WO2016120908A1 - 住宅の建築構法 - Google Patents

住宅の建築構法 Download PDF

Info

Publication number
WO2016120908A1
WO2016120908A1 PCT/JP2015/001838 JP2015001838W WO2016120908A1 WO 2016120908 A1 WO2016120908 A1 WO 2016120908A1 JP 2015001838 W JP2015001838 W JP 2015001838W WO 2016120908 A1 WO2016120908 A1 WO 2016120908A1
Authority
WO
WIPO (PCT)
Prior art keywords
floor
panels
wall
manufacturing
site
Prior art date
Application number
PCT/JP2015/001838
Other languages
English (en)
French (fr)
Inventor
成憲 岩澤
和典 西尾
余田 達也
Original Assignee
パナホーム株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by パナホーム株式会社 filed Critical パナホーム株式会社
Publication of WO2016120908A1 publication Critical patent/WO2016120908A1/ja

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Definitions

  • the present invention relates to a building construction method for a house, and more particularly to a building construction method for a house in which the house is constructed using a panel having a reinforced concrete structure.
  • Japanese Patent Publication No. 2000-248614 discloses a method of building a house by manufacturing a number of reinforced concrete panels in advance and using these reinforced concrete panels as bearing walls and floor slabs. Has been.
  • a large number of reinforced concrete panels are cured at a dedicated facility on the manufacturing site until each of them develops the desired strength (strength required as a wall or floor of a house).
  • a large number of reinforced concrete panels that have been cured in a dedicated facility are generally stored in a storage facility, etc., then transported to a construction site and assembled at the construction site.
  • the conventional construction method described above has a problem that it takes a long time from the start of the production of a large number of reinforced concrete panels to the completion of a house on the construction site using these reinforced concrete panels.
  • An object of the present invention is to provide a building construction method that can build a house composed of a plurality of reinforced concrete panels in a short period of time.
  • the residential building construction method according to the present invention includes a manufacturing process, a transporting process, an installation process, and a curing process.
  • the manufacturing process is a process of sequentially manufacturing a plurality of first floor panels having a reinforced concrete structure at a manufacturing site.
  • the transporting step is a step of sequentially transporting the plurality of first floor panels manufactured in the manufacturing process from the manufacturing site to the building site at a stage where a predetermined initial strength is developed.
  • the installation step is a step of sequentially installing the plurality of first floor panels conveyed to the building site on the foundation of the building site to form a first floor part of a house on the foundation.
  • the curing step is a step of curing the plurality of first floor panels installed in the installation step on the foundation until each of them exhibits a predetermined target strength higher than the predetermined initial strength.
  • each of the plurality of first floor panels is a first floor wall panel for forming a wall structure of the first floor portion.
  • the second floor manufacturing process is a process of sequentially manufacturing a plurality of second floor panels having a reinforced concrete structure on the second floor manufacturing site.
  • the transporting process for the second floor sequentially transports the plurality of second floor panels manufactured in the manufacturing process for the second floor from the manufacturing site for the second floor to the construction site at a stage where a predetermined initial strength is expressed. It is a process.
  • the second floor installation step sequentially installs the plurality of second floor panels conveyed to the building site on the plurality of first floor panels that express the predetermined target strength. It is a process of forming the second floor part of the house above.
  • the curing process for the second floor includes the plurality of panels for the second floor installed in the installation process for the second floor until each of them develops a predetermined target strength higher than the predetermined initial strength. It is a process of curing.
  • the second floor installation step is a step of the first floor panel that expresses the predetermined target strength among the plurality of first floor panels constituting the first floor portion. It is preferable that the plurality of second-floor panels are sequentially installed from the top.
  • a part of the period of the curing process and a part of the period of the installation process for the second floor overlap each other.
  • the building construction method for a house according to the present invention may further include a manufacturing process for the second floor, a transporting process for the second floor, an installation process for the second floor, and a curing process for the second floor. preferable.
  • the manufacturing process for the second floor is a process for sequentially manufacturing a plurality of second floor floor panels having a reinforced concrete structure at the manufacturing floor for the second floor.
  • the plurality of second floor panels manufactured in the manufacturing process for the second floor are developed from a manufacturing site for the second floor to the building site in a stage where a predetermined initial strength is expressed. It is the process of conveying sequentially.
  • the plurality of second floor panels transferred to the construction site are sequentially installed on the plurality of first floor panels exhibiting the predetermined target strength, and the first floor Forming a floor structure of the second floor part of the house on the part;
  • the curing process for the second floor the plurality of second floor panels installed in the installation process for the second floor until the first floor expresses a predetermined target strength higher than the predetermined initial strength. It is a process of curing on the part.
  • the installation process for the second floor is a first floor panel that expresses the predetermined target strength among the plurality of first floor panels constituting the first floor portion.
  • the plurality of second floor panels are sequentially installed from the top.
  • a part of the curing process period and a part of the second floor installation process period are provided so as to overlap each other.
  • the building construction method for a house according to the present invention may further include a manufacturing process for the second floor wall, a transporting process for the second floor wall, an installation process for the second floor wall, and a curing process for the second floor wall. preferable.
  • the manufacturing process for the second floor wall is a process of sequentially manufacturing a plurality of second floor wall panels having a reinforced concrete structure at the manufacturing site for the second floor wall.
  • the plurality of second-floor wall panels manufactured in the second-floor wall manufacturing process are transferred from the second-floor wall manufacturing site to the building site in a stage where a predetermined initial strength is expressed. It is the process of conveying sequentially.
  • the installation process for the second-floor wall the plurality of second-floor wall panels conveyed to the building site are sequentially installed on the plurality of second-floor floor panels that express the predetermined target strength.
  • the curing process for the second floor wall includes the floor structure until each of the plurality of second floor wall panels installed in the second floor wall installation process expresses a predetermined target strength higher than the predetermined initial strength. It is a process of curing on.
  • the second floor wall installation step includes the second floor floor panel exhibiting the predetermined target strength among the plurality of second floor panels constituting the floor structure. It is preferable that the plurality of second-floor wall panels are sequentially installed from the top.
  • a part of the curing process for the second floor and a part of the installation process for the second floor may be provided so as to overlap each other. preferable.
  • the house is a continuous house.
  • FIG. It is a figure which shows the flow of the building construction method of Embodiment 1.
  • FIG. It is a figure explaining the timing of each process of the building construction method of Embodiment 1.
  • FIG. It is a figure which shows the relationship between the manufacturing site in the building construction method of Embodiment 1, and a building site. It is a figure which shows schematically the stage which started building the first-floor part of a building with the building construction method of Embodiment 1.
  • FIG. It is a figure which shows roughly the step which formed the 1st floor part of the building with the building construction method of Embodiment 1.
  • FIG. It is a figure which shows roughly the step which formed the wall structure of the 2nd floor part of a building with the building construction method of Embodiment 1.
  • FIG. It is a figure which shows roughly the step which formed the roof structure of the building with the building construction method of Embodiment 1.
  • a panel having a reinforced concrete structure is not cured at a panel manufacturing site until a predetermined target strength is expressed, but is transported to a building site and installed. It is a construction method that realizes residential construction in a short period of time by curing until the desired strength is developed.
  • the building construction method of the present embodiment is a particularly effective construction method in a hot and humid environment.
  • the building construction method of this embodiment is a particularly effective building construction method when building a multi-family house.
  • first floor panels 1, 1... used for building the first floor portion 61 of the multi-family house 6 and the multi-family house 6 are used.
  • a plurality of second-floor panels 2, 2... used for building the second-floor portion 62 are manufactured at a manufacturing site 8 (see FIG. 3) equipped with dedicated equipment.
  • the first floor panels 1, 1... And the second floor panels 2, 2... Manufactured at the manufacturing site 8 are developed at an initial strength that can be transported, using appropriate transport means 7 such as a vehicle, Transport to building site 9.
  • the manufacturing site 8 serves as both a manufacturing site for manufacturing a plurality of first-floor panels 1, 1... And a second-floor manufacturing site for manufacturing a plurality of second-floor panels 2, 2,.
  • the manufacturing site and the manufacturing site for the second floor may be different.
  • the manufacturing site 8 and the building site 9 can be provided adjacent to each other.
  • a crane or the like can be used as the transport means 7 and the first floor panels 1, 1... And the second floor panels 2, 2,.
  • FIG. 1 schematically shows the flow of each process of building the house 6 using the building construction method of the first embodiment.
  • the process S0 of the foundation work is a process of forming the foundation 5 on the building site 9.
  • the house 6 to be built by the building construction method of this embodiment is a multi-family house with 10 buildings, and it takes several weeks to form the foundation 5.
  • the first floor building process S1 for building the first floor portion 61 of the house 6 on the foundation 5 is started from the time when the foundation work process S0 is completed or in parallel with the latter half of the foundation work process S0.
  • the first floor building process S1 includes a manufacturing process S11 for the first floor, a transport process S12 for the first floor, an installation process S13 for the first floor, and a curing process S14 for the first floor.
  • the manufacturing process S11 for the first floor is simply “manufacturing process S11”
  • the transport process S12 for the first floor is simply “transport process S12”
  • the installation process S13 for the first floor is simply “installation process S13”
  • This curing step S14 is simply referred to as “curing step S14”.
  • the manufacturing process S11 is a process of sequentially manufacturing a plurality of first floor panels 1, 1,.
  • the plurality of first floor panels 1, 1... are a total of 82 first floor wall panels 11, 11..
  • first-floor wall panels 11, 11,... Of the reinforced concrete structure within the formwork.
  • the first-floor wall panels 11, 11... Are removed from the mold after molding.
  • the manufacturing site 8 manufactures, for example, twelve first-floor wall panels 11, 11,... Per day, the period of the manufacturing process S11 is about seven days.
  • the transport step S12 when the first-floor wall panels 11, 11,... After demolding have developed an initial strength that can be transported to the construction site 9 by a vehicle or a crane vehicle, they are sequentially transported to the construction site 9. It is a process to go.
  • the transport process S12 can be performed in parallel with the manufacturing process S11.
  • the installation step S13 is a step of sequentially installing a plurality of first-floor wall panels 11, 11,... Conveyed to the construction site 9 on the foundation 5 on which the construction has been completed (see FIG. 4).
  • the first-floor wall panels 11, 11... are installed in order from the first side, and in about 7 days until the second side on the foundation 5 is reached. Panels for the first floor walls 11, 11 ... are installed. Thereby, the wall structure 611 of the first floor portion 61 of the house 6 is formed (see FIG. 5).
  • the first-floor wall panels 11, 11... Manufactured every day in the manufacturing process S ⁇ b> 11 are quickly transported to the construction site 9 and installed in order on the foundation 5 when the initial strength is developed. Therefore, a part of the period of the manufacturing process S11 (second half part) and a part of the period of the installation process S13 (first half part) overlap each other (see FIG. 2).
  • the period of the installation step S13 is about 7 days as in the manufacturing step S11.
  • the curing step S14 is a step of curing the plurality of first-floor wall panels 11, 11,... Installed in the installation step S13 in an outdoor environment on the foundation 5 until each exhibits a predetermined target strength.
  • the target strength here is higher than the initial strength of each first-floor wall panel 11, and more specifically, is the strength at which the second-floor portion 62 can be constructed on each first-floor wall panel 11. .
  • each first-floor wall panel 11 can exhibit the predetermined strength in about three days while being installed on the foundation 5.
  • the first floor portion 61 of the house 6 can be built as shown in FIG.
  • the second floor portion 62 of the house 6 is constructed by the second floor construction process S2.
  • the second floor building process S2 can be started in parallel with the first floor building process S1 from the middle of the first floor building process S1 instead of waiting for the completion of the first floor building process S1.
  • the second floor building process S2 includes a manufacturing process S21 for the second floor, a transport process S22 for the second floor, an installation process S23 for the second floor, and a curing process S24 for the second floor (see FIG. 1).
  • a plurality of second-floor floor panels 21, 21,... And a plurality of second-floor wall panels 22, 22, In the first half of the second floor building process S2, the floor structure 621 of the second floor portion 62 is constructed using a plurality of second floor floor panels 21, 21,..., And in the second half of the second floor building process S2, a plurality of second floor wall panels 22, 22 ... is used to build the wall structure 622 of the second floor portion 62.
  • the second floor manufacturing process S21 includes a second floor manufacturing process S211 performed in the first half and a second floor wall manufacturing process S212 performed in the second half.
  • the second floor transfer process S22 includes a second floor transfer process S221 performed in the first half and a second floor wall transfer process S222 performed in the second half.
  • the second floor installation process S23 includes a second floor installation process S231 performed in the first half and a second floor wall installation process S232 performed in the second half.
  • the curing process S24 for the second floor includes a curing process S241 for the second floor performed in the first half and a manufacturing process S242 for the second floor wall performed in the second half.
  • the second floor manufacturing process S211 is a process of sequentially manufacturing a plurality of second floor panels 21, 21, ... at the manufacturing site 8.
  • the manufacturing process S211 for the second floor can be continuously performed at the same manufacturing site 8 after the manufacturing process S11 for the first floor is completed.
  • the manufacturing site 8 manufactures a plurality of first floor panels 1, 1..., And a second floor manufacturing site that manufactures a plurality of second floor panels 21, 21.
  • the manufacturing site and the manufacturing site for the second floor are separate.
  • a plurality of the second floor panels 21, 21,... are manufactured in the same procedure as the manufacturing process S11.
  • the period of the manufacturing process S211 for the second floor is, for example, about 5 days.
  • the transport process S221 for the second floor when the second floor panels 21, 21... Exhibit an initial strength that can be transported to the construction site 9 by a vehicle or a crane vehicle, they are sequentially transported to the construction site 9. It is a process.
  • the transport process S221 for the second floor can be performed in parallel with the manufacturing process S211 for the second floor.
  • a plurality of second floor panels 21, 21,... Transported to the construction site 9 are sequentially installed on the first floor portion 61 (see FIG. 5) of the house 6. It is a process.
  • the second floor panels 21, 21... are installed in order from the first side where the first floor walls 11, 11,. In this embodiment, for example, in about 5 days, the installation of the second floor panels 21, 21... Is completed up to the second side on the first floor portion 61. Thereby, the floor structure 621 of the second floor portion 62 of the house 6 is formed (see FIG. 6).
  • a part of the period (first half) of the installation process S231 for the second floor is provided at a time overlapping with a part of the period (second half) of the curing process S14. be able to. That is, even when the curing process S14 is not completed, the first-floor wall panels 11, 11,... Installed in the initial stage of the installation process S13 have already developed the predetermined target strength. It is possible to install the second floor panels 21, 21. The entire construction period is further shortened by this amount.
  • the arrow t in FIG. 2 shows the passage direction of time.
  • the second-floor floor panels 21, 21, manufactured every day in the second-floor floor manufacturing process S 211 are promptly transported to the construction site 9 when the initial strength is developed, and sequentially on the first floor portion 61. Installed. Therefore, a part of the period of the manufacturing process S211 for the second floor (the second half part) and a part of the period of the installation process S231 for the second floor (the first half part) overlap each other (see FIG. 2).
  • the period of the installation process S231 for the second floor is about 5 days as in the manufacturing process S211 for the second floor.
  • the installation process S231 for the second floor can be started immediately after the installation process S13 is completed.
  • the second-floor curing step S241 is performed on the first floor portion 61 until the plurality of second-floor floor panels 21, 21... Installed in the second-floor installation step S231 exhibit a predetermined target strength. It is a process of curing in the environment.
  • the target strength here is higher than the initial strength of each second-floor floor panel 21, and more specifically, the strength at which the wall structure 622 of the second-floor portion 62 can be built on each second-floor floor panel 21. It is.
  • each of the second floor panels 21 can exhibit the predetermined target strength in about three days while being installed on the first floor portion 61.
  • the second floor wall manufacturing step S212 is a step of sequentially manufacturing a plurality of second floor wall panels 22, 22,...
  • the manufacturing process S212 for the second floor wall can be continuously performed at the same manufacturing site 8 after the manufacturing process S211 for the second floor is completed.
  • the manufacturing site 8 is for a second floor manufacturing site for manufacturing a plurality of second floor floor panels 21, 21... And a second floor wall for manufacturing a plurality of second floor wall panels 22, 22.
  • the second floor production site and the second floor production site are separate.
  • a plurality of second floor wall panels 22, 22,... are manufactured in the same procedure as the manufacturing process S11 and the like.
  • the period of the manufacturing process S212 for the second floor wall is, for example, about 6 days.
  • the second floor wall panels 22, 22,... are sequentially transported to the construction site 9 when the initial strength that can be transported to the construction site 9 by a vehicle or a crane vehicle is developed. It is a process.
  • the transport process S222 for the second floor wall can be performed in parallel with the manufacturing process S212 for the second floor wall.
  • a plurality of second floor wall panels 22, 22... Transported to the construction site 9 are sequentially installed on the floor structure 621 (see FIG. 6) of the second floor portion 62 of the house 6. It is a process to do.
  • the second-floor wall panels 22, 22... are sequentially installed from the first side where the second-floor floor panels 21, 21.
  • the installation of the second-floor wall panels 22, 22... Is completed up to the second side of the floor structure 621 of the second-floor portion 62.
  • the wall structure 622 (as a result, the whole second floor portion 62) of the second floor portion 62 of the house 6 is formed (see FIG. 7).
  • a part (first half) of the period of the installation process S232 for the second floor is a part (second half) of the period of the curing process S241 for the second floor. It can be provided at the time of overlap. That is, even when the second floor curing process S241 is not completed, the second floor panels 21, 21... Installed in the initial stage of the second floor installation process S231 already exhibit the predetermined target strength. Therefore, it is possible to install the second-floor wall panels 22, 22 ... from the first side. The entire construction period is further shortened by this amount.
  • the second-floor wall panels 22, 22... Manufactured every day in the second-floor wall manufacturing process S 212 are promptly transported to the construction site 9 when the initial strength is developed, and the floor structure 621 of the second-floor portion 62. Installed in order. Therefore, a part of the period of the second floor wall manufacturing process S212 (second half part) and a part of the period of the second floor wall installation process S232 (first half part) overlap each other (see FIG. 2).
  • the period of the installation process S232 for the second floor wall is about 6 days as in the manufacturing process S212 for the second floor wall.
  • the installation process S232 for the second floor wall can be started immediately after the installation process S231 for the second floor is completed.
  • the plurality of second floor wall panels 22, 22... Installed in the installation process S232 for the second floor wall are each of the floor structure 621 of the second floor portion 62 until each of them develops a predetermined target strength. It is a process of curing in the above outdoor environment.
  • the target strength here is strength higher than the initial strength of each second-floor wall panel 22, and more specifically, strength that allows the roof structure 63 to be constructed on each second-floor wall panel 22.
  • each of the second-floor wall panels 22 can exhibit the predetermined target strength in about three days while being installed on the floor structure of the second-floor portion 62.
  • the second-floor portion 62 of the house 6 as shown in FIG. 7 can be built in a short period of time.
  • the roof structure 63 of the house 6 is constructed by the roof construction process S3.
  • the roof building process S3 can be started in parallel with the second floor building process S2 from the middle of the second floor building process S2.
  • the roof building process S3 includes a manufacturing process S31 for roof, a transport process S32 for roof, an installation process S33 for roof, and a curing process S34 for roof (see FIG. 1).
  • the manufacturing process S31 for roof is a process of manufacturing a plurality of roof panels 3, 3.
  • the roof manufacturing process S31 can be continuously performed at the same manufacturing site 8 after the second-floor wall manufacturing process S212 is completed.
  • the manufacturing site 8 manufactures a plurality of second floor wall panels 22, 22...
  • the manufacturing site for the second floor wall and the manufacturing site for the roof may be separate.
  • a plurality of roof panels 3, 3,... are manufactured in the same procedure as the manufacturing process S11 and the like.
  • the period of the manufacturing process S31 for roof is, for example, about 4 days.
  • the roof transport process S32 is a process of sequentially transporting the roof panels 3, 3... To the construction site 9 when the roof panel 3, 3. is there.
  • the conveyance process S32 for roofs can be performed in parallel with the manufacturing process S31 for roofs.
  • a plurality of roof panels 3, 3... Transported to the construction site 9 are sequentially installed on the wall structure 622 (see FIG. 7) of the second floor portion 62 of the house 6. It is a process to go.
  • the roof panels 3, 3... Are sequentially installed from the first side where the second-floor wall panels 22, 22.
  • the roof panels 3, 3... Can be installed up to the second side of the wall structure 622 of the second floor portion 62, for example, in about 4 days. Thereby, the roof structure 63 of the house 6 (and eventually the entire housing of the house 6) is formed (see FIG. 8).
  • a part of the period of the roof installation process S33 overlaps a part of the period of the second floor wall curing process S242 (second half part).
  • the roof panels 3, 3... Manufactured every day in the roof manufacturing process S31 are quickly transported to the construction site 9 at the time when the initial strength is developed, and placed on the wall structure 622 of the second floor portion 62. Installed in order. Therefore, a part of the period of the manufacturing process S31 for roof (second half) and a part of the period of the installation process S33 for roof (first half) overlap each other (see FIG. 2).
  • the period of the installation process S33 for roof is about 4 days as in the manufacturing process S31 for roof.
  • the installation process S33 for the roof can be started immediately after the installation process S232 for the second floor wall is completed.
  • the manufacturing process S11, the manufacturing process S21 for the second floor (the manufacturing process S211 for the second floor, the manufacturing process S212 for the second floor wall) and the manufacturing process S31 for the roof are continuously performed at the manufacturing site 8.
  • the installation process S13, the installation process S23 for the second floor (the installation process S231 for the second floor, the installation process S232 for the second floor wall) and the installation process S33 for the roof Can be carried out continuously.
  • the roof curing step S34 is performed outdoors on the plurality of roof panels 3, 3... Installed in the roof installation step S33 on the second floor portion 62 on the wall structure 622 until each exhibits a predetermined target strength. It is a process of curing in the environment.
  • the target strength here is higher than the initial strength of each roof panel 3, and more specifically, various facilities such as a photovoltaic power generation panel are installed on each second-floor wall panel 22. It is the strength that can be.
  • each roof panel 3 can exhibit the predetermined target strength in about three days in a state where it is installed on the wall structure 622 of the second floor portion 62.
  • the finishing step S4 shown in FIG. 1 is a step of finishing various parts of the house 6, and can be started in parallel from the point in the middle of building the housing of the house 6 (for example, the second floor portion 62 of the house 6). is there.
  • the continuous house 6 having about 10 buildings is completed to the finish in a very short period of about 3 months after the foundation work is started. It becomes possible.
  • the building construction method of the present embodiment to a house that is not a continuous building type, the house can be provided with a short delivery time and at a low cost.
  • the building construction method of this embodiment is a construction method in which the curing of the first floor panels 1, 1... And the second floor panels 2, 2. It is preferable to be in a tropical environment or in a rainforest climate.
  • the building construction method of the present embodiment includes a manufacturing process S11, a transport process S12, an installation process S13, and a curing process S14 as the first feature.
  • a manufacturing process S11 a plurality of first floor panels 1, 1... Having a reinforced concrete structure are sequentially manufactured at the manufacturing site 8.
  • the transporting step S12 the plurality of first floor panels 1, 1... Manufactured in the manufacturing step S11 are sequentially transported from the manufacturing site 8 to the building site 9 at a stage where a predetermined initial strength is developed.
  • the installation step S ⁇ b> 13 a plurality of first floor panels 1, 1...
  • the plurality of first floor panels 1, 1... Installed in the installation step S13 are cured on the foundation 5 until each of them develops a predetermined target strength higher than the predetermined initial strength.
  • each of the plurality of first floor panels 1, 1... Is the first floor wall panel 11 for forming the wall structure 611 of the first floor portion 61.
  • the time from the start of manufacturing the plurality of first floor wall panels 11, 11... Of the reinforced concrete structure to the completion of the construction of the wall structure 611 of the first floor portion 61 is shortened. can do. Thereby, it becomes possible to build the house 6 in a short period of time.
  • the building construction method of the present embodiment further includes, as a third feature, a second-floor manufacturing process S21, a second-floor installation process S23, and a second-floor curing process S24.
  • a second floor manufacturing process S21 a plurality of second floor panels 2, 2... Having a reinforced concrete structure are sequentially manufactured at the second floor manufacturing site (manufacturing site 8).
  • a plurality of second floor panels 2, 2... Manufactured in the second floor manufacturing process S21 are constructed from the second floor manufacturing site (manufacturing site 8) at a stage where a predetermined initial strength is developed. Transport to site 9 in sequence.
  • the second floor portion 62 of the house 6 is formed on the first floor portion 61.
  • the plurality of second-floor panels 2, 2,... Installed in the installation process S23 for the second floor are processed on the first floor until each of them develops a predetermined target strength higher than the predetermined initial strength. Cured on 61.
  • the second floor installation step S21 expresses the predetermined target strength among the plurality of first floor panels 1, 1... Constituting the first floor portion 61.
  • a plurality of second-floor panels 2, 2,... are sequentially installed from the top of the first-floor panels 1, 1,.
  • a part of the period of the curing process S14 and a part of the period of the installation process S23 for the second floor are provided so as to overlap each other.
  • the time from the start of manufacturing the plurality of first floor panels 1, 1... To the completion of the construction of the second floor portion 62 can be further shortened. Thereby, it becomes possible to build the house 6 in a shorter period of time.
  • a manufacturing process S211 for the second floor, a transport process S221 for the second floor, an installation process S231 for the second floor, and a curing process S241 for the second floor Is further provided.
  • the second-floor manufacturing process S211 a plurality of second-floor floor panels 21, 21,... Having a reinforced concrete structure are sequentially manufactured at the second-floor manufacturing site (manufacturing site 8).
  • the transport process S221 for the second floor the plurality of second floor panels 21, 21,... Manufactured in the second floor manufacturing process S211 are produced at the stage where the predetermined initial strength is expressed (the production site for the second floor). Transport sequentially from 8) to construction site 9.
  • the plurality of second floor panels 21, 21... Transported to the construction site 9 are sequentially placed on the plurality of first floor panels 1, 1.
  • the floor structure 621 of the second floor portion 62 of the house 6 is formed on the first floor portion 61.
  • the plurality of second floor panels 21, 21... Installed in the installation process S231 for the second floor are each expressed with a predetermined target strength higher than the predetermined initial strength. It is cured on the first floor part 61.
  • the time from the start of manufacturing the plurality of second-floor floor panels 21, 21... Of the reinforced concrete structure to the completion of the construction of the floor structure 621 of the second-floor portion 62 is shortened. Can do. Thereby, it becomes possible to build the house 6 in a shorter period of time.
  • the installation process S231 for the second floor expresses the predetermined target strength among the plurality of first floor panels 1, 1. Is a step of sequentially installing a plurality of second-floor floor panels 21, 21...
  • the construction of the floor structure 621 of the second floor portion 62 can be started without having to wait until all of the plurality of first floor panels 1, 1... Exhibit the predetermined target strength. .
  • a part of the period of the curing process S14 and a part of the period of the installation process S231 for the second floor are provided so as to overlap each other.
  • the building construction method of the present embodiment it is possible to further reduce the time from the start of the manufacture of the plurality of first floor panels 1, 1... Until the construction of the floor structure 621 of the second floor portion 62 is completed. . Thereby, it becomes possible to build the house 6 in a shorter period of time.
  • the second-floor wall manufacturing step S212 a plurality of second-floor wall panels 22, 22... Having a reinforced concrete structure are sequentially manufactured at the second-floor wall manufacturing site (manufacturing site 8).
  • the second floor wall transfer step S222 a plurality of second floor wall panels 22, 22... Manufactured in the second floor wall manufacturing step S212 are subjected to a second floor wall manufacturing site (manufacturing site) at a stage where a predetermined initial strength is developed. Transport sequentially from 8) to construction site 9.
  • the plurality of second floor wall panels 22, 22... Transported to the construction site 9 are sequentially placed on the plurality of second floor floor panels 21, 21. It is installed and the wall structure 622 of the second floor portion 62 is formed on the floor structure 621.
  • the curing process S242 for the second floor wall until the plurality of second floor wall panels 22, 22... Installed in the second floor wall installation process S232 each express a predetermined target strength higher than the predetermined initial strength. Curing is performed on the floor structure 621.
  • the time from the start of manufacturing the plurality of second floor wall panels 22, 22... Of the reinforced concrete structure to the completion of the construction of the wall structure 622 of the second floor portion 62 is shortened. Can do. Thereby, it becomes possible to build the house 6 in a shorter period of time.
  • the installation process S232 for the second-floor wall expresses the predetermined target strength among the plurality of second-floor floor panels 21, 21 ... constituting the floor structure 621.
  • a plurality of second-floor wall panels 22, 22... are sequentially installed from the top of the second-floor panels 21, 21.
  • a part of the period of the curing process S241 for the second floor and a part of the period of the installation process S232 for the second floor are provided so as to overlap each other.
  • the building construction method of the present embodiment it is possible to further reduce the time from the start of the production of the plurality of first floor panels 1, 1... Until the construction of the wall structure 622 of the second floor portion 62 is completed. . Thereby, it becomes possible to build the house 6 in a shorter period of time.
  • the house 6 is a continuous house.
  • the building construction method of the present embodiment even if the house 6 to be built is a continuous house type where about 10 houses are continuous, the construction is completed in a very short period (for example, three months). Is possible.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

 短期間で住宅を建築することのできる、住宅の建築構法を提供することを目的とする。住宅の一階部分を建築する工程として、製造工程(S11)と搬送工程(S12)と設置工程(S13)と養生工程(S14)を備える。搬送工程(S12)では、製造工程(S11)で製造した複数の一階用パネルを、所定の初期強度を発現した段階で、製造現場から建築現場に搬送する。設置工程(S13)では、搬送された複数の一階用パネルを、建築現場の基礎上に設置する。養生工程(S14)では、設置工程(S13)で設置した複数の一階用パネルを、それぞれが所定の目的強度を発現するまで、基礎上で養生させる。二階部分を建築する工程でも、同様に、建築現場で養生を行う。

Description

住宅の建築構法
 本発明は、住宅の建築構法に関し、詳しくは、鉄筋コンクリート構造のパネルを用いて住宅を建築する、住宅の建築構法に関する。
 鉄筋コンクリート構造のパネルを用いて住宅を建築することが、従来提案されている。
 例えば、日本国特許公開公報2000-248614号には、多数の鉄筋コンクリートパネルをあらかじめ製造しておき、これらの多数の鉄筋コンクリートパネルを耐力壁や床版として利用することで、住宅を建築する方法が開示されている。
 上記した従来の建築方法では、多数の鉄筋コンクリートパネルを、それぞれが目的の強度(住宅の壁や床として要求される強度)を発現するまで、製造現場の専用施設で養生させる。専用施設内での養生を完了した多数の鉄筋コンクリートパネルは、いったん保管施設等に保管した後に、建築現場にまで搬送し、建築現場で組み立てることが一般的である。
 しかし、上記した従来の建築方法においては、多数の鉄筋コンクリートパネルの製造を始めた時点から、これらの鉄筋コンクリートパネルを用いて建築現場で住宅を完成させるまでの期間が長いという問題を有していた。
 本発明の目的は、複数の鉄筋コンクリートパネルで構成された住宅を、短期間で建築することのできる、住宅の建築構法を提供することにある。
 本発明に係る形態の住宅の建築構法は、製造工程と、搬送工程と、設置工程と、養生工程とを備える。
 前記製造工程は、鉄筋コンクリート構造の複数の一階用パネルを、製造現場で順次製造する工程である。
 前記搬送工程は、前記製造工程で製造した前記複数の一階用パネルを、所定の初期強度を発現した段階で、前記製造現場から建築現場にまで順次搬送する工程である。
 前記設置工程は、前記建築現場に搬送された前記複数の一階用パネルを、前記建築現場の基礎上に順次設置し、前記基礎上に住宅の一階部分を形成する工程である。
 前記養生工程は、前記設置工程で設置した前記複数の一階用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記基礎上で養生させる工程である。
 前記複数の一階用パネルの各々は、前記一階部分の壁構造を形成するための一階壁用パネルであることが好ましい。
 本発明に係る形態の住宅の建築構法においては、二階用の製造工程と、二階用の搬送工程と、二階用の設置工程と、二階用の養生工程と、をさらに備えることが好ましい。
 前記二階用の製造工程は、鉄筋コンクリート構造の複数の二階用パネルを、二階用の製造現場で順次製造する工程である。前記二階用の搬送工程は、前記二階用の製造工程で製造した前記複数の二階用パネルを、所定の初期強度を発現した段階で、前記二階用の製造現場から前記建築現場にまで順次搬送する工程である。前記二階用の設置工程は、前記建築現場に搬送された前記複数の二階用パネルを、前記所定の目的強度を発現した前記複数の一階用パネルの上に順次設置し、前記一階部分の上に、前記住宅の二階部分を形成する工程である。前記二階用の養生工程は、前記二階用の設置工程で設置した前記複数の二階用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記一階部分の上で養生させる工程である。
 本発明に係る形態の住宅の建築構法において、前記二階用の設置工程は、前記一階部分を構成する前記複数の一階用パネルのうち、前記所定の目的強度を発現した一階用パネルの上から順に、前記複数の二階用パネルを順次設置していく工程であることが好ましい。
 本発明に係る形態の住宅の建築構法においては、前記養生工程の期間の一部と、前記二階用の設置工程の期間の一部が、互いに重なるように設けていることが好ましい。
 本発明に係る形態の住宅の建築構法においては、二階床用の製造工程と、二階床用の搬送工程と、二階床用の設置工程と、二階床用の養生工程と、をさらに備えることが好ましい。
 前記二階床用の製造工程は、鉄筋コンクリート構造の複数の二階床用パネルを、二階床用の製造現場で順次製造する工程である。前記二階床用の搬送工程は、前記二階床用の製造工程で製造した前記複数の二階床用パネルを、所定の初期強度を発現した段階で、前記二階床用の製造現場から前記建築現場にまで順次搬送する工程である。前記二階床用の設置工程は、前記建築現場に搬送された前記複数の二階床用パネルを、前記所定の目的強度を発現した前記複数の一階用パネルの上に順次設置し、前記一階部分の上に、前記住宅の二階部分の床構造を形成する工程である。前記二階床用の養生工程は、前記二階床用の設置工程で設置した前記複数の二階床用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記一階部分の上で養生させる工程である。
 本発明に係る形態の住宅の建築構法において、前記二階床用の設置工程は、前記一階部分を構成する前記複数の一階用パネルのうち、前記所定の目的強度を発現した一階用パネルの上から順に、前記複数の二階床用パネルを順次設置していく工程であることが好ましい。
 本発明に係る形態の住宅の建築構法においては、前記養生工程の期間の一部と、前記二階床用の設置工程の期間の一部が、互いに重なるように設けていることが好ましい。
 本発明に係る形態の住宅の建築構法においては、二階壁用の製造工程と、二階壁用の搬送工程と、二階壁用の設置工程と、二階壁用の養生工程と、をさらに備えることが好ましい。
 前記二階壁用の製造工程は、鉄筋コンクリート構造の複数の二階壁用パネルを、二階壁用の製造現場で順次製造する工程である。前記二階壁用の搬送工程は、前記二階壁用の製造工程で製造した前記複数の二階壁用パネルを、所定の初期強度を発現した段階で、前記二階壁用の製造現場から前記建築現場にまで順次搬送する工程である。前記二階壁用の設置工程は、前記建築現場に搬送された前記複数の二階壁用パネルを、前記所定の目的強度を発現した前記複数の二階床用パネルの上に順次設置し、前記床構造の上に、前記二階部分の壁構造を形成する工程である。前記二階壁用の養生工程は、前記二階壁用の設置工程で設置した前記複数の二階壁用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記床構造の上で養生させる工程である。
 本発明に係る形態の住宅の建築構法において、前記二階壁用の設置工程は、前記床構造を構成する前記複数の二階床用パネルのうち、前記所定の目的強度を発現した前記二階床用パネルの上から順に、前記複数の二階壁用パネルを順次設置していく工程であることが好ましい。
 本発明に係る形態の住宅の建築構法においては、前記二階床用の養生工程の期間の一部と、前記二階壁用の設置工程の期間の一部が、互いに重なるように設けていることが好ましい。
 本発明に係る形態の住宅の建築構法において、前記住宅は、連棟式住宅であることが好ましい。
実施形態1の建築構法の流れを示す図である。 実施形態1の建築構法の各工程のタイミングを説明する図である。 実施形態1の建築構法での製造現場と建築現場の関係を示す図である。 実施形態1の建築構法で建物の一階部分を建築し始めた段階を概略的に示す図である。 実施形態1の建築構法で建物の一階部分を形成した段階を概略的に示す図である。 実施形態1の建築構法で建物の二階部分の床構造を形成した段階を概略的に示す図である。 実施形態1の建築構法で建物の二階部分の壁構造を形成した段階を概略的に示す図である。 実施形態1の建築構法で建物の屋根構造を形成した段階を概略的に示す図である。
 本発明を、添付図面に示す実施形態に基づいて説明する。
 本発明の実施形態1の建築構法は、鉄筋コンクリート構造のパネルを、所定の目的強度が発現するまでパネルの製造現場で養生するのではなく、建築現場に搬送して設置した状態で、前記所定の目的強度が発現するまで養生させることで、短期間での住宅建築を実現する構法である。
 本実施形態の建築構法は、高温多湿の環境下において、特に有効な建築構法である。
 また、本実施形態の建築構法は、連棟式の住宅を建築する際に、特に有効な建築構法である。
 以下、本実施形態の建築構法について、添付図面に基づいて詳しく説明する。
 本実施形態の建築構法では、連棟式の住宅6の一階部分61を建築するために用いる複数の一階用パネル1,1…(図5等参照)と、連棟式の住宅6の二階部分62を建築するために用いる複数の二階用パネル2,2…(図7等参照)とを、専用設備を備えた製造現場8(図3参照)で製造する。
 製造現場8で製造した一階用パネル1,1…や二階用パネル2,2…は、搬送することが可能な初期強度を発現した段階で、車両等の適宜の搬送手段7を用いて、建築現場9にまで搬送する。
 本実施形態の建築構法では、製造現場8が、複数の一階用パネル1,1…を製造する製造現場と、複数の二階用パネル2,2…を製造する二階用の製造現場とを兼ねるが、前記製造現場と前記二階用の製造現場が別々であることも有り得る。
 製造現場8と建築現場9は、隣接して設けることも可能である。この場合には、搬送手段7としてクレーン等を用い、一階用パネル1,1…や二階用パネル2,2…を、建築現場9にまで速やかに搬送することができる。
 図1には、実施形態1の建築構法で住宅6を建築する各工程の流れを、概略的に示している。
 基礎工事の工程S0は、建築現場9に基礎5を形成する工程である。本実施形態の建築構法で建築する住宅6は、10棟が連なる連棟式住宅であり、基礎5を形成するために数週間程度を要する。
 基礎工事の工程S0を完了した時点から、あるいは基礎工事の工程S0の後半部と平行して、基礎5上に住宅6の一階部分61を建築する一階建築工程S1を開始する。
 一階建築工程S1は、一階用の製造工程S11、一階用の搬送工程S12、一階用の設置工程S13及び一階用の養生工程S14を含む。以下、一階用の製造工程S11を単に「製造工程S11」、一階用の搬送工程S12を単に「搬送工程S12」、一階用の設置工程S13を単に「設置工程S13」、一階用の養生工程S14を単に「養生工程S14」と称する。
 製造工程S11は、複数の一階用パネル1,1…を、製造現場8で順次製造する工程である。本実施形態において、複数の一階用パネル1,1…は、計82枚の一階壁用パネル11,11…である。
 製造現場8では、鉄筋を組み立てて型枠に投入し、該型枠内にコンクリートを打設することで、鉄筋コンクリート構造の一階壁用パネル11,11…を、該型枠内で成形する。一階壁用パネル11,11…は、成形後に該型枠から脱型させる。
 製造現場8では、一日当たり例えば12枚の一階壁用パネル11,11…を製造するので、製造工程S11の期間は7日程度である。
 搬送工程S12は、脱型後の一階壁用パネル11,11…が、車両やクレーン車で建築現場9にまで搬送可能な初期強度を発現した時点で、順次、建築現場9に搬送していく工程である。搬送工程S12は、製造工程S11と平行して行うことができる。
 設置工程S13は、建築現場9にまで搬送された複数の一階壁用パネル11,11…を、工事が完了した基礎5上に、順次設置していく工程である(図4参照)。10棟分に区画された基礎5上に、第一の側から順に一階壁用パネル11,11…を設置していき、7日程度で、基礎5上の第二の側に至るまで、一階壁用パネル11,11…を設置する。これにより、住宅6の一階部分61の壁構造611を形成する(図5参照)。
 製造工程S11において一日毎に製造された一階壁用パネル11,11…は、初期強度が発現した時点で、速やかに建築現場9に搬送され、基礎5上に順に設置される。そのため、製造工程S11の期間の一部(後半部)と、設置工程S13の期間の一部(前半部)は、互いに重なる(図2参照)。設置工程S13の期間は、製造工程S11と同じく7日程度である。
 養生工程S14は、設置工程S13で設置した複数の一階壁用パネル11,11…を、それぞれが所定の目的強度を発現するまで、基礎5上の屋外環境で養生させる工程である。ここでの目的強度は、各一階壁用パネル11の前記初期強度よりも高い強度であり、さらに詳しくは、各一階壁用パネル11上に二階部分62を建築することのできる強度である。
 高温多湿の適切な環境下であれば、各一階壁用パネル11は、基礎5上に設置された状態で、3日程度で前記所定の目的強度を発現し得る。
 図2に示すように、設置工程S13の期間の一部(後半部)と、養生工程S14の一部(前半部)は、互いに重なる。
 以上の一階建築工程S1によって、図5に示すように、住宅6の一階部分61を建築することができる。
 住宅6の二階部分62は、二階建築工程S2によって建築する。二階建築工程S2は、一階建築工程S1の完了を待つのではなく、一階建築工程S1の途中の時点から、一階建築工程S1と平行して開始することができる。
 二階建築工程S2は、二階用の製造工程S21、二階用の搬送工程S22、二階用の設置工程S23及び二階用の養生工程S24を含む(図1参照)。
 本実施形態では、二階部分62を建築するための複数の二階用パネル2,2…として、複数の二階床用パネル21,21…と、複数の二階壁用パネル22,22…とを用いる。そして、二階建築工程S2の前半で、複数の二階床用パネル21,21…を用いて二階部分62の床構造621を建築し、二階建築工程S2の後半で、複数の二階壁用パネル22,22…を用いて二階部分62の壁構造622を建築する。
 そのため、本実施形態の建築構法において、二階用の製造工程S21は、前半に行う二階床用の製造工程S211と、後半に行う二階壁用の製造工程S212を含む。
 同様に、二階用の搬送工程S22は、前半に行う二階床用の搬送工程S221と、後半に行う二階壁用の搬送工程S222を含む。二階用の設置工程S23は、前半に行う二階床用の設置工程S231と、後半に行う二階壁用の設置工程S232を含む。二階用の養生工程S24は、前半に行う二階床用の養生工程S241と、後半に行う二階壁用の製造工程S242を含む。
 具体的には、これら各工程は、以下のとおりである。
 二階床用の製造工程S211は、複数の二階床用パネル21,21…を、製造現場8で順次製造する工程である。二階床用の製造工程S211は、一階用の製造工程S11が完了してから、引き続き同一の製造現場8で行うことができる。
 本実施形態の建築構法では、製造現場8が、複数の一階用パネル1,1…を製造する製造現場と、複数の二階床用パネル21,21…を製造する二階床用の製造現場とを兼ねるが、前記製造現場と前記二階床用の製造現場が別々であることも有り得る。
 本実施形態の二階床用の製造工程S211においては、複数の二階床用パネル21,21…を、製造工程S11と同様の手順で、計50枚製造する。二階床用の製造工程S211の期間は、例えば5日程度である。
 二階床用の搬送工程S221は、二階床用パネル21,21…が、車両やクレーン車で建築現場9にまで搬送可能な初期強度を発現した時点で、順次、建築現場9に搬送していく工程である。二階床用の搬送工程S221は、二階床用の製造工程S211と平行して行うことができる。
 二階床用の設置工程S231は、建築現場9にまで搬送された複数の二階床用パネル21,21…を、住宅6の一階部分61(図5参照)の上に、順次設置していく工程である。二階床用パネル21,21…は、一階壁用パネル11,11…を設置し始めた前記第一の側から、順に設置していく。本実施形態では、例えば5日程度で、一階部分61上の前記第二の側にまで二階床用パネル21,21…を設置し終わる。これにより、住宅6の二階部分62の床構造621を形成する(図6参照)。
 本実施形態の建築構法では、図2に示すように、二階床用の設置工程S231の期間の一部(前半部)を、養生工程S14の期間の一部(後半部)と重なる時期に設けることができる。つまり、養生工程S14が全て完了していない時点でも、設置工程S13の初期に設置した一階壁用パネル11,11…は既に前記所定の目的強度を発現しているので、前記第一の側から二階床用パネル21,21…を設置することが可能である。この分だけ、全体の建築期間がさらに短縮される。なお、図2中の矢印tは時間の経過方向を示す。
 二階床用の製造工程S211において一日毎に製造された二階床用パネル21,21…は、前記初期強度が発現した時点で、速やかに建築現場9に搬送され、一階部分61の上に順に設置される。そのため、二階床用の製造工程S211の期間の一部(後半部)と、二階床用の設置工程S231の期間の一部(前半部)は、互いに重なる(図2参照)。二階床用の設置工程S231の期間は、二階床用の製造工程S211と同じく5日程度である。二階床用の設置工程S231は、設置工程S13が完了した直後から開始することができる。
 二階床用の養生工程S241は、二階床用の設置工程S231で設置した複数の二階床用パネル21,21…を、それぞれが所定の目的強度を発現するまで、一階部分61の上の屋外環境で養生させる工程である。ここでの目的強度は、各二階床用パネル21の前記初期強度よりも高い強度であり、さらに詳しくは、各二階床用パネル21上に二階部分62の壁構造622を建築することのできる強度である。
 高温多湿の適切な環境下であれば、各二階床用パネル21は、一階部分61の上に設置された状態で、3日程度で前記所定の目的強度を発現し得る。
 図2に示すように、二階床用の設置工程S231の期間の一部(後半部)と、二階床用の養生工程S241の一部(前半部)は、互いに重なる。
 二階壁用の製造工程S212は、複数の二階壁用パネル22,22…を、製造現場8で順次製造する工程である。二階壁用の製造工程S212は、二階床用の製造工程S211が完了してから、引き続き同一の製造現場8で行うことができる。
 本実施形態の建築構法では、製造現場8が、複数の二階床用パネル21,21…を製造する二階床用の製造現場と、複数の二階壁用パネル22,22…を製造する二階壁用の製造現場とを兼ねるが、前記二階床用の製造現場と前記二階壁用の製造現場が別々であることも有り得る。
 本実施形態の二階壁用の製造工程S221においては、複数の二階壁用パネル22,22…を、製造工程S11等と同様の手順で、計72枚製造する。二階壁用の製造工程S212の期間は、例えば6日程度である。
 二階壁用の搬送工程S222は、二階壁用パネル22,22…が、車両やクレーン車で建築現場9にまで搬送可能な初期強度を発現した時点で、順次、建築現場9に搬送していく工程である。二階壁用の搬送工程S222は、二階壁用の製造工程S212と平行して行うことができる。
 二階壁用の設置工程S232は、建築現場9にまで搬送された複数の二階壁用パネル22,22…を、住宅6の二階部分62の床構造621(図6参照)の上に、順次設置していく工程である。二階壁用パネル22,22…は、二階床用パネル21,21…を設置し始めた前記第一の側から、順に設置していく。本実施形態では、例えば6日程度で、二階部分62の床構造621の前記第二の側にまで、二階壁用パネル22,22…を設置し終わる。これにより、住宅6の二階部分62の壁構造622(ひいては二階部分62の全体)を形成する(図7参照)。
 本実施形態の建築構法では、図2に示すように、二階壁用の設置工程S232の期間の一部(前半部)を、二階床用の養生工程S241の期間の一部(後半部)と重なる時期に設けることができる。つまり、二階床用の養生工程S241が全て完了していない時点でも、二階床用の設置工程S231の初期に設置した二階床用パネル21,21…は既に前記所定の目的強度を発現しているので、前記第一の側から二階壁用パネル22,22…を設置することが可能である。この分だけ、全体の建築期間がさらに短縮される。
 二階壁用の製造工程S212において一日毎に製造された二階壁用パネル22,22…は、前記初期強度が発現した時点で、速やかに建築現場9に搬送され、二階部分62の床構造621の上に順に設置される。そのため、二階壁用の製造工程S212の期間の一部(後半部)と、二階壁用の設置工程S232の期間の一部(前半部)は、互いに重なる(図2参照)。二階壁用の設置工程S232の期間は、二階壁用の製造工程S212と同じく6日程度である。二階壁用の設置工程S232は、二階床用の設置工程S231が完了した直後から開始することができる。
 二階壁用の養生工程S242は、二階壁用の設置工程S232で設置した複数の二階壁用パネル22,22…を、それぞれが所定の目的強度を発現するまで、二階部分62の床構造621の上の屋外環境で養生させる工程である。ここでの目的強度は、各二階壁用パネル22の前記初期強度よりも高い強度であり、さらに詳しくは、各二階壁用パネル22上に屋根構造63を建築することのできる強度である。
 高温多湿の適切な環境下であれば、各二階壁用パネル22は、二階部分62の床構造の上に設置された状態で、3日程度で前記所定の目的強度を発現し得る。
 図2に示すように、二階壁用の設置工程S232の期間の一部(後半部)と、二階壁用の養生工程S242の一部(前半部)は、互いに重なる。
 以上の二階建築工程S2によって、図7に示すような住宅6の二階部分62を、短期間で建築することができる。
 住宅6の屋根構造63は、屋根建築工程S3によって建築する。屋根建築工程S3は、二階建築工程S2の途中の時点から、二階建築工程S2と平行して開始することができる。
 屋根建築工程S3は、屋根用の製造工程S31、屋根用の搬送工程S32、屋根用の設置工程S33及び屋根用の養生工程S34を含む(図1参照)。
 屋根用の製造工程S31は、複数の屋根用パネル3,3…を、製造現場8で順次製造する工程である。屋根用の製造工程S31は、二階壁用の製造工程S212が完了してから、引き続き同一の製造現場8で行うことができる。
 本実施形態の建築構法では、製造現場8が、複数の二階壁パネル22,22…を製造する二階壁用の製造現場と、複数の屋根用パネル3,3…を製造する屋根用の製造現場とを兼ねるが、前記二階壁用の製造現場と前記屋根用の製造現場が別々であることも有り得る。
 本実施形態の屋根用の製造工程S31においては、複数の屋根用パネル3,3…を、製造工程S11等と同様の手順で、計40枚製造する。屋根用の製造工程S31の期間は、例えば4日程度である。
 屋根用の搬送工程S32は、屋根用パネル3,3…が、車両やクレーン車で建築現場9にまで搬送可能な初期強度を発現した時点で、順次、建築現場9に搬送していく工程である。屋根用の搬送工程S32は、屋根用の製造工程S31と平行して行うことができる。
 屋根用の設置工程S33は、建築現場9にまで搬送された複数の屋根用パネル3,3…を、住宅6の二階部分62の壁構造622(図7参照)の上に、順次設置していく工程である。屋根用パネル3,3…は、二階壁用パネル22,22…を設置し始めた前記第一の側から、順に設置していく。本実施形態の屋根用の設置工程S33では、例えば4日程度で、二階部分62の壁構造622の前記第二の側に至るまで、屋根用パネル3,3…を設置することができる。これにより、住宅6の屋根構造63(ひいては住宅6の躯体全体)を形成する(図8参照)。
 本実施形態の建築構法では、図2に示すように、屋根用の設置工程S33の期間の一部(前半部)を、二階壁用の養生工程S242の期間の一部(後半部)と重なる時期に設けることができる。つまり、二階壁用の養生工程S242が全て完了していない時点でも、二階壁用の設置工程S232の初期に設置した二階壁用パネル22,22…は既に前記所定の目的強度を発現しているので、前記第一の側から屋根用パネル3,3…を設置することが可能である。この分だけ、全体の建築期間がさらに短縮される。
 屋根用の製造工程S31において一日毎に製造された屋根用パネル3,3…は、前記初期強度が発現した時点で、速やかに建築現場9に搬送され、二階部分62の壁構造622の上に順に設置される。そのため、屋根用の製造工程S31の期間の一部(後半部)と、屋根用の設置工程S33の期間の一部(前半部)は、互いに重なる(図2参照)。屋根用の設置工程S33の期間は、屋根用の製造工程S31と同じく4日程度である。屋根用の設置工程S33は、二階壁用の設置工程S232が完了した直後から開始することができる。
 即ち、本実施形態の建築工法では、製造現場8において製造工程S11、二階用の製造工程S21(二階床用の製造工程S211、二階壁用の製造工程S212)及び屋根用の製造工程S31を連続して実施可能であることに加えて、建築現場9においては設置工程S13、二階用の設置工程S23(二階床用の設置工程S231、二階壁用の設置工程S232)及び屋根用の設置工程S33を、連続して実施することができる。
 屋根用の養生工程S34は、屋根用の設置工程S33で設置した複数の屋根用パネル3,3…を、それぞれが所定の目的強度を発現するまで、二階部分62の壁構造622の上の屋外環境で養生させる工程である。ここでの目的強度は、各屋根用パネル3の前記初期強度よりも高い強度であり、さらに詳しくは、各二階壁用パネル22上に、さらに太陽光発電パネル等の各種設備を設置することのできる強度である。
 高温多湿の適切な環境下であれば、各屋根用パネル3は、二階部分62の壁構造622の上に設置された状態で、3日程度で前記所定の目的強度を発現し得る。
 図2に示すように、屋根用の設置工程S33の期間の一部(後半部)と、屋根用の養生工程S34の一部(前半部)は、互いに重なる。
 図1に示す仕上げ工程S4は、住宅6の各所の仕上げを行う工程であり、住宅6の躯体(例えば住宅6の二階部分62)を建築している途中の時点から、平行して開始可能である。
 本実施形態の建築構法で住宅6を建築することで、基礎工事を始めてから3ヶ月程度の非常に短い期間で、10棟程度が連続する連棟式の住宅6を、仕上げに至るまで完成させることが可能となる。
 特に、連棟式の住宅6の躯体を基礎5上に建築する作業については、一ヵ月程度の非常に短い期間で完了することが可能である。連棟式でない住宅に対しても、本実施形態の建築構法を適用することで、該住宅を短納期、低コストで提供することができる。
 本実施形態の建築構法は、一階用パネル1,1…や二階用パネル2,2…の養生を、建築現場9に設置した状態で行う構法であるから、亜熱帯の環境下であることや、熱帯の環境下であることや、熱帯雨林気候の環境下であることが好ましい。
 以上、添付図面に基づいて説明したように、本実施形態の建築構法は、第1の特徴として、製造工程S11と、搬送工程S12と、設置工程S13と、養生工程S14とを備える。製造工程S11では、鉄筋コンクリート構造の複数の一階用パネル1,1…を、製造現場8で順次製造する。搬送工程S12では、製造工程S11で製造した複数の一階用パネル1,1…を、所定の初期強度を発現した段階で、製造現場8から建築現場9にまで順次搬送する。設置工程S13では、建築現場9に搬送された複数の一階用パネル1,1…を、建築現場9の基礎5上に順次設置し、基礎5上に住宅6の一階部分61を形成する。養生工程S14では、設置工程S13で設置した複数の一階用パネル1,1…を、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、基礎5上で養生させる。
 そのため、本実施形態の建築構法では、鉄筋コンクリート構造の複数の一階用パネル1,1…の製造を開始してから一階部分61の建築を完了するまでの時間を、短縮することができる。これにより、住宅6を短期間で建築することが可能となる。
 本実施形態の建築構法では、第2の特徴として、複数の一階用パネル1,1…の各々が、一階部分61の壁構造611を形成するための一階壁用パネル11である。
 そのため、本実施形態の建築構法では、鉄筋コンクリート構造の複数の一階壁用パネル11,11…の製造を開始してから一階部分61の壁構造611の建築を完了するまでの時間を、短縮することができる。これにより、住宅6を短期間で建築することが可能となる。
 本実施形態の建築構法は、第3の特徴として、二階用の製造工程S21と、二階用の設置工程S23と、二階用の養生工程S24とを、さらに備える。二階用の製造工程S21では、鉄筋コンクリート構造の複数の二階用パネル2,2…を、二階用の製造現場(製造現場8)で順次製造する。二階用の搬送工程S22では、二階用の製造工程S21で製造した複数の二階用パネル2,2…を、所定の初期強度を発現した段階で、二階用の製造現場(製造現場8)から建築現場9にまで順次搬送する。二階用の設置工程S23では、建築現場9に搬送された複数の二階用パネル2,2…を、前記所定の目的強度を発現した複数の一階用パネル1,1…の上に順次設置し、一階部分61の上に、住宅6の二階部分62を形成する。二階用の養生工程S24では、二階用の設置工程S23で設置した複数の二階用パネル2,2…を、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、一階部分61の上で養生させる。
 そのため、本実施形態の建築構法では、鉄筋コンクリート構造の複数の二階用パネル2,2…の製造を開始してから二階部分62の建築を完了するまでの時間を、短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第4の特徴として、二階用の設置工程S21は、一階部分61を構成する複数の一階用パネル1,1…のうち、前記所定の目的強度を発現した一階用パネル1,1…の上から順に、複数の二階用パネル2,2…を順次設置していく工程である。
 そのため、本実施形態の建築構法では、複数の一階用パネル1,1…の全てが前記所定の目的強度を発現するまで待つ必要なく、二階部分62の建築を始めることができる。
 本実施形態の建築構法では、第5の特徴として、養生工程S14の期間の一部と、二階用の設置工程S23の期間の一部が、互いに重なるように設けている。
 そのため、本実施形態の建築構法では、複数の一階用パネル1,1…の製造を開始してから二階部分62の建築を完了するまでの時間を、さらに短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第6の特徴として、二階床用の製造工程S211と、二階床用の搬送工程S221と、二階床用の設置工程S231と、二階床用の養生工程S241と、をさらに備える。二階床用の製造工程S211では、鉄筋コンクリート構造の複数の二階床用パネル21,21…を、二階床用の製造現場(製造現場8)で順次製造する。二階床用の搬送工程S221では、二階床用の製造工程S211で製造した複数の二階床用パネル21,21…を、所定の初期強度を発現した段階で、二階床用の製造現場(製造現場8)から建築現場9にまで順次搬送する。二階床用の設置工程S231では、建築現場9に搬送された複数の二階床用パネル21,21…を、前記所定の目的強度を発現した複数の一階用パネル1,1…の上に順次設置し、一階部分61の上に、住宅6の二階部分62の床構造621を形成する。二階床用の養生工程S241では、二階床用の設置工程S231で設置した複数の二階床用パネル21,21…を、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、一階部分61の上で養生させる。
 そのため、本実施形態の建築構法では、鉄筋コンクリート構造の複数の二階床用パネル21,21…の製造を開始してから二階部分62の床構造621の建築を完了するまでの時間を、短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第7の特徴として、二階床用の設置工程S231は、一階部分61を構成する複数の一階用パネル1,1…のうち、前記所定の目的強度を発現した一階用パネル1,1…の上から順に、複数の二階床用パネル21,21…を順次設置していく工程である。
 そのため、本実施形態の建築構法では、複数の一階用パネル1,1…の全てが前記所定の目的強度を発現するまで待つ必要なく、二階部分62の床構造621の建築を始めることができる。
 本実施形態の建築構法では、第8の特徴として、養生工程S14の期間の一部と、二階床用の設置工程S231の期間の一部が、互いに重なるように設けている。
 そのため、本実施形態の建築構法では、複数の一階用パネル1,1…の製造を開始してから二階部分62の床構造621の建築を完了するまでの時間を、さらに短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第9の特徴として、二階壁用の製造工程S212と、二階壁用の搬送工程S222と、二階壁用の設置工程S232と、二階壁用の養生工程S242と、をさらに備える。二階壁用の製造工程S212では、鉄筋コンクリート構造の複数の二階壁用パネル22,22…を、二階壁用の製造現場(製造現場8)で順次製造する。二階壁用の搬送工程S222では、二階壁用の製造工程S212で製造した複数の二階壁用パネル22,22…を、所定の初期強度を発現した段階で、二階壁用の製造現場(製造現場8)から建築現場9にまで順次搬送する。二階壁用の設置工程S232では、建築現場9に搬送された複数の二階壁用パネル22,22…を、前記所定の目的強度を発現した複数の二階床用パネル21,21…の上に順次設置し、床構造621の上に、二階部分62の壁構造622を形成する。二階壁用の養生工程S242では、二階壁用の設置工程S232で設置した複数の二階壁用パネル22,22…を、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、床構造621の上で養生させる。
 そのため、本実施形態の建築構法では、鉄筋コンクリート構造の複数の二階壁用パネル22,22…の製造を開始してから二階部分62の壁構造622の建築を完了するまでの時間を、短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第10の特徴として、二階壁用の設置工程S232は、床構造621を構成する複数の二階床用パネル21,21…のうち、前記所定の目的強度を発現した二階床用パネル21,21…の上から順に、複数の二階壁用パネル22,22…を順次設置していく工程である。
 そのため、本実施形態の建築構法では、複数の二階床用パネル21,21…の全てが前記所定の目的強度を発現するまで待つ必要なく、二階部分62の壁構造622の建築を始めることができる。
 本実施形態の建築構法では、第11の特徴として、二階床用の養生工程S241の期間の一部と、二階壁用の設置工程S232の期間の一部を、互いに重なるように設けている。
 そのため、本実施形態の建築構法では、複数の一階用パネル1,1…の製造を開始してから二階部分62の壁構造622の建築を完了するまでの時間を、さらに短縮することができる。これにより、住宅6をさらに短期間で建築することが可能となる。
 本実施形態の建築構法では、第12の特徴として、住宅6は、連棟式住宅である。
 そのため、本実施形態の建築構法では、建築しようとする住宅6が、10棟程度が連続するような連棟式住宅であっても、非常に短期間(例えば3ヶ月)で建築を完了することが可能となる。
 以上、実施形態について説明したが、本発明は前記した実施形態に限定されない。本発明の意図する範囲内であれば、適宜の設計変更を行うことが可能である。

Claims (12)

  1.  鉄筋コンクリート構造の複数の一階用パネルを、製造現場で順次製造する、製造工程と、
     前記製造工程で製造した前記複数の一階用パネルを、所定の初期強度を発現した段階で、前記製造現場から建築現場にまで順次搬送する、搬送工程と、
     前記建築現場に搬送された前記複数の一階用パネルを、前記建築現場の基礎上に順次設置し、前記基礎上に住宅の一階部分を形成する、設置工程と、
     前記設置工程で設置した前記複数の一階用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記基礎上で養生させる、養生工程と、を備えた、
     住宅の建築構法。
  2.  前記複数の一階用パネルの各々は、前記一階部分の壁構造を形成するための一階壁用パネルである、
     請求項1に記載された住宅の建築構法。
  3.  鉄筋コンクリート構造の複数の二階用パネルを、二階用の製造現場で順次製造する、二階用の製造工程と、
     前記二階用の製造工程で製造した前記複数の二階用パネルを、所定の初期強度を発現した段階で、前記二階用の製造現場から前記建築現場にまで順次搬送する、二階用の搬送工程と、
     前記建築現場に搬送された前記複数の二階用パネルを、前記所定の目的強度を発現した前記複数の一階用パネルの上に順次設置し、前記一階部分の上に、前記住宅の二階部分を形成する、二階用の設置工程と、
     前記二階用の設置工程で設置した前記複数の二階用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記一階部分の上で養生させる、二階用の養生工程と、をさらに備えた、
     請求項1または2に記載の住宅の建築構法。
  4.  前記二階用の設置工程は、前記一階部分を構成する前記複数の一階用パネルのうち、前記所定の目的強度を発現した一階用パネルの上から順に、前記複数の二階用パネルを順次設置していく工程である、
     請求項3に記載の住宅の建築構法。
  5.  前記養生工程の期間の一部と、前記二階用の設置工程の期間の一部が、互いに重なるように設けた、
     請求項4に記載の住宅の建築構法。
  6.  鉄筋コンクリート構造の複数の二階床用パネルを、二階床用の製造現場で順次製造する、二階床用の製造工程と、
     前記二階床用の製造工程で製造した前記複数の二階床用パネルを、所定の初期強度を発現した段階で、前記二階床用の製造現場から前記建築現場にまで順次搬送する、二階床用の搬送工程と、
     前記建築現場に搬送された前記複数の二階床用パネルを、前記所定の目的強度を発現した前記複数の一階用パネルの上に順次設置し、前記一階部分の上に、前記住宅の二階部分の床構造を形成する、二階床用の設置工程と、
     前記二階床用の設置工程で設置した前記複数の二階床用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記一階部分の上で養生させる、二階床用の養生工程と、をさらに備えた、
     請求項1または2に記載の住宅の建築構法。
  7.  前記二階床用の設置工程は、前記一階部分を構成する前記複数の一階用パネルのうち、前記所定の目的強度を発現した一階用パネルの上から順に、前記複数の二階床用パネルを順次設置していく工程である、
     請求項6に記載の住宅の建築構法。
  8.  前記養生工程の期間の一部と、前記二階床用の設置工程の期間の一部が、互いに重なるように設けた、
     請求項7に記載の住宅の建築構法。
  9.  鉄筋コンクリート構造の複数の二階壁用パネルを、二階壁用の製造現場で順次製造する二階壁用の製造工程と、
     前記二階壁用の製造工程で製造した前記複数の二階壁用パネルを、所定の初期強度を発現した段階で、前記二階壁用の製造現場から前記建築現場にまで順次搬送する二階壁用の搬送工程と、
     前記建築現場に搬送された前記複数の二階壁用パネルを、前記所定の目的強度を発現した前記複数の二階床用パネルの上に順次設置し、前記床構造の上に、前記二階部分の壁構造を形成する二階壁用の設置工程と、
     前記二階壁用の設置工程で設置した前記複数の二階壁用パネルを、それぞれが前記所定の初期強度よりも高い所定の目的強度を発現するまで、前記床構造の上で養生させる二階壁用の養生工程と、をさらに備えた、
     請求項6~8のいずれか一項に記載の住宅の建築構法。
  10.  前記二階壁用の設置工程は、前記床構造を構成する前記複数の二階床用パネルのうち、前記所定の目的強度を発現した前記二階床用パネルの上から順に、前記複数の二階壁用パネルを順次設置していく工程である、
     請求項9に記載の住宅の建築構法。
  11.  前記二階床用の養生工程の期間の一部と、前記二階壁用の設置工程の期間の一部が、互いに重なるように設けた、
     請求項10に記載の住宅の建築構法。
  12.  前記住宅は、連棟式住宅である、
     請求項1~11のいずれか一項に記載の住宅の建築構法。
PCT/JP2015/001838 2015-01-30 2015-03-30 住宅の建築構法 WO2016120908A1 (ja)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2015016431A JP6417230B2 (ja) 2015-01-30 2015-01-30 住宅の建築構法
JP2015-016431 2015-07-23

Publications (1)

Publication Number Publication Date
WO2016120908A1 true WO2016120908A1 (ja) 2016-08-04

Family

ID=56542576

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2015/001838 WO2016120908A1 (ja) 2015-01-30 2015-03-30 住宅の建築構法

Country Status (3)

Country Link
JP (1) JP6417230B2 (ja)
MY (1) MY179216A (ja)
WO (1) WO2016120908A1 (ja)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022234461A1 (en) * 2021-05-03 2022-11-10 Baaj Mohamad Yasser Automated modular construction factory method and system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08323728A (ja) * 1995-06-05 1996-12-10 Taisei Prefab Kk プレキャストコンクリート板とその製造方法およびそのプレキャストコンクリート板を用いた建物
JP2000248614A (ja) * 1999-03-02 2000-09-12 Ando Corp 壁式プレキャストコンクリート造建物の接合部構造
JP2003074185A (ja) * 2001-09-06 2003-03-12 Okisou Kensetsu:Kk Pc部材の現場製造施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08323728A (ja) * 1995-06-05 1996-12-10 Taisei Prefab Kk プレキャストコンクリート板とその製造方法およびそのプレキャストコンクリート板を用いた建物
JP2000248614A (ja) * 1999-03-02 2000-09-12 Ando Corp 壁式プレキャストコンクリート造建物の接合部構造
JP2003074185A (ja) * 2001-09-06 2003-03-12 Okisou Kensetsu:Kk Pc部材の現場製造施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022234461A1 (en) * 2021-05-03 2022-11-10 Baaj Mohamad Yasser Automated modular construction factory method and system
US11794293B2 (en) 2021-05-03 2023-10-24 Mohamad Yasser Baaj Automated modular construction factory method and system

Also Published As

Publication number Publication date
JP2016141952A (ja) 2016-08-08
JP6417230B2 (ja) 2018-10-31
MY179216A (en) 2020-11-02

Similar Documents

Publication Publication Date Title
US11002003B2 (en) Lightweight steel parallel modular constructions system with synthetic modules
Kreiger et al. The current state of 3D printing for use in construction
Velamati Feasibility, benefits and challenges of modular construction in high rise development in the United States: a developer's perspective
Mydin et al. Investigation of industrialised building system performance in comparison to conventional construction method
WO2011021151A1 (en) Method and system for in-situ construction of civil structures
Mohammed Precast Concrete Cost Solution
Gunawardena et al. Sustainable prefabricated modular buildings
KR102154095B1 (ko) Pc세그먼트를 이용한 모듈형 조립식 주택 및 그 시공방법
EP3647508A1 (en) Improvements to a ventilated reinforced-concrete wall module for constructing buildings in general and respective industrialized construction system
Auti et al. Prefabrication technology-A promising alternative in construction industry
WO2016120908A1 (ja) 住宅の建築構法
KR101445286B1 (ko) 기준층의 공기단축이 가능한 pc-sf공법
AU2023219854A1 (en) Reinforcing framework and slab design
WO2011077006A2 (en) Method and apparatus for manufacturing a brick wall and a brick wall structure
van Boggelen et al. Sustainable building solutions with new generation autoclaved aerated concrete panel applications
KR101220211B1 (ko) 불연속 복선격자를 활용한 모듈러 코디네이션 설계 방법 및 모듈러 코디네이션 설계 방법을 이용하여 제작된 주택
CN115146369A (zh) 一种3d打印预制叠合楼板建造方法及系统
KR20160017842A (ko) 프리캐스트 콘크리트 골조와 단위객실의 캐빈유닛을 이용한 건축물의 복합화 시공방법
US20100050555A1 (en) Building Component and Method
CN203905279U (zh) 一种采用外保温的预制外墙板
Yusof et al. Adopting automation and robotics in Malaysian industrialised building system: An Asian perspectives
CN207892018U (zh) 一种预制装配式建筑结构
Pan Universal Construction System (UCS)
Adepoju et al. Prefabrication
AU2020200564A1 (en) Integrated formwork method for concrete structures

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: IDP00201602516

Country of ref document: ID

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15879809

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 15879809

Country of ref document: EP

Kind code of ref document: A1