WO2009003331A1 - Double main girder and multi hanging point crane - Google Patents

Double main girder and multi hanging point crane Download PDF

Info

Publication number
WO2009003331A1
WO2009003331A1 PCT/CN2007/003423 CN2007003423W WO2009003331A1 WO 2009003331 A1 WO2009003331 A1 WO 2009003331A1 CN 2007003423 W CN2007003423 W CN 2007003423W WO 2009003331 A1 WO2009003331 A1 WO 2009003331A1
Authority
WO
WIPO (PCT)
Prior art keywords
main beam
hoisting
lifting
control system
main
Prior art date
Application number
PCT/CN2007/003423
Other languages
French (fr)
Chinese (zh)
Inventor
Jiajing Song
Sheng Zou
Min Gu
Original Assignee
Dalian Huarui Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN2007100119379A external-priority patent/CN101104501B/en
Priority claimed from CNU2007200130439U external-priority patent/CN201080415Y/en
Application filed by Dalian Huarui Co., Ltd. filed Critical Dalian Huarui Co., Ltd.
Priority to JP2010513610A priority Critical patent/JP5247799B2/en
Priority to KR1020107001721A priority patent/KR101184874B1/en
Publication of WO2009003331A1 publication Critical patent/WO2009003331A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C25/00Cranes not provided for in groups B66C17/00 - B66C23/00
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C6/00Girders, or track-supporting structures, specially adapted for cranes

Definitions

  • the invention relates to a lifting machine, in particular to a double main beam multi-lifting crane for overall docking and manufacturing of an offshore drilling platform.
  • the present invention aims to provide an oversized lifting crane to meet the lifting requirements of the new manufacturing process of the drilling platform.
  • a double main beam multi-lifting crane for super large load comprising a main beam, a hoisting mechanism, a translation mechanism, an electric control system, a rotary maintenance crane, a driver's cab, an anchoring device and a windproof tether, wherein:
  • the main beam consists of double main beams arranged at high and low levels.
  • the two main beams are placed on two concrete foundations, and there is no connecting end beam between the two main beams.
  • Each of the main beams is connected by anchoring device and windproof cable.
  • each main beam adopts variable cross section, which is a high-narrow composite beam composed of upper, middle and lower three-box beams; the high-narrow composite type
  • the aspect ratio of the main beam is 3 to 5.
  • the hoisting mechanism is composed of a plurality of sets of hoisting systems, respectively disposed at two ends of the two main beams; each set of each hoisting system is provided with one or more hoisting systems, and each set of hoisting systems is respectively provided with more than one set Hang Point, and synchronously drive all the above lifting points through the electronic control system; the hoisting system is equipped with a rope arranging mechanism, and adopts a single multi-layer winding rope system; to ensure that the entire lifting height is not disordered, avoiding numerous The interference between the wire ropes and the wire rope and the main beam.
  • the 20000t X 125m hook-type overhead crane project consists of 12 sets of hoisting systems, each set of 3 sets of each main beam, and 4 sets of lifting points for each set of hoisting systems. 48 lifting points.
  • the translation mechanism is a self-propelled bidirectional translation mechanism of the main beam disposed along the axial direction of the vertical main beam at the bottom ends of the low main beam;
  • the electric control system is an electric control system for a multi-point crane crane statically indeterminate system, comprising a hoist mechanism control system, a controller, a load sensor and a position sensor composed of a frequency converter, an inverter, a communication module and an electric motor. And the host computer,
  • the controller is responsible for receiving the control command with the host computer, returning the on-site information, and controlling the feedback signals of the running and receiving sensors of each lifting mechanism;
  • the load sensor and the position sensor transmit the load weight and the hoisting height information of each hoisting mechanism to the controller through the communication module carried by the hoisting mechanism, and adjust the operation of each hoisting mechanism by the processing of the controller;
  • the controller, the sensor and the lifting mechanism are all connected by bus communication.
  • the controller is a PLC
  • the load sensor is a load cell
  • the position sensor is a code sensor.
  • the electric control system is an electric control system for a multi-point crane crane statically indeterminate system, which comprises a control system for automatically calculating the centroid of the lifting piece and reasonably distributing the pulling force of each lifting point, a lifting control system for the anti-rollover balance of the lifting device, and various mechanism lines. Speed synchronization control system, crane level automatic control system. Through the electronic control system, the crane load synchronization and smooth lifting are realized.
  • the electronic control system can also realize the functions of 12 sets of hoisting systems, single movement, linkage, and horizontal traverse of the main beam.
  • the hoisting mechanism adopts a multi-winding system to make manufacturing, installation and maintenance simple and low in cost
  • the high and low arrangement double main beam structure can adapt to the large-scale hoisting and docking of the tall rig of the tower, which avoids the technical complexity and low reliability caused by the single main beam lifting scheme;
  • the high-narrow composite beam structure composed of three-box beam has reasonable structure, large carrying capacity and light weight Such characteristics can effectively solve the stress concentration problem caused by the entry and exit holes of the main beam opening wire rope;
  • the invention not only has significant economic benefits, but also can promote the change of the manufacturing method of the drilling platform, thereby bringing about huge social benefits and having a profound impact on the construction of offshore projects in China and the world.
  • Figure 1 is a front elevational view of the overall arrangement of the present invention
  • Figure 2 is a left side view of Figure 1;
  • Figure 3 is a schematic view showing the arrangement of the main beam of the present invention.
  • Figure 4 is a cross-sectional view taken along line A-A of Figure 3;
  • Figure 5 is a schematic view showing the winding of a wire rope of a hoisting system of the hoisting mechanism of the present invention
  • Figure 6 is a left side view of the hoisting mechanism of the single main beam of Figure 1;
  • Figure 7 is a front elevational view of the translation mechanism
  • Figure 8 is an automatic calculation of the centroid position of the hanger
  • Figure 9 is the target pull value for automatically assigning each lifting point
  • Figure 10 is a block diagram of the synchronous control principle of the winch system
  • FIG 11 is a block diagram of the control system.
  • the high main beam 1 and the low main beam 2 are respectively arranged on two different concrete foundations, and the hoisting mechanism is hoisted by six sets of hoisting systems 3 on each main beam, that is, a total of 12 sets.
  • the system consists of each hoisting system 3 consisting of a hoist, a wire rope, a guide pulley, a fixed pulley block, a movable pulley block, etc.; the whole system has a magnification of 40; each set of hoisting system includes 4 moving pulley blocks, and each moving pulley block controls 1 Lifting Point.
  • Winch includes reel (including wire rope press plate), reducer, brake, open gear, coupling, float
  • the hoist completes each lifting cycle through the motor-driven reel as shown in Figure 3.
  • Each hoisting system controls 4 lifting points, and 12 sets of hoisting systems have a total of 48 lifting points to jointly complete the 20,000-ton load lifting task. . See Figure 5 for the winding of the hoisting system.
  • the main beam adopts a variable cross-section form as shown in Fig. 3. It is a high-narrow composite beam composed of upper, middle and lower three-box beams, as shown in Fig. 4, and its aspect ratio is equal to 4.
  • Fig. 6 The anti-interference arrangement of the hoisting wire rope through the multi-lifting crane is shown in Fig. 6, which avoids the interference problem of many wire ropes.
  • the hoist is placed on the main girder cover, and each set of hoisting machines is arranged on each of the end plates of each main beam; the wire rope of each hoist is passed along a fixed guide pulley in the upper space of the main girder cover. From the small opening on the upper cover of the main beam, enter the inner pulley set of the main beam, then wrap it onto the movable pulley block, repeatedly wrap it, and finally fix it on the fixed point of the fixed pulley block.
  • the three sets of hoists on the main beam at each end adopt different heights of support, which makes the rope height of different hoist drum ropes different; in addition, the vertical centerline of the reel of the three sets of hoists at each end of the main beam is connected with the center line of the guide pulley.
  • the line of the main beam of the main beam is formed by the same small yaw angle.
  • the third hoist at each end is rotated by 1.04 degrees with respect to the center line of the main beam.
  • the two ends are opposite to each other; such arrangement enables the wire ropes to be staggered in space, avoiding interference between the wire ropes and the wire rope and the main beam, and making the deflection angle of the wire rope and the hoist drum and the pulley conform to the standard.
  • the linkage between the movable pulley sets maintains a fixed distance connection between the four sets of moving pulley blocks controlled by each set of winch systems, which can simultaneously raise and lower the four lifting points controlled by the four moving pulley blocks, and avoid interference between the wire ropes. .
  • the translation mechanism includes a hinge 21 for carrying the weight and load of the main beam 2, a hydraulic translation mechanism 22, a cylinder support frame 23, a stainless steel sliding track 24, a square steel guide rail 25, a modified polytetrafluoroethylene plate 26, Self-locking wedge clamping mechanism.
  • the whole hydraulic translation mechanism 22 is composed of a hydraulic system, an electric system and a support frame.
  • the hydraulic system includes two jack-up cylinders. .
  • the entire hydraulic translation mechanism 22 is carried along a square steel rail 25 Two-way crawling, each time pushing the main beam 0. 8m, each time the first clamping of the square steel rail 25 by a pair of self-locking wedge clamping mechanism, the other pair of wedge-shaped blocks are in a relaxed state, and then the piston rod pushes the cylinder to support The self-locking wedge clamping mechanism again.
  • the self-locking wedge clamping mechanism is again rotated.
  • the self-locking wedge clamping mechanism is again. By clamping the square steel rail 25, the piston rod pushes the cylinder support frame 23 again to drive the main beam 2, and so on, until the requirement of each translation distance is satisfied. When the translation is reversed, another pair of wedge blocks begin to act, and the reverse translation is also achieved by the above process. Due to the relative slip of the main beam and the foundation of the civil engineering, a mirrored stainless steel sliding track 24 is adhered to the surface of the prefabricated plate of the civil construction, and a modified polytetrafluoroethylene plate 26 is fixed at the bottom of the lower cover of the main beam hinge 21, so that The friction coefficient is greatly reduced, and the material has a small amount of compression deformation and a low wear rate.
  • the crane load is synchronized and leveled up by the electric control system of the multi-point crane crane statically indeterminate system.
  • the electronic control system adopts the design idea and various control of "automatically calculating the centroid of the hanging piece, reasonably distributing the pulling force of each lifting point, controlling the tilting prevention of the hanging piece, synchronizing the line speed of each mechanism, and automatically controlling the level of the hanging piece". Means to solve the above problems.
  • the electrical control scheme for the hoisting mechanism of the hoisting mechanism consisting of 12 sets of hoisting systems is as follows:
  • the control system automatically analyzes the load center of the 12 sets of lifting mechanisms and makes a reasonable grouping, automatically calculates the centroid position of the lifting parts, and distributes the rational force of each lifting mechanism.
  • each lifting point tension control is another important additional control means.
  • the control system detects the pulling force carried by each hook during the running process through the tension sensor. Once the lifting force of a lifting point exceeds the target pulling force value, the The mechanism corrects the tension value back to the allowable value range. Can effectively prevent tipping.
  • the hoisting motor adopts the speed control as the main reference, and the speed synchronous control as the most basic control means. Since the hoisting mechanism wire rope winding method is multi-layer winding, for a certain motor speed, the hoisting mechanism is The line speed of one layer is different. Control system through calculation and external The detection means cooperates to provide different speed reference signals for the frequency converter according to different layers, which can ensure the wire speed of each set of lifting mechanism is consistent.
  • the control system uses the displacement signal provided by the position detection encoder to detect the relative position difference of each lifting point in real time during the lifting process.
  • the coordinate plane and the hovering mode formed by each lifting point are memorized,
  • the position correction is performed; the hanger is kept at a basic level during operation.
  • control system will adopt different control methods, and automatically complete the functions of data acquisition and calculation, function judgment and data correction, so that the control system is highly automated and intelligent.

Abstract

A double girder and multi hanging point crane comprises main girders, a lifting mechanism, a translating mechanism (4) and an electric control system, characterized in that said main girders are double main girders (1,2) highly and lowly arranged, each main girder having variable sections and being high and narrow compound girders composed of three-box-typed main girders; the lifting mechanism is composed of multi sets of hoisting systems (3), each set of hoisting systems (3) respectively connected to and controlling multi hanging points and synchronously driving above all hanging points through the electric control system; a rope arranging mechanism is arranged at the hoisting systems (3), and a mono-connecting and multiplayer twisting rope system is adopted; the translating mechanism (4) is main girder bidirectionally self-translating mechanism arranged at the two ends of the lower main girder; the electric control system is an electric control system of multi hanging point crane hyperstatic system.

Description

双主梁多吊点起重机 技术领域  Double main beam multi-lift crane
本发明涉及起重机械, 尤其涉及海上钻井平台整体对接及制造用的双主梁 多吊点起重机。  The invention relates to a lifting machine, in particular to a double main beam multi-lifting crane for overall docking and manufacturing of an offshore drilling platform.
背景技术 Background technique
随着钻井平台需求的增加, 大型起重机要求被用于海上钻井平台整体制作, 要对钻井平台的大型分段的进行提升、 组装, 并能适应不同塔架高度和不同的 钻井平台的宽度, 使许多高空作业改为平地作业并一次提升安装, 不仅节省钻 井平台制造工时、 缩短建造周期, 而且能确保人员安全和提高产品质量。  As the demand for drilling platforms increases, large cranes are required to be used in the overall production of offshore drilling platforms. Large sections of the drilling platform must be upgraded and assembled, and can accommodate different tower heights and different rig widths. Many high-altitude operations have been changed to flat work and upgraded at one time, which not only saves drilling rig manufacturing hours, shortens the construction cycle, but also ensures personnel safety and improves product quality.
但由于该类型起重机必须具有超大起重量(联合起吊可达 2万吨), 超大起 升高度(最大可达 103m), 超大跨度(跨度为 125m), 因此给设计、制造、安装、 调试带来不可想象的困难, 如主梁如何构造、 起升机构如何选型、 多卷扬机构 如何布置、 主梁开钢丝绳出入孔所引起的应力集中问题如何解决、 主梁如何移 动、 多吊点起升载荷如何平衡和同步等, 故目前国际上还没有这种类型和起吊 方式的起重机。  However, due to the large lifting capacity of this type of crane (combined lifting up to 20,000 tons), large lifting height (up to 103m) and super-long span (span 125m), it brings design, manufacture, installation and commissioning. Unimaginable difficulties, such as how the main beam is constructed, how the hoisting mechanism is selected, how the multi-winding mechanism is arranged, how to solve the stress concentration problem caused by the main beam opening and exiting the wire rope, how the main beam moves, and the lifting point of the lifting point How to balance and synchronize, etc., so there is no such type and crane in the world.
发明内容 Summary of the invention
鉴于现有技术所存在的上述局限及现场实际的迫切需求, 本发明旨在提供 一种超大起重量起重机, 以满足钻井平台的制造新工艺所提出的吊装要求。  In view of the above limitations of the prior art and the actual urgent needs of the field, the present invention aims to provide an oversized lifting crane to meet the lifting requirements of the new manufacturing process of the drilling platform.
本发明的技术解决方案是这样实现的:  The technical solution of the present invention is implemented as follows:
一种超大载荷用双主梁多吊点起重机, 包括主梁、 起升机构、 平移机构、 电控系统、 回转式维修起重机、 司机室、 锚定装置和防风系缆, 其特征在于: 所述的主梁包括高低布置的双主梁, 两主梁分别安放于高低两个混凝土基 础上, 两主梁之间无连接端梁; 所述的每个主梁通过锚定装置和防风系缆加以 整体固定, 以确保主梁在工作或非工作状态的整体稳定; 每个主梁均采用变截 面, 为上、 中、 下三箱型梁组成的高窄复合梁; 所述的高窄复合型主梁的高宽 比为 3〜5。  A double main beam multi-lifting crane for super large load, comprising a main beam, a hoisting mechanism, a translation mechanism, an electric control system, a rotary maintenance crane, a driver's cab, an anchoring device and a windproof tether, wherein: The main beam consists of double main beams arranged at high and low levels. The two main beams are placed on two concrete foundations, and there is no connecting end beam between the two main beams. Each of the main beams is connected by anchoring device and windproof cable. The whole is fixed to ensure the overall stability of the main beam in working or non-working state; each main beam adopts variable cross section, which is a high-narrow composite beam composed of upper, middle and lower three-box beams; the high-narrow composite type The aspect ratio of the main beam is 3 to 5.
所述的起升机构由多套卷扬系统组成, 分别设置于两个主梁的两端; 每个 主梁的每端分别布置一套以上卷扬系统, 每套卷扬系统分别设置一个以上的吊 点, 并通过电控系统同步驱动上述全部吊点; 所述的卷扬系统上安装排绳机构, 并采用单联多层缠绕绳系; 以确保整个起升高度不乱绳, 避免了众多起升钢丝 绳之间以及钢丝绳与主梁的干涉问题。 The hoisting mechanism is composed of a plurality of sets of hoisting systems, respectively disposed at two ends of the two main beams; each set of each hoisting system is provided with one or more hoisting systems, and each set of hoisting systems is respectively provided with more than one set Hang Point, and synchronously drive all the above lifting points through the electronic control system; the hoisting system is equipped with a rope arranging mechanism, and adopts a single multi-layer winding rope system; to ensure that the entire lifting height is not disordered, avoiding numerous The interference between the wire ropes and the wire rope and the main beam.
如 20000t X 125m吊钩式桥式起重机项目, 其起升机构由 12套卷扬系统组 成, 每个主梁的每端布置 3套, 每套卷扬系统分别设置 4个吊点, 整机共 48个 吊点。  For example, the 20000t X 125m hook-type overhead crane project consists of 12 sets of hoisting systems, each set of 3 sets of each main beam, and 4 sets of lifting points for each set of hoisting systems. 48 lifting points.
所述的平移机构是在低主梁两端底部沿垂直主梁的轴向设置主梁自行式双 向平移机构;  The translation mechanism is a self-propelled bidirectional translation mechanism of the main beam disposed along the axial direction of the vertical main beam at the bottom ends of the low main beam;
所述的电控系统是一种多吊点起重机超静定系统电气控制系统, 包括由变 频器、 逆变器、 通信模块和电动机组成的起升机构控制系统、 控制器、 载荷传 感器、 位置传感器和上位机,  The electric control system is an electric control system for a multi-point crane crane statically indeterminate system, comprising a hoist mechanism control system, a controller, a load sensor and a position sensor composed of a frequency converter, an inverter, a communication module and an electric motor. And the host computer,
所述的控制器负责同上位机通信接收控制指令、 返回现场信息, 同时控制 各起升机构运行、 接收传感器的反馈信号;  The controller is responsible for receiving the control command with the host computer, returning the on-site information, and controlling the feedback signals of the running and receiving sensors of each lifting mechanism;
所述的载荷传感器和位置传感器将各起升机构的承载重量和起吊高度信息 通过自身所带的通信模块传给控制器, 通过控制器的处理后调整各起升机构的 运行;  The load sensor and the position sensor transmit the load weight and the hoisting height information of each hoisting mechanism to the controller through the communication module carried by the hoisting mechanism, and adjust the operation of each hoisting mechanism by the processing of the controller;
其中控制器、 传感器、 起升机构都通过总线通信方式进行连接。  The controller, the sensor and the lifting mechanism are all connected by bus communication.
所述的控制器为 PLC,载荷传感器为称重传感器,位置传感器为编码传感器。 所述的电控系统是一种多吊点起重机超静定系统电气控制系统, 包括自动 计算吊件质心并合理分配各吊点拉力的控制系统、 吊件防倾翻平衡控制系统、 各机构线速度同步控制系统、 吊件水平自动控制系统。 通过该电控系统实现了 起重机载荷的同步以及平稳起升, 通过电控系统还可实现 12套卷扬系统单动、 联动、 以及主梁的水平横移等功能。  The controller is a PLC, the load sensor is a load cell, and the position sensor is a code sensor. The electric control system is an electric control system for a multi-point crane crane statically indeterminate system, which comprises a control system for automatically calculating the centroid of the lifting piece and reasonably distributing the pulling force of each lifting point, a lifting control system for the anti-rollover balance of the lifting device, and various mechanism lines. Speed synchronization control system, crane level automatic control system. Through the electronic control system, the crane load synchronization and smooth lifting are realized. The electronic control system can also realize the functions of 12 sets of hoisting systems, single movement, linkage, and horizontal traverse of the main beam.
与现有技术相比, 本发明的有益效果是不言而喻的- Compared with the prior art, the beneficial effects of the present invention are self-evident -
( 1 ) 能实现超大载荷升降; (1) It can achieve super-large load lifting;
(2)起升机构采用多卷扬系统使制造、 安装和维修简单, 成本低;  (2) The hoisting mechanism adopts a multi-winding system to make manufacturing, installation and maintenance simple and low in cost;
( 3 ) 高低布置双主梁结构能适应塔架较高的钻井平台大型分段的吊装对 接, 可避免采用单根主梁升降方案所带来的技术复杂性和低可靠性等问题; (3) The high and low arrangement double main beam structure can adapt to the large-scale hoisting and docking of the tall rig of the tower, which avoids the technical complexity and low reliability caused by the single main beam lifting scheme;
(4)整机安全可靠并能适应吊点距离变化的需要; (4) The whole machine is safe and reliable and can adapt to the needs of the change of the hanging point distance;
(5)三箱型梁组成的高窄复合梁结构具有结构合理, 承载能力大, 自重轻 等特点, 可有效解决主梁开钢丝绳出入孔所带来的应力集中问题; (5) The high-narrow composite beam structure composed of three-box beam has reasonable structure, large carrying capacity and light weight Such characteristics can effectively solve the stress concentration problem caused by the entry and exit holes of the main beam opening wire rope;
(6 )特殊构造使基础设施造价降低;  (6) Special construction reduces infrastructure costs;
( 7 )使用该起重机将使海上钻井平台制造效率大大提高。  (7) The use of the crane will greatly improve the manufacturing efficiency of offshore drilling platforms.
总之, 本发明不仅经济效益显著, 而且能推动钻井平台制造方式的变更, 从而带来巨大的社会效益, 对中国乃至世界海工项目建造产生影响深远。  In short, the invention not only has significant economic benefits, but also can promote the change of the manufacturing method of the drilling platform, thereby bringing about huge social benefits and having a profound impact on the construction of offshore projects in China and the world.
附图说明 DRAWINGS
本发明附图 11 张, 其中  Figure 11 of the accompanying drawings, wherein
图 1是本发明的整机布置主视图;  Figure 1 is a front elevational view of the overall arrangement of the present invention;
图 2是图 1的左视图;  Figure 2 is a left side view of Figure 1;
图 3是本发明的主梁布置示意图;  Figure 3 is a schematic view showing the arrangement of the main beam of the present invention;
图 4是图 3的 A-A剖视图;  Figure 4 is a cross-sectional view taken along line A-A of Figure 3;
图 5是本发明的起升机构的 1套卷扬系统的钢丝绳缠绕的示意图; 图 6是图 1的单根主梁上起升机构的左视图;  Figure 5 is a schematic view showing the winding of a wire rope of a hoisting system of the hoisting mechanism of the present invention; Figure 6 is a left side view of the hoisting mechanism of the single main beam of Figure 1;
图 7是平移机构的主视图;  Figure 7 is a front elevational view of the translation mechanism;
图 8是自动计算吊件的质心位置;  Figure 8 is an automatic calculation of the centroid position of the hanger;
图 9是自动分配各吊点的目标拉力值;  Figure 9 is the target pull value for automatically assigning each lifting point;
图 10是卷扬系统同步控制原理框图;  Figure 10 is a block diagram of the synchronous control principle of the winch system;
图 11是控制系统原理框图。  Figure 11 is a block diagram of the control system.
图中, 1、高主梁 2、低主梁 3、卷扬系统 4、平移机构 21、铰座 22、 液压平移机构 23、 油缸支持架 24、 不锈钢滑移轨道 25、 方钢导轨 26、 改性聚四氟乙烯板 31、 控制器 32、 控制系统 33、 载荷传感器 34、 位置 传感器 35、 上位机。  In the figure, 1, high main beam 2, low main beam 3, hoisting system 4, translation mechanism 21, hinge seat 22, hydraulic translation mechanism 23, cylinder support frame 24, stainless steel sliding track 25, square steel guide 26, modified The PTFE plate 31, the controller 32, the control system 33, the load sensor 34, the position sensor 35, and the host computer.
具体实施方式 detailed description
现结合 20000t X 125m吊钩式桥式起重机项目, 对本发明作进一步的具体 说明如下:  The present invention will be further described in detail with the 20000t X 125m hook-type overhead crane project as follows:
如图 1所示, 高主梁 1和低主梁 2分别布置在高低两个不同的混凝土基础 上,起升机构由每根主梁上的各六套卷扬系统 3即共 12套卷扬系统组成, 每套卷 扬系统 3由卷扬机、 钢丝绳、 导向滑轮、 定滑轮组、 动滑轮组等组成; 整个系 统的倍率为 40;每套卷扬系统包含 4个动滑轮组,每个动滑轮组控制 1个吊点。 卷扬机包括卷筒(包括钢丝绳压板)、 减速器、 制动器、 开式齿轮、 联轴器、 浮 动轴、 底座等部件, 即从与电机相连的联轴器到末级制动的整套机构; 卷扬机 上安装排绳机构, 能确保整个起升高度不乱绳; 卷扬机采用单联多层缠绕绳系。 卷扬机按图 3所示所示通过电机驱动卷筒完成每次升降循环, 每个卷扬系统控 制 4个吊点, 12套卷扬系统即共有 48个吊点,共同完成 2万吨载荷升降任务。 卷扬系统钢丝绳缠绕参见图 5。 As shown in Fig. 1, the high main beam 1 and the low main beam 2 are respectively arranged on two different concrete foundations, and the hoisting mechanism is hoisted by six sets of hoisting systems 3 on each main beam, that is, a total of 12 sets. The system consists of each hoisting system 3 consisting of a hoist, a wire rope, a guide pulley, a fixed pulley block, a movable pulley block, etc.; the whole system has a magnification of 40; each set of hoisting system includes 4 moving pulley blocks, and each moving pulley block controls 1 Lifting Point. Winch includes reel (including wire rope press plate), reducer, brake, open gear, coupling, float The moving shaft, the base and other components, that is, the coupling mechanism from the coupling connected to the motor to the final stage brake; the hoisting mechanism is installed on the hoisting machine to ensure that the entire lifting height is not tangled; the hoisting machine adopts a single multi-layer winding rope system. The hoist completes each lifting cycle through the motor-driven reel as shown in Figure 3. Each hoisting system controls 4 lifting points, and 12 sets of hoisting systems have a total of 48 lifting points to jointly complete the 20,000-ton load lifting task. . See Figure 5 for the winding of the hoisting system.
主梁采用变截面形式如图 3所示, 它是由上、 中、 下三箱型梁组成的高窄 复合梁如图 4所示, 其高宽比等于 4。  The main beam adopts a variable cross-section form as shown in Fig. 3. It is a high-narrow composite beam composed of upper, middle and lower three-box beams, as shown in Fig. 4, and its aspect ratio is equal to 4.
通过多吊点起重机起升钢丝绳防干涉布置如图 6所示, 避免了众多钢丝绳 干涉问题。 如图 1所示, 将卷扬机放到主梁盖板上面, 每根主梁的每端盖板上 面各布置 3套卷扬机; 每套卷扬机的钢丝绳沿主梁盖板的上部空间经一个固定 导向滑轮从主梁上盖板上的小开孔进入主梁内定滑轮组上, 然后缠绕到动滑轮 组上, 反复缠绕, 最后固定在定滑轮组的固定点上。  The anti-interference arrangement of the hoisting wire rope through the multi-lifting crane is shown in Fig. 6, which avoids the interference problem of many wire ropes. As shown in Figure 1, the hoist is placed on the main girder cover, and each set of hoisting machines is arranged on each of the end plates of each main beam; the wire rope of each hoist is passed along a fixed guide pulley in the upper space of the main girder cover. From the small opening on the upper cover of the main beam, enter the inner pulley set of the main beam, then wrap it onto the movable pulley block, repeatedly wrap it, and finally fix it on the fixed point of the fixed pulley block.
每端主梁上面的 3套卷扬机采用不同高度的支座, 使不同卷扬机卷筒钢丝 绳的出绳高度不同; 另外使主梁每端的 3套卷扬机的卷筒垂直中心线与导向滑 轮中心线的连线对主梁中心线形成 1个相同的小偏角, 为了保证钢丝绳在卷筒 和滑轮上的偏角不超过标准规定, 最终采用每端 3套卷扬机相对主梁中心线旋 转 1. 04度, 两端偏向相对,; 这样布置能使钢丝绳在空间形成交错布置, 既避 免钢丝绳间以及钢丝绳与主梁的干涉, 又使钢丝绳与卷扬机卷筒以及滑轮的偏 角符合标准。  The three sets of hoists on the main beam at each end adopt different heights of support, which makes the rope height of different hoist drum ropes different; in addition, the vertical centerline of the reel of the three sets of hoists at each end of the main beam is connected with the center line of the guide pulley. The line of the main beam of the main beam is formed by the same small yaw angle. In order to ensure that the yaw angle of the wire rope on the reel and the pulley does not exceed the standard, the third hoist at each end is rotated by 1.04 degrees with respect to the center line of the main beam. The two ends are opposite to each other; such arrangement enables the wire ropes to be staggered in space, avoiding interference between the wire ropes and the wire rope and the main beam, and making the deflection angle of the wire rope and the hoist drum and the pulley conform to the standard.
动滑轮组间连杆使每套卷扬系统所控制的 4组动滑轮组间保持固定距离的 连接, 它既可使 4个动滑轮组控制的 4个吊点的同步升降, 又能避免钢丝绳间 的干涉。  The linkage between the movable pulley sets maintains a fixed distance connection between the four sets of moving pulley blocks controlled by each set of winch systems, which can simultaneously raise and lower the four lifting points controlled by the four moving pulley blocks, and avoid interference between the wire ropes. .
通过起重机主梁双向自行式平移机构如图 7所示, 使低基础上的主梁 2上 能沿垂直于主梁轴向作水平双向移动, 以满足不同设备的吊点位置的不同。 所 述的平移机构包括用以承载主梁 2自重及载荷的铰座 21、 液压平移机构 22、 油 缸支持架 23、 不锈钢滑移轨道 24、 方钢导轨 25、 改性聚四氟乙烯板 26、 自锁 楔块夹紧机构组成。  Through the two-way self-propelled translation mechanism of the main beam of the crane, as shown in Fig. 7, the main beam 2 on the low foundation can be horizontally moved horizontally perpendicular to the axial direction of the main beam to meet the difference of the lifting point positions of different equipments. The translation mechanism includes a hinge 21 for carrying the weight and load of the main beam 2, a hydraulic translation mechanism 22, a cylinder support frame 23, a stainless steel sliding track 24, a square steel guide rail 25, a modified polytetrafluoroethylene plate 26, Self-locking wedge clamping mechanism.
例如, 当平移距离 ±7m时, 液压缸一次伸缩 14m不现实, 所以采用步进式 液压平移机构, 整套液压平移机构 22由液压系统、 电气系统以及支持架组成液 压系统中包括两个顶升油缸。 整套液压平移机构 22沿着一根方钢导轨 25进行 双向爬移, 每次推动主梁 0. 8m, 每次移动先通过一对自锁楔块夹紧机构夹紧方 钢导轨 25,另一对楔形块处于松驰状态,然后活塞杆推动油缸支持架 23带动主 梁平移, 推到 0. 8m时, 自锁楔块夹紧机构松开轨道 25, 液压泵反向供油使支持 架同方向平移 0. 8m, 自锁楔块夹紧机构再次夹紧方钢导轨 25, 活塞杆再次推动 油缸支持架 23带动主梁 2, 如此循环, 直到满足每次平移距离的要求。 当反向 平移时, 另外一对楔形块开始作用, 同样通过上述过程来实现反向平移。 由于主梁与土建基础存在相对滑移, 在土建预埋板表面粘一层镜面不锈钢 滑移轨道 24, 在主梁铰座 21下盖板底部固定一层改性聚四氟乙烯板 26, 这样 磨擦系数大大减小, 并且该材质压缩变形量小、 磨损率也比较低。 For example, when the translation distance is ±7m, it is unrealistic for the hydraulic cylinder to retract 14m at a time, so a stepping hydraulic translation mechanism is adopted. The whole hydraulic translation mechanism 22 is composed of a hydraulic system, an electric system and a support frame. The hydraulic system includes two jack-up cylinders. . The entire hydraulic translation mechanism 22 is carried along a square steel rail 25 Two-way crawling, each time pushing the main beam 0. 8m, each time the first clamping of the square steel rail 25 by a pair of self-locking wedge clamping mechanism, the other pair of wedge-shaped blocks are in a relaxed state, and then the piston rod pushes the cylinder to support The self-locking wedge clamping mechanism again. The self-locking wedge clamping mechanism is again rotated. The self-locking wedge clamping mechanism is again. By clamping the square steel rail 25, the piston rod pushes the cylinder support frame 23 again to drive the main beam 2, and so on, until the requirement of each translation distance is satisfied. When the translation is reversed, another pair of wedge blocks begin to act, and the reverse translation is also achieved by the above process. Due to the relative slip of the main beam and the foundation of the civil engineering, a mirrored stainless steel sliding track 24 is adhered to the surface of the prefabricated plate of the civil construction, and a modified polytetrafluoroethylene plate 26 is fixed at the bottom of the lower cover of the main beam hinge 21, so that The friction coefficient is greatly reduced, and the material has a small amount of compression deformation and a low wear rate.
通过多吊点起重机超静定系统电气控制系统实现起重机载荷的同步以及平 稳起升。 所述的电控系统采用 "自动计算被吊件质心、 合理分配各吊点的拉力、 吊件防倾翻平衡控制、 各机构线速度同步控制、 吊件水平自动控制"设计思路 和多种控制手段来解决了以上问题。  The crane load is synchronized and leveled up by the electric control system of the multi-point crane crane statically indeterminate system. The electronic control system adopts the design idea and various control of "automatically calculating the centroid of the hanging piece, reasonably distributing the pulling force of each lifting point, controlling the tilting prevention of the hanging piece, synchronizing the line speed of each mechanism, and automatically controlling the level of the hanging piece". Means to solve the above problems.
由 12套卷扬系统组成的起升机构超静定系统的电气控制方案如下:  The electrical control scheme for the hoisting mechanism of the hoisting mechanism consisting of 12 sets of hoisting systems is as follows:
( 1 ) 自动计算吊件质心 (见图 8)、 合理分配各吊点拉力 (见图 9) 在 "悬停模式"下通过 12个吊点的拉力传感器测出吊件在水平状态时的拉 力值, 见附图 9 中的实测拉力值, 控制系统将根据这些值自动计算出吊件质心 所在位置, 并按照等差数列的形式给各个吊点自动分配目标拉力值, 见图 9 中 分配拉力值, 这样就可以保证在起升过程中各个吊点拉力更加合理, 可以有效 防止倾翻。  (1) Automatically calculate the centroid of the lifting piece (see Figure 8), and reasonably distribute the pulling force of each lifting point (see Figure 9). Under the "hovering mode", the tension of the hanging piece in the horizontal state is measured by the tension sensor of 12 lifting points. Value, see the measured tensile force value in Figure 9, the control system will automatically calculate the position of the centroid of the lifting piece according to these values, and automatically assign the target pulling force value to each lifting point in the form of an arithmetic progression, as shown in Figure 9. The value, so as to ensure that the lifting force of each lifting point is more reasonable during the lifting process, and can effectively prevent tipping.
( 2 ) 多套起升机构的防倾翻平衡控制  (2) Anti-rollover balance control of multiple sets of hoisting mechanisms
控制系统通过对 12套起升机构载荷情况进行分析并进行合理分组, 自动计 算出吊件的质心位置, 并对每套起升机构进行合理力的分配。 在运行过程中各 吊点拉力控制作为另一个重要的附加控制手段, 控制系统通过拉力传感器检测 各个吊钩在运行过程中所承载的拉力, 一旦某个吊点拉力超出目标拉力值, 将 对该机构进行修正, 使其拉力值回到允许值范围内。 可以有效防止倾翻。  The control system automatically analyzes the load center of the 12 sets of lifting mechanisms and makes a reasonable grouping, automatically calculates the centroid position of the lifting parts, and distributes the rational force of each lifting mechanism. In the operation process, each lifting point tension control is another important additional control means. The control system detects the pulling force carried by each hook during the running process through the tension sensor. Once the lifting force of a lifting point exceeds the target pulling force value, the The mechanism corrects the tension value back to the allowable value range. Can effectively prevent tipping.
( 3 ) 12套起升机构速度同步控制 (见图 10)  (3) 12 sets of hoisting mechanism speed synchronization control (see Figure 10)
在联合起吊过程中各起升电机采用速度控制作为主给定, 速度同步控制作 为最基本的控制手段, 由于起升机构钢丝绳缠绕方式为多层缠绕, 针对某一电 机转速, 起升机构在每一层的线速度是不同的。 控制系统通过计算及与外部多 种检测手段配合, 按层的不同为变频器提供不同的速度给定信号, 可以确保每 套起升机构钢丝绳线速度一致。 In the joint lifting process, the hoisting motor adopts the speed control as the main reference, and the speed synchronous control as the most basic control means. Since the hoisting mechanism wire rope winding method is multi-layer winding, for a certain motor speed, the hoisting mechanism is The line speed of one layer is different. Control system through calculation and external The detection means cooperates to provide different speed reference signals for the frequency converter according to different layers, which can ensure the wire speed of each set of lifting mechanism is consistent.
(4) 吊件水平控制  (4) Lift level control
吊件水平控制作为附加控制手段, 控制系统通过位置检测编码器提供的位 移信号, 在起吊过程中实时检测各吊点的相对位置差, 当各起吊点构成的坐标 平面与悬停模式时记忆的坐标平面不平行, 且超过设定值时, 进行位置修正; 使吊件在运行过程中保持基本水平。  As the additional control means, the control system uses the displacement signal provided by the position detection encoder to detect the relative position difference of each lifting point in real time during the lifting process. When the coordinate plane and the hovering mode formed by each lifting point are memorized, When the coordinate planes are not parallel, and the set value is exceeded, the position correction is performed; the hanger is kept at a basic level during operation.
总之, 通过工业控制计算机平台, 按照上述电气控制方案的建立不同数学 控制程序, 经过大量复杂计算和逻辑控制, 实现各起升机构的同步稳定运行。  In short, through the industrial control computer platform, according to the above-mentioned electrical control scheme to establish different mathematical control procedures, after a large number of complex calculations and logic control, the synchronous operation of each lifting mechanism is realized.
在联合起吊的不同阶段采用不同的控制手段, 分为准备模式、 钢丝绳预张 紧模式、 悬停模式、 联合起吊模式。 在不同的控制模式下, 控制系统将采用不 同的控制手段, 并自动完成数据采集及运算、 功能判断以及数据修正等功能, 使控制系统达到高度自动化、 智能化。  Different control methods are adopted in different stages of joint lifting, which are divided into preparation mode, wire rope pretensioning mode, hover mode, and joint lifting mode. In different control modes, the control system will adopt different control methods, and automatically complete the functions of data acquisition and calculation, function judgment and data correction, so that the control system is highly automated and intelligent.
为实现以上目标, 本系统组合采用了以下现有先进技术:  In order to achieve the above objectives, the system combination uses the following existing advanced technologies:
( 1 )采用国际领先的可逆交流多传动变频调速控制系统来对每个电机实现 精确的速度和转矩控制。  (1) Using the world's leading reversible AC multi-drive variable frequency speed control system to achieve accurate speed and torque control for each motor.
(2)采用多组整流回馈单元并联运行技术的应用来满足大容量电机供电的 需求, 并达到节能效果。  (2) The application of parallel operation technology of multiple sets of rectification and feedback units is adopted to meet the demand of large-capacity motor power supply and achieve energy-saving effect.
(3)采用功能强大、 性能优异的 PLC作为核心控制系统, 综合工业以太网 络技术以及现场总线技术, 实现集中一分散式控制, 使得各种数据的采集、 运 算稳定快捷。  (3) Using powerful PLC with excellent performance as the core control system, integrated industrial Ethernet technology and fieldbus technology to achieve centralized and decentralized control, making various data collection and operation stable and fast.
以上所述, 仅为本发明较佳的具体实施方式, 但本发明的保护范围并不局 fe于此, 任何熟悉本技术领域的技术人员在本发明披露的技术范围内, 根据本 发明的技术方案及其发明构思加以等同替换或改变, 都应涵盖在本发明的保护 范围之内。  The above is only a preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art within the technical scope disclosed by the present invention, the technology according to the present invention The alternatives and modifications of the present invention and the inventive concept are intended to be included within the scope of the present invention.

Claims

CN2007007DF 权 利 要 求 CN2007007DF Claim
1、一种双主梁多吊点起重机, 包括主梁、起升机构、平移机构、 电控系统、 回转式维修起重机、 司机室、 锚定装置和防风系缆, 其特征在于: 1. A double main beam multi-lift crane comprising a main beam, a hoisting mechanism, a translation mechanism, an electric control system, a rotary maintenance crane, a driver's cab, an anchoring device and a windproof tether, characterized in that:
所述的主梁包括高低布置的双主梁(1、 2), 两主梁分别安放于高低两个混 凝土基础上, 两主梁之间无连接端梁; 所述的每个主梁通过锚定装置和防风系 缆加以整体固定; 每个主梁均采用变截面, 为三箱型梁组成的高窄复合梁; 所述的起升机构由多套卷扬系统 (3 )组成, 分别设置于两个主梁的两端; 每个主梁的每端分别布置一套以上卷扬系统 (3), 每套卷扬系统分别设置一个 以上的吊点, 并通过电控系统同步驱动上述全部吊点; 所述的卷扬系统上安装 排绳机构, 并采用单联多层缠绕绳系;  The main beam comprises two main beams (1, 2) arranged at a height of two, the two main beams are respectively placed on two concrete foundations, and there is no connecting end beam between the two main beams; each of the main beams passes through the anchor The fixing device and the windproof tether are integrally fixed; each main beam adopts a variable cross section, which is a high-narrow composite beam composed of three box-shaped beams; the lifting mechanism is composed of multiple sets of hoisting systems (3), respectively At each end of the two main beams; each end of each main beam is arranged with more than one set of hoisting system (3), each set of hoisting system is provided with more than one lifting point, and all of the above are synchronously driven by the electronic control system Hanging point; the hoisting system is provided with a rope arranging mechanism, and a single multi-layer winding rope system is adopted;
所述的平移机构是在低主梁(2)两端底部沿垂直主梁的轴向设置主梁自行 式双向平移机构 (4)。  The translation mechanism is a self-propelled bidirectional translation mechanism (4) for the main beam at the bottom of the lower main beam (2) along the axial direction of the vertical main beam.
2、根据权利要求 1所述的双主梁多吊点起重机, 其特征在于所述的高窄复 合型主梁的高宽比为 3〜5。  The double-girder multi-lifting crane according to claim 1, wherein said high-narrow composite main beam has an aspect ratio of 3 to 5.
3、 根据权利要求 1所述的双主梁多吊点起重机, 其特征在于所述的起升机 构由 12套卷扬系统组成, 每个主梁的每端布置三套, 每套卷扬系统分别设置 4 个吊点, 整机共 48个吊点。  3. The double main beam multi-lifting crane according to claim 1, wherein the hoisting mechanism is composed of 12 sets of hoisting systems, and each set of three ends of each main beam is arranged, each set of hoisting system Set 4 lifting points respectively, and the whole machine has a total of 48 lifting points.
4、 根据权利要求 1、 2或 3所述的双主梁多吊点起重机, 其特征在于所述 的电控系统是一种多吊点起重机超静定系统电气控制系统, 包括由变频器、 逆 变器、 通信模块和电动机组成的起升机构控制系统 (32)、 控制器 (31 )、 载荷 传感器 (33)、 位置传感器 (34)和上位机 (35),  4. The double main beam multi-lifting crane according to claim 1, 2 or 3, wherein the electronic control system is an electric control system for a multi-point crane crane statically indeterminate system, comprising a frequency converter, a hoisting mechanism control system (32), a controller (31), a load sensor (33), a position sensor (34), and a host computer (35) composed of an inverter, a communication module, and an electric motor,
所述的控制器负责同上位机通信接收控制指令、 返回现场信息, 同时控制 各起升机构运行、 接收传感器的反馈信号;  The controller is responsible for receiving the control command with the host computer, returning the on-site information, and controlling the feedback signals of the running and receiving sensors of each lifting mechanism;
所述的载荷传感器和位置传感器将各起升机构的承载重量和起吊高度信息 通过自身所带的通信模块传给控制器, 通过控制器的处理后调整各起升机构的 运行;  The load sensor and the position sensor transmit the load weight and the hoisting height information of each hoisting mechanism to the controller through the communication module carried by the hoisting mechanism, and adjust the operation of each hoisting mechanism by the processing of the controller;
其中控制器、 传感器、 起升机构都通过总线通信方式进行连接。  The controller, the sensor and the lifting mechanism are all connected by bus communication.
5、 根据权力要求 4所述的双主梁多吊点起重机, 其特征在于所述的控制器 为 PLC, 载荷传感器为称重传感器, 位置传感器为编码传感器。  5. The double main beam multi-lifting crane according to claim 4, wherein the controller is a PLC, the load sensor is a load cell, and the position sensor is a coded sensor.
PCT/CN2007/003423 2007-06-29 2007-12-03 Double main girder and multi hanging point crane WO2009003331A1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2010513610A JP5247799B2 (en) 2007-06-29 2007-12-03 Double main girder multi-point crane
KR1020107001721A KR101184874B1 (en) 2007-06-29 2007-12-03 Double mian girder and multi hanging point crane

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN200720013043.9 2007-06-29
CN2007100119379A CN101104501B (en) 2007-06-29 2007-06-29 Double main bear multiple hanging point crane
CNU2007200130439U CN201080415Y (en) 2007-06-29 2007-06-29 Double main beam multi-hanging point hoisting machine
CN200710011937.9 2007-06-29

Publications (1)

Publication Number Publication Date
WO2009003331A1 true WO2009003331A1 (en) 2009-01-08

Family

ID=40225700

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2007/003423 WO2009003331A1 (en) 2007-06-29 2007-12-03 Double main girder and multi hanging point crane

Country Status (4)

Country Link
JP (1) JP5247799B2 (en)
KR (1) KR101184874B1 (en)
RU (1) RU2442743C2 (en)
WO (1) WO2009003331A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6579877B2 (en) * 2015-09-15 2019-09-25 Ihi運搬機械株式会社 How to adjust the hanging height of a structure
JP7349122B2 (en) 2019-03-13 2023-09-22 三陽メリヤス株式会社 Manufacturing method of tubular knitted fabric

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2222154Y (en) * 1995-05-26 1996-03-13 陈登云 Hinged single-beam bridge like crane
JPH1192082A (en) * 1997-09-24 1999-04-06 Kitagawa Iron Works Co Ltd Lifting device for construction of bridge beam
US6023862A (en) * 1996-08-09 2000-02-15 Kci Konecranes International Plc Control system for rope bucket
WO2004074158A1 (en) * 2003-02-22 2004-09-02 Gottwald Port Technology Gmbh Bridge crane or gantry crane
CN1785781A (en) * 2005-11-29 2006-06-14 太原重型机械集团有限公司 Lifting mechanism and sling of large tonnage single hanging point crane

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5062875U (en) * 1973-10-13 1975-06-07
JPS5351001Y2 (en) * 1974-03-15 1978-12-06
JP3196393B2 (en) * 1993-01-18 2001-08-06 石川島播磨重工業株式会社 Stage suspension mechanism
JP2639889B2 (en) * 1993-09-24 1997-08-13 川重工事株式会社 Load management system for erection of heavy structures by floating crane
JPH07187569A (en) * 1993-12-27 1995-07-25 Sumitomo Heavy Ind Ltd Plural load blocks type crane device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2222154Y (en) * 1995-05-26 1996-03-13 陈登云 Hinged single-beam bridge like crane
US6023862A (en) * 1996-08-09 2000-02-15 Kci Konecranes International Plc Control system for rope bucket
JPH1192082A (en) * 1997-09-24 1999-04-06 Kitagawa Iron Works Co Ltd Lifting device for construction of bridge beam
WO2004074158A1 (en) * 2003-02-22 2004-09-02 Gottwald Port Technology Gmbh Bridge crane or gantry crane
CN1785781A (en) * 2005-11-29 2006-06-14 太原重型机械集团有限公司 Lifting mechanism and sling of large tonnage single hanging point crane

Also Published As

Publication number Publication date
RU2442743C2 (en) 2012-02-20
RU2010102934A (en) 2011-08-10
JP5247799B2 (en) 2013-07-24
KR101184874B1 (en) 2012-09-20
KR20100023972A (en) 2010-03-04
JP2010531793A (en) 2010-09-30

Similar Documents

Publication Publication Date Title
CN101104501B (en) Double main bear multiple hanging point crane
WO2009003333A1 (en) Electric control method for crane with multiple hoisted points
CN201254775Y (en) Opening and closing roof cover system
CN201351084Y (en) Dual-machine load walking type hydraulic numerical control cross cable crane
CN101786577B (en) Dual-machine loading-and-walking type hydraulic numerical control deck erection gantry and control system and control method
CN110104522B (en) Traction type construction lifter for folding roof beam and construction method thereof
CN203624951U (en) Hoister
CN101476287B (en) Construction method for carrying large box girder by tire type portal jib crane
CN102139832B (en) Gantry crane device with lengthways and transverse traveling functions and hoisting method
CN107244620A (en) Spliced road deck hoisting structure
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
WO2023082748A1 (en) Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device
CN101761031A (en) Continuous and perpendicular lifting apparatus for large segmental bridge floor beam
CN201713229U (en) Steel box girder cable-loaded crane for suspension bridge construction
WO2009003331A1 (en) Double main girder and multi hanging point crane
CN201080415Y (en) Double main beam multi-hanging point hoisting machine
WO2009003332A1 (en) Wire rope space anti-interference arrangement for crane with multiple hoisting points
CN203903823U (en) Modular boiler barrel lifting device
CN116062626A (en) Curtain wall hoisting equipment and hoisting method for crown part of super high-rise building tower
JP2010531793A5 (en)
CN112456348B (en) Heat absorber hoisting method
CN101381057B (en) Large-sized gantry crane
CN108178110A (en) A kind of deep-sea mining water surface supports pipeline to lay recovery system
CN113636467A (en) Rolling mill frame hoisting device
CN210915057U (en) Corner reducing construction platform for hoisting wind power prefabricated concrete tower barrel

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 07845785

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 2010513610

Country of ref document: JP

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 20107001721

Country of ref document: KR

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 2010102934

Country of ref document: RU

122 Ep: pct application non-entry in european phase

Ref document number: 07845785

Country of ref document: EP

Kind code of ref document: A1