SU998759A1 - Method of controlling rock pressure - Google Patents

Method of controlling rock pressure Download PDF

Info

Publication number
SU998759A1
SU998759A1 SU813347762A SU3347762A SU998759A1 SU 998759 A1 SU998759 A1 SU 998759A1 SU 813347762 A SU813347762 A SU 813347762A SU 3347762 A SU3347762 A SU 3347762A SU 998759 A1 SU998759 A1 SU 998759A1
Authority
SU
USSR - Soviet Union
Prior art keywords
chambers
rock pressure
pillars
massive
artificial
Prior art date
Application number
SU813347762A
Other languages
Russian (ru)
Inventor
Нириман Галимович Ялымов
Олег Васильевич Рогожников
Виктор Егорович Бегляков
Original Assignee
Институт Физики И Механики Горных Пород Ан Киргсср
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт Физики И Механики Горных Пород Ан Киргсср filed Critical Институт Физики И Механики Горных Пород Ан Киргсср
Priority to SU813347762A priority Critical patent/SU998759A1/en
Application granted granted Critical
Publication of SU998759A1 publication Critical patent/SU998759A1/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

Изобретение относитс  к горной промышленности и может быть использовано при управлении горным давлением при подземной разработке рудных месторождений.The invention relates to the mining industry and can be used in the management of rock pressure in underground mining of ore deposits.

-Известен способ управлени  горным давлением, заключающийс  в периодическом искусственном обрушении или самообрушении кровли камер за пределами рабочего пространства Cll.- A method of controlling rock pressure is known, consisting in the periodic artificial collapse or self-destruction of the roof of the chambers outside the working space Cll.

Недостатками этого способа  вл ютс  повышенные потери и разубоживанив руды в св зи с ее выпуском под обрушенными породами, нарушение сплс иности налегающего массива, образование опасных деформаций и провалов на поверхности.The disadvantages of this method are increased losses and dilution of ore due to its release under collapsed rocks, violation of the splice of the overlying massif, the formation of dangerous deformations and dips on the surface.

Наиболее близким техническим решением к изобретению  вл етс  способ управлени  горным давлением, включающий поддержание налегающих пород рудными и искусственными целиками из твердеющей закладки, а также обрушение пород и отработку выемочного участка камерами с использованием перераспределени  горного давлени  на искусственные целики t2l.The closest technical solution to the invention is a method of controlling rock pressure, including maintaining overburden of ore and artificial pillars from hardening bedding, as well as breaking rocks and working out the excavation area by chambers using the redistribution of rock pressure on artificial pillars t2l.

Недостатком известного способа  вл ютс  значительные затраты, св занные с большим расходом закладочного материала.The disadvantage of this method is the considerable costs associated with high consumption of backfill material.

Цель изобретени  - снижение затрат на управление за счет уменьшени  расхода закладочного материала.The purpose of the invention is to reduce management costs by reducing the consumption of filling material.

Поставленна  цель достигаетс  тем, что согласно способу управлени  горным давлением, включающему поддержание налегающих пород рудными и ис10 кусственными целиками из твердеющей закладки, а также обрушение пород и отработку выемочного участка камерами с использованием перераспределени  горного давлени  на искусст15 венные целики, в центре выемочного участка оставл ют массивный рудный целик, и после отработки всего участка производ т закладку камер, расположенных по обе стсчоны от него, за20 тем осуществл ют выемку массивного целика.The goal is achieved by the method of controlling rock pressure, which includes maintaining overburden ore and artificial pillars from hardening bedding, as well as rock breakdown and mining the excavation site with chambers using redistribution of rock pressure to the artificial pillars, in the center of the excavation site the massive ore pillar, and after working out the entire area, the chambers located on both sides of it are laid out, then the massive pillar is excavated .

На чертеже изображена схема преплагаемого способа управлени  горным давлением.The drawing shows a diagram of the proposed method of controlling rock pressure.

2525

Claims (2)

Выемочный участок 1 раздел ют на блоки, а блоки - на камеры 2. В центре участка между кaмepa « 2 оставл ют массивный целик 3. Затем отрабатывают остальные камеры, ос30 тавл   между ними междукамерные целнки 4, Камеры 2, расположенные р дом с массивным целиком, закладывают твердеющей смесью и образуют искусственные целики 5 . После завершени  закладочных работ и отработки блока производ т выемку массивного целика и тем самым перераспредел ют горное давление на искусственные целики и междукамерные целики 4, вызыва  разрушение целиков.4 и самообрушение пород кровли 6 с заполнением ими пустот без нарушени  поверхности Использование предлагаемого изобретени  позволит снизить затраты на управление горным давлением за счет уменьшени  расхода закладочного материала и объемов работ по закладке Формула изобретени  Способ управлени  горным давление включающий поддержание налегающих пород рудными и искусственными .целик ми из твердеющей закладки, а также обрушение пород и отработку выемочного участка камерами с использованием перераспределени , горного давлени  на искусственные целики, о тли чающий с   тем, что, с целью снижени  затрат на управление за счет уменьшени  расхода закладочного материала, в центре выемочного участка оставл ют массивный рудный целик, и после отработ.ки всего участка производ т закладку камер, расположенных по обе стороны от него, затем осуществл ют выемку массивного целика. Источники информации, прин тые во внимание при экспертизе 1.Именитов В.Р. Процессы подземных горных работ при разработке рудных месторождений, М., Недра, 1978, С..393. . Extraction area 1 is divided into blocks, and blocks - into chambers 2. In the center of the area between chamber 2, a massive rear sight 3 is left. Then the remaining chambers are worked out, the distance between them between chamber cells 4, Chambers 2, located near the massive whole , lay a hardening mixture and form artificial pillars 5. After the filling operations and the block have been completed, the massive pillar is excavated and the rock pressure is redistributed to the artificial pillars and interchamber pillars 4, causing the pillars to collapse.4 and the roof rocks 6 to self-destruct without filling the cavities without breaking the surface. to control rock pressure by reducing the consumption of backfill material and the amount of work on the tab Formula of the Invention The method of controlling rock pressure includes Maintaining overburden by ore and artificial targets from hardening bookmarks, as well as rock breakdown and working out of the excavation section by chambers using redistribution, rock pressure on artificial pillars, so as to reduce management costs by reducing consumption of the filling material, a massive ore pillar is left in the center of the excavation site, and after mining the entire site, chambers located on both sides of it are laid out, then an array of th pillar. Sources of information taken into account in the examination 1.V.menit.R. The processes of underground mining in the development of ore deposits, Moscow, Nedra, 1978, p. 393. . 2.Авторское свидетельство СССР по за вке № 3301861, кл. Е 21 С 41/06, 11.06 .81.2. USSR author's certificate for application number 3301861, cl. E 21 C 41/06, 11.06 .81. ..
SU813347762A 1981-10-16 1981-10-16 Method of controlling rock pressure SU998759A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813347762A SU998759A1 (en) 1981-10-16 1981-10-16 Method of controlling rock pressure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813347762A SU998759A1 (en) 1981-10-16 1981-10-16 Method of controlling rock pressure

Publications (1)

Publication Number Publication Date
SU998759A1 true SU998759A1 (en) 1983-02-23

Family

ID=20980321

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813347762A SU998759A1 (en) 1981-10-16 1981-10-16 Method of controlling rock pressure

Country Status (1)

Country Link
SU (1) SU998759A1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2454540C1 (en) * 2010-12-27 2012-06-27 Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН Rock pressure control method
CN102678121A (en) * 2012-05-21 2012-09-19 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
RU2593667C1 (en) * 2015-06-29 2016-08-10 Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук Method of controlling rock pressure during underground development of horizontal and inclined lenticular ore deposits

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2454540C1 (en) * 2010-12-27 2012-06-27 Учреждение Российской академии наук Институт горного дела Сибирского отделения РАН Rock pressure control method
CN102678121A (en) * 2012-05-21 2012-09-19 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN102678121B (en) * 2012-05-21 2014-01-08 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
RU2593667C1 (en) * 2015-06-29 2016-08-10 Федеральное государственное бюджетное учреждение науки Институт горного дела им. Н.А. Чинакала Сибирского отделения Российской академии наук Method of controlling rock pressure during underground development of horizontal and inclined lenticular ore deposits

Similar Documents

Publication Publication Date Title
SU998759A1 (en) Method of controlling rock pressure
SU715798A1 (en) Method of mining gently sloping ore bodies
SU636394A1 (en) Method of mining mineral deposits
SU848643A1 (en) Method of mining ore bodies
SU934006A1 (en) Method of working gently-sloping mineral beds
SU1578335A1 (en) Method of mining seams of useful mineral with poorly caving roof
SU966235A1 (en) Method of winning thin gently-sloping mineral seams
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
SU909178A1 (en) Method of working beds of complex structure with intervening muck
SU1188326A1 (en) Method of mining bedded deposits
SU883447A1 (en) Method of working mineral deposits
SU1010273A1 (en) Method of underground working of thin gently-sloping bed deposits of minerals by the chamber method
SU956793A1 (en) Method of working thick ore deposits
RU1810545C (en) Method for mining mineral beds at large depth
SU403853A1 (en) '-' "- INVENTIONS
SU785488A1 (en) Method of mining minerals in the contour-adjoining areas of a quarry
SU920217A1 (en) Method of working high-capacity deposits
SU639995A1 (en) Method of shoring slopes
RU2014453C1 (en) Method for control of rock pressure
SU703661A1 (en) Method of excavating gently sloping mineral beds
SU827789A1 (en) Method of working thick sloping coal seams
SU754068A1 (en) Method of mining thin sloping seams
SU602684A1 (en) Method of mining mineral deposits
SU831975A1 (en) Method of working thick gently sloping coal beds
SU723140A1 (en) Method of controlling a roof which is caving-proof