WO2008107558A1 - Static carousel - Google Patents

Static carousel Download PDF

Info

Publication number
WO2008107558A1
WO2008107558A1 PCT/FR2008/000076 FR2008000076W WO2008107558A1 WO 2008107558 A1 WO2008107558 A1 WO 2008107558A1 FR 2008000076 W FR2008000076 W FR 2008000076W WO 2008107558 A1 WO2008107558 A1 WO 2008107558A1
Authority
WO
WIPO (PCT)
Prior art keywords
equipment
robot
production line
zone
molten metal
Prior art date
Application number
PCT/FR2008/000076
Other languages
French (fr)
Inventor
Alfred Reiter
Eric Costantini
Original Assignee
Cinetic Automation Sa
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cinetic Automation Sa filed Critical Cinetic Automation Sa
Priority to EP08761793A priority Critical patent/EP2112961B1/en
Priority to DE602008002053T priority patent/DE602008002053D1/en
Priority to AT08761793T priority patent/ATE476271T1/en
Publication of WO2008107558A1 publication Critical patent/WO2008107558A1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D47/00Casting plants
    • B22D47/02Casting plants for both moulding and casting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D33/00Equipment for handling moulds

Definitions

  • the invention relates to a new concept of automated production line for metal parts, in particular by gravitational casting.
  • Automated production lines of metal pieces by gravity casting of the state of the art include:
  • an installation of the prior art comprises a carousel which carries 4 to 8 molding equipment called shellers.
  • European Patent No. 1626830 discloses a casting chain of the prior art, organized around a carousel.
  • the shells consist of a frame that carries the different parts of the fixed or mobile mold (traps - drawers).
  • the rotation of the carousel makes it possible to transport each sheller successively in front of each unit of work, among which is:
  • a remoulding unit which consists of placing the assembled core in the mold.
  • a casting unit for pouring the metal melt into the molds
  • an extraction unit for extracting all the solidified metal and the cores.
  • a buffer stock of cores connects the core production unit to the carousel.
  • Downstream there is a set of means for ensuring the final cooling and completion of the parts.
  • this provision no longer responds appropriately to the requirements of modern production lines, particularly in terms of flexibility, ergonomics, maintainability and safety: s - the arrangement of shells on a carousel in rotation limits the possibilities of intervention and maintenance and makes dangerous the changes of molds and any intervention of the operators;
  • the object of the present invention is to overcome these disadvantages by proposing a production line using fixed workstations.
  • this arrangement makes it possible to eliminate the drawbacks of the casting carousel and to offer a flexible and flexible industrial tool.
  • the invention relates, in its most general sense, to an automated production line for metal parts comprising at least equipment for preparing molten metal, molding equipment, equipment for preparing cores, and equipment for finishing, characterized in that said mold preparation and finishing equipment are stationary, and in that the production line comprises a first poly-articulated casting robot (5) for transporting the molten metal to the equipment a second poly-articulated robot (6) for transporting cores assembled from core preparation equipment to molding equipment and a third poly-articulated extraction robot (7) for extracting mold parts after they have solidified and for transport to a downstream station .
  • the production line according to the invention comprises, in a path of movement of said robots, successively a first zone
  • said robot moving path is a single-lane path, the first robot being movable between the molten metal preparation zone and the second robot, and the third robot being movable between the second robot and the zone of the robot stations. finish.
  • said path of displacement is linear.
  • said displacement path is arched, closed or circular.
  • the production line according to the invention may comprise at least two equipment for preparing the molten metal loaded with metals of different natures.
  • the invention also relates to a process for the preparation of molded parts which comprises three main steps of extraction of the molded part, re-molding of the cores and casting of the metal, said steps being carried out by three mobile robots (5 to 7) between a zone for preparing the molten metal
  • the solution according to the invention consists in using three poly-articulated robots moving linearly (alternately in a circular path) to the ground.
  • Each robot is assigned to a particular operation: the first robot ("casting") transports the molten metal from the holding furnaces to the molds;
  • the second robot (“remoulding”) is used to transport the cores from a supply conveyor to the shells.
  • the third robot (“extraction”) is used to extract the parts of the shellers after they are solidified and to transport them, either on the cooling mat or on an intermediate treatment station (finishing station, de-reuse machine). It also ensures the transfer of the part from said intermediate processing stations and the cooling mat.
  • the functions of extraction and remoulding could be performed by a single robot equipped with 2 clamps or a device for changing clamps.
  • the robots circulate on the same rail to serve alternately the different machines arranged on either side of this rail (alternatively outside the circle formed by the rail), which are typically 6 in view of the time required to casting and solidification of the pieces.
  • a different number of casting machines is possible, as one can imagine any kind of geometric configuration of these machines depending on the implementation constraints of the line.
  • FIG. 1 shows a schematic view of a production line according to the invention, in a linear configuration
  • FIG. 2 shows a schematic view of a production line according to the invention, in a linear configuration, during the extraction phase of the molded part;
  • FIG. 3 shows a schematic view of a production line according to the invention, in a linear configuration, during the phase of depositing a molded part on a finishing equipment
  • - Figure 4 shows a schematic view of a production line according to the invention, in a linear configuration during the output phase of the molded part
  • FIG. 5 shows a schematic view of a production line according to the invention, in a linear configuration, during the return phase at the beginning of a new cycle
  • FIG. 6 shows a schematic view of a production line according to the invention, in a circular configuration
  • FIG. 7 shows a schematic view of a production line according to the invention, in a circular configuration, during the extraction phase of the molded part;
  • FIG. 8 shows a schematic view of a production line according to the invention, in circular configuration, during the phase of depositing a molded part on a finishing equipment
  • - Figure 9 shows a schematic view of a production line according to the invention, in circular configuration during the output phase of the molded part
  • FIG. 10 shows a schematic view of a production line according to the invention, in a circular configuration, during the return phase at the beginning of a new cycle.
  • Figure 1 shows a general view of the production line of molded metal parts according to the invention.
  • the chain is organized in three main zones: - a first zone (1) of implantation of the furnaces (8),
  • a path (4) traverses these three zones (1 to 3), and allows the movement of three robots (5 to 7):
  • a first poly-articulated casting robot (5) for transporting the molten metal from the oven to the mold
  • a second poly-articulated remoulding robot (6) for transporting the cores from a supply conveyor to the shells, -
  • a third robot (7) poly-articulated extraction for extracting parts shellers after solidification and for transport to a downstream station.
  • the first zone (1) is intended to receive one or more furnaces intended for melting of the metal intended for molding. Each oven can process a different alloy bath.
  • This first zone (1) also comprises a ladle skin blowing station (9), intended to remove the alumina skin that forms, in contact with the air, in the ladle after pouring into the molds.
  • a ladle skin blowing station (9) intended to remove the alumina skin that forms, in contact with the air, in the ladle after pouring into the molds.
  • the first robot (5) draws in the oven using the ladle attached to the end of the articulated arm in the case of a direct-setting furnace, or takes the ladle previously filled with a dose of molten metal in the case of a metering furnace.
  • the first robot (5) then moves to one of the shellers (10, 11, 12, 13, 14, 15) in the second zone (2).
  • the robot (5) then controls the displacement of the ladle above the mold to cause the filling of the latter according to a casting law specific to each part reference.
  • Each law of casting is configurable in the control system of the installation.
  • the size of the ladle and its level of filling are defined according to the weight of the piece and its various casting appendages.
  • the introduction of the liquid metal is mainly due to the gravity in the mold of the shellfish according to the principle of gravity casting.
  • the sheller who carries the mold may be tilting.
  • the filling is achieved by the sole action of the weight of the metal, the mold must be designed so that the footprint in its entirety is filled.
  • the second zone comprises shellfish (10,11,12,13,14,15) carrying the different parts of each mold (20,21,22,23,24,25).
  • Each mold (20 to 25) has a pouring basin for filling.
  • the feeding of a mold by gravity comprises 3 phases controlled by the first robot (5).
  • 1 - First phase Pouring into the pouring basin of the mold, according to a programmable casting law.
  • flyweights In order to avoid cavities being created at the moment of this contraction, nourishing masses or reserves of liquid metal, called flyweights, are filled at the time of casting.
  • the second robot (6) moves in the zone (2) and (2A), between the shellers (10 to 15) and the nucleus preparation station (2A).
  • the third zone (3) may include the various finishing stations: the breaking of the cores to separate the piece (s) that has just been poured, the core of sand. It is therefore to break the core, for example on a vibrating table or manually, with instruments such as hammers or electric or pneumatic chipping hammers, sand removal and recycling, breaks jets to separate the room of different appendages casting, and heat and / or chemical treatments to improve the mechanical characteristics of the parts obtained in aluminum casting.
  • the operations performed by the robots (5 to 7) comprise three main steps:
  • the extraction robot (7) and the remoaming robot (6) are stationed in the area (2A) and (3).
  • the casting robot (5) is waiting in the zone of the furnaces with the casting ladle stationed above the bath (8) or according to the case is ready to grab a ladle.
  • the extraction robot (7) manipulates the molded part to extract it from the mold (22),
  • the second remoulding robot (6) is positioned in front of the mold to be treated and deposits the cores. At the same time the first casting robot (5) draws in the furnace to fill the ladle, or as appropriate seizes a ladle.
  • the following step illustrated by FIG. 4 has for object the removal of the piece on the conveyor belt (30).
  • the remoulding robot (6) moves towards the zone (2B) 1 followed by the casting robot (5) which is positioned in front of the shell maker (22) to be treated.
  • the extraction robot loads a finalized part (31) onto a conveyor, in general, for transfer to a cooling tunnel.
  • FIG. 5 The next step illustrated in Figure 5 is the return of the robot (5) to the furnaces. Simultaneously, the casting robot (5) returns to the zone (1) to blow the ladle. In parallel, the remoaming robot (6), followed by the extraction robot (7), is positioned in the zone of the next sheller to be treated.
  • Figures 6 to 10 show an alternative embodiment in circular configuration.
  • the equipment comprises a closed displacement path, in the described example of circular shape.
  • Three poly-articulated robots (5, 6, 7) move on this circular path. These robots (5, 6, 7) can be positioned each in front of any one of the workstations. Each workstation has an area closed by a partition wall (102) with the station following an access door (101) whose opening is locked when the workstation is active.
  • This access door (101) allows an operator to access the equipment arranged inside the workstation in a secure manner.
  • a second access door (103) provided on the moving path side allows access to the arm of one of the robots. This door (103) is lockable when the workstation is idle, to allow maintenance operations safely.
  • Figure 7 shows a schematic view of a production line in circular configuration, during the extraction phase of the molded part.
  • Figure 8 shows a view of the production line, in a circular configuration, during the phase of depositing a molded part on finishing equipment.
  • Figure 9 shows a view of the production line, in circular configuration, during the exit phase of the molded part.
  • Figure 10 shows a view of the production line, in a circular configuration, during the return phase at the beginning of a new cycle.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Casting Devices For Molds (AREA)
  • Injection Moulding Of Plastics Or The Like (AREA)
  • Liquid Crystal (AREA)
  • Transition And Organic Metals Composition Catalysts For Addition Polymerization (AREA)
  • Photoreceptors In Electrophotography (AREA)
  • Polymers With Sulfur, Phosphorus Or Metals In The Main Chain (AREA)
  • Molds, Cores, And Manufacturing Methods Thereof (AREA)

Abstract

The invention relates to an automated production line for metal parts, that comprises at least equipments for preparing the molten metal, core preparation equipments, moulding equipments, and finishing equipments, characterised in that said equipments are fixed, and in that the production line includes a first polyarticulated casting robot (5) for the transport from the equipments for preparing the molten metal to the moulding equipments, a second polyarticulated robot (6) for transporting the assembled cores from the core preparation equipments to the moulding equipments, and a third stripping polyarticulated robot (7) for stripping the parts from the moulds once they have solidified and for transporting them to a downstream station.

Description

CARROUSEL STATIQUE STATIC CARROUSEL
L'invention concerne un nouveau concept de ligne de production automatisée de pièces métalliques, notamment par coulée gravitaire. Les lignes de production automatisées de pièces métalliques par coulée gravitaire de l'état de la technique comprennent :The invention relates to a new concept of automated production line for metal parts, in particular by gravitational casting. Automated production lines of metal pieces by gravity casting of the state of the art include:
- un ensemble de machines destinées à préparer les moules (coquilles, noyaux) ;- a set of machines for preparing mussels (shells, cores);
- des fours de fusion et/ou de maintien du métal liquide ; - un chantier de coulée dont la fonction est de verser le métal liquide dans les moules, et, lorsque la pièce est solidifiée, à l'extraire de son moule ;- Melting furnaces and / or maintaining the liquid metal; - A casting site whose function is to pour the liquid metal into the molds, and when the part is solidified, to extract it from its mold;
- diverses installations en aval (refroidissement, débourrage des noyaux, démasselotage etc.) en fonction du type de pièce produite et du niveau de finition souhaité.- various downstream installations (cooling, coring, demasseling, etc.) depending on the type of part produced and the desired level of finish.
Typiquement une installation de l'art antérieur comprend un carrousel qui porte de 4 à 8 équipements de moulage appelés coquilleuses. Le brevet européen n° 1626830 décrit une chaîne de coulée de l'art antérieur, organisée autour d'un carrousel. La coquilleuse est constituée d'un bâti qui porte les différentes parties du moule fixe ou mobiles (chappes - tiroirs). La rotation du carrousel permet de transporter chaque coquilleuse successivement devant chaque unité de travail, parmi lesquelles se trouve :Typically an installation of the prior art comprises a carousel which carries 4 to 8 molding equipment called shellers. European Patent No. 1626830 discloses a casting chain of the prior art, organized around a carousel. The shells consist of a frame that carries the different parts of the fixed or mobile mold (traps - drawers). The rotation of the carousel makes it possible to transport each sheller successively in front of each unit of work, among which is:
- une unité de production de noyaux assemblés ;a unit for producing assembled cores;
- une unité de remmoulage qui consiste à poser le noyau assemblé dans le moule.- A remoulding unit which consists of placing the assembled core in the mold.
- une unité de coulée pour le coulage de la masse fondue de métal dans les moules ;a casting unit for pouring the metal melt into the molds;
- des unités pour le refroidissement du métal dans les moules ;units for cooling the metal in the molds;
- une unité d'extraction pour extraire l'ensemble du métal solidifié et les noyaux.an extraction unit for extracting all the solidified metal and the cores.
En général, en amont, un stock tampon de noyaux relie l'unité de production de noyaux au carrousel. En aval, on trouve un ensemble de moyens destinés à assurer le refroidissement final et le parachèvement des pièces. Bien qu'étant adoptée dans la plupart des installations existantes, cette disposition ne répond plus de manière appropriée aux exigences des lignes de production modernes, notamment en termes de flexibilité, d'ergonomie, de maintenabilité et de sécurité : s - la disposition des coquilleuses sur un carrousel en rotation limite les possibilités d'intervention et de maintenance et rend dangereux les changements de moules et toute intervention des opérateurs ;In general, upstream, a buffer stock of cores connects the core production unit to the carousel. Downstream, there is a set of means for ensuring the final cooling and completion of the parts. Although adopted in most existing installations, this provision no longer responds appropriately to the requirements of modern production lines, particularly in terms of flexibility, ergonomics, maintainability and safety: s - the arrangement of shells on a carousel in rotation limits the possibilities of intervention and maintenance and makes dangerous the changes of molds and any intervention of the operators;
- le remplacement d'un moule est impossible lorsque les autres moules sont en phase de production ; 0 - les possibilités de modulation du temps de cycle en fonction de la pièce produite sont limitées par construction ;the replacement of a mold is impossible when the other molds are in the production phase; 0 - the possibilities of modulation of the cycle time depending on the piece produced are limited by construction;
- la concentration des équipements autour du carrousel crée une zone extrêmement encombrée qui ne facilite pas les opérations d'entretien.- the concentration of equipment around the carousel creates an extremely congested area that does not facilitate maintenance operations.
- Enfin, la mise en œuvre du carrousel, dont la partie mobile pèses généralement plus de 30 tonnes, est coûteuse et nécessite d'emporter et de distribuer sur le carrousel toutes les énergies, notamment gaz, eau, électricité, et fluides hydrauliques.- Finally, the implementation of the carousel, whose moving part generally weighs more than 30 tons, is expensive and requires to carry and distribute on the carousel all energies, including gas, water, electricity, and hydraulic fluids.
Le but de la présente invention est de remédier à ces inconvénients en0 proposant une ligne de production mettant en oeuvre des postes de travail fixesThe object of the present invention is to overcome these disadvantages by proposing a production line using fixed workstations.
(alors qu'ils étaient mobiles dans la solution carrousel) et à rendre mobiles les robots réalisant les opérations de remmoulage, de coulée et d'extraction(while they were mobile in the carousel solution) and to make mobile the robots realizing the operations of rewinding, casting and extraction
(précédemment fixes). Mise en oeuvre de manière adéquate, cette disposition permet de supprimer les inconvénients du carrousel de coulée et d'offrir un outils industriel modulable et flexible.(previously fixed). Properly implemented, this arrangement makes it possible to eliminate the drawbacks of the casting carousel and to offer a flexible and flexible industrial tool.
À ce titre, l'invention concerne selon son acception la plus générale une chaîne de production automatisée de pièces métalliques comportant au moins des équipements de préparation du métal en fusion, des équipements de0 moulage, des équipements de préparation des noyaux, et des équipements de finition, caractérisée en ce que lesdits équipements de préparation de moules et de finition sont fixes, et en ce que la chaîne de production comprend un premier robot (5) poly-articulé de coulée, pour le transport du métal en fusion jusqu'aux équipements de moulage, un second robot (6) poly-articulé pour le transport des noyaux assemblés depuis des équipements de préparation de noyaux jusqu'aux équipements de moulage et un troisième robot (7) poly-articulé d'extraction pour l'extraction des pièces des moules après qu'elles sont solidifiées et pour leur transport sur un poste aval. De préférence, la chaîne de production selon l'invention comporte, selon un chemin de déplacement desdits robots, successivement une première zoneAs such, the invention relates, in its most general sense, to an automated production line for metal parts comprising at least equipment for preparing molten metal, molding equipment, equipment for preparing cores, and equipment for finishing, characterized in that said mold preparation and finishing equipment are stationary, and in that the production line comprises a first poly-articulated casting robot (5) for transporting the molten metal to the equipment a second poly-articulated robot (6) for transporting cores assembled from core preparation equipment to molding equipment and a third poly-articulated extraction robot (7) for extracting mold parts after they have solidified and for transport to a downstream station . Preferably, the production line according to the invention comprises, in a path of movement of said robots, successively a first zone
(1) pour l'implantation d'un ou plusieurs équipements de préparation du métal en fusion, une deuxième zone (2) pour l'implantation d'une pluralité d'équipements de moulage et pour l'implantation des équipements de préparation des noyaux ( 2A ), une troisième zone (3) pour l'implantation d'un ou de plusieurs équipements de finition des pièces moulées, et une quatrième zone de préparation des noyaux.(1) for the implantation of one or more equipment for preparing the molten metal, a second zone (2) for the implantation of a plurality of molding equipment and for the implantation of the equipment for preparing the cores (2A), a third zone (3) for the implantation of one or more finishing equipment for the molded parts, and a fourth zone for preparing the cores.
Avantageusement, ledit chemin de déplacement des robots est un chemin à voie unique, le premier robot étant mobile entre la zone de préparation du métal en fusion et le second robot, et le troisième robot étant mobile entre le second robot et la zone des postes de finition.Advantageously, said robot moving path is a single-lane path, the first robot being movable between the molten metal preparation zone and the second robot, and the third robot being movable between the second robot and the zone of the robot stations. finish.
Selon une première variante, ledit chemin de déplacement est linéaire. Selon une autre variante, ledit chemin de déplacement est arqué, fermé ou circulaire. La chaîne de production selon l'invention peut comprendre au moins deux équipements de préparation du métal en fusion chargés avec des métaux de natures différentes.According to a first variant, said path of displacement is linear. According to another variant, said displacement path is arched, closed or circular. The production line according to the invention may comprise at least two equipment for preparing the molten metal loaded with metals of different natures.
L'invention concerne également un procédé de préparation de pièces moulées qui comprend trois étapes principales d'extraction de la pièce moulée, de remmoulage des noyaux et de coulée du métal, lesdites étapes étant réalisées par trois robots mobiles (5 à 7) entre une zone de préparation du métal en fusionThe invention also relates to a process for the preparation of molded parts which comprises three main steps of extraction of the molded part, re-molding of the cores and casting of the metal, said steps being carried out by three mobile robots (5 to 7) between a zone for preparing the molten metal
(1), une zone de moulage (2) et une zone de finition (3).(1), a molding zone (2) and a finishing zone (3).
Il permet également d'inclure des opérations manuelles (prélèvement d'échantillons pour contrôle, inspection, maintenance, petites séries) dans des conditions de sécurité et d'ergonomie optimales.It also allows to include manual operations (sampling for control, inspection, maintenance, small series) in optimal safety and ergonomic conditions.
La solution conforme à l'invention consiste à utiliser trois robots poly-articulés se déplaçant linéairement (alternativement selon une trajectoire circulaire) au sol.The solution according to the invention consists in using three poly-articulated robots moving linearly (alternately in a circular path) to the ground.
Chaque robot est affecté à une opération particulière : - le premier robot (« coulée ») transporte le métal en fusion depuis les fours de maintien jusqu'aux moules ;Each robot is assigned to a particular operation: the first robot ("casting") transports the molten metal from the holding furnaces to the molds;
- le second robot (« remmoulage ») sert à transporter les noyaux depuis un convoyeur d'amenée jusqu'aux coquilleuses. - le troisième robot (« extraction ») sert à extraire les pièces des coquilleuses après qu'elles sont solidifiées et à les transporter, soit sur le tapis de refroidissement, soit sur un poste de traitement intermédiaire (poste de finition, débourreuse). Il permet également d'assurer le transfert de la pièce depuis lesdits postes de traitement intermédiaire et le tapis de refroidissement. En fonction des contraintes de cadence et de temps de cycle, les fonctions d'extraction et de remmoulage pourraient être réalisées par un seul robot équipé de 2 pinces ou d'un dispositif de changement de pinces.- the second robot ("remoulding") is used to transport the cores from a supply conveyor to the shells. - The third robot ("extraction") is used to extract the parts of the shellers after they are solidified and to transport them, either on the cooling mat or on an intermediate treatment station (finishing station, de-reuse machine). It also ensures the transfer of the part from said intermediate processing stations and the cooling mat. Depending on the constraints of cadence and cycle time, the functions of extraction and remoulding could be performed by a single robot equipped with 2 clamps or a device for changing clamps.
Les robots circulent sur un même rail pour desservir alternativement les différentes machines disposées de part et d'autre de ce rail (alternativement à l'extérieur du cercle formé par le rail), qui sont typiquement au nombre de 6 compte tenu des temps nécessaires à la coulée et à la solidification des pièces. Un nombre différent de machines de coulée est envisageable, de même que l'on peut imaginer toute sorte de configuration géométrique de ces machines en fonction des contraintes d'implantation de la ligne.The robots circulate on the same rail to serve alternately the different machines arranged on either side of this rail (alternatively outside the circle formed by the rail), which are typically 6 in view of the time required to casting and solidification of the pieces. A different number of casting machines is possible, as one can imagine any kind of geometric configuration of these machines depending on the implementation constraints of the line.
L'invention sera mieux comprise à la lecture de la description qui suit, se référant aux dessins annexés relatifs à des exemples non limitatifs de réalisation OÙ :The invention will be better understood on reading the description which follows, with reference to the appended drawings relating to nonlimiting examples of embodiment where:
- la figure 1 représente une vue schématique d'une chaîne de production selon l'invention, en configuration linéaire ;- Figure 1 shows a schematic view of a production line according to the invention, in a linear configuration;
- la figure 2 représente une vue schématique d'une chaîne de production selon l'invention, en configuration linéaire, pendant la phase d'extraction de la pièce moulée ;- Figure 2 shows a schematic view of a production line according to the invention, in a linear configuration, during the extraction phase of the molded part;
- la figure 3 représente une vue schématique d'une chaîne de production selon l'invention, en configuration linéaire, pendant la phase de dépose d'une pièce moulée sur un équipement de finition ; - la figure 4 représente une vue schématique d'une chaîne de production selon l'invention, en configuration linéaire, pendant la phase de sortie de la pièce moulée ;- Figure 3 shows a schematic view of a production line according to the invention, in a linear configuration, during the phase of depositing a molded part on a finishing equipment; - Figure 4 shows a schematic view of a production line according to the invention, in a linear configuration during the output phase of the molded part;
- la figure 5 représente une vue schématique d'une chaîne de production selon l'invention, en configuration linéaire , pendant la phase de retour au début d'un nouveau cycle ;- Figure 5 shows a schematic view of a production line according to the invention, in a linear configuration, during the return phase at the beginning of a new cycle;
- la figure 6 représente une vue schématique d'une chaîne de production selon l'invention, en configuration circulaire ;- Figure 6 shows a schematic view of a production line according to the invention, in a circular configuration;
- la figure 7 représente une vue schématique d'une chaîne de production selon l'invention, en configuration circulaire, pendant la phase d'extraction de la pièce moulée ;- Figure 7 shows a schematic view of a production line according to the invention, in a circular configuration, during the extraction phase of the molded part;
- la figure 8 représente une vue schématique d'une chaîne de production selon l'invention, en configuration circulaire, pendant la phase de dépose d'une pièce moulée sur un équipement de finition ; - la figure 9 représente une vue schématique d'une chaîne de production selon l'invention, en configuration circulaire, pendant la phase de sortie de la pièce moulée ;- Figure 8 shows a schematic view of a production line according to the invention, in circular configuration, during the phase of depositing a molded part on a finishing equipment; - Figure 9 shows a schematic view of a production line according to the invention, in circular configuration during the output phase of the molded part;
- la figure 10 représente une vue schématique d'une chaîne de production selon l'invention, en configuration circulaire, pendant la phase de retour au début d'un nouveau cycle.- Figure 10 shows a schematic view of a production line according to the invention, in a circular configuration, during the return phase at the beginning of a new cycle.
La figure 1 représente une vue générale de la chaîne de production de pièces métalliques moulées selon l'invention. La chaîne est organisée en trois zones principales : - une première zone (1) d'implantation des fours (8),Figure 1 shows a general view of the production line of molded metal parts according to the invention. The chain is organized in three main zones: - a first zone (1) of implantation of the furnaces (8),
- une deuxième zone (2) d'implantation des moules,a second zone (2) for implanting the molds,
- une troisième zone (3) des équipements de finition.a third zone (3) of finishing equipment.
Un chemin de déplacement (4) traverse ces trois zones (1 à 3), et permet le déplacement de trois robots (5 à 7) :A path (4) traverses these three zones (1 to 3), and allows the movement of three robots (5 to 7):
- un premier robot (5) poly-articulé de coulée, pour le transport du métal en fusion depuis le four jusqu'au moule,a first poly-articulated casting robot (5) for transporting the molten metal from the oven to the mold,
- un second robot (6) poly-articulé de remmoulage pour le transport des noyaux depuis un convoyeur d'amenée jusqu'aux coquilleuses, - un troisième robot (7) poly-articulé d'extraction pour l'extraction des pièces des coquilleuses après solidification et pour leur transport sur un poste aval.a second poly-articulated remoulding robot (6) for transporting the cores from a supply conveyor to the shells, - A third robot (7) poly-articulated extraction for extracting parts shellers after solidification and for transport to a downstream station.
La première zone (1) est destinée à recevoir un ou plusieurs fours destinés à la mise en fusion du métal destiné au moulage. Chaque four peut traiter un bain d'alliage différent.The first zone (1) is intended to receive one or more furnaces intended for melting of the metal intended for molding. Each oven can process a different alloy bath.
Cette première zone (1) comprend également un poste de soufflage des peaux de louche (9), destiné à enlever la peau d'alumine qui se forme, au contact de l'air, dans la louche après la verse dans les moules.This first zone (1) also comprises a ladle skin blowing station (9), intended to remove the alumina skin that forms, in contact with the air, in the ladle after pouring into the molds.
Selon le type de four, le premier robot (5) puise dans le four à l'aide de la louche fixée à l'extrémité du bras articulé dans le cas d'un four à prise direct, ou prend la louche préalablement remplie avec une dose de métal en fusion dans le cas d'un four doseur. Le premier robot (5) se déplace ensuite vers une des coquilleuses (10, 11 , 12, 13, 14, 15) dans la deuxième zone (2).Depending on the type of oven, the first robot (5) draws in the oven using the ladle attached to the end of the articulated arm in the case of a direct-setting furnace, or takes the ladle previously filled with a dose of molten metal in the case of a metering furnace. The first robot (5) then moves to one of the shellers (10, 11, 12, 13, 14, 15) in the second zone (2).
Le robot (5) commande alors le déplacement de la louche au-dessus du moule pour provoquer le remplissage de ce dernier selon une loi de coulée spécifique à chaque référence de pièce. Chaque loi de coulée est paramétrable dans le système de pilotage de l'installation. La taille de la louche et son niveau de remplissage sont définis en fonction du poids de la pièce et de ses différents appendices de coulée.The robot (5) then controls the displacement of the ladle above the mold to cause the filling of the latter according to a casting law specific to each part reference. Each law of casting is configurable in the control system of the installation. The size of the ladle and its level of filling are defined according to the weight of the piece and its various casting appendages.
L'introduction du métal liquide est principalement due à la pesanteur dans le moule de la coquilleuse selon le principe de coulée par gravité. Pour faciliter cette coulée, et selon les applications, la coquilleuse qui porte le moule pourra être basculante.The introduction of the liquid metal is mainly due to the gravity in the mold of the shellfish according to the principle of gravity casting. To facilitate this casting, and according to the applications, the sheller who carries the mold may be tilting.
Le remplissage se réalisant sous la seule action du poids du métal, le moule doit être conçu pour que l'empreinte dans sa totalité soit bien remplie.The filling is achieved by the sole action of the weight of the metal, the mold must be designed so that the footprint in its entirety is filled.
La deuxième zone comprend des coquilleuses (10,11 ,12,13,14,15) portant les différentes parties de chaque moule (20,21 ,22,23,24,25).The second zone comprises shellfish (10,11,12,13,14,15) carrying the different parts of each mold (20,21,22,23,24,25).
Chaque moule (20 à 25) est doté d'un bassin de verse pour le remplissage. L'alimentation d'un moule par gravité comporte 3 phases commandées par le premier robot (5). 1 - Première phase : Coulée dans le bassin de verse du moule, suivant une loi de coulée programmable.Each mold (20 to 25) has a pouring basin for filling. The feeding of a mold by gravity comprises 3 phases controlled by the first robot (5). 1 - First phase: Pouring into the pouring basin of the mold, according to a programmable casting law.
2 - Deuxième phase : De ce bassin, le remplissage de l'empreinte par le métal en fusion s'effectue par la descente de coulée, le canal d'alimentation et d'attaque. En pénétrant dans le moule le métal chasse l'air par des tirages d'air.2 - Second phase: From this basin, the filling of the impression by the molten metal is carried out by the pouring down, the feed and attack channel. By penetrating into the mold the metal flushes the air by air drafts.
3 - Troisième phase : Le masselottage, qui sert à compenser la contraction du métal de la pièce au moment de la solidification.3 - Third phase: The masselottage, which serves to compensate the contraction of the metal of the part at the time of solidification.
Afin d'éviter, qu'au moment de cette contraction, des cavités ne se créent, on remplit, au moment de la coulée, des masses nourrissantes ou réserves de métal liquide, appelées masselottes.In order to avoid cavities being created at the moment of this contraction, nourishing masses or reserves of liquid metal, called flyweights, are filled at the time of casting.
Le deuxième robot (6) se déplace dans la zone (2) et (2A), entre les coquilleuses (10 à 15) et le ou les postes de préparation des noyaux (2A).The second robot (6) moves in the zone (2) and (2A), between the shellers (10 to 15) and the nucleus preparation station (2A).
À ce ou ces postes sont présentés des noyaux déjà assemblés ou, selon le cas, des parties de noyaux qui seront assemblées par le robot (6) avant l'opération de dépose dans le moule concerné (20 à 25).At these or these stations are presented already assembled cores or, as the case may be, parts of cores which will be assembled by the robot (6) before the removal operation in the concerned mold (20 to 25).
La troisième zone (3) peut comprendre les différents postes de finition : le cassage des noyaux pour séparer la (les) pièce(s) que l'on vient de couler, du noyau de sable. Il s'agit donc de casser le noyau, par exemple sur une table vibrante ou manuellement, avec des instruments tels que des marteaux ou des marteaux burineurs électriques ou pneumatiques, suppression du sable et recyclage, les casse jets pour séparer la pièce des différents appendices de coulée, et traitements thermiques et/ou chimiques pour améliorer les caractéristiques mécaniques des pièces obtenues en fonderie d'aluminium.The third zone (3) may include the various finishing stations: the breaking of the cores to separate the piece (s) that has just been poured, the core of sand. It is therefore to break the core, for example on a vibrating table or manually, with instruments such as hammers or electric or pneumatic chipping hammers, sand removal and recycling, breaks jets to separate the room of different appendages casting, and heat and / or chemical treatments to improve the mechanical characteristics of the parts obtained in aluminum casting.
Les opérations effectuées par les robots (5 à 7) comprennent trois étapes principales :The operations performed by the robots (5 to 7) comprise three main steps:
- extraction de la pièce moulée,- extraction of the molded part,
- remmoulage des noyaux, et- remmoulage of the nuclei, and
- coulée du métal. Les trois robots mobiles sur un axe linéaire, ou sur un axe circulaire évoluent dans l'ordre suivant :- casting of metal. The three mobile robots on a linear axis, or on a circular axis evolve in the following order:
1 - Robot poly articulé (7) pour l'extraction de la pièce moulée,1 - articulated poly robot (7) for extracting the molded part,
2 - Robot poly articulé (6) pour le remmoulage des noyaux assemblés, 3 - Robot poly articulé (5) pour la coulée du métal.2 - Articulated poly robot (6) for re-molding assembled cores, 3 - Articulated poly robot (5) for casting metal.
Le robot d'extraction (7) et le robot de remmoulage (6) sont stationnés dans la zone (2A) et (3).The extraction robot (7) and the remoaming robot (6) are stationed in the area (2A) and (3).
Dans un cycle de production, l'enchaînement des opérations est le suivant :In a production cycle, the sequence of operations is as follows:
- lors de la phase d'extraction de la pièce moulée (figure 2), le robot de coulée (5) est en attente dans la zone des fours avec la louche de coulée en stationnement au-dessus du bain (8) ou selon le cas est prêt à saisir une louche. Le robot d'extraction (7) manipule la pièce moulée pour l'extraire du moule (22),during the extraction phase of the molded part (FIG. 2), the casting robot (5) is waiting in the zone of the furnaces with the casting ladle stationed above the bath (8) or according to the case is ready to grab a ladle. The extraction robot (7) manipulates the molded part to extract it from the mold (22),
- l'étape suivante illustrée par la figure 3 a pour objet la dépose de la pièce coulée au poste de finition et se traduit par l'évolution du robot d'extraction (7) dans la zone de finition (3).- The next step illustrated in Figure 3 is to remove the casting at the finishing station and results in the evolution of the extraction robot (7) in the finishing area (3).
Le deuxième robot (6) de remmoulage se positionne devant le moule à traiter et dépose les noyaux. Parallèlement le premier robot (5) de coulée puise dans le four pour remplir la louche, ou selon le cas saisit une louche.The second remoulding robot (6) is positioned in front of the mold to be treated and deposits the cores. At the same time the first casting robot (5) draws in the furnace to fill the ladle, or as appropriate seizes a ladle.
- l'étape suivante illustrée par la figure 4 a pour objet la dépose de la pièce sur le tapis convoyeur (30).the following step illustrated by FIG. 4 has for object the removal of the piece on the conveyor belt (30).
Le robot (6) de remmoulage se déplace vers la zone (2B)1 suivi par le robot de coulée (5) qui se positionne devant la coquilleuse (22) à traiter. Parallèlement le robot d'extraction charge une pièce finalisée (31) sur un convoyeur, en général, pour le transfert vers un tunnel de refroidissement.The remoulding robot (6) moves towards the zone (2B) 1 followed by the casting robot (5) which is positioned in front of the shell maker (22) to be treated. In parallel, the extraction robot loads a finalized part (31) onto a conveyor, in general, for transfer to a cooling tunnel.
- l'étape suivante illustrée par la figure 5 a pour objet le retour du robot (5) vers les fours. Simultanément, le robot de coulée (5) revient dans la zone (1) pour procéder au soufflage de la louche. Parallèlement le robot de remmoulage (6), suivi du robot d'extraction (7) viennent se positionner dans la zone de la prochaine coquilleuse à traiter. Les figures 6 à 10 représentent une variante de réalisation en configuration circulaire. L'équipement comporte un chemin de déplacement fermé, dans l'exemple décrit de forme circulaire. Trois robots poly-articulés (5, 6, 7) se déplacent sur ce chemin circulaire. Ces robots (5, 6, 7) peuvent être positionnés chacun devant l'un quelconque des postes de travail. Chaque poste de travail comporte une zone fermée par une paroi de séparation (102) avec le poste suivant une porte d'accès (101) dont l'ouverture est verrouillée lorsque le poste de travail est en activité. Cette porte d'accès (101) permet à un opérateur d'accéder à l'équipement disposé à l'intérieur du poste de travail de manière sécurisée. Une deuxième porte d'accès (103) prévue du côté du chemin de déplacement permet l'accès au bras de l'un des robots. Cette porte (103) est verrouillable lorsque le poste de travail est inactif, afin de permettre des opérations de maintenance en toute sécurité.- The next step illustrated in Figure 5 is the return of the robot (5) to the furnaces. Simultaneously, the casting robot (5) returns to the zone (1) to blow the ladle. In parallel, the remoaming robot (6), followed by the extraction robot (7), is positioned in the zone of the next sheller to be treated. Figures 6 to 10 show an alternative embodiment in circular configuration. The equipment comprises a closed displacement path, in the described example of circular shape. Three poly-articulated robots (5, 6, 7) move on this circular path. These robots (5, 6, 7) can be positioned each in front of any one of the workstations. Each workstation has an area closed by a partition wall (102) with the station following an access door (101) whose opening is locked when the workstation is active. This access door (101) allows an operator to access the equipment arranged inside the workstation in a secure manner. A second access door (103) provided on the moving path side allows access to the arm of one of the robots. This door (103) is lockable when the workstation is idle, to allow maintenance operations safely.
La figure 7 représente une vue schématique d'une chaîne de production en configuration circulaire, pendant la phase d'extraction de la pièce moulée.Figure 7 shows a schematic view of a production line in circular configuration, during the extraction phase of the molded part.
La figure 8 représente une vue de la chaîne de production, en configuration circulaire, pendant la phase de dépose d'une pièce moulée sur un équipement de finition.Figure 8 shows a view of the production line, in a circular configuration, during the phase of depositing a molded part on finishing equipment.
La figure 9 représente une vue de la chaîne de production, en configuration circulaire, pendant la phase de sortie de la pièce moulée.Figure 9 shows a view of the production line, in circular configuration, during the exit phase of the molded part.
La figure 10 représente une vue de la chaîne de production, en configuration circulaire, pendant la phase de retour au début d'un nouveau cycle. Figure 10 shows a view of the production line, in a circular configuration, during the return phase at the beginning of a new cycle.

Claims

REVENDICATIONS
1 - Chaîne de production automatisée de pièces métalliques comportant au moins des équipements de préparation du métal en fusion, des équipements de moulage, des équipements de préparation des noyaux, et des équipements de finition, caractérisée en ce que lesdits équipements de préparation de moules et de finition sont fixes, et en ce que la chaîne de production comprend un premier robot mobile (5) poly-articulé de coulée, pour le transport du métal en fusion jusqu'aux équipements de moulage, un second robot mobile (6) poly-articulé pour le transport des noyaux assemblés depuis des équipements de préparation de noyaux jusqu'aux équipements de moulage et un troisième robot (7) poly-articulé d'extraction pour l'extraction des pièces des moules après qu'elles sont solidifiées et pour leur transport sur un poste aval.1 - Automated production line for metal parts comprising at least equipment for preparing molten metal, molding equipment, equipment for preparing cores, and finishing equipment, characterized in that said equipment for preparing molds and are fixed, and in that the production line comprises a first poly-articulated mobile robot (5) for casting, for the transport of the molten metal to the molding equipment, a second mobile robot (6) poly- articulated for transporting cores assembled from core preparation equipment to molding equipment and a third poly-articulated extraction robot (7) for extracting mold parts after they have solidified and for their transport on a downstream station.
2 - Chaîne de production selon la revendication 1 , caractérisée en ce qu'elle comporte, selon un chemin de déplacement desdits robots, successivement une première zone (1) pour l'implantation d'un ou plusieurs équipements de préparation du métal en fusion, une deuxième zone (2) pour l'implantation d'une pluralité d'équipements de moulage et pour l'implantation des équipements de préparation des noyaux ( 2A ), et une troisième zone (3) pour l'implantation d'un ou de plusieurs équipements de finition des pièces moulées, et une quatrième zone de préparation des noyaux.2 - A production line according to claim 1, characterized in that it comprises, in a path of movement of said robots, successively a first zone (1) for the implantation of one or more equipment for preparing the molten metal, a second zone (2) for the implantation of a plurality of molding equipment and for the implantation of the core preparation equipment (2A), and a third zone (3) for the implantation of one or more several finishing equipment of the molded parts, and a fourth zone of preparation of the cores.
3 - Chaîne de production selon la revendication 2, caractérisée en ce que ledit chemin de déplacement des robots est un chemin à voie unique, le premier robot étant mobile entre la zone de préparation du métal en fusion et le second robot, et le troisième robot étant mobile entre le second robot et la zone des postes de finition.3 - production line according to claim 2, characterized in that said robot moving path is a single-lane path, the first robot being movable between the molten metal preparation zone and the second robot, and the third robot being mobile between the second robot and the area of the finishing stations.
4 - Chaîne de production selon la revendication 2 ou 3, caractérisée en ce que ledit chemin de déplacement est linéaire.4 - production line according to claim 2 or 3, characterized in that said path of movement is linear.
5 - Chaîne de production selon la revendication 2 ou 3, caractérisée en ce que ledit chemin de déplacement est arqué, fermé ou circulaire. 6 - Chaîne de production selon l'une au moins des revendications précédentes, caractérisée en ce qu'elle comprend au moins deux équipements de préparation du métal en fusion chargés avec des métaux de natures différentes.5 - production line according to claim 2 or 3, characterized in that said path is arched, closed or circular. 6 - Production line according to at least one of the preceding claims, characterized in that it comprises at least two equipment for preparing the molten metal loaded with metals of different natures.
7 - Chaîne de production selon l'une au moins des revendications précédentes, caractérisée en ce qu'elle comprend seulement un premier robot mobile (5) poly-articulé de coulée, pour le transport du métal en fusion depuis les équipements de préparation du métal en fusion jusqu'aux équipements de moulage, un second robot mobile (6-7) poly-articulé pour le transport des noyaux assemblés depuis des équipements de préparation des noyaux jusqu'aux équipements de moulage et pour l'extraction des pièces des moules après qu'elles sont solidifiées et pour leur transport sur un poste aval.7 - production line according to at least one of the preceding claims, characterized in that it comprises only a first mobile robot (5) poly-articulated casting, for the transport of molten metal from the metal preparation equipment in fusion to the molding equipment, a second poly-articulated mobile robot (6-7) for transporting the cores assembled from the core preparation equipment to the molding equipment and for extracting the mold parts after that they are solidified and for their transport on a downstream station.
8 - Procédé de préparation de pièces moulées, caractérisé en ce qu'il comprend trois étapes principales d'extraction de la pièce moulée, de remmoulage des noyaux et de coulée du métal, lesdites étapes étant réalisées par trois robots mobiles (5 à 7) entre une zone de préparation du métal en fusion (1), une zone de moulage (2) et une zone de finition (3). 8 - Process for preparing molded parts, characterized in that it comprises three main steps of extraction of the molded part, remmoulage of the cores and casting of the metal, said steps being carried out by three mobile robots (5 to 7) between a molten metal preparation zone (1), a molding zone (2) and a finishing zone (3).
PCT/FR2008/000076 2007-01-22 2008-01-22 Static carousel WO2008107558A1 (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
EP08761793A EP2112961B1 (en) 2007-01-22 2008-01-22 Static carousel
DE602008002053T DE602008002053D1 (en) 2007-01-22 2008-01-22 STATIC CAROUSEL
AT08761793T ATE476271T1 (en) 2007-01-22 2008-01-22 STATIC CAROUSEL

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
FR0752812A FR2911522B1 (en) 2007-01-22 2007-01-22 AUTOMATED PRODUCTION CHAIN OF METAL PARTS AND MOLDING METHOD
FR0752812 2007-01-22
FR0704079 2007-06-07
FR0704079A FR2911521B1 (en) 2007-01-22 2007-06-07 STATIC CARROUSEL

Publications (1)

Publication Number Publication Date
WO2008107558A1 true WO2008107558A1 (en) 2008-09-12

Family

ID=38475200

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/FR2008/000076 WO2008107558A1 (en) 2007-01-22 2008-01-22 Static carousel

Country Status (5)

Country Link
EP (1) EP2112961B1 (en)
AT (1) ATE476271T1 (en)
DE (1) DE602008002053D1 (en)
FR (2) FR2911522B1 (en)
WO (1) WO2008107558A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111993053A (en) * 2020-06-28 2020-11-27 武汉中车电牵科技有限公司 Welding process for rail transit box girder framework and lean production layout method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102581228B (en) * 2012-02-20 2013-08-28 浙江万丰科技开发有限公司 Automatic core assembly production line of robot

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2635702A1 (en) * 1988-09-01 1990-03-02 Fischer Ag Georg METHOD AND DEVICE FOR MOLDING
US20010003931A1 (en) * 1999-12-16 2001-06-21 Atsushi Suzuki Apparatus and method for producing metal formed product
US20060000571A1 (en) * 2004-06-28 2006-01-05 Crafton Scott P Method and apparatus for removal of flashing and blockages from a casting
EP1626830B1 (en) * 2003-12-19 2006-06-28 Hydro Aluminium Alucast GmbH Production line and method for the continuous production of cast parts from a molten metal, in particular a molten light alloy

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2635702A1 (en) * 1988-09-01 1990-03-02 Fischer Ag Georg METHOD AND DEVICE FOR MOLDING
US20010003931A1 (en) * 1999-12-16 2001-06-21 Atsushi Suzuki Apparatus and method for producing metal formed product
FR2802454A1 (en) * 1999-12-16 2001-06-22 Honda Motor Co Ltd APPARATUS AND METHOD FOR MANUFACTURING A LIGHTWEIGHT METAL PRODUCT
EP1626830B1 (en) * 2003-12-19 2006-06-28 Hydro Aluminium Alucast GmbH Production line and method for the continuous production of cast parts from a molten metal, in particular a molten light alloy
US20060000571A1 (en) * 2004-06-28 2006-01-05 Crafton Scott P Method and apparatus for removal of flashing and blockages from a casting

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
HUI ZHANG ET AL: "Machining with flexible manipulator: toward improving robotic machining performance", ADVANCED INTELLIGENT MECHATRONICS. PROCEEDINGS, 2005 IEEE/ASME INTERNATIONAL CONFERENCE ON MONTEREY, CA JULY 24-28, 2005, PISCATAWAY, NJ, USA,IEEE, 24 July 2005 (2005-07-24), pages 1127 - 1132, XP010837769, ISBN: 0-7803-9047-4 *
SALLINEN M ET AL: "Planning of sensory feedback in industrial robot workcells", ROBOTICS AND AUTOMATION, 2006. ICRA 2006. PROCEEDINGS 2006 IEEE INTERNATIONAL CONFERENCE ON ORLANDO, FL, USA MAY 15-19, 2006, PISCATAWAY, NJ, USA,IEEE, 15 May 2006 (2006-05-15), pages 675 - 680, XP010921350, ISBN: 0-7803-9505-0 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111993053A (en) * 2020-06-28 2020-11-27 武汉中车电牵科技有限公司 Welding process for rail transit box girder framework and lean production layout method thereof

Also Published As

Publication number Publication date
FR2911522B1 (en) 2009-02-27
DE602008002053D1 (en) 2010-09-16
FR2911522A1 (en) 2008-07-25
EP2112961A1 (en) 2009-11-04
FR2911521B1 (en) 2009-02-27
FR2911521A1 (en) 2008-07-25
ATE476271T1 (en) 2010-08-15
EP2112961B1 (en) 2010-08-04

Similar Documents

Publication Publication Date Title
MX2013014363A (en) Arrangement and method for moulds for metal casting.
FR2822738A1 (en) Automated casting installation incorporates several casting stations, a molten metal lifting station, and robotic displacement devices for controlled and co-ordinated casting operations
EP2112961B1 (en) Static carousel
CN111565869A (en) Method and device for producing metal ingots
JP2866593B2 (en) Casting equipment
KR20160100630A (en) Shell Removing Apparatus For Lost Wax Casting And Method Thereof
KR0168725B1 (en) Process and device for the unpacking of casting clusters
CA2123254A1 (en) Casting process and system
FR2635702A1 (en) METHOD AND DEVICE FOR MOLDING
SU1007552A3 (en) Device for removal of casting from boxless moulds
JP2002321051A (en) Method of casting and casting line
KR101765028B1 (en) Shell Removing Apparatus For Lost Wax Casting And Method Thereof
FR2462953A1 (en) DEVICE FOR THE MANUFACTURE OF LIGHT METAL MOLDED PARTS USING PERMANENT MOLDS, PARTICULARLY FOR THE MAKING OF CYLINDER CYLINDER HEADS FOR INTERNAL COMBUSTION ENGINES
EP3283248B1 (en) Method and system for indexing moulds
FR2802454A1 (en) APPARATUS AND METHOD FOR MANUFACTURING A LIGHTWEIGHT METAL PRODUCT
JPS62207555A (en) Gate breaker for die casting product
SU1771436A3 (en) Automated cashing production line
US1823671A (en) Method of and apparatus for casting
US1031202A (en) Apparatus for forming castings.
JP2000176632A (en) Method for removing molding flask for mold and device thereof
EP3842167B1 (en) Mold extraction device from mold string conveyor
JPH0780628A (en) Casting method and apparatus
JPH02155533A (en) Casting device
SU1012500A1 (en) Rotary line for centrifugal casting of liners
US1230360A (en) Casting-machine.

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 08761793

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 2008761793

Country of ref document: EP

NENP Non-entry into the national phase

Ref country code: DE