CN114382015A - Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge - Google Patents

Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge Download PDF

Info

Publication number
CN114382015A
CN114382015A CN202110720398.6A CN202110720398A CN114382015A CN 114382015 A CN114382015 A CN 114382015A CN 202110720398 A CN202110720398 A CN 202110720398A CN 114382015 A CN114382015 A CN 114382015A
Authority
CN
China
Prior art keywords
tower
vertical
cable
bridge
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110720398.6A
Other languages
Chinese (zh)
Inventor
肖佳哲
姜炜
李文雅
孙一峰
邱锴
刘瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Original Assignee
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd filed Critical SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority to CN202110720398.6A priority Critical patent/CN114382015A/en
Publication of CN114382015A publication Critical patent/CN114382015A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method for vertical turning of a special-shaped steel main tower of a cable-stayed bridge, which comprises the steps of erecting a temporary assembling platform, assembling a steel auxiliary tower, debugging hydraulic synchronous vertical turning system equipment, synchronously loading a vertical turning device and a stabilizing rigging in a grading manner, stopping the bridge tower for more than 2 hours after pre-vertical turning, starting formal vertical turning on the premise of ensuring the absolute safety of the whole vertical turning working condition, vertically turning to a position close to a design position, measuring and controlling, slowing down the vertical turning speed, finely adjusting the vertical direction of each bridge tower by using hydraulic vertical turning equipment, accurately positioning, and performing bridge tower folding welding work and hydraulic synchronous vertical turning system equipment unloading work after the vertical turning is in place. The construction method for the vertical rotation of the special-shaped steel main tower of the cable-stayed bridge solves the problems that compared with construction methods such as erecting an integral support and the like, the construction method has great convenience and construction period superiority, construction measure cost is reduced, the total construction period is shortened, and the construction method is high in practicability and innovation.

Description

斜拉桥异形钢主塔竖向转体施工工法Construction method of vertical swivel of special-shaped steel main tower of cable-stayed bridge

技术领域technical field

本发明涉及桥体施工技术领域,具体为斜拉桥异形钢主塔竖向转体施工 工法。The invention relates to the technical field of bridge body construction, in particular to a construction method for vertical swivel of a special-shaped steel main tower of a cable-stayed bridge.

背景技术Background technique

随着国内施工技术的进展,越来越多的桥型出现在大家的眼中,在桥梁 转体施工中,平转应用较多,但竖转应用较少。现在桥梁越来越注重美观, 而美观又在施工方式上提出了新的要求,竖向转体在今后的应用会越来越多, 也是时代发展的趋势,其中斜拉桥是一种用斜拉索悬吊桥面的桥梁,又称斜 张桥,是由承压的塔,受拉的索和承弯的梁体组合起来的一种结构体系。斜 拉桥作为一种拉索体系,比梁式桥的跨越能力更大,是大跨度桥梁的最主要 桥型。With the development of domestic construction technology, more and more bridge types appear in everyone's eyes. In the construction of bridge swivel, there are more applications of horizontal rotation, but less application of vertical rotation. Nowadays, bridges pay more and more attention to aesthetics, and aesthetics puts forward new requirements on construction methods. Vertical swivels will be used more and more in the future, which is also the trend of the times. A cable-suspension bridge, also known as a cable-stayed bridge, is a structural system composed of a compression tower, a tension cable and a bending beam. Cable-stayed bridges, as a kind of cable system, have greater spanning capacity than girder bridges, and are the most important bridge type for long-span bridges.

在现有传统桥梁施工来说,相比搭设整体支架等施工方式,其施工不方 便,另外传统施工上无法减少施工措施费及施工工期,以及传统施工实用性 不强、创新性不高的问题。For the existing traditional bridge construction, compared with the construction methods such as erecting integral supports, its construction is inconvenient. In addition, the traditional construction cannot reduce the cost of construction measures and the construction period, and the traditional construction is not practical and innovative. .

发明内容SUMMARY OF THE INVENTION

(一)解决的技术问题(1) Technical problems solved

针对现有技术的不足,本发明提供了斜拉桥异形钢主塔竖向转体施工工 法,解决了相比搭设整体支架等施工方式,其施工不方便,另外传统施工上 无法减少施工措施费及施工工期,以及传统施工实用性不强、创新性不高的 问题。In view of the deficiencies of the prior art, the present invention provides a vertical swivel construction method for the special-shaped steel main tower of a cable-stayed bridge, which solves the inconvenience of construction compared with the construction methods such as erecting an integral bracket, and in addition, the traditional construction cannot reduce the cost of construction measures and construction period, as well as the problems that traditional construction is not practical and innovative.

(二)技术方案(2) Technical solutions

为实现以上目的,本发明通过以下技术方案予以实现:斜拉桥异形钢主 塔竖向转体施工工法,包括以下步骤:In order to achieve the above purpose, the present invention is realized through the following technical solutions: the construction method of vertical swivel of the special-shaped steel main tower of the cable-stayed bridge, comprises the following steps:

S1、搭设临时拼装平台,主塔结构拼装同桥面呈5°进行,在地面上完成 整体拼装;S1. Set up a temporary assembly platform, the main tower structure is assembled at a 5° angle to the bridge deck, and the overall assembly is completed on the ground;

S2、拼装钢副塔,安装两侧吊笼、液压提升器、转绞等,将钢副塔门架 安装于桥塔上,桥塔上设置前拉锚点,地面上墩附近设置后拉锚点;S2. Assemble the steel auxiliary tower, install the hanging cages on both sides, hydraulic lifters, twisting, etc., install the steel auxiliary tower gantry on the bridge tower, set the front anchor point on the bridge tower, and set the rear anchor near the pier on the ground point;

S3、进行液压同步竖转系统设备调试,试竖转;S3. Debug the hydraulic synchronous vertical rotation system equipment and test the vertical rotation;

S4、同步分级加载竖转器和稳定索具;S4, synchronously graded loading of the vertical swivel and stable rigging;

S5、桥塔预竖转后停留2小时以上,检查临时竖转结构、稳定索系统、 竖转系统、基础、吊点、底部铰点等,在确认整个竖转工况绝对安全的前提 下,开始正式竖转S5. Stay for more than 2 hours after the pre-vertical rotation of the bridge tower, and check the temporary vertical rotation structure, stable cable system, vertical rotation system, foundation, lifting point, bottom hinge point, etc. On the premise that the entire vertical rotation condition is absolutely safe, Start the official vertical rotation

S6、竖转至接近设计位置,测量控制,放慢竖转速度,利用液压竖转设 备对各桥塔进行竖直方向微调,精确定位;S6. Vertically rotate to the design position, measure and control, slow down the vertical rotation speed, and use hydraulic vertical rotation equipment to fine-tune the vertical direction of each bridge tower for precise positioning;

S7、竖转就位后,进行桥塔合拢焊接工作;S7. After the vertical rotation is in place, the bridge tower is closed and welded;

S8、液压同步竖转系统设备卸载作业,至钢绞线完全松弛,使桥塔整体 落位;液压同步竖转设备及钢副塔等其它竖转用临时措施全部拆除,完成桥 塔竖转安装工作。S8. The hydraulic synchronous vertical swivel system equipment is unloaded until the steel strands are completely relaxed, so that the bridge tower can be placed in place as a whole; the hydraulic synchronous vertical swivel equipment and other temporary measures for vertical swivel such as steel auxiliary towers are all removed, and the vertical swivel installation of the bridge tower is completed. Work.

优选的,所述S1步骤中,斜拉索最大跨径为180m,主桥为32m、38m、 110m独塔双跨混合梁斜拉桥。Preferably, in the step S1, the maximum span of the stay cable is 180m, and the main bridge is a 32m, 38m, and 110m single-pylon double-span mixed-beam cable-stayed bridge.

优选的,所述S2步骤中,拉锚点分为前锚和后锚,且前锚为预张拉锚点, 由张拉专用钢绞线、前锚耳板和张拉吊具等相互组成,所述桥塔单侧对应各 设置2个张拉锚点,且单个张拉锚点采用2个张拉吊具。Preferably, in the step S2, the tension anchor points are divided into front anchors and rear anchors, and the front anchors are pre-tensioned anchor points, which are composed of special steel strands for tensioning, front anchor lugs and tensioning hangers. , two tensioning anchor points are respectively set on one side of the bridge tower, and two tensioning spreaders are used for a single tensioning anchor point.

优选的,所述后锚为提升锚点,由后拉基础、提升专用钢绞线、液压提 升器、提升吊具、后锚埋件耳板和临时墩等相互组成,所述桥塔单侧对应各 设置2个提升吊点。Preferably, the rear anchor is a lifting anchor point, which is composed of a rear pulling foundation, a special steel strand for lifting, a hydraulic lifter, a lifting spreader, a rear anchor embedded ear plate and a temporary pier, and the like. Correspondingly set 2 lifting points for each.

优选的,所述S2步骤中,液压提升器在使用时设置有专用提升平台。Preferably, in the step S2, the hydraulic lifter is provided with a dedicated lifting platform when in use.

优选的,所述S2步骤中,钢副塔门架立柱采用P420x16的圆管,且横、 斜腹杆为P180x6,所述中间联系桁架横杆采用P273x10的圆管,且横、斜腹 杆为P180x6。Preferably, in the step S2, the steel auxiliary tower gantry column adopts P420x16 round pipes, and the transverse and inclined web rods are P180x6, the intermediate connection truss transverse rods are P273x10 circular pipes, and the transverse and inclined web rods are P180x6.

优选的,所述液压提升器调节压力为3-4MPa。Preferably, the adjustment pressure of the hydraulic lifter is 3-4MPa.

优选的,所述步骤6中,测量控制为计算机控制系统,其中吊点同步不 均时,最大高低差预警值为20-25mm。Preferably, in the described step 6, the measurement control is a computer control system, and when the synchronism of the lifting point is uneven, the maximum height difference warning value is 20-25mm.

(三)有益效果(3) Beneficial effects

本发明提供了斜拉桥异形钢主塔竖向转体施工工法。与现有技术相比具 备以下有益效果:该斜拉桥异形钢主塔竖向转体施工工法,通过主塔结构拼 装同桥面呈5°进行,在地面上完成整体拼装,安装两侧吊笼、液压提升器、 转绞等,将钢副塔门架安装于桥塔上,桥塔上设置前拉锚点,地面上墩附近 设置后拉锚点,进行液压同步竖转系统设备调试,试竖转,同步分级加载竖 转器和稳定索具,桥塔预竖转后停留2小时以上,检查临时竖转结构、稳定 索系统、竖转系统、基础、吊点、底部铰点等,在确认整个竖转工况绝对安 全的前提下,开始正式竖转,竖转至接近设计位置,测量控制,放慢竖转速 度,利用液压竖转设备对各桥塔进行竖直方向微调,精确定位,竖转就位后, 进行桥塔合拢焊接工作,至钢绞线完全松弛,使桥塔整体落位,液压同步竖 转设备及钢副塔等其它竖转用临时措施全部拆除,完成桥塔竖转安装工作, 解决相比搭设整体支架等施工方式具有很大的方便性及工期优越性,另外减 少施工措施费及缩短施工总工期上,以及实用性强、创新性高,可有效解决异形钢主塔竖转施工的问题。The invention provides a construction method for the vertical rotation of a special-shaped steel main tower of a cable-stayed bridge. Compared with the prior art, it has the following beneficial effects: the special-shaped steel main tower vertical rotation construction method of the cable-stayed bridge is carried out by assembling the main tower structure at a 5° angle to the bridge deck, and the overall assembly is completed on the ground, and the suspension on both sides is installed. Cage, hydraulic lifter, twist, etc., the steel auxiliary tower gantry is installed on the bridge tower, the front pull anchor point is set on the bridge tower, the rear pull anchor point is set near the pier on the ground, and the equipment debugging of the hydraulic synchronous vertical rotation system is carried out. Trial the vertical rotation, load the vertical rotator and stabilizing rigging synchronously in stages, stay for more than 2 hours after the pre-vertical rotation of the bridge tower, and check the temporary vertical rotation structure, stable cable system, vertical rotation system, foundation, lifting point, bottom hinge point, etc. On the premise of confirming that the entire vertical rotation condition is absolutely safe, start the official vertical rotation, close the vertical rotation to the design position, measure and control, slow down the vertical rotation speed, and use the hydraulic vertical rotation equipment to fine-tune the vertical direction of each bridge tower. After the positioning and vertical rotation are in place, the bridge tower is closed and welded until the steel strands are completely relaxed, so that the bridge tower is placed in place as a whole. The vertical rotation installation of the tower has great convenience and construction period advantages compared with the construction methods such as erecting an integral bracket. In addition, it reduces the cost of construction measures and shortens the total construction period. It has strong practicability and high innovation, and can effectively solve the problem. The problem of vertical rotation construction of special-shaped steel main tower.

附图说明Description of drawings

图1为本发明方法第一示意图;Fig. 1 is the first schematic diagram of the method of the present invention;

图2为本发明方法第二示意图;Fig. 2 is the second schematic diagram of the method of the present invention;

图3为本发明方法第三示意图;Fig. 3 is the third schematic diagram of the method of the present invention;

图4为本发明方法第四示意图;Fig. 4 is the fourth schematic diagram of the method of the present invention;

图5为本发明方法第五示意图;Fig. 5 is the fifth schematic diagram of the method of the present invention;

图6为本发明方法第六示意图;Fig. 6 is the sixth schematic diagram of the method of the present invention;

图7为本发明方法第七示意图;Fig. 7 is the seventh schematic diagram of the method of the present invention;

图8为本发明方法第八示意图;Fig. 8 is the eighth schematic diagram of the method of the present invention;

图9为本发明方法第九示意图;Fig. 9 is the ninth schematic diagram of the method of the present invention;

图10为本发明钢索塔拼装临时支墩平面示意图;Figure 10 is a schematic plan view of the steel cable tower assembled temporary buttress of the present invention;

图11为本发明钢索塔拼装临时支墩断面图;Fig. 11 is the sectional view of the steel cable tower assembled temporary buttress of the present invention;

图12为本发明方法码板安装示意图;Figure 12 is a schematic diagram of the method of the present invention for the installation of the code plate;

图13为本发明方法桥塔转铰示意图;Figure 13 is a schematic diagram of a bridge pylon hinge according to the method of the present invention;

图14为本发明方法转铰连接示意图;Figure 14 is a schematic diagram of a hinged connection according to the method of the present invention;

图15为本发明方法转铰连接剖视图。Figure 15 is a cross-sectional view of the hinged connection according to the method of the present invention.

具体实施方式Detailed ways

对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的 实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的 实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其 他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention are clearly and completely described, and obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative work, all belong to the protection scope of the present invention.

请参阅图1-11,本发明实施例提供一种技术方案:斜拉桥异形钢主塔竖 向转体施工工法,包括以下步骤:Please refer to Fig. 1-11, the embodiment of the present invention provides a kind of technical scheme: cable-stayed bridge special-shaped steel main tower vertical swivel construction method, comprises the following steps:

S1、搭设临时拼装平台,主塔结构拼装同桥面呈5°进行,在地面上完成 整体拼装;S1. Set up a temporary assembly platform, the main tower structure is assembled at a 5° angle to the bridge deck, and the overall assembly is completed on the ground;

S2、拼装钢副塔,安装两侧吊笼、液压提升器、转绞等,将钢副塔门架 安装于桥塔上,桥塔上设置前拉锚点,地面上墩附近设置后拉锚点;S2. Assemble the steel auxiliary tower, install the hanging cages on both sides, hydraulic lifters, twisting, etc., install the steel auxiliary tower gantry on the bridge tower, set the front anchor point on the bridge tower, and set the rear anchor near the pier on the ground point;

S3、进行液压同步竖转系统设备调试,试竖转;S3. Debug the hydraulic synchronous vertical rotation system equipment and test the vertical rotation;

S4、同步分级加载竖转器和稳定索具;S4, synchronously graded loading of the vertical swivel and stable rigging;

S5、桥塔预竖转后停留2小时以上,检查临时竖转结构、稳定索系统、 竖转系统、基础、吊点、底部铰点等,在确认整个竖转工况绝对安全的前提 下,开始正式竖转S5. Stay for more than 2 hours after the pre-vertical rotation of the bridge tower, and check the temporary vertical rotation structure, stable cable system, vertical rotation system, foundation, lifting point, bottom hinge point, etc. On the premise that the entire vertical rotation condition is absolutely safe, Start the official vertical rotation

S6、竖转至接近设计位置,测量控制,放慢竖转速度,利用液压竖转设 备对各桥塔进行竖直方向微调,精确定位;S6. Vertically rotate to the design position, measure and control, slow down the vertical rotation speed, and use hydraulic vertical rotation equipment to fine-tune the vertical direction of each bridge tower for precise positioning;

S7、竖转就位后,进行桥塔合拢焊接工作;S7. After the vertical rotation is in place, the bridge tower is closed and welded;

S8、液压同步竖转系统设备卸载作业,至钢绞线完全松弛,使桥塔整体 落位;液压同步竖转设备及钢副塔等其它竖转用临时措施全部拆除,完成桥 塔竖转安装工作。S8. The hydraulic synchronous vertical swivel system equipment is unloaded until the steel strands are completely relaxed, so that the bridge tower can be placed in place as a whole; the hydraulic synchronous vertical swivel equipment and other temporary measures for vertical swivel such as steel auxiliary towers are all removed, and the vertical swivel installation of the bridge tower is completed. Work.

进一步的,所述S1步骤中,斜拉索最大跨径为180m,主桥为32m、38m、 110m独塔双跨混合梁斜拉桥。Further, in the step S1, the maximum span of the stay cables is 180m, and the main bridges are 32m, 38m, and 110m single-pylon and double-span hybrid beam cable-stayed bridges.

进一步的,所述S2步骤中,拉锚点分为前锚和后锚,且前锚为预张拉锚 点,由张拉专用钢绞线、前锚耳板和张拉吊具等相互组成,所述桥塔单侧对应 各设置2个张拉锚点,且单个张拉锚点采用2个张拉吊具。Further, in the step S2, the tension anchor points are divided into front anchors and rear anchors, and the front anchors are pre-tensioned anchor points, which are composed of special steel strands for tensioning, front anchor lugs and tensioning hangers. , two tensioning anchor points are respectively set on one side of the bridge tower, and two tensioning spreaders are used for a single tensioning anchor point.

进一步的,所述后锚为提升锚点,由后拉基础、提升专用钢绞线、液压 提升器、提升吊具、后锚埋件耳板和临时墩等相互组成,所述桥塔单侧对应 各设置2个提升吊点。Further, the rear anchor is a lifting anchor point, which is composed of a rear pulling foundation, a special steel strand for lifting, a hydraulic lifter, a lifting spreader, a rear anchor embedded ear plate and a temporary pier. Correspondingly set 2 lifting points for each.

进一步的,所述S2步骤中,液压提升器在使用时设置有专用提升平台。Further, in the step S2, the hydraulic lifter is provided with a dedicated lifting platform when in use.

进一步的,所述S2步骤中,钢副塔门架立柱采用P420x16的圆管,且横、 斜腹杆为P180x6,所述中间联系桁架横杆采用P273x10的圆管,且横、斜腹 杆为P180x6。Further, in the step S2, the steel auxiliary tower gantry column adopts the round pipe of P420x16, and the horizontal and inclined web bars are P180x6, and the middle contact truss crossbar adopts the round pipe of P273×10, and the horizontal and diagonal web bars are P180x6.

进一步的,所述液压提升器调节压力为3-4MPa。Further, the adjustment pressure of the hydraulic lifter is 3-4MPa.

进一步的,所述步骤6中,测量控制为计算机控制系统,其中吊点同步 不均时,最大高低差预警值为20-25mm。Further, in the described step 6, the measurement control is a computer control system, and when the lifting point synchronization is uneven, the maximum height difference early warning value is 20-25mm.

工作时,1、钢索塔拼装胎架安装When working, 1. Steel cable tower assembled tire frame installation

根据钢索塔节段的自重及现场的地质条件,临时支墩采用钢管格构柱+H 型钢横梁+立柱调节段结构形式,临时支墩安装时,采用地面整体拼装制作, 整体吊装就位的方法进行安装,增强临时支墩的整体稳定性,临时支墩底部 采用预埋钢筋将钢管支墩法兰盲板与混凝土基础固定。并将钢管支墩法兰盲 板与预钢筋焊接,增强柱脚的刚性稳定,临时支撑调节采用调节段千斤顶进 行。主要用于钢索塔吊装时调节钢索塔标高和安装结束后进行钢索塔整体卸 载。According to the self-weight of the steel cable tower segment and the geological conditions of the site, the temporary support pier adopts the structural form of steel pipe lattice column + H-beam + vertical column adjustment section. The method is installed to enhance the overall stability of the temporary buttress. The bottom of the temporary buttress is fixed by the embedded steel bar to fix the flange blind plate of the steel pipe buttress to the concrete foundation. The flange blind plate of the steel pipe buttress is welded with the pre-reinforced reinforcement to enhance the rigidity and stability of the column foot, and the temporary support adjustment is carried out with the adjustment section jack. It is mainly used for adjusting the elevation of the steel tower during hoisting and for the overall unloading of the steel tower after the installation.

2、胎架上索塔节段拼装2. Assembling the tower segment on the tire frame

(1)400t汽车吊在吊装跨跨内位置处站好位,在每个支腿下铺垫路基板 (汽车吊自带路基板);(1) The 400t vehicle is hoisted in a good position at the position within the hoisting span, and the road substrate is laid under each outrigger (the vehicle is hoisted with the road substrate);

(2)选用4根φ64mm,抗拉强度≥1870N/mm2的钢丝绳吊索和4只各能 承载55t的卸扣,卡锁在钢箱梁4个吊耳上;(2) Select 4 steel wire rope slings with φ64mm and tensile strength ≥1870N/mm2 and 4 shackles each capable of carrying 55t, and lock them on the 4 lifting ears of the steel box girder;

(3)指挥汽车吊缓慢起吊,当钢箱梁离地面约100mm时,停止10分钟后, 进行三项检查:⑴起重机的受力是否良好;⑵吊耳受力是否完好;⑶钢丝绳 吊索、卸扣的受力是否完好。若均正常,则指挥浮吊缓慢回转;(3) Instruct the truck crane to lift slowly. When the steel box girder is about 100mm above the ground, stop for 10 minutes and then carry out three inspections: (1) Whether the force of the crane is good; (2) Whether the force of the lifting lug is in good condition; (3) The wire rope sling, Whether the force of the shackle is intact. If all are normal, command the floating crane to rotate slowly;

(4)指挥运输车驶离位置,并将塔脚重新放在地面上,转换吊点位置, 使塔脚竖向提升。指挥汽车吊缓慢起吊,当钢箱梁离地面约100mm时,停止10 分钟后,进行三项检查:⑴起重机的受力是否良好;⑵吊耳受力是否完好; ⑶钢丝绳吊索、卸扣的受力是否完好。若均正常,则指挥浮吊缓慢回转;(4) Command the transport vehicle to drive away from the position, put the tower foot on the ground again, and switch the position of the lifting point to lift the tower foot vertically. Instruct the truck crane to lift slowly. When the steel box girder is about 100mm from the ground, stop for 10 minutes and then carry out three inspections: (1) Whether the force of the crane is good; (2) Whether the force of the lifting lug is in good condition; Whether the force is intact. If all are normal, command the floating crane to rotate slowly;

(5)待索塔节段缓慢前移至就位位置上空后,再缓慢变幅,将钢索塔节 段吊装就位。稳住索塔节段,对准方位,缓慢将索塔节段松落在临时支墩上, 调整完毕后,指挥起重机松下吊钩,摘除吊索、卸扣;(5) After the cable tower segment is slowly moved forward to the air above the in-position position, slowly change the amplitude and hoist the steel cable tower segment into place. Stabilize the cable tower section, align the orientation, slowly loosen the cable tower section on the temporary support pier, and after the adjustment is completed, instruct the crane to loosen the hook and remove the sling and shackle;

(6)在第二、第三节段吊装时,根据设计要求缝口的大小,用限位码板 作好衬垫固定,专用焊接用码板定位牢固,确保中心轴线的正确性;(6) When the second and third sections are hoisted, according to the size of the seam required by the design, use the limit code plate to make a pad to fix it, and the special welding code plate is firmly positioned to ensure the correctness of the central axis;

现场拼装时必须配备足量的马板,马板的厚度14~28mm,马板厚度与构 件板厚度基本相当,置放马板的间距约500~800mm之间,具体设置根据接口 实际情况而定,但最大不得超过800mm,以确保接口双边构件板的刚度;When assembling on site, a sufficient amount of slats must be provided. The thickness of the slats is 14-28mm. The thickness of the slats is basically the same as the thickness of the component boards. The spacing between the slats is about 500-800mm. The specific setting depends on the actual situation of the interface. , but the maximum shall not exceed 800mm to ensure the rigidity of the double-sided member plate of the interface;

3、钢索塔现场焊接3. On-site welding of steel cable towers

定位焊及返修焊接:采用焊条电弧焊方法;Tack welding and repair welding: using electrode arc welding method;

顶板对接焊缝:采用陶质衬垫混合气体(CO2/Ar,CO2含量20-25%)保护 焊打底,埋弧自动焊盖面,或用陶质衬垫混合气体保护焊打底及盖面方法;Butt weld on top plate: use ceramic liner mixed gas (CO2/Ar, CO2 content 20-25%) shielded welding for bottoming, submerged arc automatic welding cover surface, or use ceramic liner mixed gas shielded welding for bottoming and cover face method;

底板及纵腹板对接焊缝:采用陶质衬垫混合气体保护焊打底及盖面方法;Butt weld of bottom plate and longitudinal web: use ceramic liner mixed gas shielded welding for bottoming and covering method;

其他对接、角接焊缝:采用混合气体保护焊或焊条电弧焊方法。Other butt and fillet welds: use mixed gas shielded welding or electrode arc welding.

对箱梁内部要求全熔透的对接焊缝,应尽量采用陶质衬垫混合气体保护 焊方法焊接,以减少箱梁内部碳弧气刨清根,减少烟尘量。For the butt welds that require full penetration inside the box girder, the mixed gas shielded welding method of ceramic liner should be used as far as possible to reduce the carbon arc air gouging inside the box girder and reduce the amount of smoke and dust.

4、桥塔底部转绞设置4. The twist setting at the bottom of the bridge tower

在桥塔竖转过程中,因塔体在立面内旋转至75°,所以在塔体底部设置 旋转销轴。由于底部要承受巨大的水平和垂直荷载,且此时塔体未形成整体, 整体性较差,因此在耳板处做了适度加强,以使销轴的局部荷载较均匀的传 递至塔体上。竖转到位后,对接补焊合拢段及内置肋板,其中,转铰耳板考 虑不拆除将作为永久结构放置于桥塔内During the vertical rotation of the bridge tower, because the tower body rotates to 75° in the elevation, a rotating pin is set at the bottom of the tower body. Since the bottom has to bear huge horizontal and vertical loads, and the tower body is not integrated at this time, the integrity is poor, so moderate reinforcement is made at the ear plate to make the local load of the pin shaft more uniformly transmitted to the tower body . After the vertical position, the butt-welded closed section and the built-in rib plate, among which the hinged lug plate will be placed in the bridge tower as a permanent structure without removing it.

5、前后锚点及提升设备的设置5. Setting of front and rear anchor points and lifting equipment

(1)前锚为预张拉锚点,由张拉专用钢绞线、前锚耳板、张拉吊具等组 成,桥塔单侧对应各设置2个张拉锚点,单个张拉锚点采用2个张拉吊具;(1) The front anchor is a pre-tensioned anchor point, which consists of special steel strands for tensioning, front anchor lugs, tensioning hangers, etc. Two tensioning anchor points are set on each side of the bridge tower, and a single tensioning anchor The point adopts 2 tension spreaders;

(2)后锚为提升锚点,由后拉基础、提升专用钢绞线、液压提升器、提 升吊具、后锚埋件耳板、临时墩等组成,桥塔单侧对应各设置2个提升吊点;(2) The rear anchor is the lifting anchor point, which consists of the rear pulling foundation, the special steel strand for lifting, the hydraulic lifter, the lifting spreader, the rear anchor embedded ear plate, and the temporary pier. Lift the lifting point;

(3)采用液压同步提升设备吊装桥塔,需要设置专用提升平台,即合理 的提升上吊点,提升上吊点布置液压提升器,提升器通过提升专用钢绞线与 塔身上的对应下吊点地锚相连接。提升上吊点作为液压提升器操作平台,能 够承受一定的载荷。考上,通过吊笼内放置液压提升器,利用销轴将后锚的 穿孔耳板连接成整体。虑将提升上吊点设在桥面后锚;(3) To hoist the bridge tower with hydraulic synchronous lifting equipment, it is necessary to set up a special lifting platform, that is, a reasonable lifting point, and a hydraulic lifter is arranged at the lifting point. Anchor connection. The lifting point is used as a hydraulic lifter operating platform, which can bear a certain load. In the test, the hydraulic lifter is placed in the hanging cage, and the perforated ear plate of the rear anchor is connected as a whole by the pin shaft. Consider setting the lifting point at the rear anchor of the bridge deck;

6、钢副塔(门架)设置6. Steel auxiliary tower (gantry) setting

钢副塔竖转工装主要由张拉系统、门架、提升吊具和转铰等组成,考虑 将门架同桥塔的连接位置做成活动铰接支座的形式,利用穿孔耳板,销轴连 接。门架立柱采用P420x16的圆管,横、斜腹杆为P180x6,中间联系桁架横 杆采用P273x10的圆管,横、斜腹杆为P180x6。The vertical rotation tooling of the steel auxiliary tower is mainly composed of a tensioning system, a gantry, a lifting spreader and a hinge. . The gantry column adopts P420x16 round pipe, the transverse and oblique web rods are P180x6, the intermediate connecting truss transverse rod adopts P273x10 round pipe, and the transverse and inclined web rods are P180x6.

7、竖转提升7. Vertical rotation lifting

(1)在地面上人工把下好料的钢绞线单根按从下到上的顺序穿进锚板并 打紧夹片,副钢塔端锚板孔钢绞线外露约300mm(主钢塔端钢绞线外露约 600mm),保证每根外露长度一至及钢绞线的旋向各一半。首先把单根钢绞线 先穿进一端锚具孔上夹片,然后用滚动方式把钢绞线放线完成再穿进另一端 锚具孔上夹片。依次重复直至穿束完成,安装两端防松压板,钢绞线穿束完 成。用汽车吊把张拉吊具起吊至主副钢塔的万向支座处,采用手拉葫芦配合 调节安装销轴将张拉吊具与万向支座进行连接牢固。小桩号(钢绞线)穿束 吊装完成。(1) Manually put a single strand of the well-loaded steel strand into the anchor plate in the order from bottom to top on the ground and tighten the clips. The exposed end of the steel strand is about 600mm), to ensure that each exposed length is one to one and the direction of rotation of the steel strand is half. First, put a single steel strand into the upper clip of the anchor hole at one end, and then use the rolling method to pay off the steel strand and then pass it into the upper clip of the other end of the anchor hole. Repeat this sequence until the bundling is completed, install the anti-loosening pressure plates at both ends, and complete the bundling of the steel strands. Lift the tensioning spreader to the universal support of the main and auxiliary steel towers with a car hoist, and use the chain hoist to cooperate with the adjustment and installation pin to connect the tensioning spreader and the universal support firmly. The small station (steel strand) is threaded and the hoisting is completed.

(2)桥面上将锚具安装在副钢塔的提升吊具上,并用约16mm厚7字型 钢板与提升吊具焊接牢固。(2) Install the anchor on the lifting sling of the auxiliary steel tower on the bridge deck, and use a 7-shaped steel plate with a thickness of about 16mm to weld firmly with the hoisting sling.

在桥面上人工把下好料的钢绞线单根解索按从下到上的顺序穿进锚板并 打紧夹片,提升吊具端钢绞线外露约300mm,保证每根外露长度一至及钢绞线 的旋向各一半,并且每个提升吊具中的第一根钢绞线用白色喷漆做好标识。 首先把钢绞线先穿进提升吊具的锚具孔上夹片,然后用滚动方式把钢绞线放 线完成再穿进对应孔位的专用分丝板上,过程中保证分丝板与提升吊具的锚 具孔位一一对应,不得有锚孔现像。依次重复直至穿束完成,后安提升吊具 上锚具的防松压板,钢绞线穿束完成。On the bridge deck, manually put the single unloaded steel strand into the anchor plate in the order from bottom to top and tighten the clips, and the exposed steel strand at the end of the lifting sling is about 300mm, ensuring that each exposed length is one to one And the rotation direction of the steel strand is half, and the first steel strand in each lifting spreader is marked with white spray paint. First, put the steel strand into the upper clip of the anchor hole of the hoisting spreader, and then use the rolling method to complete the pay-off of the steel strand and then pass it into the special wire splitting plate corresponding to the hole position. The anchor holes of the lifting spreader are in one-to-one correspondence, and there shall be no anchor holes. Repeat in sequence until the threading is completed, then install the anti-loosening pressure plate of the anchor on the lifting spreader, and the threading of the steel strand is completed.

(3)全面检查提升系统、锚具、钢绞线、吊点结构等,一切正常后,四 台提升千斤顶同步分级加载20%、40%、60%、80%进行试转,加载过程中,实 时监测塔顶位移,以确保其在设计范围内。如一切正常,继续同步分级加载 提升千斤顶,直至100%并使主钢塔离开地面拼装胎架约10cm时,停止提升竖 转。(3) Comprehensively check the lifting system, anchorage, steel strand, lifting point structure, etc. After everything is normal, the four lifting jacks are loaded with 20%, 40%, 60%, and 80% synchronously in stages for trial rotation. During the loading process, The tower top displacement is monitored in real time to ensure it is within the design range. If everything is normal, continue to load and lift the jacks synchronously in stages, until the main steel tower is about 10cm away from the ground to assemble the tire frame, and then stop lifting and vertical rotation.

停留2小时以上后,检查临时竖转结构、提升系统、钢绞线形松弛状态、 锚具锚固状态、基础、吊点、底部铰点等,在确认整个提升工况绝对安全的 前提下,开始正式提升竖转,其间每隔10米测量各吊点标高,实时监测门架 顶部位移,使之保持在允许范围内60mm以内,确保各吊点同步提升。提升至 接近设计位置,测量控制,放慢提升速度,利用液压提升设备对各桥塔进行 竖直方向微调,精确定位。竖转完成转入下道工序焊接。After staying for more than 2 hours, check the temporary vertical swivel structure, hoisting system, slack state of steel strands, anchorage state, foundation, lifting point, bottom hinge point, etc. On the premise of confirming that the entire hoisting condition is absolutely safe, start the formal inspection. When lifting and rotating vertically, the elevation of each lifting point is measured every 10 meters, and the displacement of the top of the gantry is monitored in real time to keep it within 60mm within the allowable range to ensure that each lifting point is lifted synchronously. Lift to close to the design position, measure and control, slow down the lifting speed, and use hydraulic lifting equipment to fine-tune the vertical direction of each bridge tower for precise positioning. After the vertical rotation is completed, it is transferred to the next process for welding.

在竖转过程中,要求后锚处各提升点有一个观察员,随时与泵站操作员 保持通信畅通,确保提升竖转作业安全进行。During the vertical rotation process, an observer at each lifting point at the rear anchor is required to maintain smooth communication with the pump station operator at any time to ensure the safe lifting and vertical rotation operation.

同时本说明书中未作详细描述的内容均属于本领域技术人员公知的现有 技术。Meanwhile, the content not described in detail in this specification belongs to the prior art known to those skilled in the art.

需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来 将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示 这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、 “包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系 列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明 确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有 的要素。It should be noted that, in this document, relational terms such as first and second are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or apparatus that includes a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus.

尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而 言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行 多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限 定。Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, and substitutions can be made in these embodiments without departing from the principle and spirit of the invention and modifications, the scope of the invention is defined by the appended claims and their equivalents.

Claims (8)

1.斜拉桥异形钢主塔竖向转体施工工法,其特征在于:包括以下步骤:1. the construction method of vertical swivel of special-shaped steel main tower of cable-stayed bridge is characterized in that: comprise the following steps: S1、搭设临时拼装平台,主塔结构拼装同桥面呈5°进行,在地面上完成整体拼装;S1. Set up a temporary assembly platform, the main tower structure is assembled at 5° with the bridge deck, and the overall assembly is completed on the ground; S2、拼装钢副塔,安装两侧吊笼、液压提升器、转绞等,将钢副塔门架安装于桥塔上,桥塔上设置前拉锚点,地面上墩附近设置后拉锚点;S2. Assemble the steel auxiliary tower, install the hanging cages on both sides, hydraulic lifters, twisting, etc., install the steel auxiliary tower gantry on the bridge tower, set the front anchor point on the bridge tower, and set the rear anchor near the pier on the ground point; S3、进行液压同步竖转系统设备调试,试竖转;S3. Debug the hydraulic synchronous vertical rotation system equipment and test the vertical rotation; S4、同步分级加载竖转器和稳定索具;S4, synchronously graded loading of the vertical swivel and stable rigging; S5、桥塔预竖转后停留2小时以上,检查临时竖转结构、稳定索系统、竖转系统、基础、吊点、底部铰点等,在确认整个竖转工况绝对安全的前提下,开始正式竖转S5. After the pre-vertical rotation of the bridge tower, stay for more than 2 hours, check the temporary vertical rotation structure, stable cable system, vertical rotation system, foundation, lifting point, bottom hinge point, etc. On the premise that the entire vertical rotation condition is absolutely safe, Start the official vertical rotation S6、竖转至接近设计位置,测量控制,放慢竖转速度,利用液压竖转设备对各桥塔进行竖直方向微调,精确定位;S6. Vertically rotate to close to the design position, measure and control, slow down the vertical rotation speed, and use hydraulic vertical rotation equipment to fine-tune the vertical direction of each bridge tower for precise positioning; S7、竖转就位后,进行桥塔合拢焊接工作;S7. After the vertical rotation is in place, the bridge tower is closed and welded; S8、液压同步竖转系统设备卸载作业,至钢绞线完全松弛,使桥塔整体落位;液压同步竖转设备及钢副塔等其它竖转用临时措施全部拆除,完成桥塔竖转安装工作。S8. The hydraulic synchronous vertical swivel system equipment is unloaded until the steel strands are completely relaxed, so that the bridge tower can be placed in place as a whole; the hydraulic synchronous vertical swivel equipment and other temporary measures for vertical swivel such as steel auxiliary towers are all removed, and the vertical swivel installation of the bridge tower is completed. Work. 2.根据权利要求1所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述S1步骤中,斜拉索最大跨径为180m,主桥为32m、38m、110m独塔双跨混合梁斜拉桥。2. The construction method for vertical swivel of the special-shaped steel main tower of a cable-stayed bridge according to claim 1, characterized in that: in the step S1, the maximum span of the stay cable is 180m, and the main bridge is 32m, 38m, 110m Single tower double span hybrid beam cable-stayed bridge. 3.根据权利要求1所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述S2步骤中,拉锚点分为前锚和后锚,且前锚为预张拉锚点,由张拉专用钢绞线、前锚耳板和张拉吊具等相互组成,所述桥塔单侧对应各设置2个张拉锚点,且单个张拉锚点采用2个张拉吊具。3. The construction method for vertical swivel of the special-shaped steel main tower of a cable-stayed bridge according to claim 1, characterized in that: in the step S2, the anchor point is divided into a front anchor and a rear anchor, and the front anchor is pretensioned The tension anchor point is composed of the special steel strand for tensioning, the front anchor ear plate and the tensioning hanger. Tensioning spreader. 4.根据权利要求3所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述后锚为提升锚点,由后拉基础、提升专用钢绞线、液压提升器、提升吊具、后锚埋件耳板和临时墩等相互组成,所述桥塔单侧对应各设置2个提升吊点。4. The construction method for vertical swivel of the special-shaped steel main tower of a cable-stayed bridge according to claim 3, characterized in that: the rear anchor is a lifting anchor point. , lifting spreader, rear anchor embedded ear plate and temporary pier are composed of each other, and two lifting points are set corresponding to each side of the bridge tower. 5.根据权利要求1所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述S2步骤中,液压提升器在使用时设置有专用提升平台。5 . The construction method for the vertical swivel of the special-shaped steel main tower of the cable-stayed bridge according to claim 1 , wherein: in the step S2 , the hydraulic lifter is provided with a special lifting platform when in use. 6 . 6.根据权利要求1所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述S2步骤中,钢副塔门架立柱采用P420x16的圆管,且横、斜腹杆为P180x6,所述中间联系桁架横杆采用P273x10的圆管,且横、斜腹杆为P180x6。6. the special-shaped steel main tower vertical swivel construction method of the cable-stayed bridge according to claim 1, is characterized in that: in the described S2 step, the steel auxiliary tower gantry column adopts the round pipe of P420x16, and the horizontal and inclined belly The rods are P180x6, the middle connecting truss cross rods are P273x10 round pipes, and the transverse and oblique web rods are P180x6. 7.根据权利要求5所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述液压提升器调节压力为3-4MPa。7 . The vertical swivel construction method of the special-shaped steel main tower of a cable-stayed bridge according to claim 5 , wherein the hydraulic lifter regulates the pressure to 3-4MPa. 8 . 8.根据权利要求1所述的斜拉桥异形钢主塔竖向转体施工工法,其特征在于:所述步骤6中,测量控制为计算机控制系统,其中吊点同步不均时,最大高低差预警值为20-25mm。8. The special-shaped steel main tower vertical swivel construction method of a cable-stayed bridge according to claim 1, characterized in that: in the step 6, the measurement control is a computer control system, and when the lifting points are unevenly synchronized, the maximum height The difference warning value is 20-25mm.
CN202110720398.6A 2021-06-28 2021-06-28 Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge Pending CN114382015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110720398.6A CN114382015A (en) 2021-06-28 2021-06-28 Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110720398.6A CN114382015A (en) 2021-06-28 2021-06-28 Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge

Publications (1)

Publication Number Publication Date
CN114382015A true CN114382015A (en) 2022-04-22

Family

ID=81194885

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110720398.6A Pending CN114382015A (en) 2021-06-28 2021-06-28 Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge

Country Status (1)

Country Link
CN (1) CN114382015A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115287998A (en) * 2022-09-28 2022-11-04 湖南省交通规划勘察设计院有限公司 Special-shaped cable-stayed bridge structure and construction method thereof
CN116479770A (en) * 2023-04-18 2023-07-25 宁波通途投资开发有限公司 A vertical rotation method for the main tower of a single-tower double-layer steel truss girder cable-stayed bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10195826A (en) * 1997-01-09 1998-07-28 Japan Steel & Tube Constr Co Ltd Bridge construction method and device thereof
JPH11181723A (en) * 1997-12-18 1999-07-06 East Japan Railway Co Construction method of erection and rotation of members by towing
CN101122114A (en) * 2007-09-14 2008-02-13 中铁大桥局集团第五工程有限公司 Back-cable-free cable-stayed bridge steel tower vertical turn construction method
CN104532756A (en) * 2014-12-15 2015-04-22 武汉市市政建设集团有限公司 Bi-directional traction vertical rotation construction method for cable-stayed bridge steel arch tower
CN105464001A (en) * 2015-11-05 2016-04-06 中铁十八局集团有限公司 Construction method of backward vertical rotation of steel tower

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10195826A (en) * 1997-01-09 1998-07-28 Japan Steel & Tube Constr Co Ltd Bridge construction method and device thereof
JPH11181723A (en) * 1997-12-18 1999-07-06 East Japan Railway Co Construction method of erection and rotation of members by towing
CN101122114A (en) * 2007-09-14 2008-02-13 中铁大桥局集团第五工程有限公司 Back-cable-free cable-stayed bridge steel tower vertical turn construction method
CN104532756A (en) * 2014-12-15 2015-04-22 武汉市市政建设集团有限公司 Bi-directional traction vertical rotation construction method for cable-stayed bridge steel arch tower
CN105464001A (en) * 2015-11-05 2016-04-06 中铁十八局集团有限公司 Construction method of backward vertical rotation of steel tower

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
康俊涛;何林;范杰;黄祥国;汪大海;: "马蹄形独塔斜拉桥钢主塔竖转施工监控关键技术", 公路, no. 01 *
李宇航;: "蕴藻浜公路大桥斜塔竖转采用超大型液压同步提升技术研究", 铁道建筑技术, no. 04, pages 77 - 81 *
陈军;程华强;高云;夏鹏;秦松;张哲;: "独塔斜拉桥钢拱塔竖转方案设计与施工", 交通科技, no. 01, pages 83 - 86 *
马恒;: "龙城大桥钢索塔竖转施工关键技术", 现代交通技术, no. 03 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115287998A (en) * 2022-09-28 2022-11-04 湖南省交通规划勘察设计院有限公司 Special-shaped cable-stayed bridge structure and construction method thereof
CN115287998B (en) * 2022-09-28 2023-03-03 湖南省交通规划勘察设计院有限公司 Special-shaped cable-stayed bridge structure and construction method thereof
CN116479770A (en) * 2023-04-18 2023-07-25 宁波通途投资开发有限公司 A vertical rotation method for the main tower of a single-tower double-layer steel truss girder cable-stayed bridge

Similar Documents

Publication Publication Date Title
CN101736700B (en) Construction method for hoisting broad width steel box girder cantilever
CN106115500B (en) A kind of high-rise building is special, and tearing formula roofing open hangs and tears open certainly method certainly
CN101225638A (en) Installation Method of Prestressed Concrete Stiffened Box Girder of Ground Anchored Suspension Bridge
CN113685040A (en) Large-span steel truss hoisting construction method
CN102587288B (en) Method for lifting steel box girder segments of cable-stayed bridge
CN106744351A (en) The method of hoisting the main girder of the cable-stayed bridge by using the cable crane
CN114873497B (en) Vertical lifting installation device and method for variable-diameter unbalanced load equipment
CN114382015A (en) Construction method for vertical rotation of special-shaped steel main tower of cable-stayed bridge
CN113200459B (en) The Stress State Adjustable Spreader and Its Application on the Roof Installation of Prefabricated Subway Station
CN101725114B (en) Method for hoisting hawser of long-span cable-stayed bridge and equipment thereof
CN115506604B (en) Method for installing first truss of large-span steel structure
CN116062596A (en) A method for hoisting the superstructure of a quay bridge
CN110562850A (en) Main tower integral hoisting system and method
CN110104568B (en) Tower crane installation self-checking evaluation method
CN116043713A (en) A Method for Erection of Steel Girders of Suspension Bridge by Vertical Assembly and Lifting in Air
CN101402436A (en) Method and apparatus for disassembling cargo boom of climbing tower crane
CN111576227B (en) Construction method of main and secondary arches of double-wing arch bridge and the hoisting equipment used therein
CN205346600U (en) Big plate -girder hoist and mount specialized tool
CN204983693U (en) Hoist device slides in mountain area corridor truss high altitude
CN117776008A (en) Construction process for installing and detaching tower crane
CN107487724B (en) Non-crane-assisted large floating crane arm support mounting device and mounting method
CN214531431U (en) Truss combination roof truss of opening string roof beam and encorbelmenting
CN114314372A (en) Method for installing inter-floor suspension arm and floor suspension arm
CN105883645A (en) How to remove the tower crane attachment device
CN219490682U (en) Basket hanging device for prestress construction of light T-pier cantilever cap beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220422