Prior art keywords
iec61850
leakage current
alarm
line monitoring
simulation method
Prior art date
Application number
PCT/CN2015/072877
Other languages
French (fr)
Chinese (zh)
Inventor
袁志贤
Original Assignee
袁志贤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 袁志贤 filed Critical 袁志贤
Publication of WO2015149596A1 publication Critical patent/WO2015149596A1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00001Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by the display of information or by user interaction, e.g. supervisory control and data acquisition systems [SCADA] or graphical user interfaces [GUI]
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00002Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by monitoring
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00028Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment involving the use of Internet protocols
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00032Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for
    • H02J13/00034Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for the elements or equipment being or involving an electric power substation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/30State monitoring, e.g. fault, temperature monitoring, insulator monitoring, corona discharge
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/40Display of information, e.g. of data or controls
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/20Information technology specific aspects, e.g. CAD, simulation, modelling, system security

Definitions

  • the invention relates to a communication simulation method for a leakage current online monitoring device based on IEC61850, which belongs to the field of application of a manufacturing message specification (MMS) of an international standard "Substation Communication Network and System” (IEC61850) in a power system substation automation system.
  • MMS manufacturing message specification
  • IEC61850 International Standard "Substation Communication Network and System”
  • the IEC61850 standard is the latest series of substation communication networks and systems specified by the International Electrotechnical Commission's TC57 Working Group to address new interoperability issues facing substation automation systems.
  • the standard has been supported by most mainstream manufacturers at home and abroad, and has become the only unified standard in the field of substation automation in the world. Therefore, it has been widely used in the online monitoring of leakage current intelligent electronic device communication.
  • the present invention provides a communication simulation method for a leakage current online monitoring device based on IEC61850, which can be used to establish a leakage current online monitoring intelligent electronic device simulation system using an ordinary PC to replace the actual online Monitor intelligent electronic devices, etc., to generate online monitoring data of the fault status of the equipment, to facilitate and flexibly debug and verify advanced applications such as equipment health assessment of the intelligent substation automation system.
  • a communication simulation method for leakage current online monitoring equipment based on IEC61850 comprising the following steps:
  • Step (1) simulate and start the IEC61850/MMS communication service
  • Step (2) querying the leakage current to be simulated pre-stored in the SQL database to monitor the value of each analog quantity of the intelligent electronic device for one analysis;
  • Step (3) generating a warning rule by using a pre-configured telemetry violation limit, and automatically calculating a corresponding alarm remote signaling state;
  • Step (4) transmitting each analog quantity and alarm remote signal status in the form of IEC61850 report;
  • Step (5) Wait for the next data transmission time, repeat step 2 until all pre-stored data is transmitted.
  • the step (2) specifically refers to: using the SQL database's on-time column sorting search function to find out the analog data section of a leak current analysis.
  • the step (3) specifically refers to: automatically scanning the current analog value of the telemetry by using a pre-configured rule for generating an alarm, and comparing with the upper limit or the upper limit of each telemetry, and according to The comparison result sets an alarm for the corresponding upper limit remote communication or upper limit remote communication.
  • the invention provides a communication simulation method for a leakage current online monitoring device based on IEC61850, which can establish an automatic electronic device simulation system for leaking current online monitoring using an ordinary PC, and is used for replacing the actual online monitoring intelligent electronic device, etc.
  • the online monitoring data of the fault status of the equipment is free from the dependence of the intelligent electronic equipment on the actual online monitoring of the advanced application debugging of the intelligent substation equipment, and simplifies the complexity of the commissioning work before the commissioning of these advanced applications.
  • FIG. 1 is a schematic flow chart of a simulation method according to the present invention.
  • the communication simulation method for the leakage current online monitoring device based on IEC 61850 includes the following steps: Step (1): Simulating and starting the IEC 61850/MMS communication service; Step (2): Querying and pre-storing in the SQL database The leakage current to be simulated is used to monitor the value of each analog quantity analyzed by the intelligent electronic device at a time; step (3): generating an alarm rule using the pre-configured telemetry violation limit, and automatically calculating the corresponding alarm remote signal status; step (4) : Send each analog quantity and alarm remote signal status in the form of IEC61850 report; Step (5): Wait for the next data transmission time, repeat step 2 until all pre-stored data is sent.
  • the step (1) specifically refers to: using the SQL database to sort by time column Function, find out the analog data section of a leak current analysis.
  • the step (3) specifically refers to: automatically scanning the current analog value of the telemetry by using a pre-configured rule for generating an alarm, and comparing with the upper limit or the upper limit of each telemetry, and according to The comparison result sets an alarm for the corresponding upper limit remote communication or upper limit remote communication.
  • An analog data can be stored in a database that supports SQL in the event of a device failure.
  • a lightweight in-process database such as SQLite can be used for simulation.
  • Each telemetry information should include the serial number, logical device name, and data object reference. , telemetry values and other information.
  • the simulation can use the existing CID file of the actual simulated device to parse and obtain all the information of the external communication of the device. Configure and start the IEC61850/MMS communication service.
  • the invention provides a communication simulation method for the leakage current online monitoring device based on IEC61850, which can establish an automatic electronic device simulation system for leaking current online monitoring using an ordinary PC, which is used to replace the actual online monitoring intelligent electronic device, etc., to generate a primary device failure.
  • the online monitoring data of the state has got rid of the dependence of the actual on-line monitoring of intelligent electronic equipment during the debugging of the advanced application of the intelligent substation primary equipment health status evaluation, and simplified the complexity of the commissioning work before the commissioning of these advanced applications.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Human Computer Interaction (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

An IEC61850-based communication simulation method for a leakage current on-line monitoring device. The method comprises the following steps: (1) starting an IEC61850/MMS communications service by simulation; (2) querying values of analog quantities, pre-stored in an SQL database, of an analysis on a leakage current on-line monitoring intelligent electronic device to be simulated; (3) generating alarm rules by using preconfigured telemetering limits, and automatically computing corresponding alarm telesignalling states; (4) sending the analog quantities and the alarm telesignalling states in the form of an IEC61850 report; and (5) waiting for the next moment of data sending, and repeating step (2) until all pre-stored data is sent. By using the method, a common PC can be used to simulate a leakage current on-line monitoring apparatus, so as to conveniently and flexibly debug and verify advanced applications such as state evaluation on various backgrounds and primary devices, of an intelligent substation, needing to communicate with the on-line monitoring intelligent electronic device.

Description

基于IEC61850的泄露电流在线监测设备通信仿真方法Communication simulation method for leakage current online monitoring equipment based on IEC61850 技术领域Technical field
本发明涉及一种基于IEC61850的泄露电流在线监测设备通信仿真方法,属于国际标准《变电站通信网络和系统》(IEC61850)的制造报文规范(MMS)在电力系统变电站自动化系统的应用的领域。The invention relates to a communication simulation method for a leakage current online monitoring device based on IEC61850, which belongs to the field of application of a manufacturing message specification (MMS) of an international standard "Substation Communication Network and System" (IEC61850) in a power system substation automation system.
背景技术Background technique
IEC61850标准是国际电工委员会TC57工作组针对解决变电站自动化系统面临的互操作新问题最新指定的《变电站通信网络和系统》系列标准。该标准得到国内外大部分主流厂家的支持,成为全球在变电站自动化领域唯一统一的标准,因此在在线监测泄露电流智能电子设备通信中也得到越来越广泛的应用。The IEC61850 standard is the latest series of substation communication networks and systems specified by the International Electrotechnical Commission's TC57 Working Group to address new interoperability issues facing substation automation systems. The standard has been supported by most mainstream manufacturers at home and abroad, and has become the only unified standard in the field of substation automation in the world. Therefore, it has been widely used in the online monitoring of leakage current intelligent electronic device communication.
随着基于IEC61850标准一次设备在线监测在智能变电站的推广和应用,作为智能变电站重要特点的智能高级应用如一次设备健康状态评估等功能也在逐步试点应用中。但即使利用实际的在线监测智能电子设备,也很难对一次设备的故障进行模拟,而且一般在实验室很难具备这种条件,这对于跟踪并发现高级应用的问题造成了很大的困难。另一种方法是使用通用IEC61850/MMS服务端仿真,手动产生遥测、遥信量来模拟在线监测智能电子设备的通信行为,但在线监测智能电子设备发出的各模拟量数据间,模拟量与遥信量数据是尤其内在的逻辑关系的,这种逻辑关系正是模拟一次设备故障的关键所在,通用IEC61850/MMS服务端仿真很难满足相应的要求。因此如何简单高 效地进行在线监测智能电子设备通信仿真模拟,对相关高级应用进行开发调试,以及在工程测试平台上进行验证是一个亟待解决的问题。With the promotion and application of online monitoring of primary equipment based on IEC61850 standard in intelligent substation, intelligent advanced applications such as primary equipment health assessment, which are important features of intelligent substation, are also gradually being applied in pilot applications. But even with the actual online monitoring of intelligent electronic devices, it is difficult to simulate the failure of a primary device, and it is generally difficult to have such conditions in the laboratory, which makes it difficult to track and discover problems of advanced applications. Another method is to use the universal IEC61850/MMS server-side simulation to manually generate telemetry and remote signaling to simulate the online communication of intelligent electronic devices. However, online monitoring of analog data sent by intelligent electronic devices, analog and remote The signal data is especially intrinsic logical relationship. This kind of logical relationship is the key to simulating a device failure. The general IEC61850/MMS server-side simulation is difficult to meet the corresponding requirements. So how simple is it? Efficient online monitoring of intelligent electronic device communication simulation, development and debugging of related advanced applications, and verification on the engineering test platform is an urgent problem to be solved.
发明内容Summary of the invention
目的:为了克服现有技术中存在的不足,本发明提供一种基于IEC61850的泄露电流在线监测设备通信仿真方法,可使用普通PC机建立泄露电流在线监测智能电子设备仿真系统,用于代替实际在线监测智能电子设备等,产生一次设备的故障状态的在线监测数据,以对智能变电站自动化系统的一次设备健康状态评估等高级应用进行方便灵活的调试和验证。OBJECTIVE: To overcome the deficiencies in the prior art, the present invention provides a communication simulation method for a leakage current online monitoring device based on IEC61850, which can be used to establish a leakage current online monitoring intelligent electronic device simulation system using an ordinary PC to replace the actual online Monitor intelligent electronic devices, etc., to generate online monitoring data of the fault status of the equipment, to facilitate and flexibly debug and verify advanced applications such as equipment health assessment of the intelligent substation automation system.
技术方案:为解决上述技术问题,本发明采用的技术方案为:Technical Solution: In order to solve the above technical problems, the technical solution adopted by the present invention is:
一种基于IEC61850的泄露电流在线监测设备通信仿真方法,包括如下步骤:A communication simulation method for leakage current online monitoring equipment based on IEC61850, comprising the following steps:
步骤(1):仿真启动IEC61850/MMS通信服务;Step (1): simulate and start the IEC61850/MMS communication service;
步骤(2):查询预存贮于SQL数据库中的待仿真泄露电流在线监测智能电子设备某一次分析的各模拟量的值;Step (2): querying the leakage current to be simulated pre-stored in the SQL database to monitor the value of each analog quantity of the intelligent electronic device for one analysis;
步骤(3):使用预配置的遥测越限产生告警规则,自动计算对应的告警遥信状态;Step (3): generating a warning rule by using a pre-configured telemetry violation limit, and automatically calculating a corresponding alarm remote signaling state;
步骤(4):以IEC61850报告形式发送各模拟量和告警遥信状态;Step (4): transmitting each analog quantity and alarm remote signal status in the form of IEC61850 report;
步骤(5):等待下次数据发送时刻,重复步骤2,直至所有预存数据发送完毕。Step (5): Wait for the next data transmission time, repeat step 2 until all pre-stored data is transmitted.
所述步骤(2)具体是指:使用SQL数据库的按时标列排序查找功能,查找出某一次泄露电流分析的各模拟量数据断面。 The step (2) specifically refers to: using the SQL database's on-time column sorting search function to find out the analog data section of a leak current analysis.
所述步骤(3)具体是指:使用预配置的遥测越限产生告警的规则,自动扫描个遥测量的当前模拟值,与各遥测的约越上限或越上上限值进行比较,并根据比较结果对对应的越上限遥信或越上上限遥信进行告警设置。The step (3) specifically refers to: automatically scanning the current analog value of the telemetry by using a pre-configured rule for generating an alarm, and comparing with the upper limit or the upper limit of each telemetry, and according to The comparison result sets an alarm for the corresponding upper limit remote communication or upper limit remote communication.
有益效果:本发明提供的一种基于IEC61850的泄露电流在线监测设备通信仿真方法,可使用普通PC机建立泄露电流在线监测智能电子设备仿真系统,用于代替实际在线监测智能电子设备等,产生一次设备的故障状态的在线监测数据,摆脱了智能变电站一次设备健康状态评等高级应用调试时对实际在线监测智能电子设备的依赖,同时简化了这些高级应用投运前调试工作的复杂度。Advantageous Effects: The invention provides a communication simulation method for a leakage current online monitoring device based on IEC61850, which can establish an automatic electronic device simulation system for leaking current online monitoring using an ordinary PC, and is used for replacing the actual online monitoring intelligent electronic device, etc. The online monitoring data of the fault status of the equipment is free from the dependence of the intelligent electronic equipment on the actual online monitoring of the advanced application debugging of the intelligent substation equipment, and simplifies the complexity of the commissioning work before the commissioning of these advanced applications.
附图说明DRAWINGS
图1为本发明的仿真方法流程示意图。FIG. 1 is a schematic flow chart of a simulation method according to the present invention.
具体实施方式detailed description
下面结合附图对本发明作更进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings.
如图1所示,为一种基于IEC61850的泄露电流在线监测设备通信仿真方法,包括如下步骤:步骤(1):仿真启动IEC61850/MMS通信服务;步骤(2):查询预存贮于SQL数据库中的待仿真泄露电流在线监测智能电子设备某一次分析的各模拟量的值;步骤(3):使用预配置的遥测越限产生告警规则,自动计算对应的告警遥信状态;步骤(4):以IEC61850报告形式发送各模拟量和告警遥信状态;步骤(5):等待下次数据发送时刻,重复步骤2,直至所有预存数据发送完毕。As shown in FIG. 1 , the communication simulation method for the leakage current online monitoring device based on IEC 61850 includes the following steps: Step (1): Simulating and starting the IEC 61850/MMS communication service; Step (2): Querying and pre-storing in the SQL database The leakage current to be simulated is used to monitor the value of each analog quantity analyzed by the intelligent electronic device at a time; step (3): generating an alarm rule using the pre-configured telemetry violation limit, and automatically calculating the corresponding alarm remote signal status; step (4) : Send each analog quantity and alarm remote signal status in the form of IEC61850 report; Step (5): Wait for the next data transmission time, repeat step 2 until all pre-stored data is sent.
所述步骤(1)具体是指:使用SQL数据库的按时标列排序查找 功能,查找出某一次泄露电流分析的各模拟量数据断面。The step (1) specifically refers to: using the SQL database to sort by time column Function, find out the analog data section of a leak current analysis.
所述步骤(3)具体是指:使用预配置的遥测越限产生告警的规则,自动扫描个遥测量的当前模拟值,与各遥测的约越上限或越上上限值进行比较,并根据比较结果对对应的越上限遥信或越上上限遥信进行告警设置。The step (3) specifically refers to: automatically scanning the current analog value of the telemetry by using a pre-configured rule for generating an alarm, and comparing with the upper limit or the upper limit of each telemetry, and according to The comparison result sets an alarm for the corresponding upper limit remote communication or upper limit remote communication.
在线监测智能电子设备发出的各模拟量数据间,模拟量与遥信量数据是尤其内在的逻辑关系的,这种逻辑关系正是模拟一次设备故障的关键所在。一次设备故障时个模拟量信息可存贮于支持SQL的数据库中,针对仿真可使用轻量级的进程内数据库如SQLite,每一个遥测量的信息需包括断面序号、逻辑设备名、数据对象引用、遥测值等信息。Online monitoring of analog data sent by intelligent electronic devices, analog and remote signal data is particularly intrinsic logical relationship, this logical relationship is the key to simulate a device failure. An analog data can be stored in a database that supports SQL in the event of a device failure. A lightweight in-process database such as SQLite can be used for simulation. Each telemetry information should include the serial number, logical device name, and data object reference. , telemetry values and other information.
由于IEC61850标准规定其中CID(Configured智能电子设备Description)文件包含了智能电子设备投运时的完整模型信息,仿真可使用实际被仿真设备的已有CID文件,解析获得该设备对外通信的所有信息和配置,启动IEC61850/MMS通信服务。Since the IEC61850 standard stipulates that the CID (Configured Intelligent Electronic Device Description) file contains the complete model information when the intelligent electronic device is put into operation, the simulation can use the existing CID file of the actual simulated device to parse and obtain all the information of the external communication of the device. Configure and start the IEC61850/MMS communication service.
再使用SQL数据库的查找功存贮于数据库中的某一断面的所有遥测量数据,然后使用预配置的遥测越限产生告警的规则,自动扫描个遥测量的当前模拟值,与各遥测的约越上限或越上上限值进行比较,并根据比较结果对对应的越上限遥信或越上上限遥信进行告警设置,以IEC61850报告形式发送各模拟量和告警遥信状态。Then use the SQL database search function to store all the telemetry data of a section in the database, and then use the pre-configured telemetry violation to generate the alarm rule, automatically scan the current analog value of the telemetry, and the telemetry The upper limit or the upper limit is compared, and the corresponding upper limit or upper limit remote message is set according to the comparison result, and each analog quantity and alarm remote signal status is sent in the form of IEC61850 report.
然后判断是否所有预存数据都已发送完毕,如果发送完毕则停止发送;如果还有模拟数据待发送,则进入等待流程,准备进行下一次 的故障模拟数据发送。Then judge whether all pre-stored data has been sent, if the sending is completed, stop sending; if there is still analog data to be sent, enter the waiting process, ready for the next time The fault simulation data is sent.
本发明提供的一种基于IEC61850的泄露电流在线监测设备通信仿真方法,可使用普通PC机建立泄露电流在线监测智能电子设备仿真系统,用于代替实际在线监测智能电子设备等,产生一次设备的故障状态的在线监测数据,摆脱了智能变电站一次设备健康状态评等高级应用调试时对实际在线监测智能电子设备的依赖,同时简化了这些高级应用投运前调试工作的复杂度。The invention provides a communication simulation method for the leakage current online monitoring device based on IEC61850, which can establish an automatic electronic device simulation system for leaking current online monitoring using an ordinary PC, which is used to replace the actual online monitoring intelligent electronic device, etc., to generate a primary device failure. The online monitoring data of the state has got rid of the dependence of the actual on-line monitoring of intelligent electronic equipment during the debugging of the advanced application of the intelligent substation primary equipment health status evaluation, and simplified the complexity of the commissioning work before the commissioning of these advanced applications.
以上所述仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润色,这些改进和润色也应视为本发明的保护范围。 The above description is only a preferred embodiment of the present invention, and it should be noted that those skilled in the art can also make several improvements and touches without departing from the principles of the present invention. It should be considered as the scope of protection of the present invention.

Claims (3)

  1. 一种基于IEC61850的泄露电流在线监测设备通信仿真方法,包括如下步骤:A communication simulation method for leakage current online monitoring equipment based on IEC61850, comprising the following steps:
    步骤(1):仿真启动IEC61850/MMS通信服务;Step (1): simulate and start the IEC61850/MMS communication service;
    步骤(2):查询预存贮于SQL数据库中的待仿真泄露电流在线监测智能电子设备某一次分析的各模拟量的值;Step (2): querying the leakage current to be simulated pre-stored in the SQL database to monitor the value of each analog quantity of the intelligent electronic device for one analysis;
    步骤(3):使用预配置的遥测越限产生告警规则,自动计算对应的告警遥信状态;Step (3): generating a warning rule by using a pre-configured telemetry violation limit, and automatically calculating a corresponding alarm remote signaling state;
    步骤(4):以IEC61850报告形式发送各模拟量和告警遥信状态;Step (4): transmitting each analog quantity and alarm remote signal status in the form of IEC61850 report;
    步骤(5):等待下次数据发送时刻,重复步骤(2),直至所有预存数据发送完毕。Step (5): Wait for the next data transmission time, repeat step (2) until all pre-stored data is transmitted.
  2. 根据权利要求1所述的基于IEC61850的泄露电流在线监测设备通信仿真方法,其特征在于:所述步骤(2)具体是指:使用SQL数据库的查找功能,查找出某一次泄露电流分析的各模拟量数据断面。The IEC61850-based leakage current online monitoring device communication simulation method according to claim 1, wherein the step (2) specifically refers to: using a search function of the SQL database to find out each simulation of a leakage current analysis. Volume data section.
  3. 根据权利要求1所述的基于IEC61850的泄露电流在线监测设备通信仿真方法,其特征在于:所述步骤(3)具体是指:使用预配置的遥测越限产生告警的规则,自动扫描个遥测量的当前模拟值,与各遥测的约越上限或越上上限值进行比较,并根据比较结果对对应的越上限遥信或越上上限遥信进行告警设置。 The IEC61850-based leakage current online monitoring device communication simulation method according to claim 1, wherein the step (3) specifically refers to: automatically generating a remote measurement by using a pre-configured remote detection limit to generate an alarm rule. The current analog value is compared with the upper limit or the upper limit of each telemetry, and the corresponding upper limit or upper limit remote alarm is set according to the comparison result.
PCT/CN2015/072877 2014-04-04 2015-02-12 Iec61850-based communication simulation method for leakage current on-line monitoring device WO2015149596A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410136149.2A CN103955564A (en) 2014-04-04 2014-04-04 IEC 61850-based leakage current on-line monitoring equipment communication simulation method
CN201410136149.2 2014-04-04

Publications (1)

Publication Number Publication Date
WO2015149596A1 true WO2015149596A1 (en) 2015-10-08

Family

ID=51332839

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2015/072877 WO2015149596A1 (en) 2014-04-04 2015-02-12 Iec61850-based communication simulation method for leakage current on-line monitoring device

Country Status (2)

Country Link
CN (1) CN103955564A (en)
WO (1) WO2015149596A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112329211A (en) * 2020-10-19 2021-02-05 南方电网科学研究院有限责任公司 Urban railway conductor section leakage current simulation measurement method based on CDEGS

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103955563A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for transformer grounding on-line monitoring equipment
CN103955561A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based lightning arrester on-line monitoring equipment communication simulation method
CN103955562A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for insulation on-line monitoring equipment
CN103955564A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based leakage current on-line monitoring equipment communication simulation method
CN103984795A (en) * 2014-04-04 2014-08-13 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based partial discharge on-line monitoring equipment communication simulation method
CN103995916A (en) * 2014-04-04 2014-08-20 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based SF6Communication simulation method for gas online monitoring equipment
CN112053521B (en) * 2020-08-12 2022-07-08 长沙理工大学 Residential building leakage current edge fingerprint database judgment system

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7016751B2 (en) * 2001-07-13 2006-03-21 Helix Technology Corporation Vacuum system central control information server
CN102033798A (en) * 2010-10-20 2011-04-27 国电南瑞科技股份有限公司 Method for simulating intelligent electronic device IEC61850/MMS (Microsoft media server) server
CN102496072A (en) * 2011-12-19 2012-06-13 国电南瑞科技股份有限公司 System for estimating distributive state of intelligent transformer station
US8483982B2 (en) * 2010-11-02 2013-07-09 Schneider Electric USA, Inc. Automated emergency power supply test using variable load bank stages
CN103400302A (en) * 2013-07-01 2013-11-20 国家电网公司 Risk perception and early warning method and system for cascading failures of wind power base
CN103902768A (en) * 2014-03-25 2014-07-02 中国南方电网有限责任公司电网技术研究中心 Communication simulation method for oil chromatography on-line monitoring equipment
CN103955561A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based lightning arrester on-line monitoring equipment communication simulation method
CN103955563A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for transformer grounding on-line monitoring equipment
CN103955562A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for insulation on-line monitoring equipment
CN103955564A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based leakage current on-line monitoring equipment communication simulation method
CN103984795A (en) * 2014-04-04 2014-08-13 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based partial discharge on-line monitoring equipment communication simulation method
CN103995916A (en) * 2014-04-04 2014-08-20 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based SF6Communication simulation method for gas online monitoring equipment
CN103995924A (en) * 2014-05-05 2014-08-20 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation device and method for on-line switch monitoring equipment

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7016751B2 (en) * 2001-07-13 2006-03-21 Helix Technology Corporation Vacuum system central control information server
CN102033798A (en) * 2010-10-20 2011-04-27 国电南瑞科技股份有限公司 Method for simulating intelligent electronic device IEC61850/MMS (Microsoft media server) server
US8483982B2 (en) * 2010-11-02 2013-07-09 Schneider Electric USA, Inc. Automated emergency power supply test using variable load bank stages
CN102496072A (en) * 2011-12-19 2012-06-13 国电南瑞科技股份有限公司 System for estimating distributive state of intelligent transformer station
CN103400302A (en) * 2013-07-01 2013-11-20 国家电网公司 Risk perception and early warning method and system for cascading failures of wind power base
CN103902768A (en) * 2014-03-25 2014-07-02 中国南方电网有限责任公司电网技术研究中心 Communication simulation method for oil chromatography on-line monitoring equipment
CN103955561A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based lightning arrester on-line monitoring equipment communication simulation method
CN103955563A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for transformer grounding on-line monitoring equipment
CN103955562A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation method for insulation on-line monitoring equipment
CN103955564A (en) * 2014-04-04 2014-07-30 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based leakage current on-line monitoring equipment communication simulation method
CN103984795A (en) * 2014-04-04 2014-08-13 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based partial discharge on-line monitoring equipment communication simulation method
CN103995916A (en) * 2014-04-04 2014-08-20 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based SF6Communication simulation method for gas online monitoring equipment
CN103995924A (en) * 2014-05-05 2014-08-20 中国南方电网有限责任公司电网技术研究中心 IEC 61850-based communication simulation device and method for on-line switch monitoring equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112329211A (en) * 2020-10-19 2021-02-05 南方电网科学研究院有限责任公司 Urban railway conductor section leakage current simulation measurement method based on CDEGS
CN112329211B (en) * 2020-10-19 2024-05-10 南方电网科学研究院有限责任公司 Urban rail conductor section leakage current simulation measurement method based on CDEGS

Also Published As

Publication number Publication date
CN103955564A (en) 2014-07-30

Similar Documents

Publication Publication Date Title
WO2015149596A1 (en) Iec61850-based communication simulation method for leakage current on-line monitoring device
WO2015149594A1 (en) Iec61850-based communication simulation method for partial discharge on-line monitoring device
WO2015149593A1 (en) Iec61850-based communication simulation method for transformer grounding on-line monitoring device
WO2015149595A1 (en) Iec61850-based communication simulation method for insulation on-line monitoring device
CN107346917B (en) Secondary device based on virtual machine integrates joint debugging method
WO2015149592A1 (en) Iec61850-based communication simulation method for lightning arrester on-line monitoring device
CN103746882B (en) The method of intelligent substation station level test
CN103200051B (en) Intelligent substation message emulating is tested and is associated message analysis system and method
WO2015149597A1 (en) Iec61850-based communication simulation method for sf6 gas on-line monitoring device
WO2015154527A1 (en) Automatic interlocking logic detection method based on goose communication mechanism
CN104569688A (en) Automatic testing system and method for power distribution terminal
CN105227350A (en) Based on the intelligent substation IED configuration file management-control method of CRC check code
CN204291050U (en) A kind of dispatching and monitoring information check system
CN105447247A (en) Method and system for checking regulation and control information
CN103902768A (en) Communication simulation method for oil chromatography on-line monitoring equipment
CN104052633A (en) Integrated testing method for intelligent station 61850 and telecontrol 104 protocol
CN104868599A (en) Intelligent substation message simulation test and association analysis system, and simulation method
WO2014153764A1 (en) Method and device for automatic test of relay protection function of intelligent substation
CN103107914A (en) Detection method and detection system for remote power acquisition terminal
CN103905275A (en) Electric power telecontrol equipment testing method based on IEC61850 replacement services
CN110752670A (en) Intelligent substation relay protection intelligent inspection system and inspection method
CN114123482A (en) Main plant station information joint debugging decoupling method
CN107543986A (en) A kind of relay protection test system based on mobile platform
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN107819611B (en) Client test method based on IEC61850 multi-server simulation

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 15773905

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 22.03.2017)

122 Ep: pct application non-entry in european phase

Ref document number: 15773905

Country of ref document: EP

Kind code of ref document: A1