WO2012069015A1 - 混凝土板结构构件以及其浇注施工方法 - Google Patents

混凝土板结构构件以及其浇注施工方法 Download PDF

Info

Publication number
WO2012069015A1
WO2012069015A1 PCT/CN2011/082967 CN2011082967W WO2012069015A1 WO 2012069015 A1 WO2012069015 A1 WO 2012069015A1 CN 2011082967 W CN2011082967 W CN 2011082967W WO 2012069015 A1 WO2012069015 A1 WO 2012069015A1
Authority
WO
WIPO (PCT)
Prior art keywords
concrete
cold
formed thin
walled steel
keel
Prior art date
Application number
PCT/CN2011/082967
Other languages
English (en)
French (fr)
Inventor
尹义青
徐正林
蔡志红
Original Assignee
欧文斯科宁知识产权资产有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 欧文斯科宁知识产权资产有限公司 filed Critical 欧文斯科宁知识产权资产有限公司
Priority to US13/989,120 priority Critical patent/US20140013683A1/en
Publication of WO2012069015A1 publication Critical patent/WO2012069015A1/zh

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/29Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated the prefabricated parts of the beams consisting wholly of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • E04B1/161Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2/8647Walls made by casting, pouring, or tamping in situ made in permanent forms with ties going through the forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
    • E04C2/06Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres reinforced
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2002/867Corner details
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2002/8682Mixed technique using permanent and reusable forms

Definitions

  • the present invention belongs to the field of building structural members and construction methods, and in particular, to a construction method of a concrete structural member and a cast concrete slab. Background technique
  • a cold-formed thin-walled steel frame includes a plurality of vertically cold-formed thin-walled steels spaced apart in parallel and arranged in parallel.
  • the main plane of the cold-formed thin-walled steel is arranged perpendicular to the main plane of the concrete slab structural member.
  • a compartment is formed between each of the adjacent cold-formed thin-walled steels, which causes some problems.
  • An object of the present invention is to provide a novel cold-formed thin-walled steel-concrete composite concrete structural member which can avoid or minimize the prior art cold-formed thin-walled steel reinforced concrete structural members due to cold bending
  • the main plane of the wall steel is arranged perpendicular to the main plane of the concrete slab structural member and there is a problem that the flow is hindered when the concrete is poured.
  • Another object of the present invention is to provide a cold bridge problem which is solved by vertically-arranged cold-formed thin-walled steel in a concrete slab after casting.
  • a concrete slab structural member comprising: a cold-formed thin-walled steel frame; concrete wrapped around the cold-formed thin-walled steel frame; the cold-formed thin-walled steel frame including a plurality of structural members along the concrete slab Longitudinal cold-formed thin-walled steel keels (5, 9) arranged parallel to each other in the transverse direction of the main plane; wherein each longitudinally cold-formed thin-walled steel keel comprises two longitudinally cold-formed thin-walled steels (51, 52 , 91 , 92 ), a main plane of the longitudinal cold-formed thin-walled steel is parallel to a main plane of the concrete slab structural member, and the two longitudinally cold-formed thin-walled steels are along a main member of the concrete slab structural member
  • the plane vertical directions are opposite to each other and spaced apart such that there is a space (200) between the two longitudinally cold-formed thin-walled steels through which the concrete flows when the concrete is poured, the two longitudinal cold-bending The space left between the wall
  • each longitudinally cold-formed thin-walled steel keel comprises two longitudinally cold-formed thin-walled steels, a main plane of the longitudinally cold-formed thin-walled steel,
  • the principal planes of the concrete slab structural members are parallel to each other, and the two longitudinally cold-formed thin-walled steels are opposed to each other and spaced apart in a direction perpendicular to the main plane of the concrete slab structural member, so that the two longitudinal cold bends A space is left between the thin-walled steels so that the concrete can easily flow from the space left between the two longitudinally-formed thin-walled steels when the concrete is poured.
  • the cold bend of the present invention The thin-walled steel is stretched in a direction parallel to the main plane of the concrete structural member (perpendicular from the indoor to the outdoor), avoiding the formation of a cold bridge between the inside and the outside.
  • Another problem of the present invention is to solve the problem in the prior art concrete slabs, such as wallboard or roof slab-cast concrete slabs, because the cold-formed thin-walled steel is perpendicular to the main plane of the concrete slab. Cold bridge problem.
  • the cold-formed thin-walled steel reinforced concrete structure of the present invention has additional advantages over the cold-formed thin-walled steel reinforced concrete structure of the prior art.
  • As the concrete slab its damage mainly occurs from the vicinity of the two outer main surfaces of the slab, and in the middle of the slab along the direction perpendicular to the main plane of the slab, it is practically unstrength.
  • the cold-formed thin-walled steel is arranged perpendicular to the main plane of the concrete slab, so that the load-bearing effect of the portion of the cold-formed thin-walled steel at the middle portion of the slab is not fully reflected. , caused a waste of steel.
  • each longitudinally cold-formed thin-walled steel keel comprises two longitudinally cold-formed thin-walled steels, the main plane of the longitudinally cold-formed thin-walled steel and the principal planes of the concrete slab structural members are parallel to each other,
  • the two longitudinally cold-formed thin-walled steels are opposed to each other and spaced apart in a direction perpendicular to the principal plane of the concrete slab structural member such that a space is left between the two longitudinally cold-formed thin-walled sections.
  • the cold-formed thin-walled steel structure has the effect of saving steel.
  • the main planes of the two longitudinally cold-formed thin-walled steels included in each of the longitudinally cold-formed thin-walled steel keels are parallel to the main plane of the concrete slab structural members, and the two longitudinal cold bends
  • the thin-walled steels are opposed to each other and spaced apart in a direction perpendicular to the major plane of the concrete slab structural members, which results in more stable self-supporting, which can reduce or eliminate additional support of the concrete formwork.
  • a complete building industrialization system will be formed. This system covers both architectural design, building structure and construction, and has a wide range of applications. The system has many advantages. The specific examples are as follows:
  • the temporary structure is greatly improved without increasing the total amount of steel.
  • the stability and dimensional accuracy make the construction process more convenient, fast and reliable, and also effectively reduce the use of temporary support.
  • the new industrialized assembly technology formed by the combination of the thin-walled steel frame concrete structure and the modular concrete slab of the present invention can save labor by 35% -50% and shorten the construction period by more than 40%.
  • each of the longitudinally cold-formed thin-walled steel keels (5) comprises longitudinally cold-formed thin-walled steels (51, 52) with a plurality of penetrating products distributed along the length thereof for the concrete flow when pouring concrete
  • the keel is punched (191, 192), and the connecting steel plates (61, 62) are provided with crimping holes (193, 194) through which concrete flows when concrete is poured.
  • the cold-formed thin-walled steel frame further comprises: a transversely connected cold-formed thin-walled steel keel comprising laterally cold-formed thin-walled steel (81, 82); and an obliquely supported cold-formed thin-walled steel keel including oblique To the cold-formed thin-walled steel (31, 32); a plurality of parallel-arranged longitudinally cold-formed thin-walled steel keels are connected by the transversely connected cold-formed thin-walled steel keels, the obliquely supported cold-formed thin-walled steel keels and The longitudinal cold-formed thin-walled steel keel joint, the longitudinal cold-formed thin-walled steel keel, the transversely connected cold-formed thin-walled steel keel and the obliquely supported cold-formed thin-walled steel keel are connected to form a stable The overall rigid structure.
  • a transversely connected cold-formed thin-walled steel keel comprising laterally cold
  • the concrete slab structural member is a concrete wall slab structural member
  • the longitudinal cold-formed thin-walled steel keel is a vertically cold-formed thin-walled steel keel placed along a vertical extension.
  • the starting platform is fixed with an starting sleeve (4), the starting sleeve (4) has an initial vertical cold bend protruding upwards
  • the longitudinally cold-formed thin-walled steel (51, 52) is fixedly coupled to the initial longitudinally cold-formed thin-walled steel keel (41, 42).
  • the concrete slab structural member is a concrete slab structural member or a roof slab structural member.
  • the concrete wall panel structural member is a cast-in-place concrete wall panel member, which further includes an outer concrete formwork (131) and an inner concrete formwork (132), and the outer concrete formwork (131) is located at the One side of the cold-formed thin-walled steel frame, the inner concrete formwork (132) is on the other side of the cold-formed thin-walled steel frame, and the outer concrete formwork and the inner concrete formwork are both cold a curved thin-walled steel frame fixedly connected, wherein the outer concrete formwork and the inner concrete formwork are spaced apart from the longitudinally cold-formed thin-walled steel (51, 52), the concrete being in the outer concrete formwork and The inner concrete formwork is covered between the cold-formed thin-walled steel frames.
  • a further preferred solution is: keel crimping (191, 192) on two longitudinally cold-formed thin-walled steels facing each other, the through direction of the keel punching and the main member of the concrete slab structural member
  • the concrete slab structural member further includes a pull bolt (111), an outer tension bolt (161), an inner tension bolt (162), an outer tension sleeve (171), and an inner tension sleeve (172).
  • a hole (191, 192) is inserted through the pull bolt (111), and the outer tension sleeve (171) is located at the outer concrete formwork (131) and two of the longitudinal cold-formed thin-walled steel keels Between the longitudinally cold-formed thin-walled steel (51) in the longitudinally cold-formed thin-walled steel, the inner tensioning sleeve (172) is in the inner concrete formwork (132) and each longitudinal cold bend
  • the longitudinally cold-formed thin-walled steel (52) of the two longitudinally cold-formed thin-walled steels included in the thin-walled steel keel; the two ends of the pull bolt (111) respectively pass through the keel a crimping punch is coupled to the outer tensioning sleeve and the inner tensioning sleeve, the outer tensioning bolt (161) passing through the outer concrete formwork (131) and the outer tensioning sleeve (171) Connecting to securely connect the outer concrete formwork to the longitudinally cold-formed thin-
  • transverse keel (141), between the inner tensioning bolt (162) and the inner concrete formwork (132), an inner vertical concrete formwork keel (122) and a medial concrete formwork laterally providing support for the inner concrete formwork
  • the keel (142), the outer tension bolt is sequentially connected through the outer gasket (151), the outer concrete formwork transverse keel, the outer concrete formwork vertical keel and the outer concrete formwork and the outer tension sleeve (171)
  • the inner tensioning bolt sequentially passes through the inner gasket (152), the inner concrete formwork transverse keel, the inner concrete formwork vertical keel, and the inner concrete formwork and the inner tensioning sleeve
  • the pull bolt ( 111 ) and the outer tension bolt ( 161 ) are The outer tension sleeves ( 171 ) are threadedly connected, and the pull bolts ( 111 ), the inner tension bolts ( 162 ) and the inner tension sleeves ( 172 ) are threadedly connected, each longitudinal cold bend
  • the two longitudinally cold-formed thin-walled steels included in the thin-walled steel keel are all C-shaped steel, and the outer concrete formwork and the inner concrete formwork are both modular concrete formwork.
  • the second basic scheme relates to a construction method for pouring concrete slabs, comprising: the following steps: a step of installing a thin-walled steel frame, wherein a main plane along the concrete slab A plurality of longitudinally cold-formed thin-walled steel keels (5, 9) are arranged in a laterally extending direction and arranged parallel to each other, and each vertical cold-formed thin-walled steel keel (5, 9) comprises two longitudinally cold-formed thin-walled steels (51, 52, 91, 92), the main plane of the longitudinal cold-formed thin-walled steel is disposed parallel to the main plane of the concrete slab, so that the two longitudinally cold-formed thin-walled steels are along The vertical planes of the concrete slabs are perpendicular to each other and spaced apart such that there is a space between the two longitudinally cold-formed thin-walled steels for the concrete to flow when pouring concrete (200);
  • the method includes: installing, on one side of the cold-formed thin-walled thin-walled
  • the step of installing the thin-walled steel frame includes the step of joining the two longitudinally cold-formed thin-walled steels, wherein, along the cold bend At the longitudinally spaced apart positions of the thin-walled steel, the two longitudinally cold-formed thin-walled steels are fixedly joined by connecting steel plates (61, 62).
  • each longitudinally cold-formed thin-walled steel keel (5, 9) comprises longitudinally cold-formed thin-walled steel (51, 52, 91, 92) along which a plurality of keel crimping holes (191, 192) through which the concrete flows when the concrete is poured, and the connecting steel plates (61, 62) are provided with concrete flowing through the concrete when pouring concrete Crimping punching (193, 194), in the step of pouring concrete, the concrete flows through the keel punching punch (191, 192) and the crimping punch on the connecting steel plate.
  • the concrete slab is a concrete wall panel
  • the longitudinal cold-formed thin-walled steel is a vertically cold-formed thin-walled steel
  • the step of installing the template further includes: installing the inner concrete formwork (132) on the other side of the cold-formed thin-walled steel frame, and fixing it to the thin-walled steel frame; in the step of pouring the concrete, Concrete is poured between the outer concrete formwork and the inner concrete formwork.
  • the step of installing the thin-walled steel frame comprises: using a transversely connected cold-formed thin-walled steel keel comprising transversely cold-formed thin-walled steel (81, 82)
  • the longitudinally cold-formed thin-walled steel keels arranged in parallel are joined to connect the obliquely-curved cold-formed thin-walled steel keel including the obliquely cold-formed thin-walled steel (31, 32) with the vertically cold-formed thin-walled steel keel.
  • the step of installing the thin-walled steel frame comprises: preparing a starting platform (113) at the bottom, at the starting platform
  • the upper sleeve comprises an initial sleeve (112) and an initial sleeve (4) for initiating a vertical cold-formed thin-walled steel keel (41, 42), the longitudinally cold-formed thin-walled steel (51, 52) and the The initial vertical cold-formed thin-walled steel keel (41, 42) Fixedly connected.
  • the outer concrete formwork and the vertical cold-formed thin wall at the outer side are installed when the outer concrete formwork is installed There is a space between the steel profiles (51), and when the inner concrete formwork is installed, a gap is left between the inner concrete formwork and the vertically cold-formed thin-walled steel (52) on the inner side, in the pouring
  • the concrete is filled with a space between the outer concrete formwork and the inner concrete formwork and the cold-formed thin-walled steel frame is covered.
  • the concrete slab is a concrete wall slab
  • the longitudinal cold-formed thin-walled steel is a vertically cold-formed thin-walled steel
  • the step of installing the template further includes: installing the inner concrete formwork (132) on the other side of the cold-formed thin-walled steel frame, and fixing it to the thin-walled steel frame; in the step of pouring the concrete, Casting concrete between the outer concrete formwork and the inner concrete formwork; in the step of installing the thin-walled steel frame, the keel punching holes (191, 192) on the two longitudinally cold-formed thin-walled steels are opposite each other, The through direction of the keel punching is perpendicular to the main plane of the concrete wall, and the pull bolt (111) is penetrated in a part of the keel punching hole (191, 192) to make the pull bolt ( The two ends of the 111) are respectively connected to the outer tension sleeve and the inner tension
  • the pull bolt (111), the outer tension bolt (161) and the outer tension sleeve (171) are threaded. Connecting, the pull bolt (111), the inner tension bolt (162) and the inner tension sleeve (172) are threadedly connected, and each longitudinal cold-formed thin-walled steel keel comprises two longitudinal cold bends. Thin-walled steels are all C-shaped steels.
  • a further preferred embodiment is the tenth preferred embodiment based on the construction method of pouring the concrete slab according to the eighth preferred embodiment, wherein: the outer concrete formwork and the inner concrete formwork are fixedly connected to the thin-walled steel frame, and the outer side is tightened.
  • FIG. 1 is a cross-sectional, cross-sectional structural view of a preferred embodiment of a concrete slab structural member of the present invention
  • Figure 2 is a perspective exploded perspective view of the preferred embodiment of the concrete slab structural member of the present invention.
  • Figure 3 is a perspective view showing the structure of the preferred embodiment of the concrete slab structural member of the present invention, which is schematically shown from the inside of the structural member;
  • Fig. 4 is a perspective view showing the structure of the preferred embodiment of the concrete slab structural member of the present invention, in which the structure is schematically shown from the outside of the structural member.
  • DETAILED DESCRIPTION OF THE INVENTION In the following description and the specification, the same components have the same names and the same reference numerals are used. Corresponding parts have corresponding names, with corresponding reference numerals.
  • Preferred embodiment of concrete slab structural member of the present invention See Figure 1-4 below. A concrete slab structural member in accordance with a preferred embodiment of the present invention is schematically illustrated in these figures.
  • the wall panel structural members of the preferred embodiment of the concrete slab structural member are illustrated in detail in these figures, and the slab or roof panel structural members are also suitably illustrated.
  • the structure of the floor or roof structural member is very similar to the wall panel, except that the concrete form on the side of the cold-formed thin-walled steel frame is omitted than the wall panel, that is, There is no need for a concrete formwork on the upper side of the cold-formed thin-walled steel frame, but a concrete formwork on the other side of the cold-formed thin-walled steel frame, ie the concrete form on the underside (or outside) of the cold-formed thin-walled steel frame , Vertical support of concrete formwork can be provided as needed.
  • the concrete wall panel structural members shown in Figure 1-4 are in a state of construction site.
  • the wall panel structural member includes a cold-formed thin-walled steel frame as a reinforcement, a concrete formwork, and a concrete formwork keel.
  • the concrete encased in the cold-formed thin-walled steel frame (or the state when uncast concrete is not shown) is not shown.
  • the cold-formed thin-walled steel frame includes a plurality of major planes along the structural members of the concrete wallboard (i.e., through the concrete wall panels in Figure 1 and perpendicular to the paper surface and onto the starting platform 113 of Figure 1).
  • the laterally extending plane of the surface ie, the direction perpendicular to the plane of the paper in Fig.
  • Each longitudinally cold-formed thin-walled steel keel comprises two vertical cold-formed thin-walled steels 51, 52.
  • the main plane of the vertically cold-formed thin-walled steel 51 or 52 i.e., the center of the cold-formed thin-walled steel 51 or 52 in Fig. 1 is perpendicular to the plane of the paper and perpendicular to the upper surface of the starting platform 113 in Fig. 1 The plane) is parallel to the main plane of the concrete wall panel structural member.
  • the two longitudinally cold-formed thin-walled steels 51, 52 are in a direction perpendicular to the main plane of the concrete wall structural member (i.e., the level parallel to the paper surface in Fig. 1)
  • the directions of the inclined axes shown in Fig. 2 in Fig. 2 are opposite to each other and spaced apart, so that between the two longitudinally cold-formed thin-walled steels, the concrete is allowed to flow between the concretes when pouring concrete.
  • Space 200 after the concrete wall panel is cast and formed, the space left between the two longitudinally cold-formed thin-walled steels is filled with concrete.
  • each of the vertical cold-formed thin-walled steels 51, 52 has a plurality of keel-hole punching holes 191, 192 through which the concrete flows while pouring concrete along the longitudinal direction thereof, and the connecting steel plates 61, 62 There are crimping holes 193, 194 for the concrete to flow through while pouring the concrete.
  • each of the transversely connected cold-formed thin-walled steel keels includes laterally cold-formed thin-walled steel 81, 82.
  • Each of the obliquely supported cold-formed thin-walled steel keels includes obliquely cold-formed thin-walled steels 31, 32.
  • the concrete wall panel member includes a starting platform 113 that is at the bottom as a base.
  • An initial sleeve 4 is fixed to the starting platform 113, and the starting plate 112 of the starting sleeve 4 is fixed to the starting platform 113 by means of expansion bolts 91.
  • Starting sleeve 4 The initial vertical cold-formed thin-walled steel keels 41, 42 are protruded upward.
  • Vertically cold-formed thin-walled steels 51, 52 are fixedly joined at the initial vertical cold-formed thin-walled steel keels 41, 42 (for example, by bolts or welding).
  • the concrete wall panel structural members also include an outer concrete formwork 131 and an inner concrete formwork 132 at the construction site.
  • the outer concrete formwork 131 is on one side of the cold-formed thin-walled steel frame, and the inner concrete formwork 132 is on the other side of the cold-formed thin-walled steel frame.
  • the concrete formwork will be removed, and the final hardened formwork will not have a concrete formwork; if a permanent concrete formwork is used, the permanent concrete formwork will become Part of the final formed wall panel.
  • the keel crimping holes 191, 192 on the two vertical cold-formed thin-walled steels face each other, the through direction of the keel crimping and the structural members of the concrete slab
  • the main plane is vertical.
  • the ferrule crimping holes 191, 192 extend through the pull pin 111 in a portion (depending on the number of pull points).
  • the outer tensioning sleeve 171 is between the outer concrete formwork 131 and the vertically cold-formed thin-walled steel 51 on the outside.
  • the inner tensioning sleeve 172 is between the inner concrete formwork 132 and the vertically cold-formed thin-walled steel 52 on the inside.
  • Two tensioning sleeves 171 and 172 are threaded onto both ends of the pull pin 111.
  • An outer vertical concrete formwork keel 121 and an outer concrete formwork transverse keel 141 supporting the outer concrete formwork are provided between the outer tension pin 161 and the outer concrete formwork 131, between the inner tension pin 162 and the inner concrete formwork 132
  • An inner vertical concrete formwork keel 122 and an inner concrete formwork transverse keel 142 are provided to support the inner concrete formwork.
  • the outer tension bolt 161 sequentially passes through the outer gasket 151, the outer concrete formwork transverse keel 141, the outer concrete formwork vertical keel 121 and the outer concrete formwork 131 and the outer side tensioning
  • the sleeve 171 is threaded to securely attach the outer concrete formwork to the vertically cold-formed thin-walled steel keel and to provide sufficient support to stabilize the structure.
  • the inner tensioning bolt 162 sequentially threaded through the inner shim 152, the inner concrete formwork transverse keel 142, the inner concrete formwork vertical keel 122, and the inner concrete formwork 132 to the inner tensioning sleeve 172 to join the inner concrete formwork and the vertical direction.
  • each of the two vertically cold-formed thin-walled steel ribs included in each vertical cold-formed thin-walled steel keel is a grooved C-shaped steel, and the grooves of the two steel sections are opposed to each other.
  • both the outer concrete formwork and the inner concrete formwork can be modularized concrete formwork.
  • the construction method of the cast concrete wall of the preferred embodiment of the present invention comprises the following steps: a step of installing a thin-walled steel frame, wherein a plurality of vertical cold-formed thin-walled steel keels 5 are arranged along the lateral extension direction of the main plane of the concrete wall and arranged in parallel with each other, each vertical cold bend
  • the thin-walled steel keel 5 comprises two vertical cold-formed thin-walled steels 51, 52, the main plane of which is arranged parallel to the main plane of the concrete wall, so that the two The vertically cold-formed thin-walled steels are opposed to each other and spaced apart in a direction perpendicular to the main plane of the concrete wall, so that the two vertical cold-formed thin-walled steels are left at the time of pouring concrete The space through which the concrete flows 200;
  • the method comprises: preparing a starting platform 113 at the bottom, and fixing the starting plate 112 and the initial vertical cold-formed thin-walled steel keels 41, 42 on the starting platform
  • An initial sleeve 4 the first cold-formed thin-walled steel 51, 52 is fixedly connected with the initial vertical cold-formed thin-walled steel keels 41, 42; the two vertical cold-formed thin walls a step of joining the steel profiles, wherein the keel crimping holes 191, 192 on the two vertical cold-formed thin-walled steels are opposite to each other, so that the through direction of the keel punching and the concrete wall
  • the main plane is vertical, and the two vertical cold-formed thin-walled steels are fixedly connected by connecting steel plates 61, 62 at positions vertically spaced along the cold-formed thin-walled steel; Wall steel 81, 82
  • the transversely-connected cold-formed thin-walled steel keel connects a plurality of vertical
  • the inner vertical concrete formwork keel 122 and the inner concrete formwork transverse keel 142 provide support for the inner concrete formwork.
  • the outer tension bolt 161 is connected to the outer tension sleeve 171 through the outer concrete formwork 131, the outer tension bolt is sequentially passed through the outer gasket 151, the outer concrete formwork transverse keel, the outer concrete formwork vertical keel and the outer side.
  • the concrete formwork is threadedly coupled to the outer tensioning sleeve 171 to securely attach the outer concrete formwork to the vertical cold-formed thin-walled steel keel.
  • the inner tensioning bolt 162 When the inner tensioning bolt 162 is connected to the inner tensioning sleeve 171 through the inner concrete formwork 132, the inner tensioning bolt is sequentially passed through the inner side gasket 152, and the inner side is coagulated.
  • the soil template transverse keel, the inner concrete formwork vertical keel and the inner concrete formwork are threadedly coupled to the inner tensioning sleeve 172 to securely connect the inner concrete formwork to the vertically cold-formed thin-walled steel keel.
  • the outer tensioning sleeve, the inner tensioning sleeve, the pull bolt, the outer tensioning jaw and the inner tensioning bolt are used, and the outer concrete formwork is A cavity having the same width along the extending direction of the wall is formed between the inner concrete formwork, and the outer concrete formwork and the inner concrete formwork are formed using a modular concrete formwork.
  • the concrete flows from the space 200 and flows through the keel punching holes 191, 192 and the bead punching holes on the connecting steel plate, the flow resistance is small, the flow is smooth, and the pouring efficiency is high.
  • the longitudinal connection of the longitudinally cold-formed thin-walled steel keels can be connected by the longitudinal steel connection keel 7
  • the thin-walled steels 71, 72 are fixedly joined so that the length (or height) of the profiled steel keels in the longitudinal (or vertical) direction can reach the length (or height) required for the work. Further, as shown in Figs.
  • the thin-walled steel frame structure and the construction method of the panel proposed by the present invention can be equally applied to the casting of the floor.
  • the concrete stencil is not placed on the upper side of the frame when the slab is poured, but the ordinary detachable concrete stencil is fixedly attached to the underside (outer side) of the thin-walled steel frame, and then concrete is poured from above.
  • the thin-walled steel frame structure of the present invention is applied to a building roof slab, the effect of reducing or eliminating the cold bridge can also be Get reflected.
  • the construction of the initial platform is carried out or the foundation is regarded as the starting platform.
  • the size is required to be accurate, and the entire circumference must be kept at the same level.
  • the starting sleeve is continuously fixed according to the design requirements;
  • the modular inner concrete formwork and the outer concrete formwork form a reliable equal width cavity by pulling the bolt, tightening the sleeve and tightening the bolt; 7. Repeat steps 5 and 6 to the floor.
  • the modular inner concrete formwork intersects the bottom concrete formwork of the floor (optional detachable modular concrete formwork) and is reliably supported.
  • Modular outer concrete formwork Continue to install one or two pieces upwards and connect with the raised vertical keel;
  • the thin-walled steel frame is intersected with the concrete formwork (including the outer concrete formwork and the inner concrete formwork).
  • the vertical keel is 90 cm out of the floor and used as a temporary guardrail.
  • the lower wall is completed. And the concrete pouring on the floor, pay attention to the pouring, about 0.5 m high at a time;

Description

混凝土板结构构件以及其浇注施工方法 技术领域
本发明属于建筑结构构件及施工方法领域, 特别是, 涉及混 凝土板结构构件和浇注混凝土板的施工方法。 背景技术
现有技术中存在用冷弯薄壁型钢做骨架的混凝土板结构构 件。 根据现有技术, 冷弯薄壁型钢框架包括多个沿着横向间隔开 并平行排列的多个竖向冷弯薄壁型钢。 冷弯薄壁型钢的主平面与 所述混凝土板结构构件的主平面垂直布置。 这样, 相邻的每两个 冷弯薄壁型钢之间形成一个隔腔, 这造成了一些问题。 例如: 1 ) 在外侧混凝土模板和内侧混凝土模板之间浇注混凝土时, 混凝土 的流动受到冷弯薄壁型钢的阻碍, 混凝土浇注效率低, 浇注后的 混凝土的密实性和均质性受影响; 2 )冷弯薄壁型钢的主平面垂直 于混凝土板结构构件的主平面, 使得冷弯薄壁型钢沿着从室内到 室外的方向伸展从而在室内外之间形成冷桥, 影响墙板的隔热效 果。 发明内容
本发明的一个目的在于提供一种新型的冷弯薄壁型钢与混凝 土结合的混凝土板结构构件, 其可以避免或尽可能地减弱现有技 术中冷弯薄壁型钢混凝土板结构构件由于冷弯薄壁型钢的主平面 与所述混凝土板结构构件的主平面垂直布置而存在的浇注混凝土 时其流动受到阻碍的问题。 本发明另一方面的目的在于提供一种 解决浇注成形后的混凝土板中垂直布置的冷弯薄壁型钢所产生的 冷桥问题。 本发明的技术方案如下: 第一基本方案
一种混凝土板结构构件, 包括: 冷弯薄壁型钢框架; 混凝土, 其包裹着所述冷弯薄壁型钢框架; 所述冷弯薄壁型钢框架包括多 个沿着所述混凝土板结构构件的主平面的横向伸展方向间隔开的 互相平行排列的纵向冷弯薄壁型钢龙骨(5, 9 ); 其中, 每个纵向 冷弯薄壁型钢龙骨包括两根纵向冷弯薄壁型钢( 51 , 52, 91 , 92 ), 所述纵向冷弯薄壁型钢的主平面与所述混凝土板结构构件的主平 面平行, 所述两根纵向冷弯薄壁型钢沿着与所述混凝土板结构构 件的主平面垂直的方向彼此对置并间隔开, 以致所述两根纵向冷 弯薄壁型钢之间留有在浇注混凝土时供所述混凝土流过的空间 ( 200 ), 所述两根纵向冷弯薄壁型钢之间留有的空间里充满混凝 土。 本发明的有益效果如下: 在本发明的混凝土板结构构件中, 每个纵向冷弯薄壁型钢龙 骨包括两根纵向冷弯薄壁型钢,所述纵向冷弯薄壁型钢的主平面、 所述混凝土板结构构件的主平面互相平行, 所述两根纵向冷弯薄 壁型钢沿着与所述混凝土板结构构件的主平面垂直的方向彼此对 置并间隔开, 以致所述两根纵向冷弯薄壁型钢之间留有空间, 从 而在浇注混凝土时所述混凝土能容易地从所述两根纵向冷弯薄壁 型钢之间留有的空间流过。 这避免了现有技术中的冷弯薄壁型钢 的主平面与所述混凝土板结构构件的主平面垂直而造成的问题。 1 )对于背景技术提到的第 1 )个问题, 由于本发明的冷弯薄壁型 钢在平行于混凝土结构构件的主平面的方向伸展, 不会对浇注的 混凝土沿着混凝土板的横向伸展方向、 沿着混凝土模板的流动造 成像现有技术那么大的阻碍, 使得混凝土可以顺着薄壁型钢的主 平面的方向顺畅地流动。 这可以提高浇注效率, 并提高浇注到内 侧和外侧混凝土模板之间的空间内之后混凝土的密实性和均质 性; 对于上面提到的背景技术中的第 2 ) 个问题, 本发明的冷弯 薄壁型钢在平行于混凝土结构构件的主平面的方向 (与从室内到 室外的方向垂直)伸展, 避免了在室内外之间形成冷桥。 本发明 的另一方面的问题在于解决现有技术中的混凝土板 -例如墙板或 屋面板-浇注成形后的混凝土板中由于冷弯薄壁型钢与所述混凝 土板的主平面垂直所产生的冷桥问题。 同时, 相对于现有技术中的冷弯薄壁型钢混凝土结构, 本发 明的冷弯薄壁型钢混凝土结构还有另外的优点。 作为混凝土板其 受力破坏主要从板的两个外侧主表面附近发生, 而在沿着与板的 主平面垂直方向上的板的中部处, 实际上是可以不配筋。 而在现 有技术的结构中, 冷弯薄壁型钢垂直于混凝土板的主平面布置, 这样在板的所述中部处的那部分冷弯薄壁型钢的承受荷载的作用 得不到充分的体现, 造成了钢材的浪费。 而本发明中, 每个纵向 冷弯薄壁型钢龙骨包括两根纵向冷弯薄壁型钢, 所述纵向冷弯薄 壁型钢的主平面、 所述混凝土板结构构件的主平面互相平行, 所 述两根纵向冷弯薄壁型钢沿着与所述混凝土板结构构件的主平面 垂直的方向彼此对置并间隔开, 以致所述两根纵向冷弯薄壁型钢 之间留有空间。 这样在混凝土板的所述中部处实际上没有配筋, 钢材大部分集中在板最需要配筋的两个表面附近, 使得钢材的利 用率得到了显著的提高。 相对于现有技术中冷弯薄壁型钢结构具 有节约钢材的效果。 另外, 在本发明中, 每个纵向冷弯薄壁型钢龙骨所包括的两 根纵向冷弯薄壁型钢的主平面与所述混凝土板结构构件的主平面 互相平行, 所述两根纵向冷弯薄壁型钢沿着与所述混凝土板结构 构件的主平面垂直的方向彼此对置并间隔开, 这形成了更稳定的 自支撑, 可以减少或者取消混凝土模板的附加支撑。 另外, 当将模数化的混凝土模板与冷弯薄壁型钢框架结构产 品结合时, 将形成一个完整的建筑工业化体系。 这个体系既涉及 建筑设计、 建筑结构, 又涉及建筑施工, 应用范围广泛。 该体系 优势很多, 具体举例说明如下:
1.当将模数化的混凝土模板与本发明的冷弯薄壁型钢框架结 构结合起来, 以冷弯薄壁型钢代替螺紋钢时, 在总用钢量不增加 的情况下, 大大提高临时结构的稳定性、 尺寸的精确性, 使施工 过程更方便、 快捷、 可靠, 还有效减少临时性支撑的使用。
2. 由于建造方式的转变, 现场施工的作业量(取消了现有的 钢筋绑扎工作, 简化了混凝土模板支撑工作或取消混凝土模板支 撑)大大减少, 从而节省劳动力, 降低劳动强度, 缩短施工工期。 据推算采用本发明的薄壁型钢框架混凝土结构与模数化混凝土模 板的组合形成的新式的建筑工业化的装配技术, 可节省劳动力 35% -50% , 缩短工期 40%以上。
3.当在本发明的薄壁型钢框架混凝土结构中采用永久混凝土 模板时, 节约工时, 缩短工期的效果得到进一步加强。 4. 本发明的薄壁型钢框架混凝土结构的板成形后,可以形成 型钢劲性混凝土结构。 型钢劲性混凝土结构是目前公认的抗震、 耐久、 防火性能最优异的结构形式之一。 其抗震性能远好于砌体 结构, 耐火性能和耐久性能远好于钢结构, 抗震性能和结构延性 也好于现有技术中的钢筋混凝土结构。 下面对本发明的第一基本方案的优选方案以及其他的基本方 案分别进行说明: 第一基本方案的优选方案 优选地, 所述两根纵向冷弯薄壁型钢之间通过沿着所述冷弯 薄壁型钢的纵向间隔开的连接钢板(61 , 62 ) 固定连接。 进一步优选地, 每个纵向冷弯薄壁型钢龙骨(5 )包括的纵向 冷弯薄壁型钢 (51 , 52 )上带有沿着其长度方向分布的贯穿的多 个在浇注混凝土时供混凝土流过的龙骨卷边冲孔( 191, 192 ), 所 述连接钢板(61 , 62 )上带有在浇注混凝土时供混凝土流过的卷 边冲孔( 193, 194 )。 优选地, 所述冷弯薄壁型钢框架还包括: 横向连接冷弯薄壁 型钢龙骨, 其包括横向冷弯薄壁型钢(81 , 82 ); 斜向支撑冷弯薄 壁型钢龙骨, 其包括斜向冷弯薄壁型钢(31, 32 ); 多个平行排列 的纵向冷弯薄壁型钢龙骨通过所述横向连接冷弯薄壁型钢龙骨而 连接, 所述斜向支撑冷弯薄壁型钢龙骨与所述纵向冷弯薄壁型钢 龙骨连接, 所述纵向冷弯薄壁型钢龙骨、 所述横向连接冷弯薄壁 型钢龙骨和所述斜向支撑冷弯薄壁型钢龙骨连接以形成一个稳定 的整体刚性结构。 优选地, 所述混凝土板结构构件为混凝土墙板结构构件, 所 述纵向冷弯薄壁型钢龙骨为沿着竖向伸展放置的竖向冷弯薄壁型 钢龙骨。 更优选地, 处在底部的起始平台 ( 113), 所述起始平台 上固定有起始套管(4), 所述起始套管(4)具有向上突出的起始 竖向冷弯薄壁型钢龙骨 (41, 42), 所述纵向冷弯薄壁型钢 (51, 52)与所述起始纵向冷弯薄壁型钢龙骨(41, 42) 固定连接起来。 或者, 优选地, 所述混凝土板结构构件为混凝土楼板结构构 件或屋面板结构构件。 再进一步的优选方案是: 所述混凝土墙板结构构件为现浇混 凝土墙板构件, 其还包括外侧混凝土模板( 131 )和内侧混凝土模 板( 132), 所述外侧混凝土模板 ( 131 )处在所述冷弯薄壁型钢框 架的一侧, 所述内侧混凝土模板( 132)处在所述冷弯薄壁型钢框 架的另一侧, 所述外侧混凝土模板和所述内侧混凝土模板都与所 述冷弯薄壁型钢框架固定连接, 所述外侧混凝土模板和所述内侧 混凝土模板与所述纵向冷弯薄壁型钢(51, 52 )之间都留有间隔, 所述混凝土处在所述外侧混凝土模板与所述内侧混凝土模板之间 并将所述冷弯薄壁型钢框架覆盖起来。 进一步优选的方案是: 在两根纵向冷弯薄壁型钢上的龙骨卷 边冲孔( 191, 192)彼此正对, 所述龙骨卷边冲孔的贯穿方向与 所述混凝土板结构构件的主平面垂直; 所述混凝土板结构构件还 包括拉接栓( 111 )、 外侧拉紧栓( 161 )、 内侧拉紧栓( 162)、 外 侧拉紧套管( 171 )和内侧拉紧套管( 172), 在一部分龙骨卷边冲 孔( 191, 192) 中贯穿拉接栓( 111), 所述外侧拉紧套管 ( 171) 处在所述外侧混凝土模板( 131 )与每个纵向冷弯薄壁型钢龙骨所 包括的两根纵向冷弯薄壁型钢中的处在外侧的纵向冷弯薄壁型钢 (51)之间, 所述内侧拉紧套管( 172)处在所述内侧混凝土模板 ( 132)与每个纵向冷弯薄壁型钢龙骨所包括的两根纵向冷弯薄壁 型钢中的处在内侧的纵向冷弯薄壁型钢 (52)之间; 所述拉接栓 ( 111 )的两端分别穿过所述龙骨卷边冲孔与所述外侧拉紧套管和 内侧拉紧套管连接, 所述外侧拉紧栓( 161 )穿过所述外侧混凝土 模板 ( 131 )与所述外侧拉紧套管 ( 171 )连接, 以将所述外侧混 凝土模板与所述纵向冷弯薄壁型钢龙骨固定连接, 所述内侧拉紧 栓( 162) 穿过所述内侧混凝土模板 ( 132) 与所述内侧拉紧套管
( 171)连接, 以将所述内侧混凝土模板与所述纵向冷弯薄壁型钢 龙骨固定连接。 再进一步优选的方案是: 在所述外侧拉紧栓( 161 )与所述外 侧混凝土模板( 131 )之间设有对外侧混凝土模板提供支撑的外侧 竖向混凝土模板龙骨 ( 121 )和外侧混凝土模板横向龙骨 ( 141 ), 在所述内侧拉紧栓( 162) 与所述内侧混凝土模板 ( 132)之间设 有对内侧混凝土模板提供支撑的内侧竖向混凝土模板龙骨 ( 122) 和内侧混凝土模板横向龙骨 ( 142), 所述外侧拉紧栓依次穿过外 侧垫片 ( 151)、 外侧混凝土模板横向龙骨、 外侧混凝土模板竖向 龙骨和所述外侧混凝土模板与外侧拉紧套管( 171 )连接, 所述内 侧拉紧栓依次穿过内侧垫片 ( 152)、 内侧混凝土模板横向龙骨、 内侧混凝土模板竖向龙骨和所述内侧混凝土模板与内侧拉紧套管
( 172)连接。 更优选的方案是: 所述拉接栓 ( 111 )、 外侧拉紧栓( 161 )与 外侧拉紧套管( 171 )之间为螺纹连接, 所述拉接栓( 111 )、 内侧 拉紧栓( 162 ) 与内侧拉紧套管 ( 172 )之间为螺纹连接, 每个纵 向冷弯薄壁型钢龙骨所包括的两根纵向冷弯薄壁型钢都为 C形型 钢, 所述外侧混凝土模板和所述内侧混凝土模板都为模数化混凝 土模板。 第二基本方案及其优选方案 第二基本方案涉及一种浇注混凝土板的施工方法, 其特征在 于: 包括如下步骤: 安装薄壁型钢框架的步骤, 其中, 沿着所述 混凝土板的主平面的横向伸展方向间隔开并互相平行排列地布置 多个纵向冷弯薄壁型钢龙骨(5, 9 ), 每个竖向冷弯薄壁型钢龙骨 ( 5, 9 ) 包括两根纵向冷弯薄壁型钢( 51 , 52, 91 , 92 ), 将所述 纵向冷弯薄壁型钢的主平面设置成与所述混凝土板的主平面平 行, 使所述两根纵向冷弯薄壁型钢沿着与所述混凝土板的主平面 垂直的方向彼此对置并间隔开, 以致所述两根纵向冷弯薄壁型钢 之间留有在浇注混凝土时供所述混凝土流过的空间 ( 200 ); 安装 模板的步骤, 其中, 包括: 在所述冷弯薄壁型钢框架的一侧, 安 装外侧混凝土模板( 131, 202 )将其与薄壁型钢框架固定连接; 浇注混凝土的步骤, 其中, 使所述混凝土顺畅流过所述空间 ( 200 )。。 根据以第二基本方案为基础的第一优选的方案, 在安装薄壁 型钢框架的步骤中包括将所述两根纵向冷弯薄壁型钢连接起来的 步骤, 其中, 在沿着所述冷弯薄壁型钢的纵向间隔开的位置处, 用连接钢板(61, 62 )将所述两根纵向冷弯薄壁型钢固定连接。 在上述优选方案的基础上的第二优选方案中, 每个纵向冷弯 薄壁型钢龙骨 (5, 9) 包括的纵向冷弯薄壁型钢 (51, 52, 91, 92 )上带有沿着其长度方向分布的贯穿的多个在浇注混凝土时供 混凝土流过的龙骨卷边冲孔( 191, 192), 所述连接钢板(61, 62) 上带有在浇注混凝土时供混凝土流过的卷边冲孔( 193, 194), 在 浇注混凝土的步骤中,所述混凝土从所述龙骨卷边冲孔( 191, 192) 和所述连接钢板上的卷边冲孔流过。 在以第二基本方案为基础的第三优选方案的浇注混凝土板的 施工方法中, 所述混凝土板为混凝土墙板, 所述纵向冷弯薄壁型 钢为竖向冷弯薄壁型钢, 所述安装模板的步骤还包括: 在所述冷 弯薄壁型钢框架的另一侧, 安装内侧混凝土模板( 132), 将其与 薄壁型钢框架固定连接; 在所述浇注混凝土的步驟中, 向所述外 侧混凝土模板与所述内侧混凝土模板之间浇注混凝土。 在以第二基本方案为基础的第四优选方案中, 在安装薄壁型 钢框架的步骤中包括: 用包括横向冷弯薄壁型钢 (81, 82) 的横 向连接冷弯薄壁型钢龙骨将多个平行排列的纵向冷弯薄壁型钢龙 骨连接起来, 把包括斜向冷弯薄壁型钢 (31, 32) 的斜向支撑冷 弯薄壁型钢龙骨与竖向冷弯薄壁型钢龙骨连接起来, 以形成一个 稳定的整体刚性结构。 在以第三优选方案的浇注混凝土板的施工方法为基础的第五 优选方案中, 在安装薄壁型钢框架的步骤中包括: 准备在底部的 起始平台 ( 113), 在所述起始平台上固定包括起始板( 112)和起 始竖向冷弯薄壁型钢龙骨 (41, 42) 的起始套管 (4), 将所述纵 向冷弯薄壁型钢(51, 52)与所述起始竖向冷弯薄壁型钢龙骨(41, 42 ) 固定连接起来。 在以第三优选方案的浇注混凝土板的施工方法为基础的第六 优选方案中, 在安装所述外侧混凝土模板时, 使所述外侧混凝土 模板与所述处在外侧的竖向冷弯薄壁型钢 (51 )之间留有间隔, 在安装所述内侧混凝土模板时, 使所述内侧混凝土模板与所述处 在内侧的竖向冷弯薄壁型钢 (52 )之间留有间隔, 在浇注混凝土 时, 使所述混凝土充满在所述外侧混凝土模板与所述内侧混凝土 模板之间的空间并将所述冷弯薄壁型钢框架覆盖起来。 在以第二优选方案的浇注混凝土板的施工方法为基础的第七 优选方案中, 所述混凝土板为混凝土墙板, 所述纵向冷弯薄壁型 钢为竖向冷弯薄壁型钢, 所述安装模板的步骤还包括: 在所述冷 弯薄壁型钢框架的另一侧, 安装内侧混凝土模板( 132 ), 将其与 薄壁型钢框架固定连接; 在所述浇注混凝土的步驟中, 向所述外 侧混凝土模板与所述内侧混凝土模板之间浇注混凝土; 在安装薄 壁型钢框架的步骤中, 使两根纵向冷弯薄壁型钢上的龙骨卷边冲 孔( 191, 192 )彼此正对, 使所述龙骨卷边冲孔的贯穿方向与所 述混凝土墙体的主平面垂直, 在一部分龙骨卷边冲孔( 191, 192 ) 中贯穿拉接栓 ( 111 ), 使所述拉接栓 ( 111 )的两端分别穿过所述 龙骨卷边冲孔与所述外侧拉紧套管和内侧拉紧套管连接; 在安装 外侧混凝土模板 ( 131 )的步骤中包括: 将所述外侧拉紧栓( 161 ) 穿过所述外侧混凝土模板 ( 131 ) 与所述外侧拉紧套管 ( 171 )连 接, 以将所述外侧混凝土模板与所述纵向冷弯薄壁型钢龙骨固定 连接, 在安装内侧混凝土模板( 131 )的步骤中包括: 将所述内侧 拉紧栓( 162 ) 穿过所述内侧混凝土模板 ( 132 ) 与所述内侧拉紧 套管( 171 )连接, 以将所述内侧混凝土模板与所述纵向冷弯薄壁 型钢龙骨固定连接。 根据在上面的优选方案的基础上的第八优选 方案, 还包括在所述外侧拉紧栓( 161) 与所述外侧混凝土模板 ( 131 )之间设置对外侧混凝土模板提供支撑的外侧竖向混凝土模 板龙骨( 121 )和外侧混凝土模板横向龙骨( 141 ), 在所述内侧拉 紧栓( 162) 与所述内侧混凝土模板 ( 132)之间设置对内侧混凝 土模板提供支撑的内侧竖向混凝土模板龙骨( 122)和内侧混凝土 模板横向龙骨( 142); 在将所述外侧拉紧栓( 161 )穿过所述外侧 混凝土模板 ( 131 )与所述外侧拉紧套管 ( 171 )连接时, 将所述 外侧拉紧栓依次穿过外侧垫片( 151)、外侧混凝土模板横向龙骨、 外侧混凝土模板竖向龙骨和所述外侧混凝土模板与外侧拉紧套管
( 171)连接, 在将所述内侧拉紧栓( 162) 穿过所述内侧混凝土 模板 ( 132) 与所述内侧拉紧套管 ( 171)连接时, 将所述内侧拉 紧栓依次穿过内侧垫片 ( 152)、 内侧混凝土模板横向龙骨、 内侧 混凝土模板竖向龙骨和所述内侧混凝土模板与内侧拉紧套管
( 172)连接。 作为在第七优选方案浇注混凝土板的施工方法的基础上的第 九优选方案, 所述拉接栓( 111 )、 外侧拉紧栓( 161 )与外侧拉紧 套管( 171 )之间为螺纹连接,所述拉接栓( 111 )、内侧拉紧栓( 162) 与内侧拉紧套管( 172)之间为螺纹连接, 每个纵向冷弯薄壁型钢 龙骨所包括的两根纵向冷弯薄壁型钢都为 C形型钢。 再有一个优选方案是在第八优选方案浇注混凝土板的施工方 法的基础上的第十优选方案, 其中: 安装外侧混凝土模板与内侧 混凝土模板将其与薄壁型钢框架固定连接时利用外侧拉紧套管、 内侧拉紧套管、 拉接栓、 外侧拉紧拴和内侧拉紧栓, 在外侧混凝 土模板与内侧混凝土模板之间形成沿着墙体的伸展方向等宽的空 腔, 采用模数化混凝土模板做所述外侧混凝土模板和所述内侧混 凝土模板。 下面是在第二基本方案以及以其为基础的第一、 第二和第四 优选方案的浇注混凝土板的施工方法的基础上的第十一优选方 案。 在该优选方案中, 所述混凝土板结构构件为混凝土楼板结构 构件或屋面板结构构件。 附图说明 图 1为本发明的混凝土板结构构件的一个优选实施方式的横 断面断面结构示意图;
图 2为本发明的混凝土板结构构件的该优选实施方式的立体 分解结构示意图;
图 3为本发明的混凝土板结构构件的该优选实施方式的立体 结构示意图, 该图从结构构件的内侧示意显示了结构;
图 4为本发明的混凝土板结构构件的该优选实施方式的立体 结构示意图, 该图中从结构构件的外侧示意显示了结构。 具体实施方式 在下面的说明书以及说明书中,相同的部件具有相同的名称, 采用了相同的附图标记。 相对应的部件具有相对应的名称, 采用 了相对应的附图标记。 本发明混凝土板结构构件的优选实施方式 下面参见图 1 - 4。这些图中示意性示出了根据本发明的一个 优选实施方式的一种混凝土板结构构件。 这些图中对该混凝土板 结构构件的优选实施方式的墙板结构构件进行了详细的图示, 同 时, 对楼板或屋面板结构构件也进行了适当的图示。 可以理解, 本领域技术人员在看过说明书之后可以理解, 楼板或屋面板结构 构件的结构与墙板非常相似, 只是比墙板省去了在冷弯薄壁型钢 框架一侧的混凝土模板, 即在冷弯薄壁型钢框架的上侧无需混凝 土模板, 而对于处在冷弯薄壁型钢框架的另一侧的混凝土模板, 即在冷弯薄壁型钢框架的下侧 (或外侧) 的混凝土模板, 根据需 要可以提供混凝土模板竖向支撑。 图 1 - 4所示的混凝土墙板结构构件为处在施工现场的状态。 该墙板结构构件包括作为配筋的冷弯薄壁型钢框架、 混凝土模板 和混凝土模板龙骨。 为了清楚显示结构起见, 图中没有显示包裹 着所述冷弯薄壁型钢框架的混凝土 (或理解成未浇注混凝土时的 状态)。 如图所示, 冷弯薄壁型钢框架包括多个沿着混凝土墙板结构 构件的主平面 (即图 1 中通过混凝土墙板并与纸面垂直并与图 1 中的起始平台 113的上表面垂直的平面) 的横向伸展方向 (即图 1 中与纸面垂直的方向) 间隔开的互相平行排列的纵向冷弯薄壁 型钢龙骨 5。 每个纵向冷弯薄壁型钢龙骨包括两根竖向冷弯薄壁 型钢 51 , 52。 竖向冷弯薄壁型钢 51或 52的主平面(即图 1中通 过所述冷弯薄壁型钢 51或 52的中心、 与纸面垂直并与图 1中的 起始平台 113的上表面垂直的平面) 与所述混凝土墙板结构构件 的主平面平行。 两根纵向冷弯薄壁型钢 51 , 52沿着与混凝土墙板 结构构件的主平面垂直的方向 (即图 1中与纸面平行的水平的方 向, 在图 2中为图 2中所示的倾斜的轴线的方向)彼此对置并间 隔开, 以致两根纵向冷弯薄壁型钢之间留有在浇注混凝土时供所 述混凝土流过的空间 200, 在混凝土墙板浇注成形之后, 两根纵 向冷弯薄壁型钢之间留有的空间里充满混凝土。
在沿着冷弯薄壁型钢的纵向间隔开的位置处, 图 2中为上下 两个位置处, 两根纵向冷弯薄壁型钢之间例如通过焊接或螺栓连 接而连接有连接钢板 61, 62, 以将两根竖向冷弯薄壁型钢固定连 接起来。 每竖向冷弯薄壁型钢 51 , 52上带有沿着其长度方向分布的贯 穿的多个在浇注混凝土时供混凝土流过的龙骨卷边冲孔 191 , 192, 所述连接钢板 61 , 62上带有在浇注混凝土时供混凝土流过 的卷边冲孔 193 , 194。卷边冲孔的作用,一个是便于混凝土流过, 提高混凝土的浇注效率, 另一个是可以提高型钢部件的刚度、 强 度和稳定性。 如图 1、 3和 4所示, 多个竖向冷弯薄壁型钢龙骨与多个沿着 竖向冷弯薄壁型钢龙骨的纵向分布的横向连接冷弯薄壁型钢龙骨
(例如通过自攻螺钉 118或螺丝)连接起来, 并与斜向支撑冷弯 薄壁型钢龙骨 (例如通过自攻螺钉 118或螺丝)连接, 从而形成 一个稳定的整体刚性结构整体。 每个横向连接冷弯薄壁型钢龙骨 包括横向冷弯薄壁型钢 81 , 82。 每个斜向支撑冷弯薄壁型钢龙骨 包括斜向冷弯薄壁型钢 31 , 32。 如图 1所示, 该混凝土墙板构件包括处在底部作为基座的起 始平台 113。起始平台 113上固定有起始套管 4, 起始套管 4的起 始板 112借助于膨胀螺栓 91固定在起始平台 113上。 起始套管 4 具有向上突出的起始竖向冷弯薄壁型钢龙骨 41 , 42。 竖向冷弯薄 壁型钢 51 , 52套在起始竖向冷弯薄壁型钢龙骨 41 , 42并(例如 用螺栓或焊接) 固定连接起来。 如图 1、 3和 4所示, 混凝土墙板结构构件在施工现场时还包 括外侧混凝土模板 131和内侧混凝土模板 132。 外侧混凝土模板 131处在所述冷弯薄壁型钢框架的一侧, 内侧混凝土模板 132处 在所述冷弯薄壁型钢框架的另一侧。 当然, 可以理解, 在浇注混 凝土而成形之后, 如果使用的是普通可拆卸混凝土模板, 将要把 混凝土模板拆除, 最终硬化成形的墙板不带混凝土模板; 如果使 用永久混凝土模板, 永久混凝土模板将成为最终成形的墙板的一 部分。 如图 1和 2所清楚显示的, 在两根竖向冷弯薄壁型钢上的龙 骨卷边冲孔 191 , 192彼此正对,龙骨卷边冲孔的贯穿方向与所述 混凝土板结构构件的主平面垂直。 在一部分(根据拉接点数量的 需要而定)龙骨卷边冲孔 191 , 192中贯穿拉接栓 111。 外侧拉紧 套管 171处在外侧混凝土模板 131与处在外侧的竖向冷弯薄壁型 钢 51之间。内侧拉紧套管 172处在内侧混凝土模板 132与处在内 侧的竖向冷弯薄壁型钢 52之间。两个拉紧套管 171和 172螺纹连 接在拉接栓 111的两端上。 在外侧拉紧栓 161与外侧混凝土模板 131 之间设有对外侧混凝土模板提供支撑的外侧竖向混凝土模板 龙骨 121和外侧混凝土模板横向龙骨 141 , 在内侧拉紧栓 162与 内侧混凝土模板 132之间设有对内侧混凝土模板提供支撑的内侧 竖向混凝土模板龙骨 122和内侧混凝土模板横向龙骨 142。 外侧 拉紧栓 161依次穿过外侧垫片 151、外侧混凝土模板横向龙骨 141、 外侧混凝土模板竖向龙骨 121和外侧混凝土模板 131与外侧拉紧 套管 171螺纹连接, 以将外侧混凝土模板与竖向冷弯薄壁型钢龙 骨固定连接, 并使其受到足够的支撑成为稳定的结构。 内侧拉紧 栓 162依次穿过内侧垫片 152、 内侧混凝土模板横向龙骨 142、 内 侧混凝土模板竖向龙骨 122和内侧混凝土模板 132与内侧拉紧套 管 172螺纹连接, 以将内侧混凝土模板与竖向冷弯薄壁型钢龙骨 固定连接, 并使其受到足够的支撑成为稳定的结构。 如图 1和 2所示, 每个竖向冷弯薄壁型钢龙骨所包括的两根 竖向冷弯薄壁型钢都为槽 C形型钢, 以两个型钢的槽互相相对的 方式对置。 可以理解, 外侧混凝土模板和内侧混凝土模板都可以 为模数化混凝土模板。 在外侧混凝土模板及内侧混凝土模板与竖向冷弯薄壁型钢 51 , 52之间都留有间隔, 浇注混凝土之后, 混凝土处在外侧混凝 土模板与内侧混凝土模板之间并将所述冷弯薄壁型钢框架覆盖起 来。 下面对利用本发明的各种施工方法的优选实施方式进行说 明。 以本发明的薄壁型钢框架代替钢筋的方案 -本发明混凝土板 结构构件的优选实施方式的施工方案 下面结合图 1 - 4来说明本发明优选实施方式的施工方法。 如图所示, 本发明的该优选实施方式的浇注混凝土墙体的施 工方法包括如下步骤: 安装薄壁型钢框架的步骤, 其中, 沿着所述混凝土墙体的主 平面的横向伸展方向间隔开并互相平行排列地布置多个竖向冷弯 薄壁型钢龙骨 5 , 每个竖向冷弯薄壁型钢龙骨 5 包括两根竖向冷 弯薄壁型钢 51, 52, 将所述竖向冷弯薄壁型钢的主平面设置成与 所述混凝土墙体的主平面平行, 使所述两根竖向冷弯薄壁型钢沿 着与所述混凝土墙体的主平面垂直的方向彼此对置并间隔开, 以 致所述两根竖向冷弯薄壁型钢之间留有在浇注混凝土时供所述混 凝土流过的空间 200;
安装外侧混凝土模板 131的步骤, 其中, 在所述冷弯薄壁型 钢框架的一侧, 安装外侧混凝土模板将其与薄壁型钢框架固定连 接;
安装内侧混凝土模板 132的步骤, 其中, 在所述冷弯薄壁型 钢框架的另一侧, 安装内侧混凝土模板将其与薄壁型钢框架固定 连接;
浇注混凝土的步骤, 其中, 向所述外侧混凝土模板与所述内 侧混凝土模板之间浇注混凝土, 使所述混凝土顺畅流过所述空间
200. 在安装薄壁型钢框架的步骤中包括: 准备在底部的起始平台 113 ,在所述起始平台上固定包括起始板 112和起始竖向冷弯薄壁 型钢龙骨 41 , 42的起始套管 4, 将所述竖向冷弯薄壁型钢 51, 52 与所述起始竖向冷弯薄壁型钢龙骨 41 , 42固定连接起来; 将所述 两根竖向冷弯薄壁型钢连接起来的步骤, 其中, 使两根竖向冷弯 薄壁型钢上的龙骨卷边冲孔 191 , 192彼此正对,使所述龙骨卷边 冲孔的贯穿方向与所述混凝土墙体的主平面垂直, 在沿着所述冷 弯薄壁型钢的竖向间隔开的位置处,用连接钢板 61 , 62将所述两 根竖向冷弯薄壁型钢固定连接; 用包括横向冷弯薄壁型钢 81, 82 的横向连接冷弯薄壁型钢龙骨将多个平行排列的竖向冷弯薄壁型 钢龙骨连接起来,把包括斜向冷弯薄壁型钢 31 , 32的斜向支撑冷 弯薄壁型钢龙骨与竖向冷弯薄壁型钢龙骨连接起来, 以形成一个 稳定的整体刚性结构; 在一部分龙骨卷边冲孔 191 , 192中贯穿拉 接栓 111,使拉接栓 111的两端分别穿过所述龙骨卷边冲孔与所述 外侧拉紧套管和内侧拉紧套管螺纹连接。 在安装所述外侧混凝土模板时, 使外侧混凝土模板与处在外 侧的竖向冷弯薄壁型钢 51之间留有间隔,在安装内侧混凝土模板 时,使内侧混凝土模板与处在内侧的竖向冷弯薄壁型钢 52之间留 有间隔, 在浇注混凝土时, 使混凝土充满在外侧混凝土模板与内 侧混凝土模板之间的空间并将冷弯薄壁型钢框架覆盖起来。 在外侧拉紧栓 161与外侧混凝土模板 131之间设置对外侧混 凝土模板提供支撑的外侧竖向混凝土模板龙骨 121和外侧混凝土 模板横向龙骨 141, 在内侧拉紧栓 162与内侧混凝土模板 132之 间设置对内侧混凝土模板提供支撑的内侧竖向混凝土模板龙骨 122和内侧混凝土模板横向龙骨 142。 在将外侧拉紧栓 161穿过外侧混凝土模板 131与外侧拉紧套 管 171连接时, 将外侧拉紧栓依次穿过外侧垫片 151、 外侧混凝 土模板横向龙骨、 外侧混凝土模板竖向龙骨和外侧混凝土模板与 外侧拉紧套管 171螺纹连接, 以将外侧混凝土模板与所述竖向冷 弯薄壁型钢龙骨固定连接。 在将内侧拉紧栓 162穿过内侧混凝土模板 132与内侧拉紧套 管 171连接时, 将内侧拉紧栓依次穿过内侧垫片 152、 内侧混凝 土模板横向龙骨、 内侧混凝土模板竖向龙骨和所述内侧混凝土模 板与内侧拉紧套管 172螺纹连接, 以将内侧混凝土模板与竖向冷 弯薄壁型钢龙骨固定连接。 安装外侧混凝土模板与内侧混凝土模板将其与薄壁型钢框架 固定连接时利用外侧拉紧套管、 内侧拉紧套管、 拉接栓、 外侧拉 紧拴和内侧拉紧栓, 在外侧混凝土模板与内侧混凝土模板之间形 成沿着墙体的伸展方向等宽的空腔, 采用模数化混凝土模板做所 述外侧混凝土模板和所述内侧混凝土模板。 在浇注混凝土的步骤中, 混凝土从空间 200流过并从龙骨卷 边冲孔 191, 192和所述连接钢板上的卷边冲孔流过, 流动阻碍很 小, 流动很顺畅, 浇注效率较高, 节约工时和能耗, 成形后的混 凝土的均质性和密实性都更好。 另外, 如图 1和 2所示, 沿着纵向冷弯薄壁型钢龙骨的长度 (或高度) 方向, 各段纵向冷弯薄壁型钢龙骨之间可以通过纵向 型钢连接龙骨 7所包括的纵向连接薄壁型钢 71 , 72固定连接起来, 以便在纵向 (或竖向)上的型钢龙骨的长度(或高度)可以到达 工程上所需要的长度(或高度)。 另外, 根据图 1、 3和 4中所示, 本领域技术人员可以理解, 本发明提出的薄壁型钢框架结构和板的施工方法同样可以用于楼 板的浇注。 只不过浇注楼板时在框架上侧不设置混凝土模板, 而 将普通可拆卸混凝土模板固定连接在薄壁型钢框架的下面 (外 侧), 然后从上面浇注混凝土即可。 当将本发明的薄壁型钢框架结 构应用在建筑物屋顶楼板时, 其减小或消除冷桥的效果同样可以 得到体现。 对于上面所述的以本发明的薄壁型钢框架代替钢筋的具体实 施方案, 本领域技术人员可以根据工程实践的需要, 采用具体的 工作流程, 进行各种变化和调整。 本申请提出的一种具体工程实 践中可以采用的流程如下:
1.通过计算机辅助设计程序或手工设计将薄壁型钢框架结构 布置图设计出来, 准确标注各薄壁型钢构件的位置;
2.通过计算机辅助设计程序或手工设计将混凝土模板的布置 图设计出来, 准确标注标准混凝土模板与非标混凝土模板的位置 并确定拉紧栓的孔位;
3.基础施工完毕后进行起始平台的施工或把基础当作起始平 台, 要求尺寸准确, 整个周圏须保持在同一标高上, 根据设计要 求开始连续固定起始套管;
4. 进行竖向龙骨的施工,将竖向龙骨套入起始龙骨并进行螺 栓连接, 再将横向型钢龙骨栓接在竖向龙骨上, 使其成为稳定的 结构;
5. 固定、 安装内侧混凝土模板与外侧混凝土模板;
6. 对于模数化的混凝土模板一层一层安装,模数化内侧混凝 土模板与外侧混凝土模板通过拉接栓、 拉紧套管、 拉紧栓形成可 靠等宽空腔; 7. 重复 5、 6步骤至楼板处, 模数化内侧混凝土模板与楼板 的底混凝土模板(可选用可拆卸的模数化混凝土模板)处相交, 并做好可靠支撑, 模数化外侧混凝土模板继续向上安装一至二块 并与升上去的竖向龙骨进行连接;
8. 薄壁型钢框架与混凝土模板 (包括外侧混凝土模板和内侧 混凝土模板)施工交叉进行, 通常竖向龙骨出楼面 90公分, 并作 为临时护栏, 待楼板薄壁型钢安装完成后进行下层墙体和楼面的 混凝土浇注, 注意兜圏浇注, 一次约 0.5米高;
9. 重复步骤 5~8至屋顶。 在本申请的文件中, 所有的 "包括…"都既有"包括… "又有 "由…构成"的意思。 本申请的说明书中对各种结构构件和方法的说明, 以对与本 发明相关的方面进行说明为主, 本领域技术人员根据实际的工程 设计、 施工的需要, 可以对说明书中公开的各种方法所包括的步 骤进行补充、 修改或增删, 在不脱离本发明的原理的情况下, 这 些补充、 修改或增删后的方法都不会脱离本发明的范围。 例如, 优选实施方式中说明的是在施工现场对混凝土板进行浇注的施工 方法。 但是, 本领域技术人员可以理解, 本发明的施工方法同样 可以在建材厂中应用, 以对混凝土板(包括墙板、楼板和屋面板) 进行预制。 部件和附图标记清单 起始平台 113
膨胀螺栓 91
起始套管 4
起始板 112
起始竖向冷弯薄壁型钢龙骨 41, 42 纵向冷弯薄壁型钢龙骨 5, 9 纵向冷弯薄壁型钢 51, 52, 91, 92 连接钢板 61, 62
纵向型钢连接龙骨 7
纵向连接薄壁型钢 71, 72
横向钢龙骨 8
横向薄壁型钢 81, 82
水平型钢龙骨 9
水平薄壁型钢 91, 92
斜向支撑冷弯薄壁型钢龙骨 31, 32 卷边冲孔 191, 192, 193, 194 空间 200
竖向混凝土模板龙骨 121, 122 横向混凝土模板龙骨 141, 142 混凝土模板 131, 132 拉紧栓 161, 162
拉接栓 111
垫片 151, 152
拉紧套管 171, 172 自攻螺钉 118 自供螺栓 115 支撑角钢 116

Claims

1. 一种混凝土板结构构件, 包括:
冷弯薄壁型钢框架;
混凝土, 其包裹着所述冷弯薄壁型钢框架;
所述冷弯薄壁型钢框架包括多个沿着所述混凝土板结构构件 的主平面的横向伸展方向间隔开的互相平行排列的纵向冷弯薄壁 型钢龙骨 (5, 9);
其特征在于: 每个纵向冷弯薄壁型钢龙骨包括两根纵向冷弯 薄壁型钢( 51, 52, 91, 92), 所述纵向冷弯薄壁型钢的主平面与 所述混凝土板结构构件的主平面平行, 所述两根纵向冷弯薄壁型 钢沿着与所述混凝土板结构构件的主平面垂直的方向彼此对置并 间隔开, 以致所述两根纵向冷弯薄壁型钢之间留有在浇注混凝土 时供所述混凝土流过的空间 ( 200), 所述两根纵向冷弯薄壁型钢 之间留有的空间里充满混凝土。
2. 如权利要求 1 所述的混凝土板结构构件, 其特征在于: 所述两根纵向冷弯薄壁型钢之间通过沿着所述冷弯薄壁型钢的纵 向间隔开的连接钢板(61, 62) 固定连接。
3. 如权利要求 2 所述的混凝土板结构构件, 其特征在于: 每个纵向冷弯薄壁型钢龙骨 (5) 包括的纵向冷弯薄壁型钢 (51, 52)上带有沿着其长度方向分布的贯穿的多个在浇注混凝土时供 混凝土流过的龙骨卷边冲孔( 191, 192), 所述连接钢板(61, 62) 上带有在浇注混凝土时供混凝土流过的卷边冲孔( 193, 194)。
4. 如权利要求 1 所述的混凝土板结构构件, 其特征在于: 所述冷弯薄壁型钢框架还包括:
横向连接冷弯薄壁型钢龙骨,其包括横向冷弯薄壁型钢(81,
82 );
斜向支撑冷弯薄壁型钢龙骨,其包括斜向冷弯薄壁型钢(31,
32);
多个平行排列的纵向冷弯薄壁型钢龙骨通过所述横向连接冷 弯薄壁型钢龙骨而连接, 所述斜向支撑冷弯薄壁型钢龙骨与所述 纵向冷弯薄壁型钢龙骨连接, 所述纵向冷弯薄壁型钢龙骨、 所述 横向连接冷弯薄壁型钢龙骨和所述斜向支撑冷弯薄壁型钢龙骨连 接以形成一个稳定的整体刚性结构。
5. 如权利要求 1 - 4之一所述的混凝土板结构构件, 其特征 在于: 所述混凝土板结构构件为混凝土墙板结构构件, 所述纵向 冷弯薄壁型钢 (51, 52) 为沿着竖向伸展放置的竖向冷弯薄壁型 钢。
6. 如权利要求 5 所述的混凝土板结构构件, 其特征在于: 还包括: 处在底部的起始平台 ( 113), 所述起始平台上固定有起 始套管(4), 所述起始套管(4)具有向上突出的起始竖向冷弯薄 壁型钢龙骨(41, 42), 所述纵向冷弯薄壁型钢(51, 52)与所述 起始纵向冷弯薄壁型钢龙骨 (41, 42) 固定连接起来。
7. 如权利要求 5 所述的混凝土板结构构件, 其特征在于: 所述混凝土墙板结构构件为现浇混凝土墙板构件, 其还包括外侧 混凝土模板 ( 131 )和内侧混凝土模板 ( 132), 所述外侧混凝土模 板( 131 )处在所述冷弯薄壁型钢框架的一侧, 所述内侧混凝土模 板( 132)处在所述冷弯薄壁型钢框架的另一侧, 所述外侧混凝土 模板和所述内侧混凝土模板都与所述冷弯薄壁型钢框架固定连 接, 所述外侧混凝土模板和所述内侧混凝土模板与所述纵向冷弯 薄壁型钢 (51 , 52 )之间都留有间隔, 所述混凝土处在所述外侧 混凝土模板与所述内侧混凝土模板之间并将所述冷弯薄壁型钢框 架覆盖起来。
8. 如权利要求 7 所述的混凝土板结构构件, 其特征在于: 在两根纵向冷弯薄壁型钢上的龙骨卷边冲孔( 191 , 192 )彼此正 对, 所述龙骨卷边冲孔的贯穿方向与所述混凝土板结构构件的主 平面垂直;
所述混凝土板结构构件还包括拉接栓( 111 )、 外侧拉紧栓 ( 161 )、 内侧拉紧栓( 162 )、 外侧拉紧套管( 171 )和内侧拉紧套 管( 172 ),在一部分龙骨卷边冲孔( 191, 192 )中贯穿拉接栓( 111 ), 所述外侧拉紧套管 ( 171 )处在所述外侧混凝土模板 ( 131 ) 与每 个纵向冷弯薄壁型钢龙骨所包括的两根纵向冷弯薄壁型钢中的处 在外侧的纵向冷弯薄壁型钢(51 )之间,所述内侧拉紧套管( 172 ) 处在所述内侧混凝土模板( 132 )与每个纵向冷弯薄壁型钢龙骨所 包括的两根纵向冷弯薄壁型钢中的处在内侧的纵向冷弯薄壁型钢 ( 52 )之间;
所述拉接栓( 111 )的两端分别穿过所述龙骨卷边冲孔与所述 外侧拉紧套管和内侧拉紧套管连接, 所述外侧拉紧栓( 161 )穿过 所述外侧混凝土模板 ( 131 ) 与所述外侧拉紧套管 ( 171 )连接, 以将所述外侧混凝土模板与所述纵向冷弯薄壁型钢龙骨固定连 接, 所述内侧拉紧栓( 162 ) 穿过所述内侧混凝土模板( 132 ) 与 所述内侧拉紧套管( 171 )连接, 以将所述内侧混凝土模板与所述 纵向冷弯薄壁型钢龙骨固定连接。
9. 如权利要求 8 所述的混凝土板结构构件, 其特征在于: 在所述外侧拉紧栓( 161 ) 与所述外侧混凝土模板 ( 131 )之间设 有对外侧混凝土模板提供支撑的外侧竖向混凝土模板龙骨 ( 121 ) 和外侧混凝土模板横向龙骨( 141 ), 在所述内侧拉紧栓( 162 )与 所述内侧混凝土模板 ( 132 )之间设有对内侧混凝土模板提供支撑 的内侧竖向混凝土模板龙骨 ( 122 ) 和内侧混凝土模板横向龙骨
( 142 ), 所述外侧拉紧栓依次穿过外侧垫片 ( 151 )、 外侧混凝土 模板横向龙骨、 外侧混凝土模板竖向龙骨和所述外侧混凝土模板 与外侧拉紧套管( 171 )连接, 所述内侧拉紧栓依次穿过内侧垫片
( 152 )、 内侧混凝土模板横向龙骨、 内侧混凝土模板竖向龙骨和 所述内侧混凝土模板与内侧拉紧套管 ( 172 )连接。
10. 如权利要求 8所述的混凝土板结构构件, 其特征在于: 所述拉接栓( 111 )、 外侧拉紧栓( 161 ) 与外侧拉紧套管 ( 171 ) 之间为螺纹连接, 所述拉接栓( 111 )、 内侧拉紧栓( 162 )与内侧 拉紧套管( 172 )之间为螺纹连接, 每个纵向冷弯薄壁型钢龙骨所 包括的两根纵向冷弯薄壁型钢都为 C形型钢, 所述外侧混凝土模 板和所述内侧混凝土模板都为模数化混凝土模板。
11. 如权利要求 1 - 4之一所述的混凝土板结构构件,其特征 在于: 所述混凝土板结构构件为混凝土楼板结构构件或屋面板结 构构件。
12. 一种浇注混凝土板的施工方法, 其特征在于: 包括如下 步骤:
安装薄壁型钢框架的步骤, 其中, 沿着所述混凝土板的主平 面的横向伸展方向间隔开并互相平行排列地布置多个纵向冷弯薄 壁型钢龙骨(5, 9), 每个竖向冷弯薄壁型钢龙骨(5, 9) 包括两 根纵向冷弯薄壁型钢( 51, 52, 91, 92), 将所述纵向冷弯薄壁型 钢的主平面设置成与所述混凝土板的主平面平行, 使所述两根纵 向冷弯薄壁型钢沿着与所述混凝土板的主平面垂直的方向彼此对 置并间隔开, 以致所述两根纵向冷弯薄壁型钢之间留有在浇注混 凝土时供所述混凝土流过的空间 ( 200 ),
安装模板的步骤, 其中, 包括: 在所述冷弯薄壁型钢框架的 一侧, 安装外侧混凝土模板( 131, 202)将其与薄壁型钢框架固 定连接;
浇注混凝土的步骤, 其中, 使所述混凝土顺畅流过所述空间
( 200 )。
13. 如权利要求 12 所述的浇注混凝土板的施工方法, 其特 征在于: 在安装薄壁型钢框架的步骤中包括将所述两根纵向冷弯 薄壁型钢连接起来的步骤, 其中, 在沿着所述冷弯薄壁型钢的纵 向间隔开的位置处, 用连接钢板(61, 62)将所述两根竖向冷弯 薄壁型钢固定连接。
14. 如权利要求 13 所述的浇注混凝土墙体的施工方法, 其 特征在于: 每个纵向冷弯薄壁型钢龙骨 (5, 9) 包括的纵向冷弯 薄壁型钢 ( 51, 52, 91, 92)上带有沿着其长度方向分布的贯穿 的多个在浇注混凝土时供混凝土流过的龙骨卷边冲孔( 191, 192), 所述连接钢板(61, 62)上带有在浇注混凝土时供混凝土流过的 卷边冲孔( 193, 194), 在浇注混凝土的步驟中, 所述混凝土从所 述龙骨卷边冲孔( 191, 192)和所述连接钢板上的卷边冲孔流过。
15. 如权利要求 12 所述的浇注混凝土板的施工方法, 其特 征在于: 所述混凝土板为混凝土墙板, 所述纵向冷弯薄壁型钢为 竖向冷弯薄壁型钢, 所述安装模板的步骤还包括: 在所述冷弯薄 壁型钢框架的另一侧, 安装内侧混凝土模板( 132 ), 将其与薄壁 型钢框架固定连接; 在所述浇注混凝土的步骤中, 向所述外侧混 凝土模板与所述内侧混凝土模板之间浇注混凝土。
16. 如权利要求 12 所述的浇注混凝土板的施工方法, 其特 征在于: 在安装薄壁型钢框架的步骤中包括:
用包括横向冷弯薄壁型钢 (81 , 82 ) 的横向连接冷弯薄壁型 钢龙骨将多个平行排列的纵向冷弯薄壁型钢龙骨连接起来, 把包 括斜向冷弯薄壁型钢 (31, 32 ) 的斜向支撑冷弯薄壁型钢龙骨与 纵向冷弯薄壁型钢龙骨连接起来, 以形成一个稳定的整体刚性结 构。
17. 如权利要求 15 所述的浇注混凝土板的施工方法, 其特 征在于: 在安装薄壁型钢框架的步骤中包括: 准备在底部的起始 平台 ( 113 ), 在所述起始平台上固定包括起始板( 112 )和起始竖 向冷弯薄壁型钢龙骨 (41, 42 ) 的起始套管 (4 ), 将所述纵向冷 弯薄壁型钢 (51 , 52 ) 与所述起始竖向冷弯薄壁型钢龙骨 (41 , 42 ) 固定连接起来。
18. 如权利要求 15 所述的浇注混凝土板的施工方法, 其特 征在于: 在安装所述外侧混凝土模板时, 使所述外侧混凝土模板 与所述处在外侧的竖向冷弯薄壁型钢 (51 )之间留有间隔, 在安 装所述内侧混凝土模板时, 使所述内侧混凝土模板与所述处在内 侧的竖向冷弯薄壁型钢 (52 )之间留有间隔, 在浇注混凝土时, 使所述混凝土充满在所述外侧混凝土模板与所述内侧混凝土模板 之间的空间并将所述冷弯薄壁型钢框架覆盖起来。
19. 如权利要求 14 所述的浇注混凝土板的施工方法, 其特 征在于: 所述混凝土板为混凝土墙板, 所述纵向冷弯薄壁型钢为 竖向冷弯薄壁型钢, 所述安装模板的步骤还包括: 在所述冷弯薄 壁型钢框架的另一侧, 安装内侧混凝土模板( 132 ), 将其与薄壁 型钢框架固定连接; 在所述浇注混凝土的步骤中, 向所述外侧混 凝土模板与所述内侧混凝土模板之间浇注混凝土; 在安装薄壁型 钢框架的步骤中, 使两根纵向冷弯薄壁型钢上的龙骨卷边冲孔 ( 191 , 192 )彼此正对, 使所述龙骨卷边冲孔的贯穿方向与所述 混凝土板的主平面垂直, 在一部分龙骨卷边冲孔( 191 , 192 ) 中 贯穿拉接栓 ( 111 ), 使所述拉接栓 ( 111 )的两端分别穿过所述龙 骨卷边冲孔与所述外侧拉紧套管和内侧拉紧套管连接,
在安装外侧混凝土模板 ( 131 )时, 将所述外侧拉紧栓( 161 ) 穿过所述外侧混凝土模板 ( 131 ) 与所述外侧拉紧套管 ( 171 )连 接, 以将所述外侧混凝土模板与所述纵向冷弯薄壁型钢龙骨固定 连接, 在安装内侧混凝土模板( 131 )的步骤中包括: 将所述内侧 拉紧栓( 162 ) 穿过所述内侧混凝土模板 ( 132 ) 与所述内侧拉紧 套管( 171 )连接, 以将所述内侧混凝土模板与所述纵向冷弯薄壁 型钢龙骨固定连接。
20. 如权利要求 19 所述的浇注混凝土板的施工方法, 其特 征在于: 还包括在所述外侧拉紧栓( 161 )与所述外侧混凝土模板
( 131 )之间设置对外侧混凝土模板提供支撑的外侧竖向混凝土模 板龙骨( 121 )和外侧混凝土模板横向龙骨( 141 ), 在所述内侧拉 紧栓( 162 ) 与所述内侧混凝土模板 ( 132 )之间设置对内侧混凝 土模板提供支撑的内侧竖向混凝土模板龙骨( 122 )和内侧混凝土 模板横向龙骨 ( 142 );
在将所述外侧拉紧栓( 161 )穿过所述外侧混凝土模板 ( 131 ) 与所述外侧拉紧套管( 171 )连接时, 将所述外侧拉紧栓依次穿过 外侧垫片 ( 151 )、 外侧混凝土模板横向龙骨、 外侧混凝土模板竖 向龙骨和所述外侧混凝土模板与外侧拉紧套管( 171 )连接, 在将 所述内侧拉紧栓( 162 ) 穿过所述内侧混凝土模板 ( 132 ) 与所述 内侧拉紧套管( 171 )连接时, 将所述内侧拉紧栓依次穿过内侧垫 片 ( 152 )、 内侧混凝土模板横向龙骨、 内侧混凝土模板竖向龙骨 和所述内侧混凝土模板与内侧拉紧套管 ( 172 )连接。
21. 如权利要求 19 所述的浇注混凝土板的施工方法, 其特 征在于: 所述拉接栓( 111 )、 外侧拉紧栓( 161 )与外侧拉紧套管
( 171 )之间为螺纹连接, 所述拉接栓( 111 )、 内侧拉紧栓( 162 ) 与内侧拉紧套管( 172 )之间为螺纹连接, 每个纵向冷弯薄壁型钢 龙骨所包括的两根纵向冷弯薄壁型钢都为 C形型钢。
22. 如权利要求 20 所述的浇注混凝土板的施工方法, 其特 征在于: 安装外侧混凝土模板与内侧混凝土模板将其与薄壁型钢 框架固定连接时利用外侧拉紧套管、 内侧拉紧套管、 拉接栓、 外 侧拉紧拴和内侧拉紧栓, 在外侧混凝土模板与内侧混凝土模板之 间形成沿着墙体的伸展方向等宽的空腔, 采用模数化混凝土模板 做所述外侧混凝土模板和所述内侧混凝土模板。
23. 如权利要求 12 - 14和 16之一所述的浇注混凝土板的施 工方法, 其特征在于: 所述混凝土板结构构件为混凝土楼板结构 构件或屋面板结构构件。
PCT/CN2011/082967 2010-11-25 2011-11-25 混凝土板结构构件以及其浇注施工方法 WO2012069015A1 (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US13/989,120 US20140013683A1 (en) 2010-11-25 2011-11-25 Concrete slabe structural member and construction method for pouring same

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2010105747766A CN102477770A (zh) 2010-11-25 2010-11-25 混凝土板结构构件和浇注混凝土板的施工方法
CN201010574776.6 2010-11-25

Publications (1)

Publication Number Publication Date
WO2012069015A1 true WO2012069015A1 (zh) 2012-05-31

Family

ID=46090541

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2011/082967 WO2012069015A1 (zh) 2010-11-25 2011-11-25 混凝土板结构构件以及其浇注施工方法

Country Status (3)

Country Link
US (1) US20140013683A1 (zh)
CN (1) CN102477770A (zh)
WO (1) WO2012069015A1 (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727544A (zh) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 一种铝合金外墙模板及其浇筑楼层交接处外墙的方法
CN107217758A (zh) * 2017-07-28 2017-09-29 合肥国瑞集成建筑科技有限公司 一种全预制可承重的轻钢装配式复合墙板及其制作方法
CN107338957A (zh) * 2017-09-07 2017-11-10 中国建筑第二工程局有限公司 挡墙模板支撑体系及挡墙模板支撑系统
CN108868120A (zh) * 2018-05-31 2018-11-23 中冶天工集团天津有限公司 一种楼梯间剪力墙一次支模两次浇筑的施工方法
CN110029813A (zh) * 2019-05-16 2019-07-19 江西国金建设集团有限公司 一种变形缝处墙体支模施工方法
CN110258924A (zh) * 2019-07-03 2019-09-20 中国五冶集团有限公司 冷弯c形角钢格构式异形柱及其制作方法
CN110295539A (zh) * 2019-07-30 2019-10-01 中铁二十一局集团第五工程有限公司 一种防倾覆的高薄壁钢筋混凝土结构及施工方法
CN115217070A (zh) * 2021-04-19 2022-10-21 河南正合建筑科技有限公司 一种采用网模构件加固的大堤及其施工方法

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102912982B (zh) * 2012-11-04 2015-02-18 西安建筑科技大学 一种高延性纤维混凝土楼面整浇层的施工方法
DK177889B1 (en) * 2012-11-23 2014-11-17 Kim Illner Breuning System and Method for biaxial semi-prefabricated lightweight concrete slab
US9593487B2 (en) * 2014-09-05 2017-03-14 James F. Harvey Modular building system
CN105442746B (zh) * 2014-09-17 2018-04-17 北新集团建材股份有限公司 一种复合板
CN104264982B (zh) * 2014-10-09 2016-08-17 深圳汇林达科技有限公司 一种散拼早拆建筑模板体系及其搭建方法
JP6655320B2 (ja) * 2015-07-31 2020-02-26 正 斉原 支保部材、コンクリート打設用型枠およびコンクリート構造物の建造方法
CN106592839A (zh) * 2017-03-03 2017-04-26 沈阳建筑大学 一种横张体外预应力压型钢板组合楼板
US10538907B2 (en) * 2017-08-01 2020-01-21 SkyStone Group LLC Modular assemblies and methods of construction thereof
CN107461027A (zh) * 2017-09-21 2017-12-12 付志红 一种墙体模板加固体系
CN109057041B (zh) * 2018-08-15 2024-01-26 浙江圣鑫建设有限公司 工业化冷弯薄壁型钢复合墙与钢梁连接节点及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030233801A1 (en) * 2002-06-22 2003-12-25 Pace Malcolm J. Apparatus and method for composite concrete and steel floor construction
CN1632251A (zh) * 2005-01-21 2005-06-29 朱宏宇 组合型钢网架与混凝土复合构件及制造方法
CN201148667Y (zh) * 2008-01-08 2008-11-12 长安大学 冷弯薄壁型钢多层交错桁架体系
CN101492936A (zh) * 2008-11-19 2009-07-29 李登满 越层主承重梁建筑体系
CN101851986A (zh) * 2010-05-17 2010-10-06 大连理工大学 具有组合结构的保温屋面板
CN201981699U (zh) * 2010-11-25 2011-09-21 欧文斯科宁知识产权资产有限公司 混凝土板结构构件

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2298989A (en) * 1940-05-20 1942-10-13 Ernest J Underwood Building construction
US4050213A (en) * 1970-01-12 1977-09-27 Thomas J. Dillon & Co., Inc. Method of erecting a multi-story building
EP0298008B1 (en) * 1987-07-01 1993-05-12 Juan Antonio Martinez Baena Building element comprising prefabricated panels
US5048257A (en) * 1987-10-06 1991-09-17 Luedtke Charles W Construction system for detention structures and multiple story buildings
CA1296501C (en) * 1988-01-14 1992-03-03 Herbert K. Schilger Composite column or beam for building construction
US4987719A (en) * 1988-12-29 1991-01-29 Goodson Jr Albert A Reinforced concrete building construction and method of forming same
CN2533177Y (zh) * 2002-01-30 2003-01-29 梁军 轻钢龙骨砼复合墙板
CN1587560A (zh) * 2004-07-12 2005-03-02 大连爱特钢建筑产业有限公司 冷弯薄壁格构型钢与混凝土复合的建筑构件及其生产工艺
DE202005005924U1 (de) * 2005-04-12 2005-06-30 Glatthaar-Fertigkeller Gmbh Kerngedämmte Fertigteilwand mit Verbundnadeln
EP1907642B1 (de) * 2005-07-28 2009-09-30 VST Verbundschalungstechnik GmbH Verfahren zum herstellen einer wand-decken-konstruktion in stahlbetonausführung
CN101260723A (zh) * 2007-03-09 2008-09-10 刘文博 一种轻钢龙骨
US8056291B1 (en) * 2007-10-12 2011-11-15 The Steel Networks, Inc. Concrete and light gauge cold formed steel building structure with beam and floor extending over a load bearing stud wall and method of forming
US9388561B2 (en) * 2009-07-15 2016-07-12 Frank Johnson Modular construction mold apparatus and method for constructing concrete buildings and structures

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030233801A1 (en) * 2002-06-22 2003-12-25 Pace Malcolm J. Apparatus and method for composite concrete and steel floor construction
CN1632251A (zh) * 2005-01-21 2005-06-29 朱宏宇 组合型钢网架与混凝土复合构件及制造方法
CN201148667Y (zh) * 2008-01-08 2008-11-12 长安大学 冷弯薄壁型钢多层交错桁架体系
CN101492936A (zh) * 2008-11-19 2009-07-29 李登满 越层主承重梁建筑体系
CN101851986A (zh) * 2010-05-17 2010-10-06 大连理工大学 具有组合结构的保温屋面板
CN201981699U (zh) * 2010-11-25 2011-09-21 欧文斯科宁知识产权资产有限公司 混凝土板结构构件

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727544A (zh) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 一种铝合金外墙模板及其浇筑楼层交接处外墙的方法
CN107217758A (zh) * 2017-07-28 2017-09-29 合肥国瑞集成建筑科技有限公司 一种全预制可承重的轻钢装配式复合墙板及其制作方法
CN107338957A (zh) * 2017-09-07 2017-11-10 中国建筑第二工程局有限公司 挡墙模板支撑体系及挡墙模板支撑系统
CN107338957B (zh) * 2017-09-07 2023-06-23 中国建筑第二工程局有限公司 挡墙模板支撑体系及挡墙模板支撑系统
CN108868120A (zh) * 2018-05-31 2018-11-23 中冶天工集团天津有限公司 一种楼梯间剪力墙一次支模两次浇筑的施工方法
CN110029813A (zh) * 2019-05-16 2019-07-19 江西国金建设集团有限公司 一种变形缝处墙体支模施工方法
CN110029813B (zh) * 2019-05-16 2023-06-20 江西国金建设集团有限公司 一种变形缝处墙体支模施工方法
CN110258924A (zh) * 2019-07-03 2019-09-20 中国五冶集团有限公司 冷弯c形角钢格构式异形柱及其制作方法
CN110258924B (zh) * 2019-07-03 2024-01-26 中国五冶集团有限公司 冷弯c形角钢格构式异形柱及其制作方法
CN110295539A (zh) * 2019-07-30 2019-10-01 中铁二十一局集团第五工程有限公司 一种防倾覆的高薄壁钢筋混凝土结构及施工方法
CN115217070A (zh) * 2021-04-19 2022-10-21 河南正合建筑科技有限公司 一种采用网模构件加固的大堤及其施工方法

Also Published As

Publication number Publication date
US20140013683A1 (en) 2014-01-16
CN102477770A (zh) 2012-05-30

Similar Documents

Publication Publication Date Title
WO2012069015A1 (zh) 混凝土板结构构件以及其浇注施工方法
WO2015131792A1 (zh) 一种建筑结构及其施工方法
WO2012069016A1 (zh) 预制保温复合板及其组件、包括其的模板、混凝土板、其预制方法、模具型材
CN110273466B (zh) 装配式剪力墙及其构筑方法
CN103397705A (zh) 建筑物叠合楼板与钢筋桁架剪力墙的连接结构
CN105696817A (zh) 一种多层冷成型钢整体预制装配房屋及其拼接方法
CN111424849A (zh) 一种安装便捷型预制钢筋混凝土剪力墙及施工方法
CN201649623U (zh) 大型地下室剪力墙桁架式钢管单侧支模结构
CN211775739U (zh) 一种现浇混凝土板可拆卸支模结构
CN104727476A (zh) 装配式轻体3d钢筋桁架楼层板及其制造方法
CN113482208A (zh) 预制混凝土楼板的干湿结合连接构造及施工方法
CN112282047B (zh) 一种装配式组合楼板与组合墙板的连接结构及连接方法
CN218437691U (zh) 一种应用于钢筋混凝土框架的轻型装配式楼盖体系
CN203475609U (zh) 建筑物叠合楼板与钢管剪力墙的连接结构
CN216892975U (zh) 一种预制装配式叠合钢管混凝土剪力墙
CN213926975U (zh) 混凝土墙与预制压型钢板组合板连接结构
CN212641827U (zh) 安装便捷型预制钢筋混凝土剪力墙
WO2015051551A1 (zh) 一种建筑物及其施工方法
CN113356371A (zh) 一种装配式框架结构体系的施工方法
CN111749343A (zh) 一种可拆卸装配式钢结构房屋的安装方法
CN105604246A (zh) 一种型钢混凝土t形截面柱施工方法
CN111021615A (zh) 一种新型叠合板及其制作方法
CN219825611U (zh) 一种装配式免拆型楼承板与混凝土梁的连接构造
CN214531146U (zh) 一种叠合楼板与钢柱的连接结构
CN216689800U (zh) 装配式支架立杆预埋槽道

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 11843593

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 13989120

Country of ref document: US

122 Ep: pct application non-entry in european phase

Ref document number: 11843593

Country of ref document: EP

Kind code of ref document: A1