WO2002101156A1 - A method of reinforcing an offshore structure - Google Patents

A method of reinforcing an offshore structure Download PDF

Info

Publication number
WO2002101156A1
WO2002101156A1 PCT/NO2002/000204 NO0200204W WO02101156A1 WO 2002101156 A1 WO2002101156 A1 WO 2002101156A1 NO 0200204 W NO0200204 W NO 0200204W WO 02101156 A1 WO02101156 A1 WO 02101156A1
Authority
WO
WIPO (PCT)
Prior art keywords
installation
concrete
support points
deck
support
Prior art date
Application number
PCT/NO2002/000204
Other languages
English (en)
French (fr)
Inventor
Arnstein Godejord
Original Assignee
Mpu Enterprise As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mpu Enterprise As filed Critical Mpu Enterprise As
Publication of WO2002101156A1 publication Critical patent/WO2002101156A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B17/0034Maintenance, repair or inspection of offshore constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • E02B2017/0052Removal or dismantling of offshore structures from their offshore location

Definitions

  • the present invention relates to a method of reinforcing of an offshore structure (installation), preferably a platform deck, when one or more of the natural support point(s)/lifting point(s) for the installation is (are) missing in connection with mounting/disassembling and transport of the installation, where the removal of one or more of the natural support points of the installation is compensated for by transfer of forces which are effective in the absent support points to other support points/lifting points.
  • the deck is reinforced to be able to bear the lifting and the floating to the shore.
  • the lifting vessel is flexible as to size and weight of the deck, but in some cases the vessel will not offer a support as good as the natural substructure did. Because the gain by lifting/floating the deck in one operation is so high, it is a desire in these cases to reinforce the deck to rearrange the forces out to the support points of the lifting vessel instead of disassemble/unload the deck at sea and float this to land in several operations.
  • deck structures consist of a framework of steel.
  • One way of reinforcement of such a structure is of course mounting (welding) new elements on the existing.
  • This invention is an alternative to this solution.
  • An object of this invention is to give cost savings and time savings compared to previous solutions as for instance installing new steel elements.
  • Another object of the method is that it should be flexible with regard to geometry and loads on the structure which shall be reinforced.
  • the objects of this invention are achieved by a method for reinforcement of an offshore installation as indicated in the introduction of the description, and which is characterised by that the forces from the lacking support points are transferred to the other support points by means of pre-tensioning cables which are cast into concrete and are tensioned after the curing of the concrete.
  • an offshore installation (structure) 1 which can be a platform deck construction, is shown with three supports (support points) 2, 3, 4.
  • the natural support point 2 for the deck construction cannot be used when the deck is being lifted and transported. Consequently, the forces from the lacking support point 2 have to be transferred to the other support points 3, 4.
  • This is done by placing a formwork 7 in the form of plastic or steel pipe with thin walls extending from the fastening point of support 3 to the deck structure 1 and to the lower area of the support 2 and further to the fastening point of the support 4 to the deck structure 1.
  • One or more pre-tensioning cables 5 are centrally introduced into the formwork cavity and fastened in the fastening area of the support 3, 4 to the deck structure.
  • the fastening of the pre-tensioning cable 5 in these areas is adjustable so that the degree of pretensioning the cable can be adjusted.
  • Concrete 6 is poured (filled) into the formwork 7 and thus encompasses pre- tensioning cable 5. After the curing of the concrete 6 the cable 5 is tightened in each end, so that the concrete 6 is pressurised. Tension in the cable 5 is achieved in this way and compression in the surrounding concrete 6 is achieved. During loading the tensioning force in the tension cable 5 will be further increased, while the compressive force in the concrete 6 is reduced.
  • pre-tensioning After loading the degree , of pre-tensioning still can be adjusted, although an adjustment of the pre-tension after the cables have been definitely tightened (100%) normally is not done.
  • variation of the force gives very small variation of tension in the pre-tensioning cables. Almost all variation takes place in the concrete (as long as the concrete is under pressure). This is, however, known in all pre-tensioned structures.
  • the formwork pipes can be steel pipes with thin walls which are resistive to expansion of the diameter when the concrete is pressurised. This gives a 3-dimensional tension in the concrete and consequently a higher design tension, which again leads to a smaller cross section.
  • the pre-tensioned method will give savings compared to mounting/ welding in new elements by the fact that the pre-tensioning force will give support for a lift, which causes less deflections in the platform deck. The need for reinforcement of the actual deck will be reduced. This has been demonstrated in an analysis which is briefly mentioned below.
  • the principle of pre-tensioning of concrete structures is old and well tested. This is often used in connection with bridges and other structures where deflection generally would be a problem.
  • the difference of this invention from traditional pretensioning is that it is not an integrated part of the original structure, but is installed as a reinforcing element afterwards to make up for a structure problem.
  • Analysis of the invention have been carried out in connection with reinforcement of a deck on an offshore installation, as mentioned above.
  • the enclosed figure is a simple principal drawing showing how the invention functions in the computed case.
  • the figure illustrates the storage of the deck structure 1 on a lifting vessel on two support points 3, 4. On the middle of the deck on the other hand a natural support point 2 has been removed and thus the deck has to be reinforced.
  • a pre-tensioning cable or a pre-tensioning bar is a very simple structure consisting of a cable of steel having high tensile (stretch) capacity and which is cast into concrete.
  • the invention has a large degree of flexibility with regard to load, since the level of tension can be adjusted to the load on the deck. Theoretically the most ideal tensioning force is the force which together with the load gives a tension level equal to zero in the concrete.
  • step by step as follows:
  • the concrete 8 is poured for 1 day/night
  • the cables 5 are pre-tensioned to some degree 5.
  • the rest of the formwork pipes 7 are cast out
  • the concrete 6 is cured for 3 days and nights
  • the cables 5 are tensioned up to 100%
  • Total time for mounting is estimated to be 5 - 6 days.

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Revetment (AREA)
  • Sewage (AREA)
  • Foundations (AREA)
PCT/NO2002/000204 2001-06-13 2002-06-11 A method of reinforcing an offshore structure WO2002101156A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
NO20012920A NO314093B1 (no) 2001-06-13 2001-06-13 Fremgangsmåte for å forsterke en offshoreinstallasjon
NO20012920 2001-06-13

Publications (1)

Publication Number Publication Date
WO2002101156A1 true WO2002101156A1 (en) 2002-12-19

Family

ID=19912561

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/NO2002/000204 WO2002101156A1 (en) 2001-06-13 2002-06-11 A method of reinforcing an offshore structure

Country Status (2)

Country Link
NO (1) NO314093B1 (no)
WO (1) WO2002101156A1 (no)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016001666A1 (en) * 2014-07-04 2016-01-07 Celtic Design Consultants Limited Improved apparatus

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4333725A (en) * 1977-04-25 1982-06-08 Conoco Inc. Compression stressed weld joints on offshore platforms
NO304527B1 (no) * 1991-04-19 1999-01-04 Sociutu Nationale Elf Aquitain Forsterkning av r°ranordning, samt fremgangsmÕte for Õ tilveiebringe forsterkningen
WO2001027394A1 (en) * 1999-10-15 2001-04-19 Spacelift Offshore B.V. Method for dismantling of a tilting jack

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4333725A (en) * 1977-04-25 1982-06-08 Conoco Inc. Compression stressed weld joints on offshore platforms
NO304527B1 (no) * 1991-04-19 1999-01-04 Sociutu Nationale Elf Aquitain Forsterkning av r°ranordning, samt fremgangsmÕte for Õ tilveiebringe forsterkningen
WO2001027394A1 (en) * 1999-10-15 2001-04-19 Spacelift Offshore B.V. Method for dismantling of a tilting jack

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016001666A1 (en) * 2014-07-04 2016-01-07 Celtic Design Consultants Limited Improved apparatus
US9970172B2 (en) 2014-07-04 2018-05-15 Celtic Design Consultants Ltd Apparatus for providing access to equipment or structures that require maintenance

Also Published As

Publication number Publication date
NO314093B1 (no) 2003-01-27
NO20012920D0 (no) 2001-06-13
NO20012920L (no) 2002-12-16

Similar Documents

Publication Publication Date Title
US9494131B2 (en) Monopile foundation for offshore wind turbine
KR100837608B1 (ko) 교각 코핑상면에 블럭아웃을 실시하여 매립한 중공형 철제파이프와 일체로 형성하여 지지력을 갖는 고장력 강봉과조립식 철제 브라켓을 이용한 교량 슬라브 인상공법
JP5065179B2 (ja) 型枠装置
US6561723B2 (en) High tensile tie rod connector
US20020067957A1 (en) Floating concrete dock sections and methods for making the same
US6514009B2 (en) Subterranean storage vessel system
KR100901803B1 (ko) 강합성거더 제작방법 및 강합성거더를 이용한 교량시공방법
US5960597A (en) Method for post-tensioning columns
CN110468714B (zh) 超长联不等跨非对称连续桥梁先纵后横向合拢施工方法
JP3393107B2 (ja) 橋桁支承取替え工法
WO2016089220A1 (en) Subsea platform
US5713296A (en) Lightweight concrete dock
KR101658390B1 (ko) 암거 보강 공법
JP5075392B2 (ja) ロープ式補修足場
US20040206030A1 (en) Apparatus and method for reinforcing concrete using intersectional tendon support structures
WO2002101156A1 (en) A method of reinforcing an offshore structure
US3483707A (en) Method for reinforcing steel pipe piling in situ and the resultant piling
JP3860301B2 (ja) 橋桁の仮受工法およびこれに用いうる架台
KR100944241B1 (ko) 프리스트레스 합성형교의 연속지점부상의 상부 및 하부내하력 보강을 위한 강-콘크리트 합성 거더
KR100430243B1 (ko) 프리스트레스트 합성파일 및 그 제조방법
JP4437064B2 (ja) 合成床版橋のコンクリート床版の構築方法および型枠構造
GB2259536A (en) Constructing and positioning structures and modules on an offshore platform
KR100554298B1 (ko) 영구케이블을 이용한 사장교의 비대칭 주두부 가설방법
JP4700980B2 (ja) ギャングウエイタワーのリプレース方法
CN104818678A (zh) 一种对简支空心板主梁抗弯加固的方法

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CO CR CU CZ DE DK DM DZ EC EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ OM PH PL PT RO RU SD SE SG SI SK SL TJ TM TN TR TT TZ UA UG US UZ VN YU ZA ZM ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZM ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GQ GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: JP

WWW Wipo information: withdrawn in national office

Ref document number: JP

DPE2 Request for preliminary examination filed before expiration of 19th month from priority date (pct application filed from 20040101)