WO2013177991A1 - Steel structure upright post - Google Patents

Steel structure upright post Download PDF

Info

Publication number
WO2013177991A1
WO2013177991A1 PCT/CN2013/074620 CN2013074620W WO2013177991A1 WO 2013177991 A1 WO2013177991 A1 WO 2013177991A1 CN 2013074620 W CN2013074620 W CN 2013074620W WO 2013177991 A1 WO2013177991 A1 WO 2013177991A1
Authority
WO
WIPO (PCT)
Prior art keywords
steel structure
upright post
flange
column
structure upright
Prior art date
Application number
PCT/CN2013/074620
Other languages
French (fr)
Chinese (zh)
Inventor
张跃
Original Assignee
Zhang Yue
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhang Yue filed Critical Zhang Yue
Publication of WO2013177991A1 publication Critical patent/WO2013177991A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/32Columns; Pillars; Struts of metal

Definitions

  • the invention relates to the technical field of fixed buildings, and in particular to a steel structure column for fixing a building.
  • Low-carbon energy conservation is the common task and goal of human beings around the world, and low-carbon energy-efficient buildings with sustainable scientific development are an important aspect.
  • Most of the existing fixed buildings are reinforced concrete structures, on-site pouring, on-site construction, serious waste of raw materials, construction waste, time and labor, slow speed, high energy consumption, uncontrollable quality, and cannot achieve standardization and factory production.
  • it is a backward process method that is eliminated.
  • the technical problem to be solved by the present invention is: to solve the problems existing in the prior art described above, and to provide a factory standardized production, on-site assembly, labor saving, fast speed, no construction waste, material saving, earthquake resistance, high building strength A steel structure column that is environmentally friendly and energy efficient.
  • the steel structure column has a column flange at the upper end and/or the lower end, and the steel structure column is fixed by the column flange to the floor flange and the steel structure floor.
  • the upper end and/or the lower end of the steel structure column is fixed with a guiding head.
  • the invention completely changes the traditional backward reinforced concrete on-site pouring construction method, and adopts a new steel structure system, thereby realizing factory standardized production, quality controllable, on-site assembly, saving labor and time, high speed, good quality, saving Raw materials, no construction waste, environmental protection and energy saving, and high building strength, earthquake resistance and disaster resistance are major innovations in the construction field.
  • Figure 1 is a schematic view showing the mounting structure of the present invention
  • Figure 2 is a partial enlarged view of Figure 1.
  • the upper and/or lower ends of the steel structure column 1 of the present invention have a column flange, and the steel structure column 1 is connected to the steel structure floor 2 through the column flange 3 and the floor flange 4.
  • the guide head 6 is fixed to the upper end and/or the lower end of the steel structure column 1 .

Abstract

A steel structure upright post (1) has a flange (3) arranged at the upper end and/or the lower end thereof. The steel structure upright post (1) is connected to a steel structure floor slab (2) through connection of the flange (3) thereof and a floor slab flange (4). In addition, a guide head (6) is fixed to the upper end and/or the lower end of the steel structure upright post (1). The steel structure upright post (1) implements factorized and standardized production, and is environment-friendly and energy-saving.

Description

一种钢结构立柱  Steel structure column
技术领域 Technical field
本发明涉及固定建筑物技术领域, 具体涉及一种固定建筑物的钢结构 立柱。  The invention relates to the technical field of fixed buildings, and in particular to a steel structure column for fixing a building.
背景技术 Background technique
低碳节能, 是全球人类共同的任务和目标, 而可持续科学发展的低碳 节能建筑是其中的一个重要方面。 现有的固定建筑物大都为钢筋混凝土结 构, 现场浇注, 现场施工, 原材料浪费严重, 建筑垃圾多, 费工费时, 速 度慢, 能耗高, 质量不可控, 不能实现标准化、 工厂化生产, 不符合国家 的环保节能政策, 是一种淘汰的落后工艺方法。  Low-carbon energy conservation is the common task and goal of human beings around the world, and low-carbon energy-efficient buildings with sustainable scientific development are an important aspect. Most of the existing fixed buildings are reinforced concrete structures, on-site pouring, on-site construction, serious waste of raw materials, construction waste, time and labor, slow speed, high energy consumption, uncontrollable quality, and cannot achieve standardization and factory production. In line with the national environmental protection and energy conservation policy, it is a backward process method that is eliminated.
发明内容 Summary of the invention
本发明所要解决的技术问题是: 解决上述现有技术存在的问题, 而提 供一种工厂化标准化生产、 现场组装、 省工省时、 速度快、 无建筑垃圾、 节省原材料、 抗震、 建筑强度高、 环保节能的一种钢结构立柱。  The technical problem to be solved by the present invention is: to solve the problems existing in the prior art described above, and to provide a factory standardized production, on-site assembly, labor saving, fast speed, no construction waste, material saving, earthquake resistance, high building strength A steel structure column that is environmentally friendly and energy efficient.
本发明采用的技术方案是:  The technical solution adopted by the invention is:
这种钢结构立柱的上端和 /或下端具有立柱法兰, 钢结构立柱通过立柱 法兰与楼板法兰、 钢结构楼板连接固定。  The steel structure column has a column flange at the upper end and/or the lower end, and the steel structure column is fixed by the column flange to the floor flange and the steel structure floor.
上述技术方案中, 所述的钢结构立柱上端和 /或下端固定有导向头。 本发明完全改变了传统落后的钢筋混凝土现场浇注施工方法, 而采用 新型钢结构系统, 这样就可实现工厂化标准化生产, 质量可控, 现场组装, 省工省时, 速度快, 质量好, 节省原材料, 无建筑垃圾, 环保节能, 而且 建筑强度高, 抗震抗灾, 是建筑领域的重大创新。 采用本发明的钢结构立 柱与其它工厂化标准化生产的抗震节能净化建筑部件一起构建可持续建筑 能实现 9度抗震, 5倍节能, 20倍空气净化, 7 %的建筑用工量, 93 %的工 厂化程度, 360小时建 30层高楼, 改写了人类的建筑历史。 In the above technical solution, the upper end and/or the lower end of the steel structure column is fixed with a guiding head. The invention completely changes the traditional backward reinforced concrete on-site pouring construction method, and adopts a new steel structure system, thereby realizing factory standardized production, quality controllable, on-site assembly, saving labor and time, high speed, good quality, saving Raw materials, no construction waste, environmental protection and energy saving, and high building strength, earthquake resistance and disaster resistance are major innovations in the construction field. Constructing sustainable buildings with the steel structure columns of the present invention together with other factory-standardized production of seismic energy-saving and purifying building components It can achieve 9-degree seismic, 5 times energy saving, 20 times air purification, 7 % construction work, 93% factory level, 360-hour construction of 30-storey building, rewriting the history of human architecture.
附图说明 DRAWINGS
图 1为本发明安装结构示意图;  Figure 1 is a schematic view showing the mounting structure of the present invention;
图 2为图 1中的局部放大图。  Figure 2 is a partial enlarged view of Figure 1.
图中, 1一钢结构立柱, 2—钢结构楼板, 3—立柱法兰, 4一楼板法兰, 5—楼板导向管, 6—导向头。  In the figure, 1 steel structure column, 2 - steel structure floor, 3 - column flange, 4 first floor flange, 5 - floor guide tube, 6 - guide head.
具体实施方式 detailed description
参见图 1、图 2,本发明的钢结构立柱 1的上端和 /或下端具有立柱法兰, 钢结构立柱 1通过立柱法兰 3、 楼板法兰 4与钢结构楼板 2连接。  Referring to Figures 1 and 2, the upper and/or lower ends of the steel structure column 1 of the present invention have a column flange, and the steel structure column 1 is connected to the steel structure floor 2 through the column flange 3 and the floor flange 4.
上述技术方案中, 所述的钢结构立柱 1上端和 /或下端固定有导向头 6。  In the above technical solution, the guide head 6 is fixed to the upper end and/or the lower end of the steel structure column 1 .

Claims

权利要求 Rights request
1、 一种钢结构立柱, 其特征在于: 这种钢结构立柱的上端和 /或下端具 有立柱法兰, 钢结构立柱通过立柱法兰与楼板法兰、 钢结构楼板连接固定。 1. A steel structure column, characterized in that: the upper end and/or the lower end of the steel structure column has a column flange, and the steel structure column is connected and fixed with the floor flange and the steel structure floor through the column flange.
2、 根据权利要求 1所述的钢结构立柱, 其特征在于: 所述的钢结构立 柱上端和 /或下端固定有导向头。 2. The steel structure column according to claim 1, characterized in that: a guide head is fixed at the upper end and/or the lower end of the steel structure column.
PCT/CN2013/074620 2012-05-30 2013-04-24 Steel structure upright post WO2013177991A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201210172543.2 2012-05-30
CN2012101725432A CN103452240A (en) 2012-05-30 2012-05-30 Steel structure upright post

Publications (1)

Publication Number Publication Date
WO2013177991A1 true WO2013177991A1 (en) 2013-12-05

Family

ID=49672381

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2013/074620 WO2013177991A1 (en) 2012-05-30 2013-04-24 Steel structure upright post

Country Status (2)

Country Link
CN (1) CN103452240A (en)
WO (1) WO2013177991A1 (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09328817A (en) * 1996-06-11 1997-12-22 Ohbayashi Corp Reinforcing construction of joint section and manufacturing of pipe-like body used therefor
CN2429555Y (en) * 2000-07-14 2001-05-09 北京深华科交通工程有限公司 Gantry for traffic sign
CN2656490Y (en) * 2003-10-22 2004-11-17 深圳市捷顺科技实业有限公司 Handrail conncting device
CN101498149A (en) * 2008-01-22 2009-08-05 奥塔诺姆建筑元件推销股份有限公司 Attachment head and system for creating superstructures
CN101775840A (en) * 2010-01-27 2010-07-14 江苏省电力设计院 Beam column node suitable for quadrate steel pipe column
AU2012200684A1 (en) * 2004-11-19 2012-03-01 Onesteel Trading Pty Limited Frame Fitting
CN202627316U (en) * 2012-05-30 2012-12-26 远大可建科技有限公司 Steel structure upright

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3303190C2 (en) * 1983-02-01 1985-05-23 Octanorm-Vertriebs-GmbH für Bauelemente, 7024 Filderstadt Kit for creating mobile structures, in particular for trade fair and exhibition structures
JP2003278273A (en) * 2002-03-27 2003-10-02 Shimizu Corp Connection-section structure of steel structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09328817A (en) * 1996-06-11 1997-12-22 Ohbayashi Corp Reinforcing construction of joint section and manufacturing of pipe-like body used therefor
CN2429555Y (en) * 2000-07-14 2001-05-09 北京深华科交通工程有限公司 Gantry for traffic sign
CN2656490Y (en) * 2003-10-22 2004-11-17 深圳市捷顺科技实业有限公司 Handrail conncting device
AU2012200684A1 (en) * 2004-11-19 2012-03-01 Onesteel Trading Pty Limited Frame Fitting
CN101498149A (en) * 2008-01-22 2009-08-05 奥塔诺姆建筑元件推销股份有限公司 Attachment head and system for creating superstructures
CN101775840A (en) * 2010-01-27 2010-07-14 江苏省电力设计院 Beam column node suitable for quadrate steel pipe column
CN202627316U (en) * 2012-05-30 2012-12-26 远大可建科技有限公司 Steel structure upright

Also Published As

Publication number Publication date
CN103452240A (en) 2013-12-18

Similar Documents

Publication Publication Date Title
CN104032840B (en) The prestressing force assembling frame node connecting structure of additional angle steel
CN204163196U (en) A kind of embedded concrete-filled steel square tubular column in T-steel top flange and steel beam connecting joint
CN203334425U (en) Steel structure unit and steel structure system
CN103541511A (en) Method for manufacturing concrete-filled steel tube special-shaped column with built-in polyvinyl chloride-fiber reinforce plastic (PVC-FRP) pipe and high-strength concrete core column
WO2013135108A1 (en) Assembled steel structure hollow building
CN203924364U (en) The prestressing force assembling frame structure node syndeton of additional angle steel
CN203546912U (en) Penetrating rib type node of channel steel connected rectangular concrete filled steel tubular column and steel girder
CN203284969U (en) Bamboo-plastic composite pipe-restrained section steel high-strength concrete structure
CN103452187A (en) Steel structure concrete internal-external thermal insulation integration module house
CN204098241U (en) Trapezoidal steel plate interpolation type rectangular steel-tube concrete column and steel beam connecting joint
CN201991226U (en) Flange template support structure
CN202810195U (en) Template reinforcing system
CN203475600U (en) Steel-structure concrete inside and outside heat-preservation integrated module-built house
WO2013177991A1 (en) Steel structure upright post
WO2013177993A1 (en) Integral steel structure upright post
CN201635417U (en) Reinforcing constructional column of masonry structure
CN202990256U (en) Reinforcing steel bar positioning frame
CN103541512B (en) A kind of preparation method of FRP pipe concrete hetermorphiscal column of built-in high strength concrete filled steel tube stem stem
CN106284681B (en) Assembly concrete is whole without heat bridge board wall and the connection method of running-on floor
WO2013177988A1 (en) Floor slab with prefabricated water and electricity components
CN208870191U (en) A kind of novel fabricated reinforced concrete building
WO2013177994A1 (en) Double-head steel structure upright post
CN202492930U (en) Connecting device of composite wallboards and floorslabs
WO2013177989A1 (en) Floor slab with prefabricated pipelines and prefabricated joints
CN206428805U (en) A kind of concrete prefabricated balcony of assembled steel

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 13796674

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 11-06-2015)

122 Ep: pct application non-entry in european phase

Ref document number: 13796674

Country of ref document: EP

Kind code of ref document: A1