US3563044A - Method for constructing stabilized construction wall in unstable footing - Google Patents

Method for constructing stabilized construction wall in unstable footing Download PDF

Info

Publication number
US3563044A
US3563044A US811331A US3563044DA US3563044A US 3563044 A US3563044 A US 3563044A US 811331 A US811331 A US 811331A US 3563044D A US3563044D A US 3563044DA US 3563044 A US3563044 A US 3563044A
Authority
US
United States
Prior art keywords
wall
site
construction
mat
footing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US811331A
Inventor
Ben C Gerwick Jr
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
J H POMEROY AND CO Inc
Original Assignee
J H POMEROY AND CO Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by J H POMEROY AND CO Inc filed Critical J H POMEROY AND CO Inc
Application granted granted Critical
Publication of US3563044A publication Critical patent/US3563044A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/04Flat foundations in water or on quicksand

Definitions

  • a method of providing stabilization for a construction wall during construction is an unstable footing includes the formation of a basin above the pre-existing surface level of a proposed construction zone or site.
  • the basin is used to receive fluid therein to provide increased hydrostatic pressure, acting on the wall from inside the construction site to provide pressure within the site to a degree approximating the countervailing pressures acting on the construction wall from outside the site.
  • the wall structure formed ' will ultimately be characterized by an unstable footing material on one side of the wall at the lower end thereof, a mat of stable footing material on the other side of the wall, and a mat of concrete superimposed upon the mat of stabilized footing material so that the concrete mat can counteract laterally acting forces pressing against the outside of the wall.
  • This invention pertains to wall constructions and methods of stabilizing same in soil conditions where the footing is highly unstable.
  • foundation walls which extend down to a predetermined depth in unstable soil conditions, e.g., where the soil is somewhat fluid or marshy or otherwise unstable, as in a swamp or the like, may fail to encounter a proper footing or stable material. Without a stable footing during excavation of the construction site, it will be readily apparent that the load of earth pressure on the exterior surfaces of the wall can readily force the lower portion of the wall inwardly toward the construction sites as support is removed from the construction wall within the excavation site. However, when the bottom end of the wall is embedded in a stable soil condition, the excavation can proceed without undue concern for the problems of the increasing pressures developing against the wall on the outside of the excavation site.
  • a wall structure is provided by a method which serves to stabilize the footing of an upright diaphragm wall structure of a type found commonly encircling a construction site.
  • a method for stabilization of a construction wall in an otherwise unstable footing material comprising the steps of forming a basin on top of the surface of a proposed construction zone or site.
  • the basin has a predetermined depth and substantially fluid-impervious side wall boundaries including the upright wall structure which is to be stabilized.
  • the wall to be stabilized also serves to define at least a portion of the boundaries of the site. Then, the hydrostatic pressure acting on the wall from inside the construction site or zone is increased to a degree approximating the countervailing pressure acting on the wall from outside the zone.
  • the method contemplates removing the soil materials of the construction site down to a predetermined level while replacing the removed materials with a stabilizing fill material of greater strength. Thereafter, the applied hydrostatic pressure is removed to permit completion of construction by excavating and providing a concrete mat overlaid upon a pad of stable fill.
  • the degree of hydrostatic pressure employed within the site will, of course, vary with the passive resistance of the footing material within the site and also with the placement and use of strut supports.
  • a wall structure in an unstable footing wherein an upright diaphragm wall is arranged in the unstable footing material in a manner whereby the unstable material is on one side of the wall at the lower end of the wall while a mat of stable footing material is on the other side of the wall.
  • a concrete mat is superimposed which serves to counteract laterally acting forces pressing against the outside of the wall tending to force the bottom end of the wall inwardly toward the excavation.
  • FIGS. 1-8 are schematic side elevation section views showing a sequence of steps incorporated in the method according to the invention.
  • FIG. 9 and FIG. 10, respectively, are plan views of two different construction sites utilizing the method according to the invention.
  • FIGS. l8 represent a sequence of steps which are pursued to provide stabilization to a construction wall disposed upright in an unstable footing, such as may be found, for example, in a marsh, river bed, or bay bottom or other extremely weak soil condition.
  • the construction zone is graded in the region 11, as necessary, to provide a relieved outer margin disposed about the exterior of the construction lot or zone 12. Accordingly, the terrain is graded down to the existing lever 13 of lot 12.
  • a diaphragm wall 14 of a type which is impervious to fluid and which is to be stabilized in its upstanding position is disposed upright in the ground 16.
  • a suitable wall construction for this purpose may, for example, be a sheet-pile wall or, if the wall 14 is to be come a permanent portion of the building structure to be erected on the site of the construction zone 12, it may be a slurry trench wall of the type, for example, as disclosed in US. Pat. No. 3,412,562.
  • Each of the foregoing types of walls form an impervious fluid diaphragm satisfactory for the present method.
  • Wall 14 serves to complete the impervious boundary wall extending about the construction site 12 to the extent needed.
  • the construction site 12 can be enclosed by providing the sheet-pile walls to extend about three sides of the site 12.
  • Walls 14 into the earth is done in a manner to permit the upper end of the walls to extend above the level of the surface 13 of the construction site 12.
  • the upper edge of walls 14 enclosing site 12 form the rim of the construction zone boundaries and define a basin located above the level of the surface 13.
  • a berm 18 consisting of suitable fill material is built up within site 12.
  • a strut 19, if needed can be disposed to bear against the inner face of wall 14 and may suitably be anchored at its interior end by a conventional deadman or other anchor device 21.
  • strut 19 serves to provide means serving to provide lateral support to the upper end of wall 14. It will be readily evident that other means such as the use of conventional tie-back devices may also be employed to introduce support to the upper end of wall 14 as desired and as feasible under the circumstances.
  • piles 22 may be driven into the earth for purposes of later providing support to a concrete mat 23.
  • the driving of piles 22 can be accomplished by use of the driving extensions commonly employed in driving deep piles into the ground.
  • the basin 24 which was originally defined between the upper extension 14a of wall 14 and berm 18 and which included a bottom defined by the existing surface 13 of the construction site is filled with a heavy liquid, hereinafter referred to as a brine.
  • the brine must not adversely coat the stabilizing fill material, such as sand, which will later replace the unstable material to be excavated out of the construction site.
  • the brine should not cause the normally stabilizing material to become unstable by virtue of contact with the liquid brine.
  • the brine preferably should be heavier than water since its purpose is to apply a supplemental hydrostatic pressure acting with passive resistance and/ or strut forces acting against the wall from within the excavation site.
  • the inside forces approximate the forces acting from outside. Conditions in any given circumstance will serve to dictate the degree of supplemental hydrostatic pressure required to properly hold the wall.
  • the brine solution has been satisfactorily employed when consisting of a liquid having a density running on the order of 75 lbs. per cubic foot as compared to the conventional weight of Water.
  • sodium chloride, calcium chloride, zinc chloride, sodium silicate, or mixtures of various other materials can be added to water together with other desirable materials such as dispersing agents, suspensions, or the like.
  • brine is not to be limited herein merely to the use of salt water since a number of suitable ways of increasing the density will be readily apparent to those skilled in the art.
  • the supplemental hydrostatic pressure on the inside of the wall essentially contributes to the support force countering the support forces acting on the outside of the wall.
  • this level 26 can advantageously be located on the order of ten feet below the bottom of the structure to be built on the construction site.
  • the hydrostatic head is maintained therein by merely supplying additional brine material as desired by suitable means (not shown).
  • a suitable stable soil material is introduced, such as sand, rock, or weak mixtures of cementitious materials, all characteristically having a relatively high internal friction angle as compared to the internal friction angle of that material 16 which was removed from basin 24, is introduced.
  • sand 27 is shown having been filled into the excavation as a replacement for the material 16 which has been previously removed.
  • the level 28 of the brine is maintained substantially constant so as to ensure that the head pressure applied against the inside of Wall 14 remains throughout the interchange of stable material for the unstable material being removed.
  • the internal friction angle of the fill material can be enhanced by re acting materials with the brine residue so as to cause crystal growth, solidification, etc., thereby further increasing the internal friction angle of the fill and hence improving the stabilization property of the fill material.
  • portions (or all) of the stabilized fill may be further strengthened by intrusions of special reacting or cementing materials or special tremie placements of cemetitious mixtures.
  • the strut 19 can, if desired, be removed and further excavation conducted down to a level exposing the tops of piles 22. At that point, a layer 32 of good rock is placed around the tops of the piles 22 whereby a concrete mat 23 can be formed on the tops of piles 22.
  • Mat 23 preferably can include a tapered or bevelled edge 33 against which a strut 34 can be positioned. The other end of strut 34 can then be attached near the upper edge of wall 14 in a manner to provide support between wall 14 and mat 23.
  • the volume of the fill material 27 is suflicient to stand alone in providing suflicient stability to the lower end of the wall to permit the construction of the rest of the foundation to proceed as where the concrete mat 23 is then subsequently laid taking advantage of the stable block of material 27a then located at the base of wall 14.
  • the stabilized wall construction comprises means forming an upright diaphragm wall, unstable footing material being located on one side of the wall at the lower end thereof while a mat of stable footing material on the other side of the wall has been formed. Further, a mat of concrete is superimposed upon the first name mat and serves to counteract laterally acting forces pressing against the outside of the wall.
  • the portion 27a forms a mat of stable footing material upon which the mat 36 of concrete can be applied.
  • the method described above serves to keep the walls 14 of the construction site from losing their support notwithstanding the fact that they are lodged in an unstable soil material.
  • a method of providing stabilization for a construction wall in an unstable footing comprising forming a basin upon the surfane of a construction zone, said basin having a predetermined depth and substantially fluid-impervious side wall boundaries including the upright wall structure to be stabilized forming at least a portion of said boundaries, applying a hydrostatic pressure to said wall from inside said zone to supplement other forces serving to resist countervailing forces acting on said wall from outside said zone, said supplemental hydrostatic pressure serving to bring the forces acting from within said zone to a level approximating the level of forces acting upon the wall from outside said zone, and, while maintaining said hydrostatic pressure, removing the soil materials of said zone down to a predetermined level and replacing the removed materials with a stabilizing fill material of greater strength, and thereafter removing the applied hydrostatic pressure.
  • step of applying the hydrostatic pressure includes the introduction into said basin of a head of fluid pressure relative to the level of the pre-existing surface of the zone.
  • step of applying the hydrostatic pressure includes the introduction of fluid into said basin said fluid having a density greater than that of Water.
  • step of applying the hydrostatic pressure includes the introduction of a head of fluid pressure into said basin, said fluid having a density greater than that of water.
  • a method of providing stabilization for a construction wall in an unstable footing comprising forming an upright wall substantially impervious to fluid to define at least a portion of the peripheral boundary of a construction zone, the top of the wall extending above the level of the pre-existing surface of said zone, completing the boundaries around said zone to extend upwardly to form a basin above the level of said preexisting surface, applying a hydrostatic pressure to act on said wall from inside said zone to raise the forces acting on the wall from within said zone to resist the countervailing forces acting on said wall from outside said zone, and, while maintaining said pressure, removing the soil materials of said zone down to a predetermined level and replacing the removed materials with a stabilizing fill of greater strength, and thereafter removing the applied hydrostatic pressure.
  • a method of providing stabilization for a construction wall in an unstable footing comprising forming an upright wall substantially impervious to fluid to define at least a portion of the boundaries of a construction zone, the top of the Wall extending a predetermined distance above the level of the existing surface of said zone, extending the rim of the zone boundaries upwards to form a basin above the level of the existing surface of the zone, filling the basin with fluid material to increase the hydrostatic pressure on the inside of the wall to provide a countering pressure acting to offset the forces pressing on the outside of the wall, and maintaining the applied pressure while removing the soil materials of the zone down to a predetermined level, and replacing the removed materials with a stabilizing fill of greater strength, while maintaining said hydrostatic pressure, thereafter removing the applied hydrostatic pressure.
  • a stabilized wall construction comprising means forming an upright diaphragm wall, untable footing material on one side of the wall at the lower end thereof, a mat of stable footing material on the other side of the wall, and a mat of concrete superimposed upon the first named mat serving to counteract laterally acting forces pressing against the outside of the Wall.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A METHOD OF PROVIDING STABILIZATION FOR A CONSTRUCTION WALL DURING CONSTRUCTION IS AN UNSTABLE FOOTING INCLUDES THE FORMATION OF A BASIN ABOVE THE PRE-EXISTING SURFACE LEVEL OF A PROPOSED CONSTRUCTION ZONE OR SITE. THE BASIN IS USED TO RECEIVE FLUID THEREIN TO PROVIDE INCREASED HYDROSTATIC PRESSURE, ACTING ON THE WALL FROM INSIDE THE CONSTRUCTION SITE TO PROVIDE PRESSURE WITHIN THE SITE TO A DEGREE APPROXIMATING THE COUNTERVAILING PRESSURES ACTING ON THE CONSTRUCTION WALL FROM OUTSIDE THE SITE. THEN, WHILE MAINTAINING THE HYDROSTATIC PRESSURE, THE SOIL MATERIALS WITHIN THE SITE ARE REMOVED BY EXCAVATING DOWN TO A PREDETERMINED LEVEL AND REPLACED (WHILE STILL MAINTAINING THE HYDROSTATIC PRESSURE) WITH A STABILIZING FILL MATERIAL OF GREATER STRENGTH THAN THE UNSTABLE MATERIAL REMOVED FROM THE SITE. THEREAFTER, THE HYDROSTATIC PRESSURE CAN BE RELIEVED AND PREPARATION OF THE SITE CONTINUED. THE WALL STRUCTURE FORMED WILL ULTIMATELY BE CHARACTERIZED BY AN UNSTABLE FOOTING MATERIAL ON ONE SIDE OF THE WALL AT THE LOWER END THEREOF, A MAT OF STABLE FOOTING MATERIAL ON THE OTHER SIDE OF THE WALL, AND A MAT OF CONCRETE SUPERIMPOSED UPON THE MAT OF STABILIZED FOOTING MATERIAL SO THAT THE CONCRETE MAT CAN COUNTERACT LATERALLY ACTING FORCES PRESSING AGAINST THE OUTSIDE OF THE WALL.

Description

Feb. 16, 1971 B. c. GERWICK, JR 3,563,044
METHOD FOR CONSTRUCTING STABILIZED CONSTRUCTION WALL IN UNSTABLE FOOTING Filed March 28, 1969 2 Sheets-Sheet 1 INVENTOR. BEN C. GERWICK JR.
ATTORNEYS Feb. 16, 1971 B. c. GERWICK, JR 3,563,044
METHOD FOR CONSTRUCTING STABILIZED CONSTRUCTION WALL IN UNSTABLE FOOTING Filed March 28, 1969 2 Sheets-Sheet z INVENTOR.
F/ 6'. /0 BEN c. GERWICK JR. BY/ 7Vr4fl fM ATTORNEYS United States Patent O US. Cl. 61--50 7 Claims ABSTRACT OF THE DISCLOSURE A method of providing stabilization for a construction wall during construction is an unstable footing includes the formation of a basin above the pre-existing surface level of a proposed construction zone or site. The basin is used to receive fluid therein to provide increased hydrostatic pressure, acting on the wall from inside the construction site to provide pressure within the site to a degree approximating the countervailing pressures acting on the construction wall from outside the site. Then, while maintaining the hydrostatic pressure, the soil materials within the site are removed by excavating down to a predetermined level and replaced (while still maintaining the hydrostatic pressure) with a stabilizing fill material of greater strength than the unstable material removed from the site. Thereafter, the hydrostatic pressure can be relieved and preparation of the site continued. The wall structure formed 'will ultimately be characterized by an unstable footing material on one side of the wall at the lower end thereof, a mat of stable footing material on the other side of the wall, and a mat of concrete superimposed upon the mat of stabilized footing material so that the concrete mat can counteract laterally acting forces pressing against the outside of the wall.
BACKGROUND OF THE INVENTION This invention pertains to wall constructions and methods of stabilizing same in soil conditions where the footing is highly unstable.
In the construction of a building, foundation walls which extend down to a predetermined depth in unstable soil conditions, e.g., where the soil is somewhat fluid or marshy or otherwise unstable, as in a swamp or the like, may fail to encounter a proper footing or stable material. Without a stable footing during excavation of the construction site, it will be readily apparent that the load of earth pressure on the exterior surfaces of the wall can readily force the lower portion of the wall inwardly toward the construction sites as support is removed from the construction wall within the excavation site. However, when the bottom end of the wall is embedded in a stable soil condition, the excavation can proceed without undue concern for the problems of the increasing pressures developing against the wall on the outside of the excavation site.
As disclosed herein, a wall structure is provided by a method which serves to stabilize the footing of an upright diaphragm wall structure of a type found commonly encircling a construction site.
Where the footing material is quite stable, the passive resistance of the material within the excavation site will ordinarily be suflicient to counter balance the pressures acting against the exterior of the wall surfaces.
In many instances, temporary struts have been packed against the wall to insure a proper force counteracting the outside pressures bearing against the wall.
However, in highly unstable footing conditions, where the passive resistance is quite low, the present invention 3,563,M4 Patented Feb. 16, 1971 provides supporting forces acting from within the excavation site in a controlled manner to approximate the pressures acting from outside the excavation site.
SUMMARY OF THE INVENTION AND OBJECTS In general, a method has been provided for stabilization of a construction wall in an otherwise unstable footing material comprising the steps of forming a basin on top of the surface of a proposed construction zone or site. The basin has a predetermined depth and substantially fluid-impervious side wall boundaries including the upright wall structure which is to be stabilized. Thus, the wall to be stabilized also serves to define at least a portion of the boundaries of the site. Then, the hydrostatic pressure acting on the wall from inside the construction site or zone is increased to a degree approximating the countervailing pressure acting on the wall from outside the zone. This is accomplished, preferably, by the more particular steps of filling the basin with fluid material having a greater density than water so as to increase the hydrostatic pressure on the inside of the wall for countering the pressure acting on the outside of the Wall. Then, while maintaining the increased pressure, the method contemplates removing the soil materials of the construction site down to a predetermined level while replacing the removed materials with a stabilizing fill material of greater strength. Thereafter, the applied hydrostatic pressure is removed to permit completion of construction by excavating and providing a concrete mat overlaid upon a pad of stable fill.
The degree of hydrostatic pressure employed within the site will, of course, vary with the passive resistance of the footing material within the site and also with the placement and use of strut supports.
Thus, in general, pursuant to the above method of construction, there is provided a wall structure in an unstable footing wherein an upright diaphragm wall is arranged in the unstable footing material in a manner whereby the unstable material is on one side of the wall at the lower end of the wall while a mat of stable footing material is on the other side of the wall. On the mat of stable material, a concrete mat is superimposed which serves to counteract laterally acting forces pressing against the outside of the wall tending to force the bottom end of the wall inwardly toward the excavation.
In general, it is an object of the present invention to provide an improved wall construction technique and stabilized wall construction in an unstable footing.
The foregoing and other objects of the invention will be more clearly apparent from the following detailed description of preferred embodiments of the invention when considered in conjunction with the drawings.
DESCRIPTION OF THE DRAWINGS FIGS. 1-8 are schematic side elevation section views showing a sequence of steps incorporated in the method according to the invention.
FIG. 9 and FIG. 10, respectively, are plan views of two different construction sites utilizing the method according to the invention.
DESCRIPTION OF THE PREFERRED EMBODIMENT Where excavation is to take place on one side of a construction wall while the other side of the wall remains subject to the earth pressures acting against the wall, it is readily apparent that the footing into which the wall is embedded must be sufficiently firm to hold the wall at the lower end thereof and prevent the pressure on the unexcavated side from forcing the bottom of the wall into the excavation whereby support of the earth is lost.
By the procedure now to be described, it is possible to provide a stabilized construction wall where the lower end of the Wall will be properly supported against forces otherwise acting to move the bottom of the wall into the excavation. The procedure as described herein further properly stabilizes the wall but in a manner whereby the bottom of the wall is not, on the other hand, forced outwardly away from the excavation zone.
Referring to the drawings, FIGS. l8 represent a sequence of steps which are pursued to provide stabilization to a construction wall disposed upright in an unstable footing, such as may be found, for example, in a marsh, river bed, or bay bottom or other extremely weak soil condition.
Preliminarily, depending upon site conditions, the construction zone is graded in the region 11, as necessary, to provide a relieved outer margin disposed about the exterior of the construction lot or zone 12. Accordingly, the terrain is graded down to the existing lever 13 of lot 12.
Subsequently, a diaphragm wall 14 of a type which is impervious to fluid and which is to be stabilized in its upstanding position is disposed upright in the ground 16. A suitable wall construction for this purpose may, for example, be a sheet-pile wall or, if the wall 14 is to be come a permanent portion of the building structure to be erected on the site of the construction zone 12, it may be a slurry trench wall of the type, for example, as disclosed in US. Pat. No. 3,412,562. Each of the foregoing types of walls form an impervious fluid diaphragm satisfactory for the present method.
Wall 14 serves to complete the impervious boundary wall extending about the construction site 12 to the extent needed. Thus, for example, where one side of the construction site 12 is bounded by substantially impervious terrain 17, the construction site 12 can be enclosed by providing the sheet-pile walls to extend about three sides of the site 12.
On the other hand, where no substantially impervious terrain is available, the construction site can be completely enclosed by walls 14.
The placement of Walls 14 into the earth is done in a manner to permit the upper end of the walls to extend above the level of the surface 13 of the construction site 12. Thus, the upper edge of walls 14 enclosing site 12 form the rim of the construction zone boundaries and define a basin located above the level of the surface 13.
In order to provide a suitable location within construction site 12 from which to work and conduct the construction activity, a berm 18 consisting of suitable fill material is built up within site 12.
Next, a strut 19, if needed can be disposed to bear against the inner face of wall 14 and may suitably be anchored at its interior end by a conventional deadman or other anchor device 21. Thus, strut 19 serves to provide means serving to provide lateral support to the upper end of wall 14. It will be readily evident that other means such as the use of conventional tie-back devices may also be employed to introduce support to the upper end of wall 14 as desired and as feasible under the circumstances.
Pursuant to the above preliminary steps, piles 22 may be driven into the earth for purposes of later providing support to a concrete mat 23. The driving of piles 22 can be accomplished by use of the driving extensions commonly employed in driving deep piles into the ground.
Next, the basin 24 which was originally defined between the upper extension 14a of wall 14 and berm 18 and which included a bottom defined by the existing surface 13 of the construction site is filled with a heavy liquid, hereinafter referred to as a brine.
The brine must not adversely coat the stabilizing fill material, such as sand, which will later replace the unstable material to be excavated out of the construction site. Thus, the brine should not cause the normally stabilizing material to become unstable by virtue of contact with the liquid brine. In addition, the brine preferably should be heavier than water since its purpose is to apply a supplemental hydrostatic pressure acting with passive resistance and/ or strut forces acting against the wall from within the excavation site. Thus, the inside forces approximate the forces acting from outside. Conditions in any given circumstance will serve to dictate the degree of supplemental hydrostatic pressure required to properly hold the wall.
In one particular application, the brine solution has been satisfactorily employed when consisting of a liquid having a density running on the order of 75 lbs. per cubic foot as compared to the conventional weight of Water. In order to prepare suitable brine solution, sodium chloride, calcium chloride, zinc chloride, sodium silicate, or mixtures of various other materials can be added to water together with other desirable materials such as dispersing agents, suspensions, or the like. Thus, the use of the term brine is not to be limited herein merely to the use of salt water since a number of suitable ways of increasing the density will be readily apparent to those skilled in the art.
After filling the basin 24 with the brine, it will be readily apparent that the supplemental hydrostatic pressure on the inside of the wall essentially contributes to the support force countering the support forces acting on the outside of the wall. Then, while maintaining the supplemental hydrostatic pressure within the construction site 12, the unstable soil material 16 are excavated from the construction site, or zone, down to a predetermined desired level 26. For example, this level 26 can advantageously be located on the order of ten feet below the bottom of the structure to be built on the construction site. As noted above, during the excavation of the unstable materials 16 from the basin 24, the hydrostatic head is maintained therein by merely supplying additional brine material as desired by suitable means (not shown).
After reaching the predetermined level 26, a suitable stable soil material is introduced, such as sand, rock, or weak mixtures of cementitious materials, all characteristically having a relatively high internal friction angle as compared to the internal friction angle of that material 16 which was removed from basin 24, is introduced. Thus. in FIG. 4, sand 27 is shown having been filled into the excavation as a replacement for the material 16 which has been previously removed. During this manipulation, the level 28 of the brine is maintained substantially constant so as to ensure that the head pressure applied against the inside of Wall 14 remains throughout the interchange of stable material for the unstable material being removed.
Subsequently, substantially all of the brine is drained from the stable soil material 27 by means of pumps 29 and hoses 31 or the like.
If necessary, as for extremely deep holes or other conditions requiring greater strength than provided by the usual normal fill materials, such as sand, the internal friction angle of the fill material can be enhanced by re acting materials with the brine residue so as to cause crystal growth, solidification, etc., thereby further increasing the internal friction angle of the fill and hence improving the stabilization property of the fill material.
In addition, portions (or all) of the stabilized fill may be further strengthened by intrusions of special reacting or cementing materials or special tremie placements of cemetitious mixtures.
After having drained the brine from the fill material 27, the strut 19 can, if desired, be removed and further excavation conducted down to a level exposing the tops of piles 22. At that point, a layer 32 of good rock is placed around the tops of the piles 22 whereby a concrete mat 23 can be formed on the tops of piles 22.
Mat 23 preferably can include a tapered or bevelled edge 33 against which a strut 34 can be positioned. The other end of strut 34 can then be attached near the upper edge of wall 14 in a manner to provide support between wall 14 and mat 23.
Subsequently, further excavation proceeds down through the sand 27 (or other stable material) placed into basin 24 until the only remaining stable material within the basin 24 is that which lies below the level of the bottom of mat 23. This remaining mat portion 27a (FIG. 8) is then graded level with the layer 32 of rock whereby additional concrete mat 36 can be formed between wall 14 and mat 23. Thus, lateral support is provided to the bottom end of wall 14 to counteract the inwardly pressing forces acting against the exterior of wall 14 at the lower end. In this manner, the lower end of wall 14 is securely stabilized.
From the foregoing, it will be apparent that the volume of the fill material 27 is suflicient to stand alone in providing suflicient stability to the lower end of the wall to permit the construction of the rest of the foundation to proceed as where the concrete mat 23 is then subsequently laid taking advantage of the stable block of material 27a then located at the base of wall 14. Once mat 23 has been laid, it is then possible to utilize struts cooperating with mat 23 and wall 14 at various levels to counteract inwardly pressing forces acting against the wall while the concrete of mat 36 is being poured and permitted to harden.
From the foregoing, it is also readily apparent that during one stage of the proceedings there is provided a construction wall structure in an unstable footing Wherein the stabilized wall construction comprises means forming an upright diaphragm wall, unstable footing material being located on one side of the wall at the lower end thereof while a mat of stable footing material on the other side of the wall has been formed. Further, a mat of concrete is superimposed upon the first name mat and serves to counteract laterally acting forces pressing against the outside of the wall.
Thus, the portion 27a forms a mat of stable footing material upon which the mat 36 of concrete can be applied.
In operation, the method described above serves to keep the walls 14 of the construction site from losing their support notwithstanding the fact that they are lodged in an unstable soil material.
What is claimed is:
1. In a method of providing stabilization for a construction wall in an unstable footing the steps comprising forming a basin upon the surfane of a construction zone, said basin having a predetermined depth and substantially fluid-impervious side wall boundaries including the upright wall structure to be stabilized forming at least a portion of said boundaries, applying a hydrostatic pressure to said wall from inside said zone to supplement other forces serving to resist countervailing forces acting on said wall from outside said zone, said supplemental hydrostatic pressure serving to bring the forces acting from within said zone to a level approximating the level of forces acting upon the wall from outside said zone, and, while maintaining said hydrostatic pressure, removing the soil materials of said zone down to a predetermined level and replacing the removed materials with a stabilizing fill material of greater strength, and thereafter removing the applied hydrostatic pressure.
2. In the method according to claim 1 wherein the step of applying the hydrostatic pressure includes the introduction into said basin of a head of fluid pressure relative to the level of the pre-existing surface of the zone.
3. In the method according to claim 1 wherein the step of applying the hydrostatic pressure includes the introduction of fluid into said basin said fluid having a density greater than that of Water.
4. In the method according to claim 1 wherein the step of applying the hydrostatic pressure includes the introduction of a head of fluid pressure into said basin, said fluid having a density greater than that of water.
5. In a method of providing stabilization for a construction wall in an unstable footing the steps comprising forming an upright wall substantially impervious to fluid to define at least a portion of the peripheral boundary of a construction zone, the top of the wall extending above the level of the pre-existing surface of said zone, completing the boundaries around said zone to extend upwardly to form a basin above the level of said preexisting surface, applying a hydrostatic pressure to act on said wall from inside said zone to raise the forces acting on the wall from within said zone to resist the countervailing forces acting on said wall from outside said zone, and, while maintaining said pressure, removing the soil materials of said zone down to a predetermined level and replacing the removed materials with a stabilizing fill of greater strength, and thereafter removing the applied hydrostatic pressure.
6. In a method of providing stabilization for a construction wall in an unstable footing the steps comprising forming an upright wall substantially impervious to fluid to define at least a portion of the boundaries of a construction zone, the top of the Wall extending a predetermined distance above the level of the existing surface of said zone, extending the rim of the zone boundaries upwards to form a basin above the level of the existing surface of the zone, filling the basin with fluid material to increase the hydrostatic pressure on the inside of the wall to provide a countering pressure acting to offset the forces pressing on the outside of the wall, and maintaining the applied pressure while removing the soil materials of the zone down to a predetermined level, and replacing the removed materials with a stabilizing fill of greater strength, while maintaining said hydrostatic pressure, thereafter removing the applied hydrostatic pressure.
7. In the construction of a wall structure in an unstable footing, a stabilized wall construction comprising means forming an upright diaphragm wall, untable footing material on one side of the wall at the lower end thereof, a mat of stable footing material on the other side of the wall, and a mat of concrete superimposed upon the first named mat serving to counteract laterally acting forces pressing against the outside of the Wall.
References Cited UNITED STATES PATENTS 1,320,720 11/1919 Tomlinson 61-50 2,184,974 12/1939 Henderson 6139 2,413,867 1/1947 Easterday 6139 2,960,745 11/ 1960 Wallace 61-50 JACOB SHAPIRO, Primary Examiner US. Cl. X.R.
US811331A 1969-03-28 1969-03-28 Method for constructing stabilized construction wall in unstable footing Expired - Lifetime US3563044A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US81133169A 1969-03-28 1969-03-28

Publications (1)

Publication Number Publication Date
US3563044A true US3563044A (en) 1971-02-16

Family

ID=25206252

Family Applications (1)

Application Number Title Priority Date Filing Date
US811331A Expired - Lifetime US3563044A (en) 1969-03-28 1969-03-28 Method for constructing stabilized construction wall in unstable footing

Country Status (1)

Country Link
US (1) US3563044A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4222684A (en) * 1977-10-26 1980-09-16 Winfried Rosenstock Method of driving sheet piles into a rock substratum
US4643111A (en) * 1985-08-21 1987-02-17 Jones Robert L Resource recovery utility
US4694625A (en) * 1986-04-02 1987-09-22 Gregory Steven D Foundation filing system
US4754588A (en) * 1987-06-26 1988-07-05 Gregory Steven D Foundation piling system
DE19616188A1 (en) * 1996-04-23 1997-11-13 Jan Dipl Ing Forster Method of placing a wall in a floor
US20040096277A1 (en) * 2002-06-03 2004-05-20 Russell Matthew F. Subterranean structrues and methods for constructing subterranean structures

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4222684A (en) * 1977-10-26 1980-09-16 Winfried Rosenstock Method of driving sheet piles into a rock substratum
US4643111A (en) * 1985-08-21 1987-02-17 Jones Robert L Resource recovery utility
US4694625A (en) * 1986-04-02 1987-09-22 Gregory Steven D Foundation filing system
US4754588A (en) * 1987-06-26 1988-07-05 Gregory Steven D Foundation piling system
DE19616188A1 (en) * 1996-04-23 1997-11-13 Jan Dipl Ing Forster Method of placing a wall in a floor
DE19616188C2 (en) * 1996-04-23 1998-07-02 Jan Dipl Ing Forster Method of erecting a wall in a floor
US20040096277A1 (en) * 2002-06-03 2004-05-20 Russell Matthew F. Subterranean structrues and methods for constructing subterranean structures
US7025537B2 (en) * 2002-06-03 2006-04-11 Russell Matthew F Subterranean structures and methods for constructing subterranean structures

Similar Documents

Publication Publication Date Title
US4165198A (en) Method for forming pier foundation columns
US4797031A (en) Caisson sinking method
CN108755731A (en) A kind of well foundation and construction method
US3563044A (en) Method for constructing stabilized construction wall in unstable footing
US4938634A (en) Process for lowering basement
US2381014A (en) Foundation and method of forming the same
US3526096A (en) Method of making rockfill foundations
JPH0220720A (en) Underground construction method by muddy water excavation
US3667238A (en) Stabilized construction wall in unstable footing
CN207211176U (en) A kind of big open caisson of superelevation
US4981399A (en) Method and apparatus for increasing bearing capacity of soft soil and constructing cutoff wall
US3269126A (en) Methods for stabilizing and raising foundation structures
JPS62215727A (en) Foundation work for structure
US2317017A (en) Pier and method of constructing the same
JPH0144852B2 (en)
JPH0776845A (en) Method of settling open caisson
JPS63535A (en) Earthquake-proof fortifying work for existing structure
US4468156A (en) Underwater structure and method for its construction
JPH1129927A (en) Ground subsidence preventive foundation pile using old tire block
JPH03103535A (en) Countermeasure structure for liquefaction of building
JP3176530B2 (en) Liquefaction countermeasures
JPH0536044Y2 (en)
RU2004691C1 (en) Method for construction of foundation in grounds with underlying soft grounds
RU2014394C1 (en) Method for constructing foundation for buildings on subsiding ground
JPH03281829A (en) Construction method of underground structure