SU998642A1 - Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure - Google Patents

Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure Download PDF

Info

Publication number
SU998642A1
SU998642A1 SU813278508A SU3278508A SU998642A1 SU 998642 A1 SU998642 A1 SU 998642A1 SU 813278508 A SU813278508 A SU 813278508A SU 3278508 A SU3278508 A SU 3278508A SU 998642 A1 SU998642 A1 SU 998642A1
Authority
SU
USSR - Soviet Union
Prior art keywords
crane
span
assembly
lifting
frame
Prior art date
Application number
SU813278508A
Other languages
Russian (ru)
Inventor
Владимир Максович Эпштейн
Сергей Владимирович Высотский
Original Assignee
за вители
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by за вители filed Critical за вители
Priority to SU813278508A priority Critical patent/SU998642A1/en
Application granted granted Critical
Publication of SU998642A1 publication Critical patent/SU998642A1/en

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

ное положение грузоподъемным оборудованием и нижнюю платформу с рамой поперечными балками, лебедками дл  продольного перемещени  сборочного крана и подкрановыми тележками , объединенными попарно посредством поперечных балок, рама и поперечные балки нижней платформы разъе но соединены между собой и снабжены поЛиспастными роликами, причем рама нижней платформы расположена под по перечными балками. При этом согласно способу установк сборочного крана на смонтированную ба вую часть сквозного пролетного строен включающему подъем и установку сборочного Красна на верхние по са пролетного строени , закрепление т говых тросов лебедок дл  продольног перемещени  сборочного крана за вер ние по са .пролетного строени , до подъема сборочного крана производ т .подъем и установку этим краном объединенных попарно посредством по перечных балок подкрановых тележек на верхние по са смонтированной базоной части пролетного строени , по ле чего перемещают подкрановые тележки и сборочный кран к месту его подъема и производ т запасовку т говых тросов лебедок дл  продольног перемещени  сборочного крана через полиспастные ролики поперечных балок и рамы нижней платформы, а подъ крана на верхние по са пролетного строени  осуществл ют лебедками дл  продольного перемещени  сборочного крана с последующим разъемным прикреплением рамы нижней платформы к поперечным балкам, а перед закреп лением т говых тросов за верхние по са пролетного строени  тросы высвобождают из полиспастных роликов. На фиг.1 изображен момент установки сборочным краном подкрановых тележек на верхние по са смонтированной базовой части сквозного пролетного строени  с ездой понизу; на фиг.2 - разрез А-А на фиг.1; на фиг.З - момент подъема сборочного крана, сложенного .в габаритном пол жении, на верхние по са смонтированной части пролетного строени ; на фиг.4 - разрез Б-Б на фиг.З; на фиг.З - сборочный кран в рабочем положении на верхних по сах смонтированной части пролетного строени ; на фиг.б - разрез В-В на фиг.5; на фиг.7 - разрез Г-Г на фиг.6. Сборочный кран 1 содержит верхнюю поворотную платформу 2 со складывающимс  в габаритное положение грузоподъемным оборудованием 3 и ни нюю платформу с рамой 4, поперечными балками 5, лебедками б дл  продольного перемещени  сборочного кран и подкрановыми тележками 7, объединен ными попарно посредством попёречных балок 5. Рама 4 нижней платформы расположена под поперечными балками 5 и раэъемно соединена с ними. При этом рама 4 и поперечные балки 5 снабжены укрепленными на них полиспастными роликагиш 8 и 9, соответственно . Установку сборочного крана на предварительно смонтированную этим же краном базовую часть 10 сквозного пролетного строени  моста производ т в следующей последовательности . Первоначально сборочным краном производ т подъем и установку объединенных попарно посредством поперечных балок 5 подкрановых тележек 7 на верхние по са 11 смонтированной части 10 сквозного пролетного строени , после чего подкрановые тележки 7 и сложенный в габаритном положении сборочный кран перемещают к месту подъема крана, соответственно по пут м катани  12, уложенным по верхним по сам 11 пролетного строени  и с использованием вспомогательного транспортного средства 13, перемещаемого в уровне проезжей части 14 пролетного строени . Затем производ т запасовку т говых тросов 15 лебедок б дл  продольного перемещени  сборочного крана через полиспастные ролики 9 и 8, соответственно поперечных балок 5 и рамы 4 нижней платформы, и подъем этими лебедками сборочного крана до уровн  верхних по сов 11 пролетного строени  с последующим разъемным прикреплением, например, с использованием щкворней 16, рамы 4 нижней платформы крана к поперечным балкам 5. После этого т говые тросы 15 высвобождают из полиспастных роликов 8 и 9 и закрепл ют их за верхние по са 11 пролетного строени . Далее производ т поэлементный монтаж посредством сборочного крана пролетного .строени , перемеща  кран по расположенным на верхних по сах 11 пут м катани  12 с помощью лебедок 6 продольного перемещени  сборочного крана. Предлагаема  конструкци  сборочного крана дл  монтажа сквозных пролетных строений мостов обеспечивает высокую эффективность их применени  за счет осуществлени  самоподъема сборочного крана в требуемое рабочее положение, а предлагаемый способ установки сборочного крана обеспечивает существенное снижение ее трудоемкости за счет исключени  необходимости использовани  дополнительного крана, предусмотренного в известном техническом решении, а также исключени  поэлементной сборки крана на верхних по сах смонтированной базовой части пролетного строени .the position of the lifting equipment and the lower platform with the frame of transverse beams, winches for the longitudinal movement of the assembly crane and crane trolleys combined in pairs by means of transverse beams, the frame and transverse beams of the lower platform are disconnected and interconnected and equipped with side pulleys, the frame of the lower platform is located under on pepper beams. In this case, according to the method of installation of the assembly crane on the assembled base part of the through span, including lifting and installing the assembly Red on the upper span, securing the winch cables for longitudinal movement of the assembly crane for the span structure, before lifting the assembly the crane makes lifting and installation of the crane united in pairs by means of pepper beams of crane gantries on the upper parts of the span structure mounted on the base, therefore move the crane trucks and the assembly crane to the place of its lifting and stockpile the winch cables for the longitudinal movement of the assembly crane through the polyspastny rollers of the transverse beams and the frame of the lower platform, and the crane for the upper span structure are winched for the longitudinal movement of the assembly crane with subsequent detachable attachment of the frame of the lower platform to the transverse beams, and before securing the haul cables to the upper span structure, the cables are released from the polyspast x videos. Fig. 1 shows the moment of installation of the crane crane for the crane trucks on the upper mounted base part of the through span with the ride to the bottom; figure 2 - section aa in figure 1; Fig. 3 shows the moment of lifting the assembly crane, folded in the overall position, onto the upper parts of the assembled part of the superstructure; figure 4 - section bb in fig.Z; Fig. 3 shows an assembly crane in the working position on the upper parts of the assembled part of the superstructure; on figb - section bb In figure 5; figure 7 - section GG in figure 6. Assembly crane 1 contains an upper rotary platform 2 with lifting equipment 3 folding into an overall position and a lower platform with frame 4, transverse beams 5, winches b for longitudinal movement of the assembly crane and crane cranes 7 combined in pairs by means of cross beams 5. Frame 4 the lower platform is located under the transverse beams 5 and is detachably connected with them. In this case, the frame 4 and the transverse beams 5 are equipped with polyspast rollers 8 and 9 fixed to them, respectively. The installation of the assembly crane on the base part 10 of the bridge span-through structure that was pre-mounted by the same crane is carried out in the following sequence. Initially, the assembly crane lifts and installs the pairwise joined by means of transverse beams 5 crane trolleys 7 to the upper parts 11 of the mounted part 10 of the through span, then the crane trolleys 7 and the assembly crane folded in the overall position are moved to the crane lifting point, respectively, along the way. m katani 12, laid on the top of the span 11 itself and using an auxiliary vehicle 13, which is moved in the level of the carriageway 14 of the span. Then, stockpile of traction cables 15 of winches b is made for longitudinal movement of the assembly crane through polyspast rollers 9 and 8, respectively transverse beams 5 and frame 4 of the lower platform, and these assembly winches the assembly crane to the level of the top 11 span structure with subsequent detachable attachment for example, using pins 16, frames 4 of the lower crane platform to the transverse beams 5. Thereafter, the pull cables 15 are released from the polysped rollers 8 and 9 and secured to the upper runway 11 of the span. Next, element-by-element assembly is carried out by means of an assembly crane of the span structure, moving the crane along the tracks on the upper 11 axles of the tub 12 with the help of winches 6 of longitudinal displacement of the assembly crane. The proposed construction of an assembly crane for the installation of through-span bridge structures ensures high efficiency of their use by self-lifting the assembly crane to the desired operating position, and the proposed method of installing an assembly crane ensures a significant reduction in its labor intensity by eliminating the need for an additional crane provided for in the known technical solution as well as the elimination of the element-by-element assembly of the crane on the upper parts of the mounted base part minute span.

Claims (2)

1. Сборочный кран дл  монтажа сквозного пролетного строени  моста, включающий верхнюю поворотную платформу со складывающимс  в габаритное положение грузоподъемным оборудованием и нижнюю платформу с рамой,, поперечными балками, лебедками дл  продольного перемещени  сборочного крана и подкрановыми тележками, объединенными попарно посредством поперечных балок, отличающийс   тем, что, с целью повьлиени  эффективности использовани  сборочного крана за счет обеспечени  его самоподъема на смонтированную базовую часть пролетного строени , рама и поперечные балки нижней платформы разъемно соединены между собой и снабжены полиспастными роликами , причем рама нижней платформы расположена под поперечными балками .1. An assembly crane for mounting the bridge span, comprising an upper rotary platform with lifting equipment folded into the overall position and a lower platform with a frame, transverse beams, winches for longitudinal movement of the assembly crane and crane cranes combined in pairs by means of transverse beams, distinguished by that, in order to increase the efficiency of use of the assembly crane by ensuring its self-lifting to the mounted base part of the span crane and the lower transverse frame and a platform girder detachably interconnected and provided polispastnymi rollers, wherein the frame is located under the lower platform crossbeams. 2. Способ установки сборочного крана на смонтированную базовую часть сквозного пролетного строени , включающий подъем и установку сборочного крана на верхние по са пролетного строени , закрепление т говых тросов лебедок дл  продольного перемещени  сборочного крана за верхние по са пролетного строени , о т л и 2. The method of installation of the assembly crane on the mounted basic part of the through-span, including lifting and installing the assembly crane on the upper span of the span, securing the winch cables for longitudinal movement of the assembly crane over the upper span, чающийс  тем, что, с целью снижени  трудоемкости установки кра- . на за счет исключени  необходимости применени  дополнительного монтажного крана, до подъема сборо-шого крана производ т подъем и установку этим краном объединенных попарно посредством поперечных балок подкрановых тележек на верхние по са смонтированной базовой части пролетного строени , после чего перемещают под0 крановые тележки и сборочный кран к месту его подъема и производ т - запасовку т говьдх тросов лебедок дл  продольного перемещени  сборочного 5 крана через полиспастные ролики поперечных балок и рамы нижней платформы , а подъем крана на верхние по са пролетного строени  осуществл ют лебедками дл  продольного перемещени  сборочного крана с после0 дующим разъемным прикреплением рамы нижней платформы к поперечным балкам, а перед закреплением т говых тросов за верхние по са пролетного строени  т говые тросы вы5 свобождают из полиспастныхРОЛИКОВ .due to the fact that, in order to reduce the complexity of the installation, by eliminating the need to use an additional mounting crane, prior to lifting the assembled crane, this crane is used to lift and install United crane in pairs by means of transverse beams of crane cranes onto the upper mounted base part of the span, then move the crane trolleys and the assembly crane to the place of its lifting and producing - stockpile of beef hoist cables for the longitudinal movement of the assembly 5 crane through the polyspast rollers of the transverse beams and the frame of the lower platform, and Lifting the crane to the upper span of the span is carried out with winches for longitudinal movement of the assembly crane with the subsequent detachable attachment of the frame of the lower platform to the transverse beams, and before fixing the pull cables to the upper span of the span, the pull of cables from the polyspast RICs. Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination 1. Кручинкин А.В. и др. Монтаж стальных пролетных строений мостов. М., Транспорт, 1978, с.129, 1. Kruchinkin A.V. et al. Installation of steel bridge span structures. M., Transport, 1978, p.129, 0 ркс. У.4.0 rks D.4. дЧ «./dch "./
SU813278508A 1981-04-14 1981-04-14 Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure SU998642A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU813278508A SU998642A1 (en) 1981-04-14 1981-04-14 Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU813278508A SU998642A1 (en) 1981-04-14 1981-04-14 Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure

Publications (1)

Publication Number Publication Date
SU998642A1 true SU998642A1 (en) 1983-02-23

Family

ID=20954387

Family Applications (1)

Application Number Title Priority Date Filing Date
SU813278508A SU998642A1 (en) 1981-04-14 1981-04-14 Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure

Country Status (1)

Country Link
SU (1) SU998642A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112160246A (en) * 2020-09-07 2021-01-01 中交路桥华南工程有限公司 Method for mounting combined beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112160246A (en) * 2020-09-07 2021-01-01 中交路桥华南工程有限公司 Method for mounting combined beam

Similar Documents

Publication Publication Date Title
CN109653105B (en) Main truss system of box girder bridge cantilever construction hanging basket and use method thereof
CN101559905A (en) Deck unit erection gantry
SU998642A1 (en) Assembly crane for mounting pass-through bridge span structure and method of setting it onto mounted base part of pass-through span structure
CN210049105U (en) Self-propelled bridge formwork operation trolley
CN101104499A (en) Tyre gantry crane
CN212924170U (en) Light door machine system for mounting prefabricated panel of wharf
CN212953978U (en) Bridge deck hoisting and transporting multifunctional vehicle for high-speed railway construction
US3982634A (en) Method and apparatus for erecting a vertical structure
JP2994935B2 (en) Bridge overhang erection method and equipment
JP2001020225A (en) Erection method of bridge and equipment therefor
SU781257A1 (en) Sluice crane
CN209618693U (en) A kind of encircling type single-beam operation trolley
CN109626208A (en) A kind of encircling type single-beam operation trolley and application method
SU1337339A1 (en) Arrangement for lifting self-propelled crane
CN221027294U (en) Double-beam truss vehicle for roof large-span steel structure steel beam construction
RU2225829C2 (en) Crane for mounting railway bridge framework
CN109457613B (en) Bridge maintenance truss vehicle installation construction method
CN216549392U (en) Simple reinforcing mesh mounting trolley
CN211079921U (en) Single-side sidewalk support mounting device
KR19980085896A (en) Anti-shake device of container crane
CN213444790U (en) Belt head optimizing device
SU1017657A1 (en) Bridge crane and method of mounting same
CN111254831B (en) Hoisting method of steel structure frame beam of through arch bridge
CN216764103U (en) Hoisting portal frame for roller type combined cable saddle
CN214692976U (en) Steel structure box girder hoisting device for crossing high frame