US20120227353A1 - Method for installing a large-span cylindrical reticulated shell - Google Patents

Method for installing a large-span cylindrical reticulated shell Download PDF

Info

Publication number
US20120227353A1
US20120227353A1 US13/475,499 US201213475499A US2012227353A1 US 20120227353 A1 US20120227353 A1 US 20120227353A1 US 201213475499 A US201213475499 A US 201213475499A US 2012227353 A1 US2012227353 A1 US 2012227353A1
Authority
US
United States
Prior art keywords
vault
mother
installation
ball joint
reticulated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/475,499
Inventor
Yuping XU
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of US20120227353A1 publication Critical patent/US20120227353A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • E04B1/3205Structures with a longitudinal horizontal axis, e.g. cylindrical or prismatic structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • E04B1/1906Connecting nodes specially adapted therefor with central spherical, semispherical or polyhedral connecting element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B2001/1924Struts specially adapted therefor
    • E04B2001/1927Struts specially adapted therefor of essentially circular cross section
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B2001/1957Details of connections between nodes and struts
    • E04B2001/196Screw connections with axis parallel to the main axis of the strut
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • E04B2001/3217Auxiliary supporting devices used during erection of the arched structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/32Arched structures; Vaulted structures; Folded structures
    • E04B2001/3235Arched structures; Vaulted structures; Folded structures having a grid frame

Definitions

  • the invention relates to a method of construction and installation of a large-span cylindrical reticulated shell structure, in particular to a method for installing a large-span cylindrical reticulated shell.
  • a heat power plant often needs a dry coal shed with net span of more than 76 meters generally, and sometimes even more than 100 meters because of the usage of coal stoker.
  • the net height is above twenty-eight meters generally.
  • a scientific, economical and reasonable scheme for the large-span closed shed with a great height is a cylindrical reticulated shell, which has been validated through calculation of mathematical theory and mechanical theory.
  • the installation process is a changing and developing process. The expenses and construction periods vary with different installation processes, thus the effect is different.
  • Traditional construction processes include an overall scaffold construction method and a local scaffold construction method.
  • the scaffold In the overall scaffold construction method, the scaffold is required to be built in the coverage area of the entire cylindrical reticulated shell, thus the construction period is long, and the cost is high; in the local scaffold construction method, firstly, the scaffold is built for installing an anchor ring, and the anchor ring extends towards two sides by adopting a high-altitude overhanging construction method based on the anchor ring. Since only partial scaffolds are required to be built, the local scaffold construction method is favorable for reducing the construction period and the construction cost.
  • Chinese Patent Application No. 200810231497.2 entitled “A High-Altitude Overhanging Construction Method for a Cylindrical Shell Type Bolted Ball Joint Net Frame” discloses a local scaffold construction method.
  • a scaffold with a height equivalent to the highest position of the cylindrical reticulated shell has to be built even in the local scaffold construction method, and as to the extra-large and extra-high cylindrical reticulated shells, the construction cost and the construction difficulty are still relatively high.
  • the invention provides a method for installing a large-span cylindrical reticulated shell.
  • a scaffold is not required to be built, and a crane is used as an auxiliary tool, therefore the method is simple and practical and has high reliability, low cost and short construction period.
  • the method for installing a large-span cylindrical reticulated shell comprises the following steps:
  • each reticulated vault at least comprises four support bases ( 1 ) symmetrically arranged on both sides of the reticulated vault and ball joints and pull rods which are respectively installed on the four support bases ( 1 ) and mutually connected into a net frame shape; firstly, a reticulated vault is installed and called as a mother vault, a rotatable ball joint ( 2 ) is respectively installed on the support base ( 1 ) on any side of the mother vault, and then other ball joints and pull rods on the mother vault are respectively installed in sequence by taking the rotatable ball joint ( 2 ) as the starting point; the mother vault which should be installed in a vertical high-altitude extending manner is installed in a transverse extending manner during the installation of the ball joints and the pull rods, and a lifting device ( 3 ) is used for lifting the extension tail end of the mother vault during the transverse
  • the ball joint in the symmetrical position of the rotatable ball joint ( 2 ) is fixed on the support base in the corresponding position, i.e., the installation of the entire mother vault is completed; a high-altitude overhanging construction method is adopted after the completion of installation of the mother vault, and other reticulated vaults adjacent to the mother vault are respectively installed in sequence along the axial extending direction of the mother vault until the completion of installation of the entire large-span cylindrical reticulated shell.
  • the rotatable ball joint ( 2 ) is rotatably installed on the support base ( 1 ) during the installation of the mother vault; the rotatable ball joint ( 2 ) is fixed with the support base after the completion of installation of the reticulated vaults and before the completion of installation of the entire large-span cylindrical reticulated shell.
  • the scaffold is not required, and the crane and other lifting devices are used as auxiliary tools, therefore, the installation process is simple and practical and is highly reliable, with a low cost and a short construction period.
  • FIG. 1 is an elevational view of an embodiment of the large-span cylindrical reticulated shell ;
  • FIG. 2 is an elevational view of the mother vault when the mother vault is being installed
  • FIG. 3 is an elevational view of the mother vault at the last stage of the assembling process
  • FIG. 4 is an elevational view of the mother vault after the assembling process is completed.
  • FIG. 5 is a schematic view of the support base and a ball joint.
  • FIG. 6 is a schematic view of a ball joint.
  • FIG. 7 is a schematic view showing a high altitude overhanging construction method.
  • FIG. 8 is a schematic view of a finished structure by a method of installing a large-span cylindrical reticulated shell.
  • the method for installing the large-span cylindrical reticulated shell comprises the following steps:
  • each reticulated vault at least comprises four support bases ( 1 ) symmetrically arranged on both sides of the reticulated vault and ball joints and pull rods which are respectively installed on the four support bases ( 1 ) and mutually connected into a net shape frame; firstly, a reticulated vault called a mother vault is installed, two support bases ( 1 ) are respectively arranged on both sides of the mother vault in the embodiment, and a rotatable ball joint ( 2 ) is respectively installed on the support base ( 1 ) on any side of the mother vault; the rotatable ball joint ( 2 ) is rotatably installed on the support base ( 1 ).
  • the rotatable ball joint ( 2 ) can be bound on the support base ( 1 ) through a chain or a steel wire rope. As shown in FIG. 5 , one end of the steel wire rope ( 7 ) is connected to the support base ( 1 ), and the other end movably holds the ball joint ( 2 ). Alternatively, a deeper ball socket is directly arranged at the top end of the support base ( 1 ), and the rotatable ball joint ( 2 ) is installed in the ball socket; the rotatable ball joint ( 2 ) can be installed at the top end of the support base ( 1 ) by adopting the two methods above, which can rotate, but cannot fall off from the support base ( 1 ).
  • a lifting device ( 3 ) is used for properly lifting the extension tail end of the mother vault at the moment, so that the height of the extension tail end always allows the installation construction to be performed on the ground level, and the rotatable ball joint ( 2 ) gradually rotates to the designed angle along the rise of the extension tail end.
  • the lifting device ( 3 ) can adopt various devices capable of raising the height such as cranes, hoists, hydraulic jacks, chain blocks and the like. The mother vault is hung in the position where the stress is most reasonable, and the deformation is smallest during the lifting process according to the force principle.
  • the ball joint in the symmetrical position of the rotatable ball joint ( 2 ) is fixed on the support base, i.e., the installation of the entire mother vault is completed; after the completion of installation of the mother vault, the rotatable ball joint ( 2 ) can be fixed with the support base ( 1 ), by a fastening method, e.g., a welding method.
  • the installed mother vault is the first vault. After the installation of the mother vault, a high-altitude overhanging construction method is adopted to install the other reticulated vaults one by one longitudinally.
  • each reticulated vault After the installation of a top ball joint 51 in a bottom circumferential vault line, the very adjacent bottom ball joint 52 in a top circumferential vault line will be installed. This step is repeated until the whole reticulated vault is finished.
  • the whole large-span cylindrical reticulated shell is longitudinally divided into several reticulated vaults.
  • the span of each reticulated vault is equal to the designed span of the reticulated shell.
  • every ball joint ( 5 ) is connected to one circumferential vertical chord rod, one circumferential chord rod, and two flank rod to form an installing unit containing one ball and four rods.
  • a crane is then used to lift a unit to the proper installation position in the air, then the unit is connected to other installed units.
  • other reticulated vaults adjacent to the mother vault are respectively installed in sequence in an axially extending direction of the mother vault until the completion of the installation of the entire large-span cylindrical reticulated shell.
  • J, L and N are top circumferential vault lines, which contains top ball joints J 1 , J 1 + 1 , J 1 ⁇ 1 , L 1 , L 1 + 1 , L 1 ⁇ 1 , N 1 , N 1 + 1 and N 1 ⁇ 1 ;
  • K, M are bottom circumferential vault lines, which contains bottom ball joints K 1 , K 1 ⁇ 1 , M 1 , and M 1 ⁇ 1 .
  • the solid lines indicate the part where ball joints and pull rods have been installed on the top circumferential vault lines J and L, and the bottom circumferential vault line K in the mother vault.
  • the dashed lines indicate the uninstalled parts in the top circumferential vault line N and the bottom circumferential vault line M.
  • each ball joint is connected to the corresponding rods on the ground to form an installation unit with one ball and four rods according to design requirements.
  • the ball joint on the bottom circumferential line M 1 is connected to a vertical rod M 1 K 1 , a bottom circumferential chord rod M 1 M 1 ⁇ 1 and two flank rods M 1 L 1 and M 1 L 1 + 1 to form an unit of one ball and four rods. The unit is then lifted to its corresponding installation position.
  • Each ball joint on the top circumferential line N is connected to corresponding rods on the ground to form an installation unit with one ball and four rods according to design requirements.
  • the ball joint on the top circumferential line N 1 is connected to a top circumferential vertical rod N 1 L 1 , a bottom circumferential chord rod N 1 N 1 ⁇ 1 and two flank rods N 1 M 1 ⁇ 1 and N 1 M 1 to form a unit of one ball and four rods. The unit is then lifted to its corresponding installation position.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

A method of construction and installation of a large-span cylindrical reticulated shell comprises: installing a mother vault on the ground by a bulk method; pushing the mother vault gradually during the installation, so as to be match with a lifting device for lifting the extension tail end of the mother vault; adjusting the height of the extension tail end to allow the extension tail end to be maintained at a ground level for ground installation construction; and after the installation of the mother vault is completed, using a high-altitude overhanging construction method to install the other reticulated vaults adjacent to the mother vault, respectively, in sequence along the axial extending direction of the mother vault until the completion of installation of the entire large-span cylindrical reticulated shell is completed.

Description

    TECHNICAL FIELD
  • The invention relates to a method of construction and installation of a large-span cylindrical reticulated shell structure, in particular to a method for installing a large-span cylindrical reticulated shell.
  • BACKGROUND
  • A heat power plant often needs a dry coal shed with net span of more than 76 meters generally, and sometimes even more than 100 meters because of the usage of coal stoker. The net height is above twenty-eight meters generally. A scientific, economical and reasonable scheme for the large-span closed shed with a great height is a cylindrical reticulated shell, which has been validated through calculation of mathematical theory and mechanical theory. However, the installation process is a changing and developing process. The expenses and construction periods vary with different installation processes, thus the effect is different. Traditional construction processes include an overall scaffold construction method and a local scaffold construction method. In the overall scaffold construction method, the scaffold is required to be built in the coverage area of the entire cylindrical reticulated shell, thus the construction period is long, and the cost is high; in the local scaffold construction method, firstly, the scaffold is built for installing an anchor ring, and the anchor ring extends towards two sides by adopting a high-altitude overhanging construction method based on the anchor ring. Since only partial scaffolds are required to be built, the local scaffold construction method is favorable for reducing the construction period and the construction cost. For example, Chinese Patent Application No. 200810231497.2, entitled “A High-Altitude Overhanging Construction Method for a Cylindrical Shell Type Bolted Ball Joint Net Frame” discloses a local scaffold construction method. However, a scaffold with a height equivalent to the highest position of the cylindrical reticulated shell has to be built even in the local scaffold construction method, and as to the extra-large and extra-high cylindrical reticulated shells, the construction cost and the construction difficulty are still relatively high.
  • SUMMARY
  • The invention provides a method for installing a large-span cylindrical reticulated shell. A scaffold is not required to be built, and a crane is used as an auxiliary tool, therefore the method is simple and practical and has high reliability, low cost and short construction period.
  • To achieve its purposes, the invention adopts the following technical scheme:
  • The method for installing a large-span cylindrical reticulated shell comprises the following steps:
  • A) The large-span cylindrical reticulated shell is divided into a plurality of axially arranged reticulated vaults according to the supporting conditions, and each reticulated vault at least comprises four support bases (1) symmetrically arranged on both sides of the reticulated vault and ball joints and pull rods which are respectively installed on the four support bases (1) and mutually connected into a net frame shape; firstly, a reticulated vault is installed and called as a mother vault, a rotatable ball joint (2) is respectively installed on the support base (1) on any side of the mother vault, and then other ball joints and pull rods on the mother vault are respectively installed in sequence by taking the rotatable ball joint (2) as the starting point; the mother vault which should be installed in a vertical high-altitude extending manner is installed in a transverse extending manner during the installation of the ball joints and the pull rods, and a lifting device (3) is used for lifting the extension tail end of the mother vault during the transverse extending process of the mother vault, so that the height of the extension tail end always meets the requirement of ground installation construction;
  • B) After the completion of connection between all the ball joints and pull rods on the mother vault, the ball joint in the symmetrical position of the rotatable ball joint (2) is fixed on the support base in the corresponding position, i.e., the installation of the entire mother vault is completed; a high-altitude overhanging construction method is adopted after the completion of installation of the mother vault, and other reticulated vaults adjacent to the mother vault are respectively installed in sequence along the axial extending direction of the mother vault until the completion of installation of the entire large-span cylindrical reticulated shell.
  • The rotatable ball joint (2) is rotatably installed on the support base (1) during the installation of the mother vault; the rotatable ball joint (2) is fixed with the support base after the completion of installation of the reticulated vaults and before the completion of installation of the entire large-span cylindrical reticulated shell.
  • By adopting the technical scheme, in the installation process, the scaffold is not required, and the crane and other lifting devices are used as auxiliary tools, therefore, the installation process is simple and practical and is highly reliable, with a low cost and a short construction period.
  • BRIEF DESCRIPTION OF DRAWINGS
  • FIG. 1 is an elevational view of an embodiment of the large-span cylindrical reticulated shell ;
  • FIG. 2 is an elevational view of the mother vault when the mother vault is being installed;
  • FIG. 3 is an elevational view of the mother vault at the last stage of the assembling process;
  • FIG. 4 is an elevational view of the mother vault after the assembling process is completed.
  • FIG. 5 is a schematic view of the support base and a ball joint.
  • FIG. 6 is a schematic view of a ball joint.
  • FIG. 7 is a schematic view showing a high altitude overhanging construction method.
  • FIG. 8 is a schematic view of a finished structure by a method of installing a large-span cylindrical reticulated shell.
  • DETAILED DESCRIPTION
  • As shown in the drawings, the method for installing the large-span cylindrical reticulated shell comprises the following steps:
  • A) The large-span cylindrical reticulated shell is divided into a plurality of axially arranged reticulated vaults according to the supporting conditions, and each reticulated vault at least comprises four support bases (1) symmetrically arranged on both sides of the reticulated vault and ball joints and pull rods which are respectively installed on the four support bases (1) and mutually connected into a net shape frame; firstly, a reticulated vault called a mother vault is installed, two support bases (1) are respectively arranged on both sides of the mother vault in the embodiment, and a rotatable ball joint (2) is respectively installed on the support base (1) on any side of the mother vault; the rotatable ball joint (2) is rotatably installed on the support base (1). The specific structure is as follows: the rotatable ball joint (2) can be bound on the support base (1) through a chain or a steel wire rope. As shown in FIG. 5, one end of the steel wire rope (7) is connected to the support base (1), and the other end movably holds the ball joint (2). Alternatively, a deeper ball socket is directly arranged at the top end of the support base (1), and the rotatable ball joint (2) is installed in the ball socket; the rotatable ball joint (2) can be installed at the top end of the support base (1) by adopting the two methods above, which can rotate, but cannot fall off from the support base (1).
  • After the completion of installation of the rotatable ball joint (2), other ball joints and pull rods on the mother vault are respectively installed in sequence by taking the rotatable ball joint (2) as the starting point; when the ball joints and the pull rods are installed, the mother vault which should be installed in a vertical high-altitude extending manner is installed in a transverse extending manner, so that the mother vault can be installed on the ground, and a scaffold is not required to be built. Because the mother vault has a certain radian, the installation of the ball joint and the pull rod is blocked by the ground or a construction platform with the progress of installation and the transverse extending process of the mother vault. A lifting device (3) is used for properly lifting the extension tail end of the mother vault at the moment, so that the height of the extension tail end always allows the installation construction to be performed on the ground level, and the rotatable ball joint (2) gradually rotates to the designed angle along the rise of the extension tail end. The lifting device (3) can adopt various devices capable of raising the height such as cranes, hoists, hydraulic jacks, chain blocks and the like. The mother vault is hung in the position where the stress is most reasonable, and the deformation is smallest during the lifting process according to the force principle.
  • B) After the completion of connection between all the ball joints and pull rods of the mother vault, the ball joint in the symmetrical position of the rotatable ball joint (2) is fixed on the support base, i.e., the installation of the entire mother vault is completed; after the completion of installation of the mother vault, the rotatable ball joint (2) can be fixed with the support base (1), by a fastening method, e.g., a welding method.
  • The installed mother vault is the first vault. After the installation of the mother vault, a high-altitude overhanging construction method is adopted to install the other reticulated vaults one by one longitudinally.
  • Within each reticulated vault, after the installation of a top ball joint 51 in a bottom circumferential vault line, the very adjacent bottom ball joint 52 in a top circumferential vault line will be installed. This step is repeated until the whole reticulated vault is finished.
  • As shown in FIG. 6, ball joints and pull rods are manufactured before the installation. Based on the supporting requirement, the whole large-span cylindrical reticulated shell is longitudinally divided into several reticulated vaults. The span of each reticulated vault is equal to the designed span of the reticulated shell. Before installation, every ball joint (5) is connected to one circumferential vertical chord rod, one circumferential chord rod, and two flank rod to form an installing unit containing one ball and four rods. A crane is then used to lift a unit to the proper installation position in the air, then the unit is connected to other installed units. Similarly, other reticulated vaults adjacent to the mother vault are respectively installed in sequence in an axially extending direction of the mother vault until the completion of the installation of the entire large-span cylindrical reticulated shell.
  • As shown in FIG. 7, J, L and N are top circumferential vault lines, which contains top ball joints J1, J1+1, J11, L1, L1+1, L11, N1, N1+1 and N11; K, M are bottom circumferential vault lines, which contains bottom ball joints K1, K11, M1, and M11. The solid lines indicate the part where ball joints and pull rods have been installed on the top circumferential vault lines J and L, and the bottom circumferential vault line K in the mother vault. The dashed lines indicate the uninstalled parts in the top circumferential vault line N and the bottom circumferential vault line M.
  • Using the installation of a ball joint to a bottom circumferential vault line M as an example, each ball joint is connected to the corresponding rods on the ground to form an installation unit with one ball and four rods according to design requirements. For example, the ball joint on the bottom circumferential line M1 is connected to a vertical rod M1K1, a bottom circumferential chord rod M1M11 and two flank rods M1L1 and M1L1+1 to form an unit of one ball and four rods. The unit is then lifted to its corresponding installation position. Four workers at the positions of K1, L1, L11, M11 that already have ball joints then connect the other ends of the four rods to the corresponding installed ball joints on the bottom circumferential lines K1, L1, L11 and M11, and tight the bolts. After confirming the quality of the connection, the connection of the bottom circumferential line ball joint M1 and its corresponding rods is finished. The installation is then moved to the very next ball joint on the bottom circumferential line M11. After installing all the ball joints on the bottom circumferential line M and confirming the quality of the installation, the ball joints on the immediately adjacent top circumferential line N are then installed.
  • Each ball joint on the top circumferential line N is connected to corresponding rods on the ground to form an installation unit with one ball and four rods according to design requirements. For example, the ball joint on the top circumferential line N1 is connected to a top circumferential vertical rod N1L1, a bottom circumferential chord rod N1N11 and two flank rods N1M11 and N1M1 to form a unit of one ball and four rods. The unit is then lifted to its corresponding installation position. Four workers at the positions of L1, M11, M1, and N11 that already have ball joints then connect the other ends of the four rods to the corresponding installed ball joints on the top circumferential lines L1, M11, M1 and N11, and tight the bolts. After confirming the quality of the connection, the connection of the top circumferential line ball joint N1 and its corresponding rods is finished. The installation is then moved to the next ball joint on the top circumferential line N1 1.
  • The same procedure is repeated to finish the whole circumferential line. Then the installation is moved to the next vault until the whole reticulated shell as shown in FIG. 8 is finished.

Claims (3)

1. A method for installing a large-span cylindrical reticulated shell, comprising:
A) the large-span cylindrical reticulated shell is divided into a plurality of axially arranged reticulated vaults according to the supporting conditions, and each reticulated vault at least comprises four support bases symmetrically arranged on both sides of the reticulated vault and ball joints and pull rods which are respectively installed on the four support bases and mutually connected into a net frame shape; firstly, a reticulated vault is installed and called as a mother vault, a rotatable ball joint is respectively installed on the support base on any side of the mother vault, and then other ball joints and pull rods on the mother vault are respectively installed in sequence by taking the rotatable ball joint as the starting point; the mother vault which should be installed in a vertical high-altitude extending manner is installed in a transverse extending manner during the installation of the ball joints and the pull rods, and a lifting device is used for lifting the extension tail end of the mother vault during the transverse extending process of the mother vault, so that the height of the extension tail end always meets the recruitment of ground installation construction;
B) after the completion of connection between all the ball joints and pull rods on the mother vault, the ball joint in the symmetrical position of the rotatable ball joint is fixed on the support base in the corresponding position, i.e., the installation of the entire mother vault is completed; a high-altitude overhanging method is adopted for construction after the completion of installation of the mother vault, and other reticulated vaults adjacent to the mother vault are respectively installed in sequence along the axial extending direction of the mother vault until the completion of installation of the entire large-span cylindrical reticulated shell.
2. A method for installing a large-span cylindrical reticulated shell according to claim 1, wherein, the rotatable ball joint is rotatably installed on the support base during the installation of the mother vault; the rotatable ball joint is fixed with the support base after the completion of installation of the reticulated vaults and before the completion of installation of the entire large-span cylindrical reticulated shell.
3. A method for installing a vault of a large-span cylindrical reticulated shell, comprising:
installing a rotatable ball joint on a support base; and
taking the rotatable ball joint as a starting point, installing a plurality of fixed ball joints and a plurality of pull rods in sequence,
wherein the vault is installed in a transverse extending manner during the installation of the ball joints and the pull rods, and a lifting device lifts an extension tail end of the vault during the transverse extending process of the vault, so that a height of the extension tail end is maintained at a ground level to allow ground installation construction.
US13/475,499 2009-11-20 2012-05-18 Method for installing a large-span cylindrical reticulated shell Abandoned US20120227353A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN2009102239711A CN101718115B (en) 2009-11-20 2009-11-20 Method for mounting wide-span cylindrical reticulated shell
CN200910223971.1 2009-11-20
PCT/CN2010/076514 WO2011060659A1 (en) 2009-11-20 2010-08-31 Erection method of large-span cylindrical surface reticulated shell

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2010/076514 Continuation-In-Part WO2011060659A1 (en) 2009-11-20 2010-08-31 Erection method of large-span cylindrical surface reticulated shell

Publications (1)

Publication Number Publication Date
US20120227353A1 true US20120227353A1 (en) 2012-09-13

Family

ID=42432747

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/475,499 Abandoned US20120227353A1 (en) 2009-11-20 2012-05-18 Method for installing a large-span cylindrical reticulated shell

Country Status (3)

Country Link
US (1) US20120227353A1 (en)
CN (1) CN101718115B (en)
WO (1) WO2011060659A1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243806A (en) * 2013-05-31 2013-08-14 周丰峻 Grid structure based on spherical polyhedron
EP2921600A1 (en) * 2014-03-19 2015-09-23 Airbus Operations GmbH Rotary joint, framework construction kit and method for constructing a framework
CN105951994A (en) * 2016-06-29 2016-09-21 铁道第三勘察设计院集团有限公司 Cylindrical latticed shell sealed canopy and expanded installation method thereof
CN112380602A (en) * 2020-11-13 2021-02-19 上海二十冶建设有限公司 High-precision construction method for spatial curved surface reticulated shell in limited environment
CN113502923A (en) * 2021-06-30 2021-10-15 中国二十二冶集团有限公司 Construction method for assisting second start-free of reticulated shell structure at expansion joint
CN115199038A (en) * 2022-08-15 2022-10-18 中国建筑第八工程局有限公司 Multidirectional multi-curvature large-span curved surface reticulated shell system

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101718115B (en) * 2009-11-20 2011-06-22 山东宏跃网架钢结构有限公司 Method for mounting wide-span cylindrical reticulated shell
CN102003078A (en) * 2010-12-24 2011-04-06 青建集团股份公司 Assembling method of net rack
CN102953554A (en) * 2012-11-14 2013-03-06 中冶天工集团有限公司 Method for installing large-span honeycomb-shaped dual-layer net shell structure
CN103233582B (en) * 2013-04-25 2015-02-11 东北林业大学 Method for achieving prestressed cylindrical cable bar latticed shell structure forming by aid of length-adjustable press rod
CN104878914B (en) * 2013-07-25 2017-03-01 中冶天工集团有限公司 Based on oblique abnormal load full hall scaffold erection method
CN104097914B (en) * 2014-07-24 2016-06-08 中交一航局第五工程有限公司 A kind of pier storage yard is closed booth rack and is crossed over the installation method of belt feeder
CN104295141B (en) * 2014-08-22 2017-02-01 环球汇能(北京)科技有限公司 Modular storage shed and grading building method
CN110185188A (en) * 2019-06-04 2019-08-30 中国十九冶集团有限公司 Large-span shell installation method
CN111042541A (en) * 2019-12-18 2020-04-21 徐州中煤(宁夏)钢结构建设有限公司 Large-span welding spherical cylindrical net shell jacking construction method
CN113431204A (en) * 2021-07-21 2021-09-24 安徽中亚钢结构工程有限公司 Stable rotatory rack support
CN114277938B (en) * 2022-01-04 2023-05-02 浙江东南网架股份有限公司 Assembled space reticulated shell structure based on space four-bar mechanism and preparation method thereof
CN115467416A (en) * 2022-10-08 2022-12-13 中建八局第二建设有限公司 Steel latticed shell structure with curved surface streamer shape and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0359244A (en) * 1989-07-26 1991-03-14 Tomoegumi Iron Works Ltd Prestress introducing device for large-span frame body
US6192634B1 (en) * 1996-09-20 2001-02-27 Temcor Dual network dome structure
US7143550B1 (en) * 2002-09-19 2006-12-05 Conservatek Industries, Inc. Double network reticulated frame structure
CN101169001A (en) * 2007-10-30 2008-04-30 浙江大学 Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191228685A (en) * 1912-12-12 1913-11-13 Heinrich Holland Improvements in the Construction of Trusses for Halls, Air-ship Hangars and like Buildings.
GB191228840A (en) * 1912-12-14 1913-10-30 Heinrich Holland Improvements in or relating to the Construction of Halls, Airship Hangars and other Structures.
US4276733A (en) * 1979-07-25 1981-07-07 Liftech Consultants, Inc. Method of constructing and erecting a dome-shaped structure
CN1393607A (en) * 2001-07-03 2003-01-29 浙江大学 Method for integrally lifting reticulated shell 'mechanism-structure' of column surface of jacking construction method
CN1188575C (en) * 2003-05-23 2005-02-09 浙江大学 Whole forming method for cylindrical netting support with horizontal sliding structure
CN100427690C (en) * 2004-03-18 2008-10-22 上海市机械施工有限公司 Matrix form push installing method for large span deep space steel structure
CN100545365C (en) * 2004-08-11 2009-09-30 中国机械工业建设总公司 Building truss integral lifting method and equipment thereof
CN101435224A (en) * 2008-12-24 2009-05-20 河南中美铝业有限公司 High altitude suspension selecting bulk construction method of barrel shell type bolt ball node network frame
CN101718115B (en) * 2009-11-20 2011-06-22 山东宏跃网架钢结构有限公司 Method for mounting wide-span cylindrical reticulated shell

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0359244A (en) * 1989-07-26 1991-03-14 Tomoegumi Iron Works Ltd Prestress introducing device for large-span frame body
US6192634B1 (en) * 1996-09-20 2001-02-27 Temcor Dual network dome structure
US7143550B1 (en) * 2002-09-19 2006-12-05 Conservatek Industries, Inc. Double network reticulated frame structure
CN101169001A (en) * 2007-10-30 2008-04-30 浙江大学 Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243806A (en) * 2013-05-31 2013-08-14 周丰峻 Grid structure based on spherical polyhedron
EP2921600A1 (en) * 2014-03-19 2015-09-23 Airbus Operations GmbH Rotary joint, framework construction kit and method for constructing a framework
US9562352B2 (en) 2014-03-19 2017-02-07 Airbus Operations Gmbh Rotary joint, framework construction kit and method for constructing a framework
CN105951994A (en) * 2016-06-29 2016-09-21 铁道第三勘察设计院集团有限公司 Cylindrical latticed shell sealed canopy and expanded installation method thereof
CN112380602A (en) * 2020-11-13 2021-02-19 上海二十冶建设有限公司 High-precision construction method for spatial curved surface reticulated shell in limited environment
CN113502923A (en) * 2021-06-30 2021-10-15 中国二十二冶集团有限公司 Construction method for assisting second start-free of reticulated shell structure at expansion joint
CN115199038A (en) * 2022-08-15 2022-10-18 中国建筑第八工程局有限公司 Multidirectional multi-curvature large-span curved surface reticulated shell system

Also Published As

Publication number Publication date
WO2011060659A1 (en) 2011-05-26
CN101718115A (en) 2010-06-02
CN101718115B (en) 2011-06-22

Similar Documents

Publication Publication Date Title
US20120227353A1 (en) Method for installing a large-span cylindrical reticulated shell
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN101538936B (en) Hydraulic slip-and-lift construction method for water tower
US10012005B2 (en) Crane system incorporated into a tower
CN104234200B (en) A kind of suspen-shell structure rope leverage is by ring lifting installation method
CN103866986B (en) Long span variable cross-section bolted spherical node net shell mounting method
CN104040096A (en) Assembly Process Of A Telescopic Tower
CN103938875A (en) Ground single body tensioning lifting construction method of single layer suspendome
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN103556627A (en) Cage hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage
CN103352576A (en) Externally expanding, assembling, converting and lifting method for medium/small span steel structure roof net rack
CN202544468U (en) Drawbar-type electrical steel tubular rod
CN104481194A (en) Reversed assembling method of upright cylindrical equipment
CN109629449B (en) Mounting and positioning support and alignment method for steel-concrete combined section of arch foot of steel box arch bridge
CN109252656B (en) High-rise building climbing template and assembling, pouring and lifting method
CN207647152U (en) Tower lifts constructing device certainly
CN107013044A (en) The modularization installation method of lighting roof and the lowering or hoisting gear for installing lighting roof
CN111058538B (en) Large-span portal reticulated shell tower support construction method
CN110562850B (en) Main tower integral hoisting system and method
CN204401995U (en) Encorbelment support system in a kind of center of installing for dome structure
CN207160721U (en) A kind of super-huge iron tower of power transmission line supervisor
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN109440942B (en) Installation structure and construction process of factory building roof grid
CN205369948U (en) Lifting device for daylighting top is used for installing

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION