SU675186A1 - Method of mining minerals - Google Patents

Method of mining minerals

Info

Publication number
SU675186A1
SU675186A1 SU782576576A SU2576576A SU675186A1 SU 675186 A1 SU675186 A1 SU 675186A1 SU 782576576 A SU782576576 A SU 782576576A SU 2576576 A SU2576576 A SU 2576576A SU 675186 A1 SU675186 A1 SU 675186A1
Authority
SU
USSR - Soviet Union
Prior art keywords
bookmark
pillars
laying
mining
workings
Prior art date
Application number
SU782576576A
Other languages
Russian (ru)
Inventor
Дмитрий Михайлович Бронников
Николай Федорович Замесов
Григорий Степанович Кириченко
Геннадий Ильич Богданов
Игорь Израильевич Айнбиндер
Юрий Васильевич Поляков
Казбек Тимофеевич Мезенцев
Геннадий Вениаминович Вебер
Original Assignee
Институт проблем комплексного освоения недр АН СССР
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт проблем комплексного освоения недр АН СССР filed Critical Институт проблем комплексного освоения недр АН СССР
Priority to SU782576576A priority Critical patent/SU675186A1/en
Application granted granted Critical
Publication of SU675186A1 publication Critical patent/SU675186A1/en

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Claims (2)

тил ции и как запасной выход, а нижн   - как рудоспуск, наращиваемый по мере выемки в закладке. --Очистные работы в пределах участка начинают с проходки выработок 4 в основании будущих временных целиков 5 на всю их ширину, например 4м. Затем всфаботкн ,4 полностью запблнШтс  закладкой с ЭаданнЕШй кЪмпрёс сйЬнй ыли cBoftcTBjiMH. Основные эапасаа 6 рудного тела 1 отрабатыв ают между целиками 5 сло  ми снизу вверх с закладкой. Целики 5 опирают на податливые основани , обр зованные закладкой выработок 4 материёшом с заданными компрессионными С а6йствами. На заключительной стадии очистныйс работ извлекают целики 5 на податливых основани х сло ми Ьверху вниз с последующей закладкой . Одновременно с этим начинают от работку последующего участка 3. Предаагаемый способ позвол ет обеспечить безопасную выемку пЬйезных ископаемых любых размеров в усло ви х noBbsseHHOro горного давлени  без снижени  эффективности использовани  крупногабаритного высокопроизводительного самоходного добычного и транспортного оборудовани . Формула изЪбретени  1. Способ разработки месторсовдений полезных ископаемых, включающий сплошную слоевую выемку полезного ископаемого снизу вверх с закладкой выработанного пространства, отличающий с   тем, что, с целью повышени  эффективности очистной выемки на больижх глубинах путем снижени  горного давлени  в зоне очистных работ, у почвы рудного тела проход т выработки, заполн ют их закладкой с заданными компрессионными свойствами и по мере отработки участка рудного тела между заложенными выработками над последними оставл ют рудные цеЛики, а после отработки и закладки участка отрабатывйют указанные целики сверху вниз с после чующей закладкой выработанного йространства, причем ширину отрабатываемого участка-принимают меньше ширины зоны разгрузки. 2. Способ по п. 1, о т л и чающийс  тем, что последующего участка провод т . одновременно с извлечением целиков отработанного участка. Источники информации, прин тые во внимание экспертизе 1.Бронников Д. М. и др. Основы технологии подземной разработки, рудных месторождений с закладкой, М., Наука, 1973, с. 15-19, liO-118. as well as an emergency exit, and the bottom as an ore pass, which grows as you dig in the tab. - Cleaning work within the site begins with the excavation of workings 4 at the base of future temporary pillars 5 for their entire width, for example, 4 m. Then scroll through, 4 completely bookmarked with the EdenAnSHympy sympy sylny cABoftcTBjiMH. The main components of the ore body 1 are worked out between the pillars 5 layers upwards with a bookmark. The entire pillars 5 are supported on the pliable bases, formed by the laying of the workings 4 with a given material with the specified compression gears. At the final stage of cleansing works, pillars 5 are removed on ductile bases with layers b from top to bottom with subsequent laying. At the same time, the next section 3 is started from the proposed method. This method allows for safe extraction of useful minerals of any size under noBbsseHHOro mining pressure conditions without reducing the efficiency of using large-sized high-performance self-propelled mining and transport equipment. The formula of the extract is 1. A method of developing mineral deposits, including a continuous layered excavation of minerals from the bottom up with laying out of the exhausted space, characterized in bodies pass the mine workings, fill them with a bookmark with given compression properties, and as the area of the ore body is mined between the laid workings above the latter, p After the mining and laying of the section, the unitary heels are worked from top to bottom with the remaining bookmark of the developed area, and the width of the section being worked out is taken less than the width of the unloading zone. 2. The method of claim 1, wherein the following section is carried out. simultaneously with the extraction of the plots of the waste area. Sources of information taken into account in the examination 1. DM Bronnikov and others. Fundamentals of technology of underground mining, ore deposits with bookmark, M., Nauka, 1973, p. 15-19, liO-118. 2.Авторское свидетельство СССР 487236, кл. Е 21 С 41/06, 1971.2. Authors certificate of the USSR 487236, cl. E 21 C 41/06, 1971. / // /
SU782576576A 1978-02-03 1978-02-03 Method of mining minerals SU675186A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782576576A SU675186A1 (en) 1978-02-03 1978-02-03 Method of mining minerals

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782576576A SU675186A1 (en) 1978-02-03 1978-02-03 Method of mining minerals

Publications (1)

Publication Number Publication Date
SU675186A1 true SU675186A1 (en) 1979-07-25

Family

ID=20747510

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782576576A SU675186A1 (en) 1978-02-03 1978-02-03 Method of mining minerals

Country Status (1)

Country Link
SU (1) SU675186A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4799738A (en) * 1981-11-03 1989-01-24 Tatabanyai Szenbanyak Mining method for working large-scale mineral deposits by the caving system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4799738A (en) * 1981-11-03 1989-01-24 Tatabanyai Szenbanyak Mining method for working large-scale mineral deposits by the caving system

Similar Documents

Publication Publication Date Title
SU675186A1 (en) Method of mining minerals
SU1668667A1 (en) Method for combination mining of gently sloping seams
RU2034149C1 (en) Method for mineral mining from pipeline orebody
SU666276A1 (en) Mine drainage method
SU750072A1 (en) Method of working sloping ore deposits
SU898074A1 (en) Method of working gently sloping ore deposits
SU883446A1 (en) Method of working ore bodies
SU800371A1 (en) Method of working thick mineral fields
SU1461942A1 (en) Method of mining thick ore deposits
SU1668670A1 (en) Method for mining inclined ore bodies
SU1723326A1 (en) Method for recultivation of land broken by open-pit mining
SU1020580A1 (en) Method of mining thick ore bodies
SU706536A1 (en) Method of mining great ore deposits
SU546715A1 (en) The way to develop weak unstable ores
SU1083662A1 (en) Method of mining steep-slope ore-bodies
SU998756A1 (en) Method of working coal beds in suit within safety pillar under water basins
SU1337517A1 (en) Method of combined underground/open mining of coal beds
RU2086767C1 (en) Method for development of flat deposits
SU732533A1 (en) Method for mining ore deposits
SU492662A1 (en) Method for developing steeply dipping ore bodies
RU2215145C1 (en) Method of mineral deposit underground mining in strips
RU2083833C1 (en) Method for development of steep coal seams with backing worked-out area
SU1717821A1 (en) Method for mining mineral deposits
SU1382958A1 (en) Method of mining thick deposits
SU742589A1 (en) Method of mining super-thin sharply assending seams