WO2014136644A1 - 液化ガス供給用接続機構 - Google Patents
液化ガス供給用接続機構 Download PDFInfo
- Publication number
- WO2014136644A1 WO2014136644A1 PCT/JP2014/054834 JP2014054834W WO2014136644A1 WO 2014136644 A1 WO2014136644 A1 WO 2014136644A1 JP 2014054834 W JP2014054834 W JP 2014054834W WO 2014136644 A1 WO2014136644 A1 WO 2014136644A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- valve
- liquefied gas
- connection
- gas supply
- joint
- Prior art date
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C13/00—Details of vessels or of the filling or discharging of vessels
- F17C13/004—Details of vessels or of the filling or discharging of vessels for large storage vessels not under pressure
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2205/00—Vessel construction, in particular mounting arrangements, attachments or identifications means
- F17C2205/03—Fluid connections, filters, valves, closure means or other attachments
- F17C2205/0302—Fittings, valves, filters, or components in connection with the gas storage device
- F17C2205/037—Quick connecting means, e.g. couplings
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2221/00—Handled fluid, in particular type of fluid
- F17C2221/03—Mixtures
- F17C2221/032—Hydrocarbons
- F17C2221/033—Methane, e.g. natural gas, CNG, LNG, GNL, GNC, PLNG
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2223/00—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
- F17C2223/01—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the phase
- F17C2223/0146—Two-phase
- F17C2223/0153—Liquefied gas, e.g. LPG, GPL
- F17C2223/0161—Liquefied gas, e.g. LPG, GPL cryogenic, e.g. LNG, GNL, PLNG
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2223/00—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel
- F17C2223/03—Handled fluid before transfer, i.e. state of fluid when stored in the vessel or before transfer from the vessel characterised by the pressure level
- F17C2223/033—Small pressure, e.g. for liquefied gas
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2227/00—Transfer of fluids, i.e. method or means for transferring the fluid; Heat exchange with the fluid
- F17C2227/04—Methods for emptying or filling
- F17C2227/044—Methods for emptying or filling by purging
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2270/00—Applications
- F17C2270/01—Applications for fluid transport or storage
- F17C2270/0102—Applications for fluid transport or storage on or in the water
- F17C2270/0105—Ships
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F17—STORING OR DISTRIBUTING GASES OR LIQUIDS
- F17C—VESSELS FOR CONTAINING OR STORING COMPRESSED, LIQUEFIED OR SOLIDIFIED GASES; FIXED-CAPACITY GAS-HOLDERS; FILLING VESSELS WITH, OR DISCHARGING FROM VESSELS, COMPRESSED, LIQUEFIED, OR SOLIDIFIED GASES
- F17C2270/00—Applications
- F17C2270/01—Applications for fluid transport or storage
- F17C2270/0134—Applications for fluid transport or storage placed above the ground
- F17C2270/0136—Terminals
Definitions
- the present invention relates to a system for sending liquefied gas, and more particularly to a system for purging vaporized gas fuel from the pipe when sending liquefied gas fuel to transport equipment.
- the present invention relates to a system for sending liquefied gas through a separable line, and for purging necessary to suppress release of vaporized liquefied gas remaining in the line and the liquefied gas itself to the atmosphere when the line is separated.
- the aim is to greatly reduce the amount of gas.
- connection mechanism for supplying liquefied gas includes a first connection portion including a first valve, a first connection joint, and a purge gas supply valve communicated with each other, a second valve, and a second valve. And a second connecting portion including a second connecting joint that can be connected to the first connecting joint.
- the first connection portion further includes a joint for connecting the purge gas supply valve to the purge gas supply source. It is preferable that the second connection portion further includes a sampling valve communicated with the second valve and the second connection joint.
- the purge gas supply source is preferably located in the transport equipment. It is preferable that the first valve is a valve on the side for supplying liquefied gas, and the second valve is a valve on the side for receiving supply of liquefied gas.
- the ship of the present invention is characterized by including either one of the first and second connection portions of the liquefied gas supply connection mechanism described above.
- the liquefied gas is a liquefied gas fuel.
- the liquefied gas supply connection mechanism disconnecting method of the present invention includes a first connection portion including a first valve, a first connection joint, and a purge gas supply valve that are communicated with each other, a second valve, and a second valve.
- a liquefied gas supply connection mechanism comprising: a second connecting portion including a second connecting joint connected to the first connecting joint and connected to the first connecting joint; and supplying the liquefied gas by closing the first valve Is stopped, the purge gas supply valve is opened, the purge gas is supplied to the first and second connection portions, and it is monitored whether the liquefied gas has been purged from the first and second connection portions, and the purge is completed. After the confirmation, the second valve is closed, and the connection of the first and second connection joints is released.
- the second connection portion further includes a sampling valve communicated with the second valve and the second connection joint, and the monitor is executed at the sampling valve. After confirming the completion of purging, it is preferable to close the second valve after closing the sampling valve. It is preferable that the second valve is opened slightly after the liquefied gas supply is stopped until the second valve is closed.
- the present invention in a system for sending a liquefied gas through a separable line, it is necessary to suppress the release of the vaporized liquefied gas remaining in the line and the liquefied gas itself to the atmosphere when the line is separated.
- the amount of purge gas can be greatly reduced.
- FIG. 1 is a block diagram illustrating a configuration of a liquefied gas supply system including a line connection mechanism according to an embodiment of the present invention.
- the liquefied gas supply system 10 of the present embodiment is a bunker system that supplies liquefied gas fuel such as LNG to transportation equipment that uses liquefied gas as fuel, such as the LNG fuel ship 11.
- the LNG fuel ship moored from the LNG storage tank (liquefied gas storage tank) 13 of the fuel supply facility (liquefied gas supply facility) 12 installed in the harbor through the fuel line (liquefied gas line).
- the liquefied natural gas (liquefied gas) is supplied to 11 LNG fuel tanks (liquefied gas tank) 15.
- LNG is delivered from the LNG storage tank 13 through, for example, a flexible bunker hose 16.
- An outlet connecting portion 17 is provided at the tip of the bunker hose 16 and is connected to the inlet connecting portion 18 of the LNG fuel ship 11 during bunkering.
- the outlet connection portion 17 includes, for example, a letter pipe, and a liquefied gas supply valve 19 is provided at one end of the main pipe, and a connection joint 20 is provided at the other end of the main pipe.
- the branch pipe is provided with a purge gas supply valve 21 and a joint 22.
- the liquefied gas supply valve 19 is connected to the bunker hose 16, and the flow of the liquefied gas supplied from the bunker hose 16 is controlled by opening and closing the liquefied gas supply valve 19.
- the connection joint 20 is, for example, a flange joint, and is connected to the flange joint of the ship side inlet connection portion 18 during bunkering.
- the purge gas supply valve 21 is a valve that controls the supply of a purge gas such as nitrogen gas to the clove tube, and can be connected to the purge gas supply equipment 23 via a joint 22 provided at the tip of the branch pipe.
- the purge gas supply facility 23 is provided in the LNG fuel ship 11 serving as a transportation device.
- nitrogen gas is supplied from a nitrogen gas cylinder (purge gas supply source) 24 loaded on the ship via a fixed pipe 25 and a flexible hose 26 to the outlet connecting portion 17.
- a joint 27 that can be connected to the joint 22 provided on the branch pipe of the outlet connecting portion 17 is provided at the tip of the flexible hose 26.
- the inlet connecting portion 18 is also provided with, for example, a letter pipe, and a connecting joint 28 is provided at one end of the main pipe, and a liquefied gas on-off valve 29 is provided at the other end of the main pipe.
- a sampling valve 30 is provided in the branch pipe.
- the connection joint 28 is complementary to the connection joint 20 of the outlet connection portion 17, and is a flange in this embodiment.
- the liquefied gas on-off valve 29 is connected to the inboard LNG fuel tank 15 through the fixed pipe 31.
- liquefied natural gas is supplied from the LNG storage tank 13 to the LNG fuel tank 15 of the LNG fuel ship 11 by connecting the flange joints 20 and 28 and opening the liquefied gas supply valve 19 and the liquefied gas on-off valve 29.
- the bunkering is ended by closing the liquefied gas supply valve 19, for example, and at this time, the liquefied gas on-off valve 29 is opened, more preferably slightly opened.
- the purge gas supply valve 21 is opened, and nitrogen gas is supplied from the nitrogen gas cylinder 24 of the purge gas supply equipment 23 to the outlet connecting portion 17 through the joints 27 and 22.
- the joints 22 and 27 may be connected before bunkering starts, during bunkering, or after bunkering ends.
- the liquefied natural gas remaining in the outlet connecting portion 17 and the inlet connecting portion 18 and the vaporized natural gas are pushed by the nitrogen gas through the liquefied gas on-off valve 29 to the LNG fuel tank 15 side and purged.
- the operator opens the sampling valve 30 and monitors the completion of the purge by confirming the composition of the gas in the pipe (for example, confirming that the methane gas concentration is sufficiently low).
- the sampling valve 30 is closed, the liquefied gas on-off valve 29 and the purge gas supply valve 21 are closed, and the supply of nitrogen gas (purge gas) is stopped.
- the couplings 22 and 27 are disconnected, and the outlet connecting portion 17 on the fuel supply facility 12 side is disconnected from the inlet connecting portion 18 on the ship 11 side.
- the purge gas supply source on the transportation equipment side, and for example, even when using a small-scale facility that does not have a purge gas supply facility, leakage of liquefied gas fuel can be prevented. .
- the fuel supply facility may be an onshore tank as in this embodiment, but may also be a bunker ship or a tank truck.
- the transportation device using liquefied gas fuel is a ship.
- the transportation device is limited to a ship, such as when liquefied gas fuel is transferred from a storage tank to a tank truck, or when liquefied gas fuel is supplied to a rocket. It is not something.
- the present embodiment can also be used for disconnecting a supply line of liquefied gas that needs to be prevented from being released into the atmosphere, and the liquefied gas is not limited to liquefied gas fuel.
- the purge gas is supplied from the branch pipe of the connection part on the supply facility side because the purge is performed to the ship side.
- the purge gas is supplied from the branch pipe on the ship side.
- a configuration is also possible.
- each valve and joint are communicated with each other using a clove tube, but the both connection portions are not limited to a clove tube, and the number of branches is also limited to this embodiment. is not. It is also possible to omit the sampling valve by adopting another method for sampling. Further, in this embodiment, the purge gas supply valve and the sampling valve are provided in different connecting portions, but both may be provided in the same connecting portion.
- a stop valve is used as each valve in the present embodiment.
- Valves also exist on the liquefied gas storage tank side and the purge gas supply equipment side, and these valves are closed at the end of bunkering or at the end of purge, but the description thereof is omitted in this embodiment.
- the purge gas supply source nitrogen gas cylinder
- the purge gas is connected to the fixed pipe (25), and the purge gas is supplied to the outlet connecting portion via the flexible hose (26) connected to the fixed pipe.
- the configuration may be such that the fixed pipe (25) is omitted and the purge gas is supplied from the purge gas supply source directly to the outlet connection portion via the flexible hose.
- Liquefied gas supply system 11 LNG fuel ship (transport equipment) 12 Fuel supply facility (liquefied gas supply facility) 13 LNG storage tank (liquefied gas storage tank) 15 LNG fuel tank (liquefied gas tank) 16 Bunker hose (flexible hose) 17 Outlet connection portion 18 Inlet connection portion 19 Liquefied gas supply valve 20 Connection joint 21 Purge gas supply valve 22 Joint 23 Purge gas supply equipment 24 Nitrogen gas cylinder (purge gas supply source) 25 Fixed pipe 26 Flexible hose 27 Joint 28 Connection joint 29 Liquefied gas on-off valve 30 Sampling valve 31 Fixed pipe
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Filling Or Discharging Of Gas Storage Vessels (AREA)
Abstract
液化ガス供給施設12側に、相互に連通される液化ガス供給弁19、接続継手20、パージガス供給弁21とを備えるアウトレット接続部17を設ける。船11側に、液化ガス開閉弁29と、これに連通され、接続継手20に接続された接続継手28を備えるインレット接続部18を設ける。液化ガス供給弁19を閉じて液化ガスの供給を停止する。パージガス供給弁21を開き、パージ用のガスをアウトレット接続部17、インレット接続部18へ供給する。液化ガスが両接続部17、18からパージされたか否かをモニタする。パージ完了確認後、液化ガス開閉弁29を閉じ、接続継手20、28の接続を解除する。
Description
本発明は、液化ガスを送液するためのシステムに関し、特に液化ガス燃料を輸送機器へ送液する際に、気化したガス燃料を管内からパージするためのシステムに関する。
近年、環境負荷がより少ない液化天然ガスを燃料として利用するLNG燃料船の普及が進められている。LNG燃料船におけるバンカー作業は、バンカーホースを船舶に接続して行われるが、液化天然ガスは、外部からの熱によりバンカーホースを含む燃料ライン内において一部沸騰し気化する。そのため送液を停止しても燃料ライン内には気化した天然ガスが残留し、バンカーホース切離しの際に、残留天然ガスが大気中に放出される。このような天然ガスの大気への漏出を防止するため、燃料ライン内に残留する天然ガスを窒素ガスなどで予めパージするLNGバンカーシステムも知られている(特許文献1)。
特表2011-503463号公報
しかし、従来のパージ方法は、燃料ライン全体をパージしているため、パージ用のガス(窒素ガス)を大量に必要とする。にもかかわらず、小型な設備や、ローリ車やバンカー船などから液化ガス燃料の供給を受ける場合、パージ用のガス設備を設けていない場合もある。
本発明は、切離し可能なラインを通して液化ガスを送液するシステムにおいて、ライン切離しの際、ライン内に残留する気化された液化ガスおよび液化ガスそのものの大気への放出を抑えるために必要なパージ用ガスの量を大幅に減らすことを目的としている。
本発明の液化ガス供給用接続機構は、相互に連通される第1の弁、第1の接続継手、パージガス供給弁とを備える第1の接続部と、第2の弁と、第2の弁に連通され、第1の接続継手と接続可能な第2の接続継手とを備える第2の接続部とを備えることを特徴としている。
第1の接続部は、パージガス供給弁をパージガス供給源へと接続するための継手を更に備えることが好ましい。第2の接続部は、第2の弁および第2の接続継手に連通されるサンプリング弁を更に備えることが好ましい。パージガス供給源は、輸送機器に配置されることが好ましい。第1の弁が液化ガスを供給する側の弁であり、第2の弁が液化ガスの供給を受ける側の弁であることが好ましい。
本発明の船舶は、上記何れかに記載の液化ガス供給用接続機構の第1または第2の接続部の何れか一方を備えることを特徴としている。
液化ガスは液化ガス燃料であり、例えば船舶は液化ガスを燃料として使用する。
本発明の液化ガス供給用接続機構切離し方法は、相互に連通される第1の弁、第1の接続継手、パージガス供給弁とを備える第1の接続部と、第2の弁と、第2の弁に連通され、第1の接続継手と接続された第2の接続継手とを備える第2の接続部とを備える液化ガス供給用接続機構において、第1の弁を閉じて液化ガスの供給を停止し、パージガス供給弁を開き、パージ用のガスを第1及び第2の接続部へ供給し、液化ガスが第1及び第2の接続部からパージされたか否かをモニタし、パージ完了確認後、第2の弁を閉じ、第1及び第2の接続継手の接続を解除することを特徴としている。
本発明の液化ガス供給用接続機構切離し方法は、相互に連通される第1の弁、第1の接続継手、パージガス供給弁とを備える第1の接続部と、第2の弁と、第2の弁に連通され、第1の接続継手と接続された第2の接続継手とを備える第2の接続部とを備える液化ガス供給用接続機構において、第1の弁を閉じて液化ガスの供給を停止し、パージガス供給弁を開き、パージ用のガスを第1及び第2の接続部へ供給し、液化ガスが第1及び第2の接続部からパージされたか否かをモニタし、パージ完了確認後、第2の弁を閉じ、第1及び第2の接続継手の接続を解除することを特徴としている。
第2の接続部が、第2の弁および第2の接続継手に連通されるサンプリング弁を更に備え、モニタがサンプリング弁において実行されることが好ましい。パージ完了確認後、サンプリング弁を閉じた後に第2の弁を閉じることが好ましい。液化ガス供給停止後、第2の弁を閉じるまでの間、第2の弁を微開とすることが好ましい。
本発明によれば、切離し可能なラインを通して液化ガスを送液するシステムにおいて、ライン切離しの際、ライン内に残留する気化された液化ガスおよび液化ガスそのものの大気への放出を抑えるために必要なパージ用ガスの量を大幅に減らすことができる。
以下、本発明の実施形態について添付図面を参照して説明する。
図1は、本発明の一実施形態であるライン接続機構を備える液化ガス供給システムの構成を示すブロック図である。
図1は、本発明の一実施形態であるライン接続機構を備える液化ガス供給システムの構成を示すブロック図である。
本実施形態の液化ガス供給システム10は、例えばLNG燃料船11など、液化ガスを燃料とする輸送機器へ、LNGなどの液化ガス燃料を供給するバンカーシステムである。図1に示される例では、港湾に設置された燃料供給施設(液化ガス供給施設)12のLNG貯蔵タンク(液化ガス貯蔵タンク)13から、燃料ライン(液化ガスライン)を通して係留されたLNG燃料船11のLNG燃料タンク(液化ガスタンク)15へ液化天然ガス(液化ガス)が供給される。
LNG貯蔵タンク13からは、例えばフレキシブルなバンカーホース16を通してLNGが送出される。バンカーホース16の先端にはアウトレット接続部17が設けられ、バンカー作業時、LNG燃料船11のインレット接続部18に接続される。アウトレット接続部17は、例えば丁字管を備え、主管の一端には液化ガス供給弁19、主管の他端には接続継手20が設けられる。また枝管にはパージガス供給弁21と継手22が設けられる。
液化ガス供給弁19はバンカーホース16に接続されており、これを開閉することによりバンカーホース16から供給される液化ガスの流通が制御される。接続継手20は例えばフランジ継手であり、バンカー作業時、船側のインレット接続部18のフランジ継手に接続される。パージガス供給弁21は、窒素ガスなどパージ用のガスの丁字管への供給を制御する弁であり、枝管の先端に設けられた継手22等を介してパージガス供給設備23と接続可能である。
パージガス供給設備23は、輸送機器であるLNG燃料船11に設けられ、例えば船上に積み込まれた窒素ガスボンベ(パージガス供給源)24から固定管25、フレキシブルホース26を介して窒素ガスをアウトレット接続部17へ供給する。なおフレキシブルホース26の先端には、アウトレット接続部17の枝管に設けられた継手22と連結可能な継手27が設けられる。
インレット接続部18も例えば丁字管を備え、主管の一端には接続継手28、主管の他端には液化ガス開閉弁29が設けられる。枝管には、例えばサンプリング弁30が設けられる。接続継手28は、アウトレット接続部17の接続継手20に相補的であり、本実施形態ではフランジである。液化ガス開閉弁29は、固定パイプ31を通して船内LNG燃料タンク15へと接続される。
次に本実施形態のバンカーシステムでのバンカー作業の手順について説明する。本実施形態では、フランジ継手20、28を接続し、液化ガス供給弁19、液化ガス開閉弁29を開くことで、LNG貯蔵タンク13からLNG燃料船11のLNG燃料タンク15へ液化天然ガスを供給する。バンカリングは、例えば液化ガス供給弁19を閉じることで終了し、このとき液化ガス開閉弁29は、開状態、より好ましくは微開状態とされる。
その後、パージガス供給弁21を開き、パージガス供給設備23の窒素ガスボンベ24から継手27、22を介してアウトレット接続部17へ窒素ガスを供給する。なお、継手22、27の接続は、バンカリング開始前、バンカリング中、あるいはバンカリング終了後の何れに行ってもよい。
このときアウトレット接続部17、インレット接続部18内に残留する液化天然ガスおよび気化した天然ガスは、窒素ガスにより液化ガス開閉弁29を通してLNG燃料タンク15側へと押しやられ、パージされる。作業者は、サンプリング弁30を開き、管内ガスの組成を確認(例えばメタンガス濃度が十分に低いことを確認)することでパージの完了をモニタする。パージ完了確認後、サンプリング弁30を閉めるとともに液化ガス開閉弁29及びパージガス供給弁21を閉じ、窒素ガス(パージガス)の供給を停止する。そして継手22、27の連結を解き、燃料供給施設12側のアウトレット接続部17を、船舶11側のインレット接続部18から切り離す。
以上のように、本実施形態によれば、アウトレット接続部の液化ガス供給弁とインレット接続部の液化ガス開閉弁の間のみをパージすればよく、パージに必要なガスの量を大幅に低減できる。このため、パージ用のガス供給源を輸送機器側に配置することが可能となり、例えばパージ用のガス供給施設を持たない小規模施設などを利用する場合にも、液化ガス燃料の漏洩を防止できる。
なお燃料供給施設は、本実施形態のように陸上タンクであってもよいが、バンカー船であってもよく、またタンクローリ車であってもよい。また、本実施形態では液化ガス燃料を使用する輸送機器を船舶としたが、貯蔵タンクからタンクローリへ液化ガス燃料を移す場合や、ロケットへの液化ガス燃料の供給など、輸送機器は船舶に限定されるものではない。また、本実施形態は、大気への放出を防止する必要がある液化ガスの供給ラインの切離しにも利用でき、液化ガスとして液化ガス燃料に限定されるものではない。
本実施形態では、船側へパージしたため供給施設側の接続部の枝管からパージ用のガスを供給したが、供給施設側へパージする場合には、船側の枝管からパージ用のガスを供給する構成とすることも可能である。また本実施形態では両接続部に丁字管を用い各弁および継手が連通されていたが、両接続部は丁字管に限定されるものではなく、その岐数も本実施形態に限定されるものではない。またサンプリング用に別の方法を採用することにより、サンプリング弁を省略することも可能である。また、本実施形態ではパージガス供給弁とサンプリング弁をそれぞれ異なる接続部に設けたが、両者を同じ接続部に設けることも可能である。
本実施形態の各弁には、例えば止め弁が用いられる。また液化ガス貯蔵タンク側やパージガス供給設備側などにも、バルブは存在し、バンカリング終了時やパージ終了時には、これらの弁が閉じられるが、本実施形態ではその説明が省略されている。
また、本実施形態では、パージガス供給源(窒素ガスボンベ)を固定管(25)に接続し、固定管に接続されたフレキシブルホース(26)を介してアウトレット接続部へパージガスを供給した。しかし、固定管(25)を省き、パージガス供給源から直接フレキシブルホースを介してアウトレット接続部へパージガスを供給する構成であってもよい。
10 液化ガス供給システム
11 LNG燃料船(輸送機器)
12 燃料供給施設(液化ガス供給施設)
13 LNG貯蔵タンク(液化ガス貯蔵タンク)
15 LNG燃料タンク(液化ガスタンク)
16 バンカーホース(可撓ホース)
17 アウトレット接続部
18 インレット接続部
19 液化ガス供給弁
20 接続継手
21 パージガス供給弁
22 継手
23 パージガス供給設備
24 窒素ガスボンベ(パージガス供給源)
25 固定管
26 フレキシブルホース
27 継手
28 接続継手
29 液化ガス開閉弁
30 サンプリング弁
31 固定パイプ
11 LNG燃料船(輸送機器)
12 燃料供給施設(液化ガス供給施設)
13 LNG貯蔵タンク(液化ガス貯蔵タンク)
15 LNG燃料タンク(液化ガスタンク)
16 バンカーホース(可撓ホース)
17 アウトレット接続部
18 インレット接続部
19 液化ガス供給弁
20 接続継手
21 パージガス供給弁
22 継手
23 パージガス供給設備
24 窒素ガスボンベ(パージガス供給源)
25 固定管
26 フレキシブルホース
27 継手
28 接続継手
29 液化ガス開閉弁
30 サンプリング弁
31 固定パイプ
Claims (11)
- 相互に連通される第1の弁、第1の接続継手、パージガス供給弁とを備える第1の接続部と、
第2の弁と、前記第2の弁に連通され、前記第1の接続継手と接続可能な第2の接続継手とを備える第2の接続部と
を備えることを特徴とする液化ガス供給用接続機構。 - 前記第1の接続部が、前記パージガス供給弁をパージガス供給源へと接続するための継手を更に供えることを特徴とする請求項1に記載の液化ガス供給用接続機構。
- 前記第2の接続部が、第2の弁および第2の接続継手に連通されるサンプリング弁を更に備えることを特徴とする請求項1または請求項2に記載の液化ガス供給用接続機構。
- 前記パージガス供給源が、輸送機器に配置されることを特徴とする請求項1~3の何れか一項に記載の液化ガス供給用接続機構。
- 前記第1の弁が、液化ガスを供給する側の弁であり、前記第2の弁が前記液化ガスの供給を受ける側の弁であることを特徴とする請求項1~4の何れか一項に記載の液化ガス供給用接続機構。
- 請求項1~5の何れか一項に記載の液化ガス供給用接続機構の前記第1または第2の接続部の何れか一方を備えることを特徴とする船舶。
- 前記液化ガスが液化ガス燃料であり、前記液化ガスを燃料として使用することを特徴とする請求項6に記載の船舶。
- 相互に連通される第1の弁、第1の接続継手、パージガス供給弁とを備える第1の接続部と、第2の弁と、前記第2の弁に連通され、前記第1の接続継手と接続された第2の接続継手とを備える第2の接続部とを備える液化ガス供給用接続機構において、
前記第1の弁を閉じて液化ガスの供給を停止し、
前記パージガス供給弁を開き、パージ用のガスを前記第1及び第2の接続部へ供給し、
前記液化ガスが前記第1及び第2の接続部からパージされたか否かをモニタし、
パージ完了確認後、前記第2の弁を閉じ、前記第1及び第2の接続継手の接続を解除する
ことを特徴とする液化ガス供給用接続機構切離し方法。 - 前記第2の接続部が、第2の弁および第2の接続継手に連通されるサンプリング弁を更に備え、前記モニタが前記サンプリング弁において実行されることを特徴とする請求項8に記載の液化ガス供給用接続機構切離し方法。
- 前記パージ完了確認後、前記サンプリング弁を閉じた後に前記第2の弁を閉じることを特徴とする請求項9に記載の液化ガス供給用接続機構切離し方法。
- 前記液化ガス供給停止後、前記第2の弁を閉じるまでの間、前記第2の弁を微開とすることを特徴とする請求項8~10の何れか一項に記載の液化ガス供給用接続機構切離し方法。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201480012291.4A CN105008787A (zh) | 2013-03-08 | 2014-02-27 | 液化气供给用连接机构 |
KR1020157024136A KR20150125659A (ko) | 2013-03-08 | 2014-02-27 | 액화 가스 공급용 접속 기구 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2013046921A JP5894097B2 (ja) | 2013-03-08 | 2013-03-08 | 液化ガス供給用接続機構 |
JP2013-046921 | 2013-03-08 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2014136644A1 true WO2014136644A1 (ja) | 2014-09-12 |
Family
ID=51491163
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2014/054834 WO2014136644A1 (ja) | 2013-03-08 | 2014-02-27 | 液化ガス供給用接続機構 |
Country Status (4)
Country | Link |
---|---|
JP (1) | JP5894097B2 (ja) |
KR (1) | KR20150125659A (ja) |
CN (1) | CN105008787A (ja) |
WO (1) | WO2014136644A1 (ja) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019038364A3 (en) * | 2017-08-23 | 2019-05-16 | Englemer B.V.B.A. | Method and system to drain a liquid gas transfer hose |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101887051B1 (ko) * | 2016-02-12 | 2018-08-10 | 한국과학기술원 | 오브젝트 탐닉행동을 활용한 동물행동 조절 방법 |
JP6709195B2 (ja) * | 2017-06-30 | 2020-06-10 | 千代田化工建設株式会社 | 液化ガスの排出システム及び排出方法 |
CN108791691A (zh) * | 2018-06-13 | 2018-11-13 | 南通诺德瑞海洋工程研究院有限公司 | 一种用于lng罐箱运输的双燃料甲板运输船 |
JP2021127083A (ja) * | 2020-02-17 | 2021-09-02 | 住友重機械マリンエンジニアリング株式会社 | 漏洩監視システム |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006307936A (ja) * | 2005-04-27 | 2006-11-09 | Kita Kyushu Lng Kk | Lngの出荷方法 |
JP2009014057A (ja) * | 2007-07-03 | 2009-01-22 | Ihi Corp | 低温液化ガスタンクの窒素ガスパージ方法及び装置 |
JP2011093551A (ja) * | 2009-10-28 | 2011-05-12 | Ihi Plant Construction Co Ltd | Lng受入基地タンクからのlng出荷方法及びその装置 |
JP2012207710A (ja) * | 2011-03-29 | 2012-10-25 | Ihi Corp | Lngタンクのパージ方法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58178097A (ja) * | 1982-04-12 | 1983-10-18 | Ishikawajima Harima Heavy Ind Co Ltd | ロ−デイングア−ム内の液落し、ガスパ−ジ装置 |
AT405442B (de) * | 1997-12-19 | 1999-08-25 | Wiener Stadtwerke | Verfahren und anordnung zur entfernung von brenngasen aus gasnetzen |
NO312715B2 (no) * | 1999-10-27 | 2002-06-24 | Statoil Asa | System for offshore overforing av flytendegjort naturgass |
CN102264596B (zh) * | 2008-11-20 | 2015-11-25 | 单点系泊公司 | 用于海上输送碳氢化合物的多功能单元 |
JP5820628B2 (ja) * | 2011-06-10 | 2015-11-24 | 岩谷産業株式会社 | 極低温流体用配管の接続継手及び極低温流体の供給設備 |
-
2013
- 2013-03-08 JP JP2013046921A patent/JP5894097B2/ja active Active
-
2014
- 2014-02-27 WO PCT/JP2014/054834 patent/WO2014136644A1/ja active Application Filing
- 2014-02-27 CN CN201480012291.4A patent/CN105008787A/zh active Pending
- 2014-02-27 KR KR1020157024136A patent/KR20150125659A/ko not_active Application Discontinuation
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006307936A (ja) * | 2005-04-27 | 2006-11-09 | Kita Kyushu Lng Kk | Lngの出荷方法 |
JP2009014057A (ja) * | 2007-07-03 | 2009-01-22 | Ihi Corp | 低温液化ガスタンクの窒素ガスパージ方法及び装置 |
JP2011093551A (ja) * | 2009-10-28 | 2011-05-12 | Ihi Plant Construction Co Ltd | Lng受入基地タンクからのlng出荷方法及びその装置 |
JP2012207710A (ja) * | 2011-03-29 | 2012-10-25 | Ihi Corp | Lngタンクのパージ方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2019038364A3 (en) * | 2017-08-23 | 2019-05-16 | Englemer B.V.B.A. | Method and system to drain a liquid gas transfer hose |
Also Published As
Publication number | Publication date |
---|---|
JP5894097B2 (ja) | 2016-03-23 |
JP2014173661A (ja) | 2014-09-22 |
CN105008787A (zh) | 2015-10-28 |
KR20150125659A (ko) | 2015-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2014136644A1 (ja) | 液化ガス供給用接続機構 | |
JP4933452B2 (ja) | 流体を接続および輸送するキットおよび装置ならびに前記装置の使用方法 | |
JP6389011B2 (ja) | 燃料タンク、特にlngタンクの弁システム | |
US9416906B2 (en) | System and method for transferring natural gas for utilization as a fuel | |
DK178151B1 (en) | Liquid Natural Gas transfer | |
KR102351073B1 (ko) | 실내 안전 장치, 액화 연료 가스 시스템 및 차량 | |
JP2014031829A (ja) | 残留lng回収方法 | |
US9546759B2 (en) | System and method for transferring natural gas for utilization as a fuel | |
US11441738B2 (en) | Pressure vessel system for a motor vehicle | |
JP6215985B2 (ja) | 液化ガス供給用接続機構 | |
JP7569683B2 (ja) | 液体水素用の可搬型荷役設備 | |
KR200476889Y1 (ko) | 카고 탱크의 가스 배출 장치 | |
JP4936750B2 (ja) | 燃料供給システム | |
AU2015329208B2 (en) | Liquefied hydrogen transferring system | |
CN106061832B (zh) | 用于将液化天然气从一船只输送至一设施的系统 | |
JP7445763B2 (ja) | 船舶の液化ガスの供給システム及び液化ガスの供給方法 | |
JP2013170648A (ja) | タンク搭載車両 | |
JP2010196823A (ja) | 低温液化ガス払出し装置 | |
JP2008144878A (ja) | 液化ガスの受入システム及び液化ガスの受入システムの運転方法 | |
WO2024111078A1 (ja) | 移送設備及びガス置換方法 | |
WO2024105781A1 (ja) | ガス置換方法及び液化ガス設備 | |
WO2014152373A1 (en) | System and method for transferring natural gas for utilization as a fuel | |
KR20170120422A (ko) | Lng 생산기지 시운전 장치 및 이를 이용한 lng 생산기지 시운전 방법 | |
JP2009115179A (ja) | 液化天然ガス受入システム及び受入方法 | |
KR20180020447A (ko) | Lng 재기화 시스템의 고압펌프 가압 장치 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 14760421 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 20157024136 Country of ref document: KR Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 14760421 Country of ref document: EP Kind code of ref document: A1 |