SU680987A1
SU680987A1 SU782606630A SU2606630A SU680987A1 SU 680987 A1 SU680987 A1 SU 680987A1 SU 782606630 A SU782606630 A SU 782606630A SU 2606630 A SU2606630 A SU 2606630A SU 680987 A1 SU680987 A1 SU 680987A1
Authority
SU
USSR - Soviet Union
Prior art keywords
sections
section
load
carrying
boom
Prior art date
Application number
SU782606630A
Other languages
Russian (ru)
Inventor
Марк Ильич Лифшиц
Original Assignee
Дрогобычский завод автомобильных кранов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Дрогобычский завод автомобильных кранов filed Critical Дрогобычский завод автомобильных кранов
Priority to SU782606630A priority Critical patent/SU680987A1/en
Application granted granted Critical
Publication of SU680987A1 publication Critical patent/SU680987A1/en

Links

Landscapes

  • Jib Cranes (AREA)

Description

1one

.Изобретение относитс  к области грузоподъемных устройств, а именно к телескопическим крановым стрелам.The invention relates to the field of lifting devices, namely to telescopic crane booms.

Известна телескопическа  стрела крана, состо ща  из неподвижной, промежуточной и грузонесущей секций, гидроцилиндра и канатных полиспастов выдвижени  и складывани  секций, одними концами соединенных с грузонесущей секцией 1.The famous telescopic crane arm consists of fixed, intermediate and load-carrying sections, a hydraulic cylinder and cable polyspasts for extending and folding sections, with ends only connected to the load-carrying section 1.

Цель изобретени  - снизить нагрузки , деЧствующие на грузонесущую секцию стрелы.The purpose of the invention is to reduce the loads applied to the load-carrying boom section.

Дл  этого на неподвижной и промежуточной секци х смонтированы захваты , а другие концы канатных полиспастов снабжены скобами, взаимодействующими с захвагёц ш, причем рассто ние .между захватами йеподвижной и промежуточной секци ми в сложенном положении равно рассто нию совместного выдвижени  промежуточной и грузонесущей секций стрелы, кроме этого канатный полиспаст складывани  секций снабжен обводным блоком, смонтированным на головной части промежуточной секции.For this purpose, the grippers are mounted on the fixed and intermediate sections, and the other ends of the wire rope pulleys are equipped with brackets that interact with the gripper, and the distance between the grippers and the fixed and intermediate sections in the folded position is equal to the joint extension of the intermediate and load-carrying boom sections This cable tackle for folding sections is provided with a bypass unit mounted on the head section of the intermediate section.

На чертеже показано устройство телескопической стрелы крана.Устройство имзет основание 1, подвижкые .промежуточную 2 и грузонесущую 3 секции стрелы. Промежуточна  секци  2 жестко св зана с двусторонним гидроцилиндром 4 выдвижени  .стрелы, а грузонесуща   секци  3 св зана с промежуточной секцией 2 канатными полиспастами 5 и 6 выдвижени  и складывани  секций стрелы. Канатные полиспасты одним концом закреплены The drawing shows the device of the telescopic boom of the crane. The device has a base 1, movable. Intermediate 2 and carrying the 3 sections of the boom. The intermediate section 2 is rigidly connected to the double-sided hydraulic cylinder 4 extension arms, and the load-carrying section 3 is connected to the intermediate section 2 cable polyspasts 5 and 6 of the extension and folding of the boom sections. Rope tackles with one end secured

0 на концевом участке грузонесущей секции 3. Канатный полиспаст 5 выдвижени  имеет двустороннюю скобу 7, сцепленную с захватом 8 промежуточной секции 2 стрелы. Полиспаст про5 ходит через канаты .блока 9, который смонтирован на концевой части промежуточной секции 2, На основной секции имеетс  неподвижный захват 10. Канатный полиспаст 6 складывани  0 at the end section of the load-carrying section 3. The rope hoist 5 of the extension has a double-sided bracket 7 coupled to the catch 8 of the intermediate section 2 of the boom. The chain hoist passes through the ropes of the block 9, which is mounted on the end part of the intermediate section 2. There is a fixed grip 10 on the main section. The cable hoist 6 folds

0 стрелы имеет двустороннюю скобу 11, сцепленную с захватом 12 промежуточной 2 секции стрелы, полиспаст проходит через канатный 13 и обводной 14 блоки, укрепленные на обоих кон5 цах промежуточной 2 секции. На основной секции имеетс  неподвижный захват 15.The boom 0 has a double-sided brace 11 coupled to the gripper 12 of the intermediate 2 boom section, the pulley passes through the cable 13 and the bypass 14 blocks, fixed at both ends of the intermediate 2 section. There is a fixed gripper 15 on the main section.

Телескопическа  стрела крана ра0 ботает следующим образом.The telescopic boom of the crane works as follows.

В начальной стгщии движени , пока скобы 7 и 11 канатных полиспастов 5 и 6 сцеплены с захватами 8 и 12 промежуточной секции 2, подвижные секции 2 и 3 выдвигаютс  вместе и оперта  на промежуточную 2 секцию своим оголовком (не показан), грузонесуща  3 секци  разгружена от сжимающих и изгибающих усилий. Сжимающие усили  передаютс  непосредственно на гидроцилиндр, а изгибающие на основную секцию стрелы. При дгшьнейшем движении скоба 7 полиспаста 5 сцепл етс  с захватом 10, а скоба 11 полиспаста 6 сцепл етс  с захватом 15 основной секции стрелы. Теперь одновременно движетс  промежуточна  секци  2 за счет движени  гидроцилиндра и выдвигаетс  грузонесуща  секции за счет канатного полиспаста 5. Полиспаст 6 подт гиваетс  дл  вт гивани  секции 3.In the initial movement, while the shackles 7 and 11 of the rope pulley 5 and 6 are engaged with the grippers 8 and 12 of the intermediate section 2, the movable sections 2 and 3 are pushed together and supported on the intermediate 2 section with their tip (not shown), the load-carrying 3 section is unloaded from compressive and bending forces. The compressive forces are transmitted directly to the hydraulic cylinder, and the booms bending onto the main section. In the case of the most recent movement, the clevis 7 of the chain pulley 5 engages with the grip 10, and the clevis 11 of the polyspast 6 engages with the gripper 15 of the main boom section. Now the intermediate section 2 is simultaneously moving due to the movement of the hydraulic cylinder, and the load-carrying section is advanced at the expense of the cable hoist 5. The pulley 6 is pulled up to retract section 3.

При вт гивании цилиндра одновремйнно вт гиваютс  промежуточные секции 2 стрелы и грузонесуща  секци  3 за счет работы полиспаста 6. После сцеплени  скобы 11 с захватом 12 вт гиваетс  только промежуточна  секци  2. Секци  3 соединена с секцией 2 неподвижно.When the cylinder is pulled in at the same time, the intermediate sections 2 of the boom and the load-carrying section 3 are drawn in due to the operation of the polyspast 6. After the clamping of the bracket 11 with the gripper 12, only the intermediate section 2 is drawn in. Section 3 is connected to section 2 stationary.

Claims (2)

1.Телескопическа  стрела крана, состо ща  из основной, промежуточной и грузонесущей секций гидроцилиндра и канатных полиспастов выдвижени  и складывани  секций, одними концалш соединенных с грузонесущей секцией, отличающа с   тем, что, с целью снижени  нагрузок действующих на грузонесущую секцию стрелы, на неподвижной и промежуточной секци х смонтированы захваты , а другие концы канатных полиспастов снабжены скобами, взаимодействующими с зг1хватами, причем рассто ние между захватс1ми неподвижной и промежуточной секци ми в сложенном положении равно рассто ни совместного выдвижени  промежуточно и грузонесущей секций стрелы.1. A telescopic crane boom consisting of the main, intermediate and load-carrying sections of the hydraulic cylinder and cable polyspasts for extending and folding the sections, one end connected to the load-carrying section, is characterized by the fact that, in order to reduce the loads acting on the load-carrying boom section, the intermediate sections are fitted with clamps, and the other ends of the cable hoists are equipped with brackets that interact with the grippers, and the distance between the gripping fixed and intermediate sections in the folded The position is equal to the distance of the joint extension of the intermediate and load carrying boom sections. 2.Стрела по п.1, отличающа с  тем, что канатный полиспаст складывани  секций снабжен обводным блоком, смонтированным на головной части промежуточной секции .2. Arrow according to claim 1, characterized in that the rope tackle of folding sections is provided with a bypass unit mounted on the head part of the intermediate section. Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination 1. Акцептованна  за вка Японии 48-5141, кл. 83 F 2, 1973.1. Accepted for Japan 48-5141, cl. 83 F 2, 1973. 6 //4-4- ,6 // 4-4-, -Л,L//-L, L // -Z „ - -JИ/И .SO-Z „- -JИ / И .SO лl ЯI
SU782606630A 1978-04-20 1978-04-20 Telescopic crane boom SU680987A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782606630A SU680987A1 (en) 1978-04-20 1978-04-20 Telescopic crane boom

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782606630A SU680987A1 (en) 1978-04-20 1978-04-20 Telescopic crane boom

Publications (1)

Publication Number Publication Date
SU680987A1 true SU680987A1 (en) 1979-08-25

Family

ID=20760662

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782606630A SU680987A1 (en) 1978-04-20 1978-04-20 Telescopic crane boom

Country Status (1)

Country Link
SU (1) SU680987A1 (en)

Similar Documents

Publication Publication Date Title
US3465899A (en) Telescoping boom for hydraulic crane
KR900700375A (en) Extension Hook Shifter for Deep Water
SU680987A1 (en) Telescopic crane boom
WO2011124122A1 (en) Telescoping jib mechanism of crane
JP2801649B2 (en) 5-stage telescopic boom device
US4453643A (en) Cranes
CN202379623U (en) Hoisting mechanism and reach stacker
GB1262553A (en) A telescopic crane boom
FI80005C (en) FOERFARANDE FOER FASTGOERING AV LYFTKRAN.
RU2025456C1 (en) Telescopic boom of crane
SU1079601A1 (en) Crane telescopic boom
SU1728123A1 (en) Telescopic crane boom
RU2045467C1 (en) Load-lifting crane boom
CN220283413U (en) Lifting arm with single-cylinder five-section arm telescopic mechanism
SU1557081A1 (en) Crane
SU1402556A1 (en) Cargo-lifting crane
RU2356827C1 (en) Manipulating device
SU1324993A1 (en) Crane
SU653208A1 (en) Crane
SU455063A1 (en) Jib crane
JPH0441691Y2 (en)
SU1654238A1 (en) Erecting crane
US4068881A (en) Arrangement for automatic regulation of the cable length of a holding cable of grab means
SU1331814A1 (en) Outrigger of load-handling machine
JPH0427915Y2 (en)