US20050241857A1 - Method to transport and operate a small footprint tower to reduce environmental impact - Google Patents
Method to transport and operate a small footprint tower to reduce environmental impact Download PDFInfo
- Publication number
- US20050241857A1 US20050241857A1 US11/117,958 US11795805A US2005241857A1 US 20050241857 A1 US20050241857 A1 US 20050241857A1 US 11795805 A US11795805 A US 11795805A US 2005241857 A1 US2005241857 A1 US 2005241857A1
- Authority
- US
- United States
- Prior art keywords
- transfigurable
- drilling
- container
- drilling equipment
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims abstract description 46
- 230000007613 environmental effect Effects 0.000 title description 3
- 238000005553 drilling Methods 0.000 claims abstract description 130
- 238000004891 communication Methods 0.000 claims abstract description 5
- 230000008878 coupling Effects 0.000 claims description 13
- 238000010168 coupling process Methods 0.000 claims description 13
- 238000005859 coupling reaction Methods 0.000 claims description 13
- 239000007787 solid Substances 0.000 claims description 5
- 230000003028 elevating effect Effects 0.000 claims description 4
- 238000007667 floating Methods 0.000 claims description 3
- 230000005484 gravity Effects 0.000 claims description 2
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 4
- 239000000969 carrier Substances 0.000 description 2
- 239000003345 natural gas Substances 0.000 description 2
- 238000010276 construction Methods 0.000 description 1
- 239000000446 fuel Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B15/00—Supports for the drilling machine, e.g. derricks or masts
Definitions
- the present embodiments relate generally to methods for a transfigurable standardized shipping container for drilling rigs.
- FIG. 1 depicts a flow chart of an embodiment of a method to construct and transport a modular drilling.
- FIG. 2 depicts a side view of an embodiment of a transfigurable container.
- FIG. 3 depicts a side view of an embodiment of an unfolded transfigurable container.
- FIG. 4 depicts a side view of an embodiment of a transfigurable container acting as a support to drilling equipment.
- FIG. 5 examples a partial side view of an erected drilling rig made from a transfigurable container.
- FIG. 6 examples a partial top view of an erected rig made from a transfigurable container.
- FIG. 7 depicts a partial side view of an erected drilling rig shown in FIG. 5 , but in the limited footprint configuration for land of offshore use.
- FIG. 8 depicts a partial top view of an erected drilling rig shown in FIG. 5 but in the limited footprint configuration for land of offshore use.
- FIG. 9 depicts a side view of a straddle carrier usable with the embodied systems.
- FIG. 10 depicts a top view of a straddle carrier and the manner of folding according to the embodied methods.
- FIG. 11 depicts a top view of a containerized straddle carrier and the manner of folding according to the embodied methods.
- FIGS. 12 a through 12 e provide an example of a rig up sequence showing the erection of the drilling derrick or mast.
- FIGS. 13 a through 13 c provide an example of a rig up sequence involving a BOP container.
- the present embodiments save the environment by reducing the number of vessels that are required to ship a drilling rig to different locations around the world.
- the embodied methods reduce the amount of environmental impact on the earth caused by truck, train, or other types of land transportation. The reduction is accomplished by reducing the space required to transport the standard sized devices.
- the embodied methods save the environment by reducing the number of vessels that are required to ship a drilling rig to different locations around the world. This method also reduces the amount of environmental impact on the earth when being transported by truck, train or other land transportation device. The reduction is accomplished by reducing the space required to transport the standard sized devices. Once the rig has reached a drilling site the surface area that is needed to setup and operate the drill rig is less than a comparable drilling rig not using the method. The reduction in area that must be cleared of trees is approximately 1200 m2 versus approximately 2000 m2 on a comparable conventional drilling rig.
- the amount of area that must be cleared on the path to the drilling site is considerably less with a comparable drilling rig. Since the individual weight of the transfigurable containers is less compared with a normal drilling rig the load on the road is less severe. This enables easier transportation across less developed roads and makes the drilling rig easier to be used in less developed countries.
- the embodied methods reduce the number of vessels needed to transport a drilling rig, the methods provide a reduction of fuel usage; a benefit to both cost and the environment. For example, a common sized drilling rig can be transported with seventeen containers. Other drilling rigs of a comparable size often cannot be broken down into container sized packages of less than seventeen. Usually the drilling rigs of a comparable size require containers and shipping parts doubling and tripling the number used with the embodied methods.
- An embodiment of the transfigurable container of drilling equipment allows for two or more two pieces of drilling equipment with associated load bearing devices to be attached together using connectors, preferably pivotable connectors.
- the drilling equipment modules are transformable between an initial shipping container size and shape and a second size and shape.
- the shipping container can be formed into a rectangular shape when transported and transformed into a non-rectangular shape when in operation.
- the ability to transform readily between these two sizes and shapes provides an operational drilling structure that can easily be transported and then erected on different locations and in different shapes depending on the operational demands.
- FIG. 1 depicts a flow chart of the steps in the creation of the transfigurable container.
- the method to construct and transport a modular drilling rig includes transporting drilling equipment in the form of a transfigurable container to a drilling site.
- One or more transfigurable shipping containers are placed at a drilling location (Step 200 ).
- the method can also include a step of forming the standardized transfigurable shipping containers into a larger rectangular shape.
- the transfigurable shipping containers are unfolded at the drilling location (Step 202 ). Two or more of the transfigurable shipping containers, now unfolded at the drilling site, are connected to one another to operable drilling equipment (Step 204 ).
- the method can also include a step of forming a mast or derrick from the standardized transfigurable container.
- the operable drilling equipment is erected into a drilling rig (Step 206 ).
- Erecting the drilling rig can include setting up the drill floor; a mast substructure; a mast; a control cabin, a drawworks; a blow out preventer; a choke and kill manifold; and a blow out preventer (BOP) control unit.
- BOP blow out preventer
- the method can include the step of coupling the drilling equipment to the load bearing supports or load bearing bottom with a moveable coupling selected from the group of, a rotatable coupling between the drilling equipment, a rotatable coupling between load supports, a rotatable coupling between one load bearing support and a load bearing bottom, a device for elevating the drilling equipment above one load bearing support or a load bearing bottom, and a container connector that removably connects the standardized transfigurable shipping containers together.
- a moveable coupling selected from the group of, a rotatable coupling between the drilling equipment, a rotatable coupling between load supports, a rotatable coupling between one load bearing support and a load bearing bottom, a device for elevating the drilling equipment above one load bearing support or a load bearing bottom, and a container connector that removably connects the standardized transfigurable shipping containers together.
- Piping and cabling for communication and power cabling are then installed on the drilling rig (Step 208 ).
- the drilling rig is then in condition to begin operations (Step 210 ).
- FIG. 2 examples attaching the drilling equipment to either a load bearing support or a load bearing bottom with telescoping, rotatable connectors or with pivotable, rotatable connectors.
- a transfigurable container ( 10 ) can be attached to the first load bearing support ( 14 ), the second load bearing support ( 16 ), or the load bearing bottom ( 18 ).
- the drilling equipment can be attached to either load bearing support ( 14 and 16 ) or load bearing bottom ( 18 ) using telescoping, rotatable connectors or pivotable, rotatable connectors, sliding connectors, or non-rotating telescoping connectors.
- the transfigurable container ( 10 ) can be a component of a modular drilling rig.
- the transfigurable container ( 10 ) can include a first and second load support ( 14 and 16 ) and a load bearing bottom ( 18 ).
- the first and second load bearing supports ( 14 and 16 ) can be positioned to form a mast or a derrick.
- the load bearing bottom ( 18 ) is located between the first and second load bearing supports ( 14 and 16 ), thereby forming a space ( 20 ).
- the load bearing bottom ( 18 ) can have a lattice construction or be a load-bearing plate.
- FIG. 3 depicts a side view of an unfolded transfigurable container.
- FIG. 3 shows examples of drilling equipment attached to the loading bearing structure.
- a rotatable coupling ( 68 ) can be used between the drilling equipment.
- a rotatable coupling ( 70 ) can be between the load supports.
- a rotatable coupling (not shown) can be used between one of the load-bearing supports and the load bearing bottom.
- FIG. 4 depicts an embodiment of a device for elevating the drilling equipment ( 74 ) above one of the load bearing supports or load bearing bottom.
- FIG. 4 examples the second load support ( 16 ) and the load bearing bottom ( 18 ) supporting various pieces of solids control equipment ( 50 a , 50 b , 50 c , 50 d , 50 e , and 50 f ).
- a device for elevating the drilling equipment ( 74 ) can be used rather than a cranage device.
- the drilling equipment is preferably located within the space between the first and second load bearing supports.
- the drilling equipment can be attached together and movable from the space to create an operational position outside of the transfigurable container.
- FIG. 5 examples the drilling equipment erected from the transfigurable container in the offshore embodiment.
- the drilling equipment can include a mast ( 24 ), a control cabin ( 30 ), a drawworks module ( 32 ), a choke and kill manifold ( 36 ), active mud tank ( 102 ), and a BOP control unit, not shown.
- drilling equipment examples include a winch ( 40 ), a crown block ( 42 ), a top drive ( 44 ), a rotary table (not shown), piece of solids control equipment ( 50 a ), a second load support ( 16 ), a power source ( 52 ), a hydraulic power unit ( 54 ), a tank ( 56 ), electrical control equipment, a pipe rack, a crane ( 91 ), a traveling block ( 66 ), a container connector ( 76 ) and combinations thereof.
- the drilling equipment can further include a deck or supporting structure ( 5 ) of an offshore platform.
- FIG. 6 examples the drilling equipment erected from the transfigurable container in a land embodiment.
- the drilling equipment can include a casing ( 9 ), such as drill pipe, a drill collar, and bottom hole assembly (BHA).
- the drilling equipment can include a mast ( 24 ), a drill floor ( 26 ), a mast substructure ( 28 ), a drawworks ( 32 ), a blow out preventer (BOP) ( 34 ), a choke and kill manifold ( 36 ), a well head ( 106 ), and a BOP control unit (not shown).
- drilling equipment examples include a winch ( 40 ), a second load support ( 16 ), a crown block ( 42 ), a top drive ( 44 ), a rotary table, electrical control equipment, a pipe rack, pipe handling equipment ( 62 ), a crane ( 91 ), a traveling block ( 66 ) and combinations thereof.
- FIG. 7 examples drilling equipment that can be included inside of a transfigurable container ( 11 ).
- FIG. 7 shows a control cabin ( 30 ), a mud pump ( 48 a ), a mud tank ( 56 ), electrical control equipment, a pipe rack, pipe handling equipment and combinations thereof.
- the shipping containers can be assembled to create a mast or derrick.
- Transfigurable containers for the drilling equipment are transformed to form a portion of an operable drilling rig or standardized shipping containers.
- the transfigurable containers can be compliant with ISO standards.
- Typical sizes for standardized shipping containers include overall lengths ranging from about 8 feet to about 64 feet, overall widths ranging from about 2 feet to about 15 feet, and overall heights ranging from about 2 feet to about 15 feet.
- An example dimension for a transfigurable container is an overall width of 8 feet, an overall height of 9.5 feet, and an overall length of 45 feet, 40 feet, or 20 feet.
- FIG. 8 examples how a containerized straddle carrier can fold inside a transfigurable shipping container.
- the transfigurable shipping containers can include containerized straddle carriers ( 119 ) that are adapted to fold inside a standard shipping container.
- the containerized straddle carrier ( 119 ) with a transfigurable container ( 11 ) can be transported by a truck ( 150 ).
- FIG. 8 depicts the truck ( 150 ), but only two wheels ( 170 and 171 ) and two frames ( 163 and 164 ) associated with containerized straddle carrier ( 119 ) are shown.
- the drilling rig can be configured as an offshore oil or natural gas drilling rig or as a land-based oil or natural gas drilling rig.
- the drilling rigs can be configured for use on a semisubmersible, a tension leg platform, a jack up platform, or another floating vessel.
- the drilling rigs can be configured for use on a fixed offshore platform, such as a gravity based platform, compliant tower or any other offshore platform that is standing on the seafloor.
- the modular transfigurable drilling rig can be made from numerous transfigurable containers for drilling equipment.
- the standardized transfigurable containers can be stacked on skid beams to present a small footprint.
- the transfigurable containers can be stacked on top of each other to present a very small footprint.
- the small footprint is useful for offshore platforms and jungle pads.
- FIG. 9 depicts a top view of an embodiment of a modular drilling rig.
- FIG. 9 depicts an example of the transfigurable container ( 11 ) with other types of equipment on the drilling rig.
- FIG. 9 examples locations of the drawworks ( 32 ), a rotary table ( 46 ), a piece of solids control equipment ( 50 b ), a power source ( 52 ), a tank ( 56 ), pipe handling equipment ( 62 ), with casing ( 9 ), piping ( 80 ), a mud tank ( 102 ) and a second load support ( 16 ).
- the equipment is supported by a drilling rig (floating or fixed) ( 5 ).
- the transfigurable containers can be lifted on board the drilling rig using a crane available on the drilling rigs.
- the transfigurable containers ( 11 ), after being unfolded, are connected to form an operational modular drilling rig.
- the drilling rig can be partially formed from the transfigurable containers and other drilling equipment.
- the container connectors can be a load bearing device or a non-load bearing device.
- Examples of the container connectors used as a load bearing device include pins, hydraulic clamps, mechanical clamps, threaded connectors, male receptacles, female receptacles, and combinations thereof.
- Examples of the container connectors used as a non-load bearing device include threaded connectors, plugs, hydraulic clamps, mechanical clamps, pins, male and female receptacles, and combinations thereof.
- Piping can be used to connect the drilling equipment together.
- Cabling can be used with the drilling rig provides communication and/or electrical power between the drilling equipment.
- a power source is typically connected to the drilling equipment to provide power to the drilling equipment.
- FIG. 10 depicts a top view of a constructed modular rig using the transfigurable containers and the embodied methods.
- the methods entail transporting numerous standardized transfigurable shipping containers with drilling equipment to a drilling location.
- the standardized transfigurable shipping containers with the drilling equipment are unfolded at the drilling location. Two or more of the unfolded transfigurable containers are connected together to form operable drilling equipment and an operable drilling rig.
- FIG. 10 depicts a top view of a constructed modular rig using the transfigurable containers and the embodied methods.
- the methods entail transporting numerous standardized transfigurable shipping containers with drilling equipment to a drilling location.
- the standardized transfigurable shipping containers with the drilling equipment are unfolded at the drilling location. Two or more of the unfolded transfigurable containers are connected together to form operable drilling equipment and an operable drilling rig.
- FIG. 10 depicts a top view of a constructed modular rig using the transfigurable containers and the embodied methods.
- the methods entail
- the drilling equipment includes a control cabin ( 30 ), a drawworks ( 32 ), a BOP control unit ( 38 ), a rotary table ( 46 ), various pumps ( 48 a and 48 b ), solids control equipment ( 50 a , 50 b , and 50 c ), power sources ( 52 a and 52 b ), hydraulic power units ( 54 a , and 54 b ), a tank ( 56 ), electrical control equipment ( 58 ), a pipe rack ( 60 ), a mud pit ( 100 ), an active mud tank ( 102 ), and other such equipment.
- the connected equipment is erected with piping ( 78 , 80 , and 82 ) and cabling ( 84 , 86 , and 88 ) for communication and power cabling for complete operation.
- FIG. 11 depicts a top view of a containerized straddle carrier ( 119 ) and the manner of folding according to the embodied methods.
- the straddle carrier ( 119 ) comprises four wheels (two are identified, 170 and 171 ) that are movably attached to a frame ( 161 , 162 , 163 , and 164 ).
- the lifting section of the frame is fixably connected to a support section of the frame.
- the support section of the frame is of the size of a standard size shipping container, preferably an ISO standardized container.
- the spreader section of the frame is temporarily to the support section.
- the spreader section connects to the load to be lifted.
- the lifting section can move the support section in a vertical direction to pick up loads from and to container carriers.
- the wheels (two are identified, 170 and 171 ) can be folded upwards when the straddle carrier “transforms” to a transportable size.
- the folding direction of the wheels is depicted in FIG. 11 by the arrows (A, B, C, and D).
- FIGS. 12 a though 12 e example an embodiment of a rig up procedure for the embodied drilling rig.
- the procedure begins by moving two transfigurable containers together ( 210 and 212 ).
- FIGS. 12 a though 12 e example a base container ( 210 ) and a mast or derrick container ( 212 ).
- hoisting means ( 214 ) which are part of base container ( 210 ) are rotated out towards the mast or derrick container ( 212 ) and then connected to the mast or derrick container ( 212 ).
- the mast container ( 212 ) is rotated into vertical position and finally locked in place.
- FIGS. 13 a through 13 c provide an example of a rig up sequence involving a BOP container ( 216 ).
- the BOP container ( 216 ) is moved towards base container ( 210 ) and connected to base container ( 210 ). After connection is complete, the BOP container ( 216 ) is rotated into vertical position. The rotation can be done using various hoisting means (not shown). The BOP container ( 216 ) with the drill floor is locked firmly in place with the other containers.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
Abstract
A method to construct and transport a modular drilling rig comprising drilling equipment in the form of a transfigurable container begins by transporting transfigurable shipping containers comprising drilling equipment to a drilling location. The method continues by unfolding the transfigurable shipping containers and the drilling equipment at the drilling location, and connecting two or more of the unfolded transfigurable shipping containers to form operable drilling equipment. The operable drilling equipment is erected into a drilling rig, wherein the operable drilling equipment comprises a drill floor, a mast substructure; a mast; a control cabin, a drawworks; a blow out preventer; a choke and kill manifold; a blow out preventer (BOP) control unit (38), not shown. The method ends by connecting piping and cabling for communication and power cabling to the erected operable drilling equipment and, then, operating the drilling rig.
Description
- The present application claims priority to the co-pending Provisional Patent Application No. 60/567,660, entitled “Transfigurable Shipping Container for Drilling Equipment” and filed on May 3, 2004.
- The present embodiments relate generally to methods for a transfigurable standardized shipping container for drilling rigs.
- A need exists for a system to provide a standardized transfigurable container system because shipping non-standard containers is expensive and difficult.
- A need exists for a modular drilling rig system and method that provides a drilling rig that can be easily assembled or “unfolded” on-site in order to reduce labor need, time, and expense.
- A need exists for a drilling rig that has less impact on the ground cover or foliage when being transported. A need also exists for less impact on the ground when the drilling rig is set up and in use.
- A need also exists for a drilling rig that can be used as a land drilling rig and by assembling the components in a different manner can also be used as an offshore drilling rig.
- The present embodiments meet these needs.
- The detailed description will be better understood in conjunction with the accompanying drawings as follows:
-
FIG. 1 depicts a flow chart of an embodiment of a method to construct and transport a modular drilling. -
FIG. 2 depicts a side view of an embodiment of a transfigurable container. -
FIG. 3 depicts a side view of an embodiment of an unfolded transfigurable container. -
FIG. 4 depicts a side view of an embodiment of a transfigurable container acting as a support to drilling equipment. -
FIG. 5 examples a partial side view of an erected drilling rig made from a transfigurable container. -
FIG. 6 examples a partial top view of an erected rig made from a transfigurable container. -
FIG. 7 depicts a partial side view of an erected drilling rig shown inFIG. 5 , but in the limited footprint configuration for land of offshore use. -
FIG. 8 depicts a partial top view of an erected drilling rig shown inFIG. 5 but in the limited footprint configuration for land of offshore use. -
FIG. 9 depicts a side view of a straddle carrier usable with the embodied systems. -
FIG. 10 depicts a top view of a straddle carrier and the manner of folding according to the embodied methods. -
FIG. 11 depicts a top view of a containerized straddle carrier and the manner of folding according to the embodied methods. -
FIGS. 12 a through 12 e provide an example of a rig up sequence showing the erection of the drilling derrick or mast. -
FIGS. 13 a through 13 c provide an example of a rig up sequence involving a BOP container. - The present embodiments are detailed below with reference to the listed Figures.
- Before explaining the present embodiments in detail, it is to be understood that the embodiments are not limited to the particular embodiments and that it can be practiced or carried out in various ways.
- The present embodiments save the environment by reducing the number of vessels that are required to ship a drilling rig to different locations around the world. The embodied methods reduce the amount of environmental impact on the earth caused by truck, train, or other types of land transportation. The reduction is accomplished by reducing the space required to transport the standard sized devices.
- The embodied methods save the environment by reducing the number of vessels that are required to ship a drilling rig to different locations around the world. This method also reduces the amount of environmental impact on the earth when being transported by truck, train or other land transportation device. The reduction is accomplished by reducing the space required to transport the standard sized devices. Once the rig has reached a drilling site the surface area that is needed to setup and operate the drill rig is less than a comparable drilling rig not using the method. The reduction in area that must be cleared of trees is approximately 1200 m2 versus approximately 2000 m2 on a comparable conventional drilling rig.
- The amount of area that must be cleared on the path to the drilling site is considerably less with a comparable drilling rig. Since the individual weight of the transfigurable containers is less compared with a normal drilling rig the load on the road is less severe. This enables easier transportation across less developed roads and makes the drilling rig easier to be used in less developed countries.
- Since the embodied methods reduce the number of vessels needed to transport a drilling rig, the methods provide a reduction of fuel usage; a benefit to both cost and the environment. For example, a common sized drilling rig can be transported with seventeen containers. Other drilling rigs of a comparable size often cannot be broken down into container sized packages of less than seventeen. Usually the drilling rigs of a comparable size require containers and shipping parts doubling and tripling the number used with the embodied methods.
- An embodiment of the transfigurable container of drilling equipment allows for two or more two pieces of drilling equipment with associated load bearing devices to be attached together using connectors, preferably pivotable connectors. When pivotably connected together, the drilling equipment modules are transformable between an initial shipping container size and shape and a second size and shape. For example, the shipping container can be formed into a rectangular shape when transported and transformed into a non-rectangular shape when in operation. The ability to transform readily between these two sizes and shapes provides an operational drilling structure that can easily be transported and then erected on different locations and in different shapes depending on the operational demands.
- With reference to the figures,
FIG. 1 depicts a flow chart of the steps in the creation of the transfigurable container. The method to construct and transport a modular drilling rig includes transporting drilling equipment in the form of a transfigurable container to a drilling site. One or more transfigurable shipping containers, usually of a standardized container size, are placed at a drilling location (Step 200). The method can also include a step of forming the standardized transfigurable shipping containers into a larger rectangular shape. - The transfigurable shipping containers are unfolded at the drilling location (Step 202). Two or more of the transfigurable shipping containers, now unfolded at the drilling site, are connected to one another to operable drilling equipment (Step 204). The method can also include a step of forming a mast or derrick from the standardized transfigurable container.
- After connecting the containers, the operable drilling equipment is erected into a drilling rig (Step 206). Erecting the drilling rig can include setting up the drill floor; a mast substructure; a mast; a control cabin, a drawworks; a blow out preventer; a choke and kill manifold; and a blow out preventer (BOP) control unit. The method can include the step of coupling the drilling equipment to the load bearing supports or load bearing bottom with a moveable coupling selected from the group of, a rotatable coupling between the drilling equipment, a rotatable coupling between load supports, a rotatable coupling between one load bearing support and a load bearing bottom, a device for elevating the drilling equipment above one load bearing support or a load bearing bottom, and a container connector that removably connects the standardized transfigurable shipping containers together.
- Piping and cabling for communication and power cabling are then installed on the drilling rig (Step 208). The drilling rig is then in condition to begin operations (Step 210).
-
FIG. 2 examples attaching the drilling equipment to either a load bearing support or a load bearing bottom with telescoping, rotatable connectors or with pivotable, rotatable connectors. A transfigurable container (10) can be attached to the first load bearing support (14), the second load bearing support (16), or the load bearing bottom (18). The drilling equipment can be attached to either load bearing support (14 and 16) or load bearing bottom (18) using telescoping, rotatable connectors or pivotable, rotatable connectors, sliding connectors, or non-rotating telescoping connectors. - The transfigurable container (10) can be a component of a modular drilling rig. The transfigurable container (10) can include a first and second load support (14 and 16) and a load bearing bottom (18). The first and second load bearing supports (14 and 16) can be positioned to form a mast or a derrick. The load bearing bottom (18) is located between the first and second load bearing supports (14 and 16), thereby forming a space (20). The load bearing bottom (18) can have a lattice construction or be a load-bearing plate.
-
FIG. 3 depicts a side view of an unfolded transfigurable container.FIG. 3 shows examples of drilling equipment attached to the loading bearing structure. A rotatable coupling (68) can be used between the drilling equipment. A rotatable coupling (70) can be between the load supports. A rotatable coupling (not shown) can be used between one of the load-bearing supports and the load bearing bottom. -
FIG. 4 depicts an embodiment of a device for elevating the drilling equipment (74) above one of the load bearing supports or load bearing bottom. In particular,FIG. 4 examples the second load support (16) and the load bearing bottom (18) supporting various pieces of solids control equipment (50 a, 50 b, 50 c, 50 d, 50 e, and 50 f). In an alternative embodiment, a device for elevating the drilling equipment (74) can be used rather than a cranage device. - The drilling equipment is preferably located within the space between the first and second load bearing supports. The drilling equipment can be attached together and movable from the space to create an operational position outside of the transfigurable container.
-
FIG. 5 examples the drilling equipment erected from the transfigurable container in the offshore embodiment. The drilling equipment can include a mast (24), a control cabin (30), a drawworks module (32), a choke and kill manifold (36), active mud tank (102), and a BOP control unit, not shown. Other types of drilling equipment include a winch (40), a crown block (42), a top drive (44), a rotary table (not shown), piece of solids control equipment (50 a), a second load support (16), a power source (52), a hydraulic power unit (54), a tank (56), electrical control equipment, a pipe rack, a crane (91), a traveling block (66), a container connector (76) and combinations thereof. The drilling equipment can further include a deck or supporting structure (5) of an offshore platform. -
FIG. 6 examples the drilling equipment erected from the transfigurable container in a land embodiment. The drilling equipment can include a casing (9), such as drill pipe, a drill collar, and bottom hole assembly (BHA). The drilling equipment can include a mast (24), a drill floor (26), a mast substructure (28), a drawworks (32), a blow out preventer (BOP) (34), a choke and kill manifold (36), a well head (106), and a BOP control unit (not shown). Other examples of drilling equipment include a winch (40), a second load support (16), a crown block (42), a top drive (44), a rotary table, electrical control equipment, a pipe rack, pipe handling equipment (62), a crane (91), a traveling block (66) and combinations thereof. -
FIG. 7 examples drilling equipment that can be included inside of a transfigurable container (11). For example,FIG. 7 shows a control cabin (30), a mud pump (48 a), a mud tank (56), electrical control equipment, a pipe rack, pipe handling equipment and combinations thereof. The shipping containers can be assembled to create a mast or derrick. - Transfigurable containers for the drilling equipment are transformed to form a portion of an operable drilling rig or standardized shipping containers. The transfigurable containers can be compliant with ISO standards.
- Typical sizes for standardized shipping containers include overall lengths ranging from about 8 feet to about 64 feet, overall widths ranging from about 2 feet to about 15 feet, and overall heights ranging from about 2 feet to about 15 feet. An example dimension for a transfigurable container is an overall width of 8 feet, an overall height of 9.5 feet, and an overall length of 45 feet, 40 feet, or 20 feet.
-
FIG. 8 examples how a containerized straddle carrier can fold inside a transfigurable shipping container. The transfigurable shipping containers can include containerized straddle carriers (119) that are adapted to fold inside a standard shipping container. The containerized straddle carrier (119) with a transfigurable container (11) can be transported by a truck (150).FIG. 8 depicts the truck (150), but only two wheels (170 and 171) and two frames (163 and 164) associated with containerized straddle carrier (119) are shown. - Another embodiment is a modular transfigurable drilling rig. The drilling rig can be configured as an offshore oil or natural gas drilling rig or as a land-based oil or natural gas drilling rig. The drilling rigs can be configured for use on a semisubmersible, a tension leg platform, a jack up platform, or another floating vessel. The drilling rigs can be configured for use on a fixed offshore platform, such as a gravity based platform, compliant tower or any other offshore platform that is standing on the seafloor. The modular transfigurable drilling rig can be made from numerous transfigurable containers for drilling equipment.
- The standardized transfigurable containers can be stacked on skid beams to present a small footprint. Alternatively, the transfigurable containers can be stacked on top of each other to present a very small footprint. The small footprint is useful for offshore platforms and jungle pads.
-
FIG. 9 depicts a top view of an embodiment of a modular drilling rig.FIG. 9 depicts an example of the transfigurable container (11) with other types of equipment on the drilling rig.FIG. 9 examples locations of the drawworks (32), a rotary table (46), a piece of solids control equipment (50 b), a power source (52), a tank (56), pipe handling equipment (62), with casing (9), piping (80), a mud tank (102) and a second load support (16). The equipment is supported by a drilling rig (floating or fixed) (5). The transfigurable containers can be lifted on board the drilling rig using a crane available on the drilling rigs. - The transfigurable containers (11), after being unfolded, are connected to form an operational modular drilling rig. In another embodiment, the drilling rig can be partially formed from the transfigurable containers and other drilling equipment.
- The container connectors can be a load bearing device or a non-load bearing device. Examples of the container connectors used as a load bearing device include pins, hydraulic clamps, mechanical clamps, threaded connectors, male receptacles, female receptacles, and combinations thereof. Examples of the container connectors used as a non-load bearing device include threaded connectors, plugs, hydraulic clamps, mechanical clamps, pins, male and female receptacles, and combinations thereof.
- Piping can be used to connect the drilling equipment together. Cabling can be used with the drilling rig provides communication and/or electrical power between the drilling equipment. A power source is typically connected to the drilling equipment to provide power to the drilling equipment.
-
FIG. 10 depicts a top view of a constructed modular rig using the transfigurable containers and the embodied methods. The methods entail transporting numerous standardized transfigurable shipping containers with drilling equipment to a drilling location. The standardized transfigurable shipping containers with the drilling equipment are unfolded at the drilling location. Two or more of the unfolded transfigurable containers are connected together to form operable drilling equipment and an operable drilling rig. Typically, as shown inFIG. 9 , the drilling equipment includes a control cabin (30), a drawworks (32), a BOP control unit (38), a rotary table (46), various pumps (48 a and 48 b), solids control equipment (50 a, 50 b, and 50 c), power sources (52 a and 52 b), hydraulic power units (54 a, and 54 b), a tank (56), electrical control equipment (58), a pipe rack (60), a mud pit (100), an active mud tank (102), and other such equipment. The connected equipment is erected with piping (78, 80, and 82) and cabling (84, 86, and 88) for communication and power cabling for complete operation. -
FIG. 11 depicts a top view of a containerized straddle carrier (119) and the manner of folding according to the embodied methods. The straddle carrier (119) comprises four wheels (two are identified, 170 and 171) that are movably attached to a frame (161, 162, 163, and 164). The lifting section of the frame is fixably connected to a support section of the frame. The support section of the frame is of the size of a standard size shipping container, preferably an ISO standardized container. The spreader section of the frame is temporarily to the support section. The spreader section connects to the load to be lifted. The lifting section can move the support section in a vertical direction to pick up loads from and to container carriers. The wheels (two are identified, 170 and 171) can be folded upwards when the straddle carrier “transforms” to a transportable size. The folding direction of the wheels (two are identified, 170 and 171) is depicted inFIG. 11 by the arrows (A, B, C, and D). -
FIGS. 12 a though 12 e example an embodiment of a rig up procedure for the embodied drilling rig. The procedure begins by moving two transfigurable containers together (210 and 212).FIGS. 12 a though 12 e example a base container (210) and a mast or derrick container (212). After the containers are connected, hoisting means (214), which are part of base container (210), are rotated out towards the mast or derrick container (212) and then connected to the mast or derrick container (212). The mast container (212) is rotated into vertical position and finally locked in place. -
FIGS. 13 a through 13 c provide an example of a rig up sequence involving a BOP container (216). The BOP container (216) is moved towards base container (210) and connected to base container (210). After connection is complete, the BOP container (216) is rotated into vertical position. The rotation can be done using various hoisting means (not shown). The BOP container (216) with the drill floor is locked firmly in place with the other containers. - The embodiments have been described in detail with particular reference to certain preferred embodiments thereof, but it will be understood that variations and modifications can be effected within the scope of the embodiments, especially to those skilled in the art.
Claims (20)
1. A method to construct and transport a modular drilling rig, wherein the method comprises the steps of:
a. transporting a transfigurable container comprising drilling equipment to a drilling location;
b. unfolding the transfigurable container to the drilling location, thereby forming unfolded transfigurable container;
c. connecting at least two unfolded transfigurable containers and the drilling equipment to form the module drilling rig;
d. erecting the modular drilling rig at the drilling location;
e. connecting piping and cabling for communication and power cabling to drilling equipment on the modular drilling rig; and
f. operating the modular drilling rig.
2. The method of claim 1 , further comprising the step of stacking two or more transfigurable containers on skid beams to present a small footprint for the modular drilling rig.
3. The method of claim 1 , further comprising the step of stacking two or more transfigurable containers on top of one another to present a small footprint for the modular drilling rig.
4. The method of claim 1 , wherein the step of erecting the modular drilling rig is performed by using a crane.
5. The method of claim 4 , wherein the crane is remotely controlled.
6. The method of claim 4 , wherein the crane folds inside a second transfigurable container.
7. The method of claim 1 , wherein the transfigurable container is compliant with ISO standards.
8. The method of claim 1 , further comprising the step of adapting a containerized straddle carrier to fold inside the transfigurable container.
9. The method of claim 1 , further comprising the step of attaching the drilling equipment to either a load bearing support or a load bearing bottom with a telescoping, rotatable connector.
10. The method of claim 1 , further comprising the step of attaching the drilling equipment to either a load bearing support or a load bearing bottom with a pivotable, rotatable connector.
11. The method of claim 1 , further comprising the step of coupling the drilling equipment to a load bearing support or a load bearing bottom with a moveable coupling, wherein the moveable coupling is selected from the group consisting of:
a. a rotatable coupling between the drilling equipment;
b. a rotatable coupling between two or more load supports;
c. a device for elevating the drilling equipment above the load bearing support or the load bearing bottom; and
d. a container connector that removably connects at least two transfigurable shipping containers together.
12. The method of claim 1 , further comprising the step of forming a mast from the transfigurable shipping container.
13. The method of claim 1 , further comprising the step of forming a derrick from the transfigurable container.
14. The method of claim 1 , wherein the drilling equipment comprises: a winch, a crown block, a top drive, a rotary table, a pump, solids control equipment, a power source, a hydraulic power unit, a tank, electrical control equipment, a pipe rack, pipe handling equipment, a crane, a traveling block, a blow out preventer and combinations thereof.
15. The method of claim 1 , wherein the transfigurable container is lifted on an offshore platform using a crane that is available on the offshore platform.
16. The method of claim 15 , wherein the offshore platform is a selected from the group consisting of a semi-submersible, a tension leg platform, a jack up platform, a floating vessel and combinations thereof.
17. The method of claim 15 , wherein the offshore platform is a selected from the group consisting of a gravity based platform, a compliant tower, and a platform connected to the seafloor.
18. The method of claim 1 , wherein the modular drilling rig is adapted to be deployed on land or offshore.
19. The method of claim 1 , wherein the transfigurable shipping container further comprises a blow out preventer contains and a portion of a drill floor.
20. The method of claim 1 , further comprising the step of using a crane to lift the drilling equipment into an operational position.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/117,958 US20050241857A1 (en) | 2004-05-03 | 2005-04-29 | Method to transport and operate a small footprint tower to reduce environmental impact |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US56766004P | 2004-05-03 | 2004-05-03 | |
US11/117,958 US20050241857A1 (en) | 2004-05-03 | 2005-04-29 | Method to transport and operate a small footprint tower to reduce environmental impact |
Publications (1)
Publication Number | Publication Date |
---|---|
US20050241857A1 true US20050241857A1 (en) | 2005-11-03 |
Family
ID=35185922
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/117,958 Abandoned US20050241857A1 (en) | 2004-05-03 | 2005-04-29 | Method to transport and operate a small footprint tower to reduce environmental impact |
Country Status (1)
Country | Link |
---|---|
US (1) | US20050241857A1 (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050279492A1 (en) * | 2004-06-07 | 2005-12-22 | Folk Robert A | Wellbore top drive systems |
US20060231273A1 (en) * | 2005-03-24 | 2006-10-19 | Armstrong James E | Apparatus for protecting wellheads and method of installing the same |
WO2009023042A1 (en) * | 2007-04-19 | 2009-02-19 | Wise Well Intervention Services, Inc. | Well servicing modular combination unit |
CN101985873A (en) * | 2010-05-12 | 2011-03-16 | 殷江虹 | Mechanical operation device for lifting and lowering oil tube of oil well |
US20120043136A1 (en) * | 2008-08-15 | 2012-02-23 | Dirk Alfermann | Drilling rig for deep well drilling |
CN103132923A (en) * | 2013-03-06 | 2013-06-05 | 张家口维克特机械有限公司 | Integrated high-wind-pressure down-the-hole drill |
CN103615198A (en) * | 2013-11-21 | 2014-03-05 | 中煤第一建设有限公司 | Construction method for using parallel double-mast half-turning method to hoist large box type derrick |
US20150135607A1 (en) * | 2012-05-09 | 2015-05-21 | Drillmec S.P.A. | Well drilling apparatus and assembling and disassembling method |
CN104818950A (en) * | 2015-05-08 | 2015-08-05 | 中国石油集团西部钻探工程有限公司 | Swabbing truck derrick workbench |
US9267341B2 (en) | 2012-05-14 | 2016-02-23 | Nabors Drilling International Limited | Drilling rig employing pivoting drilling tower |
CN105781445A (en) * | 2016-03-29 | 2016-07-20 | 宝鸡石油机械有限责任公司 | Continuously moving oil rig as well as pull-out and run-in methods thereof |
US9410382B2 (en) | 2012-05-14 | 2016-08-09 | Nabors Drilling International Limited | Drilling rig carriage movable along racks and including pinions driven by electric motors |
CN105888582A (en) * | 2016-04-26 | 2016-08-24 | 中国石油集团渤海石油装备制造有限公司 | Double-control tubing device for petroleum workover operation and using method thereof |
CN108319230A (en) * | 2017-12-19 | 2018-07-24 | 昆山吉海实业公司 | A kind of intelligent Fully-automatic lock system of container train |
US10295263B2 (en) * | 2014-12-05 | 2019-05-21 | Schlumberger Technology Corporation | System and method using buffer tank for heat exchange |
CN112313391A (en) * | 2017-10-11 | 2021-02-02 | 巴西石油公司 | Apparatus, system and method for transporting and installing blowout preventer stack for land-based drilling rig |
Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3033527A (en) * | 1954-10-05 | 1962-05-08 | Wilson John Hart | Portable rig, mast and substructure |
US3145786A (en) * | 1960-07-11 | 1964-08-25 | Leyman Corp | Portable drill rig |
US3533223A (en) * | 1968-04-12 | 1970-10-13 | Walter W Gunn | Sand trap trimmer with floatable blade-carrying arm |
US3739853A (en) * | 1971-06-04 | 1973-06-19 | B Wales | Rig substructure and method of moving the same |
US4269395A (en) * | 1978-07-23 | 1981-05-26 | Newman James L | Portable hydraulic rig for performing workover, drilling and other operations on a well |
US4290495A (en) * | 1979-06-18 | 1981-09-22 | Hydra-Rig, Inc. | Portable workover rig with extendable mast substructure, platform mounted drawworks and adjustable wellhead anchor |
US4371041A (en) * | 1978-09-15 | 1983-02-01 | Drill Systems, Inc. | Multi-purpose mobile drill rig |
US4582205A (en) * | 1983-06-29 | 1986-04-15 | Fmc Corporation | Modularized pedestal-mount crane and method of disassembly |
US4666340A (en) * | 1986-03-28 | 1987-05-19 | Shell Offshore Inc. | Offshore platform with removable modules |
US4899832A (en) * | 1985-08-19 | 1990-02-13 | Bierscheid Jr Robert C | Modular well drilling apparatus and methods |
US20020166698A1 (en) * | 2001-05-01 | 2002-11-14 | Beato Christopher Louis | Multipurpose unit with multipurpose tower and method for tendering with a semisubmersible |
US6533045B1 (en) * | 2001-05-02 | 2003-03-18 | Jack M. Cooper | Portable drilling rig |
US6554075B2 (en) * | 2000-12-15 | 2003-04-29 | Halliburton Energy Services, Inc. | CT drilling rig |
US6848515B2 (en) * | 2003-04-24 | 2005-02-01 | Helmerich & Payne, Inc. | Modular drilling rig substructure |
-
2005
- 2005-04-29 US US11/117,958 patent/US20050241857A1/en not_active Abandoned
Patent Citations (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3033527A (en) * | 1954-10-05 | 1962-05-08 | Wilson John Hart | Portable rig, mast and substructure |
US3145786A (en) * | 1960-07-11 | 1964-08-25 | Leyman Corp | Portable drill rig |
US3533223A (en) * | 1968-04-12 | 1970-10-13 | Walter W Gunn | Sand trap trimmer with floatable blade-carrying arm |
US3739853A (en) * | 1971-06-04 | 1973-06-19 | B Wales | Rig substructure and method of moving the same |
US4269395A (en) * | 1978-07-23 | 1981-05-26 | Newman James L | Portable hydraulic rig for performing workover, drilling and other operations on a well |
US4371041A (en) * | 1978-09-15 | 1983-02-01 | Drill Systems, Inc. | Multi-purpose mobile drill rig |
US4290495A (en) * | 1979-06-18 | 1981-09-22 | Hydra-Rig, Inc. | Portable workover rig with extendable mast substructure, platform mounted drawworks and adjustable wellhead anchor |
US4582205A (en) * | 1983-06-29 | 1986-04-15 | Fmc Corporation | Modularized pedestal-mount crane and method of disassembly |
US4899832A (en) * | 1985-08-19 | 1990-02-13 | Bierscheid Jr Robert C | Modular well drilling apparatus and methods |
US4666340A (en) * | 1986-03-28 | 1987-05-19 | Shell Offshore Inc. | Offshore platform with removable modules |
US6554075B2 (en) * | 2000-12-15 | 2003-04-29 | Halliburton Energy Services, Inc. | CT drilling rig |
US20020166698A1 (en) * | 2001-05-01 | 2002-11-14 | Beato Christopher Louis | Multipurpose unit with multipurpose tower and method for tendering with a semisubmersible |
US6533045B1 (en) * | 2001-05-02 | 2003-03-18 | Jack M. Cooper | Portable drilling rig |
US6848515B2 (en) * | 2003-04-24 | 2005-02-01 | Helmerich & Payne, Inc. | Modular drilling rig substructure |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7222683B2 (en) * | 2004-06-07 | 2007-05-29 | Varco I/P, Inc. | Wellbore top drive systems |
US20050279492A1 (en) * | 2004-06-07 | 2005-12-22 | Folk Robert A | Wellbore top drive systems |
US20060231273A1 (en) * | 2005-03-24 | 2006-10-19 | Armstrong James E | Apparatus for protecting wellheads and method of installing the same |
US7419006B2 (en) * | 2005-03-24 | 2008-09-02 | Wzi, Inc. | Apparatus for protecting wellheads and method of installing the same |
WO2009023042A1 (en) * | 2007-04-19 | 2009-02-19 | Wise Well Intervention Services, Inc. | Well servicing modular combination unit |
US20120043136A1 (en) * | 2008-08-15 | 2012-02-23 | Dirk Alfermann | Drilling rig for deep well drilling |
CN101985873A (en) * | 2010-05-12 | 2011-03-16 | 殷江虹 | Mechanical operation device for lifting and lowering oil tube of oil well |
US20150135607A1 (en) * | 2012-05-09 | 2015-05-21 | Drillmec S.P.A. | Well drilling apparatus and assembling and disassembling method |
US9410382B2 (en) | 2012-05-14 | 2016-08-09 | Nabors Drilling International Limited | Drilling rig carriage movable along racks and including pinions driven by electric motors |
US9267341B2 (en) | 2012-05-14 | 2016-02-23 | Nabors Drilling International Limited | Drilling rig employing pivoting drilling tower |
US9273524B2 (en) | 2012-05-14 | 2016-03-01 | Nabors Drilling International Limited | Drilling rig carriage movable along racks and including pinions driven by electric motors |
US9309728B2 (en) | 2012-05-14 | 2016-04-12 | Nabors Drilling International Limited | Drilling rig employing tubular handling device |
US9790751B2 (en) | 2012-05-14 | 2017-10-17 | Nabors Drilling International Limited | Drilling rig employing top drive |
CN103132923A (en) * | 2013-03-06 | 2013-06-05 | 张家口维克特机械有限公司 | Integrated high-wind-pressure down-the-hole drill |
CN103615198A (en) * | 2013-11-21 | 2014-03-05 | 中煤第一建设有限公司 | Construction method for using parallel double-mast half-turning method to hoist large box type derrick |
US10295263B2 (en) * | 2014-12-05 | 2019-05-21 | Schlumberger Technology Corporation | System and method using buffer tank for heat exchange |
CN104818950A (en) * | 2015-05-08 | 2015-08-05 | 中国石油集团西部钻探工程有限公司 | Swabbing truck derrick workbench |
CN105781445A (en) * | 2016-03-29 | 2016-07-20 | 宝鸡石油机械有限责任公司 | Continuously moving oil rig as well as pull-out and run-in methods thereof |
CN105888582A (en) * | 2016-04-26 | 2016-08-24 | 中国石油集团渤海石油装备制造有限公司 | Double-control tubing device for petroleum workover operation and using method thereof |
CN112313391A (en) * | 2017-10-11 | 2021-02-02 | 巴西石油公司 | Apparatus, system and method for transporting and installing blowout preventer stack for land-based drilling rig |
CN108319230A (en) * | 2017-12-19 | 2018-07-24 | 昆山吉海实业公司 | A kind of intelligent Fully-automatic lock system of container train |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7255180B2 (en) | Modular drill system requiring limited field assembly and limited equipment support | |
US20050241857A1 (en) | Method to transport and operate a small footprint tower to reduce environmental impact | |
US10465377B2 (en) | Drilling rig with self-elevating drill floor | |
US9938777B2 (en) | Land drilling rig and methods of assembly | |
US8556003B2 (en) | Split sub-basement drill rig | |
CN104160106A (en) | Modular drilling rig system | |
US6675899B2 (en) | Self-erecting rig | |
EP2364909B1 (en) | Deep Water Offshore Apparatus Assembly Method | |
AU2002231022A1 (en) | Self-erecting rig | |
US10851595B2 (en) | Shipping arrangement and assembly procedure for drilling rig structures | |
EP3688232B1 (en) | Plug and abandonment of one or more offshore platform wellbores of an offshore platform using a marine jack-up type vessel | |
KR20110044497A (en) | Transporting process for derrick | |
GB2495717A (en) | Gangway for an offshore structure | |
WO2016102910A1 (en) | Modular tubing rack assembly | |
Hayes | The Minimum Space Platform Rig (MSPR)-Its Adaptability to Onshore Drilling Applications | |
KR20110045299A (en) | Operating process for ship or offshore structure with derrick in low COG condition | |
KR20130115449A (en) | Construction method for jack up type structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: DRILLMAR, INC., TEXAS Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:BEATO, MR. CHRISTOPHER LOUIS;REEL/FRAME:017149/0556 Effective date: 20050622 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |