WO2015168950A1 PCT/CN2014/077192 CN2014077192W WO2015168950A1 WO 2015168950 A1 WO2015168950 A1 WO 2015168950A1 CN 2014077192 W CN2014077192 W CN 2014077192W WO 2015168950 A1 WO2015168950 A1 WO 2015168950A1
Authority
WO
WIPO (PCT)
Prior art keywords
base station
uplink power
uplink
allocated
cell controlled
Prior art date
Application number
PCT/CN2014/077192
Other languages
English (en)
French (fr)
Inventor
贺传峰
曲秉玉
李秉肇
Original Assignee
华为技术有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 华为技术有限公司 filed Critical 华为技术有限公司
Priority to CN201480074079.0A priority Critical patent/CN105940732A/zh
Priority to PCT/CN2014/077192 priority patent/WO2015168950A1/zh
Publication of WO2015168950A1 publication Critical patent/WO2015168950A1/zh

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W52/00Power management, e.g. TPC [Transmission Power Control], power saving or power classes
    • H04W52/04TPC
    • H04W52/06TPC algorithms
    • H04W52/14Separate analysis of uplink or downlink

Definitions

  • the embodiments of the present invention relate to the field of mobile communications technologies, and in particular, to a UE, a base station, and an uplink power coordination method. Background technique
  • the power headroom of the UE is an important reference for the eNodeB (3G base station) to perform uplink scheduling on the UE.
  • the difference between the maximum transmit power and the calculated uplink power can be reported to the eNodeB through the PHR (Power Headroom Report), and the eNodeB can obtain the remaining power information of the UE according to this, and then determine the radio resource scheduled for the UE.
  • the estimated uplink power can be calculated on the UE side according to the power control command sent by the eNodeB and the path loss value obtained by measuring the downlink reference signal.
  • the UE may establish a connection with at least one base station at the same time, for example, in DC
  • a UE can simultaneously connect two cells (cells), which belong to different eNodeBs. At this time, each base station separately schedules the UE according to the power headroom reported by the UE.
  • the coordination of the base station power usage is particularly important. If the base stations are not coordinated, the sum of the powers of multiple carriers may exceed the maximum uplink power that the UE can allow. Or, the uplink power of the UE is not fully utilized, resulting in a waste of uplink power.
  • DC technology can be regarded as a kind of non-ideal backhaul (Carrier Aggregation). Since backhaul is non-ideal, the scheduling of a base station to the UE cannot be notified to another eNodeB through backhaul. Therefore, the eNodeB cannot interact with the power of the UE in time, and the effective coordination of the uplink power of the UE cannot be achieved.
  • backhaul Carrier Aggregation
  • the purpose of the embodiments of the present invention is to provide a UE, a base station, and an uplink power coordination method, to solve the technical problem that the base stations cannot achieve effective coordination in the uplink power usage of the UE.
  • a user equipment UE is provided, where the UE establishes a connection with at least one base station, where the UE includes:
  • a determining unit configured to determine, according to the specified information, uplink power allocated to each of the at least one base station, where the uplink power is power used by the UE for uplink transmission under each of the base stations;
  • a notification unit configured to notify the each base station of the uplink power allocated for each of the base stations.
  • the specified information includes at least one of the following information:
  • the uplink transmission request includes a bit rate requirement
  • the determining unit is specifically configured to: acquire the UE in each of the The bit rate requirement under the cell controlled by the base station determines the uplink power allocated to each of the base stations according to the bit rate requirement.
  • the determining unit is specifically configured to:
  • the determining unit is specifically configured to:
  • the determining unit is specifically configured to:
  • the notification unit is specifically configured to: report, by using the uplink power that is allocated to each of the base stations, a power headroom of each of the base stations to replace the maximum uplink power of the UE; or And determining, according to the uplink power allocated to each of the base stations, the number of resource block RBs that can be scheduled by each of the base stations, and reporting the number of the RBs to each of the base stations.
  • the notification unit is configured to report the number of the RBs to each of the base stations, The RB number is reported to each of the base stations by MAC signaling or physical layer signaling.
  • a second aspect provides an uplink power coordination method, where the method is used for a user equipment UE, and the UE establishes a connection with at least one base station, where the method includes:
  • the specified information includes at least one of the following information:
  • the uplink transmission request includes a bit rate requirement
  • the determining, according to the specified information, the allocation to each of the base stations Upstream power including:
  • the uplink power allocated to each of the base stations is determined according to the bit rate requirement.
  • the specified information includes the historical scheduling information of the UE in the cell controlled by each of the base stations, determining, according to the specified information, the uplink power allocated to each of the base stations, including: according to the historical scheduling Obtaining, by the information, the historical uplink power generated by the UE under the scheduling of each base station;
  • determining the uplink power allocated to each of the base stations according to the specified information includes:
  • the notifying the uplink power allocated to each of the base stations to each of the base stations includes:
  • the reporting the number of the RBs to each of the base stations includes:
  • a base station where the base station includes:
  • An acquiring unit configured to acquire uplink power allocated by the user equipment UE to the base station, where the uplink power is power used by the UE for uplink transmission by the UE, and the uplink power is determined by the UE according to the specified information.
  • a scheduling unit configured to perform uplink scheduling on the UE according to the uplink power allocated by the UE to the base station.
  • the specified The information includes at least one of the following information:
  • the uplink transmission request includes a bit rate requirement
  • the uplink power is determined by the UE according to the specified information, and includes:
  • the UE acquires a bit rate requirement under a cell controlled by the base station
  • the UE determines an uplink power allocated to the base station according to the bit rate requirement.
  • the uplink power is obtained by the UE according to the historical scheduling information, and the UE is generated under the scheduling of the base station.
  • Historical uplink power and determined based on the historical uplink power.
  • the uplink power is obtained by the UE according to the amount of data in the cache, and is allocated to the base station.
  • the proportion of the uplink power in the total uplink power of the UE is determined according to the proportion that should be occupied in the total uplink power of the UE. .
  • the uplink power is obtained by the UE according to the received system message of the cell controlled by the base station, and the carrier bandwidth information of the cell controlled by the base station is acquired. Obtaining, according to the carrier bandwidth information, a proportion of the uplink power allocated to the base station in the total uplink power of the UE, according to the total uplink of the UE The proportion of power should be determined.
  • the acquiring unit is specifically configured to: obtain an uplink power allocated by the UE to the base station according to a power headroom PH reported by the UE Or,
  • the acquiring unit is specifically configured to: receive, by the UE, the number of resource blocks RB that can be scheduled by the base station, to obtain uplink power allocated by the UE to the base station.
  • the acquiring unit is configured to receive, by the UE, the resource blocks RB that can be scheduled by the UE When used, it is specifically used to:
  • a fourth aspect provides an uplink power coordination method, where the method is used in a base station, and the method includes:
  • the uplink power is the power used by the UE for uplink transmission by the UE, and the uplink power is determined by the UE according to the specified information
  • the specified information includes at least one of the following information:
  • the amount of data in the cache when the UE sends uplink data under the base station is the amount of data in the cache when the UE sends uplink data under the base station.
  • Carrier bandwidth information of the cell controlled by the base station is Carrier bandwidth information of the cell controlled by the base station.
  • the uplink transmission request includes a bit rate requirement
  • the uplink power is used by the UE according to a cell controlled by the base station.
  • the bit rate requirements are determined.
  • the uplink power is obtained by the UE according to the historical scheduling information, and the UE is generated under the scheduling of the base station.
  • Historical uplink power and determined based on the historical uplink power.
  • the uplink power is obtained by the UE according to the amount of data in the cache, and is allocated to the base station.
  • the proportion of the uplink power in the total uplink power of the UE is determined according to the proportion that should be occupied in the total uplink power of the UE.
  • the uplink power is obtained by the UE according to the received system message of the cell controlled by the base station, and the carrier bandwidth information of the cell controlled by the base station is acquired. And obtaining, according to the carrier bandwidth information, a proportion of the uplink power allocated to the base station in the total uplink power of the UE, which is determined according to a proportion that should be occupied in the total uplink power of the UE.
  • the acquiring the uplink power allocated by the UE to the base station includes:
  • the receiving, by the UE, the number of resource blocks RB that can be scheduled by the base station includes: And receiving, by using MAC signaling or physical layer signaling, the number of resource blocks RB that are reported by the UE and that can be scheduled by the base station.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The manner in which the original UE passively obtains the uplink power to be used according to the scheduling of the base station is converted into how much uplink power is allocated to each base station by the UE according to some information, and the allocation result is reported to the corresponding base station, thereby being The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 1 is a schematic block diagram of a user equipment UE according to an embodiment of the present invention
  • FIG. 2 is a schematic diagram of a connection between a UE and a base station according to an embodiment of the present invention
  • FIG. 3 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention
  • FIG. 4 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention
  • FIG. 6 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention
  • FIG. 7 is an uplink power coordination method according to an embodiment of the present invention.
  • FIG. 8 is an exemplary block diagram of a base station according to an embodiment of the present invention.
  • FIG. 9 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention.
  • FIG. 10 is an exemplary block diagram of a user equipment UE according to an embodiment of the present invention.
  • FIG. 11 is an exemplary block diagram of a base station according to an embodiment of the present invention.
  • the first method may be to enable a base station to obtain related information of another base station in a manner similar to information sharing, for example, in a dual connectivity technology, two eNodeBs (MeNodeB, Master eNodeB, primary base station; SeNodeB, Secondary eNodeB, secondary base station)
  • the RRC (Radio Resource Control) function is controlled by the RRC of the MeNodeB, so the RRC configuration information of the SeNodeB is known to the MeNodeB, in other words, the power control used by the UE in calculating the PH under the SeNodeB
  • the RRC configuration parameters are known to MeNodeB.
  • the independent RRC of the MeNodeB and the SeNodeB is a big trend, and the two base stations constituting the dual connection will maintain a certain independence, so in the future, the RRC configuration information Etc. For two eNodeBs it will most likely be mutually unknown.
  • the second method may be to enable direct signaling communication between the two base stations to implement interaction.
  • the number of UEs in a normal base station is large. If the configuration information of each UE is transmitted through a signaling interface, the signaling load is inevitably large, and it is difficult to be feasible.
  • a third method may be to forward the RRC configuration information of one eNodeB to another eNodeB by means of the UE.
  • this method if this method is adopted, the UE needs to forward a large amount of information, the uplink overhead for the UE is relatively large, affecting the uplink throughput, and on the other hand, even if the UE can forward the configuration information, due to the foregoing independent RRC scenario.
  • the difficulty of interaction between the eNodeBs an eNodeB cannot coordinate the scheduling of the UE by another eNodeB through the signaling interface of the eNodeB according to the configuration information.
  • FIG. 1 is an exemplary block diagram of a user equipment UE provided in an embodiment of the present invention.
  • the UE establishes a connection with at least one base station, as shown in FIG. 2.
  • the UE may include:
  • a determining unit 101 configured to determine, according to the specified information, uplink power allocated to each of the at least one base station, where the uplink power is power used by the UE for uplink transmission at each of the base stations;
  • the notifying unit 102 is configured to notify the each base station of the uplink power allocated to each of the base stations.
  • the specifying information may include at least one of the following information:
  • the historical scheduling information of the UE in the cell controlled by each of the base stations where the historical scheduling information is scheduling information scheduled by the UE by each of the base stations in a period of time before the current time;
  • the uplink transmission request includes a bit rate requirement
  • the determining unit 101 may be specifically configured to:
  • the determining unit 101 may be specifically configured to:
  • the determining unit 101 may be specifically configured to:
  • the determining unit 101 may be specifically configured to:
  • the notification unit 102 may be specifically configured to: perform power headroom PH reporting on each of the base stations by replacing the maximum uplink power of the UE with the uplink power allocated by each of the base stations; or, the notification unit 102 may be specifically configured to: according to the uplink work allocated for each of the base stations Rate, determine the number of resource block RBs that can be scheduled by each of the base stations, and report the number of RBs to each of the base stations.
  • the notification unit 102 is configured to: when reporting the number of RBs to each of the base stations, specifically, by: performing MAC signaling or physical layer signaling. And reporting the number of RBs to each of the base stations.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 3 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention. The method is used for a user equipment UE, and the UE establishes a connection with at least one base station. Referring to FIG. 3, the method may include:
  • S301 Determine uplink power allocated to each of the at least one base station according to the specified information, where the uplink power is power used by the UE for uplink transmission under each of the base stations.
  • the basic idea of this embodiment is to actively allocate the uplink power on the UE side, and then notify the base station of the allocation result, thereby avoiding the problem of difficulty in coordination between the base stations.
  • the UE can make a decision on how to perform uplink power allocation by using some specified information that is known by the UE.
  • some specified information that is known by the UE.
  • the embodiment does not need to be limited, and may be determined according to a specific scenario.
  • the specifying information may include at least one of the following information:
  • the above four types of specified information can reflect the uplink power of the UE to some extent. According to one of the four specified information, or a combination of two or more, the UE can determine which base station should be allocated for which power. .
  • the base station After the base station obtains the uplink power allocated by the UE, it is equivalent to knowing the limitation of the UE, which is similar to the maximum uplink power of the UE (or even the uplink power directly allocated to the UE). It is erroneously described as "the maximum uplink power of the UE.” Therefore, the scheduling mode of the UE can be determined according to the prior art.
  • the present embodiment is not limited to how to notify the uplink power to a base station.
  • the UE can notify the base station of the uplink power allocated by the base station by means of various existing methods for communicating with the base station.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • the above specified information is further illustrated below.
  • FIG. 4 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention.
  • the uplink transmission request may include a bit rate requirement, and the determining is determined according to the specified information.
  • the uplink power allocated by each of the base stations, that is, step S301, may include:
  • S402. Determine, according to the bit rate requirement, an uplink power allocated to each of the base stations.
  • the network side can configure the lowest bit rate of the UE in one cell.
  • the RRC function of the two eNodeBs is controlled by the RRC of the MeNodeB.
  • the control plane data of the UE is always sent to the MeNodeB, so that the UE needs to be the MeNodeB when allocating the uplink power.
  • the allocated uplink power should enable the UE to guarantee bits under the MeNodeB
  • the rate is uplinked, which is the bit rate requirement of the MeNodeB to the UE.
  • an eNodeB can also determine and inform the UE of the guaranteed bit rate under the eNodeB according to the service established with the UE.
  • the UE allocates power to the eNodeB, the allocated power should at least satisfy the UE for uplink transmission at the guaranteed bit rate notified by the eNodeB.
  • the bit rate requirement can be embodied in some scenarios as a required transport block size requirement for one subframe.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 5 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention. As shown in FIG. 5, when the specified information includes historical scheduling information of the UE under the cell controlled by each of the base stations, determining, according to the specified information, uplink power allocated to each of the base stations, that is, Step S301, which may include:
  • S502. Determine, according to the historical uplink power, an uplink power allocated to each of the base stations.
  • the UE may perform according to the eNodeB pair.
  • the historical scheduling situation of the UE determines the uplink power allocated by the UE to the eNodeB.
  • the uplink power that the UE consumes or is used for each time under the scheduling of the eNodeB can be derived, and then the uplink power that should be allocated for the eNodeB is determined.
  • the uplink power that the UE pays under the scheduling of the eNodeB has a direct record on the UE side, the UE can also make a decision according to the record without recalculating.
  • Pl, P2 and P3 can be obtained by the following formula (1), that is, the PUSCH power calculation formula.
  • P CMAX . ( ) is the maximum transmit power configured by the UE when there is a PUSCH channel transmission on the subframe i of the cell c; M PUSCH .
  • a c (j) V
  • PL c the path loss of the serving cell c measured by the UE.
  • ⁇ ( ) is the transmission format compensation value; _;( ) is the closed-loop power control adjustment value, which is determined by the power control command sent by the base station.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 6 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention. Referring to FIG.
  • the uplink power may include:
  • the S602. Determine an uplink power allocated to each of the base stations according to the proportion that should be occupied by the total uplink power of the UE.
  • the data buffer of the UE is used to buffer the uplink data to be sent.
  • the buffer of the UE is unique, and the data in the buffer is transmitted through different base stations.
  • the UE may have one buffer for each base station, and the data in each buffer can only be sent through the corresponding base station.
  • the amount of data in the buffer of the UE for one base station represents the number of data transmission requirements of the UE under the base station.
  • the buffer occupancy is full, meaning that the UE needs to use more power for the data transmission at the base station. Therefore, the power allocation of the UE at each base station can be proportional to the amount of data in the buffer corresponding to each base station.
  • one way is that the UE's allocation of uplink power is proportional to the amount of buffer data of each base station.
  • P el and P e2 are uplink powers allocated by the UE to the base station 1 and the base station 2, respectively.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 7 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention. Referring to FIG. 7 , when the specified information includes the carrier bandwidth information of the cell controlled by each of the base stations, determining, according to the specified information, the uplink power allocated to each of the base stations, that is, step S301, Includes:
  • S702 Obtain, according to the carrier bandwidth information, a proportion of uplink power allocated to each base station in a total uplink power of the UE; S703. Determine an uplink power allocated to each of the base stations according to the proportion that should be occupied by the total uplink power of the UE.
  • the carrier bandwidth of a cell means that how many time-frequency resources can be scheduled for the UE to use for uplink transmission. The wider the bandwidth of the cell, the more time-frequency resources are scheduled for the UE, so the UE may need to allocate more power to the cell with a large carrier bandwidth.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE. After determining how the UE uplink power is allocated, the remaining problem is how to notify the corresponding base station of the allocation result.
  • the UE may notify the base station of the uplink power allocated by the base station by using various existing methods, which is not limited in this embodiment. As an example:
  • the notifying the uplink power allocated to each of the base stations to each of the base stations may include:
  • the UE may perform power headroom PH reporting to the base station.
  • the maximum uplink power of the UE is an important parameter, and the UE performs the PH calculation according to the maximum uplink power.
  • the UE still uses the original PH reporting mechanism, but, for the largest The parameter of the uplink power is not assigned as it is, but is replaced by the uplink power allocated by the base station as the maximum uplink power, and participates in the PH reporting mechanism, so that the base station obtains the allocated by means of the PH reporting mechanism.
  • the uplink power determines the scheduling mode for the UE.
  • the PH calculation can be performed according to various existing formulas. For example, in carrier aggregation, two types of power headroom PHs are defined, which are classified into Typel and Type2.
  • the UE When the UE simultaneously transmits the PUSCH and the PUCCH on the subframe i of the Pcell (ie, the primary cell, which refers to the cell c in the following formula),
  • P. - PuccH is the open loop power control adjustment value, which is determined by the RRC configuration parameters
  • g (0 is the closed loop power control adjustment value, which is determined by the power control command sent by the base station.
  • the corresponding P CMAX» (or ⁇ » ) in the above formulas (2) ⁇ (6) can be replaced by the assigned uplink power value, and then the calculated ⁇ is reported to the existing PHR mechanism. Base station.
  • the eNB may perform scheduling on the UE according to the ,, and the scheduling process belongs to the prior art, and is not described in this embodiment.
  • the UE can calculate the required transmit power of the PUSCH channel in the case of different RBs, the UE can determine the power allocated by the UE in the cell by determining the number of RBs of the PUSCH that can be scheduled by each cell. .
  • the base station After receiving the number of resource block RBs that the UE can be scheduled by the base station, the base station can determine the scheduling rule for the UE based on the number of the RBs, for example, the number of the RBs should not exceed the number of the RBs.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 8 is an exemplary block diagram of a base station according to an embodiment of the present disclosure, where the base station may include:
  • the obtaining unit 801 is configured to obtain uplink power allocated by the user equipment UE to the base station, where the uplink power is power used by the UE for uplink transmission at the base station, and the uplink power is specified by the UE according to the Information determination;
  • the scheduling unit 802 is configured to perform uplink scheduling on the UE according to the uplink power allocated by the UE to the base station.
  • the specified information includes at least one of the following information:
  • the uplink transmission request includes a bit rate requirement, where the uplink power is determined by the UE according to a cell controlled by the base station.
  • the bit rate requirement is determined.
  • the uplink power is obtained by the UE according to the historical scheduling information, and the UE is generated under the scheduling of the base station.
  • Historical uplink power and determined based on the historical uplink power.
  • the uplink power is obtained by the UE according to the amount of data in the cache, and is allocated to the base station.
  • the ratio of the uplink power to the total uplink power of the UE is determined according to the proportion that should be occupied by the total uplink power of the UE.
  • the uplink power is obtained by the UE according to the received system message of the cell controlled by the base station, and the base is obtained.
  • the carrier bandwidth information of the cell controlled by the station according to the carrier bandwidth information, the proportion of the uplink power allocated to the base station in the total uplink power of the UE, which should be occupied according to the total uplink power of the UE. The ratio is determined.
  • the acquiring unit 801 is specifically configured to: obtain, according to the power headroom PH reported by the UE, uplink power allocated by the UE to the base station; or
  • the acquiring unit is specifically configured to: receive, by the UE, the number of resource block RBs that can be scheduled by the base station, to obtain uplink power allocated by the UE to the base station.
  • the acquiring unit is configured to: when receiving, by the UE, the number of resource blocks RB that can be scheduled by the UE, specifically:
  • the number of resource blocks RB that can be scheduled by the UE and is scheduled by the UE is received by MAC signaling or physical layer signaling.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 9 is an exemplary flowchart of an uplink power coordination method according to an embodiment of the present invention. The method can be applied to a base station, and the method includes:
  • S901 Obtain an uplink power allocated by the user equipment UE to the base station, where the uplink power is used by the UE for uplink transmission, and the uplink power is determined by the UE according to the specified information.
  • S902 Perform uplink scheduling on the UE according to the uplink power allocated by the UE to the base station.
  • the scheduling mode of the UE may be determined according to the prior art, which is not described in this embodiment.
  • the specified information includes at least one of the following Information:
  • the amount of data in the cache when the UE sends uplink data under the base station is the amount of data in the cache when the UE sends uplink data under the base station.
  • Carrier bandwidth information of the cell controlled by the base station is Carrier bandwidth information of the cell controlled by the base station.
  • the uplink transmission request includes a bit rate requirement, where the uplink power is determined by the UE according to a cell controlled by the base station.
  • the bit rate requirement is determined.
  • the specified information includes historical uplink power generated by the base station scheduling of the historical scheduling information of the UE under the cell controlled by the base station, and determined according to the historical uplink power.
  • the uplink power is obtained by the UE according to the amount of data in the cache, and is allocated to the base station.
  • the ratio of the uplink power to the total uplink power of the UE is determined according to the proportion that should be occupied by the total uplink power of the UE.
  • the uplink power is obtained by the UE according to the received system message of the cell controlled by the base station, and the carrier bandwidth information of the cell controlled by the base station is acquired. And obtaining, according to the carrier bandwidth information, a proportion of the uplink power allocated to the base station in the total uplink power of the UE, which is determined according to a proportion that should be occupied in the total uplink power of the UE.
  • the acquiring uplink power allocated by the UE to the base station includes:
  • the base station may schedule the UE by scheduling the number of RBs that cannot be exceeded by the number of RBs reported by the UE.
  • the receiving, by the UE, the number of resource blocks RB that may be scheduled by the base station includes:
  • the number of resource blocks RB that can be scheduled by the UE and is scheduled by the UE is received by MAC signaling or physical layer signaling.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 10 is an exemplary block diagram of a user equipment UE provided in an embodiment of the present invention.
  • the UE can include: a processor 1002 and a transmitter 1001.
  • the processor 1002 is configured to: determine uplink power allocated to each of the at least one base station according to the specified information, where the uplink power is used by the UE for uplink transmission under each of the base stations The power of the uplink power allocated to each of the base stations to each of the base stations;
  • the transmitter 1001 is configured to send the uplink power.
  • the specified information includes at least one of the following information:
  • the uplink transmission request includes a bit rate requirement
  • the processor 1002 may be specifically configured to: acquire the UE in the The bit rate requirement under the cell controlled by each base station;
  • the uplink power allocated to each of the base stations is determined according to the bit rate requirement.
  • the processor 1002 may be specifically configured to:
  • the processor 1002 may be specifically configured to:
  • the processor 1002 may be specifically configured to:
  • the processor 1002 may be specifically configured to: replace, by using the uplink power allocated by each of the base stations, a maximum uplink power of the UE.
  • Each base station performs power headroom PH reporting;
  • the processor 1002 may be specifically configured to: report the number of the RBs to each of the base stations by using MAC signaling or physical layer signaling.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and the UE determines how much uplink power is allocated to each base station according to some information, and reports the allocation result to the corresponding base station, thereby The side solves the problem that each base station coordinates the uplink power of the UE.
  • FIG. 11 is an exemplary block diagram of a base station provided in an embodiment of the present invention.
  • the base station can include: a processor 1102 and a receiver 1101.
  • the processor 1102 is configured to: obtain uplink power allocated by the user equipment UE to the base station, where the uplink power is power used by the UE for uplink transmission under the base station, and the uplink power is Determining, according to the specified information, the UE performs uplink scheduling on the UE according to the uplink power allocated by the UE to the base station;
  • the receiver 1101 is configured to receive uplink power sent by the UE.
  • the specified information includes at least one of the following information:
  • the uplink transmission requirement includes a bit rate requirement
  • the uplink power is determined by the UE according to a bit rate requirement under a cell controlled by the base station.
  • the specified information includes historical uplink power generated by the base station scheduling of the historical scheduling information of the UE under the cell controlled by the base station, and determined according to the historical uplink power.
  • the uplink power is obtained by the UE according to the amount of data in the cache, and is allocated to the base station.
  • the ratio of the uplink power to the total uplink power of the UE is determined according to the proportion that should be occupied by the total uplink power of the UE.
  • the uplink power is obtained by the UE according to the received system message of the cell controlled by the base station, and the carrier bandwidth information of the cell controlled by the base station is acquired. And obtaining, according to the carrier bandwidth information, a proportion of the uplink power allocated to the base station in the total uplink power of the UE, which is determined according to a proportion that should be occupied in the total uplink power of the UE.
  • the processor 1102 is specifically configured to: obtain, according to the power headroom PH reported by the UE, uplink power allocated by the UE to the base station; or
  • the processor 1102 is specifically configured to: receive, by using MAC signaling or physical layer signaling, a resource block RB that is reported by the UE and may be scheduled by the base station. number.
  • the base station is not used as a starting point to consider how to deal with the coordination problem of the uplink power of the UE, but instead, the idea of directly transmitting the uplink power of the UE for each base station is directly performed on the UE side, that is, The original UE passively obtains the uplink power to be used according to the scheduling of the base station, and converts to how much uplink power the UE allocates for each base station according to some information. The result of the allocation is reported to the corresponding base station, so that the problem of coordination of the uplink power of each base station is solved in the UE side.

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Mobile Radio Communication Systems (AREA)

Abstract

UE、基站及上行功率协调方法,所述UE与至少一个基站建立连接,包括:确定单元,用于根据指定信息,确定为所述至少一个基站中的每个基站分配的上行功率,其中所述上行功率为所述UE在所述每个基站下用于上行传输的功率;通知单元,用于将所述为所述每个基站分配的上行功率通知给所述每个基站。本发明中不再以基站为出发点考虑如何处理UE 上行功率的协调问题,而是直接在UE侧主动针对每个基站进行本UE上行功率的分配,即,将原先的UE根据基站的调度被动得到应使用的上行功率的方式,转变为UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分配结果分别上报给相应的基站,从而解决了各基站在UE 上传功率协调上的难题。

Description

UE、 基站及上行功率协调方法 技术领域
本发明实施例涉及移动通讯技术领域, 尤其是涉及 UE、基站及上行功 率协调方法。 背景技术
在无线通讯系统中, 例如 LTE ( Long Term Evolution , 长期演进) 系统 中, UE (用户设备) 的 ΡΗ ( Power Headroom, 功率余量)是 eNodeB ( 3G 基站)对 UE进行上行调度的重要参考, UE可以通过 PHR( Power Headroom Report, 功率余量上报) 将自身的最大发射功率与计算的上行功率之差上 报给 eNodeB , eNodeB可以据此获得 UE的剩余功率信息, 从而再决定为 UE调度的无线资源。 其中, 在 UE侧可以根据 eNodeB发送的功控指令及 测量下行参考信号得到的路损值等计算得到预计的上行功率。
在一些场景中, UE 可以同时与至少一个基站建立连接, 例如在 DC
( Dual Connectivity, 双连接 )技术中, UE可以同时连接两个 Cell (小区), 这两个小区分属于不同的 eNodeB。 此时, 每个基站会分别根据 UE上报的 功率余量对 UE进行调度。 然而, 在这些场景下, 各基站在使用 UE功率问 题上的协调尤为重要, 若各基站未协调好, 则可能会出现多个载波的功率 之和已超过了 UE可以允许的最大上行功率的情况,或者出现 UE的上行功 率未被充分利用, 导致上行功率存在浪费的情况。
DC 技术可以看作是一类非理想 backhaul (回程) 下的 CA ( Carrier Aggregation, 载波聚合), 由于 backhaul 是非理想的, 会导致一个基站对 UE的调度情况不能通过 backhaul及时的通知给另一个 eNodeB , 从而造成 eNodeB之间不能及时地交互对于 UE的功率的使用情况, 也就在对 UE上 行功率的使用问题上无法实现有效的协调。
发明内容 有鉴于此, 本发明实施例的目的是提供 UE、 基站及上行功率协调方法, 以解决在 UE上行功率使用上各基站无法实现有效协调的技术问题。
为了解决上述技术问题, 本发明实施例公开了如下技术方案: 第一方面, 提供一种用户设备 UE , 所述 UE与至少一个基站建立连接, 所述 UE包括:
确定单元, 用于根据指定信息, 确定为所述至少一个基站中的每个基 站分配的上行功率, 其中所述上行功率为所述 UE在所述每个基站下用于上 行传输的功率;
通知单元, 用于将所述为所述每个基站分配的上行功率通知给所述每 个基站。
结合第一方面, 在第一方面的第一种可能的实现方式中, 所述指定信 息包括如下至少一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和, 所述每个基站控制的小区的载波带宽信息。
结合第一方面的第一种可能的实现方式, 在第一方面的第二种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传输 要求时, 所述上行传输要求包括比特速率要求, 所述确定单元具体用于: 获取 UE在所述每个基站控制的小区下的比特速率要求, 根据所述比特 速率要求, 确定为所述每个基站分配的上行功率。
结合第一方面的第一种可能的实现方式, 在第一方面的第三种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调度 信息时, 所述确定单元具体用于:
根据所述历史调度信息, 获取所述 UE在所述每个基站调度下产生的历 史上行功率, 根据所述历史上行功率, 确定为所述每个基站分配的上行功 率。 结合第一方面的第一种可能的实现方式, 在第一方面的第四种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的緩 存中的数据量时, 所述确定单元具体用于:
根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所 述 UE总上行功率中应占的比例, 根据所述在所述 UE总上行功率中应占的比 例, 确定为所述每个基站分配的上行功率。
结合第一方面的第一种可能的实现方式, 在第一方面的第五种可能的 实现方式中:
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时, 所 述确定单元具体用于:
根据接收的所述每个基站控制的小区的系统消息, 获取所述每个基站 控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述每个基 站控制的小区分配的上行功率在所述 U E总上行功率中应占的比例, 根据所 述在所述 UE总上行功率中应占的比例, 确定为所述每个基站分配的上行功 率。
结合第一方面, 在第一方面的第六种可能的实现方式中:
所述通知单元具体用于: 以所述为所述每个基站分配的上行功率替换 所述 UE的最大上行功率对所述每个基站进行功率余量 ra上报; 或者, 所述 通知单元具体用于: 根据所述为所述每个基站分配的上行功率, 确定可被 所述每个基站调度的资源块 RB个数,并将所述 RB个数上报给所述每个基站。
结合第一方面的第六种可能的实现方式, 在第一方面的第七种可能的 实现方式中, 所述通知单元用于将所述 RB个数上报给所述每个基站时, 具 体用于: 通过 MAC信令或物理层信令, 将所述 RB个数上报给所述每个基站。 第二方面, 提供一种上行功率协调方法, 所述方法用于用户设备 UE , 所述 UE与至少一个基站建立连接, 所述方法包括:
根据指定信息, 确定为所述至少一个基站中的每个基站分配的上行功 率, 其中所述上行功率为所述 UE在所述每个基站下用于上行传输的功率; 将所述为所述每个基站分配的上行功率通知给所述每个基站。 结合第二方面, 在第二方面的第一种可能的实现方式中, 所述指定信 息包括如下至少一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和, 所述每个基站控制的小区的载波带宽信息。
结合第二方面的第一种可能的实现方式, 在第二方面的第二种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传输 要求时, 所述上行传输要求包括比特速率要求, 所述根据指定信息, 确定 为所述每个基站分配的上行功率, 包括:
获取 UE在所述每个基站控制的小区下的比特速率要求;
根据所述比特速率要求, 确定为所述每个基站分配的上行功率。
结合第二方面的第一种可能的实现方式, 在第二方面的第三种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调度 信息时, 所述根据指定信息, 确定为所述每个基站分配的上行功率, 包括: 根据所述历史调度信息, 获取所述 UE在所述每个基站调度下产生的历 史上行功率;
根据所述历史上行功率, 确定为所述每个基站分配的上行功率。
结合第二方面的第一种可能的实现方式, 在第二方面的第四种可能的 实现方式中:
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的緩 存中的数据量时, 所述根据指定信息, 确定为所述每个基站分配的上行功 率, 包括:
根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所 述 UE总上行功率中应占的比例;
根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基站分 配的上行功率。
结合第二方面的第一种可能的实现方式, 在第二方面的第五种可能的 实现方式中
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时, 所 述根据指定信息, 确定为所述每个基站分配的上行功率, 包括:
根据接收的所述每个基站控制的小区的系统消息, 获取所述每个基站 控制的小区的载波带宽信息;
根据所述载波带宽信息, 获取为所述每个基站分配的上行功率在所述 UE总上行功率中应占的比例;
根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基站分 配的上行功率。
结合第二方面, 在第二方面的第六种可能的实现方式中, 所述将所述 为所述每个基站分配的上行功率通知给所述每个基站, 包括:
以所述为所述每个基站分配的上行功率替换所述 UE的最大上行功率对 所述每个基站进行功率余量 ra上报;
或者,
根据所述为所述每个基站分配的上行功率, 确定可被所述每个基站调 度的资源块 RB个数, 并将所述 RB个数上报给所述每个基站。
结合第二方面的第六种可能的实现方式, 在第二方面的第七种可能的 实现方式中, 所述将所述 RB个数上报给所述每个基站, 包括:
通过 MAC信令或物理层信令, 将所述 RB个数上报给所述每个基站。 第三方面, 提供一种基站, 所述基站包括:
获取单元, 用于获取用户设备 UE为所述基站分配的上行功率, 其中所 述上行功率为所述 UE在所述基站下用于上行传输的功率, 所述上行功率由 所述 UE根据指定信息确定;
调度单元, 用于根据所述 UE为所述基站分配的上行功率, 对所述 UE进 行上行调度。
结合第三方面, 在第三方面的第一种可能的实现方式中, 所述指定信 息包括如下至少一种信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下用于发送上行数据的緩存中的数据量; 和, 所述基站控制的小区的载波带宽信息。
结合第三方面的第一种可能的实现方式, 在第三方面的第二种可能的 实现方式中:
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要求 时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE根据指 定信息确定, 包括:
所述 UE获取在所述基站控制的小区下的比特速率要求;
所述 UE根据所述比特速率要求, 确定为所述基站分配的上行功率。 结合第三方面的第一种可能的实现方式, 在第三方面的第三种可能的 实现方式中:
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信息 时, 所述上行功率由所述 UE根据所述历史调度信息, 获取所述 UE在所述基 站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
结合第三方面的第一种可能的实现方式, 在第三方面的第四种可能的 实现方式中:
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存中 的数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取为所 述基站分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE 总上行功率中应占的比例确定的。。
结合第三方面的第一种可能的实现方式, 在第三方面的第五种可能的 实现方式中:
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上 行功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述基 站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基站 分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总上行 功率中应占的比例确定的。
结合第三方面, 在第三方面的第六种可能的实现方式中, 所述获取单 元具体用于: 根据所述 UE上报的功率余量 PH , 获取所述 UE为所述基站分配 的上行功率; 或者,
所述获取单元具体用于: 接收所述 UE上报的可为所述基站调度的资源 块 RB个数以获取所述 UE为所述基站分配的上行功率。
结合第三方面的第六种可能的实现方式, 在第三方面的第七种可能的 实现方式中, 所述获取单元用于接收所述 UE上报的可为所述基站调度的资 源块 RB个数时, 具体用于:
通过 MAC信令或物理层信令,接收所述 UE上报的可为所述基站调度的资 源块 RB个数。 第四方面, 提供一种上行功率协调方法, 所述方法用于基站, 所述方 法包括:
获取用户设备 UE为所述基站分配的上行功率, 其中所述上行功率为所 述 UE在所述基站下用于上行传输的功率, 所述上行功率由所述 UE根据指定 信息确定;
根据所述 UE为所述基站分配的上行功率, 对所述 UE进行上行调度。 结合第四方面, 在第四方面的第一种可能的实现方式中, 所述指定信 息包括如下至少一种信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下发送上行数据时緩存中的数据量; 和,
所述基站控制的小区的载波带宽信息。
结合第四方面的第一种可能的实现方式, 在第四方面的第二种可能的 实现方式中:
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要求 时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE根据在 所述基站控制的小区下的比特速率要求确定的。 结合第四方面的第一种可能的实现方式, 在第四方面的第三种可能的 实现方式中:
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信息 时, 所述上行功率由所述 UE根据所述历史调度信息, 获取所述 UE在所述基 站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
结合第四方面的第一种可能的实现方式, 在第四方面的第四种可能的 实现方式中:
当所述指定信息包括所述 UE 在所述基站下用于发送上行数据的緩存 中的数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取 为所述基站分配的上行功率在所述 UE 总上行功率中应占的比例, 根据在 所述 UE总上行功率中应占的比例确定的。 结合第四方面的第一种可能的实现方式, 在第四方面的第五种可能的 实现方式中:
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上 行功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述 基站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基 站分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总 上行功率中应占的比例确定的。
结合第四方面, 在第四方面的第六种可能的实现方式中, 所述获取 UE 为所述基站分配的上行功率, 包括:
根据所述 UE上报的功率余量 PH , 获取所述 UE为所述基站分配的上行功 率; 或者,
接收所述 UE上报的可为所述基站调度的资源块 RB个数以获取所述 UE为 所述基站分配的上行功率。
结合第四方面的第六种可能的实现方式, 在第四方面的第七种可能的 实现方式中, 所述接收所述 UE上报的可为所述基站调度的资源块 RB个数, 包括: 通过 MAC信令或物理层信令,接收所述 UE上报的可为所述基站调度的资 源块 RB个数。 本发明的一些有益效果可以包括:
在本发明实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的 协调问题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE 上行功率的分配, 即, 将原先的 UE根据基站的调度被动得到应使用的上行 功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上 行功率, 并将分配结果分别上报给相应基站, 从而在 UE侧一举解决了各基 站在 UE上传功率协调上的难题。
应当理解的是, 以上的一般描述和后文的细节描述仅是示例性的, 并 不能限制本发明的保护范围。
附图说明 为了更清楚地说明本发明实施例或现有技术中的技术方案, 下面将对 实施例或现有技术描述中所需要使用的附图作简单地介绍, 显而易见地, 下面描述中的附图仅仅是本发明的一些实施例, 对于本领域普通技术人员 来讲, 在不付出创造性劳动的前提下, 还可以根据这些附图获得其他的附 图。
图 1是本发明实施例中提供的一种用户设备 UE的示例性框图; 图 2是本发明实施例中 UE与基站连接示意图;
图 3是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 4是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 5是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 6是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 7是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 8是本发明实施例提供的一种基站的示例性框图;
图 9是本发明实施例提供的一种上行功率协调方法的示例性流程图; 图 10是本发明实施例提供的一种用户设备 UE的示例性框图; 图 11是本发明实施例提供的一种基站的示例性框图。
通过上述附图, 已示出本发明明确的实施例, 后文中将有更详细的描
具体实施方式 下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清 楚、 完整地描述, 显然, 所描述的实施例仅仅是本发明一部分实施例, 而不是 全部的实施例。基于本发明中的实施例, 本领域普通技术人员在没有作出创造 性劳动前提下所获得的所有其他实施例, 都属于本发明保护的范围。
为了全面理解本发明,在以下详细描述中提到了众多具体的细节,但是本 领域技术人员应该理解, 本发明可以无需这些具体细节而实现。在其他实施例 中, 不详细描述公知的方法、 过程、 组件和电路, 以免不必要地导致实施例模 糊。 为了解决在 UE上行功率使用上各基站无法有效协调的问题,可以想办法 使一个基站通过获知 UE在另一个基站下的 PH和 PH对应的信道配置信息等 信息而获知该 UE在另一基站下的功率使用情况, 进而协调对该 UE的调度, 以更加合理的使用 UE的发射功率。
第一种办法可以是通过类似信息共享的方式使一基站获得另一基站的相 关信息, 例如在双连接技术中, 两个 eNodeB ( MeNodeB, Master eNodeB , 主 基站; SeNodeB, Secondary eNodeB , 辅基站)的 RRC (无线资源控制)功能 由其中的 MeNodeB 的 RRC 控制, 因此 SeNodeB 的 RRC 配置信息对于 MeNodeB来说是已知的,换句话说, UE在计算 SeNodeB下的 PH时用到的与 功率控制相关的 RRC配置参数对于 MeNodeB来说是已知的。 然而, 在未来 网络部署中, 以双连接技术为例, MeNodeB和 SeNodeB釆用独立的 RRC是 很大的趋势, 组成双连接的两基站将会保持一定的独立性, 因此在未来, RRC 配置信息等对于两个 eNodeB来说将很可能是相互未知的。
第二种办法可以是令两基站之间直接进行信令通信实现交互。然而由于通 常基站下的 UE数量众多,若每个 UE的配置信息等都通过信令接口传输的话, 其信令负荷必然会很大, 很难具备可行性。
第三种办法可以是借助 UE把一个 eNodeB的 RRC配置信息转发给另一个 eNodeB。 然而, 一方面, 若釆取这种办法则需要 UE转发大量的信息, 对于 UE的上行开销比较大, 影响上行吞吐量, 而且另一方面, 即使 UE可以转发 这些配置信息, 由于前述独立 RRC 场景下 eNodeB 之间交互的困难, 一个 eNodeB 也无法根据这些配置信息, 通过 eNodeB 的信令接口协调另一个 eNodeB对 UE的调度。
可见,使用现有技术始终无法解决上述在对 UE上行功率使用时的协调问 题。 而本发明实施例则改变了传统思维, 从 UE侧入手进行研究, 解决了这一 难题。 图 1是本发明实施例中提供的一种用户设备 UE的示例性框图。 所述 UE 与至少一个基站建立连接, 可参见图 2所示。
在本实施例中, 所述 UE可以包括:
确定单元 101 , 用于根据指定信息, 确定为所述至少一个基站中的每个基 站分配的上行功率,其中所述上行功率为所述 UE在所述每个基站下用于上行 传输的功率;
通知单元 102 , 用于将所述为所述每个基站分配的上行功率通知给所述每 个基站。
在本实施例或本发明其他某些实施例中,所述指定信息可以包括如下至少 一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息,其中所述历史调 度信息为当前时间之前的一段时间内所述 UE被所述每个基站调度的调度信 息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和, 所述每个基站控制的小区的载波带宽信息。
在本实施例或本发明其他某些实施例中, 当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传输要 求时, 所述上行传输要求包括比特速率要求, 所述确定单元 101具体可以用 于:
获取 UE在所述每个基站控制的小区下的比特速率要求,根据所述比特速 率要求, 确定为所述每个基站分配的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调度信 息时, 所述确定单元 101具体可以用于:
根据所述历史调度信息,获取所述 UE在所述每个基站调度下产生的历史 上行功率, 根据所述历史上行功率, 确定为所述每个基站分配的上行功率, 其 中所述历史上行功率为当前时刻之前的一段时间内所述 UE被所述每个基站调 度时的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的緩存 中的数据量时, 所述确定单元 101具体可以用于:
根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所述 UE总上行功率中应占的比例,根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基站分配的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时,所述确 定单元 101具体可以用于:
根据接收的所述每个基站控制的小区的系统消息,获取所述每个基站控制 的小区的载波带宽信息,根据所述载波带宽信息, 获取为所述每个基站控制的 小区分配的上行功率在所述 UE 总上行功率中应占的比例, 根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基站分配的上行功率。
在本实施例或本发明其他某些实施例中,
所述通知单元 102具体可以用于:以所述为所述每个基站分配的上行功率 替换所述 UE的最大上行功率对所述每个基站进行功率余量 PH上报; 或者, 所述通知单元 102具体可以用于:根据所述为所述每个基站分配的上行功 率, 确定可被所述每个基站调度的资源块 RB个数, 并将所述 RB个数上报给 所述每个基站。
在本实施例或本发明其他某些实施例中, 所述通知单元 102 用于将所述 RB个数上报给所述每个基站时, 具体可以用于: 通过 MAC信令或物理层信 令, 将所述 RB个数上报给所述每个基站。
对于上述实施例中的 UE, 其中各个单元执行操作的具体方式在下文方法 实施例中进行了详细描述, 此处将不做详细阐述说明。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 3是本发明实施例中提供的一种上行功率协调方法的示例性流程图。所 述方法用于用户设备 UE, 所述 UE与至少一个基站建立连接。 参见图 3所示, 所述方法可以包括:
S301、根据指定信息,确定为所述至少一个基站中的每个基站分配的上行 功率, 其中所述上行功率为所述 UE在所述每个基站下用于上行传输的功率。
本实施例的基本思路即在 UE侧主动进行自身上行功率的分配, 然后将分 配结果通知给基站, 从而避免了基站之间协调困难的问题。 UE可以借助自身 获知的一些指定信息来做出如何进行上行功率分配的决定,对于这些指定信息 的具体内容本实施例并不需要进行限制, 可以根据具体场景而定。 作为示例: 在本实施例或本发明其他某些实施例中,所述指定信息可以包括如下至少 一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和, 所述每个基站控制的小区的载波带宽信息。 上述四种指定信息均能从一定程度上反映出 UE的上行功率情况,根据上 述四种指定信息中的一种, 或者两种或多种的组合, UE可以判断出应为哪个 基站分配多少功率。
S302、 将所述为所述每个基站分配的上行功率通知给所述每个基站。
一基站获得了该 UE为其分配的上行功率后, 相当于得知了 UE所受的限 制, 类似于得知了 UE的最大上行功率(或者甚至是直接将该 UE为其分配的 上行功率 "误认为" 就是 UE的最大上行功率), 所以可以根据现有技术确定 对该 UE的调度方式, 本实施例不再赘述。
对于如何将上行功率通知给一个基站, 本实施例并不进行限制, UE可以 借助各种现有的与基站通讯的方式、途径将为基站分配的上行功率通知给该基 站。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 下面再对上述指定信息进行进一步的举例说明。
图 4是本发明实施例中提供的一种上行功率协调方法的示例性流程图。参 见图 4所示, 当所述指定信息包括所述 UE在所述每个基站控制的小区下的上 行传输要求时, 所述上行传输要求可以包括比特速率要求, 所述根据指定信 息, 确定为所述每个基站分配的上行功率, 即步骤 S301 , 可以包括:
S401、 获取 UE在所述每个基站控制的小区下的比特速率要求。
S402、 根据所述比特速率要求, 确定为所述每个基站分配的上行功率。 网络侧可以配置 UE在一个小区的最低比特速率。例如,对于双连接技术, 两个 eNodeB的 RRC功能由 MeNodeB的 RRC控制, 为了保证 UE可靠的移 动性, UE的控制面数据总是发送给 MeNodeB, 这样就需要 UE在分配上行功 率时, 为 MeNodeB分配的上行功率应能够使 UE在 MeNodeB下以保证比特 速率进行上行传输, 该保证比特速率即 MeNodeB对 UE的比特速率要求。 另 夕卜,一个 eNodeB还可以根据与 UE建立的业务来决定并通知 UE在该 eNodeB 下的保证比特速率。 当 UE为 eNodeB分配功率时, 所分配的功率至少应满足 UE以该 eNodeB所通知的保证比特速率进行上行传输。 比特速率要求在一些 场景下可以体现为一个子帧的需要的传输块大小要求。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 5是本发明实施例中提供的一种上行功率协调方法的示例性流程图。参 见图 5所示, 当所述指定信息包括所述 UE在所述每个基站控制的小区下的历 史调度信息时, 所述根据指定信息, 确定为所述每个基站分配的上行功率, 即 步骤 S301 , 可以包括:
5501、 根据所述历史调度信息, 获取所述 UE在所述每个基站调度下产生 的历史上行功率。
5502、 根据所述历史上行功率, 确定为所述每个基站分配的上行功率。 为了使 UE在 eNodeB下的上行传输得到保证, UE可以根据 eNodeB对
UE的历史调度情况决定 UE为该 eNodeB分配的上行功率。 eNodeB历史上对 UE调度的上行传输的 RB个数、 MCS ( Modulation and Coding Scheme, 调制 编码方案)和 /或与上行传输功率设置相关的高层配置参数,这些对于 UE来说 是已知的, UE可以根据这些信息中的一种或多种推算出 UE在 eNodeB的调 度下每次所消耗或者说是所釆用的上行功率, 进而决定应为该 eNodeB分配的 上行功率。 当然,如果历史上 UE在 eNodeB的调度下所付出的上行功率在 UE 侧有直接的记录的话, UE也可以根据该记录作出决定, 而不需要再推算。
作为示例,在一些场景下 UE可以根据这些历史上行功率的均值来决定为 基站分配的上行功率。 例如, 在 T时间段内, eNodeB共 3次调度 UE, UE的 PUSCH 的发送功率分别为 Pl、 P2 和 P3。 则 UE 可以据此确定出分配给该 eNodeB的上行功率为 P = (Pl+P2+P3)/3。
其中, Pl、 P2和 P3可以通过下面的式( 1 ) 即 PUSCH功率计算公式获 付。
η ■、 . ¾MAX,c (''), ) PUSCH'c W [10 log10 ( PUSCH;C ( )) + ¾_ρυ8θΗ,ο U) + ac (j) - PLC + AXF>C ( ) + fc ( ) J ( 1 ) 在式(1 )中, PCMAX。( )为在小区 c的子帧 i上, 当有 PUSCH信道发射时, UE配置的最大发射功率; MPUSCH。(0为子帧 i上为 PUSCH分配的 RB个数; P。― PUS(¾。(J')为开环功控调整值, j与 PUSCH的调度授权方式有关, 当 PUSCH 传输是通过半静态调度授权, 则 j=0 , 当 PUSCH传输是通过动态调度授权, 则 j=l , 当 PUSCH传输是通过随机接入应答授权, 则 j=2 ; « )为部分路损 补偿值, 由高层配置参数和变量 j共同决定, 当 j=0或 1时, 由小区 c高层配 置的参数决定,当 j=2 , ac(j) =V, PLc为 UE测量得到的服务小区 c的路损; Δ^( ) 为传输格式补偿值; _;( )为闭环功控调整值, 由基站发送的功控命令决定。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 6是本发明实施例中提供的一种上行功率协调方法的示例性流程图。参 见图 6所示, 当所述指定信息包括所述 UE在所述每个基站下用于发送上行数 据的緩存中的数据量时, 所述根据指定信息,确定为所述每个基站分配的上行 功率, 即步骤 S301 , 可以包括:
S601、根据所述緩存中的数据量,获取为所述每个基站分配的上行功率在 所述 UE总上行功率中应占的比例。
S602、 根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基 站分配的上行功率。 UE的数据 buffer (緩存)用于緩存待发送的上行数据。 在现有的上行 CA 技术中, UE的 buffer是唯一的, buffer中的数据通过不同的基站进行发送。 在双连接技术中, 由于 eNodeB间非理想 backhaul的原因, UE可能对于每个 基站分别有一个 buffer, 每个 buffer 中的数据只能通过对应的基站发送。 UE 针对一个基站的 buffer 中的数据量代表 UE在该基站下的数据发送需求的多 少, buffer占用较满意味着 UE需要在该基站使用更多的功率用于数据的发送。 因此 UE在每个基站的功率分配可以与各个基站对应 buffer 中的数据量成正 比。
作为示例, 一种方式是 UE对上行功率的分配与各个基站的 buffer数据量 成正比。 以两个基站为例, Pel和 Pe2分别是 UE分配给基站 1和基站 2的上行 功率。 BScl和 BSc2分别是与这两个基站对应的 buffer 中的数据量, 若 BScl=BSc2=1000byte, 则有 Pcl/Pc2= BScl/ BSc2=l , 即应将 UE的上行功率均分 给这两个基站。 注意, 当两基站同时对 UE进行调度时需满足 PC1+PC2<=PMAX, 其中 PMAX为 UE的最大发射功率。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 7是本发明实施例中提供的一种上行功率协调方法的示例性流程图。参 见图 7 所示, 当所述指定信息包括所述每个基站控制的小区的载波带宽信息 时,所述根据指定信息,确定为所述每个基站分配的上行功率,也即步骤 S301 , 可以包括:
5701、根据接收的所述每个基站控制的小区的系统消息,获取所述每个基 站控制的小区的载波带宽信息。
5702、根据所述载波带宽信息,获取为所述每个基站分配的上行功率在所 述 UE总上行功率中应占的比例; S703、 根据所述在所述 UE总上行功率中应占的比例, 确定为所述每个基 站分配的上行功率。
小区的载波带宽意味着可以有多少时频资源调度给 UE用于上行传输。 小 区的带宽越宽, 调度给 UE的时频资源也可能越多, 因此 UE可能需要将更多 的功率分配给载波带宽大的小区。
作为示例, 以两个小区为例, Pc^o Pc2分别是 UE分配给小区 1和小区 2 的功率, BWc o BWc2分别是小区 1和小区 2的载波带宽,若 8\\^为 20MHz, BWc2为 10MHz, 则有 Pcl/Pc2= BWcl/ BWc2=2。 同样注意, 当两基站同时对 UE 进行调度时需满足 Pel+Pe2<=PMAX。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 在确定了 UE上行功率如何分配之后,剩下的问题就是如何将分配结果通 知给相应的基站。 在本实施例中, UE可以借助各种现有的途径将为基站分配 的上行功率通知给该基站, 对此本实施例并不进行限制。 作为示例:
在本实施例或本发明其他某些实施例中,所述将所述为所述每个基站分配 的上行功率通知给所述每个基站, 即步骤 S302, 可以包括:
以所述为所述每个基站分配的上行功率替换所述 UE的最大上行功率对所 述每个基站进行功率余量 PH上报;
或者,
根据所述为所述每个基站分配的上行功率,确定可被所述每个基站调度的 资源块 RB个数, 并将所述 RB个数上报给所述每个基站。
在现有技术中, UE可以向基站进行功率余量 PH上报。 在 PH上报机制 中, UE的最大上行功率是一个重要参量, UE会根据该最大上行功率进行 PH 的计算。 而在本实施例中, UE仍使用原有的 PH上报机制, 但是, 对于最大 上行功率这一参量, 不再如实的进行赋值, 而是做了替换, 即, 以为该基站分 配的上行功率作为最大上行功率, 参与到 PH上报机制中, 使得基站借助 PH 上报机制获取到被分配的上行功率, 进而确定对 UE的调度方式。
可以根据多种现有公式进行 PH计算, 例如在载波聚合中, 定义有两种类 型的功率余量 PH, 分为 Typel和 Type2。
Type 1方式中:
当 UE在小区 c的子帧 i上发送 PUSCH、 不发送 PUCCH时,
) = ^cMAXc (0 - { 101og10 ( pusc¾ ()) + 0_PUSCHp 0) + "C 0)■ 4 + (0 + fa (0 } C (2) 其中, ΑΜΑΧ»为在小区 c的子帧 i上, 当有 PUSCH信道发射时, UE配 置的最大发射功率。
当 UE在小区 c的子帧 i上发送 PUSCH和 PUCCH时,
尸 尸 CMA^(')— il01。g。(Mpusc (/))+尸。 PUSCH(/)+«c(/).尸 4+ArFp()+ (' [ (3 ) 其中, 。(0为在小区 c的子帧 i上, 当有 PUSCH信道发射时, 但假设 UE只有 PUCCH传输时 UE的最大发射功率。
上面两公式中的其他参数的含义可参见公式(1)。
Type 2方式中:
当 UE在 Pcell (即主小区, 在下面的公式里就是指小区 c) 的子帧 i上同 时发送 PUSCH和 PUCCH时,
Figure imgf000021_0001
当 UE在 Pcell的子帧 i上只发送 PUSCH, 不发送 PUCCH时,
1 Q
Figure imgf000021_0002
当 UE在 Pcell的子帧 i上只发送 PUCCH, 不发送 PUSCH时,
,c )+«s(D--PLs+/s( )/l0
[dB]
+-P
(6) 其中, A^^a^)为与 pUCCH格式相关的参数, 由高层配置参数决定; ^½/,¾^, )为与 PUCCH格式相关的变量,其中, 为 CQI的比特数; 如果配置子帧 i可以传输 SR( Scheduling Request, 调度请求), 则" ^=1, 否则 nsR =Q " Q与 UE 配置的服务小区数、 PUCCH传输的 PUCCH格式以及 HARQ-ACK比特数有关, 在不同的 PUCCH format下,
Figure imgf000022_0001
)根据相 应的" 、 nHARQ ¾ 的取值计算得到;
P。- PuccH为开环功控调整值, 由 RRC配置参数决定;
为与发送 PUCCH的天线端口数和 PUCCH格式相关的参数, 当
PUCCH釆用两天线端口发送, 为与 PUCCH格式相关的参数, 由高层 通过专用信令配置给 UE; 否则, A^^) = Q ;
g(0为闭环功控调整值, 由基站发送的功控命令决定。
在本实施例中, 可以用分配的上行功率值, 替换上面公式(2 ) ~ ( 6 ) 中相应的 PCMAX» (或 ΑΜΑΧ» ), 然后将计算出来的 ΡΗ通过现有的 PHR机制 上报给基站。
基站收到 ΡΗ后, 可以根据该 ΡΗ对 UE进行调度, 该调度过程属于现有 技术, 本实施例不再赘述。
因为 UE可以计算得到 PUSCH信道在不同的 RB个数情况下需要的发射 功率, 所以反过来, UE也就可以通过决定每个小区可以调度的 PUSCH的 RB 个数来决定 UE在该小区分配的功率。
UE根据公式( 1 )可以得到所分配的功率对应的 PUSCH发送的 RB个数。 例如, UE在小区 c分配的功率为 Pc,则对于公式( 1 ),可以令公式中的 PpUSCH,c = PC,然后根据该公式可以反向算出 MpUSCH,c的取值即为 PUSCH分配的 RB个 数。
基站在收到了 UE可被本基站调度的资源块 RB个数后,就可以基于该 RB 个数确定对该 UE的调度规则, 例如调度时尽量不超过该 RB个数。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 8 是本发明实施例中提供的一种基站的示例性框图, 所述基站可以包 括:
获取单元 801 , 用于获取用户设备 UE为所述基站分配的上行功率, 其中 所述上行功率为所述 UE在所述基站下用于上行传输的功率, 所述上行功率由 所述 UE根据指定信息确定;
调度单元 802,用于根据所述 UE为所述基站分配的上行功率,对所述 UE 进行上行调度。
在本实施例或本发明其他某些实施例中,所述指定信息包括如下至少一种 信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下用于发送上行数据的緩存中的数据量; 和, 所述基站控制的小区的载波带宽信息。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要求 时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE 根据 所述基站控制的小区下的比特速率要求确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信息 时, 所述上行功率由所述 UE根据所述历史调度信息, 获取所述 UE在所述 基站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存中的 数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取为所述 基站分配的上行功率在所述 UE总上行功率中应占的比例, 根据在所述 UE 总上行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上行 功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述基 站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基站 分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总上 行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中, 所述获取单元 801具体用于: 根 据所述 UE上报的功率余量 PH, 获取所述 UE为所述基站分配的上行功率; 或者,
所述获取单元具体用于:接收所述 UE上报的可为所述基站调度的资源块 RB个数以获取所述 UE为所述基站分配的上行功率。
在本实施例或本发明其他某些实施例中, 所述获取单元用于接收所述 UE 上报的可为所述基站调度的资源块 RB个数时, 具体用于:
通过 MAC信令或物理层信令, 接收所述 UE上报的可为所述基站调度的 资源块 RB个数。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 9是本发明实施例中提供的一种上行功率协调方法的示例性流程图。所 述方法可以用于基站, 所述方法包括:
S901、 获取用户设备 UE为所述基站分配的上行功率, 其中所述上行功率 为所述 UE在所述基站下用于上行传输的功率, 所述上行功率由所述 UE根据 指定信息确定;
S902、 根据所述 UE为所述基站分配的上行功率, 对所述 UE进行上行调 度。
基站获知了该上行功率后, 可以根据现有技术确定对 UE的调度方式, 本 实施例不再赘述。
在本实施例或本发明其他某些实施例中,所述指定信息包括如下至少一种 信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下发送上行数据时緩存中的数据量; 和,
所述基站控制的小区的载波带宽信息。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要求 时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE 根据 所述基站控制的小区下的比特速率要求确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信息 基站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存中的 数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取为所述 基站分配的上行功率在所述 UE总上行功率中应占的比例, 根据在所述 UE 总上行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上行 功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述基 站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基站 分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总上 行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中,所述获取 UE为所述基站分配的 上行功率, 包括:
根据所述 UE上报的功率余量 PH, 获取所述 UE为所述基站分配的上行 功率; 或者,
接收所述 UE上报的可为所述基站调度的资源块 RB个数以获取所述 UE 为所述基站分配的上行功率。
例如, 以 RB个数表征该上行功率的场景下, 基站在调度 UE时, 可以以 调度该 UE的 RB个数不能超过所述 UE上报的 RB个数为原则对该 UE进行 调度。
在本实施例或本发明其他某些实施例中,所述接收所述 UE上 "^的可为所 述基站调度的资源块 RB个数, 包括:
通过 MAC信令或物理层信令, 接收所述 UE上报的可为所述基站调度的 资源块 RB个数。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 10是本发明实施例中提供的一种用户设备 UE的示例性框图。
该 UE可以包括: 处理器 1002和发射器 1001。
其中,
所述处理器 1002, 用于: 根据指定信息, 确定为所述至少一个基站中的 每个基站分配的上行功率,其中所述上行功率为所述 UE在所述每个基站下用 于上行传输的功率;将所述为所述每个基站分配的上行功率通知给所述每个基 站;
所述发射器 1001 , 用于发送所述上行功率。
在本实施例或本发明其他某些实施例中,所述指定信息包括如下至少一种 信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和, 所述每个基站控制的小区的载波带宽信息。 在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传输要 求时, 所述上行传输要求包括比特速率要求, 所述处理器 1002可具体用于: 获取 UE在所述每个基站控制的小区下的比特速率要求;
根据所述比特速率要求, 确定为所述每个基站分配的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调度信 息时, 所述处理器 1002可具体用于:
根据所述历史调度信息,获取所述 UE在所述每个基站调度下产生的历史 上行功率;
根据所述历史上行功率, 确定为所述每个基站分配的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的緩存 中的数据量时, 所述处理器 1002可具体用于:
根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所述
UE总上行功率中应占的比例;
根据所述在所述 UE总上行功率中应占的比例,确定为所述每个基站分配 的上行功率。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时,所述处 理器 1002可具体用于:
根据接收的所述每个基站控制的小区的系统消息,获取所述每个基站控制 的小区的载波带宽信息;
根据所述载波带宽信息, 获取为所述每个基站分配的上行功率在所述 UE 总上行功率中应占的比例;
根据所述在所述 UE总上行功率中应占的比例,确定为所述每个基站分配 的上行功率。
在本实施例或本发明其他某些实施例中, 所述处理器 1002可具体用于: 以所述为所述每个基站分配的上行功率替换所述 UE的最大上行功率对所 述每个基站进行功率余量 PH上报;
或者,
根据所述为所述每个基站分配的上行功率,确定可被所述每个基站调度的 资源块 RB个数, 并将所述 RB个数上报给所述每个基站。
在本实施例或本发明其他某些实施例中, 所述处理器 1002可具体用于: 通过 MAC信令或物理层信令, 将所述 RB个数上报给所述每个基站。 在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。 图 11是本发明实施例中提供的一种基站的示例性框图。
该基站可以包括: 处理器 1102和接收器 1101。
其中,
所述处理器 1102, 用于: 获取用户设备 UE为所述基站分配的上行功率, 其中所述上行功率为所述 UE在所述基站下用于上行传输的功率,所述上行功 率由所述 UE根据指定信息确定; 根据所述 UE为所述基站分配的上行功率, 对所述 UE进行上行调度;
所述接收器 1101 , 用于接收 UE发送的上行功率。
在本实施例或本发明其他某些实施例中,所述指定信息包括如下至少一种 信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下用于发送上行数据的緩存中的数据量; 和, 所述基站控制的小区的载波带宽信息。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要求 时,所述上行传输要求包括比特速率要求,所述上行功率由所述 UE根据所 述基站控制的小区下的比特速率要求确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信息 基站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存中的 数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取为所述 基站分配的上行功率在所述 UE总上行功率中应占的比例, 根据在所述 UE 总上行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中,
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上行 功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述基 站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基站 分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总上 行功率中应占的比例确定的。
在本实施例或本发明其他某些实施例中, 所述处理器 1102具体用于: 根据所述 UE上报的功率余量 PH, 获取所述 UE为所述基站分配的上行 功率; 或者,
接收所述 UE上报的可为所述基站调度的资源块 RB个数以获取所述 UE 为所述基站分配的上行功率。
在本实施例或本发明其他某些实施例中, 所述处理器 1102具体用于: 通过 MAC信令或物理层信令, 接收所述 UE上报的可为所述基站调度的 资源块 RB个数。
在本实施例中, 不再以基站为出发点考虑如何处理 UE上行功率的协调问 题, 而是换了一种思路, 直接在 UE侧主动针对每个基站进行本 UE上行功率 的分配,即,将原先的 UE根据基站的调度被动得到应使用的上行功率的方式, 转变为 UE根据一些信息主动的决定该为每个基站分配多少上行功率,并将分 配结果分别上报给相应的基站, 从而在 UE侧一举解决了各基站在 UE上传功 率协调上的难题。
明的其它实施方案。本发明旨在涵盖本发明的任何变型、用途或者适应性变化, 这些变型、用途或者适应性变化遵循本发明的一般性原理并包括本发明未公开 的本技术领域中的公知常识或惯用技术手段。说明书和实施例仅被视为示例性 的, 本发明的真正范围和精神由下面的权利要求指出。
应当理解的是,本发明并不局限于上面已经描述并在附图中示出的精确结 构, 并且可以在不脱离其范围进行各种修改和改变。本发明的范围仅由所附的 权利要求来限制。

Claims

权 利 要 求
1、 一种用户设备 UE, 其特征在于, 所述 UE与至少一个基站建立连 接, 所述 UE包括:
确定单元, 用于根据指定信息, 确定为所述至少一个基站中的每个基 站分配的上行功率, 其中所述上行功率为所述 UE在所述每个基站下用于 上行传输的功率;
通知单元, 用于将所述为所述每个基站分配的上行功率通知给所述每 个基站。
2、 根据权利要求 1所述的 UE, 其特征在于, 所述指定信息包括如下 至少一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求;
所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和 , 所述每个基站控制的小区的载波带宽信息。
3、 根据权利要求 2所述的 UE, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传 输要求时, 所述上行传输要求包括比特速率要求, 所述确定单元具体用于: 获取 UE在所述每个基站控制的小区下的比特速率要求, 根据所述比 特速率要求, 确定为所述每个基站分配的上行功率。
4、 根据权利要求 2所述的 UE, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调 度信息时, 所述确定单元具体用于:
根据所述历史调度信息, 获取所述 UE在所述每个基站调度下产生的 历史上行功率, 根据所述历史上行功率, 确定为所述每个基站分配的上行 功率。
5、 根据权利要求 2所述的 UE, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的 緩存中的数据量时, 所述确定单元具体用于: 根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所 述 UE总上行功率中应占的比例,根据所述在所述 UE总上行功率中应占的 比例, 确定为所述每个基站分配的上行功率。
6、 根据权利要求 2所述的 UE, 其特征在于,
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时, 所 述确定单元具体用于:
根据接收的所述每个基站控制的小区的系统消息, 获取所述每个基站 控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述每个基 站控制的小区分配的上行功率在所述 UE 总上行功率中应占的比例, 根据 所述在所述 UE 总上行功率中应占的比例, 确定为所述每个基站分配的上 行功率。
7、 根据权利要求 1所述的 UE, 其特征在于,
所述通知单元具体用于: 以所述为所述每个基站分配的上行功率替换 所述 UE的最大上行功率对所述每个基站进行功率余量 PH上报;
或者, 所述通知单元具体用于: 根据所述为所述每个基站分配的上行 功率, 确定可被所述每个基站调度的资源块 RB个数, 并将所述 RB个数上 报给所述每个基站。
8、 根据权利要求 7所述的 UE, 其特征在于, 所述通知单元用于将所 述 RB个数上报给所述每个基站时, 具体用于: 通过 MAC信令或物理层信 令, 将所述 RB个数上报给所述每个基站。
9、 一种上行功率协调方法, 其特征在于, 所述方法用于用户设备 UE, 所述 UE与至少一个基站建立连接, 所述方法包括:
根据指定信息, 确定为所述至少一个基站中的每个基站分配的上行功 率, 其中所述上行功率为所述 UE在所述每个基站下用于上行传输的功率; 将所述为所述每个基站分配的上行功率通知给所述每个基站。
10、 根据权利要求 9所述的方法, 其特征在于, 所述指定信息包括如 下至少一种信息:
所述 UE在所述每个基站控制的小区下的上行传输要求; 所述 UE在所述每个基站控制的小区下的历史调度信息;
所述 UE在所述每个基站下用于发送上行数据的緩存中的数据量; 和 , 所述每个基站控制的小区的载波带宽信息。
11、 根据权利要求 10所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的上行传 输要求时, 所述上行传输要求包括比特速率要求, 所述根据指定信息, 确 定为所述每个基站分配的上行功率, 包括:
获取 UE在所述每个基站控制的小区下的比特速率要求;
根据所述比特速率要求, 确定为所述每个基站分配的上行功率。
12、 根据权利要求 10所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站控制的小区下的历史调 度信息时, 所述根据指定信息, 确定为所述每个基站分配的上行功率, 包 括:
根据所述历史调度信息, 获取所述 UE在所述每个基站调度下产生的 历史上行功率;
根据所述历史上行功率, 确定为所述每个基站分配的上行功率。
13、 根据权利要求 10所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述每个基站下用于发送上行数据的 緩存中的数据量时, 所述根据指定信息, 确定为所述每个基站分配的上行 功率, 包括:
根据所述緩存中的数据量, 获取为所述每个基站分配的上行功率在所 述 UE总上行功率中应占的比例;
根据所述在所述 UE 总上行功率中应占的比例, 确定为所述每个基站 分配的上行功率。
14、 根据权利要求 10所述的方法, 其特征在于,
当所述指定信息包括所述每个基站控制的小区的载波带宽信息时, 所 述根据指定信息, 确定为所述每个基站分配的上行功率, 包括:
根据接收的所述每个基站控制的小区的系统消息, 获取所述每个基站 控制的小区的载波带宽信息; 根据所述载波带宽信息, 获取为所述每个基站分配的上行功率在所述 UE总上行功率中应占的比例;
根据所述在所述 UE 总上行功率中应占的比例, 确定为所述每个基站 分配的上行功率。
15、 根据权利要求 9所述的方法, 其特征在于, 所述将所述为所述每 个基站分配的上行功率通知给所述每个基站, 包括:
以所述为所述每个基站分配的上行功率替换所述 UE 的最大上行功率 对所述每个基站进行功率余量 PH上报;
或者,
根据所述为所述每个基站分配的上行功率, 确定可被所述每个基站调 度的资源块 RB个数, 并将所述 RB个数上报给所述每个基站。
16、 根据权利要求 15所述的方法, 其特征在于, 所述将所述 RB个数 上报给所述每个基站, 包括:
通过 MAC信令或物理层信令, 将所述 RB个数上报给所述每个基站。
17、 一种基站, 其特征在于, 所述基站包括:
获取单元, 用于获取用户设备 UE 为所述基站分配的上行功率, 其中 所述上行功率为所述 UE在所述基站下用于上行传输的功率, 所述上行功 率由所述 UE根据指定信息确定;
调度单元, 用于根据所述 UE为所述基站分配的上行功率, 对所述 UE 进行上行调度。
18、 根据权利要求 17所述基站, 其特征在于, 所述指定信息包括如下 至少一种信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下用于发送上行数据的緩存中的数据量; 和, 所述基站控制的小区的载波带宽信息。
19、 根据权利要求 18所述的基站, 其特征在于,
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要 求时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE根 据所述基站控制的小区下的比特速率要求确定的。
20、 根据权利要求 18所述的基站, 其特征在于,
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信 述基站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
21、 根据权利要求 18所述的基站, 其特征在于,
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存 中的数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取 为所述基站分配的上行功率在所述 UE 总上行功率中应占的比例, 根据在 所述 UE总上行功率中应占的比例确定的。
22、 根据权利要求 18所述的基站, 其特征在于,
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上 行功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述 基站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基 站分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总 上行功率中应占的比例确定的。
23、 根据权利要求 17所述的基站, 其特征在于, 所述获取单元具体用 于: 根据所述 UE上报的功率余量 PH, 获取所述 UE为所述基站分配的上 行功率; 或者,
所述获取单元具体用于: 接收所述 UE上报的可被所述基站调度的资 源块 RB个数以获取所述 UE为所述基站分配的上行功率。
24、 根据权利要求 23所述的基站, 其特征在于, 所述获取单元用于接 收所述 UE上报的可被所述基站调度的资源块 RB个数时, 具体用于: 通过 MAC信令或物理层信令,接收所述 UE上报的可被所述基站调度 的资源块 RB个数。
25、 一种上行功率协调方法, 其特征在于, 所述方法用于基站, 所述 方法包括: 获取用户设备 UE 为所述基站分配的上行功率, 其中所述上行功率为 所述 UE在所述基站下用于上行传输的功率,所述上行功率由所述 UE根据 指定信息确定;
根据所述 UE为所述基站分配的上行功率, 对所述 UE进行上行调度。
26、 根据权利要求 25所述方法, 其特征在于, 所述指定信息包括如下 至少一种信息:
所述 UE在所述基站控制的小区下的上行传输要求;
所述 UE在所述基站控制的小区下的历史调度信息;
所述 UE在所述基站下发送上行数据时緩存中的数据量; 和, 所述基站控制的小区的载波带宽信息。
27、 根据权利要求 26所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述基站控制的小区下的上行传输要 求时, 所述上行传输要求包括比特速率要求, 所述上行功率由所述 UE根 据在所述基站控制的小区下的比特速率要求确定的。
28、 根据权利要求 26所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述基站控制的小区下的历史调度信 述基站调度下产生的历史上行功率, 并根据所述历史上行功率确定的。
28、 根据权利要求 26所述的方法, 其特征在于,
当所述指定信息包括所述 UE在所述基站下用于发送上行数据的緩存 中的数据量时, 所述上行功率由所述 UE根据所述緩存中的数据量, 获取 为所述基站分配的上行功率在所述 UE 总上行功率中应占的比例, 根据在 所述 UE总上行功率中应占的比例确定的。
30、 根据权利要求 26所述的方法, 其特征在于,
当所述指定信息包括所述基站控制的小区的载波带宽信息时, 所述上 行功率由所述 UE根据接收的所述基站控制的小区的系统消息, 获取所述 基站控制的小区的载波带宽信息, 根据所述载波带宽信息, 获取为所述基 站分配的上行功率在所述 UE总上行功率中应占的比例,根据在所述 UE总 上行功率中应占的比例确定的。
31、 根据权利要求 25所述的方法, 其特征在于, 所述获取 UE为所述 基站分配的上行功率, 包括:
根据所述 UE所上报的功率余量 PH, 获取所述 UE为所述基站分配的 上行功率; 或者,
接收所述 UE上报的可被所述基站调度的资源块 RB个数以获取所述 UE为所述基站分配的上行功率。
32、 根据权利要求 31所述的方法, 其特征在于, 所述接收所述 UE上 报的可被所述基站调度的资源块 RB个数, 包括:
通过 MAC信令或物理层信令,接收所述 UE上报的可被所述基站调度 的资源块 RB个数。
PCT/CN2014/077192 2014-05-09 2014-05-09 Ue、基站及上行功率协调方法 WO2015168950A1 (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201480074079.0A CN105940732A (zh) 2014-05-09 2014-05-09 Ue、基站及上行功率协调方法
PCT/CN2014/077192 WO2015168950A1 (zh) 2014-05-09 2014-05-09 Ue、基站及上行功率协调方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2014/077192 WO2015168950A1 (zh) 2014-05-09 2014-05-09 Ue、基站及上行功率协调方法

Publications (1)

Publication Number Publication Date
WO2015168950A1 true WO2015168950A1 (zh) 2015-11-12

Family

ID=54392031

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2014/077192 WO2015168950A1 (zh) 2014-05-09 2014-05-09 Ue、基站及上行功率协调方法

Country Status (2)

Country Link
CN (1) CN105940732A (zh)
WO (1) WO2015168950A1 (zh)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102348269A (zh) * 2011-09-27 2012-02-08 电信科学技术研究院 一种上行功率控制的方法和设备
WO2013018856A1 (ja) * 2011-08-02 2013-02-07 シャープ株式会社 端末、通信システムおよび通信方法
WO2013137656A1 (ko) * 2012-03-14 2013-09-19 삼성전자 주식회사 무선 통신 시스템에서 단말의 상향링크 송신 전력을 효율적으로 제어하는 방법 및 장치

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101969685B (zh) * 2010-09-30 2015-11-25 中兴通讯股份有限公司 一种物理上行控制信道的功率设置方法及用户设备
CN102932892B (zh) * 2011-08-12 2018-03-23 中兴通讯股份有限公司 一种功率控制方法及装置
WO2014036734A1 (en) * 2012-09-10 2014-03-13 Broadcom Corporation Uplink configuration and transmission control in inter-site carrier aggregation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013018856A1 (ja) * 2011-08-02 2013-02-07 シャープ株式会社 端末、通信システムおよび通信方法
CN102348269A (zh) * 2011-09-27 2012-02-08 电信科学技术研究院 一种上行功率控制的方法和设备
WO2013137656A1 (ko) * 2012-03-14 2013-09-19 삼성전자 주식회사 무선 통신 시스템에서 단말의 상향링크 송신 전력을 효율적으로 제어하는 방법 및 장치

Also Published As

Publication number Publication date
CN105940732A (zh) 2016-09-14

Similar Documents

Publication Publication Date Title
US11172469B2 (en) Transmission of device-to-device (D2D) control data from a first D2D device to a second D2D device in a cellular communication system
US10992589B2 (en) LTE based V2X communication QOS and congestion mitigation
AU2017310952B2 (en) Congestion control for LTE-V2V with decode-based channel busy ratio determination
US10448374B2 (en) Power headroom report method of dual-connectivity UE in mobile communication system
KR102184585B1 (ko) 이중 연결을 고려한 전력 제한 상황에서의 pusch/pucch 전력 스케일링 방법 및 그 장치
EP2981123B1 (en) Method for controlling uplink transmission power of inter-base station carrier aggregation, base station and device
JP2021503733A (ja) Nrにおけるcsi報告のための新たなcsi基準リソース定義
US20140241293A1 (en) Method and base station for coordinating physical downlink control channel interference
TW202209853A (zh) 控制資源區域中的資料傳輸的速率匹配
WO2017173920A1 (zh) 一种功率控制方法及设备
CA2920003A1 (en) Uplink power sharing control
WO2018089145A1 (en) Method and apparatus for indexing cellular v2x coverage range to vehicle speed
US10588095B2 (en) Power usage state information transmission method and apparatus
EP3826217B1 (en) Multicarrier-based data transmission
TW201543930A (zh) 使用者終端、無線基地台、無線通訊系統及無線通訊方法
JPWO2015170726A1 (ja) ユーザ端末、無線基地局、無線通信方法及び無線通信システム
WO2021014548A1 (ja) 端末及び通信方法
WO2014108028A1 (zh) 无线通信方法和无线通信设备
WO2021037639A1 (en) Power control
WO2021014546A1 (ja) 端末及び通信方法
JP2017188931A (ja) 移動通信システム、ユーザ端末、及びプロセッサ
WO2015045960A1 (ja) ユーザ端末および無線通信方法
WO2015143600A1 (zh) 上行功率控制方法、用户设备和基站
WO2015168950A1 (zh) Ue、基站及上行功率协调方法
JP6254240B2 (ja) ユーザ端末、無線基地局及び無線通信方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14891537

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 14891537

Country of ref document: EP

Kind code of ref document: A1