US2317017A - Pier and method of constructing the same - Google Patents
Pier and method of constructing the same Download PDFInfo
- Publication number
- US2317017A US2317017A US363753A US36375340A US2317017A US 2317017 A US2317017 A US 2317017A US 363753 A US363753 A US 363753A US 36375340 A US36375340 A US 36375340A US 2317017 A US2317017 A US 2317017A
- Authority
- US
- United States
- Prior art keywords
- mat
- piles
- pier
- shell
- trench
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/20—Caisson foundations combined with pile foundations
Definitions
- This invention has reference generally to improvements in that class of inventions known as bridges and more particularly relates to an improved pier and method of constructing the same.
- the invention is an improvement or variation over my co-pending application bearing Serial Number 300,482 filed October 20, 1939.
- the primary object of the invention resides in a provision of a bridge or pier to be built in very deep water, and where the river bed does not offer sufiicient support for a cofferdam or caisson of the general types now in use.
- the invention may be said to conslst in the provision of a foundation, preferably, though not necessarily, in the form of a pier, temporarily maintaining a support above the bed of a river; driving plumb and batter piles therethrough until they strike rock and leaving portions projecting above the support, positioning a metallic shell over the projecting pile ends and on the temporary support, effecting a pour of Tremie concrete within the shell and on the support and allowing the same to set so that it will be bonded to the piles and the shell and constitute a main support for the latter; then making further pours which are bonded to the extreme upper projecting and capped ends of the piles and the shell and inserting reinforcing material in the shell.
- the invention may be said to consist in the provision of a pier and a method of erecting or constructing the same consisting, briefly, in excavating a trench in the bottom of a river bed wherein the top soil is too soft or yielding to support a pier without piles; then temporarily arranging pile clusters or dolphins at or beyond the corners of the trench; then driving and cutting off at proper elevation suincient timber piles at desired points in the trench so as toform a temporary support; then taking a buoyant body in the form of a timber mat and positioning the same as by floating to a position above the trench; then driving guide piles through openings positioned substantially, centrally, or in other convenient points of th mat until they strike rock; then sinking the mat preferably through the aid of diaphragm supports, along the guide piles so that the mat will rest in the proper position in the prepared trench; then removing or cutting off the extreme upper part of the guide pile or piles; then driving plumb and batter piles through openings provided in the mat in such manner that portions
- Figure l is a sectional view through a river bed showing a trench dug therein, the bottom of which is reinforced by timber piles.
- Figure 2 is a top plan View showing diagrammatically a mat connected with temporary dolphins in a position to be properly sunk into the trench.
- Figure 3 is a sectional view showing guide piles which have been driven through desired points of the mat and trench until they strike rock, the mat being shown prior to being sunk and anchored to the dolphins.
- Figure i is a similar view showing the mat after it has been
- Figure 5 is a similar View with the guide piles cut off and with plumb and batter piles driven through th mat to the rock.
- Figure 6 is an enlarged sectional view partly in elevation of the completed pier.
- Figure '7 is a top plan detail showing an arrangement of piles in the mat.
- Figure 8 is a top plan View of a completed pier.
- Figure 9 is an elevational view of a modified arrangement.
- a river bed which consists of soft river mud over a layer of silty sand 2, which rests on solid rock 5.
- a trench l is dredged in the soft river mud to a sufficient depth to insure that the piles supporting th pier may be protected by the surrounding mud or sand in the river bed after the trench has been backfilled.
- timber piles 5 for reinforcing purposes which are cut off to a predetermined elevation by means of an underwater or submarine saw.
- pile dolphins 5 Temporarily arranged about the trench in the proximity of, or otherwise arranged in convenient locations are pile dolphins 5.
- mat l subsequently to be used as a bottom form, which is preferably constructed on shore, and is provided with openings 8 and $3.
- the mat is towed to a position over the trench and is fastened to the pile dolphins t'by suitable connecting means it adjustable in any suitable manner in order that he mat may be accurately positioned on the exact center line of the bridge and the exact center line of the pier prior to being sunk.
- supports H for the diaphragm of the pier shell are also arranged transversely of the mat. These supports, in effect, constitute a weight.
- guide piles i2 which later are to be used in a permanent manner, are driven through the central openings 3 and into and through the mud and sand of the river bed until they strike the rock formation 3.
- the mat is sunk and is controlled by suitable means such as cables it on derrick scows ill or other floating equipment utilized for this purpose.
- the mat on contacting the previously cut off timber piles or the bottom of the trench acts as a support and a bottom form.
- the upper parts of the guide piles 52 are removed to facilitate the driving of additional plumb and batter piles it, through the mat which may be of any desired form, such as H-piles or pipe piles, or combination pipe and H-piles, or wood, or concrete, or, in effect, any type of pile in use today.
- These piles preferably are driven through the mud and silty sand until they strike the rock, and driving may be effected by telescopic leads and with the use of an underwater or they may be driven to the exact position by a pile driver it supported a scow l5.
- the batter piles are located, only at the outside of the mat, to overcome the efiect longitudinal and lateral forces applied to the or.
- the suitable covers In order to positively exclude the of mud from passing upwardly through the suitable covers it are installed on the upper surface of the mat to close the openings through the mat and around each pile. This also eflecte a saving of concrete, in a manner which will appear.
- the next step is the arranging of the steel pier shell generally designated 56 about the clustered upper ends of the piles and on the mat.
- the pier shell consists of two leg portions ll, having enlarged or bell shaped lower ends it, the leg portions being connected by a diaphragm or reinforced steel web is consistirn of, for instance, spaced walls 20 reinforced in proper space relation by suitable steel struts or ties The sinking of each reinforced shell is effected in any desired manner.
- the reinforced web lil has its walls joined with the shells in such a manner that it forms a buoyant body and it is highly instrumental in effecting a proper sinking of the unit by permitting of the desired amount of water being pumped tliereinto during the sinking operation; or the entire unit consisting of the two leg portions ll connected rigidly by the reinforced web ill may be lowered into position by means of suitable cables without efiecting the watertight connection, by allowing the leg portions and the entire connecting reinforced web to be entirely opened to allow water to pass freely between the side walls of the reinforced web into the steel shells.
- temporary domes or caps may be applied to the top of the steel sheel IE to facilitate the floating of the same into position, the caps being removed prior to the sinking of the shells.
- a first pour of Tremie concrete 22 is now made within the bell-shaped portions E8 to a depth, for instance in practice of about five fee or to a point short of the upper ends of the piles l2 and This pour is allowed to set and being bonded to the piles l2 and i3 and to the pier shells constitute the main support for the latter.
- a second pour of Tremie concrete is now made to the tops of the enlarged portions or bells l8 and is bonded to the first pour and the extreme upper projecting ends of the piles l2 and I3.
- Tremie concrete Additional pours of Tremie concrete are made, for instance to a point 2 in Figure 6 from which point the pier shells may be unwatered and the remainder fitted with further reinforcing means 25 in a manner similar to that described in my co-pending application 390,482 filed October 20, 1939, and concrete poured in a dry state to the top of the pier.
- a method of making a bridge pier including excavating a trench in the bottom of a river bed, temporarily arranging pile dolphins at the corners of the trench. floating a perforated buoyant mat into a position above the trench, adjustably connecting the buoyant mat to the pile dolphins to ensure an accurate positioning of the mat, driving guide piles at desired points through perforations in the mat, applying diaphragm pier supports to the mat to serve as Weights to facilitate sinking of the mat along the guide piles so that the mat rests properly in the prepared trench, then removing the upper part of the guide piles, then driving plumb and batter piles through perforations in the mat in such manner as to leave the upper portions projecting above the mat, then floating a pier shell having spaced and diaphragm connected leg portions and sinking the same so that the lower ends of the leg portions enclose the upper projecting ends of the piles and contact the mat while the diaphragm portion between the leg portions rests on the supports on the mat, then effecting a pour of Tre
- a pier of the character described including a perforated mat, piles arranged through the mat and having the upper ends projecting above the mat, a metallic pier shell including spaced leg portions having open bottoms and a hollow web connecting the leg portions together, the leg portions having enlarged bell-shaped lower ends disposed over the upper projecting ends of the piles and arranged on the mat, supports on the mat between the leg portions for the connecting web, a pour of Tremie concrete arranged Within the enlarged ends of the leg portions of the pier shell and on the mat and forming a base and bonded to the projecting ends of the piles and to the pier shell, a second pour of Tremie concrete also arranged within the lower ends of the leg portions and bonded to the extreme upper ends of the piles situated therein, and further pours of Tremie concrete arranged in the leg portions and the web and extending to the top of the pier shell, and reinforcing means within the pier shell.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Description
April 20, 1943. H. H. ALLEN 2,317,017
PIER AND METHOD OF CONSTRUCTING THE SAME Filed Oct. 31, 1940 4 Sheets-Sheet l A ril 20, 1943. H. H. ALLEN 2,317,017
PIER AND METHOD OF CONSTRUCTING THE SAME Filed Oct. 51, 1940 4 Sheets-Sheet 2 if Eyen}; F l
April 20, 1943. H. H. ALLEN 2,317,017
PIER AND METHOD OF CONSTRUCTING THE SAME Filed Oct. 51, 1940 4 Sheets-Sheet 3 I, sag 11'" .25 I I Eye/2%);
H. H. ALLEN April 20, 1943.
P IER AND METHOD OF CONSTRUCTING THE SAME 4 Sheets-Sheet 4 Filed 001;. 31, 1940 w: til
-&
Patented Apr. 20, 1943 PIER AND METHOD OF SAME Herschel H. Allen, Baltimore, Md.
Application October 31, 1940, Serial No. 363,753
2 Claims.
This invention has reference generally to improvements in that class of inventions known as bridges and more particularly relates to an improved pier and method of constructing the same.
The invention is an improvement or variation over my co-pending application bearing Serial Number 300,482 filed October 20, 1939.
The primary object of the invention resides in a provision of a bridge or pier to be built in very deep water, and where the river bed does not offer sufiicient support for a cofferdam or caisson of the general types now in use.
Generally, the invention may be said to conslst in the provision of a foundation, preferably, though not necessarily, in the form of a pier, temporarily maintaining a support above the bed of a river; driving plumb and batter piles therethrough until they strike rock and leaving portions projecting above the support, positioning a metallic shell over the projecting pile ends and on the temporary support, effecting a pour of Tremie concrete within the shell and on the support and allowing the same to set so that it will be bonded to the piles and the shell and constitute a main support for the latter; then making further pours which are bonded to the extreme upper projecting and capped ends of the piles and the shell and inserting reinforcing material in the shell.
More particularly the invention may be said to consist in the provision of a pier and a method of erecting or constructing the same consisting, briefly, in excavating a trench in the bottom of a river bed wherein the top soil is too soft or yielding to support a pier without piles; then temporarily arranging pile clusters or dolphins at or beyond the corners of the trench; then driving and cutting off at proper elevation suincient timber piles at desired points in the trench so as toform a temporary support; then taking a buoyant body in the form of a timber mat and positioning the same as by floating to a position above the trench; then driving guide piles through openings positioned substantially, centrally, or in other convenient points of th mat until they strike rock; then sinking the mat preferably through the aid of diaphragm supports, along the guide piles so that the mat will rest in the proper position in the prepared trench; then removing or cutting off the extreme upper part of the guide pile or piles; then driving plumb and batter piles through openings provided in the mat in such manner that portions of the upper part of the piles extend consider- CONSTRUCTING THE ably above the mat, then arranging covers on the upper surface of the mat about the projecting ends of the piles to close any openings in th mat and preventing the passage of mud therethrough then flotating and sinking a hollow steel pier shell of metal so that the leg portion or portions of the metal shell enclose th upper projecting ends of the cluster or clusters of piles on the mat; then pouring Tremie concrete into the lower portions of the pier shell or form, for instance to a depeth of five feet, and allowing the same to set and to be bound to the upper portions of the batter piles so that th weight will thereby be transmitted through this pour to the piles and thence to the rock then effecting a second pour of Tremie concrete on the first pour and about the upper projecting and preferably capped ends of the piles, for instance to the top of the enlarged leg portions or bells of the pier shell then continuing Tremie pours to a point near the surface of the water; then unwatering the top of the shells and finally pouring concrete in a dry state to the top of the pier shell and simultaneously with the various pourings arranging reinforced steel throughout the height of the pier from the mat to the top thereof,
Other objects, as well as the nature, charac teristic features and scope of the invention will be more readily apparent from th following description taken in connection with the accompanying drawings and pointed out in the claims which form a part of this specification.
Th invention is clearly illustrated in the accompanying drawings in which:
Figure l is a sectional view through a river bed showing a trench dug therein, the bottom of which is reinforced by timber piles.
Figure 2 is a top plan View showing diagrammatically a mat connected with temporary dolphins in a position to be properly sunk into the trench.
Figure 3 is a sectional view showing guide piles which have been driven through desired points of the mat and trench until they strike rock, the mat being shown prior to being sunk and anchored to the dolphins.
Figure i is a similar view showing the mat after it has been Figure 5 is a similar View with the guide piles cut off and with plumb and batter piles driven through th mat to the rock.
Figure 6 is an enlarged sectional view partly in elevation of the completed pier.
Figure '7 is a top plan detail showing an arrangement of piles in the mat.
Figure 8 is a top plan View of a completed pier.
Figure 9 is an elevational view of a modified arrangement.
Similar characters of reference are employed in all of the above described views to indicate corresponding parts.
Referring now, mor particularly, to the accompanying drawings, there is illustrated a river bed which consists of soft river mud over a layer of silty sand 2, which rests on solid rock 5. A trench l, is dredged in the soft river mud to a sufficient depth to insure that the piles supporting th pier may be protected by the surrounding mud or sand in the river bed after the trench has been backfilled. Driven into the trench 4, are timber piles 5, for reinforcing purposes which are cut off to a predetermined elevation by means of an underwater or submarine saw.
Temporarily arranged about the trench in the proximity of, or otherwise arranged in convenient locations are pile dolphins 5.
There is now provided in mat l, subsequently to be used as a bottom form, which is preferably constructed on shore, and is provided with openings 8 and $3. The mat is towed to a position over the trench and is fastened to the pile dolphins t'by suitable connecting means it adjustable in any suitable manner in order that he mat may be accurately positioned on the exact center line of the bridge and the exact center line of the pier prior to being sunk.
Also arranged transversely of the mat, are supports H for the diaphragm of the pier shell. These supports, in effect, constitute a weight.
In order to guide the mat with the supports l l thereon into a proper position prior to being sunk, guide piles i2, which later are to be used in a permanent manner, are driven through the central openings 3 and into and through the mud and sand of the river bed until they strike the rock formation 3. After the adjusting means lb has been released, the mat is sunk and is controlled by suitable means such as cables it on derrick scows ill or other floating equipment utilized for this purpose. The mat, on contacting the previously cut off timber piles or the bottom of the trench acts as a support and a bottom form.
After the mat has been sunk to the position shown in Figure 5, the upper parts of the guide piles 52 are removed to facilitate the driving of additional plumb and batter piles it, through the mat which may be of any desired form, such as H-piles or pipe piles, or combination pipe and H-piles, or wood, or concrete, or, in effect, any type of pile in use today. These piles preferably are driven through the mud and silty sand until they strike the rock, and driving may be effected by telescopic leads and with the use of an underwater or they may be driven to the exact position by a pile driver it supported a scow l5.
Preferably, the batter piles are located, only at the outside of the mat, to overcome the efiect longitudinal and lateral forces applied to the or. In order to positively exclude the of mud from passing upwardly through the suitable covers it are installed on the upper surface of the mat to close the openings through the mat and around each pile. This also eflecte a saving of concrete, in a manner which will appear.
The next step is the arranging of the steel pier shell generally designated 56 about the clustered upper ends of the piles and on the mat. In the present instance, the pier shell consists of two leg portions ll, having enlarged or bell shaped lower ends it, the leg portions being connected by a diaphragm or reinforced steel web is consistirn of, for instance, spaced walls 20 reinforced in proper space relation by suitable steel struts or ties The sinking of each reinforced shell is effected in any desired manner. It is to be noted that the reinforced web lil has its walls joined with the shells in such a manner that it forms a buoyant body and it is highly instrumental in effecting a proper sinking of the unit by permitting of the desired amount of water being pumped tliereinto during the sinking operation; or the entire unit consisting of the two leg portions ll connected rigidly by the reinforced web ill may be lowered into position by means of suitable cables without efiecting the watertight connection, by allowing the leg portions and the entire connecting reinforced web to be entirely opened to allow water to pass freely between the side walls of the reinforced web into the steel shells. If desired, temporary domes or caps may be applied to the top of the steel sheel IE to facilitate the floating of the same into position, the caps being removed prior to the sinking of the shells.
A first pour of Tremie concrete 22 is now made within the bell-shaped portions E8 to a depth, for instance in practice of about five fee or to a point short of the upper ends of the piles l2 and This pour is allowed to set and being bonded to the piles l2 and i3 and to the pier shells constitute the main support for the latter. A second pour of Tremie concrete is now made to the tops of the enlarged portions or bells l8 and is bonded to the first pour and the extreme upper projecting ends of the piles l2 and I3. Additional pours of Tremie concrete are made, for instance to a point 2 in Figure 6 from which point the pier shells may be unwatered and the remainder fitted with further reinforcing means 25 in a manner similar to that described in my co-pending application 390,482 filed October 20, 1939, and concrete poured in a dry state to the top of the pier.
Finally the trench is backfilled as shown at 26. The second and additional pourings of Tremie concrete into the shell I 5 and about the reinforcing means therein, act to tie the leg portions and the web together as a unit and insure the transit of all vertical and horizontal portions to the first pour within the bottom of the leg portions, particularly since the second pour is bonded to the first pour by the extreme upper projecting ends of the piles i2 and I3.
Obviously, instead of having two leg portions in a pier only one may be used, or a four-legged or four stemmed pier may be used as in my copending' application, Serial Number 300,482 filed October 20, 1939. It is to be noted that the supports I! which serve as a weight, act to support the diaphragm or web I?! of the bridge shell.
As shown in Figure 9 instead of excavating a trench, timber piles 21 are driven through the mud and part of the sand while the upper ends terminate at points considerably above the river bed and constitute a support for the mat which if desired instead of being buoyant may consist of a perforated metal plate 23. The plumb and batter piles 29 are now driven through the perforated mat 29 until they strike rock in the same manner as in the preferred form. The pier shell generally designated 30 is now arranged on the mat and then pourings of concrete as described in connection with the preferred form indicated herein.
It is believed in view of the foregoing description that a further detailed description of the invention is entirely unnecessary. Likewise it is believed that the advantages of the invention Will be readily apparent.
Having thus fully described the invention, what is claimed as new and desired to be secured by Letters Patent is:
l. A method of making a bridge pier including excavating a trench in the bottom of a river bed, temporarily arranging pile dolphins at the corners of the trench. floating a perforated buoyant mat into a position above the trench, adjustably connecting the buoyant mat to the pile dolphins to ensure an accurate positioning of the mat, driving guide piles at desired points through perforations in the mat, applying diaphragm pier supports to the mat to serve as Weights to facilitate sinking of the mat along the guide piles so that the mat rests properly in the prepared trench, then removing the upper part of the guide piles, then driving plumb and batter piles through perforations in the mat in such manner as to leave the upper portions projecting above the mat, then floating a pier shell having spaced and diaphragm connected leg portions and sinking the same so that the lower ends of the leg portions enclose the upper projecting ends of the piles and contact the mat while the diaphragm portion between the leg portions rests on the supports on the mat, then effecting a pour of Tremie concrete within the lower portion of the leg portions so as to form a base and to bond the leg portions to the piles, then effecting a second pour of Tremie concrete on the first pour and about the upper projecting ends of the piles,
applying reinforcing material within the pier shell, and finally completely filling the pier with cementitious material.
2. A pier of the character described including a perforated mat, piles arranged through the mat and having the upper ends projecting above the mat, a metallic pier shell including spaced leg portions having open bottoms and a hollow web connecting the leg portions together, the leg portions having enlarged bell-shaped lower ends disposed over the upper projecting ends of the piles and arranged on the mat, supports on the mat between the leg portions for the connecting web, a pour of Tremie concrete arranged Within the enlarged ends of the leg portions of the pier shell and on the mat and forming a base and bonded to the projecting ends of the piles and to the pier shell, a second pour of Tremie concrete also arranged within the lower ends of the leg portions and bonded to the extreme upper ends of the piles situated therein, and further pours of Tremie concrete arranged in the leg portions and the web and extending to the top of the pier shell, and reinforcing means within the pier shell.
HERSCI-IEL H. ALLEN.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US363753A US2317017A (en) | 1940-10-31 | 1940-10-31 | Pier and method of constructing the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US363753A US2317017A (en) | 1940-10-31 | 1940-10-31 | Pier and method of constructing the same |
Publications (1)
Publication Number | Publication Date |
---|---|
US2317017A true US2317017A (en) | 1943-04-20 |
Family
ID=23431576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US363753A Expired - Lifetime US2317017A (en) | 1940-10-31 | 1940-10-31 | Pier and method of constructing the same |
Country Status (1)
Country | Link |
---|---|
US (1) | US2317017A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2608830A (en) * | 1946-06-13 | 1952-09-02 | Western Foundation Corp | Foundation structure |
US2612024A (en) * | 1948-12-18 | 1952-09-30 | William A Hunsucker | Submarine foundation and method of erecting |
US2912828A (en) * | 1954-03-25 | 1959-11-17 | Ben C Gerwick Inc | Pier construction method |
US3255591A (en) * | 1961-08-23 | 1966-06-14 | Thornley Beatrice | Horizontally stabilized foundation |
AT394221B (en) * | 1988-02-15 | 1992-02-25 | Ut Vasuttervezoe Vallalat | Method of erecting a construction object |
-
1940
- 1940-10-31 US US363753A patent/US2317017A/en not_active Expired - Lifetime
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2608830A (en) * | 1946-06-13 | 1952-09-02 | Western Foundation Corp | Foundation structure |
US2612024A (en) * | 1948-12-18 | 1952-09-30 | William A Hunsucker | Submarine foundation and method of erecting |
US2912828A (en) * | 1954-03-25 | 1959-11-17 | Ben C Gerwick Inc | Pier construction method |
US3255591A (en) * | 1961-08-23 | 1966-06-14 | Thornley Beatrice | Horizontally stabilized foundation |
AT394221B (en) * | 1988-02-15 | 1992-02-25 | Ut Vasuttervezoe Vallalat | Method of erecting a construction object |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20150071711A1 (en) | Partially floating marine platform for offshore wind-power, bridges and marine buildings, and construction method | |
US2236682A (en) | Marine foundation and method of construction | |
CN106223355A (en) | A kind of high bearing platform supported on piles in deep water Hold Hoop method has device and the construction method of end steel jacket box | |
WO2014121684A1 (en) | Pre-formed marine fixed platform and method of installation | |
US4648752A (en) | Marine template retaining wall and method of construction | |
US2317017A (en) | Pier and method of constructing the same | |
US2317016A (en) | Bridge foundation and method of making same | |
US2472869A (en) | Island for well drilling | |
GB263997A (en) | Improvements in and relating to the construction of quay walls, piers and other marine structures | |
US2101358A (en) | Method of making load sustaining structures | |
RU2057845C1 (en) | Method for installation of marine stationary platform with flat bottom and marine stationary platform | |
NO742938L (en) | ||
US1856312A (en) | Island structure | |
US1907854A (en) | Sinking foundation | |
JP2000290936A (en) | Method and caisson for constructing bridge pier footing | |
US3563044A (en) | Method for constructing stabilized construction wall in unstable footing | |
US3824794A (en) | Offshore marine anchoring structure | |
US2043452A (en) | Combined cofferdam and pier fender construction method | |
US1727085A (en) | Concrete bridge pier and pier foundation | |
SU433272A1 (en) | ISLAND ICE-RESISTANT KNIFE FOR DRILLING ON THE SEAS | |
US1418879A (en) | Cofferdam construction | |
US2203978A (en) | Means and method of shoring bell bottom pile holes | |
JPS60215924A (en) | Settlement of steel skeleton for underwater foundation structure | |
JPS6313482B2 (en) | ||
US1750137A (en) | Method of and apparatus for setting precast forms in aqueous bodies |