WO2023082748A1 - Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device - Google Patents

Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device Download PDF

Info

Publication number
WO2023082748A1
WO2023082748A1 PCT/CN2022/113043 CN2022113043W WO2023082748A1 WO 2023082748 A1 WO2023082748 A1 WO 2023082748A1 CN 2022113043 W CN2022113043 W CN 2022113043W WO 2023082748 A1 WO2023082748 A1 WO 2023082748A1
Authority
WO
WIPO (PCT)
Prior art keywords
lifting
tower section
tower
installation
centralized control
Prior art date
Application number
PCT/CN2022/113043
Other languages
French (fr)
Chinese (zh)
Inventor
谭志国
高鹏
杨天冉
姚飞雄
吴国林
Original Assignee
中国长江三峡集团有限公司
中国三峡建工(集团)有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国长江三峡集团有限公司, 中国三峡建工(集团)有限公司 filed Critical 中国长江三峡集团有限公司
Publication of WO2023082748A1 publication Critical patent/WO2023082748A1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D1/00Rope, cable, or chain winding mechanisms; Capstans
    • B66D1/02Driving gear
    • B66D1/12Driving gear incorporating electric motors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D1/00Rope, cable, or chain winding mechanisms; Capstans
    • B66D1/28Other constructional details
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Definitions

  • the invention relates to the technical field of engineering construction, in particular to a device and method for vertically lifting and installing variable-diameter unbalanced load equipment.
  • the installation of fans and other equipment in the lifting method has two prominent difficulties: on the one hand, the fan tower is a variable-diameter tower, generally with a thin upper and thicker structure, which is not convenient for the arrangement of lifting equipment; on the other hand, the upper part of the fan Machine rooms, generators, blades and other equipment cannot achieve complete equal moment balance at the front and rear, which will bring the risk of unbalanced load during the lifting process.
  • This is a key problem that must be solved when the wind turbine is installed using the vertical lifting method. This patent solves the above problems well through innovative and reasonable design.
  • the present invention provides a vertical lifting and installation device for variable-diameter unbalanced load-type equipment to solve the above-mentioned problems.
  • a vertical lifting installation device for variable-diameter unbalanced load equipment which includes a track and a track-type transfer device installed on the track; a lifting frame, and the lifting frame is
  • the truss structure includes a plurality of pillars and installation rods connected to the upper part of the pillars, the lifting frame spans above the track; it also includes multiple groups of lifting centralized control devices installed in different directions on the outside of the lifting frame, the The lifting centralized control device is used to smoothly lift the variable-diameter unbalanced load equipment to the installation station after the track-type transfer device transfers the variable-diameter unbalanced load equipment to the lifting frame.
  • the track-type transfer device includes a transfer frame, the bottom of the transfer frame is equipped with rollers adapted to the track, and the top is provided with a plurality of support cylinders for fixing variable-diameter unbalanced load equipment.
  • the piston rod of the supporting oil cylinder is connected with the support tile, and the transfer frame is provided with a transfer frame hydraulic station and a transfer frame electric control box, and the transfer frame hydraulic station is electrically connected with the transfer frame; it also includes a rail clamp.
  • each group of the lifting centralized control devices includes three continuous stretching hydraulic hoists, a lifting hydraulic station that provides power for the three continuous stretching hydraulic hoists, and a lifting electric station that controls the lifting hydraulic station.
  • a plurality of fixed pulleys are arranged on the installation rod, and the fixed pulleys are used for the steel strand group of the continuous stretching hydraulic hoist to pass through and lift the variable-diameter unbalanced load equipment.
  • the continuous stretching hydraulic hoist includes a support base and a continuous stretching hydraulic jack hinged on the support base, and a steel strand group reel arranged behind the continuous stretching hydraulic jack , the continuous stretching hydraulic jack is connected to the lifting hydraulic station, and the motor of the steel strand group reel is connected to the lifting electric control box; in each group of lifting centralized control devices, one of the continuous stretching hydraulic hoist The wind rope is connected, and the other two continuous stretching hydraulic hoists are connected to the steel strand group, and the steel strand group of each continuous stretching hydraulic jack is connected to the anchor assembly.
  • the lifting frame includes three or four uprights, and the uprights are installed on both sides of the track, and the height of the installation rod is greater than the height of the rail-type transfer device; the installation rod is circular, A plurality of said fixed pulleys are equiangularly distributed on said installation rod.
  • the anchor assembly includes two groups of anchors sequentially connected to the steel strand group; the anchor includes a cylindrical shell, and also includes multiple groups of anchor seats that are evenly distributed in the shell. It is fixedly connected with the shell, and each group of anchor seats is equipped with anchor pieces and locking pieces; the connection method between the steel strand group and the anchor assembly is: after all steel strands pass through the anchor at the front end, any Two adjacent steel strands are respectively locked on different anchors.
  • the present invention also provides a method for vertically lifting and installing variable-diameter unbalanced load-type equipment, including the following steps:
  • S1 Auxiliary work before lifting: including foundation construction, fan base section installation, lifting frame installation, lifting centralized control device installation and commissioning;
  • S2 Wind turbine lifting assembly Install lifting points at equal angles in the circumferential direction of each tower section of the wind turbine tower, and assemble the third tower section, the second tower section, the first tower section and the upper part of the first tower section of the wind tower.
  • the fan machine room, generator and blades so that the steel strand group of one of the continuous stretching hydraulic hoists in each group of hoisting centralized control devices is connected to the third tower section, so that the other one of each group of hoisting centralized control devices is connected continuously
  • the steel strand group of the stretching hydraulic hoist is connected to the second tower section, so that the wind rope of the last continuous stretching hydraulic hoist in each group of lifting centralized control device is connected to the first tower section, and the lifting centralized control device is started
  • Lift the installed equipment as a whole over one tower section height so that the new tower section can be placed and installed.
  • the connection method between the steel strand group and the tower section is: after all the steel strands pass through the anchor at the front end, any Two adjacent steel strands are respectively
  • S5 wind turbine is connected to the foundation section: After the tower section connected to the foundation section is connected to other tower sections of the fan tower, after the installed wind turbine is raised by one tower section height, the tower section transfer frame is moved out of the lifting frame, and then, linkage Control the lifting centralized control device, slowly lower the installed tower section of the fan and the overall equipment, and connect the entire fan tower with the foundation section;
  • S2 is hoisted by a mobile crane, which specifically includes the following steps:
  • S2-1 Use the mobile crane to hoist the third tower section to the foundation section, and connect the steel strand group of one of the continuous stretching hydraulic hoists in each group of lifting centralized control devices to the third tower section, and connect the third tower section
  • the three-tower section adjusts the vertical and tightens the force of the steel strand group
  • S2-2 Enable the mobile crane to hoist the second tower section above the third tower section, connect and fix the second tower section and the third tower section coaxially, and continuously stretch the other one of each group of lifting centralized control devices
  • the steel strand group of the type hydraulic hoist is connected to the second tower section;
  • S2-3 Use the mobile crane to hoist the first tower section above the second tower section, connect and fix the first tower section and the second tower section coaxially, and continuously stretch the last one of each group of lifting centralized control devices
  • the wind rope of the type hydraulic hoist is connected to the first tower section.
  • S2 is carried out by hoisting using the installation device of the present invention, which specifically includes the following steps:
  • S2-1 first uses the transfer frame to transfer the second tower section to the installation position in the lifting frame, drives a continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the hoisting The lifting points are connected, tightened, and then the second tower section is lifted to exceed the clear height of the first tower section;
  • S2-2 uses the transfer frame to transfer the third tower section to the installation position in the lifting frame, drives another continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the tower section respectively. Lift the lifting point to connect and tighten, slowly lift the third tower section to the position where it fits with the second tower section, and fasten the second tower section to the third tower section;
  • the present invention has the following beneficial effects:
  • the installation is economical.
  • the device and method avoid the purchase of expensive large-scale crawler cranes, and the required installation equipment is general equipment, and the installation is economical. It has more advantages in the installation of the taller and heavier fan or tower equipment.
  • the large crawler crane hoisting method requires a large space for the installation and hoisting of the crawler crane, especially for the assembly of the boom of the large crawler crane, and the turning over of the tower section and the unloading of the truck by other cranes. Due to the small hoisting weight of all components, the device and method can be completed only by ordinary wheeled cranes, and do not require a large-scale crawler crane boom assembly site.
  • the multi-transfer frame can store part of the fan tower sections while installing, further reducing
  • the requirements for the site are greatly reduced, and auxiliary work such as the installation of large crawler cranes and the assembly of booms are greatly reduced; it has great advantages for the installation of wind turbines in mountainous areas, and the cost input and construction period of the site are greatly reduced.
  • this patent adopts the lifting steel strand to connect the lifting point to avoid the influence of the diameter change of the tower section, and the diameter change will only cause a slight change in the angle between the steel strand and the lifting point , because the hydraulic steel strand lifting equipment has a large lifting capacity margin, which can solve this problem well.
  • this patent adopts the multi-anchor vertical three-dimensional lifting method of the steel strand of the lifting cylinder on the one hand.
  • the method strengthens the stability and dynamic adjustment ability of the lifting process.
  • the overall verticality of the tower section can be automatically or manually adjusted at any time, which effectively overcomes the interference of eccentric loads. .
  • the installation and preparation can be operated in parallel, and the installation efficiency is high.
  • the device and method can complete the installation and tower section transfer preparation synchronously and in parallel, shorten the preparation time to a great extent, ensure the continuity of installation, and shorten the total installation time.
  • this device and method has a large margin of lifting capacity of the hydraulic steel strand, strong deviation correction and adjustment capabilities, and good synchronization of the hydraulic lifting device, which can reach millimeter level, and all dimensions of the lifting process are within a certain range.
  • the device and method of this patent divides the debugging into preliminary debugging and confirmatory debugging.
  • the preliminary debugging is completed when the fan is at a lower installation height, which facilitates the handling of faults and improves the debugging efficiency; the confirmatory debugging is completed after the fan is lifted.
  • the final inspection and confirmation are carried out, and it can be put into normal operation after being correct, which greatly improves the quality of debugging, increases safety, and advances the construction period.
  • the equipment is highly versatile.
  • the core equipment of this patent, the lifting frame and the centralized lifting control device are easy to transfer, highly versatile, and easy to maintain. They can be used not only in the installation of wind turbines and other tower equipment, but also in other engineering fields. Widely used, high utilization rate and good economy; unlike the original installation method, the super-large crawler crane has poor versatility. If it is used in the occasion of small lifting capacity, because it is difficult to install, dismantle and transfer, the gain outweighs the gain. Therefore, the utilization rate of ultra-large crawler cranes is very low, the maintenance cost is generally high, and the economy is often poor.
  • Fig. 1 is a schematic structural view of the transport rack in the present invention.
  • Fig. 2 is a structural schematic diagram of the lifting frame in the present invention.
  • Fig. 3 is a schematic diagram of an installation state of S2 in the method of the present invention.
  • Fig. 4 is a schematic diagram of another installation state of S2 in the method of the present invention.
  • Fig. 5 is a schematic diagram of another installation state of S2 in the method of the present invention.
  • Fig. 6 is a schematic diagram of an installation state of S3 in the method of the present invention.
  • Fig. 7 is a schematic diagram of another installation state of S3 in the method of the present invention.
  • Fig. 8 is a schematic diagram of the connection state of the steel strand group and the tower section in the present invention.
  • Fig. 9 is a schematic structural view of the lifting centralized control device in the present invention.
  • Fig. 10 is a schematic structural view of the anchor in the present invention.
  • Fig. 11 is a schematic structural view of the rail clamp in the present invention.
  • FIG. 1 and accompanying drawing 2 provide a kind of variable-diameter unbalanced load type equipment vertical lifting installation device, it comprises that it comprises track 10 and is installed on the track type transfer device on track 10 20; a lifting frame 30, the lifting frame 30 is a truss structure, including three pillars 31 and a mounting rod 32 connected to the upper part of the pillars 31, the lifting frame 30 spans above the track 10; There are multiple sets of lifting centralized control devices 40 on different positions outside the lifting frame 30.
  • each group of the lifting centralized control device 40 includes three continuous stretching hydraulic hoists 41, and a lifting hydraulic station 42 that provides power for the three continuous stretching hydraulic lifting machines 41, and a control lift hydraulic station 42.
  • the pulleys 33 are evenly distributed on the installation rod 32 at equal angles; the fixed pulley 33 is preferably in an angle-adjustable form, so as to adapt to the angle change of the steel strand.
  • the number and structural form of the hoisting frame pillars are matched with each other according to the comprehensive consideration of the overall weight of the hoisting fan, the design of the foundation geology and the bearing capacity of the embedded parts, and the capacity of the hoisting centralized control device.
  • the lower part of the lifting frame is at least slightly higher than the height of a tower section, and there are no horizontal braces or diagonal braces that affect the passage of the transfer frame in the direction of travel.
  • the lifting frame structure is preferably connected by pins and bolts, which is convenient for installation, disassembly and reuse.
  • Walkways, ladders and operating platforms are arranged on the structure of the lifting frame as required to ensure safe and convenient operation; the lifting frame is reliably installed on a solid foundation through the pre-buried foundation.
  • the hoisting frame, hoisting centralized control device, track, and foundation section are preferably jointly arranged and constructed so as to form an overall force bearing and simplify the structure.
  • the track-type transfer device 20 includes a transfer frame 21, the bottom of the transfer frame 21 is equipped with rollers 22 adapted to the track 10, and a plurality of rollers 22 for fixing variable-diameter unbalanced load equipment are arranged on the top.
  • the rail clamp 27 When it is transferred to a predetermined position, in order to facilitate the hoisting operation, the rail clamp 27 is firmly locked with the track 10 at this time to prevent the displacement of the rail-type transfer device 20 and bring potential safety hazards.
  • the specific structure of the rail clamp 27 is referring to accompanying drawing 11.
  • the continuous stretching hydraulic hoist 41 includes a support base 411 and a continuous stretching hydraulic jack 412 hinged on the support base 411, and is arranged on the continuous stretching hydraulic jack 412.
  • the steel strand group reel 413 at the rear of the jack 412, the continuous stretching hydraulic jack 412 is connected with the lifting hydraulic station 42, and the motor of the steel strand group reel 413 is connected with the lifting electric control box 43; each group of lifting In the centralized control device, one of the continuous stretching hydraulic hoists is connected to the wind rope 44, and the other two continuous stretching hydraulic hoists are connected to the steel strand group 45, and the steel strands of each continuous stretching hydraulic jack Connect the anchor components on the group.
  • a lifting centralized control device may be provided at each leg of the lifting frame, or a lifting centralized control device may be provided for several legs. Regardless of whether the hoisting centralized control device is installed separately or jointly, the hoisting electric control cabinet and the hoisting hydraulic station, as the driving control device of the hoisting centralized control device, can be selected separately or jointly. Connection, so as to carry out the linkage control during the lifting or lowering process of the fan tower section. Standardized container or frame structure is preferred to improve versatility and facilitate layout and transshipment.
  • the container or the frame can be a one-layer or multi-layer structure, which is reliably connected to the preset ground anchor point or the connection point of the lifting frame to withstand the tension during the wind turbine lifting process.
  • the lifting centralized control device can choose steel strands or steel wire ropes according to the use occasions, the reel is used to store steel strands or steel wire ropes, and the continuous stretching hydraulic jack is used to pull steel strands or steel wire ropes.
  • Steel strands are preferred. This patent is for For the convenience of description, they are all referred to as steel strands for short below.
  • the hinge or turntable is used to adjust the direction and angle of the oil cylinder according to the height of the lifting tower section and the angle of the steel strand.
  • the anchor assembly includes two groups of anchors 50 sequentially connected to the steel strand group; A plurality of groups of anchor seats 52, the anchor seats 52 are fixedly connected with the housing 51, and each group of anchor seats 52 is correspondingly provided with an anchor piece 53 and a locking piece 54; the connection mode between the steel strand group 45 and the anchor assembly is : After all the steel strands pass through the anchor at the front end, any two adjacent steel strands are respectively locked on different anchors.
  • the number of hoisting points on the tower also matches the number of anchors, and each set of continuous stretching hydraulic jacks is equipped with a steel strand tension detection device to synchronize the tension of each steel strand Detection and comparison, if the deviation from the design value is too large, it will alarm immediately for inspection and troubleshooting.
  • the present invention takes the installation of the wind power generator tower as an example, and introduces the installation method of the present invention.
  • the naming method of tower sections is named according to the order of fans from high to low, that is, the tower section where blades are installed It is the first tower section, followed by the second tower section, the third tower section...
  • the steel strand group is represented by a single straight line, which is actually distributed in a circle
  • the steel strand group formed by multiple steel strands those skilled in the art should know the layout form of the steel strand group used in conjunction with the continuous stretching hydraulic jack;
  • the wire groups are displayed in bold to facilitate understanding and distinguish the connection relationship between different steel strand groups and fan tower sections.
  • foundation construction includes lifting frame, lifting centralized control device, tower section transfer frame track, fan tower section in place, etc.
  • joint layout and joint construction are preferred, so as to reduce the engineering quantity, improve the stressed structure and improve reliability through joint force bearing.
  • the foundation section of the fan should be installed in place in advance to avoid difficulties in installation due to large interference in the later stage.
  • the lifting frame and the lifting centralized control device should be installed and debugged in place in advance to ensure that each device functions well.
  • S2 Fan lifting assembly Refer to attached drawings 2-5, install lifting points at equal angles in the circumferential direction of each tower section of the fan tower, and assemble the third tower section, the second tower section and the first tower section of the fan tower.
  • the fan machine room, generator and blades on the tower section and the upper part of the first tower section are connected to the steel strand group under tension during the installation of each tower section, so that one of the lifting centralized control devices in each group is continuously stretched
  • the steel strand group of the type hydraulic hoist is connected to the third tower section, so that the steel strand group of another continuous tension hydraulic hoist in each group of lifting centralized control device is connected to the second tower section, so that each group of lifting centralized control
  • the wind rope 44 of the last continuous stretching hydraulic hoist in the device is connected to the first tower section, and the hoisting centralized control device is activated to lift the installed equipment to the height of one tower section so that the new tower section can be placed and installed.
  • the connection method between the steel strand group and the tower section is as follows:
  • S3 new tower section transfer in place According to the number of groups of transfer frames selected, one tower section is hoisted for each transfer frame, and the support oil cylinders are respectively activated to make the support tiles push the tower sections tightly, and the tower sections are transported in sequence according to the assembly sequence Go to the next step in the lifting frame; according to the number of tower section transfer frames selected, hoist a tower section for each tower section transfer frame, and the tower section should be placed on the corresponding transfer frame in a vertical position according to the installation sequence of the tower sections.
  • the angle of the circumference of the tower section on the transfer frame should be reasonable, and should match the installation angle of the circumference of the previous tower section, so as to facilitate the alignment between the two tower sections and facilitate the lifting of the steel strands.
  • the group is connected with lifting lifting points.
  • the supporting cylinders of the transfer frame should be driven to tighten the tower section together to ensure that the tower section is in a stable vertical state, and then drive the transfer frame to move along the track to the installation position under the installed tower section, and then clamp the The rail device and the track are reliably locked, and the locked state is shown in Figure 11.
  • the transfer frame of the tower section can also be used in series with multiple sections. In this working condition, the transfer frame is connected by the hinge point of the transfer frame, and a set of control system can be shared for overall joint control.
  • the advantage of the combined use of multi-section tower section transfer frames is that loading multi-section towers at one time can make the lifting more continuous and efficient.
  • S4 new tower section connection and lifting refer to attached drawings 6 and 7, loosen the steel strand group connected to the second tower section from the hoisting point of the second tower section, and install it on the tower section transfer frame
  • the support tile and the tower section are loosened, and the new tower section is slowly lifted and the top of the new tower section is connected to the bottom of the third tower section;
  • the centralized control device is linked and controlled to lift the installed tower section and equipment as a whole. After a tower section height is steadily raised, another transfer frame equipped with a tower section is moved to the bottom of the installed tower section, and the rail clamp is locked with the track.
  • S5 wind turbine is connected to the foundation section: After the tower section connected to the foundation section is connected to other tower sections of the fan tower, after the installed wind turbine is raised by one tower section height, the tower section transfer frame is moved out of the lifting frame, and then, linkage Control the lifting centralized control device, slowly lower the fan tower section and equipment as a whole, slowly lower the fan tower section and equipment as a whole, accurately align and adjust the holes with the flange of the foundation section, and tighten the connecting bolts. The whole is connected with the foundation section. After this step is completed, the overall structure of the fan has been installed.
  • S7 Auxiliary device removal: Remove the lifting frame, lifting centralized control device and transfer frame, and the installation is complete.
  • the connection between the wind rope and the first tower section can be unhooked and dismantled by personnel from the manhole to the operation platform outside the tower section by means of lifting equipment.
  • On-site sub-control refers to sub-systems such as lifting centralized control device and tower section transfer frame, which have operation modes such as on-site equipment operation and on-site wireless remote control; summary general control refers to the lifting centralized control device and tower section transfer frame etc.
  • the signals of the sub-systems, as well as the signals of multiple other fan lifting devices are aggregated to the site or remote centralized control room, and the method of overall system control is carried out through the transmission of camera and sensor signals.
  • the overall control can also be automatically controlled or manually controlled according to program settings. , ensuring the safety and efficiency of the lifting process.
  • the device and method can also be used for fan removal, and the removal step is the reverse operation of the installation step.
  • an automatic verticality measuring device is installed on the fan tower section to ensure that the verticality deviation of the overall structure is within a reasonable range during the overall lifting process of the fan.
  • the verticality can be measured by mechanical, optical, or electronic methods. and other measurement methods.
  • a wind speed measurement device is installed on the fan tower section to measure the wind speed level during the wind turbine lifting process.
  • the lifting operation will be suspended in time.
  • device, and the measuring device equipped with this system can also be temporarily installed, and the measuring signal needs to be connected to the master control system.
  • the manhole of the tower section and the operating platform are used to facilitate the installation and removal of each lifting point of the steel strand.
  • this embodiment adopts the lifting steel strand to connect the lifting point so that it will not be affected by the diameter change of the tower section, and the diameter change will only cause a slight change in the angle between the steel strand and the lifting point. Changes, because the continuous stretching hydraulic hoist in this embodiment has a large margin of hoisting capacity, which can solve this problem well.
  • this patent adopts a continuous stretching hydraulic jack with multiple anchor points.
  • the vertical three-dimensional lifting method strengthens the stability and dynamic adjustment ability of the lifting process.
  • the overall verticality of the tower section can be automatically or manually adjusted at any time, effectively overcoming the eccentric load interference.
  • step S2 of the above embodiment is hoisted by a mobile crane, which specifically includes the following steps:
  • S2-1 Use the mobile crane to hoist the third tower section to the foundation section, and connect the steel strand group of one of the continuous stretching hydraulic hoists in each group of lifting centralized control devices to the third tower section, and connect the third tower section
  • the three-tower section adjusts the vertical and tightens the force of the steel strand group
  • S2-2 Enable the mobile crane to hoist the second tower section above the third tower section, connect and fix the second tower section and the third tower section coaxially, and continuously stretch the other one of each group of lifting centralized control devices
  • the steel strand group of the type hydraulic hoist is connected to the second tower section;
  • S2-3 Use the mobile crane to hoist the first tower section above the second tower section, connect and fix the first tower section and the second tower section coaxially, and continuously stretch the last one of each group of lifting centralized control devices
  • the wind rope of the type hydraulic hoist is connected to the first tower section.
  • the wind rope is connected to the wind wind lifting point of the first tower section of the fan through the lifting point; the end of each set of lifting rope device is connected to the same tower section through at least two vertical anchors, and the two sets of lifting centralized control devices are respectively connected to the upper and lower Wind tower section.
  • the first tower section is provided with a plurality of lifting points for lifting the wind
  • the other tower sections are provided with several groups of lifting points for lifting.
  • the strand ends should match where they hang.
  • step S2 in the above embodiment is hoisted by using the installation device of the present invention, which specifically includes the following steps:
  • S2-1 first uses the transfer frame to transfer the second tower section to the installation position in the lifting frame, drives a continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the hoisting The lifting points are connected, tightened, and then the second tower section is lifted to exceed the clear height of the first tower section;
  • S2-2 uses the transfer frame to transfer the third tower section to the installation position in the lifting frame, drives another continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the tower section respectively. Lift the lifting point to connect and tighten, slowly lift the third tower section to the position where it fits with the second tower section, and fasten the second tower section to the third tower section;
  • the preliminary debugging is carried out.
  • the advantage is that the debugging is carried out at a lower installation position, which is convenient for confirming the integrity and reliability of the installed equipment and for the maintenance of the faulty equipment.
  • the main debugging work can be done here After the stage is completed, only confirmatory debugging can be carried out after the overall installation of the fan is completed, which reduces the overall debugging workload, avoids high-altitude debugging, and reduces the difficulty and danger of debugging operations.
  • the continuous stretching hydraulic jack 37 is the equipment quoted in the standard DL/T 5400-2007 hydraulic building sliding formwork construction technical specification, and it is also the present invention disclosed in the Chinese patent application document with the publication number CN100424003C. There is equipment, so the specific structure of this existing equipment is not described in detail in the description of this patent, and those skilled in the art should know that it does not affect the realization of this patent.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

An apparatus for vertically lifting and installing a variable-diameter unbalanced-load device, the apparatus comprising: a track (10) and a track-type transport device (20) mounted on the track (10); and further comprising: a lifting frame (30), comprising a plurality of support columns (31) and, connected at the upper portions of the support columns, a mounting rod (32), wherein the lifting frame (30) is disposed transversely above the track (10); and further comprising: a plurality of groups of lifting centralized-control apparatuses (40) mounted at different orientations on the outer side of the lifting frame (30), wherein the lifting centralized-control apparatuses (40) are used, after the track-type transport device (20) transports a variable-diameter unbalanced-load device into the lifting frame (30), for stably lifting the variable-diameter unbalanced-load device to a mounting position. Additionally disclosed is a method for vertically lifting and installing a variable-diameter unbalanced-load device. The apparatus and the method are highly versatile, reduce installation difficulty, are successful at reducing risks such as severe weather, have a high safety coefficient, can adapt to the requirements of complex lifting working conditions such as variable-diameter tower sections and unbalanced loads, occupy a small amount of space, involve little auxiliary installation work, and are relatively economical in installation.

Description

一种变径非平衡载荷类设备垂直提升安装装置及方法A device and method for vertical lifting and installation of variable-diameter unbalanced load equipment 技术领域technical field
本发明涉及工程施工技术领域,尤其涉及一种变径非平衡载荷类设备垂直提升安装装置及方法。The invention relates to the technical field of engineering construction, in particular to a device and method for vertically lifting and installing variable-diameter unbalanced load equipment.
背景技术Background technique
发电风机等高塔筒式设备安装一直是设备安装中的难题,以往采用大型履带吊安装的方式,这就需要大型履带吊及其他中小型吊装设备配合,安装效率低,经济性也很差,随着风机技术的不断发展,风机塔筒越来越高,一味采用更大型的履带吊,提高履带吊的起吊高度和起重量将越来越困难,经济性也会越来越差。基于上述原因,需要一种效率更高、经济性更好、通用性更强的安装或拆除装置和方法。The installation of high-tower-type equipment such as power generation fans has always been a difficult problem in equipment installation. In the past, large-scale crawler cranes were used for installation, which required the cooperation of large crawler cranes and other small and medium-sized hoisting equipment. The installation efficiency was low and the economy was also poor. With the continuous development of wind turbine technology, the wind turbine tower is getting higher and higher, blindly adopting larger crawler cranes, it will become more and more difficult to increase the lifting height and lifting capacity of crawler cranes, and the economy will become worse and worse. Based on the above reasons, there is a need for an installation or removal device and method with higher efficiency, better economy and greater versatility.
但风机等设备采用提升方式安装具有两个突出的难点:一方面,风机塔筒为变径式塔筒,一般为上细下粗式结构,不便于提升设备的布置;另一方面,风机上部机房、发电机、叶片等设备无法做到前后部完全等力矩平衡,会给提升过程带来偏载风险,这都是风机采用垂直提升方法安装必须解决的关键问题。本专利通过创新性、合理的设计,很好解决了上述问题。However, the installation of fans and other equipment in the lifting method has two prominent difficulties: on the one hand, the fan tower is a variable-diameter tower, generally with a thin upper and thicker structure, which is not convenient for the arrangement of lifting equipment; on the other hand, the upper part of the fan Machine rooms, generators, blades and other equipment cannot achieve complete equal moment balance at the front and rear, which will bring the risk of unbalanced load during the lifting process. This is a key problem that must be solved when the wind turbine is installed using the vertical lifting method. This patent solves the above problems well through innovative and reasonable design.
发明内容Contents of the invention
针对现有技术中所存在的不足,本发明提供了一种变径非平衡载荷类设备垂直提升安装装置,以解决上述问题。Aiming at the deficiencies in the prior art, the present invention provides a vertical lifting and installation device for variable-diameter unbalanced load-type equipment to solve the above-mentioned problems.
为了解决上述技术问题,本发明采用的技术方案是:一种变径非平衡载荷类设备垂直提升安装装置,它包括轨道和安装在轨道上的轨道式转运装置;提升架,所述提升架为桁架结构,包括多个支柱和连接在支柱上部的安装杆,所述提升架横跨在所述轨道上方;还包括安装在所述提升架外侧不同方位上的多组提升集控装置,所述提升集控装置用于当轨道式转运装置将变径非平衡载荷类设备转运至提升架内后,将变径非平衡载荷类设备平稳提升至安装工位。In order to solve the above-mentioned technical problems, the technical solution adopted by the present invention is: a vertical lifting installation device for variable-diameter unbalanced load equipment, which includes a track and a track-type transfer device installed on the track; a lifting frame, and the lifting frame is The truss structure includes a plurality of pillars and installation rods connected to the upper part of the pillars, the lifting frame spans above the track; it also includes multiple groups of lifting centralized control devices installed in different directions on the outside of the lifting frame, the The lifting centralized control device is used to smoothly lift the variable-diameter unbalanced load equipment to the installation station after the track-type transfer device transfers the variable-diameter unbalanced load equipment to the lifting frame.
优选的方案中,所述轨道式转运装置包括转运架,所述转运架底部安装与所述轨道适配的滚轮,顶部设置多个用于固定变径非平衡载荷类设备的支撑油缸,所述支撑油缸的活塞杆上连接支撑瓦,转运架上设置转运架液压站和转运架电控箱,所述转运架液压站与所述转运架电控电连接;还包括夹轨器。In a preferred solution, the track-type transfer device includes a transfer frame, the bottom of the transfer frame is equipped with rollers adapted to the track, and the top is provided with a plurality of support cylinders for fixing variable-diameter unbalanced load equipment. The piston rod of the supporting oil cylinder is connected with the support tile, and the transfer frame is provided with a transfer frame hydraulic station and a transfer frame electric control box, and the transfer frame hydraulic station is electrically connected with the transfer frame; it also includes a rail clamp.
优选的方案中,每组所述提升集控装置包括三台连续拉伸式液压提升机,和为三台连续拉伸式液压提升机提供动力的提升液压站,和控制提升液压站的提升电控箱,所述安装 杆上设置多个定滑轮,所述定滑轮用于供连续拉伸式液压提升机的钢绞线组穿过并提升变径非平衡载荷类设备。In a preferred solution, each group of the lifting centralized control devices includes three continuous stretching hydraulic hoists, a lifting hydraulic station that provides power for the three continuous stretching hydraulic hoists, and a lifting electric station that controls the lifting hydraulic station. In the control box, a plurality of fixed pulleys are arranged on the installation rod, and the fixed pulleys are used for the steel strand group of the continuous stretching hydraulic hoist to pass through and lift the variable-diameter unbalanced load equipment.
优选的方案中,所述连续拉伸式液压提升机包括支撑底座和铰接在支撑底座上的连续拉伸式液压千斤顶,和设置在所述连续拉伸式液压千斤顶后方的钢绞线组卷盘,所述连续拉伸式液压千斤顶与提升液压站连接,所述钢绞线组卷盘的电机与提升电控箱连接;每组提升集控装置中,其中一台连续拉伸式液压提升机连接揽风绳,另两台连续拉伸式液压提升机连接钢绞线组,每台连续拉伸式液压千斤顶的钢绞线组上连接锚固组件。In a preferred solution, the continuous stretching hydraulic hoist includes a support base and a continuous stretching hydraulic jack hinged on the support base, and a steel strand group reel arranged behind the continuous stretching hydraulic jack , the continuous stretching hydraulic jack is connected to the lifting hydraulic station, and the motor of the steel strand group reel is connected to the lifting electric control box; in each group of lifting centralized control devices, one of the continuous stretching hydraulic hoist The wind rope is connected, and the other two continuous stretching hydraulic hoists are connected to the steel strand group, and the steel strand group of each continuous stretching hydraulic jack is connected to the anchor assembly.
优选的方案中,所述提升架包括三根或四根立柱,所述立柱均安装在轨道两侧,所述安装杆的高度大于所述轨道式转运装置的高度;所述安装杆呈圆形,多个所述定滑轮等角度均布在所述安装杆上。In a preferred solution, the lifting frame includes three or four uprights, and the uprights are installed on both sides of the track, and the height of the installation rod is greater than the height of the rail-type transfer device; the installation rod is circular, A plurality of said fixed pulleys are equiangularly distributed on said installation rod.
优选的方案中,所述锚固组件包括依次连接在钢绞线组上的两组锚固器;所述锚固器包括筒型壳体,还包括环形均布在壳体内的多组锚座,锚座与壳体固定连接,每组锚座对应的设置锚片和锁紧片;所述钢绞线组与所述锚固组件的连接方式为:所有钢绞线穿过位于前端的锚固器后,任意相邻的两根钢绞线分别锁紧在不同的锚固器上。In a preferred solution, the anchor assembly includes two groups of anchors sequentially connected to the steel strand group; the anchor includes a cylindrical shell, and also includes multiple groups of anchor seats that are evenly distributed in the shell. It is fixedly connected with the shell, and each group of anchor seats is equipped with anchor pieces and locking pieces; the connection method between the steel strand group and the anchor assembly is: after all steel strands pass through the anchor at the front end, any Two adjacent steel strands are respectively locked on different anchors.
本发明还提供了变径非平衡载荷类设备垂直提升安装方法,包括以下步骤:The present invention also provides a method for vertically lifting and installing variable-diameter unbalanced load-type equipment, including the following steps:
S1提升前辅助工作:包括基础施工、风机基础节安装、提升架安装、提升集控装置安装和调试;S1 Auxiliary work before lifting: including foundation construction, fan base section installation, lifting frame installation, lifting centralized control device installation and commissioning;
S2风机提升组装:在风机塔筒的每个塔节的圆周方向上等角度安装提升吊点,组装风机塔筒第三塔节、第二塔节和第一塔节以及第一塔节上部的风机机房、发电机和叶片,使每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,使每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节,使每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳连接第一塔节,启动提升集控装置将已安装设备整体提升超过一个塔节高度,以便新塔节的就位和安装,其中钢绞线组与塔节的连接方式为:所有钢绞线穿过位于前端的锚固器后,使任意相邻的两根钢绞线分别锁紧在不同的锚固器上;S2 Wind turbine lifting assembly: Install lifting points at equal angles in the circumferential direction of each tower section of the wind turbine tower, and assemble the third tower section, the second tower section, the first tower section and the upper part of the first tower section of the wind tower. The fan machine room, generator and blades, so that the steel strand group of one of the continuous stretching hydraulic hoists in each group of hoisting centralized control devices is connected to the third tower section, so that the other one of each group of hoisting centralized control devices is connected continuously The steel strand group of the stretching hydraulic hoist is connected to the second tower section, so that the wind rope of the last continuous stretching hydraulic hoist in each group of lifting centralized control device is connected to the first tower section, and the lifting centralized control device is started Lift the installed equipment as a whole over one tower section height, so that the new tower section can be placed and installed. The connection method between the steel strand group and the tower section is: after all the steel strands pass through the anchor at the front end, any Two adjacent steel strands are respectively locked on different anchors;
S3新塔节转运就位:根据选用转运架的组数,为每个转运架吊装一节塔节,并分别启动支撑油缸,使支撑瓦将塔节顶紧,按照组装顺序将塔节依次运输至提升架内,进入下一步;S3 new tower section transfer in place: According to the number of groups of transfer frames selected, one tower section is hoisted for each transfer frame, and the support oil cylinders are respectively activated to make the support tiles push the tower sections tightly, and the tower sections are transported in sequence according to the assembly sequence Go to the lifting frame and go to the next step;
S4新塔节连接和提升:将连接在第二塔节的钢绞线组松开与第二塔节提升吊点的连接,并安装至新塔节的提升吊点上,此组钢绞线组全部均匀受力后松开支撑瓦与塔节的支 撑,缓慢提升新塔节并将新塔节的顶部与第三塔节的底部连接;然后联动控制提升集控装置,将已安装塔节和设备整体稳步提升一个塔节高度后,将另一装有塔节的转运架移动至已安装塔节的下方,将夹轨器与轨道锁定,重复上述操作将风机塔筒全部连接完毕;S4 Connection and lifting of new tower section: loosen the connection of the steel strand group connected to the second tower section with the hoisting point of the second tower section, and install it on the hoisting point of the new tower section. After all the groups are evenly stressed, loosen the support of the supporting tiles and the tower section, slowly lift the new tower section and connect the top of the new tower section with the bottom of the third tower section; After steadily raising the height of one tower section with the equipment as a whole, move the transfer frame with another tower section to the bottom of the installed tower section, lock the rail clamp and the track, and repeat the above operations to complete the connection of the fan tower;
S5风机与基础节连接:当与基础节连接的塔节与风机塔筒的其它塔节连接后,将已安装风机整体提升一个塔节高度后,将塔节转运架移出提升架,然后,联动控制提升集控装置,将风机已安装塔节和设备整体缓慢下降,将风机塔筒整体与基础节连接;S5 wind turbine is connected to the foundation section: After the tower section connected to the foundation section is connected to other tower sections of the fan tower, after the installed wind turbine is raised by one tower section height, the tower section transfer frame is moved out of the lifting frame, and then, linkage Control the lifting centralized control device, slowly lower the installed tower section of the fan and the overall equipment, and connect the entire fan tower with the foundation section;
S6:风机确认性调试:进行风机各部件、设备进行调试;S6: Fan confirmatory debugging: carry out debugging of each component and equipment of the fan;
S7:辅助装置拆除:拆除提升架、提升集控装置和转运架,安装即全部完成。S7: Auxiliary device removal: Remove the lifting frame, lifting centralized control device and transfer frame, and the installation is complete.
优选的方案中,S2采用移动式起重机吊装进行,具体包括如下步骤:In the preferred solution, S2 is hoisted by a mobile crane, which specifically includes the following steps:
S2-1启用移动式起重机吊装第三塔节到基础节上,并将每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,将第三塔节调整垂直并绷紧钢绞线组受力;S2-1 Use the mobile crane to hoist the third tower section to the foundation section, and connect the steel strand group of one of the continuous stretching hydraulic hoists in each group of lifting centralized control devices to the third tower section, and connect the third tower section The three-tower section adjusts the vertical and tightens the force of the steel strand group;
S2-2启用移动式起重机吊装第二塔节到第三塔节上方,并将第二塔节与第三塔节同轴连接固定,并将每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节;S2-2 Enable the mobile crane to hoist the second tower section above the third tower section, connect and fix the second tower section and the third tower section coaxially, and continuously stretch the other one of each group of lifting centralized control devices The steel strand group of the type hydraulic hoist is connected to the second tower section;
S2-3启用移动式起重机吊装第一塔节到第二塔节上方,并将第一塔节与第二塔节同轴连接固定,并将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳连接第一塔节。S2-3 Use the mobile crane to hoist the first tower section above the second tower section, connect and fix the first tower section and the second tower section coaxially, and continuously stretch the last one of each group of lifting centralized control devices The wind rope of the type hydraulic hoist is connected to the first tower section.
优选的方案中,S2采用本发明安装装置吊装进行,具体包括如下步骤:In a preferred solution, S2 is carried out by hoisting using the installation device of the present invention, which specifically includes the following steps:
S2-1先用转运架将第二塔节转运至提升架内的安装位,驱动每组提升集控装置中一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,然后将第二塔节提升至超过一节塔节的净高;S2-1 first uses the transfer frame to transfer the second tower section to the installation position in the lifting frame, drives a continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the hoisting The lifting points are connected, tightened, and then the second tower section is lifted to exceed the clear height of the first tower section;
S2-2再用转运架将第三塔节转运至提升架内的安装位,驱动每组提升集控装置中另一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,缓慢将第三塔节提升至与第二塔节贴合的位置,将第二塔节与第三塔节连接紧固;S2-2 uses the transfer frame to transfer the third tower section to the installation position in the lifting frame, drives another continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the tower section respectively. Lift the lifting point to connect and tighten, slowly lift the third tower section to the position where it fits with the second tower section, and fasten the second tower section to the third tower section;
S2-3再用起重机将第一塔节吊至第二塔节上方,在起重机不松钩的状态下将第一塔节与第二塔节连接紧固,再将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳与第一塔节上连接、绷紧;S2-3 Then use the crane to hoist the first tower section above the second tower section, connect and fasten the first tower section and the second tower section under the condition that the crane does not loosen the hook, and then place each group of lifting centralized control device The wind rope of the last continuous stretching hydraulic hoist is connected and tightened to the first tower section;
S2-4在整体垂直稳定的状态下,进行风机机房、发电机和叶片的吊装和调整,安装完成后将可转动或可移动部件锁定。S2-4 Carry out the hoisting and adjustment of the fan machine room, generator and blades in the overall vertically stable state, and lock the rotatable or movable parts after the installation is completed.
优选的方案中,S2完成后,即风机主要功能部件安装完成后,先进行功能性调试,调试合格后再提升连接后续塔节。In the preferred solution, after S2 is completed, that is, after the main functional components of the fan are installed, the functional debugging is carried out first, and after the debugging is passed, the subsequent tower sections are lifted and connected.
相比于现有技术,本发明具有如下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
1、安装经济性好。本装置和方法避免了采购价格昂贵的大型履带吊,所需的安装设备均为通用性设备,安装经济性好。在越是高、越是重的风机或塔筒类设备的安装方面越有优势。1. The installation is economical. The device and method avoid the purchase of expensive large-scale crawler cranes, and the required installation equipment is general equipment, and the installation is economical. It has more advantages in the installation of the taller and heavier fan or tower equipment.
2、对场地占用少,安装辅助工作少。大型履带吊吊装方式,履带吊安装、吊装工作状态所需场地较大,特别是大型履带吊起重臂拼装,和由其它起重机配合进行塔节翻身、卸车等也需要较大的场地。本装置和方法因所有构件吊装重量均较小,仅需要普通轮式起重机即可完成,不需要大型履带吊的起重臂拼装场地,多转运架可以边安装边储存一部分风机塔节,进一步降低了对场地的要求,也大量减少了大型履带吊安装和起重臂拼装等辅助工作;对于在山区安装风机的情况具有很大的优势,大幅度减少了费用投入和场地施工工期。2. Occupies less space and less auxiliary work for installation. The large crawler crane hoisting method requires a large space for the installation and hoisting of the crawler crane, especially for the assembly of the boom of the large crawler crane, and the turning over of the tower section and the unloading of the truck by other cranes. Due to the small hoisting weight of all components, the device and method can be completed only by ordinary wheeled cranes, and do not require a large-scale crawler crane boom assembly site. The multi-transfer frame can store part of the fan tower sections while installing, further reducing The requirements for the site are greatly reduced, and auxiliary work such as the installation of large crawler cranes and the assembly of booms are greatly reduced; it has great advantages for the installation of wind turbines in mountainous areas, and the cost input and construction period of the site are greatly reduced.
3、能适应变径塔节和非平衡载荷等复杂提升工况的要求。因每节风机塔筒的直径均不一样,本专利采用提升钢绞线连接提升吊点即可不受塔节直径变化的影响,直径变化仅会导致钢绞线与提升吊点的角度发生稍许变化,因为液压钢绞线提升设备的提升能力富余量大,能很好解决此问题。对于风机上部机房、发电机、叶片等设备无法做到前后部完全等力矩平衡,给提升过程带来偏载风险的问题,本专利一方面采用提升油缸钢绞线多锚点竖向立体提升的方式强化了提升过程的稳定性和动态调整能力,另一方面,通过设置一组多点揽风液压钢绞线的方式,随时自动或手动调整塔节整体垂直度,有效克服了偏载的干扰。3. It can adapt to the requirements of complex lifting conditions such as variable-diameter tower sections and unbalanced loads. Because the diameter of each fan tower is different, this patent adopts the lifting steel strand to connect the lifting point to avoid the influence of the diameter change of the tower section, and the diameter change will only cause a slight change in the angle between the steel strand and the lifting point , because the hydraulic steel strand lifting equipment has a large lifting capacity margin, which can solve this problem well. For the problem that the upper machine room, generator, blade and other equipment of the fan cannot achieve complete equal moment balance at the front and rear parts, which brings the risk of unbalanced load during the lifting process, this patent adopts the multi-anchor vertical three-dimensional lifting method of the steel strand of the lifting cylinder on the one hand. The method strengthens the stability and dynamic adjustment ability of the lifting process. On the other hand, by setting up a group of multi-point wind-covering hydraulic steel strands, the overall verticality of the tower section can be automatically or manually adjusted at any time, which effectively overcomes the interference of eccentric loads. .
4、安装和准备可并行操作,安装效率高。本装置和方法可将安装和塔节转运准备同步并行完成,很大程度缩短了准备时间,确保了安装的连续性,缩短了总安装时间。4. The installation and preparation can be operated in parallel, and the installation efficiency is high. The device and method can complete the installation and tower section transfer preparation synchronously and in parallel, shorten the preparation time to a great extent, ensure the continuity of installation, and shorten the total installation time.
5、抗恶劣天气等风险能力强,安全系数大。原超大型履带吊吊装方式因高空作业,履带吊司机视线受限,不便观察,在突遇大风等恶劣天气情况下容易失稳发生安全事故和风险。本装置和方法相较于大型履带吊安装方式,因为液压钢绞线提升能力富裕度大、纠偏和调整能力强,并且液压提升装置同步性好,可达毫米级,提升过程各维度均处于可调、在控状态,如遇突发性强风天气,可快速将各钢绞线绷紧锁定,抗风险能力强,安全性大大提高,避免了大型履带吊高空吊装突遇大风落钩慢、容易倾覆的问题。5. Strong ability to resist bad weather and other risks, and large safety factor. Due to the high-altitude operation of the original ultra-large crawler crane hoisting method, the crawler crane driver's vision is limited and it is inconvenient to observe. In severe weather conditions such as sudden strong winds, it is easy to lose stability and cause safety accidents and risks. Compared with the large-scale crawler crane installation method, this device and method has a large margin of lifting capacity of the hydraulic steel strand, strong deviation correction and adjustment capabilities, and good synchronization of the hydraulic lifting device, which can reach millimeter level, and all dimensions of the lifting process are within a certain range. In the state of adjustment and control, in case of sudden strong winds, the steel strands can be quickly locked and tightened, with strong anti-risk ability and greatly improved safety, avoiding the slow and easy drop of the hook when the large crawler crane is hoisted in high winds. The overturning problem.
6、降低调试难度、提高调试效率。本专利的装置和方法将调试分为初步调试和确认 性调试,初步调试在风机处于较低安装高度阶段即完成,方便了故障的处理,提高了调试效率;确认性调试在风机提升完成后,风机投运前仅进行最后的检查、确认,无误后即可投入正常运行,大幅度提高了调试质量、增加了安全性、提前了工期。6. Reduce the difficulty of debugging and improve the efficiency of debugging. The device and method of this patent divides the debugging into preliminary debugging and confirmatory debugging. The preliminary debugging is completed when the fan is at a lower installation height, which facilitates the handling of faults and improves the debugging efficiency; the confirmatory debugging is completed after the fan is lifted. Before the fan is put into operation, only the final inspection and confirmation are carried out, and it can be put into normal operation after being correct, which greatly improves the quality of debugging, increases safety, and advances the construction period.
7、装备通用性强。本专利的核心设备,提升架和提升集控装置,转移方便、通用性很强、维保简单,不仅可以在风机安装,以及其他塔筒类设备安装中均可使用,还可以在其他工程领域广泛使用,使用率高和经济性好;不像原安装方法,超大型履带吊通用性很差,如用在小起重量的场合,因为其安拆转移困难,往往得不偿失。所以超大型履带吊使用率很低,维保成本一般高,经济性往往很差。7. The equipment is highly versatile. The core equipment of this patent, the lifting frame and the centralized lifting control device, are easy to transfer, highly versatile, and easy to maintain. They can be used not only in the installation of wind turbines and other tower equipment, but also in other engineering fields. Widely used, high utilization rate and good economy; unlike the original installation method, the super-large crawler crane has poor versatility. If it is used in the occasion of small lifting capacity, because it is difficult to install, dismantle and transfer, the gain outweighs the gain. Therefore, the utilization rate of ultra-large crawler cranes is very low, the maintenance cost is generally high, and the economy is often poor.
附图说明Description of drawings
图1为本发明中转运架的结构示意图。Fig. 1 is a schematic structural view of the transport rack in the present invention.
图2为本发明中提升架的结构示意图。Fig. 2 is a structural schematic diagram of the lifting frame in the present invention.
图3为本发明方法中S2的一种安装状态示意图。Fig. 3 is a schematic diagram of an installation state of S2 in the method of the present invention.
图4为本发明方法中S2的另一种安装状态示意图。Fig. 4 is a schematic diagram of another installation state of S2 in the method of the present invention.
图5为本发明方法中S2的另一种安装状态示意图。Fig. 5 is a schematic diagram of another installation state of S2 in the method of the present invention.
图6为本发明方法中S3的一种安装状态示意图。Fig. 6 is a schematic diagram of an installation state of S3 in the method of the present invention.
图7为本发明方法中S3的另一种安装状态示意图Fig. 7 is a schematic diagram of another installation state of S3 in the method of the present invention
图8为本发明中钢绞线组与塔节的的连接状态示意图。Fig. 8 is a schematic diagram of the connection state of the steel strand group and the tower section in the present invention.
图9为本发明中提升集控装置的结构示意图。Fig. 9 is a schematic structural view of the lifting centralized control device in the present invention.
图10为本发明中锚固器的结构示意图。Fig. 10 is a schematic structural view of the anchor in the present invention.
图11为本发明中夹轨器的结构示意图。Fig. 11 is a schematic structural view of the rail clamp in the present invention.
上述附图中:10、轨道;20、轨道式转运装置;21、转运架;22、滚轮;23、支撑油缸;24、支撑瓦;25、转运架液压站;26、转运架电控箱;27、夹轨器;30、提升架;31、支柱;32、安装杆;33、定滑轮;40、提升集控装置;41、连续拉伸式液压提升机;411、支撑底座;412、连续拉伸式液压千斤顶;413、钢绞线组线盘;42、提升液压站;43、提升电控箱;44、揽风绳;45、钢绞线组;50、锚固器;51、壳体;52、锚座;53、锚片;54、锁紧片。In the above drawings: 10, track; 20, track-type transfer device; 21, transfer frame; 22, roller; 23, support cylinder; 24, support tile; 25, transfer frame hydraulic station; 26, transfer frame electric control box; 27. Rail clamp; 30. Lifting frame; 31. Pillar; 32. Installation rod; 33. Fixed pulley; 40. Lifting centralized control device; 41. Continuous stretching hydraulic hoist; Stretching hydraulic jack; 413, steel strand group reel; 42, lifting hydraulic station; 43, lifting electric control box; 44, wind rope; 45, steel strand group; 50, anchor; 51, shell ; 52, anchor seat; 53, anchor sheet; 54, locking sheet.
具体实施方式Detailed ways
为了使本领域的技术人员更好地理解本发明的技术方案,下面结合具体实施例对本发明的优选实施方案进行描述,但是应当理解,附图仅用于示例性说明,不能理解为对本专利的限制;为了更好说明本实施例,附图某些部件会有省略、放大或缩小,并不代表实际 产品的尺寸;对于本领域技术人员来说,附图中某些公知结构及其说明可能省略是可以理解的;附图中描述位置关系仅用于示例性说明,不能理解为对本专利的限制。In order to enable those skilled in the art to better understand the technical solutions of the present invention, the preferred embodiments of the present invention will be described below in conjunction with specific examples, but it should be understood that the accompanying drawings are for illustrative purposes only, and cannot be interpreted as an explanation of this patent. Restrictions; In order to better illustrate this embodiment, some parts in the drawings will be omitted, enlarged or reduced, and do not represent the size of the actual product; for those skilled in the art, some known structures and their descriptions in the drawings may The omission is understandable; the positional relationship described in the drawings is only for illustrative purposes, and should not be construed as a limitation on this patent.
作为本发明的一种实施例,参阅附图1和附图2,提供一种变径非平衡载荷类设备垂直提升安装装置,它包括它包括轨道10和安装在轨道10上的轨道式转运装置20;提升架30,所述提升架30为桁架结构,包括三根支柱31和连接在支柱31上部的安装杆32,所述提升架30横跨在所述轨道10上方;还包括安装在所述提升架30外侧不同方位上的多组提升集控装置40,所述提升集控装置40用于当轨道式转运装置20将变径非平衡载荷类设备转运至提升架30内后,将变径非平衡载荷类设备平稳提升至安装工位。其中,每组所述提升集控装置40包括三台连续拉伸式液压提升机41,和为三台连续拉伸式液压提升机41提供动力的提升液压站42,和控制提升液压站42的提升电控箱43,所述安装杆32上设置多个定滑轮33,所述定滑轮33用于供连续拉伸式液压提升机41的钢绞线组穿过并提升变径非平衡载荷类设备,本实施例中,立柱31均安装在轨道10两侧,安装杆32的高度大于轨道式转运装置20的高度;安装杆呈圆形,也可以是方形等其他横截面形式,多个定滑轮33等角度均布在安装杆32上;定滑轮33优选采用角度可调整形式,以便适应钢绞线的角度变化。As an embodiment of the present invention, referring to accompanying drawing 1 and accompanying drawing 2, provide a kind of variable-diameter unbalanced load type equipment vertical lifting installation device, it comprises that it comprises track 10 and is installed on the track type transfer device on track 10 20; a lifting frame 30, the lifting frame 30 is a truss structure, including three pillars 31 and a mounting rod 32 connected to the upper part of the pillars 31, the lifting frame 30 spans above the track 10; There are multiple sets of lifting centralized control devices 40 on different positions outside the lifting frame 30. The lifting centralized control devices 40 are used to transfer the variable-diameter unbalanced load equipment to the lifting frame 30 after the rail-type transfer device 20 transfers the variable-diameter Unbalanced load equipment is smoothly lifted to the installation station. Wherein, each group of the lifting centralized control device 40 includes three continuous stretching hydraulic hoists 41, and a lifting hydraulic station 42 that provides power for the three continuous stretching hydraulic lifting machines 41, and a control lift hydraulic station 42. Elevate the electric control box 43, and a plurality of fixed pulleys 33 are arranged on the installation rod 32, and the fixed pulleys 33 are used for the steel strand group of the continuous stretching hydraulic hoist 41 to pass through and lift the variable-diameter unbalanced load class Equipment, in the present embodiment, column 31 is installed on both sides of track 10, and the height of mounting rod 32 is greater than the height of track-type transfer device 20; The pulleys 33 are evenly distributed on the installation rod 32 at equal angles; the fixed pulley 33 is preferably in an angle-adjustable form, so as to adapt to the angle change of the steel strand.
提升架支柱的数量和结构形式,根据提升风机整体重量、基础地质和埋件承载力设计、提升集控装置容量等综合考虑,互相匹配。为保证转运架的通过,提升架下部至少略高于一节塔节高度,转运架通行方向上不设置影响通行的横撑或斜撑。提升架结构优选采用销轴和螺栓连接,便于安拆和重复利用。提升架结构上根据需要布置走道、爬梯和操作平台,确保操作的安全性和便捷性;提升架通过预埋基础,可靠安装在坚实的基础上。提升架、提升集控装置、轨道、基础节优选联合布置、联合施工,以便形成整体受力,简化结构。The number and structural form of the hoisting frame pillars are matched with each other according to the comprehensive consideration of the overall weight of the hoisting fan, the design of the foundation geology and the bearing capacity of the embedded parts, and the capacity of the hoisting centralized control device. In order to ensure the passage of the transfer frame, the lower part of the lifting frame is at least slightly higher than the height of a tower section, and there are no horizontal braces or diagonal braces that affect the passage of the transfer frame in the direction of travel. The lifting frame structure is preferably connected by pins and bolts, which is convenient for installation, disassembly and reuse. Walkways, ladders and operating platforms are arranged on the structure of the lifting frame as required to ensure safe and convenient operation; the lifting frame is reliably installed on a solid foundation through the pre-buried foundation. The hoisting frame, hoisting centralized control device, track, and foundation section are preferably jointly arranged and constructed so as to form an overall force bearing and simplify the structure.
本实施例中,所述轨道式转运装置20包括转运架21,所述转运架21底部安装与所述轨道10适配的滚轮22,顶部设置多个用于固定变径非平衡载荷类设备的支撑油缸23,所述支撑油缸23的活塞杆上连接支撑瓦24,转运架21上设置转运架液压站25和转运架电控箱26,所述转运架液压站25与所述转运架电控26电连接;还包括夹轨器27,当转运到预定位置后,为便于吊装作业,此时利用夹轨器27与轨道10牢固锁定,防止轨道式转运装置20发生位移,带来安全隐患,夹轨器27的具体结构参阅附图11。In this embodiment, the track-type transfer device 20 includes a transfer frame 21, the bottom of the transfer frame 21 is equipped with rollers 22 adapted to the track 10, and a plurality of rollers 22 for fixing variable-diameter unbalanced load equipment are arranged on the top. A support cylinder 23, the piston rod of the support cylinder 23 is connected with a support tile 24, a transfer frame hydraulic station 25 and a transfer frame electric control box 26 are arranged on the transfer frame 21, and the transfer frame hydraulic station 25 is connected with the transfer frame electric control box. 26 electrical connection; it also includes a rail clamp 27. When it is transferred to a predetermined position, in order to facilitate the hoisting operation, the rail clamp 27 is firmly locked with the track 10 at this time to prevent the displacement of the rail-type transfer device 20 and bring potential safety hazards. The specific structure of the rail clamp 27 is referring to accompanying drawing 11.
本实施例中,参阅附图9,所述连续拉伸式液压提升机41包括支撑底座411和铰接在支撑底座411上的连续拉伸式液压千斤顶412,和设置在所述连续拉伸式液压千斤顶412后方的钢绞线组卷盘413,所述连续拉伸式液压千斤顶412与提升液压站42连接,所述钢 绞线组卷盘413的电机与提升电控箱43连接;每组提升集控装置中,其中一台连续拉伸式液压提升机连接揽风绳44,另两台连续拉伸式液压提升机连接钢绞线组45,每台连续拉伸式液压千斤顶的钢绞线组上连接锚固组件。In this embodiment, referring to accompanying drawing 9, the continuous stretching hydraulic hoist 41 includes a support base 411 and a continuous stretching hydraulic jack 412 hinged on the support base 411, and is arranged on the continuous stretching hydraulic jack 412. The steel strand group reel 413 at the rear of the jack 412, the continuous stretching hydraulic jack 412 is connected with the lifting hydraulic station 42, and the motor of the steel strand group reel 413 is connected with the lifting electric control box 43; each group of lifting In the centralized control device, one of the continuous stretching hydraulic hoists is connected to the wind rope 44, and the other two continuous stretching hydraulic hoists are connected to the steel strand group 45, and the steel strands of each continuous stretching hydraulic jack Connect the anchor components on the group.
在实施时,可为提升架每个支腿处各设置一个提升集控装置,也可几个支腿共同设置一个提升集控装置。无论分设还是共设提升集控装置,提升电控柜和提升液压站作为提升集控装置的驱动控制装置,均可选择分设或共设方式,即使是分设,也要通过控制线或网络进行信号连接,以便进行风机塔节顶升或下降过程中的联动控制。优选标准化集装箱或框架结构,提高通用性,方便布置和转运。集装箱或框架可以为一层或多层结构,通过与预设地锚点或提升架连接点可靠连接,以承受风机提升过程的拉力。提升集控装置可以根据使用场合选择钢绞线或钢丝绳,卷盘用于收纳钢绞线或钢丝绳,连续拉伸式液压千斤顶用于拉动钢绞线或钢丝绳,优选钢绞线方式,本专利为了描述方便以下均简称为钢绞线,支铰或转台用于根据提升塔节的高度而配合钢绞线的角度进行油缸方向和角度的调整。During implementation, a lifting centralized control device may be provided at each leg of the lifting frame, or a lifting centralized control device may be provided for several legs. Regardless of whether the hoisting centralized control device is installed separately or jointly, the hoisting electric control cabinet and the hoisting hydraulic station, as the driving control device of the hoisting centralized control device, can be selected separately or jointly. Connection, so as to carry out the linkage control during the lifting or lowering process of the fan tower section. Standardized container or frame structure is preferred to improve versatility and facilitate layout and transshipment. The container or the frame can be a one-layer or multi-layer structure, which is reliably connected to the preset ground anchor point or the connection point of the lifting frame to withstand the tension during the wind turbine lifting process. The lifting centralized control device can choose steel strands or steel wire ropes according to the use occasions, the reel is used to store steel strands or steel wire ropes, and the continuous stretching hydraulic jack is used to pull steel strands or steel wire ropes. Steel strands are preferred. This patent is for For the convenience of description, they are all referred to as steel strands for short below. The hinge or turntable is used to adjust the direction and angle of the oil cylinder according to the height of the lifting tower section and the angle of the steel strand.
上述实施例中,参阅附图10,所述锚固组件包括依次连接在钢绞线组上的两组锚固器50;所述锚固器50包括筒型壳体51,还包括环形均布在壳体内的多组锚座52,锚座52与壳体51固定连接,每组锚座52对应的设置锚片53和锁紧片54;所述钢绞线组45与所述锚固组件的连接方式为:所有钢绞线穿过位于前端的锚固器后,任意相邻的两根钢绞线分别锁紧在不同的锚固器上。In the above embodiment, referring to accompanying drawing 10, the anchor assembly includes two groups of anchors 50 sequentially connected to the steel strand group; A plurality of groups of anchor seats 52, the anchor seats 52 are fixedly connected with the housing 51, and each group of anchor seats 52 is correspondingly provided with an anchor piece 53 and a locking piece 54; the connection mode between the steel strand group 45 and the anchor assembly is : After all the steel strands pass through the anchor at the front end, any two adjacent steel strands are respectively locked on different anchors.
将钢绞线组与风机塔节连接时,先将尾端的锚固器与塔节上的提升吊点连接,然后调整前端的锚固器与尾端锚固器的相对距离,以适应风机塔筒上的提升吊点距离,然后将前端的锚固器与风机塔筒上的另一提升吊点采用插销铰接,在提升过程中,前端的锚固器可以转动一定角度,以适应在不同提升状态下的受力,达到稳定的目的。When connecting the steel strand group to the tower section of the wind turbine, first connect the anchor at the tail end to the hoisting point on the tower section, and then adjust the relative distance between the anchor at the front end and the anchor at the end end to adapt to the wind turbine tower. Raise the distance of the lifting point, and then hinge the anchor at the front end to another lifting point on the wind turbine tower with a bolt. During the lifting process, the anchor at the front end can rotate at a certain angle to adapt to the force under different lifting states , to achieve the purpose of stability.
本实施例中,塔架上的提升吊点的数量也与锚固器的数量相匹配,每套连续拉伸式液压千斤顶上均设置钢绞线拉力检测装置,以便对各钢绞线拉力进行同步检测和比对,发现与设计值偏差过大随即报警,以供检查和排除故障。In this embodiment, the number of hoisting points on the tower also matches the number of anchors, and each set of continuous stretching hydraulic jacks is equipped with a steel strand tension detection device to synchronize the tension of each steel strand Detection and comparison, if the deviation from the design value is too large, it will alarm immediately for inspection and troubleshooting.
本发明以风力发电机塔筒的安装为例,介绍本发明的安装方法,参阅附图3-附图8,按照提升前辅助工作、风机提升组装、新塔节转运节就位、新塔节连接和提升、风机与基础节连接、风机确认性调试、辅助装置拆除等步骤完成全部安装工作,本发明为便于理解,塔节的命名方式按照风机从高向低命名,即安装叶片的塔节为第一塔节,向下依次为第二塔节、第三塔节…,在本发明的附图中,为便于清晰展示,钢绞线组采用单一的直线表示,实际是成圆周分布的多跟钢绞线形成的钢绞线组,本领域技术人员应当知晓与连续拉伸式 液压千斤顶配套使用的钢绞线组布置形式;同时,本专利在不同的附图中对不同的钢绞线组进行加粗显示,以便于理解区分不同钢绞线组与风机塔节的连接关系。The present invention takes the installation of the wind power generator tower as an example, and introduces the installation method of the present invention. Referring to accompanying drawings 3 to 8, according to auxiliary work before lifting, fan lifting assembly, new tower section transfer section in place, new tower section Steps such as connection and lifting, connection between fan and foundation section, confirmatory debugging of fan, removal of auxiliary devices and other steps complete all installation work. In order to facilitate understanding in this invention, the naming method of tower sections is named according to the order of fans from high to low, that is, the tower section where blades are installed It is the first tower section, followed by the second tower section, the third tower section... in the accompanying drawings of the present invention, for the convenience of clear display, the steel strand group is represented by a single straight line, which is actually distributed in a circle For the steel strand group formed by multiple steel strands, those skilled in the art should know the layout form of the steel strand group used in conjunction with the continuous stretching hydraulic jack; The wire groups are displayed in bold to facilitate understanding and distinguish the connection relationship between different steel strand groups and fan tower sections.
现分步骤进行安装:Now install step by step:
S1提升前辅助工作:包括基础施工、风机基础节安装、提升架安装、提升集控装置安装和调试;基础施工包括提升架、提升集控装置、塔节转运架轨道、风机塔节就位等基础的施工,优选联合布置、联合施工,以通过联合受力减少工程量、改善受力结构、提高可靠性。应将风机基础节提前安装到位,避免后期因为干扰大,安装存在困难。应提前将提升架和提升集控装置安装和调试到位,确保各装置功能良好。S1 Auxiliary work before lifting: including foundation construction, wind turbine foundation section installation, lifting frame installation, lifting centralized control device installation and commissioning; foundation construction includes lifting frame, lifting centralized control device, tower section transfer frame track, fan tower section in place, etc. For foundation construction, joint layout and joint construction are preferred, so as to reduce the engineering quantity, improve the stressed structure and improve reliability through joint force bearing. The foundation section of the fan should be installed in place in advance to avoid difficulties in installation due to large interference in the later stage. The lifting frame and the lifting centralized control device should be installed and debugged in place in advance to ensure that each device functions well.
S2风机提升组装:参阅附图2-附图5,在风机塔筒的每个塔节的圆周方向上等角度安装提升吊点,组装风机塔筒第三塔节、第二塔节和第一塔节以及第一塔节上部的风机机房、发电机和叶片,安装每个塔节过程中与钢绞线组连接绷紧受力,使每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,使每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节,使每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳44连接第一塔节,启动提升集控装置将已安装设备整体提升超过一个塔节高度,以便新塔节的就位和安装,参阅附图10,其中钢绞线组与塔节的连接方式为:所有钢绞线穿过位于前端的锚固器后,使任意相邻的两根钢绞线分别锁紧在不同的锚固器上。S2 Fan lifting assembly: Refer to attached drawings 2-5, install lifting points at equal angles in the circumferential direction of each tower section of the fan tower, and assemble the third tower section, the second tower section and the first tower section of the fan tower. The fan machine room, generator and blades on the tower section and the upper part of the first tower section are connected to the steel strand group under tension during the installation of each tower section, so that one of the lifting centralized control devices in each group is continuously stretched The steel strand group of the type hydraulic hoist is connected to the third tower section, so that the steel strand group of another continuous tension hydraulic hoist in each group of lifting centralized control device is connected to the second tower section, so that each group of lifting centralized control The wind rope 44 of the last continuous stretching hydraulic hoist in the device is connected to the first tower section, and the hoisting centralized control device is activated to lift the installed equipment to the height of one tower section so that the new tower section can be placed and installed. Referring to accompanying drawing 10, the connection method between the steel strand group and the tower section is as follows: after all the steel strands pass through the anchor at the front end, any two adjacent steel strands are respectively locked on different anchors .
S3新塔节转运就位:根据选用转运架的组数,为每个转运架吊装一节塔节,并分别启动支撑油缸,使支撑瓦将塔节顶紧,按照组装顺序将塔节依次运输至提升架内,进入下一步;根据选用塔节转运架的组数,为每个塔节转运架吊装一节塔节,应结合塔节安装顺序将塔节在相应的转运架上以立式安装的方式就位,塔节在转运架上的圆周就位角度应合理,应与上一塔节的圆周安装角度相匹配,方便两塔节间的对位,也应方便各提升钢绞线组与提升吊点连接。在塔节转运架移动前应驱动转运架各支撑油缸共同顶紧塔节,确保塔节处于稳定的垂直状态后,再驱动转运架沿轨道运动至已安装塔节下方的安装位置后,将夹轨器与轨道可靠锁定,锁定状态参阅附图11。S3 new tower section transfer in place: According to the number of groups of transfer frames selected, one tower section is hoisted for each transfer frame, and the support oil cylinders are respectively activated to make the support tiles push the tower sections tightly, and the tower sections are transported in sequence according to the assembly sequence Go to the next step in the lifting frame; according to the number of tower section transfer frames selected, hoist a tower section for each tower section transfer frame, and the tower section should be placed on the corresponding transfer frame in a vertical position according to the installation sequence of the tower sections. The way of installation is in place, the angle of the circumference of the tower section on the transfer frame should be reasonable, and should match the installation angle of the circumference of the previous tower section, so as to facilitate the alignment between the two tower sections and facilitate the lifting of the steel strands. The group is connected with lifting lifting points. Before the tower section transfer frame moves, the supporting cylinders of the transfer frame should be driven to tighten the tower section together to ensure that the tower section is in a stable vertical state, and then drive the transfer frame to move along the track to the installation position under the installed tower section, and then clamp the The rail device and the track are reliably locked, and the locked state is shown in Figure 11.
塔节转运架还可多节串接联合使用,此工况转运架间采用转运架铰点连接,可共用一套控制系统进行整体联合控制。多节塔节转运架联合使用的优点在于,一次性装载多节塔架,可以让提升更连续、更高效。The transfer frame of the tower section can also be used in series with multiple sections. In this working condition, the transfer frame is connected by the hinge point of the transfer frame, and a set of control system can be shared for overall joint control. The advantage of the combined use of multi-section tower section transfer frames is that loading multi-section towers at one time can make the lifting more continuous and efficient.
S4新塔节连接和提升:参阅附图6和附图7,将连接在第二塔节的钢绞线组松开与第二塔节提升吊点的连接,并安装至塔节转运架上塔节的提升吊点上,此组钢绞线组全部均 匀受力后松开支撑瓦与塔节的支撑,缓慢提升新塔节并将新塔节的顶部与第三塔节的底部连接;然后联动控制提升集控装置,将已安装塔节和设备整体稳步提升一个塔节高度后,将另一装有塔节的转运架移动至已安装塔节的下方,将夹轨器与轨道锁定,重复上述操作将风机塔筒全部连接完毕;在同时启用多组转运架的情形下,装有塔节的转运架处于待安装状态,上一步骤已经吊装塔节的转运架也已移出提升架外,可以同步进行新塔节的吊装,通过同时作业,可以缩短准备和等待时间,保证连续安装。安装过程中如遇超标准大风等不适宜安装的恶劣天气,应立刻联动控制揽风绳油缸、两组提升绳油缸,确保整体已安装塔节处于垂直状态,绷紧各组钢绞线,即可保证整体结构的稳定。S4 new tower section connection and lifting: refer to attached drawings 6 and 7, loosen the steel strand group connected to the second tower section from the hoisting point of the second tower section, and install it on the tower section transfer frame On the hoisting point of the tower section, after all the steel strand groups are uniformly stressed, the support tile and the tower section are loosened, and the new tower section is slowly lifted and the top of the new tower section is connected to the bottom of the third tower section; Then the centralized control device is linked and controlled to lift the installed tower section and equipment as a whole. After a tower section height is steadily raised, another transfer frame equipped with a tower section is moved to the bottom of the installed tower section, and the rail clamp is locked with the track. , repeat the above operation to connect all the wind turbine towers; when multiple sets of transfer frames are enabled at the same time, the transfer frames with tower sections are in the state to be installed, and the transfer frames that have been hoisted with tower sections in the previous step have also been moved out of the lifting frame In addition, the hoisting of new tower sections can be carried out simultaneously. Through simultaneous operations, the preparation and waiting time can be shortened and continuous installation can be ensured. During the installation process, in case of severe weather that is not suitable for installation such as super-standard strong winds, you should immediately control the wind rope cylinder and the two sets of hoist rope cylinders to ensure that the overall installed tower section is in a vertical state, and tighten each group of steel strands, that is It can ensure the stability of the overall structure.
S5风机与基础节连接:当与基础节连接的塔节与风机塔筒的其它塔节连接后,将已安装风机整体提升一个塔节高度后,将塔节转运架移出提升架,然后,联动控制提升集控装置,将风机已安装塔节和设备整体缓慢下降,将风机已安装塔节和设备整体缓慢下降、准确与基础节法兰对孔和调整、连接螺栓和拧紧,将风机塔筒整体与基础节连接,此步骤完成后,风机整体结构已完成安装。S5 wind turbine is connected to the foundation section: After the tower section connected to the foundation section is connected to other tower sections of the fan tower, after the installed wind turbine is raised by one tower section height, the tower section transfer frame is moved out of the lifting frame, and then, linkage Control the lifting centralized control device, slowly lower the fan tower section and equipment as a whole, slowly lower the fan tower section and equipment as a whole, accurately align and adjust the holes with the flange of the foundation section, and tighten the connecting bolts. The whole is connected with the foundation section. After this step is completed, the overall structure of the fan has been installed.
S6:风机确认性调试:进行风机各部件、设备进行调试。S6: Fan confirmatory debugging: carry out debugging of each component and equipment of the fan.
S7:辅助装置拆除:拆除提升架、提升集控装置和转运架,安装即全部完成。揽风绳与第一塔节的连接可由人员从进人孔上至塔节外操作平台上,借助起吊设备进行脱钩、拆除。S7: Auxiliary device removal: Remove the lifting frame, lifting centralized control device and transfer frame, and the installation is complete. The connection between the wind rope and the first tower section can be unhooked and dismantled by personnel from the manhole to the operation platform outside the tower section by means of lifting equipment.
本专利优选采用现地分控+汇总总控相结合的控制方法。现地分控指提升集控装置和塔节转运架等分系统具备现地设备操作、现场无线遥控等操作模式;汇总总控指通过无线或有线方式将提升集控装置和塔节转运架等分系统的信号,以及多台其它风机提升装置信号汇总至现场或远程集控室,通过摄像头和各传感器信号的传输进行系统总体控制的方法,总控还可以是根据程序设置进行自动控制或人工控制,确保了提升过程的安全、高效。This patent preferably adopts a control method combining local sub-control + aggregated overall control. On-site sub-control refers to sub-systems such as lifting centralized control device and tower section transfer frame, which have operation modes such as on-site equipment operation and on-site wireless remote control; summary general control refers to the lifting centralized control device and tower section transfer frame etc. The signals of the sub-systems, as well as the signals of multiple other fan lifting devices are aggregated to the site or remote centralized control room, and the method of overall system control is carried out through the transmission of camera and sensor signals. The overall control can also be automatically controlled or manually controlled according to program settings. , ensuring the safety and efficiency of the lifting process.
本装置和方法也可用于风机拆除,拆除步骤为安装步骤的逆操作。The device and method can also be used for fan removal, and the removal step is the reverse operation of the installation step.
本实施例中,在风机塔节上安装垂直度自动测量装置,用于在风机整体提升过程中保证整体结构垂直度偏差处于合理范围内,测量垂直度可以采用机械式、光学仪器式、电子式等测量方式。In this embodiment, an automatic verticality measuring device is installed on the fan tower section to ensure that the verticality deviation of the overall structure is within a reasonable range during the overall lifting process of the fan. The verticality can be measured by mechanical, optical, or electronic methods. and other measurement methods.
在本实施例中,在风机塔节上安装风速测量装置,用于测量在风机提升过程中的风速等级,当出现风速过大的情况,及时暂停提升作业,风速测量装置可以使用风机自带的装置,也可临时安装本系统配备的测量装置,需将测量信号接入总控系统。塔节进人孔和操作平台用于方便挂装和拆除钢绞线各吊点。In this embodiment, a wind speed measurement device is installed on the fan tower section to measure the wind speed level during the wind turbine lifting process. When the wind speed is too high, the lifting operation will be suspended in time. device, and the measuring device equipped with this system can also be temporarily installed, and the measuring signal needs to be connected to the master control system. The manhole of the tower section and the operating platform are used to facilitate the installation and removal of each lifting point of the steel strand.
因每节风机塔筒的直径均不一样,本实施例采用提升钢绞线连接提升吊点即可不受塔节直径变化的影响,直径变化仅会导致钢绞线与提升吊点的角度发生稍许变化,因本实施例中连续拉伸式液压提升机的提升能力富余量大,能很好解决此问题。Because the diameter of each wind turbine tower is different, this embodiment adopts the lifting steel strand to connect the lifting point so that it will not be affected by the diameter change of the tower section, and the diameter change will only cause a slight change in the angle between the steel strand and the lifting point. Changes, because the continuous stretching hydraulic hoist in this embodiment has a large margin of hoisting capacity, which can solve this problem well.
另外,对于风机上部的机房、发电机、叶片等设备无法做到前后部完全等力矩平衡布置,给提升过程带来偏载风险的问题,本专利一方面采用连续拉伸式液压千斤顶多锚点竖向立体提升的方式强化了提升过程的稳定性和动态调整能力,另一方面,通过设置一组多点揽风液压钢绞线的方式,随时自动或手动调整塔节整体垂直度,有效克服了偏载的干扰。In addition, for the machine room, generator, blades and other equipment on the upper part of the fan, the front and rear parts cannot be arranged in a completely equal moment balance, which brings the risk of unbalanced load to the lifting process. On the one hand, this patent adopts a continuous stretching hydraulic jack with multiple anchor points. The vertical three-dimensional lifting method strengthens the stability and dynamic adjustment ability of the lifting process. On the other hand, by setting up a group of multi-point wind-covering hydraulic steel strands, the overall verticality of the tower section can be automatically or manually adjusted at any time, effectively overcoming the eccentric load interference.
作为本发明的一种优选实施例,上述实施例步骤S2采用移动式起重机吊装进行,具体包括如下步骤:As a preferred embodiment of the present invention, step S2 of the above embodiment is hoisted by a mobile crane, which specifically includes the following steps:
S2-1启用移动式起重机吊装第三塔节到基础节上,并将每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,将第三塔节调整垂直并绷紧钢绞线组受力;S2-1 Use the mobile crane to hoist the third tower section to the foundation section, and connect the steel strand group of one of the continuous stretching hydraulic hoists in each group of lifting centralized control devices to the third tower section, and connect the third tower section The three-tower section adjusts the vertical and tightens the force of the steel strand group;
S2-2启用移动式起重机吊装第二塔节到第三塔节上方,并将第二塔节与第三塔节同轴连接固定,并将每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节;S2-2 Enable the mobile crane to hoist the second tower section above the third tower section, connect and fix the second tower section and the third tower section coaxially, and continuously stretch the other one of each group of lifting centralized control devices The steel strand group of the type hydraulic hoist is connected to the second tower section;
S2-3启用移动式起重机吊装第一塔节到第二塔节上方,并将第一塔节与第二塔节同轴连接固定,并将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳连接第一塔节。S2-3 Use the mobile crane to hoist the first tower section above the second tower section, connect and fix the first tower section and the second tower section coaxially, and continuously stretch the last one of each group of lifting centralized control devices The wind rope of the type hydraulic hoist is connected to the first tower section.
揽风绳通过吊点与风机第一塔节的揽风吊点连接;每套提升绳装置末端通过至少两个竖向锚固器分别与同一塔节连接,2套提升集控装置分别连接上下个风机塔节。与其对应,第一塔节上设置有多个揽风吊点,其它塔节上设置有若干组提升吊点,揽风绳吊点与提升吊点在塔节圆周上按等角度均匀分布,与钢绞线端头应悬挂的位置相匹配。The wind rope is connected to the wind wind lifting point of the first tower section of the fan through the lifting point; the end of each set of lifting rope device is connected to the same tower section through at least two vertical anchors, and the two sets of lifting centralized control devices are respectively connected to the upper and lower Wind tower section. Correspondingly, the first tower section is provided with a plurality of lifting points for lifting the wind, and the other tower sections are provided with several groups of lifting points for lifting. The strand ends should match where they hang.
作为本发明的一种优选实施例,上述实施例中步骤S2采用本发明安装装置吊装进行,具体包括如下步骤:As a preferred embodiment of the present invention, step S2 in the above embodiment is hoisted by using the installation device of the present invention, which specifically includes the following steps:
S2-1先用转运架将第二塔节转运至提升架内的安装位,驱动每组提升集控装置中一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,然后将第二塔节提升至超过一节塔节的净高;S2-1 first uses the transfer frame to transfer the second tower section to the installation position in the lifting frame, drives a continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the hoisting The lifting points are connected, tightened, and then the second tower section is lifted to exceed the clear height of the first tower section;
S2-2再用转运架将第三塔节转运至提升架内的安装位,驱动每组提升集控装置中另一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,缓慢将第三塔节提升至与第二塔节贴合的位置,将第二塔节与第三塔节连接紧固;S2-2 uses the transfer frame to transfer the third tower section to the installation position in the lifting frame, drives another continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the tower section respectively. Lift the lifting point to connect and tighten, slowly lift the third tower section to the position where it fits with the second tower section, and fasten the second tower section to the third tower section;
S2-3再用起重机将第一塔节吊至第二塔节上方,在起重机不松钩的状态下将第一塔节与第二塔节连接紧固,再将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳与第一塔节上连接、绷紧;S2-3 Then use the crane to hoist the first tower section above the second tower section, connect and fasten the first tower section and the second tower section under the condition that the crane does not loosen the hook, and then place each group of lifting centralized control device The wind rope of the last continuous stretching hydraulic hoist is connected and tightened to the first tower section;
S2-4在整体垂直稳定的状态下,进行风机机房、发电机和叶片的吊装和调整,安装完成后将可转动或可移动部件锁定。S2-4 Carry out the hoisting and adjustment of the fan machine room, generator and blades in the overall vertically stable state, and lock the rotatable or movable parts after the installation is completed.
作为本发明的一种优选实施例,本实施例在S2完成后,即风机主要功能部件安装完成后,先进行功能性调试,调试合格后再提升连接后续塔节。As a preferred embodiment of the present invention, in this embodiment, after S2 is completed, that is, after the main functional components of the wind turbine are installed, functional debugging is carried out first, and after the debugging is passed, the subsequent tower section is lifted and connected.
上述实施例,S2完成后,即进行初步调试,好处在于在较低的安装部位进行调试,便于确认安装设备的完好性和可靠性,方便对故障设备的维修,主要的调试工作均可在此阶段完成,在风机整体完成安装后只进行确认性调试即可,减少了总体调试的工作量,也避免高空调试,降低调试作业的难度和危险性。In the above embodiment, after the completion of S2, the preliminary debugging is carried out. The advantage is that the debugging is carried out at a lower installation position, which is convenient for confirming the integrity and reliability of the installed equipment and for the maintenance of the faulty equipment. The main debugging work can be done here After the stage is completed, only confirmatory debugging can be carried out after the overall installation of the fan is completed, which reduces the overall debugging workload, avoids high-altitude debugging, and reduces the difficulty and danger of debugging operations.
在本发明的描述中,连续拉伸式液压千斤顶37为标准DL/T 5400—2007水工建筑物滑动模板施工技术规范中引用的设备,也是公开号为CN100424003C的中国专利申请文件中公开的现有设备,故本专利的描述中对该现有设备未赘述其具体结构,本领域技术人员应当知晓其不影响本专利的实现。In the description of the present invention, the continuous stretching hydraulic jack 37 is the equipment quoted in the standard DL/T 5400-2007 hydraulic building sliding formwork construction technical specification, and it is also the present invention disclosed in the Chinese patent application document with the publication number CN100424003C. There is equipment, so the specific structure of this existing equipment is not described in detail in the description of this patent, and those skilled in the art should know that it does not affect the realization of this patent.
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solutions of the present invention without limitation. Although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solutions of the present invention can be carried out Modifications or equivalent replacements without departing from the spirit and scope of the technical solution of the present invention shall be covered by the claims of the present invention.

Claims (10)

  1. 一种变径非平衡载荷类设备垂直提升安装装置,其特征是,包括:A vertical lifting and installation device for variable-diameter unbalanced load equipment, characterized in that it includes:
    轨道和安装在轨道上的轨道式转运装置;Rails and rail-type transfer devices mounted on rails;
    提升架,所述提升架为桁架结构,包括多个支柱和连接在支柱上部的安装杆,所述提升架横跨在所述轨道上方;还包括A lifting frame, the lifting frame is a truss structure, including a plurality of pillars and a mounting rod connected to the upper part of the pillars, and the lifting frame spans above the track; also includes
    安装在所述提升架外侧不同方位上的多组提升集控装置,所述提升集控装置用于当轨道式转运装置将变径非平衡载荷类设备转运至提升架内后,将变径非平衡载荷类设备平稳提升至安装工位。Multiple sets of lifting centralized control devices installed on different positions outside the lifting frame, the lifting centralized control device is used to transfer the variable diameter non-balanced load equipment to the lifting frame after the rail-type transfer device transfers the variable diameter non-balanced load equipment Balanced load equipment is smoothly lifted to the installation station.
  2. 根据权利要求1所述的一种变径非平衡载荷类设备垂直提升安装装置,其特征是:所述轨道式转运装置包括转运架,所述转运架底部安装与所述轨道适配的滚轮,顶部设置多个用于固定变径非平衡载荷类设备的支撑油缸,所述支撑油缸的活塞杆上连接支撑瓦,转运架上设置转运架液压站和转运架电控箱,所述转运架液压站与所述转运架电控电连接;还包括夹轨器。According to claim 1, a vertical lifting installation device for variable-diameter unbalanced load-type equipment is characterized in that: the rail-type transfer device includes a transfer frame, and the bottom of the transfer frame is equipped with rollers adapted to the rails, The top is provided with a plurality of support cylinders for fixing variable-diameter unbalanced load equipment. The piston rods of the support cylinders are connected with support tiles. The transfer frame hydraulic station and the transfer frame electric control box are installed on the transfer frame. The transfer frame hydraulic pressure The station is electrically controlled and electrically connected with the transfer rack; it also includes a rail clamp.
  3. 根据权利要求1所述的一种变径非平衡载荷类设备垂直提升安装装置,其特征是:每组所述提升集控装置包括三台连续拉伸式液压提升机,和为三台连续拉伸式液压提升机提供动力的提升液压站,和控制提升液压站的提升电控箱,所述安装杆上设置多个定滑轮,所述定滑轮用于供连续拉伸式液压提升机的钢绞线组穿过并提升变径非平衡载荷类设备。According to claim 1, a vertical lifting installation device for variable-diameter unbalanced load-type equipment is characterized in that: each set of lifting centralized control devices includes three continuous tension hydraulic hoists, and three continuous tension hydraulic hoists The lifting hydraulic station powered by the extension hydraulic hoist, and the lifting electric control box controlling the lifting hydraulic station, a plurality of fixed pulleys are arranged on the installation rod, and the fixed pulleys are used for the steel of the continuous stretching hydraulic hoist. The twisted wire group passes through and lifts the variable diameter unbalanced load type equipment.
  4. 根据权利要求3所述的一种变径非平衡载荷类设备垂直提升安装装置,其特征是:所述连续拉伸式液压提升机包括支撑底座和铰接在支撑底座上的连续拉伸式液压千斤顶,和设置在所述连续拉伸式液压千斤顶后方的钢绞线组卷盘,所述连续拉伸式液压千斤顶与提升液压站连接,所述钢绞线组卷盘的电机与提升电控箱连接;每组提升集控装置中,其中一台连续拉伸式液压提升机连接揽风绳,另两台连续拉伸式液压提升机连接钢绞线组,每台连续拉伸式液压千斤顶的钢绞线组上连接锚固组件。According to claim 3, a device for vertical lifting and installation of variable-diameter unbalanced load-type equipment is characterized in that: the continuous stretching hydraulic lift includes a supporting base and a continuous stretching hydraulic jack hinged on the supporting base , and the steel strand group reel arranged at the rear of the continuous stretching hydraulic jack, the continuous stretching hydraulic jack is connected to the lifting hydraulic station, the motor of the steel strand group reel is connected to the lifting electric control box connection; in each group of lifting centralized control devices, one of the continuous stretching hydraulic hoists is connected to the wind rope, and the other two continuous stretching hydraulic hoists are connected to the steel strand group, and each continuous stretching hydraulic jack An anchor assembly is connected to the steel strand group.
  5. 根据权利要求3所述的一种变径非平衡载荷类设备垂直提升安装装置,其特征是:所述提升架包括三根或四根立柱,所述立柱均安装在轨道两侧,所述安装杆的高度大于所述轨道式转运装置的高度;所述安装杆呈圆形,多个所述定滑轮等角度均布在所述安装杆上。According to claim 3, a device for vertical lifting and installation of variable-diameter unbalanced load-type equipment is characterized in that: the lifting frame includes three or four uprights, and the uprights are installed on both sides of the track, and the installation rod The height is greater than the height of the track-type transfer device; the installation rod is circular, and a plurality of the fixed pulleys are evenly distributed on the installation rod at equal angles.
  6. 根据权利要求4所述的一种变径非平衡载荷类设备垂直提升安装装置,其特征是,所述锚固组件包括依次连接在钢绞线组上的两组锚固器;所述锚固器包括筒型壳体,还包括环形均布在壳体内的多组锚座,锚座与壳体固定连接,每组锚座对应的设置锚片和锁紧片;所述钢绞线组与所述锚固组件的连接方式为:所有钢绞线穿过位于前端的锚固器后, 任意相邻的两根钢绞线分别锁紧在不同的锚固器上。According to claim 4, a device for vertical lifting and installation of variable-diameter unbalanced load-type equipment is characterized in that, the anchor assembly includes two groups of anchors sequentially connected to the steel strand group; the anchor includes a barrel Type shell, also includes multiple groups of anchor seats uniformly distributed in the shell, the anchor seats are fixedly connected with the shell, and each set of anchor seats is correspondingly provided with anchor pieces and locking pieces; the steel strand group and the anchor The connection method of the components is: after all steel strands pass through the anchor at the front end, any two adjacent steel strands are respectively locked on different anchors.
  7. 变径非平衡载荷类设备垂直提升安装方法,其特征是,包括以下步骤:The method for vertically lifting and installing variable-diameter unbalanced load-type equipment is characterized in that it includes the following steps:
    S1提升前辅助工作:包括基础施工、风机基础节安装、提升架安装、提升集控装置安装和调试;S1 Auxiliary work before lifting: including foundation construction, fan base section installation, lifting frame installation, lifting centralized control device installation and commissioning;
    S2风机提升组装:在风机塔筒的每个塔节的圆周方向上等角度安装提升吊点,组装风机塔筒第三塔节、第二塔节和第一塔节以及第一塔节上部的风机机房、发电机和叶片,使每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,使每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节,使每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳连接第一塔节,启动提升集控装置将已安装设备整体提升超过一个塔节高度,以便新塔节的就位和安装,其中钢绞线组与塔节的连接方式为:所有钢绞线穿过位于前端的锚固器后,使任意相邻的两根钢绞线分别锁紧在不同的锚固器上;S2 Wind turbine lifting assembly: Install lifting points at equal angles in the circumferential direction of each tower section of the wind turbine tower, and assemble the third tower section, the second tower section, the first tower section and the upper part of the first tower section of the wind tower. The fan machine room, generator and blades, so that the steel strand group of one of the continuous stretching hydraulic hoists in each group of hoisting centralized control devices is connected to the third tower section, so that the other one of each group of hoisting centralized control devices is connected continuously The steel strand group of the stretching hydraulic hoist is connected to the second tower section, so that the wind rope of the last continuous stretching hydraulic hoist in each group of lifting centralized control device is connected to the first tower section, and the lifting centralized control device is started Lift the installed equipment as a whole over one tower section height, so that the new tower section can be placed and installed. The connection method between the steel strand group and the tower section is: after all the steel strands pass through the anchor at the front end, any Two adjacent steel strands are respectively locked on different anchors;
    S3新塔节转运就位:根据选用转运架的组数,为每个转运架吊装一节塔节,并分别启动支撑油缸,使支撑瓦将塔节顶紧,按照组装顺序将塔节依次运输至提升架内,进入下一步;S3 new tower section transfer in place: According to the number of groups of transfer frames selected, one tower section is hoisted for each transfer frame, and the support oil cylinders are respectively activated to make the support tiles push the tower sections tightly, and the tower sections are transported in sequence according to the assembly sequence Go to the lifting frame and go to the next step;
    S4新塔节连接和提升:将连接在第二塔节的钢绞线组松开与第二塔节提升吊点的连接,并安装至新塔节的提升吊点上,此组钢绞线组全部均匀受力后松开支撑瓦与塔节的支撑,缓慢提升新塔节并将新塔节的顶部与第三塔节的底部连接;然后联动控制提升集控装置,将已安装塔节和设备整体稳步提升一个塔节高度后,将另一装有塔节的转运架移动至已安装塔节的下方,将夹轨器与轨道锁定,重复上述操作将风机塔筒全部连接完毕;S4 Connection and lifting of new tower section: loosen the connection of the steel strand group connected to the second tower section with the hoisting point of the second tower section, and install it on the hoisting point of the new tower section. After all the groups are evenly stressed, loosen the support of the supporting tiles and the tower section, slowly lift the new tower section and connect the top of the new tower section with the bottom of the third tower section; After steadily raising the height of one tower section with the equipment as a whole, move the transfer frame with another tower section to the bottom of the installed tower section, lock the rail clamp and the track, and repeat the above operations to complete the connection of the fan tower;
    S5风机与基础节连接:当与基础节连接的塔节与风机塔筒的其它塔节连接后,将已安装风机整体提升一个塔节高度后,将塔节转运架移出提升架,然后,联动控制提升集控装置,将风机已安装塔节和设备整体缓慢下降,将风机塔筒整体与基础节连接;S5 wind turbine is connected to the foundation section: After the tower section connected to the foundation section is connected to other tower sections of the fan tower, after the installed wind turbine is raised by one tower section height, the tower section transfer frame is moved out of the lifting frame, and then, linkage Control the lifting centralized control device, slowly lower the installed tower section of the fan and the overall equipment, and connect the entire fan tower with the foundation section;
    S6:风机确认性调试:进行风机各部件、设备进行调试;S6: Fan confirmatory debugging: carry out debugging of each component and equipment of the fan;
    S7:辅助装置拆除:拆除提升架、提升集控装置和转运架,安装即全部完成。S7: Auxiliary device removal: Remove the lifting frame, lifting centralized control device and transfer frame, and the installation is complete.
  8. 根据权利要求7所述的变径非平衡载荷类设备垂直提升安装方法,其特征是,S2采用移动式起重机吊装进行,具体包括如下步骤:According to the method for vertically lifting and installing variable-diameter unbalanced load-type equipment according to claim 7, it is characterized in that S2 is hoisted by a mobile crane, and specifically includes the following steps:
    S2-1启用移动式起重机吊装第三塔节到基础节上,并将每组提升集控装置中的其中一台连续拉伸式液压提升机的钢绞线组连接第三塔节,将第三塔节调整垂直并绷紧钢绞线组受力;S2-1 Use the mobile crane to hoist the third tower section to the foundation section, and connect the steel strand group of one of the continuous stretching hydraulic hoists in each group of lifting centralized control devices to the third tower section, and connect the third tower section The three-tower section adjusts the vertical and tightens the force of the steel strand group;
    S2-2启用移动式起重机吊装第二塔节到第三塔节上方,并将第二塔节与第三塔节同轴连接固定,并将每组提升集控装置中另一台连续拉伸式液压提升机的钢绞线组连接第二塔节;S2-2 Enable the mobile crane to hoist the second tower section above the third tower section, connect and fix the second tower section and the third tower section coaxially, and continuously stretch the other one of each group of lifting centralized control devices The steel strand group of the type hydraulic hoist is connected to the second tower section;
    S2-3启用移动式起重机吊装第一塔节到第二塔节上方,并将第一塔节与第二塔节同轴连接固定,并将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳连接第一塔节。S2-3 Use the mobile crane to hoist the first tower section above the second tower section, connect and fix the first tower section and the second tower section coaxially, and continuously stretch the last one of each group of lifting centralized control devices The wind rope of the type hydraulic hoist is connected to the first tower section.
  9. 根据权利要求7所述的变径非平衡载荷类设备垂直提升安装方法,其特征是,S2采用本发明安装装置吊装进行,具体包括如下步骤:According to claim 7, the method for vertically lifting and installing variable-diameter unbalanced load-type equipment is characterized in that S2 is hoisted by using the installation device of the present invention, and specifically includes the following steps:
    S2-1先用转运架将第二塔节转运至提升架内的安装位,驱动每组提升集控装置中一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,然后将第二塔节提升至超过一节塔节的净高;S2-1 first uses the transfer frame to transfer the second tower section to the installation position in the lifting frame, drives a continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the hoisting The lifting points are connected, tightened, and then the second tower section is lifted to exceed the clear height of the first tower section;
    S2-2再用转运架将第三塔节转运至提升架内的安装位,驱动每组提升集控装置中另一台连续拉伸式液压提升机,将其锚固器分别与此塔节的提升吊点连接、绷紧,缓慢将第三塔节提升至与第二塔节贴合的位置,将第二塔节与第三塔节连接紧固;S2-2 uses the transfer frame to transfer the third tower section to the installation position in the lifting frame, drives another continuous stretching hydraulic hoist in each group of lifting centralized control device, and connects its anchors with the tower section respectively. Lift the lifting point to connect and tighten, slowly lift the third tower section to the position where it fits with the second tower section, and fasten the second tower section to the third tower section;
    S2-3再用起重机将第一塔节吊至第二塔节上方,在起重机不松钩的状态下将第一塔节与第二塔节连接紧固,再将每组提升集控装置中最后一台连续拉伸式液压提升机的揽风绳与第一塔节上连接、绷紧;S2-3 Then use the crane to hoist the first tower section above the second tower section, connect and fasten the first tower section and the second tower section under the condition that the crane does not loosen the hook, and then place each group of lifting centralized control device The wind rope of the last continuous stretching hydraulic hoist is connected and tightened to the first tower section;
    S2-4在整体垂直稳定的状态下,进行风机机房、发电机和叶片的吊装和调整,安装完成后将可转动或可移动部件锁定。S2-4 Carry out the hoisting and adjustment of the fan machine room, generator and blades in the overall vertically stable state, and lock the rotatable or movable parts after the installation is completed.
  10. 根据权利要求7所述的变径非平衡载荷类设备垂直提升安装方法,其特征是,S2完成后,即风机主要功能部件安装完成后,先进行功能性调试,调试合格后再提升连接后续塔节。According to claim 7, the method for vertical lifting and installation of equipment with variable diameter and unbalanced loads is characterized in that after S2 is completed, that is, after the main functional components of the fan are installed, functional debugging is carried out first, and after the debugging is passed, the subsequent tower is lifted and connected Festival.
PCT/CN2022/113043 2022-05-24 2022-08-17 Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device WO2023082748A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202210569493.5A CN114873497B (en) 2022-05-24 2022-05-24 Vertical lifting installation device and method for variable-diameter unbalanced load equipment
CN202210569493.5 2022-05-24

Publications (1)

Publication Number Publication Date
WO2023082748A1 true WO2023082748A1 (en) 2023-05-19

Family

ID=82677347

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/113043 WO2023082748A1 (en) 2022-05-24 2022-08-17 Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device

Country Status (2)

Country Link
CN (1) CN114873497B (en)
WO (1) WO2023082748A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117927428A (en) * 2024-03-21 2024-04-26 山西禄泽重工科技有限公司 Offshore wind driven generator mounting structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114873497B (en) * 2022-05-24 2023-06-16 中国长江三峡集团有限公司 Vertical lifting installation device and method for variable-diameter unbalanced load equipment
CN115893175B (en) * 2023-01-09 2023-06-16 中铁城建集团第一工程有限公司 Synchronous integral lifting system for hyperboloid overhanging steel net frame and construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5490364A (en) * 1994-08-30 1996-02-13 Dreco, Inc. Telescopic flare pipe tower
JP2001254668A (en) * 2000-03-09 2001-09-21 Tokyo Electric Power Co Inc:The Device and method for assembling wind power generation tower
US20090087311A1 (en) * 2007-09-29 2009-04-02 Gavin Raymond Wyborn Vertically Adjustable Horizontal Axis Type Wind Turbine And Method Of Construction Thereof
US20100044330A1 (en) * 2008-08-19 2010-02-25 Vorhies Roger W Wind turbine erector
WO2013123383A1 (en) * 2012-02-16 2013-08-22 Belinsky Sidney Stationary positioned offshore windpower plant (owp) and the methods and means for its assembling,transportation, installation and servicing
CN106812670A (en) * 2017-04-01 2017-06-09 中冶建工集团有限公司 The construction method for hanging of large-scale wind electricity equipment under Mountain Conditions
CN110407097A (en) * 2019-07-22 2019-11-05 中国电建集团河南工程有限公司 The construction method of the novel phase modifier of lifting based on portal frame and Lao Xinge device
US20210207393A1 (en) * 2020-01-03 2021-07-08 Dreco Energy Services Ulc Tower erection and climbing systems
CN114873497A (en) * 2022-05-24 2022-08-09 中国长江三峡集团有限公司 Vertical lifting installation device and method for variable-diameter unbalanced load equipment

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2069591A4 (en) * 2006-10-02 2010-12-01 Wind Tower Systems Llc Lifting system and appartus for constructing and enclosing wind turbine towers
CN102496771B (en) * 2011-12-19 2013-11-06 宝钢钢构有限公司 Method and device for installing large-sized steel structural antenna
CN106115474B (en) * 2016-08-29 2018-03-23 共享钢构有限责任公司 The method for improving of super high steel structure pylon

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5490364A (en) * 1994-08-30 1996-02-13 Dreco, Inc. Telescopic flare pipe tower
JP2001254668A (en) * 2000-03-09 2001-09-21 Tokyo Electric Power Co Inc:The Device and method for assembling wind power generation tower
US20090087311A1 (en) * 2007-09-29 2009-04-02 Gavin Raymond Wyborn Vertically Adjustable Horizontal Axis Type Wind Turbine And Method Of Construction Thereof
US20100044330A1 (en) * 2008-08-19 2010-02-25 Vorhies Roger W Wind turbine erector
WO2013123383A1 (en) * 2012-02-16 2013-08-22 Belinsky Sidney Stationary positioned offshore windpower plant (owp) and the methods and means for its assembling,transportation, installation and servicing
CN106812670A (en) * 2017-04-01 2017-06-09 中冶建工集团有限公司 The construction method for hanging of large-scale wind electricity equipment under Mountain Conditions
CN110407097A (en) * 2019-07-22 2019-11-05 中国电建集团河南工程有限公司 The construction method of the novel phase modifier of lifting based on portal frame and Lao Xinge device
US20210207393A1 (en) * 2020-01-03 2021-07-08 Dreco Energy Services Ulc Tower erection and climbing systems
CN114873497A (en) * 2022-05-24 2022-08-09 中国长江三峡集团有限公司 Vertical lifting installation device and method for variable-diameter unbalanced load equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117927428A (en) * 2024-03-21 2024-04-26 山西禄泽重工科技有限公司 Offshore wind driven generator mounting structure
CN117927428B (en) * 2024-03-21 2024-05-28 山西禄泽重工科技有限公司 Offshore wind driven generator mounting structure

Also Published As

Publication number Publication date
CN114873497A (en) 2022-08-09
CN114873497B (en) 2023-06-16

Similar Documents

Publication Publication Date Title
WO2023082748A1 (en) Apparatus and method for vertically lifting and installing variable-diameter unbalanced-load device
CN111364363B (en) Stay cable construction tensioning method
CN102359302B (en) Extra-high voltage large-span iron tower assembling method
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN105003090A (en) Temporary support frame for mounting assembly type steel structure
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN111852074A (en) Adjustable lifting type supporting device
CN116163535A (en) Construction method for lifting prefabricated part in delta shape by walking on top of column
CN108928783B (en) Shear type climbing hoisting machine for existing building additionally installed elevator
CN115818458A (en) Standard knot assembling and disassembling system and operation method
CN2379090Y (en) Multi-purpose miniature machine for cleaning windows
JP2002097819A (en) Method and device for assembling transmission tower
CN113636467A (en) Rolling mill frame hoisting device
CN114382015A (en) Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge
CN220098355U (en) Double-shaft hinged arm support type offshore crane
CN220886668U (en) Hoisting device for arranging equipment without overhauling space in parallel
CN220432160U (en) T-shaped cross-railway light portal frame
CN117166812B (en) Construction method for reforming protective structure of building curtain wall during tower crane limitation
CN212024599U (en) Column cantilever crane convenient to transportation
CN220978760U (en) Elevator derrick construction platform
RU2815701C1 (en) Method of mounting sections of single-column inclined pylon of cable-stayed bridge and one-sided self-lifting device for mounting sections of steel pylon
CN209940311U (en) Movable portal frame for construction of lock chamber wall template of ship lock
JPH0835358A (en) Construction method for tower shaped structure and support structure used for the method
CN117228497B (en) Multi-point vertical lifting installation device and method for single-axis tracking photovoltaic bracket
CN214220803U (en) Railway monitoring equipment mounting tower

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22891556

Country of ref document: EP

Kind code of ref document: A1