US3594974A - Method of assembling supporting structures utilizing an inflatable tube - Google Patents
Method of assembling supporting structures utilizing an inflatable tube Download PDFInfo
- Publication number
- US3594974A US3594974A US861784A US3594974DA US3594974A US 3594974 A US3594974 A US 3594974A US 861784 A US861784 A US 861784A US 3594974D A US3594974D A US 3594974DA US 3594974 A US3594974 A US 3594974A
- Authority
- US
- United States
- Prior art keywords
- concrete
- tube
- gap
- building elements
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/18—Separately-laid insulating layers; Other additional insulating measures; Floating floors
- E04F15/20—Separately-laid insulating layers; Other additional insulating measures; Floating floors for sound insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
- E04B1/68—Sealings of joints, e.g. expansion joints
- E04B1/6813—Compressable seals of hollow form
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/08—Load-carrying floor structures formed substantially of prefabricated units assembled of block-shaped elements, e.g. hollow stones
Definitions
- the object of the present invention is to overcome this defeet.
- the characteristic feature of the invention is that in the said gap beneath the joint there is laid a tube of flexible material, filled with air, so that the tube walls on both sides of the joint are pressed sealingly against the slab-shaped building elements, to prevent any material being forced into and filling the said gap. There can thus be no filling up of the joint with mortar to affect sound insulation, so that sound insulation is very satisfactory in the composite building elements.
- This method also makes the seaming of the concrete-building elements considerably cheaper than with previously used methods wherein the gap was filled to the upper surface of the slab by a soft material, such as mineral wool or foam.
- the invention also relates to a specific form of the tube used in this method.
- FIGS. 4 and are cross sections through two different embodiments of tubes for use in this method.
- the concrete-building elements 1 and 2 shown in the drawings each consist of a concrete coffer 3 reinforced by strengthening bars (not shown) and a superimposed flat concrete slab 4, also reinforced by strengthening bars (not shown).
- a sound barrier 6 is disposed in the gap 5 between these two elements 3 and 4.
- this barrier consists of wedges of neoprene or other suitable istrophic and flexible plastic or rubber, superimposed in pairs and axially movable relative to each other to vary their total thickness, these pairs of wedges being laid at equal distances on the upper edge 7 of the concrete coffer 3.
- the wedges are so chosen and located, and the elasticity of the wedge material is such, that with an increase in the load on the concrete slab by e.g. 50 kg., the wedges are compressed by about 0.2-0.5 mm. Very effective sound-damping values are produced by such a construction.
- a layer 9 of mineral wool or similar heatand sound-absorbing material is applied in the cavity 8 in the interior of the concrete coffer 3.
- the composite concrete-building elements I, 2 are factory made so that they all have the same thickness. Before being sent to the building site, the building elements preferably have their upper part covered by a protective plastic foil 10 (FIG. 2), so that the gap 5 between the concrete coffer 3 and the concrete slab 4 is completely closed.
- a protective plastic foil 10 FIG. 2
- the air in the tube 14 is let out, so that the tube collapses and lies flat on the top 7 of the concrete coffer 3. If so desired, the tube 14 can then be withdrawn and reused in further seams between concrete building elements 1, 2.
- the tube 14 can with advantage have a channel-shaped longitudinal expanded portion 19 or a head which when the tube is applied enters the gap 12 between the concrete coffers 3 and thus centers the tube in its correct position immediately below the seam joint between the concrete slabs 4.
- longitudinal reinforcing filaments or wires 21 in its two diametrally opposite fins 20.
- Similar reinforcing filaments or wires 22 should also be embedded in the longitudinal edge portions 23 of the tube whereat the channel-shaped widened portion 19 joins the head portion of the tube I4.
- a method of assembling supporting structures comprising a number of adjacently disposed composite concrete-building elements each consisting of a preferably coffer-shaped first concrete support element, a vertically spaced superimposed slablike second concrete element and sound insulation means disposed in the horizontal gap between said first and second concrete elements, wherein after these composite-concretebuilding elements have been laid on a support portions of the composite concrete-building elements are spaced apart forming a vertical gap, the vertical gap between adjacent composite concrete-building elements is filled with mortar or similar material to bond together these composite concretebuilding elements, wherein the improvement comprises placing in the said, horizontal gap at the joint between the superimposed composite concrete-building elements a tube of flexible material, filled with air, so that the tube walls lie on both sides of the joint and are pressed sealingly against the building elements to prevent any mortar from the vertical gap being forced into and filling the said horizontal gap.
Abstract
A joint between concrete coffer beams and between slabs which are placed on the beams with sound insulation between the slabs and beams. A rubber tube is located at the joint, and is inflated while the slab joint is filled. The tube is then deflated, and possibly withdrawn, and this leaves a clean unbridged gap which prevents the sound insulation being impaired at this juncture.
Description
United States Patent ll 1 1 3,594,974
[72] invento s er 0l0f Jonell [50] Field of Search 52/421, 2, Goteborg; 743, 741, 744, 576, 577; 249/65 Sven Melker Nilsson. Kallered, both of, Sweden [56] References Cited [2|] Appl. No. 861.784 UNITED STATES PATENTS 5" d i f g gf 2,239,989 4 1941 Britton 249/65 atente u y [73] Assignee lngeniorsfirman Nilcon Aktiebolag QTHER REFERENCES vannedal oslergard Popular Mechanics, Oct., 1963 page 148 class 249-65 I Kanered, swede Primary Examiner-John E. Murtagh Pnomy P 1968 Atmrneyl(ane, Dalsimer, Kane, Sullivan and Kurucz [33] Sweden [31] 13166/1968 (54] METHOD OF ASSEMBLING SUPPORTING STRUCTURES UTILIZING AN INFLATABLE TUBE ABSTRACT. A Joint between concrete coffer beams and 2 CM 5 D between slabs which are placed on the beams with sound insurawmg lation between the slabs and beams. A rubber tube is located [52] US. Cl 52/743, at the joint, and is inflated while the slab joint is filled. The 52/2, 52/421, 249/65 tube is then deflated, and possibly withdrawn, and this leaves a [51] Int. Cl B28b 7/32, clean unbridged gap which prevents the sound insulation E04g 1 1/04 being impaired at this juncture.
4 I 8 6 I5 I 5 I 4 I 7 6 4 I PATENTEU JULZ'I'ISEI 3 5 4 Fig. I
IN VEN T095 METHOD OF ASSEMBLING SUPPORTING STRUCTURES UTILIZING AN INFLATABLE TUBE BACKGROUND OF THE INVENTION It is known to assemble supporting structures in buildings in the form of adjacent light concreteconstructional elements each consisting of a longitudinal concrete coffer and closed by a concrete slab and a sound insulation disposed in the gap between this slab and the concrete coffer. After these composite constructional elements had been laid on a support, eg on transverse support beams, the joint between adjacent compound elements was often filled with mortar, either accidentally or because of poor workmanship. This mortar formed a type of bridge between the concrete slabs and the concrete coffers in the various building elements. This bridging was found to be very deleterious from the sound insulation aspect, since sound waves were able to pass readily from the concrete slab to the coffer. The effect of the sound-damping material applied in the gap between the concrete slab and the coffer was therefore almost lost.
SUMMARY OFTHE INVENTION The object of the present invention is to overcome this defeet. The characteristic feature of the invention is that in the said gap beneath the joint there is laid a tube of flexible material, filled with air, so that the tube walls on both sides of the joint are pressed sealingly against the slab-shaped building elements, to prevent any material being forced into and filling the said gap. There can thus be no filling up of the joint with mortar to affect sound insulation, so that sound insulation is very satisfactory in the composite building elements. This method also makes the seaming of the concrete-building elements considerably cheaper than with previously used methods wherein the gap was filled to the upper surface of the slab by a soft material, such as mineral wool or foam.
The invention also relates to a specific form of the tube used in this method.
BRIEF DESCRIPTION OF THE DRAWINGS adjacent concrete-building elements before it is filled with mortar,
FIGS. 4 and are cross sections through two different embodiments of tubes for use in this method.
DETAILED DESCRIPTION OF A PREFERRED- EMBODIMENT The concrete-building elements 1 and 2 shown in the drawings each consist of a concrete coffer 3 reinforced by strengthening bars (not shown) and a superimposed flat concrete slab 4, also reinforced by strengthening bars (not shown). A sound barrier 6 is disposed in the gap 5 between these two elements 3 and 4. In the embodiment shown, this barrier consists of wedges of neoprene or other suitable istrophic and flexible plastic or rubber, superimposed in pairs and axially movable relative to each other to vary their total thickness, these pairs of wedges being laid at equal distances on the upper edge 7 of the concrete coffer 3. The wedges are so chosen and located, and the elasticity of the wedge material is such, that with an increase in the load on the concrete slab by e.g. 50 kg., the wedges are compressed by about 0.2-0.5 mm. Very effective sound-damping values are produced by such a construction. A layer 9 of mineral wool or similar heatand sound-absorbing material is applied in the cavity 8 in the interior of the concrete coffer 3.
The composite concrete-building elements I, 2 are factory made so that they all have the same thickness. Before being sent to the building site, the building elements preferably have their upper part covered by a protective plastic foil 10 (FIG. 2), so that the gap 5 between the concrete coffer 3 and the concrete slab 4 is completely closed.
On the building site the concrete-building elements I, 2 are laid out so that their ends rest on a support, for example on transversely aligned support beams 11. Cement mortar 13 is then dropped into the gap 12 between the adjacent building elements I, 2 so that the coffers 3 can be bonded together. In the gap 5 between the sound-damping means 6 there is then inserted a rubber or plastic tube 14 which is sufficiently inflated for its walls 15 to be pressed upwards against the concrete slab 4 on both sides of gap 12. A seaming material 16, erg. fine mortar, is then filled into the gap between the two plates 4, which have a longitudinally extending groove along their edges. The adjacent edge portions of the plates .4 are smoothed over with the aid of a filler l7, and finally a floor covering 18, e.g. a sheet of linoleum, is laid on the finished support surface.
As soon as the seaming material 16 has set, the air in the tube 14 is let out, so that the tube collapses and lies flat on the top 7 of the concrete coffer 3. If so desired, the tube 14 can then be withdrawn and reused in further seams between concrete building elements 1, 2.
It is obvious that with the use of a sealing tube the danger of a solid bridge being formed by the seaming material 16 between the concrete slab 4 and the concrete coffer 3 does not arise. It also becomes possible to provide good air circulation, e.g. of hot air, through the gaps between the adjacent concrete-building elements 1, 2.
As shown for instance in FIG. 4, the tube 14 can with advantage have a channel-shaped longitudinal expanded portion 19 or a head which when the tube is applied enters the gap 12 between the concrete coffers 3 and thus centers the tube in its correct position immediately below the seam joint between the concrete slabs 4. In order to give the tube 14 the necessary stiffness it may be desirable to provide longitudinal reinforcing filaments or wires 21 in its two diametrally opposite fins 20. Similar reinforcing filaments or wires 22 should also be embedded in the longitudinal edge portions 23 of the tube whereat the channel-shaped widened portion 19 joins the head portion of the tube I4.
The embodiment shown and described is only to be considered as an example; both the shape and construction of the concrete-building elements 1, 2 and the shape of tube 14 can be changed in various ways within the scope of the following claims.
What we claim is:
l. A method of assembling supporting structures comprising a number of adjacently disposed composite concrete-building elements each consisting of a preferably coffer-shaped first concrete support element, a vertically spaced superimposed slablike second concrete element and sound insulation means disposed in the horizontal gap between said first and second concrete elements, wherein after these composite-concretebuilding elements have been laid on a support portions of the composite concrete-building elements are spaced apart forming a vertical gap, the vertical gap between adjacent composite concrete-building elements is filled with mortar or similar material to bond together these composite concretebuilding elements, wherein the improvement comprises placing in the said, horizontal gap at the joint between the superimposed composite concrete-building elements a tube of flexible material, filled with air, so that the tube walls lie on both sides of the joint and are pressed sealingly against the building elements to prevent any mortar from the vertical gap being forced into and filling the said horizontal gap.
2. Method as in claim 1, wherein the improvement comprises letting out, after setting of the material in the joint, the air in the tube, so that the tube collapses and can if desired then be removed from the said gap.
Claims (2)
1. A method of assembling supporting structures comprising a number of adjacently disposed composite concrete-building elements each consisting of a preferably coffer-shaped first concrete support element, a vertically spaced superimposed slablike second concrete element and sound insulation means disposed in the horizontal gap between said first and second concrete elements, wherein after these composite concretebuilding elements have been laid on a support portions of the composite concrete-building elements are spaced apart forming a vertical gap, the vertical gap between adjacent composite concrete-building elements Is filled with mortar or similar material to bond together these composite concrete-building elements, wherein the improvement comprises placing in the said, horizontal gap at the joint between the superimposed composite concrete-building elements a tube of flexible material, filled with air, so that the tube walls lie on both sides of the joint and are pressed sealingly against the building elements to prevent any mortar from the vertical gap being forced into and filling the said horizontal gap.
2. Method as in claim 1, wherein the improvement comprises letting out, after setting of the material in the joint, the air in the tube, so that the tube collapses and can if desired then be removed from the said gap.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SE13166/68A SE323790B (en) | 1968-09-30 | 1968-09-30 |
Publications (1)
Publication Number | Publication Date |
---|---|
US3594974A true US3594974A (en) | 1971-07-27 |
Family
ID=20296936
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US861784A Expired - Lifetime US3594974A (en) | 1968-09-30 | 1969-09-29 | Method of assembling supporting structures utilizing an inflatable tube |
Country Status (11)
Country | Link |
---|---|
US (1) | US3594974A (en) |
JP (1) | JPS4916975B1 (en) |
CH (1) | CH520842A (en) |
DE (1) | DE1946026A1 (en) |
DK (1) | DK132292C (en) |
FI (1) | FI48867C (en) |
FR (1) | FR2019257A1 (en) |
GB (1) | GB1267048A (en) |
NL (1) | NL6914372A (en) |
NO (1) | NO122151B (en) |
SE (1) | SE323790B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20150013255A1 (en) * | 2013-03-14 | 2015-01-15 | Christopher M. Hunt | Hybrid cementitious buildings for a multi-level habitat |
US8959859B2 (en) | 2012-09-17 | 2015-02-24 | Steelcase Inc. | Floor-to-ceiling partition wall assembly |
CN113152763A (en) * | 2021-04-12 | 2021-07-23 | 中国十七冶集团有限公司 | Wrong platform prevention device for ZDB prestressed concrete laminated slab and use method of wrong platform prevention device |
CN113235798A (en) * | 2021-05-21 | 2021-08-10 | 铜陵有色建安钢构有限责任公司 | Method for mounting assembled laminated slab |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2239989A (en) * | 1939-05-27 | 1941-04-29 | Verner E Britton | Sealing means for use in grouting vertical seams in sea walls or the like |
-
1968
- 1968-09-30 SE SE13166/68A patent/SE323790B/xx unknown
-
1969
- 1969-09-11 NO NO3642/69A patent/NO122151B/no unknown
- 1969-09-11 DE DE19691946026 patent/DE1946026A1/en active Pending
- 1969-09-17 CH CH1422469A patent/CH520842A/en not_active IP Right Cessation
- 1969-09-18 FI FI692670A patent/FI48867C/en active
- 1969-09-19 GB GB1267048D patent/GB1267048A/en not_active Expired
- 1969-09-23 NL NL6914372A patent/NL6914372A/xx unknown
- 1969-09-29 DK DK518369A patent/DK132292C/en active
- 1969-09-29 US US861784A patent/US3594974A/en not_active Expired - Lifetime
- 1969-09-30 FR FR6933423A patent/FR2019257A1/fr not_active Withdrawn
- 1969-09-30 JP JP44077483A patent/JPS4916975B1/ja active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2239989A (en) * | 1939-05-27 | 1941-04-29 | Verner E Britton | Sealing means for use in grouting vertical seams in sea walls or the like |
Non-Patent Citations (1)
Title |
---|
Popular Mechanics, Oct., 1963 page 148 class 249-65 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8959859B2 (en) | 2012-09-17 | 2015-02-24 | Steelcase Inc. | Floor-to-ceiling partition wall assembly |
US9045896B2 (en) | 2012-09-17 | 2015-06-02 | Steelcase Inc. | Floor-to-ceiling partition wall assembly |
US20150013255A1 (en) * | 2013-03-14 | 2015-01-15 | Christopher M. Hunt | Hybrid cementitious buildings for a multi-level habitat |
CN113152763A (en) * | 2021-04-12 | 2021-07-23 | 中国十七冶集团有限公司 | Wrong platform prevention device for ZDB prestressed concrete laminated slab and use method of wrong platform prevention device |
CN113235798A (en) * | 2021-05-21 | 2021-08-10 | 铜陵有色建安钢构有限责任公司 | Method for mounting assembled laminated slab |
CN113235798B (en) * | 2021-05-21 | 2022-10-25 | 铜陵有色建安钢构有限责任公司 | Method for mounting assembled laminated slab |
Also Published As
Publication number | Publication date |
---|---|
JPS4916975B1 (en) | 1974-04-26 |
DK132292B (en) | 1975-11-17 |
GB1267048A (en) | 1972-03-15 |
FI48867B (en) | 1974-09-30 |
DK132292C (en) | 1976-04-20 |
FI48867C (en) | 1975-01-10 |
NL6914372A (en) | 1970-04-01 |
FR2019257A1 (en) | 1970-06-26 |
NO122151B (en) | 1971-05-24 |
DE1946026A1 (en) | 1970-04-09 |
SE323790B (en) | 1970-05-11 |
CH520842A (en) | 1972-03-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3552076A (en) | Concrete form | |
US4942707A (en) | Load-bearing roof or ceiling assembly made up of insulated concrete panels | |
EP0551276B1 (en) | Modular panel of expanded synthetic material provided with staggered longitudinal "t"-shaped channels, receiving "t"-shaped wooden posts useful for erecting walls | |
US9181699B2 (en) | Precast concrete structures, precast tilt-up concrete structures and methods of making same | |
AU742071B2 (en) | An improved formwork for building walls | |
US4698949A (en) | Self-leveling block | |
US4841702A (en) | Insulated concrete building panels and method of making the same | |
US20020043045A1 (en) | Modular panels for building construction | |
US5248122A (en) | Pre-attached form system for insulated concrete wall panel | |
US1912290A (en) | Slab floor or roof construction | |
US3594974A (en) | Method of assembling supporting structures utilizing an inflatable tube | |
US3683577A (en) | Building construction systems | |
US2250319A (en) | Building wall | |
US3693928A (en) | Concrete wall form with adjustable bulkhead | |
JP2703274B2 (en) | Sound absorbing component and method of manufacturing the same | |
US1053646A (en) | Building construction. | |
DE69107129D1 (en) | Modular foam element covered with a layer of plaster and connectable to adjacent elements and method for forming a layer of plaster and building a wall. | |
KR101895803B1 (en) | Housing construction method | |
US8590242B1 (en) | Insulated concrete wall | |
US2092408A (en) | Building construction | |
US468871A (en) | Construction of fire-proof buildings | |
US2219043A (en) | Floor construction | |
RU32803U1 (en) | FORMWORK UNIT FOR INTER-FLOOR CEILINGS | |
JP7229836B2 (en) | Hollow slab structure | |
JP2595313Y2 (en) | Railway station platform |