TWI665365B - Checkerboard jacking construction method - Google Patents

Checkerboard jacking construction method Download PDF

Info

Publication number
TWI665365B
TWI665365B TW107142230A TW107142230A TWI665365B TW I665365 B TWI665365 B TW I665365B TW 107142230 A TW107142230 A TW 107142230A TW 107142230 A TW107142230 A TW 107142230A TW I665365 B TWI665365 B TW I665365B
Authority
TW
Taiwan
Prior art keywords
wall
reinforcement
trench
construction method
casing
Prior art date
Application number
TW107142230A
Other languages
Chinese (zh)
Other versions
TW202020279A (en
Inventor
沈茂松
Original Assignee
國立高雄科技大學
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 國立高雄科技大學 filed Critical 國立高雄科技大學
Priority to TW107142230A priority Critical patent/TWI665365B/en
Application granted granted Critical
Publication of TWI665365B publication Critical patent/TWI665365B/en
Publication of TW202020279A publication Critical patent/TW202020279A/en

Links

Abstract

本發明係一種棋盤腳頂昇施工法,其包含千斤頂配置步驟、支撐配置步驟、挖掘配筋步驟、澆注步驟、移除步驟及托基步驟,於待施工牆的前、後側挖掘配置溝以配置千斤頂,並跨設通過牆下方的鋼軌與套管鋼筋組件,並於牆下方設置穿牆鋼筋,且穿牆鋼筋與套管鋼筋組件之間以支架鋼筋連接並點焊固定,再於牆下方開挖條形基礎的土溝而進行條形基礎的施作,並於條形基礎下方設置傾斜的高壓噴射成型樁,於採用無地樑之獨立基腳柱間或磚柱間,可進行該棋盤腳頂昇施工法而施作條形基礎,達到降低沉陷量的目的。The invention relates to a checkerboard foot lifting construction method, which comprises a jack disposition step, a support disposition step, an excavation and reinforcement step, a pouring step, a removal step, and a supporting step. A configuration trench is excavated at the front and rear sides of the wall to be constructed. Configure a jack and cross the steel rail and casing reinforcement components below the wall, and pass through the steel reinforcement below the wall, and the steel reinforcement through the wall and the casing reinforcement components are connected by bracket reinforcement and fixed by spot welding, and then below the wall Excavate the soil trench of the strip foundation for the construction of the strip foundation, and set an inclined high-pressure spray-formed pile below the strip foundation. The checkerboard can be used between independent footing columns or brick columns without ground beams. The foot-lift construction method is used to form a strip foundation to reduce the amount of subsidence.

Description

棋盤腳頂昇施工法Checkerboard jacking construction method

本發明係一種棋盤腳頂昇施工法,尤指於無地樑之獨立基腳柱間與磚柱間施作條形基礎時,可頂住牆的棋盤腳頂昇施工法。 The invention relates to a checkerboard foot lifting construction method, particularly a checkerboard foot lifting construction method capable of supporting a wall when a strip foundation is applied between independent footing columns without bricks and between brick columns.

舊建築物的周邊進行新建築物的施工時,新建築物的施工會造成舊建築物的不一定程度的沉陷,若舊建築物採用獨立基腳柱或磚柱,與採用筏式基礎相比較,採用獨立基腳柱或磚柱的抗沉陷能力較差,容易產生較大沉陷量,而造成結構體損壞,因此如何降低採用獨立基腳柱或磚柱之建築物的沉陷量,為業界亟欲解決的問題。 When the construction of a new building is carried out around the old building, the construction of the new building will cause the subsidence of the old building to a certain extent. If the old building uses independent footings or brick columns, compared with the raft foundation The use of independent footing columns or brick columns has a poor anti-sinking ability, and it is easy to generate a large amount of subsidence, which will cause damage to the structure. Therefore, how to reduce the settlement of buildings using independent footing columns or brick columns is an industry urge solved problem.

目前採用頂昇施工法改善建築物在傾斜扶正過程中沉陷量較大的問題,現有頂昇施工法係利用人工於已傾斜建築物的地樑下方挖掘一配置溝,將墊木放置於該配置溝中,再將千斤頂放置於墊木上,讓千斤頂的上部接觸地樑的底部,由於需要將千斤頂直接放置於地樑下方,且需要於已傾斜建築物的地樑下方進行挖掘,會影響已傾斜建築物的穩定與施工人員的安全,若已傾斜建築物無地樑,則要補做地樑,且補做地樑仍需其他支撐與牆下方局部千斤頂的頂昇,對已傾斜建築物與施工人員有影響。 At present, the jacking construction method is used to improve the problem of the large subsidence of the building during the tilting and righting process. The existing jacking construction method uses manual excavation of a configuration trench under the ground beam of the inclined building, and places the stow in the configuration. In the trench, the jack is placed on the backing block, so that the upper part of the jack contacts the bottom of the ground beam. Since the jack needs to be placed directly below the ground beam, and it needs to be excavated under the ground beam of the inclined building, it will affect the The stability of the inclined building and the safety of the construction personnel. If the inclined building has no ground beam, the ground beam must be supplemented, and the additional ground beam still needs other support and the lifting of the partial jack below the wall. Construction personnel have influence.

另外,千斤頂的上部接觸地樑的底部,以及千斤頂的下部透過墊木與地面接觸,若接觸面不平整或地面太軟而下陷歪斜,很容易影響上方的建築物。 In addition, the upper part of the jack is in contact with the bottom of the ground beam, and the lower part of the jack is in contact with the ground through the padding. If the contact surface is uneven or the ground is too soft to sag and skew, it will easily affect the buildings above.

此外,現有頂昇施工法進一步以水管尺控制地樑的抬起高程,無法透過水管尺瞭解牆壁的前後傾斜狀態。 In addition, the existing jacking construction method further uses a water pipe ruler to control the elevation of the ground beam, and it is impossible to understand the front-to-rear tilt state of the wall through the water pipe ruler.

本發明之主要目的在於提供一種棋盤腳頂昇施工法,藉此改善採用獨立基腳柱或磚柱之建築物在傾斜扶正過程中的沉陷量較大的問題,以及改善目前頂昇施工法於地樑下方挖掘並設置千斤頂,影響建築物的穩定並增加施工人員危險性的問題,以及無地樑的建築物需要補做地樑而影響建築物與施工人員的問題。 The main purpose of the present invention is to provide a checkerboard foot lifting construction method, thereby improving the problem of a large subsidence of a building using an independent footing column or a brick column during the tilt and righting process, and improving the current lifting construction method in Excavation and installation of jacks under the ground beams affect the stability of the building and increase the danger of the construction personnel, and the problems of buildings without ground beams that need to be supplemented by ground beams and affect the buildings and construction personnel.

為達成前揭目的,本發明棋盤腳頂昇施工法包含:一千斤頂配置步驟,於原建築物之待施工的牆兩側的土壤挖出以得知牆深度,再於牆的前側方與後側方的地面上分別挖掘一配置溝,於所述配置溝鋪設鋼筋混凝土,放置墊木,再放置千斤頂於墊木上;一支撐配置步驟,於千斤頂上設置承壓鋼鈑,再於相對的承壓鋼鈑上跨設並點焊固定鋼軌與套管鋼筋組件,且鋼軌與套管鋼筋組件通過牆下方,鋼軌與套管鋼筋組件之間焊接加勁連結鈑,再於牆下方設置間隔排列的穿牆鋼筋,且穿牆鋼筋與套管鋼筋組件之間以支架鋼筋連接並點焊固定;一挖掘配筋步驟,於牆下方開挖條形基礎的土溝,先挖掘穿牆鋼筋下方,再挖掘套管鋼筋組件的滾軸下方,配置監測系統監測牆的沉陷、上浮、前傾與後傾,並以千斤頂調整牆,待調整完後,於土溝內配筋;一澆注步驟,將混凝土澆注於土溝內,讓混凝土掩蓋套管鋼筋組件的滾軸、位於土溝的鋼軌、支架鋼筋與穿牆鋼筋,且混凝土澆注到牆底部上方10公分處,以形成條形基礎;一移除步驟,切除條形基礎兩側外伸的套管鋼筋組件與鋼軌的部分,以及 移除配置溝內的千斤頂、承壓鋼鈑與墊木,再將混凝土澆注於配置溝至牆底部上方10公分處;以及一托基步驟,於條形基礎下方設置高壓噴射成型樁,且高壓噴射成型樁與一鉛直基準面的夾角為5°,並由地面下21公尺至牆下0.4公尺。 In order to achieve the purpose of the previous disclosure, the chessboard foot lifting construction method of the present invention includes: a jack configuration step, digging the soil on both sides of the wall of the original building to be constructed to know the depth of the wall, and then the front side of the wall and the rear A configuration trench is excavated on the ground on the side, and reinforced concrete is laid on the configuration trench, a cushion is placed, and then a jack is placed on the cushion. A supporting configuration step is to place a pressure-bearing steel sheet on the jack, and then to the opposite The rail and casing reinforcement components are straddled and spot-welded on the pressure steel sheet, and the rail and casing reinforcement components pass through the wall, and the rails and casing reinforcement components are welded to strengthen the connection sheet. Through-wall reinforcement, and the through-wall reinforcement and casing reinforcement components are connected by bracket reinforcement and fixed by spot welding. In the excavation and reinforcement step, a trench with a strip foundation is excavated below the wall. Below the roller of the excavated casing steel component, a monitoring system is configured to monitor the wall subsidence, uplift, forward and backward tilt, and adjust the wall with a jack. After the adjustment is completed, reinforcement is provided in the trench; a pouring step, The concrete is poured into the trench, so that the concrete covers the rollers of the casing reinforcing steel components, the rails located in the trench, the bracket reinforcement and the through-rebar, and the concrete is poured 10 cm above the bottom of the wall to form a strip foundation; Except for the steps, cut out the parts of the casing steel bars and rails protruding from both sides of the strip foundation, and Remove the jacks, pressure-bearing steel plates and stows in the configuration trench, and then pour concrete into the configuration trench to 10 cm above the bottom of the wall; and a step of supporting the foundation, setting a high-pressure spray-formed pile under the strip foundation, and high pressure The included angle between the spray-formed pile and a vertical reference plane is 5 °, and it ranges from 21 meters below the ground to 0.4 meters below the wall.

上述中,建築物中採用無地樑之獨立基腳柱間或磚柱間,可進行該棋盤腳頂昇施工法而施作條形基礎,讓建築物可較耐差異沉陷且較不易龜裂,達到降低沉陷量的目的,其中,穿牆鋼筋的承載力透過支架鋼筋傳至套管鋼筋組件而構成牆下方的棋盤腳頂昇系統,可支撐牆並便於條形基礎的土溝的挖掘與條形基礎的施作,並採取千斤頂與監測系統的配合,可調整牆的位置,以及該托基步驟中施作傾斜的高壓噴射成型樁可承托條形基礎,並防止建築物的沉陷,達到降低沉陷量的目的。 In the above, the building uses independent floor or brick columns without ground beams. The checkerboard foot lifting construction method can be used to form a strip foundation to make the building more resistant to differential subsidence and less likely to crack. To achieve the purpose of reducing the amount of subsidence, the bearing capacity of the through-bar reinforcement is transmitted to the casing reinforcement component through the bracket reinforcement to form a checkerboard jacking system under the wall, which can support the wall and facilitate the excavation and strip of soil trenches with strip foundations. The construction of the foundation is adopted, and the cooperation of the jack and the monitoring system can be used to adjust the position of the wall, and the inclined high-pressure spray-formed pile applied in the supporting step can support the strip foundation and prevent the building from subsiding. The purpose of reducing subsidence.

該棋盤腳頂昇施工法於該千斤頂配置步驟中,於牆的前側方與後側方挖掘配置溝再放置千斤頂,避免於牆的下方進行挖掘,讓千斤頂的配置可避開牆的下方,有效降低對建築物的影響並提高安全性,於該支撐配置步驟與該挖掘配筋步驟中,透過鋼軌、套管鋼筋組件、穿牆鋼筋與支架鋼筋可提高建築物的穩定性,以提高後續施工人員於牆下方挖掘的安全性,且該棋盤腳頂昇施工法適用於無地樑的建築物,且不需要先補做地樑,有效改善補做地樑對建築物與施工人員的影響。 In the step of jack configuration, the checkerboard foot lifting construction method digs a configuration groove on the front side and the back side of the wall, and then places the jack to avoid digging under the wall, so that the configuration of the jack can avoid the bottom of the wall, which is effective. Reduce the impact on the building and improve the safety. In this support configuration step and the excavation and reinforcement step, the stability of the building can be improved through the use of steel rails, casing reinforcement components, through-wall reinforcement and support reinforcement to improve subsequent construction. The safety of personnel excavating under the wall, and the checkerboard foot lifting construction method is suitable for buildings without ground beams, and it is not necessary to make ground beams first, which effectively improves the impact of the ground beams on the buildings and construction personnel.

此外,該棋盤腳頂昇施工法於挖掘配筋步驟中,配置監測系統可監測牆的沉陷、上浮、前傾與後傾,搭配千斤頂而能針對牆的沉陷、上浮、前傾與後傾進行調整。 In addition, the checkerboard foot lifting construction method is used in the excavation and reinforcement steps. A monitoring system can be configured to monitor the wall subsidence, ascent, forward and backward tilt. With a jack, it can be used for wall subsidence, ascent, forward and backward tilt. Adjustment.

另外,於該千斤頂配置步驟中,配置千斤頂之前先鋪設鋼筋混凝土再放置墊木,且千斤頂的上部不會與牆直接接觸,可降低接觸不平整、地面太軟下陷歪斜對建築物的影響。 In addition, in the jack configuration step, the reinforced concrete is laid before the jack is placed, and the cushion is placed, and the upper part of the jack will not directly contact the wall, which can reduce the impact of uneven contact and too soft subsidence on the building.

10‧‧‧牆 10‧‧‧ wall

20‧‧‧配置溝 20‧‧‧ Configuration trench

21‧‧‧墊木 21‧‧‧ Stow

22‧‧‧千斤頂 22‧‧‧ jack

23‧‧‧承壓鋼鈑 23‧‧‧Pressed steel sheet

24‧‧‧加勁連結鈑 24‧‧‧ Strengthen the connection sheet

25‧‧‧穿牆鋼筋 25‧‧‧ Rebar

26‧‧‧支架鋼筋 26‧‧‧ Rebar

27‧‧‧墊高片 27‧‧‧ padding film

28‧‧‧連結鋼條 28‧‧‧ connected steel bar

30‧‧‧鋼軌 30‧‧‧ Rail

40、40A、40B‧‧‧套管鋼筋組件 40, 40A, 40B ‧‧‧ Casing Rebar Assembly

41‧‧‧支撐鋼筋 41‧‧‧ supporting steel

42‧‧‧滾軸 42‧‧‧Roller

43‧‧‧第一軸管 43‧‧‧First shaft tube

44‧‧‧第二軸管 44‧‧‧Second shaft tube

50‧‧‧土溝 50‧‧‧ Trench

60‧‧‧條形基礎 60‧‧‧ strip foundation

70‧‧‧高壓噴射成型樁 70‧‧‧High Pressure Spray Forming Pile

80‧‧‧鉛直基準面 80‧‧‧Vertical datum

圖1:為本發明棋盤腳頂昇施工法之一較佳實施例之流程示意圖。 FIG. 1 is a schematic flow chart of a preferred embodiment of a method for lifting a chessboard foot according to the present invention.

圖2:為本發明棋盤腳頂昇施工法之一較佳實施例之施工場地局部俯視示意圖。 FIG. 2 is a schematic partial plan view of a construction site according to a preferred embodiment of the chessboard foot jacking construction method of the present invention.

圖3:為本發明棋盤腳頂昇施工法之一較佳實施例之施工場地局部側視示意圖。 FIG. 3 is a schematic partial side view of a construction site, which is a preferred embodiment of the construction method of the checkerboard foot jacking of the present invention.

圖4:為圖3之局部放大示意圖。 FIG. 4 is a partially enlarged schematic diagram of FIG. 3.

圖5:為圖3之千斤頂放大示意圖。 FIG. 5 is an enlarged schematic diagram of the jack of FIG. 3.

圖6:為本發明棋盤腳頂昇施工法之一較佳實施例之單套管鋼筋組件的側視示意圖。 FIG. 6 is a schematic side view of a single casing steel bar assembly according to a preferred embodiment of the chessboard foot jacking construction method of the present invention.

圖7:為本發明棋盤腳頂昇施工法之一較佳實施例之單套管鋼筋組件的端視示意圖。 FIG. 7 is a schematic end view of a single casing steel bar assembly according to a preferred embodiment of the chessboard foot jacking construction method of the present invention.

圖8:為本發明棋盤腳頂昇施工法之一較佳實施例之雙套管鋼筋組件的側視示意圖。 FIG. 8 is a schematic side view of a double-sleeve rebar assembly according to a preferred embodiment of the chessboard foot jacking construction method of the present invention.

圖9:為本發明棋盤腳頂昇施工法之一較佳實施例之雙套管鋼筋組件的端視示意圖。 FIG. 9 is a schematic end view of a double-sleeve rebar assembly according to a preferred embodiment of the chessboard foot jacking construction method of the present invention.

圖10:為本發明棋盤腳頂昇施工法之一較佳實施例之高壓噴射成型樁的配置示意圖。 FIG. 10 is a schematic diagram of the configuration of a high-pressure spray-molded pile according to a preferred embodiment of the checkerboard foot jacking construction method of the present invention.

請參閱圖1,為本發明棋盤腳頂昇施工法之一較佳實施例,其包含一千斤頂配置步驟、一支撐配置步驟、一挖掘配筋步驟、一澆注步驟、一移除步驟及一托基步驟。 Please refer to FIG. 1, which is a preferred embodiment of the board foot lifting construction method of the present invention, which includes a jack configuration step, a support configuration step, an excavation and reinforcement step, a pouring step, a removal step, and a bracket.基 步骤。 Basic steps.

如圖1至圖3,該千斤頂配置步驟係於原建築物之待施工的牆10兩側的土壤挖出,以得知牆10深度,即得知牆10的底面至地面的距離為多少,待得知牆10深度之後,接著於待施工的牆10的前側方與後側方的地面上分別挖掘深至牆10下60-70公分的一配置溝20,即配置溝20的底面與牆10的底面的距離為60-70公分,接著於所述配置溝20鋪設鋼筋混凝土,鋪設的鋼筋混凝土的厚度為20公分,鋪設的鋼筋混凝土是配置雙向單筋並採用抗壓強度為245kg/cm2的混凝土,接著於鋪設的鋼筋混凝土上放置墊木21,再放置千斤頂22於墊木21上,可透過墊木21調整千斤頂22的高度。 As shown in Fig. 1 to Fig. 3, the jack configuration step is to excavate the soil on both sides of the wall 10 of the original building to be constructed to obtain the depth of the wall 10, that is, the distance from the bottom surface of the wall 10 to the ground. After the depth of the wall 10 is known, a configuration trench 20 is digged on the ground on the front and rear sides of the wall 10 to the depth of 60-70 cm below the wall 10, that is, the bottom surface of the configuration trench 20 and the wall. The distance of the bottom surface of 10 is 60-70 cm, and then the reinforced concrete is laid on the configuration groove 20, and the thickness of the reinforced concrete is 20 cm. The reinforced concrete is laid with a two-way single reinforcement and a compressive strength of 245 kg / cm. 2 concrete, and then place a pad 21 on the laid reinforced concrete, and then place a jack 22 on the pad 21, and the height of the jack 22 can be adjusted through the pad 21.

配置溝20鋪設鋼筋混凝土7天後,接著進行該支撐配置步驟,於千斤頂22上設置承壓鋼鈑23,再於相對的承壓鋼鈑23上跨設並點焊固定鋼軌30與套管鋼筋組件40,且鋼軌30與套管鋼筋組件40通過牆10下方,鋼軌30與套管鋼筋組件40之間焊接加勁連結鈑24,再於牆10下方設置間隔排列的穿牆鋼筋25,且穿牆鋼筋25與套管鋼筋組件40之間以支架鋼筋26連接並點焊固定,其中,承壓鋼鈑23的厚度為2公分,進一步長度為60公分,寬度為25公分,並如圖3、圖4所示,於牆10下方設置至少7支間隔排列的穿牆鋼筋25,且最外側之二穿牆鋼筋25的最小間距為60公分,其中,穿牆鋼筋25可選用#11鋼筋,如圖5所示,承壓鋼鈑23上可設置墊高片27,套管鋼筋組件40的兩端抵靠於相對的墊高片27並可點焊固定,以及墊高片27點焊固定於承壓鋼鈑23。 After 7 days of laying reinforced concrete in the configuration trench 20, the support configuration step is followed. A pressure-bearing steel sheet 23 is provided on the jack 22, and the rail 30 and the casing steel bar are fixed by spot welding on the opposite pressure-bearing steel sheet 23 Component 40, and the rail 30 and the casing reinforcement component 40 pass under the wall 10, and the steel plate 30 and the casing reinforcement component 40 are welded and stiffened to connect the sheet 24, and then the wall 10 is arranged at intervals below the wall 10 and penetrates the wall The reinforcing steel bar 25 and the casing steel bar assembly 40 are connected by bracket steel bars 26 and fixed by spot welding. Among them, the pressure steel sheet 23 has a thickness of 2 cm, a further length of 60 cm, and a width of 25 cm. As shown in Figure 4, at least 7 spaced through bars 25 are arranged below the wall 10, and the minimum distance between the outermost two through bars 25 is 60 cm. Among them, # 11 bars can be used as the through bars 25, as shown in the figure. As shown in FIG. 5, a bearing plate 27 may be provided on the pressure-bearing steel sheet 23. Both ends of the casing steel bar assembly 40 abut against the opposite bearing plate 27 and can be fixed by spot welding, and the bearing plate 27 is fixed by spot welding on the bearing plate.压 钢板 23。 Steel plate 23.

如圖3、圖5所示,套管鋼筋組件40具有一支撐鋼筋41及一滾軸42,該滾軸42套設於該支撐鋼筋41,且該支撐鋼筋41的兩端伸出該滾軸42,該滾軸42位於牆10下方,該支撐鋼筋41跨設於相對的千斤頂22上的承壓鋼鈑23,其中,該滾軸42可具有一第一軸管43,進一步具有一第二軸管44,另參閱圖6至圖9,套管鋼筋組件40可以為單套管鋼筋組件40A或雙套管鋼筋組件40B,如圖6、圖7,單套管鋼筋組件40A的滾軸42具有該第一軸管43,該第一軸管43套 設於該支撐鋼筋41,如圖8、圖9,雙套管鋼筋組件40B的滾軸42具有該第一軸管43及該第二軸管44,該第一軸管43套設於該支撐鋼筋41,該第二軸管44套設於該第一軸管43,另外,單套管鋼筋組件40設置於T樑牆下,雙套管鋼筋組件40設至於主樑牆下。 As shown in FIG. 3 and FIG. 5, the casing steel bar assembly 40 has a supporting steel bar 41 and a roller 42, the roller 42 is sleeved on the supporting steel bar 41, and both ends of the supporting steel bar 41 protrude from the roller shaft. 42. The roller 42 is located below the wall 10, and the supporting steel bar 41 straddles the pressure-bearing steel sheet 23 on the opposite jack 22. The roller 42 may have a first shaft tube 43 and further a second shaft tube 43. Axle tube 44, see also FIGS. 6-9. The casing steel bar assembly 40 may be a single casing steel bar assembly 40A or a double casing steel bar assembly 40B. As shown in FIGS. 6 and 7, the roller 42 of the single casing steel bar assembly 40A. Have the first shaft tube 43, the first shaft tube 43 sets 8 and 9, the roller 42 of the double-sleeve steel bar assembly 40B has the first shaft tube 43 and the second shaft tube 44, and the first shaft tube 43 is sleeved on the support. Reinforcement 41, the second shaft tube 44 is sleeved on the first shaft tube 43, in addition, a single-sleeve steel bar assembly 40 is disposed under the T-beam wall, and a double-sleeve steel bar assembly 40 is disposed under the main beam wall.

於支撐配置步驟中,兩相對的承壓鋼鈑23上跨設一鋼軌30及二套管鋼筋組件40,該二套管鋼筋組件40位於該鋼軌30兩側,如圖5所示,於鋼軌30和其兩側之套管鋼筋組件40的支撐鋼筋41之間焊接加勁連結鈑24,以及可於鋼軌30和其兩側之套管鋼筋組件40的滾軸42之間焊接連結鋼條28,連結鋼條28鄰近牆10的前側、後側並可作擋牆鈑。 In the supporting configuration step, a steel rail 30 and two casing steel bar assemblies 40 are set across the two opposite pressure steel plates 23, and the two casing steel bar assemblies 40 are located on both sides of the steel rail 30, as shown in FIG. Welding stiffening connection sheet 24 is welded between 30 and the supporting reinforcement 41 of the casing reinforcing bar assembly 40 on both sides, and steel bars 28 may be welded between the rail 30 and the roller 42 of the casing reinforcing bar assembly 40 on both sides. The connecting steel bars 28 are adjacent to the front side and the rear side of the wall 10 and can be used as retaining wall sheets.

完成支撐配置步驟後,接著進行挖掘配筋步驟,於牆10下方開挖條形基礎60的土溝50,先挖掘穿牆鋼筋25下方,再挖掘套管鋼筋組件40的滾軸42下方,配置監測系統監測牆10的沉陷、上浮、前傾與後傾,並以千斤頂22調整牆10,待調整完後,於土溝50內配筋,其中,挖掘的土溝50深至牆10下方40公分,於土溝50配筋為雙層雙向並焊接拉力鋼筋,以及於鄰近原建築物的鋼筋混凝土柱或磚柱之版筋以鋼筋植筋入柱,再與接續的版筋焊接。 After the support configuration step is completed, the excavation and reinforcement step is then performed. The soil trench 50 of the strip foundation 60 is excavated below the wall 10, and the wall reinforcement 25 is excavated first, and then the roller 42 of the casing reinforcement assembly 40 is excavated. The monitoring system monitors the subsidence, uplift, forward and backward tilt of the wall 10, and adjusts the wall 10 with jacks 22. After the adjustment, the reinforcement is reinforced in the soil trench 50, wherein the excavated soil trench 50 is as deep as 40 below the wall 10 In centimeters, the reinforcement in the soil trench 50 is a double-layer bidirectional and welded tensile steel bar, and the plate bars of the reinforced concrete column or brick column adjacent to the original building are inserted into the column with steel bars, and then welded with the subsequent plate bars.

接著進行澆注步驟,將混凝土澆注於土溝50內,讓混凝土掩蓋套管鋼筋組件40的滾軸42、位於土溝50的鋼軌30、支架鋼筋26與穿牆鋼筋25,且混凝土澆注到牆10底部上方10公分處,以形成條形基礎60,其中,採用抗壓強度為245kg/cm2的混凝土澆注至土溝50。 Next, a pouring step is performed, and the concrete is poured into the trench 50, so that the concrete covers the roller 42 of the casing reinforcing bar assembly 40, the rail 30 located in the trench 50, the bracket reinforcing bar 26 and the through-bar reinforcing bar 25, and the concrete is poured into the wall 10 10 cm above the bottom to form a strip-shaped foundation 60, in which concrete with a compressive strength of 245 kg / cm 2 is cast into the trench 50.

接著進行移除步驟,切除條形基礎60兩側外伸的套管鋼筋組件40與鋼軌30的部分,以及移除配置溝20內的千斤頂22、承壓鋼鈑23與墊木21,再將混凝土澆注於配置溝20至牆10底部上方10公分處,其中,採用抗壓強度為140kg/cm2的混凝土澆注至配置溝20。 Then, the removal step is performed, and the parts of the casing reinforcing bar assembly 40 and the rail 30 protruding from the two sides of the strip foundation 60 are cut off, and the jack 22, the pressure-bearing steel sheet 23 and the spacer 21 are removed in the configuration groove 20, and then The concrete is poured from the configuration trench 20 to 10 cm above the bottom of the wall 10, and the concrete with a compressive strength of 140 kg / cm 2 is poured into the configuration trench 20.

接著進行托基步驟,如圖10所示,於條形基礎60下方設置高壓噴射成型樁70,且高壓噴射成型樁70與一鉛直基準面80的夾角為5°,並由地面下21公尺至牆10下0.4公尺。 Next, the step of supporting the foundation is performed. As shown in FIG. 10, a high-pressure injection-molded pile 70 is set under the strip foundation 60, and the angle between the high-pressure injection-molded pile 70 and a vertical reference plane 80 is 5 °, and 21 meters below the ground. 0.4 meters below the wall.

於該棋盤腳頂昇施工法中,可於該移除步驟完成後,接著挖掘騎樓下方的條形基礎60土溝50,以植筋方式接續已完成的條形基礎60,騎樓處的條形基礎60土溝50配筋後澆注抗壓強度為245kg/cm2的混凝土,並澆注至牆10底部上方10公分處,另外,於托基步驟完成後,接著鋪設屋內地面。 In the checkerboard foot lifting construction method, after the removal step is completed, the strip foundation 60 soil trench 50 below the pavilion can be excavated, and the completed strip foundation 60 can be continued by planting tendons. After the foundation 60 soil trench 50 is reinforced, concrete with a compressive strength of 245 kg / cm 2 is poured, and is poured 10 cm above the bottom of the wall 10. In addition, after the step of supporting the foundation is completed, the floor of the house is then laid.

上述中,監測系統採用三台雷射水準儀與三個覘標監測牆10的沉陷或上浮,三個覘標分別設於牆10的左、中、右的三個觀測定點,並配合該三台雷射水準儀監測,若雷射水準儀沒掃描到覘標,代表牆10沉陷或上浮,接著可調整牆10前側方或後側方的千斤頂22頂昇或調降,同時,監測系統於牆10的左、中、右設置前後夾牆之指標與鋼絲垂球,以及其下方設置固定於地上的標尺,其中,指標可設置於牆10前,鋼絲垂球可設置於牆10後,標尺位於牆10下方,也位於指標與鋼絲垂球的下方,若牆10有前後傾斜,則可調整對應牆10前或牆10後的千斤頂22頂昇或調降。 In the above, the monitoring system uses three laser levels and three targets to monitor the sinking or floating of the wall 10, and the three targets are set at the three observation points on the left, center, and right of the wall 10, and cooperate with the three Laser level monitoring. If the laser level does not scan the target, it means that the wall 10 has sunk or floated. Then, the jack 22 on the front side or the back side of the wall 10 can be adjusted to rise or fall. At the same time, the monitoring system Left, middle, and right sets the indicators of the front and rear clamp walls and steel wire vertical balls, and a ruler fixed to the ground below it. Among them, the indicator can be set in front of the wall 10, the steel wire vertical ball can be set behind the wall 10, and the ruler is located on the wall 10. The lower part is also located below the indicator and the steel wire ball. If the wall 10 is tilted back and forth, the jack 22 corresponding to the front of the wall 10 or behind the wall 10 can be adjusted to rise or fall.

於托基步驟中,高壓噴射成型樁70的噴漿壓力為180-200kg/cm2,且灌注高壓噴射成型樁70時,雷射水準儀仍要監測噴漿的高壓是否頂裂建築物。 In the torch step, the spray pressure of the high-pressure spray-molded pile 70 is 180-200 kg / cm 2 , and when the high-pressure spray-molded pile 70 is poured, the laser level still needs to monitor whether the high-pressure sprayed high pressure cracks the building.

該棋盤腳頂昇施工法適用於建築物中採用無地樑之獨立基腳柱間或磚柱間,該棋盤腳頂昇施工法透過千斤頂22、鋼軌30、套管鋼筋組件40、穿牆鋼筋25與支架鋼筋26的依序配置,可頂住牆10並便於條形基礎60的施作,再挖掘配筋步驟與澆注步驟進行條形基礎60施作時,讓牆10不會發生沉陷變形。 The checkerboard foot lifting construction method is applicable to independent footings or brick columns in a building without ground beams. The checkerboard foot lifting construction method uses jacks 22, steel rails 30, casing reinforcement components 40, and wall reinforcement 25 Sequential arrangement with the reinforcing steel bar 26 can support the wall 10 and facilitate the application of the strip foundation 60. When the reinforcement foundation and the pouring step are performed for the strip foundation 60, the wall 10 will not be deformed.

上述中,透過該棋盤腳頂昇施工法可將既有建築物中的獨立基腳改為較耐沉陷的條形基礎60,讓建築物可較耐差異沉陷且不易龜裂,達到降低沉陷量的目的。 In the above, through the checkerboard foot lifting construction method, the independent footings in the existing building can be changed to a more subsidence-resistant strip foundation 60, so that the building can be more resistant to differential subsidence and less cracking, thereby reducing the amount of subsidence. the goal of.

其中,千斤頂22頂昇牆10並配合支撐配置步驟中穿牆鋼筋25與支撐鋼筋41的配置,可提高對牆10的支撐力與提高施作過程中牆10的穩定性,以及千斤頂22配合監測系統,可調整牆10至正確位置,避免牆10的傾斜,以及托基步驟中,在條形基礎60下方設置傾斜的高壓噴射成型樁70,可有效防止建築物的沉陷並達到降低沉陷量的目的。 Among them, the jack 22 lifts the wall 10 and cooperates with the configuration of the through-bar reinforcement 25 and the support reinforcement 41 in the support configuration step, which can improve the support force for the wall 10 and the stability of the wall 10 during the construction process, and the cooperation of the jack 22 monitoring The system can adjust the wall 10 to the correct position to avoid the inclination of the wall 10, and in the step of supporting the foundation, the inclined high-pressure spray-molded pile 70 is arranged below the strip foundation 60, which can effectively prevent the building from subsiding and reduce the amount of subsidence. purpose.

上述中,於該千斤頂配置步驟中,在牆10的前側方與後側方挖掘配置溝20再放置千斤頂22,讓配置千斤頂22的挖掘與配置作業不在牆10的下方進行,有效降低對建築物的影響並提高安全性,且於該支撐配置步驟與該挖掘配筋步驟中,透過鋼軌30、套管鋼筋組件40、穿牆鋼筋25與支架鋼筋26可提高建築物的穩定性,以提高後續施工人員於牆10下方挖掘的安全性,其中,配置千斤頂22之前先鋪設鋼筋混凝土再放置墊木21,且千斤頂22的上部不會與牆10直接接觸,可降低接觸不平整、地面太軟下陷歪斜對建築物的影響。 In the above, in the jack configuration step, the configuration groove 20 is excavated on the front side and the back side of the wall 10 and then the jack 22 is placed, so that the excavation and configuration operations of the jack 22 are not performed under the wall 10, which effectively reduces the impact on the building. Influence and improve safety, and in the support configuration step and the excavation and reinforcement step, the stability of the building can be improved through the rail 30, the casing reinforcement assembly 40, the wall reinforcement 25 and the support reinforcement 26 to improve the follow-up The safety of the excavator under the wall 10, in which the reinforced concrete is laid before the jack 22 is placed, and the stiffener 21 is placed, and the upper part of the jack 22 will not directly contact the wall 10, which can reduce uneven contact and the ground is too soft and subsided The effect of skew on buildings.

該棋盤腳頂昇施工法適用於無地樑的建築物,且不需要先補做地樑,有效改善補做地樑對建築物與施工人員的影響。 The checkerboard foot lifting construction method is suitable for buildings without ground beams, and does not need to be supplemented to make ground beams, which effectively improves the impact of supplementary ground beams on buildings and construction workers.

Claims (10)

一種棋盤腳頂昇施工法,其包含:一千斤頂配置步驟,於原建築物之待施工的牆兩側的土壤挖出以得知牆深度,再於牆的前側方與後側方的地面上分別挖掘一配置溝,於所述配置溝鋪設鋼筋混凝土,放置墊木,再放置千斤頂於墊木上;一支撐配置步驟,於千斤頂上設置承壓鋼鈑,再於相對的承壓鋼鈑上跨設並點焊固定鋼軌與套管鋼筋組件,且鋼軌與套管鋼筋組件通過牆下方,鋼軌與套管鋼筋組件之間焊接加勁連結鈑,再於牆下方設置間隔排列的穿牆鋼筋,且穿牆鋼筋與套管鋼筋組件之間以支架鋼筋連接並點焊固定;一挖掘配筋步驟,於牆下方開挖條形基礎的土溝,先挖掘穿牆鋼筋下方,再挖掘套管鋼筋組件的滾軸下方,配置監測系統監測牆的沉陷、上浮、前傾與後傾,並以千斤頂調整牆,待調整完後,於土溝內配筋;一澆注步驟,將混凝土澆注於土溝內,讓混凝土掩蓋套管鋼筋組件的滾軸、位於土溝的鋼軌、支架鋼筋與穿牆鋼筋,且混凝土澆注到牆底部上方10公分處,以形成條形基礎;一移除步驟,切除條形基礎兩側外伸的套管鋼筋組件與鋼軌的部分,以及移除配置溝內的千斤頂、承壓鋼鈑與墊木,再將混凝土澆注於配置溝至牆底部上方10公分處;以及一托基步驟,於條形基礎下方設置高壓噴射成型樁,且高壓噴射成型樁與一鉛直基準面的夾角為5°,並由地面下21公尺至牆下0.4公尺。A checkerboard foot lifting construction method includes: a jack configuration step, digging soil on both sides of a wall of an original building to be constructed to know the depth of the wall, and then on the ground on the front and rear sides of the wall Digging a configuration trench separately, laying reinforced concrete on the configuration trench, placing staging, and then placing a jack on the staging; a supporting configuration step, setting a pressure-bearing steel sheet on the jack, and then on the opposite pressure-bearing steel sheet The rail and casing reinforcement components are fixed across the spot and welded, and the rail and casing reinforcement components pass under the wall, and the steel plates and casing reinforcement components are welded to stiffen the connection sheet, and the wall-through reinforcement is arranged below the wall, and The through-wall reinforcement and casing reinforcement components are connected by bracket reinforcement and fixed by spot welding. In the excavation and reinforcement step, a trench with a strip foundation is excavated below the wall. The under-wall reinforcement is first excavated, and then the casing reinforcement components are excavated. Below the rollers, a monitoring system is configured to monitor the wall subsidence, uplift, forward and backward tilt, and adjust the wall with a jack. After the adjustment is completed, reinforcement is provided in the soil trench; in a pouring step, the concrete is poured into In the trench, the concrete is used to cover the rollers of the casing reinforcing steel components, the rails located in the trench, the reinforcing steel bars and the through-wall reinforcements, and the concrete is poured to a height of 10 cm above the bottom of the wall to form a strip foundation. The parts of the casing steel bars and rails protruding from the two sides of the strip foundation, as well as removing the jacks, pressure steel plates and staging in the configuration trench, and then pouring the concrete into the configuration trench 10 cm above the bottom of the wall; and In a supporting step, a high-pressure spray-formed pile is set under the strip foundation, and the angle between the high-pressure spray-formed pile and a vertical reference plane is 5 °, and the height is 21 meters below the ground to 0.4 meters below the wall. 如請求項1所述之棋盤腳頂昇施工法,其中,於該移除步驟完成後,接著挖掘騎樓下方的條形基礎土溝,以植筋方式接續已完成的條形基礎,騎樓處的條形基礎土溝配筋後澆注抗壓強度為245kg/cm2的混凝土,並澆注至牆底部上方10公分處。The chessboard foot lifting construction method according to claim 1, wherein after the removal step is completed, the strip foundation soil trench below the tower is then excavated, and the completed strip foundation is connected by means of planting tendons. After the strip foundation trench is reinforced, concrete with a compressive strength of 245 kg / cm 2 is poured, and it is poured 10 cm above the bottom of the wall. 如請求項1所述之棋盤腳頂昇施工法,其中,於托基步驟完成後,接著鋪設屋內地面。The chessboard foot lifting construction method according to claim 1, wherein after the completion of the torquing step, the floor of the house is then laid. 如請求項2所述之棋盤腳頂昇施工法,其中,於托基步驟完成後,接著鋪設屋內地面。The chessboard foot lifting construction method according to claim 2, wherein after the completion of the torquing step, the floor of the house is then laid. 如請求項1至4中任一項所述之棋盤腳頂昇施工法,其中,於千斤頂配置步驟中,挖掘的配置溝深至牆下60-70公分,所述配置溝中鋪設的鋼筋混凝土的厚度為20公分,鋪設的鋼筋混凝土是配置雙向單筋並採用抗壓強度為245kg/cm2的混凝土。The chessboard foot lifting construction method according to any one of claims 1 to 4, wherein, in the jack configuration step, the configuration trenches dug to the depth of 60-70 cm below the wall are reinforced concrete laid in the configuration trenches The thickness of the reinforced concrete is 20 cm. The reinforced concrete is laid with two-way single reinforcement and adopts concrete with a compressive strength of 245 kg / cm 2 . 如請求項5所述之棋盤腳頂昇施工法,其中,於支撐配置步驟中,設置厚度2公分的承壓鋼鈑,並於牆下方設置至少7支間隔排列的穿牆鋼筋,且最外側之二穿牆鋼筋的最小間距為60公分。The construction method of lifting a chessboard foot as described in claim 5, wherein in the supporting configuration step, a pressure-resistant steel sheet with a thickness of 2 cm is set, and at least 7 spaced-through steel bars are arranged below the wall, and the outermost side The minimum distance between wall reinforcements is 60 cm. 如請求項6所述之棋盤腳頂昇施工法,其中,於挖掘配筋步驟中,挖掘的土溝深至牆下方40公分,於土溝配筋為雙層雙向並焊接拉力鋼筋,以及於鄰近原建築物的鋼筋混凝土柱或磚柱之版筋以鋼筋植筋入柱,再與接續的版筋焊接。The chessboard foot lifting construction method according to claim 6, wherein in the excavation and reinforcement step, the trench is excavated to a depth of 40 cm below the wall, and the reinforcement in the trench is a two-layer bidirectional and welded tensile steel bar, and The reinforcing bars of the reinforced concrete column or brick column adjacent to the original building are inserted into the column with steel bars, and then welded with the subsequent plates. 如請求項7所述之棋盤腳頂昇施工法,其中,於澆注步驟中,採用抗壓強度為245kg/cm2的混凝土澆注至土溝。The chessboard foot lifting construction method according to claim 7, wherein, in the pouring step, concrete with a compressive strength of 245 kg / cm 2 is poured into the trench. 如請求項8所述之棋盤腳頂昇施工法,其中,於移除步驟中,採用抗壓強度為140kg/cm2的混凝土澆注至配置溝。The chessboard foot lifting construction method according to claim 8, wherein, in the removing step, concrete with a compressive strength of 140 kg / cm 2 is poured into the configuration groove. 如請求項1至4中任一項所述之棋盤腳頂昇施工法,其中,套管鋼筋組件為單套管鋼筋組件或雙套管鋼筋組件,套管鋼筋組件具有一支撐鋼筋及一滾軸,該滾軸套設於該支撐鋼筋,且該支撐鋼筋的兩端伸出該滾軸,該滾軸位於牆下方,該支撐鋼筋跨設於相對的千斤頂上的承壓鋼鈑,其中,該滾軸具有一第一軸管,進一步具有一第二軸管,單套管鋼筋組件的滾軸具有該第一軸管,該第一軸管套設於該支撐鋼筋,雙套管鋼筋組件的滾軸具有該第一軸管與該第二軸管,該第一軸管套設於該支撐鋼筋,該第二軸管套設於該第一軸管。The chessboard foot lifting construction method according to any one of claims 1 to 4, wherein the casing steel bar component is a single casing steel bar component or a double casing steel bar component, and the casing steel bar component has a supporting steel bar and a roll A shaft, the roller sleeve is sleeved on the supporting steel bar, and both ends of the supporting steel bar protrude from the roller shaft, the roller is located below the wall, and the supporting steel bar straddles the pressure-bearing steel sheet on the opposite jack, wherein, The roller has a first shaft tube, and further has a second shaft tube. The roller of a single sleeve steel bar component has the first shaft tube, and the first shaft tube is sleeved on the supporting steel bar, and the double sleeve steel bar component. The roller has the first shaft tube and the second shaft tube, the first shaft tube is sleeved on the supporting steel bar, and the second shaft tube is sleeved on the first shaft tube.
TW107142230A 2018-11-27 2018-11-27 Checkerboard jacking construction method TWI665365B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW107142230A TWI665365B (en) 2018-11-27 2018-11-27 Checkerboard jacking construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW107142230A TWI665365B (en) 2018-11-27 2018-11-27 Checkerboard jacking construction method

Publications (2)

Publication Number Publication Date
TWI665365B true TWI665365B (en) 2019-07-11
TW202020279A TW202020279A (en) 2020-06-01

Family

ID=68049770

Family Applications (1)

Application Number Title Priority Date Filing Date
TW107142230A TWI665365B (en) 2018-11-27 2018-11-27 Checkerboard jacking construction method

Country Status (1)

Country Link
TW (1) TWI665365B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW222016B (en) * 1992-11-23 1994-04-01 Jia-Shyong Hwang Method of digging ground with retaining wall supported by floor plates
CN102444147A (en) * 2011-11-08 2012-05-09 山西太行建设开发有限公司 Slant correction method for building
CN102767180A (en) * 2012-08-08 2012-11-07 龙信建设集团有限公司 Construction method for strengthening base of static-pressure anchor rod pile
CN203174619U (en) * 2013-01-22 2013-09-04 管自立 Reverse raft concrete terrace
CN104805876A (en) * 2015-05-18 2015-07-29 中国化学工程第三建设有限公司 Method for correcting inclined independent bent frame column by vertically jacking and pushing

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW222016B (en) * 1992-11-23 1994-04-01 Jia-Shyong Hwang Method of digging ground with retaining wall supported by floor plates
CN102444147A (en) * 2011-11-08 2012-05-09 山西太行建设开发有限公司 Slant correction method for building
CN102767180A (en) * 2012-08-08 2012-11-07 龙信建设集团有限公司 Construction method for strengthening base of static-pressure anchor rod pile
CN203174619U (en) * 2013-01-22 2013-09-04 管自立 Reverse raft concrete terrace
CN104805876A (en) * 2015-05-18 2015-07-29 中国化学工程第三建设有限公司 Method for correcting inclined independent bent frame column by vertically jacking and pushing

Also Published As

Publication number Publication date
TW202020279A (en) 2020-06-01

Similar Documents

Publication Publication Date Title
KR20090002344A (en) Land-side protection wall that use ground structure
KR101111594B1 (en) Method for constructing underground structure
JP2007182741A (en) Differentially settled foundation correcting and reinforcing method by underpinning
CN106088127A (en) Open caisson construction method
CN104563146A (en) Construction method for open caisson engineering of fixed and direct burial type rainwater and sewage pumping station
CN108999225B (en) Inclination correcting method for rotary shifting brick-concrete structure building
CN112681332A (en) Construction method for supporting system by using steel sheet piles in complex environment
CN106193047A (en) Big width base pit stand construction
CN114673169A (en) Multi-layer large-span deep foundation pit cover-excavation forward-backward combined construction method for urban core area
CN114215096A (en) Tower crane lattice column pile foundation bearing platform
CN103132465A (en) Underground box culvert constructing method closely attached to pile foundation bearing platform
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove
CN110241863B (en) Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof
TWI665365B (en) Checkerboard jacking construction method
CN210106749U (en) Counter-force structure of soft soil foundation super large section push pipe jacking operation
CN110924404A (en) Construction method for deep backfill filling wall foundation
CN216999797U (en) Foundation pit supporting pile and foundation pit cofferdam
CN215715333U (en) Pre-buried device of flow plasticity geology bottom plate construction
TWI623669B (en) Construction method of advance pavement for preventing underground subsidence before continuous wall construction
JP6422084B2 (en) Underground space construction method
CN211143136U (en) Pipe gallery deformation control device in soft soil foundation pit excavation process
CN105780938A (en) Vertical construction seam construction method of core tube bottom board for super high-rise
JP2008280738A (en) Retaining wall reinforcing structure and method of constructing the same
CN115198794B (en) Steel pipe column section reverse construction method based on cover-excavation reverse construction method deep foundation pit engineering
CN112609706B (en) Construction method of opposite-bracing angle brace concrete horizontal supporting structure of foundation pit in sea reclamation area