SU752016A1 - Laminated roof support of mine working - Google Patents

Laminated roof support of mine working Download PDF

Info

Publication number
SU752016A1
SU752016A1 SU762413844A SU2413844A SU752016A1 SU 752016 A1 SU752016 A1 SU 752016A1 SU 762413844 A SU762413844 A SU 762413844A SU 2413844 A SU2413844 A SU 2413844A SU 752016 A1 SU752016 A1 SU 752016A1
Authority
SU
USSR - Soviet Union
Prior art keywords
roof support
mine working
laminated roof
solution
rocks
Prior art date
Application number
SU762413844A
Other languages
Russian (ru)
Inventor
Юлий Зиновьевич Заславский
Евгений Борисович Дружко
Игорь Вильевич Качан
Моисей Акимович Пивник
Original Assignee
Макеевский Инженерно-Строительный Институт
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Макеевский Инженерно-Строительный Институт filed Critical Макеевский Инженерно-Строительный Институт
Priority to SU762413844A priority Critical patent/SU752016A1/en
Application granted granted Critical
Publication of SU752016A1 publication Critical patent/SU752016A1/en

Links

Landscapes

  • Laminated Bodies (AREA)

Description

1one

Изобретение относитс  к областн подземного строительства п горнодобывающей промышленности, а нменно к креплению горных выработок.The invention relates to the area of underground construction and mining industry, and especially to the fastening of mine workings.

Известны многослойные крени горных 5 выработок, включающпе внешний податливый и внутренний несущий слои 1.Known multilayer trenches of mining 5 workings, including the external pliable and internal bearing layers 1.

Недостатком их  вл етс  значительна  толщнна, что требует соответствуюн1его увеличени  сеченн  выработки.юTheir disadvantage is a significant thickness, which requires a corresponding increase in sechennogo production.

Известны также многослойные крепн, включающие нокрытие из набрызгбетона н упрочненные скрепл ющим раствором породы прикоптурной зоны 2.Also known are multi-layer fasteners, including a covering of concrete sprays and reinforced rock of a prikipturny zone 2 with a fastening solution.

Такое техннческое рещение наиболее 15 близко к изобретению по технической сущности и достигаемому результату.Such a technical solution is the most 15 close to the invention according to the technical essence and the achieved result.

Недостатком его  вл етс  ограниченна  область прпменени  - только в услови х пород, дающих незначительное смещенне 20 контура выработки.The disadvantage of it is the limited area of application - only in the conditions of the rocks, giving a slight offset of the contour 20 generation.

Целью нзобретепи   вл етс  расширение области применени  крепи.The purpose of the inventor is to expand the field of application of the support.

Достигаетс  это тем, что ограждающее покрытие выполнено из эластичного мате- 95 рнала, например, нанесением состава на основе синтетических смол или прикленваннем пленки заводского изготовлени .This is achieved by the fact that the barrier coating is made of an elastic material, for example, by applying a composition based on synthetic resins or a factory-attached film.

Предлагаема  крепь показана па чертеже . Она состоит из уироченных скрепл ю- зоThe proposed support is shown pa drawing. It consists of welded fasteners

щнх раствором разрущенных н разгруженных от напр жепнй пород прнконтурной зоны 1, выполн ющей функцнн несущей конструкпни , п эластпчпой спнтетнческой пленкп-оболочкн 2, нанесенной на контур выработкн н выно.чн ющей ограждающие и изолирующие функции.Schnh solution diluted n unloaded from the strands of the rocks of the contour zone 1, which performs the function of the supporting structure, n elastepnoy spnttehnicheskoy film-shells 2, deposited on the contour of the excavating shield enclosing and insulating functions.

Работает конструкци  следующпм образом . При отходе забо  выработки на одну заходку на породную новерхность по ее пернметру наноситс  покрытие в виде эластичной оболочки 2, выполн ющей ограждающие фуикции временной кренн и изолирующего покрыти  при пагнетании скрепл ющего раствора. Такое нокрытие снособно смещатьс  вместе с иородиым контуром без нарушени  снлошности. При необходимости может пронзводнтьс  доиолнительио установка податлпвых металлнчеекнх арок, выноли ющих несуп1ие фуикцпп временной крепи. За зоиой интенснвных смещений производптс  нагнетанне скрепл ющего раствора через трубкн-инъекторы 3 в разрушенные п разгруженные от напр жений породы прпкоптурпой зоны. Вытекание раствора в выработку при его нагнетании предотвращает изолирующа  эластична  оболочка. После затвердевани  раствора крепь представл ет собой слой затампонпрованных пород, покрытых синтетпческойThe construction works in the following way. During the withdrawal of the excavation, a coating in the form of an elastic sheath 2 is applied to its pedigree surface by its permeter; this coating is made in the form of an elastic sheath 2, which performs a fencing of a temporary roll and an insulating coating during the bonding of the bonding solution. Such a cover can be shifted along with the heterogeneous contour without disrupting the gap. If necessary, it can penetrate the installation of under-metal metal arch arches that do not accommodate a temporary support. For such intensive displacements, a solution is injected into the bonding solution through pipe-injectors 3 into the fractured and unloaded from the strains of the rock of the test zone. The outflow of the solution into the production during its injection prevents the insulating elastic shell. After solidification of the solution, the lining is a layer of sealed rocks covered with synthetic

пленкой. Слой скрепленных пород воспринимает нагрузки со стороны массива и выполн ет несущие функции крепи, а эластична  синтетическа  оболочка предохран ет нороды от выветривани .film. The layer of bonded rocks receives loads from the side of the massif and performs the supporting functions of the support, and the elastic synthetic envelope protects the rocks from weathering.

Claims (2)

1.Джанджгава Г. П. и др. Податливые креии дл  капитальных горных выработок глубокнх шахт Ткибули-Шаорского каменноугольного месторождени . Тезисы Всесоюзного научно-технического семинара 22-24 декабр  1974, Ленинград. М., 1974.1. Janjgava, G.P., et al. Compliant creations for capital mine workings at the deep mines of the Tkibuli-Shaor coal field. Abstracts of the All-Union Scientific and Technical Seminar, December 22-24, 1974, Leningrad. M., 1974. 2.Мостков В. М. Подземные сооружени  большого сечени . М., «Недра 1974, с. 57-58.2.Mostkov V.M. Underground structures of a large section. M., "The Subsurface 1974, p. 57-58.
SU762413844A 1976-10-21 1976-10-21 Laminated roof support of mine working SU752016A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU762413844A SU752016A1 (en) 1976-10-21 1976-10-21 Laminated roof support of mine working

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU762413844A SU752016A1 (en) 1976-10-21 1976-10-21 Laminated roof support of mine working

Publications (1)

Publication Number Publication Date
SU752016A1 true SU752016A1 (en) 1980-07-30

Family

ID=20680507

Family Applications (1)

Application Number Title Priority Date Filing Date
SU762413844A SU752016A1 (en) 1976-10-21 1976-10-21 Laminated roof support of mine working

Country Status (1)

Country Link
SU (1) SU752016A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103670444A (en) * 2013-10-22 2014-03-26 淮南矿业(集团)有限责任公司 Roadway bottom plate supporting structure and construction method thereof
RU175401U1 (en) * 2017-03-21 2017-12-04 Виктор Прокопьевич Тациенко Mining support

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103670444A (en) * 2013-10-22 2014-03-26 淮南矿业(集团)有限责任公司 Roadway bottom plate supporting structure and construction method thereof
CN103670444B (en) * 2013-10-22 2015-11-04 淮南矿业(集团)有限责任公司 Roadway floor supporting and protection structure and construction method thereof
RU175401U1 (en) * 2017-03-21 2017-12-04 Виктор Прокопьевич Тациенко Mining support

Similar Documents

Publication Publication Date Title
KR100473965B1 (en) How to cover building structures and materials
SU752016A1 (en) Laminated roof support of mine working
RU2214511C1 (en) Method of support of mine workings (versions)
SU629347A1 (en) Mine working roof support
SU1795100A1 (en) Method for mining thick steeply dipping coal seams
SU1467219A1 (en) Arrangement for supporting and sealing a filling chamber
SU602125A3 (en) Rock contour roof support of underground working
SU777228A1 (en) Interlayer cap for working thick steep seams with power complex
SU1511415A1 (en) Arch support
US3417568A (en) Mine shaft bratticing
SU1129365A1 (en) Earthquake-proof tunnel lining
SU726349A1 (en) Mine partition
CN214787406U (en) I-steel self-filling roadside support facility
SU1634783A1 (en) Method for protecting development galleries
SU968426A2 (en) Method of producing roof support of rock
RU2011823C1 (en) Method for mining of thick steep fire-hazardous coal seams
SU939767A1 (en) Roof support for mine workings
SU806873A1 (en) Support for carrying interlevel pillars
SU1442659A1 (en) Method of supporting mine workings
SU1043325A1 (en) Method of erecting filling-up mine partition
SU861614A1 (en) Method of erecting steel-concrete lining
SU1546650A1 (en) Method of relieving the outline of mine working
RU94006946A (en) METHOD OF MANAGEMENT OF ROOFS AT MULTILAYER SIMULTANEOUS EXTRACT OF POWERFUL CUTTING COAL AGAIN AND DEVICE FOR ITS IMPLEMENTATION
SU1740540A1 (en) Dome-shaped pressure tunnel
SU1710750A1 (en) Method of mining thick coal seams with filling