strong wire slot may be spaced apart along the length of the strong electric wire.
  • the electric wire in this embodiment can be selected from a strong electric wire.
  • the working voltage is strong under 24V AC, and the following is weak.
  • a strong electric wire generally refers to a transmission line with an AC voltage of 24V or more.
  • the first sub-dragon skeleton 11 is assembled at the corner of the wall panel 100 and the floor panel 200.
  • One end of the L-shape is fixedly connected with the floor panel 200, and the other end is fixedly connected with the wall panel 100, and the wiring member with the electric wire 7 is installed.
  • the ceiling side panel 3 is mounted on the side of the first sub-dragon skeleton 11, and the end of the ceiling bottom panel 2 adjacent to the wall panel 100 is connected to the dragon skeleton crossbar 12, and one end away from the wall panel 12 is bent downwardly.
  • the card member 21 is engaged with the upwardly bent hook-shaped card member 31 at the bottom end of the ceiling side panel 3, and the lighting device 8 is mounted between the ceiling side panel 3 and the shutter member 22 of the ceiling panel 2.
  • the above-mentioned water pipe fitting 4 can be installed not only on the wall panel 100 between the first sub-dragon skeleton 11 and the dragon skeleton crossbar 12, but also in other positions in the ceiling of the ceiling, and by screws and bonding. Or the way of the buckle is fixed, just need to be stable and not easy to fall off.
  • the notch of the tank body of the water pipe fitting 4 for placing the water pipe 5 needs to be smaller than the inner width of the groove, and the groove wall has elasticity, and the water pipe 5 is inserted into the groove by pressing. In the body, such a design serves to prevent the water pipe from falling off.
  • the above-mentioned strong electric wiring member 6 can be installed not only at the bottom of the first sub-dragon skeleton 11, but also at other positions in the ceiling of the ceiling, and is fixed by screws, bonding or snapping. Satisfy stability, not easy to fall off. It should be noted that when the strong electric wiring member 6 is installed at the bottom of the first sub-dragon skeleton 11, the slot of the strong electric wiring member 6 for embedding the strong electric wire 7 needs to be smaller than the inner groove width, and the groove wall has The elastic, strong electric wire 7 is embedded in the wire groove by pressing, and this design serves to prevent the strong electric wire 7 from falling off.
  • the ceiling bottom plate 2 and the ceiling side plate 3 of the present invention may be made of PVC foamed wood plastic material, which is produced by processing the following weight ratio raw materials: polyvinyl chloride (PVC): 100 parts; lignified plant fiber: 15-20 parts; active light calcium: 10-20 parts; zinc-calcium composite stabilizer: 7-10 parts, compound type foaming agent: 1-3 parts, lubricant OPE wax: 1.5-2 parts; compound lubricant: 0.5-1 part, foaming regulator: 3-8 parts, the above mixture is uniformly mixed by a mixer and directly added to a screw extruder, and extruded at 160 to 170 ° C Form it.
  • PVC polyvinyl chloride
  • lignified plant fiber 15-20 parts
  • active light calcium 10-20 parts
  • zinc-calcium composite stabilizer 7-10 parts
  • compound type foaming agent 1-3 parts
  • lubricant OPE wax 1.5-2 parts
  • compound lubricant 0.5-1 part
  • foaming regulator 3-8 parts
  • the water pipe installation component is installed on the wall panel in the ceiling of the ceiling, and the wiring component is installed at the bottom of the first sub-dragon skeleton, thereby overcoming the water pipe and the electric wire buried in the prior art.
  • the separation of the support body and the filler body is realized, and the difficulty and cost of overhauling the water pipe and the strong electric wire are reduced.
  • the present invention can see the electric wires and the water pipes after the ceiling plate is removed, and the water pipes and the wires can be repaired in one step, thereby improving the efficiency of maintenance.
  • the water pipe, the line and the main structure adopt a separate design to provide more space for interior installation and equipment renewal.
  • the water pipes, lines and equipment can be updated without destroying the main structure, which greatly saves the cost of later maintenance and modification. It greatly reduces the construction waste and noise pollution generated during the later maintenance and renovation, and reduces the damage to the natural environment. Reducing the impact on the downstairs users during maintenance can greatly improve the satisfaction of the occupants.
  • the occupants can modify the unit according to the needs of each individual to maximize the satisfaction of residential use requirements.

Abstract

La présente invention a trait au domaine technique de la construction immobilière. L'invention concerne en particulier un procédé de construction de système de plafond suspendu, comprenant les étapes consistant : à installer un élément de maintien de conduite d'eau au niveau d'une paroi à l'intérieur d'un plafond suspendu ; et à installer un élément d'acheminement de câbles au niveau d'une partie inférieure d'un premier sous-cadre. Le système de plafond suspendu selon l'invention permet de résoudre les problèmes des antériorités causés par l'incorporation de conduites d'eau et de câbles électriques dans la structure principale d'un bâtiment, et de réaliser la séparation d'un élément de support d'un composant monté, ce qui réduit la difficulté et les coûts liés à l'inspection et à la réparation de conduites d'eau et de câbles à haute tension. Selon l'invention, un câble électrique et une conduite d'eau peuvent être découverts après le retrait d'un panneau de base de plafond suspendu, de sorte qu'une seule opération est nécessaire avant l'inspection et la réparation de conduites d'eau et de câbles électriques, ce qui accroît l'efficacité de l'inspection et de la réparation.
PCT/CN2018/087005 2018-05-16 2018-05-16 Procédé de construction de système de plafond suspendu WO2019218236A1 (fr)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201880000559.0A CN112154241A (zh) 2018-05-16 2018-05-16 一种天花吊顶系统的施工方法
PCT/CN2018/087005 WO2019218236A1 (fr) 2018-05-16 2018-05-16 Procédé de construction de système de plafond suspendu

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2018/087005 WO2019218236A1 (fr) 2018-05-16 2018-05-16 Procédé de construction de système de plafond suspendu

Publications (1)

Publication Number Publication Date
WO2019218236A1 true WO2019218236A1 (fr) 2019-11-21

Family

ID=68539224

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/087005 WO2019218236A1 (fr) 2018-05-16 2018-05-16 Procédé de construction de système de plafond suspendu

Country Status (2)

Country Link
CN (1) CN112154241A (fr)
WO (1) WO2019218236A1 (fr)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1146428A (ja) * 1997-07-25 1999-02-16 Sekisui Chem Co Ltd 建物の配線構造
CN101613509A (zh) * 2009-06-03 2009-12-30 石河子天露节水设备有限责任公司 Pvc发泡木塑材料
CN203023646U (zh) * 2012-10-23 2013-06-26 韦明凡 一种线卡
CN105649256A (zh) * 2016-01-10 2016-06-08 胡崇亮 吊顶竖立装饰板的安装结构及转角吊顶层
CN106013732A (zh) * 2016-06-30 2016-10-12 张健 一种安装导线管道底板墙角线
CN106786235A (zh) * 2016-12-14 2017-05-31 浙江亚厦装饰股份有限公司 一种线管或线槽卡扣件及安装方法

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6115002B2 (ja) * 2011-03-14 2017-04-19 Dic株式会社 無変性のけい酸カルシウム粉の抗菌剤としての使用
CN204590382U (zh) * 2015-04-24 2015-08-26 谢凯 一种天花吊顶的安装结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1146428A (ja) * 1997-07-25 1999-02-16 Sekisui Chem Co Ltd 建物の配線構造
CN101613509A (zh) * 2009-06-03 2009-12-30 石河子天露节水设备有限责任公司 Pvc发泡木塑材料
CN203023646U (zh) * 2012-10-23 2013-06-26 韦明凡 一种线卡
CN105649256A (zh) * 2016-01-10 2016-06-08 胡崇亮 吊顶竖立装饰板的安装结构及转角吊顶层
CN106013732A (zh) * 2016-06-30 2016-10-12 张健 一种安装导线管道底板墙角线
CN106786235A (zh) * 2016-12-14 2017-05-31 浙江亚厦装饰股份有限公司 一种线管或线槽卡扣件及安装方法

Also Published As

Publication number Publication date
CN112154241A (zh) 2020-12-29

Similar Documents

Publication Publication Date Title
WO2019218200A1 (fr) Système de plafond suspendu ayant un câble à haute tension installé dans celui-ci
WO2019218201A1 (fr) Système de plafond suspendu dans lequel est installé un tuyau d'eau
WO2019218229A1 (fr) Procédé de construction d'un système de plafond suspendu
WO2019218236A1 (fr) Procédé de construction de système de plafond suspendu
WO2019218177A1 (fr) Procédé de construction pour maison ayant un tuyau et un câble séparés de la structure principale
WO2019218208A1 (fr) Plafond suspendu
WO2019218170A1 (fr) Procédé de construction de système de plafond suspendu
WO2019218238A1 (fr) Système de plafond suspendu ayant un tuyau d'eau et câble haute tension installé à l'intérieur de ce dernier
WO2019218226A1 (fr) Système de plafond suspendu ayant une conduite d'eau et un câble haute tension installés à l'intérieur de ce dernier
WO2019218227A1 (fr) Système de plafond suspendu dans lequel sont installés un tuyau d'eau et un câble à basse tension
WO2019218220A1 (fr) Plafond suspendu
WO2019218253A1 (fr) Système de plafond suspendu ayant une conduite d'eau et un câble électrique séparés
WO2019218210A1 (fr) Système de plafond suspendu présentant un tuyau d'eau et un câble basse tension installé à l'intérieur de ce dernier
WO2019218184A1 (fr) Système de plafond suspendu présentant un câble basse tension installé en son sein
WO2019218212A1 (fr) Système de plafond suspendu ayant un tuyau d'eau séparé et un câble électrique
WO2019218209A1 (fr) Système de plafond suspendu à l'intérieur duquel un tuyau d'eau et un câble haute tension sont installés
WO2019218228A1 (fr) Système de plafond suspendu présentant des câbles haute tension et basse tension installés en son sein
WO2019218182A1 (fr) Système de plafond suspendu au sein duquel est installé un câble à haute tension
WO2019218183A1 (fr) Système de plafond suspendu à l'intérieur duquel un tuyau d'eau est installé
WO2019218211A1 (fr) Système de plafond suspendu ayant des câbles haute tension et basse tension installés dans celui-ci
WO2019218245A1 (fr) Système mural décoratif équippé d'une conduite d'eau et d'un câble haute tension
WO2019218233A1 (fr) Procédé de construction destiné à une maison ayant une conduite d'eau séparée de la structure principale
WO2019218250A1 (fr) Système mural décoratif dans lequel un tuyau d'eau et un fil basse tension sont montés
WO2019218255A1 (fr) Système mural décoratif ayant des composants électriques et des composants de plomberie séparés
WO2019218179A1 (fr) Procédé de construction pour maison ayant une conduite d'eau et un câble haute tension séparés de la structure principale

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18918892

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18918892

Country of ref document: EP

Kind code of ref document: A1