WO2018045772A1 - 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统 - Google Patents

基于顶推移动平台进行水上钻孔桩的施工方法及施工系统 Download PDF

Info

Publication number
WO2018045772A1
WO2018045772A1 PCT/CN2017/083957 CN2017083957W WO2018045772A1 WO 2018045772 A1 WO2018045772 A1 WO 2018045772A1 CN 2017083957 W CN2017083957 W CN 2017083957W WO 2018045772 A1 WO2018045772 A1 WO 2018045772A1
Authority
WO
WIPO (PCT)
Prior art keywords
platform
construction
steel casing
pile
positioning device
Prior art date
Application number
PCT/CN2017/083957
Other languages
English (en)
French (fr)
Inventor
张鸿
汪文霞
翟世鸿
谢道平
郭强
薛志武
张晓平
刘益平
张梦元
周维
江群龙
李曾曾
许超斌
Original Assignee
中交第二航务工程局有限公司
中交武汉港湾工程设计研究院有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中交第二航务工程局有限公司, 中交武汉港湾工程设计研究院有限公司 filed Critical 中交第二航务工程局有限公司
Publication of WO2018045772A1 publication Critical patent/WO2018045772A1/zh
Priority to IL260791A priority Critical patent/IL260791B/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/40Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles

Definitions

  • the invention belongs to the technical field of water-drilled pile construction, and specifically relates to a construction method and a construction system for water-bored piles based on a push-pull mobile platform.
  • the construction technology of water-drilled piles is routinely constructed using a self-elevating platform or a fixed working platform.
  • the self-elevating platform can adapt to piling operations in different water depths and wave environments, but it is expensive, requires professional operation, and is affected by wind and waves. It takes a long time to move and locate, and is greatly affected by the sea environment. When the position is changed, the positioning accuracy is not high, and the work efficiency is low.
  • the positioning accuracy is high, and it is very convenient to perform position conversion within the platform range, but the large-area fixed platform erecting cost High, narrow application range, only piling work within the platform range, and poor environmental adaptability, generally only used in inland rivers and lakes environment, can not set up platforms in harsh environments such as the open sea, and has a greater impact on the environment.
  • the object of the present invention is to solve the deficiencies of the above background art, and provide a construction method and a construction system for water-bored piles based on a push-pull mobile platform for rapid positioning and rapid drilling on water.
  • the construction method of the water-drilled pile based on the push-pull mobile platform designed by the present invention is based on the N-wheeled steel casing, and N is a natural number greater than or equal to 3, and the removal has been applied.
  • a pile top pushing positioning device is installed on the top of the steel casing pile which has been applied, and then the construction platform is built on the pile top pushing positioning device; the crawler belt on the construction platform is utilized.
  • the hanging and guide frame are applied with N+1 wheel steel casing, and the pile top pushing positioning device is installed on the top of the N+1 wheel steel casing pile.
  • the first wheel steel is completed by the rotary drilling rig on the construction platform.
  • construction method includes the following steps:
  • N is a natural number greater than or equal to 3;
  • the construction platform includes a load bearing platform supported on the top of the pile top pushing positioning device, a working platform laid on the carrying platform, and a guiding frame disposed at the front end of the working platform;
  • step 2) using the crawler crane and guide frame on the working platform to apply N+2 wheel steel casing, and at the same time, use the rotary drilling rig on the working platform to complete the drilling of the second round steel casing.
  • the second round of steel casings that have completed the drilling construction is completed by the crawler crane;
  • step 3 install the pile top pushing and positioning device removed from the second round steel casing on the top of the N+2 wheel steel casing pile, and the three directions of the pile top pushing positioning device
  • the jack pushes the load platform off the support locking device of the pile top pushing and positioning device and pushes the construction platform horizontally to the N+2 wheel steel casing, and locks the construction platform to the fourth wheel steel casing to N+2 wheel
  • the pile top pushing positioning device on the third wheel steel casing is removed and placed on the platform; continue to repeat steps 2) and 3) until all the bore pile construction is completed.
  • construction platform further includes an operation platform located below the carrying platform and hanging on the left and right sides of the carrying platform.
  • pile top positioning seats of the adjacent pile top pushing positioning devices are connected by an adjustable link mechanism.
  • the loading platform of the construction platform comprises a plurality of main longitudinal beams arranged in parallel, a plurality of beams arranged perpendicular to the main longitudinal beams, and cantilever beams distributed outside the main longitudinal beams, the cantilever beams being fixed on the beams The end.
  • the construction platform includes a load platform supported on the top of the pile top pushing positioning device, a work platform laid on the load platform, and a guide frame disposed at the front end of the work platform and corresponding to the pile position.
  • construction platform further includes an operation platform located below the carrying platform and hanging on the left and right sides of the carrying platform.
  • pile top positioning seats of the adjacent pile top pushing positioning devices are connected by an adjustable link mechanism.
  • the loading platform of the construction platform comprises a plurality of main longitudinal beams arranged in parallel, a plurality of beams arranged perpendicular to the main longitudinal beams, and cantilever beams distributed outside the main longitudinal beams, the cantilever beams being fixed on the beams The end.
  • the equipment on the platform is in a stable environment during construction, and the accuracy of the pile construction and the bored pile construction is ensured, and the construction method of the invention is not Wind and wave effects, suitable for use in various waters;
  • Pushing and positioning device through the top of the pile can easily push the platform to walk.
  • the adjustment and movement process of the platform is extremely simple and convenient. All the bored piles can be completed without any other equipment by walking in the forward direction;
  • the construction method and construction system of the water-drilled pile based on the push-pull mobile platform of the invention has the advantages of simple structure and convenient operation, and the use of the steel casing which has been applied as the pile foundation can greatly improve the stability of the construction system. To ensure the accuracy of the construction of bored piles, and the construction process is simpler and has great promotion value.
  • FIG. 1 is a top plan view of a construction system for a method for constructing a water-drilled pile based on a push-pull mobile platform according to the present invention
  • FIG. 2 is a schematic view showing the installation structure of a crawler crane, a rotary drilling rig and a guide frame according to the present invention
  • Figure 3 is a front elevational view showing the structure of the pile top pushing and positioning device of Figure 2;
  • Figure 4 is a side elevational view of Figure 3;
  • Figure 5 is a top plan view of the bearing platform structure of Figure 2;
  • Figure 6 is a front elevational view showing the structure of the guide frame of Figure 2;
  • FIG. 7 to 10 are schematic views showing the flow of the construction method of the embodiment.
  • the pile top pushing positioning device 100 in which: the pile top positioning seat 101, the lifting adjustment device 102, the supporting locking device 103, the three-way jack 104, the adjustable link mechanism 105, the rocker arm plate 106
  • the carrying platform 200 in which: main longitudinal beam 201, cross member 202, cantilever beam 203
  • work platform 300 in which: main longitudinal beam 201, cross member 202, cantilever beam 203
  • guide frame 400 where: large wheel frame guide rail 401, slider 402, large wheel frame guide frame body 403
  • operating platform 500 steel casing 600.
  • the construction method of the water-drilled pile based on the push-up mobile platform designed by the present invention is a steel casing 600 that has been applied in the N-round (the N-wheel has been applied to complete the steel casing) Mainly using the piling ship or other platform structure to arrange, or relying on the shore foundation for the pile foundation) loading construction system, the construction system includes the top of the pile top installed on the top of the 600 steel piles that have been applied The position device 100 (removing the first round steel casing that has been applied, the first round steel casing directly performing the bored pile construction) and the construction platform built on the pile top pushing and positioning device 100, where N is greater than And is equal to the natural number of 3.
  • the principle is: after removing the first round steel casing 600 that has been applied, the pile top pushing positioning device 100 is installed on the top of the steel casing 600 which has been applied, and then the positioning device 100 is pushed on the pile top. Constructing a construction platform; using the crawler crane 700 and the guide frame 400 on the construction platform to apply the N+1 wheel steel casing 600, and installing the pile top pushing positioning device 100 on the top of the N+1 wheel steel casing 600, At the same time, the drilling of the first round of steel casing 600 is completed by using the rotary drilling rig 800 on the construction platform. After the N+1 wheel steel casing 600 is applied, the crawler crane 700 is used to complete the first drilling construction.
  • the wheel steel casing 600 completes the construction of the bored pile; then, the pile top pushing and positioning device 100 is used to push the construction platform horizontally to the N+1 steel casing 600 and lock the construction platform, and the pile top of the second round steel casing is removed. Pushing the positioning device 100 again completes the application of the N+2 wheel steel casing 600 and the drilling pile construction of the second wheel steel casing 600 until the construction of all the bored piles is completed.
  • the construction platform includes a load platform 200 supported on the top of the pile top pushing and positioning device 100, a work platform 300 laid on the load platform 200, an operation platform 500 located under the load platform 200 and hung on the left and right sides of the load platform 200, and a setting A guide frame 400 at the front end of the work platform 300.
  • the structure of the pile top pushing and positioning device 100 is disclosed in the patent number "201510853400.1", which is a pile top pushing and positioning device, as shown in FIG. 3 and FIG. 4, including a pile top positioning seat 101 and a lifting adjustment device. 102.
  • Supporting locking device 103 including support frame, rocker card and locking device
  • three-way jack 104 The pile top positioning seat 101 is installed on the top of the steel casing 600 and is limited to and supported by the steel casing 600.
  • the lower part of the lifting adjustment device 102 is connected to the pile top positioning seat 101, and the upper part of the lifting adjustment device 102 is supported and locked.
  • the device 103 is connected such that the elevation of the top surface of the supporting locking device 103 is adjusted by the lifting adjustment device 102; the three-way jack 104 is placed on the supporting locking device 103, and the three-way jack 104 realizes the longitudinal movement, the vertical lifting and the lateral correction.
  • the bearing platform 200 supports the top surface of the rocker arm on both sides of the supporting locking device 103.
  • the rocker card board 106 is removed, and the three-way jack 104 lifts the loading platform 200 out of the support.
  • the rocker arm of the locking device 103 is moved forward, and when the offset occurs, the three-way jack 104 pushes the lateral displacement of the bearing platform 200.
  • the load bearing platform 200 includes a plurality of main longitudinal beams 201 arranged in parallel, a plurality of transverse beams 202 arranged perpendicular to the main longitudinal beams 201, and cantilever beams 203 distributed outside the main longitudinal beams 201.
  • the cantilever beams 203 are fixed at The end of the beam 202; the main longitudinal beam 201 is arranged longitudinally according to the distance of the steel casing 600, and the span thereof is not less than two steel casings 600, and the beam 202 is horizontally arranged according to the working area required for the lifting equipment.
  • the cantilever beam 203 is disposed outside the outermost main longitudinal beam 201 in accordance with the space required for the auxiliary equipment.
  • the operation platform 500 is hung on both sides of the main longitudinal beam 201 to meet the space requirement for the personnel to reach the pile top pushing positioning device 100 and the transportation adjustable linkage mechanism 105.
  • the working platform 300 is disposed on the carrying platform 200, and the space of the working platform 300 not only satisfies the installation of the guiding frame 400 and the piling construction of the front wheel steel casing 600, but also meets the drilling and reinforcing cage of the rear wheel steel casing 600. Construction of drilled piles such as decentralization and formwork hoisting.
  • the guiding frame 400 is arranged corresponding to the position of the pile position to cover the construction working surface of the whole wheel steel casing 600 at the front of the working platform 300.
  • the large wheel frame guide frame includes a large wheel frame guide frame body 403, a large wheel frame guide rail 401, and a slider 402 disposed on the large wheel frame guide rail 401.
  • the large wheel frame guide frame body The 403 can be moved and positioned along the large wheel frame guiding track 401, and the large wheel frame guiding frame body 401 is opened to feed the pile when the steel casing 600 is applied.
  • the pile top positioning seats 101 of the adjacent two pile top pushing positioning devices 100 are connected by an adjustable link mechanism 105, and the adjustable length adjustable link mechanism 105 adopts two-way adjustment.
  • the lead screw connects all the installed pile top pushing and positioning devices 100 together.
  • the height of the pile top pushing and positioning device 100 is adjusted on the ground, and the top of the steel casing 600 has been installed on the N-1 wheel (ie, the first wheel steel casing is removed)
  • the pile top pushing positioning device 100, N is a natural number greater than and equal to 3; then the supporting platform 200 is supported on the top end of the pile top pushing positioning device 100, the working platform 300 is laid on the carrying platform 200, and the operating platform 500 is hung on the bearing
  • the guiding frame 400 is disposed at the front end of the working platform 300 and corresponding to the position of the pile position. After the construction platform is installed in position, the loading platform 200 is locked by the locking device supporting the locking device 103;
  • the N+1 steel casing 600 is applied by the crawler crane 700 and the guide frame 400 on the work platform 300, and the drilling of the first wheel steel casing 600 is completed by the rotary drilling rig 800 on the working platform 300.
  • the crawler crane 700 travels to the middle of the working platform 300, and the crawler pile is completed by the crawler crane 700 for the first round steel casing 600 that has completed the drilling construction;
  • the first round of steel casing 600 completes the construction of the bored pile, and the pile top pushing and positioning device 100 is installed on the top of each of the steel guards 600 of the N+1 wheel corresponding to the main longitudinal beam 201.
  • Pile top push The three-way jack 104 of the positioning device 100 lifts the load-bearing platform 200 from the rocker arm of the support locking device 103 and pushes the entire construction platform horizontally to the N+1 wheel steel casing 600, and the three-way jack 104 descends, and the construction platform Locked on the rocker arm of the support locking device 103 of the third round steel casing 600 to the N+1 wheel steel casing 600, and locked by the rocker chuck 106, when the offset occurs, the three-way jack 104 can be pushed The entire construction platform is laterally corrected, and after the platform is pushed into position, the pile top pushing positioning device 100 on each steel casing 600 of the second wheel is removed by the operation platform 500;
  • step 2) is repeated, and the N+2 wheel steel casing 600 is applied by the crawler crane 700 and the guide frame 400 on the work platform 300, and at the same time, the rotary drilling rig on the working platform 300 is utilized. 800 completes the drilling of the second round of steel casing 600.
  • the crawler pile is completed by using the crawler crane 700 for the second round steel casing 600 that has completed the drilling construction. ;
  • step 3 install the pile top pushing and positioning device removed from the second wheel steel casing on the top of each steel casing 600 corresponding to the N+2 wheel of the main longitudinal beam 201 100.
  • the three-way jack 104 of the pile top pushing and positioning device 100 lifts the load platform 200 from the rocker arm of the support locking device 103 of the pile top pushing positioning device 100 and pushes the entire construction platform horizontally to the N+2 wheel.
  • the steel casing 600 locks the construction platform on the pile top pushing and positioning device 100 of the fourth wheel steel casing 600 to the N+2 wheel steel casing 600, and removes the third wheel of each steel casing 600 by means of the operating platform 500.
  • the upper pile top pushes the positioning device 100; the steps 2) and 3) are continued until all the bore pile construction is completed.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

一种基于顶推移动平台进行水上钻孔桩的施工方法及施工系统,将N轮已施打完成的钢护筒(600)作为基础,去除已施打完成的第一轮钢护筒(600)后在已施打完成的钢护筒(600)桩顶上安装有桩顶顶推定位装置(100),然后再在桩顶顶推定位装置(100)搭建施工平台;施打N+1轮钢护筒,同时,完成第一轮钢护筒(600)的钻孔桩施工;然后利用桩顶顶推定位装置(100)推动施工平台水平前移至N+1钢护筒(600)并锁定施工平台,再次完成N+2轮钢护筒(600)的施打及对第二轮钢护筒(600)的钻孔桩施工,直至完成所有钻孔桩的施工;该结构简单,操作方便,使用已经施打完成的钢护筒(600)作为沉桩基础能够极大程度的提高施工系统的稳定性,保证钻孔桩施工的精确,且施工工序更为简单。

Description

基于顶推移动平台进行水上钻孔桩的施工方法及施工系统 技术领域
本发明属于水上钻孔桩施工技术领域,具体地指一种基于顶推移动平台进行水上钻孔桩的施工方法及施工系统。
背景技术
水上钻孔桩施工技术常规采用自升式平台或者搭设的固定作业平台作为基础进行施工。自升式平台作为专用设备,可以适应不同水深和波浪环境下的打桩作业,但是造价高昂,需要专业人员进行操作,且受风浪影响大,移动和定位耗时长,受海况环境影响大,每次位置转换时定位精度不高,工效较低;以搭设的固定作业平台作为基础进行钻孔桩施工时,定位精度高,在平台范围内进行位置转换时非常方便,但是大面积的固定平台搭设成本高,适用范围窄,仅能进行平台范围内的打桩作业,且环境适应性差,一般仅用于内河和湖泊环境,无法在外海等恶劣环境搭设平台,并对环境也有较大影响。
发明内容
本发明的目的就是要解决上述背景技术的不足,提供一种水上快速定位且快速钻孔的基于顶推移动平台进行水上钻孔桩的施工方法及施工系统。
为实现上述目的,本发明所设计的基于顶推移动平台进行水上钻孔桩的施工方法,将N轮已施打完成的钢护筒作为基础,N为大于且等于3的自然数,去除已施打完成的第一轮钢护筒后在已施打完成的钢护筒桩顶上安装有桩顶顶推定位装置,然后再在桩顶顶推定位装置搭建施工平台;利用施工平台上的履带吊和导向架施打N+1轮钢护筒,并在N+1轮的钢护筒桩顶上安装桩顶顶推定位装置,同时,利用施工平台上的旋挖钻机完成第一轮钢护筒的钻孔施工,N+1钢护筒施打完成后,利用履带吊对已完成钻孔施工的第一轮钢护筒完成钻孔桩的施工;然后利用桩顶顶推定位装置推动施工平台水平前 移至N+1钢护筒并锁定施工平台,再次完成N+2轮钢护筒的施打及对第二轮钢护筒的钻孔桩施工,直至完成所有钻孔桩的施工。
进一步地,所述施工方法包括如下步骤:
1)去除已施打完成的第一轮钢护筒后在已施打完成的钢护筒桩顶上安装桩顶顶推定位装置,然后再在桩顶顶推定位装置搭建施工平台,N为大于且等于3的自然数;所述施工平台包括支撑在桩顶顶推定位装置顶端的承载平台、铺设在承载平台上的作业平台及设置在作业平台前端的导向架;
2)利用作业平台上的履带吊和导向架施打N+1钢护筒,同时,利用作业平台上的旋挖钻机完成第一轮钢护筒的钻孔施工,N+1轮钢护筒施打完成后,利用履带吊对已完成钻孔施工的第一轮钢护筒完成钻孔桩的施工;
3)在施打完成的N+1轮钢护筒桩顶上安装桩顶顶推定位装置,桩顶顶推定位装置的三向千斤顶将承载平台顶起脱离桩顶顶推定位装置的支撑锁紧装置并推动施工平台水平前移至N+1轮钢护筒,将施工平台锁定在第三轮钢护筒至N+1轮钢护筒的桩顶顶推定位装置上,拆除第二轮钢护筒上的桩顶顶推定位装置放置在平台上;
4)然后重复步骤2),利用作业平台上的履带吊和导向架施打N+2轮钢护筒,同时,利用作业平台上的旋挖钻机完成第二轮钢护筒的钻孔施工,N+2钢护筒施打完成后,利用履带吊对已完成钻孔施工的第二轮钢护筒完成钻孔桩的施工;
5)然后重复步骤3),在施打完成的N+2轮钢护筒桩顶上安装从第二轮钢护筒拆下的桩顶顶推定位装置,桩顶顶推定位装置的三向千斤顶将承载平台顶起脱离桩顶顶推定位装置的支撑锁紧装置并推动施工平台水平前移至N+2轮钢护筒,将施工平台锁定在第四轮钢护筒至N+2轮钢护筒的桩顶顶推定位装置上,拆除第三轮钢护筒上的桩顶顶推定位装置放置在平台上;继续重复步骤2)和步骤3)直至完成所有的钻孔桩施工。
进一步地,所述施工平台还包括位于所述承载平台下方且挂在承载平台左右两侧的操作平台。
进一步地,两两相邻的所述桩顶顶推定位装置的桩顶定位座之间通过可调连杆机构相连。
进一步地,所述施工平台的承载平台包括多根平行布置的主纵梁、与主纵梁垂直布置的多根横梁及分布在主纵梁外侧的悬臂梁,所述悬臂梁固定在所述横梁的端部。
一种如上述基于顶推移动平台进行水上钻孔桩施工方法的施工系统,包括安装在已施打完成的钢护筒桩顶上的桩顶顶推定位装置及搭建在桩顶顶推定位装置上的施工平台,所述施工平台包括支撑在桩顶顶推定位装置顶端的承载平台、铺设在承载平台上的作业平台及设置在作业平台前端且与桩位对应位置的导向架。
进一步地,所述施工平台还包括位于所述承载平台下方且挂在承载平台左右两侧的操作平台。
进一步地,两两相邻的所述桩顶顶推定位装置的桩顶定位座之间通过可调连杆机构相连。
进一步地,所述施工平台的承载平台包括多根平行布置的主纵梁、与主纵梁垂直布置的多根横梁及分布在主纵梁外侧的悬臂梁,所述悬臂梁固定在所述横梁的端部。
本发明的优点如下:
1、通过利用已施打完成的钢护筒作为平台基础保证了平台上的设备在施工时处于稳定的环境,保证了沉桩施工和钻孔桩施工的精确性,本发明的施工方法不受风浪影响,适合应用于各种水域;
2、通过使用施打完成的钢护筒作为平台基础,避免了需要施打辅助桩,直接利用施打完成的钢护筒节省了工序,降低了施工的难度,提高了钻孔桩施工的效率;
3、通过在钢护筒上架设施工平台,避免了投入新的设备进行平台的搭建,平台的施工过程简单方便,充分利用用了已施打完成的钢护筒,工程投入量少;
4、通过桩顶顶推定位装置能够方便的推动平台行走,平台的调节移动过程极为简单方便,通过顺向行走无需引入其他设备就可以完成所有钻孔桩的施工;
5、通过在两两相邻的桩顶顶推定位装置的桩顶定位座之间通过可调连杆 机构相连,提高了钢护筒之间的稳定性,减少了施工工序。
本发明的基于顶推移动平台进行水上钻孔桩的施工方法及施工系统,结构简单,操作方便,使用已经施打完成的钢护筒作为沉桩基础能够极大程度的提高施工系统的稳定性,保证钻孔桩施工的精确,且施工工序更为简单,具有极大的推广价值。
附图说明
图1为本发明基于顶推移动平台进行水上钻孔桩施工方法的施工系统俯视示意图;
图2为本发明履带吊、旋挖钻机与导向架的安装结构示意图;
图3为图2中桩顶顶推定位装置结构主视示意图;
图4为图3的侧视示意图;
图5为图2中承载平台结构俯视示意图;
图6为图2中导向架结构主视示意图;
图7~图10为实施例施工方法流程示意图。
其中:桩顶顶推定位装置100(其中:桩顶定位座101、升降调节装置102、支撑锁紧装置103、三向千斤顶104、可调连杆机构105、摇臂卡板106)、承载平台200(其中:主纵梁201、横梁202、悬臂梁203)、作业平台300、导向架400(其中:大轮架导向轨道401、滑块402、大轮架导向架体403)、操作平台500、钢护筒600。
具体实施方式
下面结合附图和具体实施例对本发明作进一步的详细说明。
如图1、2所示,本发明所设计的基于顶推移动平台进行水上钻孔桩的施工方法是在N轮已施打完成的钢护筒600(N轮已施打完成的钢护筒主要是使用打桩船或是其他的平台结构进行布置,也可以依托岸基进行沉桩)上装载施工系统,施工系统包括安装在已施打完成的钢护筒600桩顶上的桩顶顶推定位装置100(去除已施打完成的第一轮钢护筒,第一轮钢护筒直接进行钻孔桩施工)及搭建在桩顶顶推定位装置100上的施工平台,此处N为大于 且等于3的自然数。原理为:去除已施打完成的第一轮钢护筒600后在已施打完成的钢护筒600桩顶上安装有桩顶顶推定位装置100,然后再在桩顶顶推定位装置100搭建施工平台;利用施工平台上的履带吊700和导向架400施打N+1轮钢护筒600,并在N+1轮的钢护筒600桩顶上安装桩顶顶推定位装置100,同时,利用施工平台上的旋挖钻机800完成第一轮钢护筒600的钻孔施工,N+1轮钢护筒600施打完成后,利用履带吊700对已完成钻孔施工的第一轮钢护筒600完成钻孔桩的施工;然后利用桩顶顶推定位装置100推动施工平台水平前移至N+1钢护筒600并锁定施工平台,拆除第二轮钢护筒的桩顶顶推定位装置100,再次完成N+2轮钢护筒600的施打及对第二轮钢护筒600的钻孔桩施工,直至完成所有钻孔桩的施工。
该施工平台包括支撑在桩顶顶推定位装置100顶端的承载平台200、铺设在承载平台200上的作业平台300、位于承载平台200下方且挂在承载平台200左右两侧的操作平台500及设置在作业平台300前端的导向架400。
本实施例中,桩顶顶推定位装置100的结构见专利号“201510853400.1”公开的一种桩顶顶推定位装置,结合图3、图4所示,包括桩顶定位座101、升降调节装置102、支撑锁紧装置103(即包括支撑架、摇臂卡板及锁紧装置)及三向千斤顶104。桩顶定位座101安装于钢护筒600桩顶并与钢护筒600起限位和承载作用;升降调节装置102的下部与桩顶定位座101相连,升降调节装置102的上部与支撑锁紧装置103相连,使得支撑锁紧装置103顶面的标高由升降调节装置102调整;三向千斤顶104置于支撑锁紧装置103上,三向千斤顶104实现纵移、竖向顶升及横向纠偏,具体结构请参见公开文献;承载平台200支撑在支撑锁紧装置103两侧摇臂顶面,承载平台200前移时,将摇臂卡板106拆除,三向千斤顶104顶升承载平台200脱离支撑锁紧装置103的摇臂后前移,发生偏移时,三向千斤顶104推动承载平台200横向纠偏。
如图5所示,承载平台200包括多根平行布置的主纵梁201、与主纵梁201垂直布置的多根横梁202及分布在主纵梁201外侧的悬臂梁203,悬臂梁203固定在横梁202的端部;主纵梁201按钢护筒600间距沿纵向布置,其跨度不小于两根钢护筒600,横梁202按起重设备所需工作区域横向布置, 悬臂梁203按辅助设备所需空间布置在最边上主纵梁201的外侧。同时,操作平台500挂在主纵梁201的两侧,满足人员到达桩顶顶推定位装置100和运输可调连杆机构105的空间需要。
作业平台300布置于承载平台200上,其作业平台300的空间不仅要满足导向架400的安装及前轮钢护筒600的打桩施工,还要满足后轮钢护筒600的钻孔及钢筋笼下放、模板吊装等钻孔桩的施工。
导向架400与桩位位置对应布置,以覆盖作业平台300前部整轮钢护筒600施工作业面,导向架400的结构见专利号“201510856316.5”公开的一种桩顶支撑步履式移动打桩平台中的大轮架导向架,结合图6所示,包括大轮架导向架体403、大轮架导向轨道401及设置在大轮架导向轨道401上的滑块402,大轮架导向架体403可沿大轮架导向轨道401移动和定位,大轮架导向架体401的开合适应钢护筒600施打时的喂桩。
另外,本实施例中两两相邻的桩顶顶推定位装置100的桩顶定位座101之间通过可调连杆机构105相连,长度可调的可调连杆机构105采用的是双向调节丝杆,使所有已安装的桩顶顶推定位装置100连成一体。
施工方法具体步骤如下:结合图7~图10所示,
1)根据现场测量数据,在地面调整好桩顶顶推定位装置100的高度,在N-1轮(即去除第一轮钢护筒)已施打完成的钢护筒600桩顶上安装有桩顶顶推定位装置100,N为大于且等于3的自然数;然后将承载平台200支撑在桩顶顶推定位装置100的顶端,作业平台300铺设在承载平台200上,操作平台500挂在承载平台200的主纵梁201两侧,导向架400设置在作业平台300的前端且与桩位位置对应布置,施工平台安装到位后,用支撑锁紧装置103的锁紧装置将承载平台200锁定;
2)利用作业平台300上的履带吊700和导向架400施打N+1钢护筒600,同时,利用作业平台300上的旋挖钻机800完成第一轮钢护筒600的钻孔施工,N+1轮钢护筒600施打完成后,履带吊700行走至作业平台300的中部,利用履带吊700对已完成钻孔施工的第一轮钢护筒600完成钻孔桩的施工;
3)第一轮钢护筒600完成钻孔桩的施工,在对应主纵梁201的已施打完成的N+1轮每个钢护筒600桩顶上均安装桩顶顶推定位装置100,桩顶顶推 定位装置100的三向千斤顶104将承载平台200顶起脱离支撑锁紧装置103的摇臂并推动整个施工平台水平前移至N+1轮钢护筒600,三向千斤顶104下降,将施工平台锁定在第三轮钢护筒600至N+1轮钢护筒600的支撑锁紧装置103的摇臂上,并用摇臂卡板106上并锁定,发生偏移时,三向千斤顶104可推动整个施工平台进行横向纠偏,平台顶推到位后,借助操作平台500拆除第二轮每个钢护筒600上的桩顶顶推定位装置100,;
4)施工平台同步移动到位后,然后重复步骤2),利用作业平台300上的履带吊700和导向架400施打N+2轮钢护筒600,同时,利用作业平台300上的旋挖钻机800完成第二轮钢护筒600的钻孔施工,N+2钢护筒600施打完成后,利用履带吊700对已完成钻孔施工的第二轮钢护筒600完成钻孔桩的施工;
5)然后重复步骤3),在对应主纵梁201的已施打完成的N+2轮每个钢护筒600桩顶上安装从第二轮钢护筒拆下的桩顶顶推定位装置100,桩顶顶推定位装置100的三向千斤顶104将承载平台200顶起脱离桩顶顶推定位装置100的支撑锁紧装置103的摇臂并推动整个施工平台水平前移至N+2轮钢护筒600,将施工平台锁定在第四轮钢护筒600至N+2轮钢护筒600的桩顶顶推定位装置100上,借助操作平台500拆除第三轮每个钢护筒600上的桩顶顶推定位装置100;继续重复步骤2)和步骤3)直至完成所有的钻孔桩施工。
以上显示和描述了本发明的基本原理、主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的只是说明本发明的原理,在不脱离本发明精神和范围的前提下本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等同物界定。

Claims (9)

  1. 一种基于顶推移动平台进行水上钻孔桩的施工方法,将N轮已施打完成的钢护筒(600)作为基础,N为大于且等于3的自然数,其特征在于:去除已施打完成的第一轮钢护筒(600)后在已施打完成的钢护筒桩(600)顶上安装有桩顶顶推定位装置(100),然后再在桩顶顶推定位装置(600)搭建施工平台;利用施工平台上的履带吊(700)和导向架(400)施打N+1轮钢护筒(600),并在N+1轮的每个钢护筒(600)桩顶上安装桩顶顶推定位装置(100),同时,利用施工平台上的旋挖钻机(800)完成第一轮钢护筒(600)的钻孔施工,N+1钢护筒(600)施打完成后,利用履带吊(700)对已完成钻孔施工的第一轮钢护筒(600)完成钻孔桩的施工;然后利用桩顶顶推定位装置(100)推动施工平台水平前移至N+1钢护筒(600)并锁定施工平台,再次完成N+2轮钢护筒(600)的施打及对第二轮钢护筒(600)的钻孔桩施工,直至完成所有钻孔桩的施工。
  2. 根据权利要求1基于顶推移动平台进行水上钻孔桩的施工方法,其特征在于:所述施工方法包括如下步骤:
    1)去除已施打完成的第一轮钢护筒(600)后在已施打完成的钢护筒(600)桩顶上安装有桩顶顶推定位装置(100),然后再在桩顶顶推定位装置(600)搭建施工平台,N为大于且等于3的自然数;所述施工平台包括支撑在桩顶顶推定位装置(100)顶端的承载平台(200)、铺设在承载平台(200)上的作业平台(300)及设置在作业平台(300)前端的导向架(400);
    2)利用作业平台(300)上的履带吊(700)和导向架(400)施打N+1钢护筒(600),同时,利用作业平台(300)上的旋挖钻机(800)完成第一轮钢护筒(600)的钻孔施工,N+1轮钢护筒(600)施打完成后,利用履带吊(700)对已完成钻孔施工的第一轮钢护筒(600)完成钻孔桩的施工;
    3)在施打完成的N+1轮每个钢护筒(100)桩顶上安装桩顶顶推定位装置(100),桩顶顶推定位装置(100)的三向千斤顶(104)将承载平台(200)顶起脱离桩顶顶推定位装置(100)的支撑锁紧装置(103)并推动施工平台水平前移至N+1轮钢护筒(600),将施工平台锁定在第三轮钢护筒(600)至N+1轮钢护筒(600)的桩顶顶推定位装置(100)上,拆除第二轮每个钢护筒(600) 上的桩顶顶推定位装置(100)放置在平台上;
    4)然后重复步骤2),利用作业平台(300)上的履带吊(700)和导向架(400)施打N+2轮钢护筒(600),同时,利用作业平台(300)上的旋挖钻机(800)完成第二轮钢护筒(600)的钻孔施工,N+2钢护筒施(600)打完成后,利用履带吊(700)对已完成钻孔施工的第二轮钢护筒(600)完成钻孔桩的施工;
    5)然后重复步骤3),在施打完成的N+2轮每个钢护筒(600)桩顶上安装从第二轮钢护筒拆下的桩顶顶推定位装置(100),桩顶顶推定位装置(100)的三向千斤顶(104)将承载平台(200)顶起脱离桩顶顶推定位装置(100)的支撑锁紧装置(103)并推动施工平台水平前移至N+2轮钢护筒(600),将施工平台锁定在第四轮钢护筒(600)至N+2轮钢护筒(600)的桩顶顶推定位装置(100)上,拆除第三轮每个钢护筒(600)上的桩顶顶推定位装置(100)放置在平台上;继续重复步骤2)和步骤3)直至完成所有的钻孔桩施工。
  3. 根据权利要求1或2基于顶推移动平台进行水上钻孔桩的施工方法,其特征在于:所述施工平台还包括位于所述承载平台(200)下方且挂在承载平台(200)左右两侧的操作平台(500)。
  4. 根据权利要求1或2基于顶推移动平台进行水上钻孔桩的施工方法,其特征在于:两两相邻的所述桩顶顶推定位装置(100)的桩顶定位座(101)之间通过可调连杆机构(105)相连。
  5. 根据权利要求1或2基于顶推移动平台进行水上钻孔桩的施工方法,其特征在于:所述施工平台的承载平台(200)包括多根平行布置的主纵梁(201)、与主纵梁(201)垂直布置的多根横梁(202)及分布在主纵梁(201)外侧的悬臂梁(203),所述悬臂梁(203)固定在所述横梁(202)的端部。
  6. 一种如权利要求1或2基于顶推移动平台进行水上钻孔桩施工方法的施工系统,其特征在于:包括安装在已施打完成的钢护筒(600)桩顶上的桩顶顶推定位装置(100)及搭建在桩顶顶推定位装置(100)上的施工平台,所述施工平台包括支撑在桩顶顶推定位装置(100)顶端的承载平台(200)、铺设在承载平台(200)上的作业平台(300)及设置在作业平台(300)前端且与桩位对应位置的导向架(400)。
  7. 根据权利要求6所述基于顶推移动平台进行水上钻孔桩施工方法的施工 系统,其特征在于:所述施工平台还包括位于所述承载平台(200)下方且挂在承载平台(200)左右两侧的操作平台(500)。
  8. 根据权利要求6或7所述基于顶推移动平台进行水上钻孔桩施工方法的施工系统,其特征在于:两两相邻的所述桩顶顶推定位装置(100)的桩顶定位座(101)之间通过可调连杆机构(105)相连。
  9. 根据权利要求6或7所述基于顶推移动平台进行水上钻孔桩施工方法的施工系统,其特征在于:所述施工平台的承载平台(200)包括多根平行布置的主纵梁(201)、与主纵梁(201)垂直布置的多根横梁(202)及分布在主纵梁(201)外侧的悬臂梁(203),所述悬臂梁(203)固定在所述横梁(202)的端部。
PCT/CN2017/083957 2016-09-09 2017-05-11 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统 WO2018045772A1 (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
IL260791A IL260791B (en) 2016-09-09 2018-07-26 Construction method and construction system for overwater bored piles based on incremental launching movement platform

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610812760.1A CN106320332B (zh) 2016-09-09 2016-09-09 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统
CN201610812760.1 2016-09-09

Publications (1)

Publication Number Publication Date
WO2018045772A1 true WO2018045772A1 (zh) 2018-03-15

Family

ID=57786989

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2017/083957 WO2018045772A1 (zh) 2016-09-09 2017-05-11 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统

Country Status (3)

Country Link
CN (1) CN106320332B (zh)
IL (1) IL260791B (zh)
WO (1) WO2018045772A1 (zh)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113136882A (zh) * 2021-04-27 2021-07-20 中交一公局第八工程有限公司 密集桩群深水承台双壁钢吊箱围堰施工工艺
CN113216840A (zh) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 冲击成孔超长钻孔灌注桩及施工方法
CN114000525A (zh) * 2021-11-23 2022-02-01 中国二十二冶集团有限公司 水中系梁施工方法
CN114525787A (zh) * 2022-01-20 2022-05-24 浙江欧佩亚海洋工程有限公司 一种基于万向水平仪和液压推杆的钢护筒定位纠偏装置
CN114562224A (zh) * 2022-01-12 2022-05-31 中交第二航务工程局有限公司 群桩基础泥浆循环净化系统及其施工方法
CN114673144A (zh) * 2022-04-28 2022-06-28 中铁十五局集团有限公司 一种斜基面裸岩上栈桥钢管桩快速植桩工法
CN114753357A (zh) * 2022-04-08 2022-07-15 中铁七局集团有限公司 水中钻孔桩的施工方法
CN114808947A (zh) * 2022-05-31 2022-07-29 保利长大工程有限公司 一种用于桩基开孔的施工平台
CN115362292A (zh) * 2022-07-06 2022-11-18 中交第二航务工程局有限公司 一种高桩码头新型上部结构及其施工装备和施工方法
CN115961626A (zh) * 2022-12-08 2023-04-14 保利长大工程有限公司 一种水下桩基护筒锚固方法
CN116024975A (zh) * 2022-09-07 2023-04-28 中交第四航务工程局有限公司 一种海上深层搅拌桩水转陆施工系统及施工方法
CN116837806A (zh) * 2023-06-12 2023-10-03 中国铁建港航局集团有限公司 一种防撞墩水上平台搭设方法
CN116856408A (zh) * 2023-09-04 2023-10-10 中交第一航务工程局有限公司 适用于深水裸岩区的钢护筒的沉设方法
CN117306534A (zh) * 2023-11-30 2023-12-29 中国海洋大学 一种装配式海工桩基建筑物逆作施工方法

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320332B (zh) * 2016-09-09 2018-08-31 中交第二航务工程局有限公司 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统
CN107653858A (zh) * 2017-08-14 2018-02-02 中交第二航务工程局有限公司 水上自升式的桩顶可移动打桩平台及其施工方法
CN108396744B (zh) * 2018-04-27 2024-03-22 中交武汉港湾工程设计研究院有限公司 一种可移动的钢护筒沉放导向装置的安装结构
CN109113057A (zh) * 2018-09-06 2019-01-01 中交第二航务工程局有限公司 基于桩顶顶推平台的无覆盖层地质条件下嵌岩桩施工方法
CN109208533B (zh) * 2018-09-26 2023-04-25 中交第二航务工程局有限公司 基于桩顶顶推平台的码头一体化施工系统和方法
CN109208595A (zh) * 2018-09-26 2019-01-15 中交第二航务工程局有限公司 一种基于桩顶顶推平台的斜桩施工系统
CN109457700B (zh) * 2018-12-07 2024-02-13 中交第一航务工程局有限公司 桩顶行走式桩基施工平台、其搭设方法及桩基施工方法
CN114808978A (zh) * 2022-03-24 2022-07-29 中建国际建设有限公司 一种具有桩柱导向功能的不落地移动钢平台
CN114808725B (zh) * 2022-05-11 2023-07-07 浙江省二建建设集团有限公司 水上桥墩桩基施工平台

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201857618U (zh) * 2010-11-11 2011-06-08 四川路桥桥梁工程有限责任公司 浮式导向平台和钢护筒支撑钻孔平台深水桩基础
CN103741657A (zh) * 2013-12-27 2014-04-23 中铁大桥局集团第一工程有限公司 大型多功能水上施工平台的施工方法
WO2014113386A2 (en) * 2013-01-21 2014-07-24 Conocophillips Company Jack-up drilling unit with tension legs
CN104594352A (zh) * 2015-01-14 2015-05-06 中铁大桥局集团有限公司 一种稳固结构及基于该稳固结构的钻孔平台施工方法
CN104895056A (zh) * 2015-06-02 2015-09-09 杭州江润科技有限公司 防冲刷大直径钻孔灌注桩施工方法
CN106320332A (zh) * 2016-09-09 2017-01-11 中交第二航务工程局有限公司 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统
CN206070516U (zh) * 2016-09-09 2017-04-05 中交第二航务工程局有限公司 基于顶推移动平台进行水上钻孔桩的施工系统

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2863902Y (zh) * 2005-12-29 2007-01-31 中交第二航务工程局有限公司 钢护筒沉放导向装置
MX2013003989A (es) * 2010-10-12 2013-10-08 Bp Corp North America Inc Montajes submarinos maritimos.
CN203049602U (zh) * 2012-11-23 2013-07-10 浙江大学 一种便于拔桩的海上平台桩腿及安装有该桩腿的安装平台
CN103422782A (zh) * 2013-09-03 2013-12-04 张家港固耐特围栏系统有限公司 一种上梁导向装置
CN105002890B (zh) * 2015-07-15 2017-03-08 杭州江润科技有限公司 一种深水区钻孔灌注桩无损装拆双层钢护筒群结构及施工方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201857618U (zh) * 2010-11-11 2011-06-08 四川路桥桥梁工程有限责任公司 浮式导向平台和钢护筒支撑钻孔平台深水桩基础
WO2014113386A2 (en) * 2013-01-21 2014-07-24 Conocophillips Company Jack-up drilling unit with tension legs
CN103741657A (zh) * 2013-12-27 2014-04-23 中铁大桥局集团第一工程有限公司 大型多功能水上施工平台的施工方法
CN104594352A (zh) * 2015-01-14 2015-05-06 中铁大桥局集团有限公司 一种稳固结构及基于该稳固结构的钻孔平台施工方法
CN104895056A (zh) * 2015-06-02 2015-09-09 杭州江润科技有限公司 防冲刷大直径钻孔灌注桩施工方法
CN106320332A (zh) * 2016-09-09 2017-01-11 中交第二航务工程局有限公司 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统
CN206070516U (zh) * 2016-09-09 2017-04-05 中交第二航务工程局有限公司 基于顶推移动平台进行水上钻孔桩的施工系统

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113136882A (zh) * 2021-04-27 2021-07-20 中交一公局第八工程有限公司 密集桩群深水承台双壁钢吊箱围堰施工工艺
CN113216840B (zh) * 2021-05-18 2023-12-29 浙江交工集团股份有限公司 冲击成孔超长钻孔灌注桩及施工方法
CN113216840A (zh) * 2021-05-18 2021-08-06 浙江交工集团股份有限公司 冲击成孔超长钻孔灌注桩及施工方法
CN114000525A (zh) * 2021-11-23 2022-02-01 中国二十二冶集团有限公司 水中系梁施工方法
CN114000525B (zh) * 2021-11-23 2023-08-22 中国二十二冶集团有限公司 水中系梁施工方法
CN114562224A (zh) * 2022-01-12 2022-05-31 中交第二航务工程局有限公司 群桩基础泥浆循环净化系统及其施工方法
CN114562224B (zh) * 2022-01-12 2023-05-23 中交第二航务工程局有限公司 群桩基础泥浆循环净化系统及其施工方法
CN114525787A (zh) * 2022-01-20 2022-05-24 浙江欧佩亚海洋工程有限公司 一种基于万向水平仪和液压推杆的钢护筒定位纠偏装置
CN114753357A (zh) * 2022-04-08 2022-07-15 中铁七局集团有限公司 水中钻孔桩的施工方法
CN114673144A (zh) * 2022-04-28 2022-06-28 中铁十五局集团有限公司 一种斜基面裸岩上栈桥钢管桩快速植桩工法
WO2023207250A1 (zh) * 2022-04-28 2023-11-02 中铁十五局集团有限公司 一种斜基面裸岩上栈桥钢管桩快速植桩工法
CN114808947A (zh) * 2022-05-31 2022-07-29 保利长大工程有限公司 一种用于桩基开孔的施工平台
CN115362292A (zh) * 2022-07-06 2022-11-18 中交第二航务工程局有限公司 一种高桩码头新型上部结构及其施工装备和施工方法
CN115362292B (zh) * 2022-07-06 2023-08-18 中交第二航务工程局有限公司 一种高桩码头上部结构及其施工装备和施工方法
CN116024975A (zh) * 2022-09-07 2023-04-28 中交第四航务工程局有限公司 一种海上深层搅拌桩水转陆施工系统及施工方法
CN116024975B (zh) * 2022-09-07 2023-09-26 中交第四航务工程局有限公司 一种海上深层搅拌桩水转陆施工系统及施工方法
CN115961626A (zh) * 2022-12-08 2023-04-14 保利长大工程有限公司 一种水下桩基护筒锚固方法
CN116837806A (zh) * 2023-06-12 2023-10-03 中国铁建港航局集团有限公司 一种防撞墩水上平台搭设方法
CN116856408A (zh) * 2023-09-04 2023-10-10 中交第一航务工程局有限公司 适用于深水裸岩区的钢护筒的沉设方法
CN116856408B (zh) * 2023-09-04 2023-11-07 中交第一航务工程局有限公司 适用于深水裸岩区的钢护筒的沉设方法
CN117306534A (zh) * 2023-11-30 2023-12-29 中国海洋大学 一种装配式海工桩基建筑物逆作施工方法
CN117306534B (zh) * 2023-11-30 2024-03-12 中国海洋大学 一种装配式海工桩基建筑物逆作施工方法

Also Published As

Publication number Publication date
CN106320332A (zh) 2017-01-11
CN106320332B (zh) 2018-08-31
IL260791B (en) 2018-12-31

Similar Documents

Publication Publication Date Title
WO2018045772A1 (zh) 基于顶推移动平台进行水上钻孔桩的施工方法及施工系统
KR101230424B1 (ko) 고정형 석유굴착용 플랫폼의 요소를 이송, 설치 및분해하기 위한 구조물과 이러한 구조물을 이용하는 방법
CN104652394B (zh) 一种新型多功能浅海作业平台
WO2018000409A1 (zh) 桩顶支撑步履式移动打桩平台
WO2021179466A1 (zh) 一种用于码头改造的移动式陆上施工平台及方法
US8517637B2 (en) Structure for the transport, installation and dismantling of an oil rig deck and method for using one such structure
CN110206067B (zh) 一种沉管隧道管段浮运沉放位置调节装置及其作业方法
CN101792015B (zh) 一种多功能的拼装式水上移动设备
CN112240025A (zh) 车站基坑工程盖挖施工方法
CN113026563B (zh) 一种悬索桥高低位移梁栈桥吊装钢梁设施及其施工方法
CN101177933B (zh) 桥梁拱肋吊运及支撑支架一体化施工方法及装置
CN112027001B (zh) 自升式海上整体风机安装船
CN206070516U (zh) 基于顶推移动平台进行水上钻孔桩的施工系统
CN109056534A (zh) 一种移动式钻孔灌注桩施工平台及方法
CN202595747U (zh) 用于u形混凝土板桩沉桩的型钢导向架
CN111501756A (zh) 一种抱桩导管架及其施工方法
CN109537466B (zh) 一种钢结构梁悬吊在空中的定位方法
CN110485418A (zh) 应用于深水强浪海域的钢管桩水下打桩方法
US3511057A (en) Erection and construction of multispan bridges and piers
CN108840234B (zh) 一种预制节段用吊装装置及其吊装方法
CN114182710B (zh) 一种风电安装平台桩靴的安装方法
RU89130U1 (ru) Установка для погружения свай
CN111926714A (zh) 钢桁架梁桥的安装方法
CN205999893U (zh) 用于沉桩的装配移动式平台
CN212714942U (zh) 一种抱桩导管架

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 260791

Country of ref document: IL

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17847945

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 17847945

Country of ref document: EP

Kind code of ref document: A1