SU1723326A1 - Method for recultivation of land broken by open-pit mining - Google Patents

Method for recultivation of land broken by open-pit mining Download PDF

Info

Publication number
SU1723326A1
SU1723326A1 SU904807803A SU4807803A SU1723326A1 SU 1723326 A1 SU1723326 A1 SU 1723326A1 SU 904807803 A SU904807803 A SU 904807803A SU 4807803 A SU4807803 A SU 4807803A SU 1723326 A1 SU1723326 A1 SU 1723326A1
Authority
SU
USSR - Soviet Union
Prior art keywords
layer
soil
recultivation
overburden
mining
Prior art date
Application number
SU904807803A
Other languages
Russian (ru)
Inventor
Геннадий Валентинович Секисов
Юрий Алексеевич Мамаев
Виктор Семенович Литвинцев
Original Assignee
Институт горного дела Дальневосточного отделения АН СССР
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт горного дела Дальневосточного отделения АН СССР filed Critical Институт горного дела Дальневосточного отделения АН СССР
Priority to SU904807803A priority Critical patent/SU1723326A1/en
Application granted granted Critical
Publication of SU1723326A1 publication Critical patent/SU1723326A1/en

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

Изобретение относитс  к горной промышленности и может быть использовано при рекультивации карьеров при открытой разработке месторождений полезных ископаемых . Цель изобретени  - повышение эф- фективности рекультивации за счет интенсификации процесса восстановлени  земель и повышени  качества рекультивации при снижении затрат на рекультивацию . Перед обработкой полезного ископаемого производ т выемку почвенно- растител ьного сло  совместно со слоем подстилающих пород вскрыши. Величину этого сло  принимают равной глубине проникновени  в него биологической и гидрологической св зей.3 ил. (ЛThe invention relates to the mining industry and can be used in the rehabilitation of quarries in the open pit mining of mineral deposits. The purpose of the invention is to improve the efficiency of recultivation due to the intensification of the process of land restoration and improving the quality of reclamation while reducing the costs of recultivation. Before processing the mineral, the soil and vegetation layer is excavated together with the bedding rock overburden. The size of this layer is assumed to be equal to the depth of penetration of biological and hydrological bonds into it. 3 Il. (L

Description

Изобретение относитс  к горной промышленности и может быть использовано при рекультивации карьеров при открытой разработке месторождений полезных ископаемых .The invention relates to the mining industry and can be used in the rehabilitation of quarries in the open pit mining of mineral deposits.

Известен способ рекультивации при открытой разработке месторождений полез- ных ископаемых, включающий выемку, перемещение и складирование во временные отвалы почвенного сло , отработку карьерного пол , погрузку и транспортировку почвенного сло  к месту укладки.There is a known method of recultivation in case of open-cast mining of mineral deposits, including excavation, relocation and storage in the temporary dumps of the soil layer, mining of the quarry floor, loading and transportation of the soil layer to the place of laying.

Недостатками известного способа почвенного сло   вл етс  смешивание его с вскрышными породами, что затрудн ет процесс восстановлени  нарушенных земель.The disadvantages of this method of soil layer is mixing it with overburden, which makes it difficult to restore disturbed lands.

Наиболее близким к предлагаемому  вл етс  способ рекультивации, включающий раздельную выемку, перемещение и складирование во временные отвалы почвенногоThe closest to the present invention is a reclamation method, which includes separate excavation, relocation and storage in temporary dumps of soil.

сло  и вскрышных пород, отработку карьерного пол , перемещение и укладку вскрышных пород и почвенного сло .layer and overburden, quarrying, moving and laying of overburden and soil layer.

Недостатком способа  вл етс  его низка  эффективность.The disadvantage of this method is its low efficiency.

Целью изобретени   вл етс  повышение эффективности рекультивации за счет интенсификации процесса восстановлени  земель и повышени  качества рекультивации при снижении затрат на рекультивацию.The aim of the invention is to improve the efficiency of recultivation due to the intensification of the land restoration process and the improvement of the quality of reclamation while reducing the costs of reclamation.

Поставленна  цель достигаетс  тем, что в способе рекультивации при открытой разработке месторождений полезных ископаемых , включающем выемку, перемещение и складирование во временные отвалы вскрышных пород и почвенно-растительного сло , отработку полезного ископаемого, перемещение м укладку вскрышных пород и почвенно-растител ьного сло  на место первоначального залегани , выемку почвенноVIThe goal is achieved by the fact that in the method of recultivation during the open development of mineral deposits, including the excavation, movement and storage in temporary dumps of overburden and soil and vegetation layer, mining, moving overburden laying and soil and vegetation layer in place initial bedding, soil excavation VI

ГО CJGO CJ

ы ю оs o

растительного сло  осуществл ют совместно с подстилающими породами вскрыши на глубину проникновени  в них биологической и гидрологической св зи с почвенно- растительным слоем.the plant layer is carried out together with the underlying rocks of overburden to the depth of penetration of biological and hydrological bonds with the soil and plant layer in them.

На фиг.1 схематично показано карьерное поле, разрез; на фиг,2 - то же, в стадии ведени  работ; на фиг.З - то же, в стадии закладки.Figure 1 schematically shows a career field, a section; Fig. 2 is the same under maintenance; on fig.Z - the same, in a bookmark stage.

Способ осуществл ют следующим об- разом.The method is carried out as follows.

Карьерное поле месторождени  раздел ют на блоки. В пределах блока заходками специальным горным оборудованием с Фре- зерно-грейферным рабочим органом произ- вод т выемку почвенно-растительного сло  совместно с подстилающими породами вскрыши 2 на глубину их биологической и гидрологической св зи с почвенно-расти- тельным слоем и перемещают их во вре- менные отвалы за пределы разрабатываемого блока. Далее производ т выемку и перемещение пород вскрыши 3. Затем отрабатывают продуктивный пласт 4 с извлечением из него ценного компонента. После отработки продуктивного пласта 4 осуществл ют закладку выработанного пространства 5 пустой породой 6, включающей в себ  породы вскрыши и хвосты обогащени  полезного ископаемого, а также почвен- The career field of the deposit is divided into blocks. Within the block, with special mountain equipment with a freestone-clamshell working unit, the soil and vegetation layer is excavated together with the underlying rocks of overburden 2 to the depth of their biological and hydrological connection with the soil and vegetation layer. - exchange heaps outside the developed block. Then, excavations and overburden rocks 3 are removed and then reservoir 4 is processed with extraction of a valuable component from it. After mining the productive formation 4, the excavated space 5 is laid with waste rock 6, which includes overburden rock and the tailings of the mineral, as well as soil

но-растительным слоем 1 совместно с подстилающими породами вскрыши 2, Этим заканчиваетс  горно-технический процесс рекультивации блока. Пор док отработки последующих блоков повтор етс .but the vegetative layer 1 together with the bedding of the overburden 2, this ends the mining and technical process of reclamation of the block. The order of processing subsequent blocks is repeated.

Использование предлагаемого способа позвол ет сократить продолжительность процесса восстановлени  нарушенных горными породами земель, тем самым повышает эффективность рекультивации.The use of the proposed method allows to reduce the duration of the process of restoring the lands disturbed by rocks, thereby increasing the efficiency of reclamation.

Claims (1)

Формула изобретени  Способ рекультивации земель нарушенных открытыми горными работами, включающий выемку почвенно-растительного сло  и подстилающих вскрышных пород, их раздельное складирование, перемещение вскрышных пород и почвенно-растительного сло  на прежнее место после отработки полезного ископаемого, отличающийс  тем, что, с целью повышени  эффективности рекультивации за счет интенсификации процесса восстановлени  земель и повышени  качества рекультивации при снижении затрат на рекультивацию, выемку почвенно- растительного сло  производ т совместно с подстилающими вскрышными породами слоем, равным глубине проникновени  в них биологической игидрологической св зй с почвен но-растительным слоем.Claims The method of land reclamation disturbed by open-pit mining, including the excavation of the soil and vegetation layer and underlying overburden, their separate storage, movement of the overburden and the soil and vegetation layer to its former place after mining, which is different in that recultivation due to the intensification of the land restoration process and the improvement of the quality of recultivation while reducing the cost of reclamation and soil and vegetation This layer is produced together with the underlying overburden layer, equal to the depth of penetration into them of biological and hydrological bonds with the soil-plant layer. Фиг. IFIG. I Фмг. 3Fmg 3 ФМП.: 2FMP .: 2
SU904807803A 1990-03-29 1990-03-29 Method for recultivation of land broken by open-pit mining SU1723326A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU904807803A SU1723326A1 (en) 1990-03-29 1990-03-29 Method for recultivation of land broken by open-pit mining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU904807803A SU1723326A1 (en) 1990-03-29 1990-03-29 Method for recultivation of land broken by open-pit mining

Publications (1)

Publication Number Publication Date
SU1723326A1 true SU1723326A1 (en) 1992-03-30

Family

ID=21504797

Family Applications (1)

Application Number Title Priority Date Filing Date
SU904807803A SU1723326A1 (en) 1990-03-29 1990-03-29 Method for recultivation of land broken by open-pit mining

Country Status (1)

Country Link
SU (1) SU1723326A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2478165C2 (en) * 2011-07-01 2013-03-27 Алексей Тимофеевич Лавриненко Formation method of root layer of surface of dumps formed with open mining of mineral deposits for biological reclamation
CN102877846B (en) * 2012-09-18 2014-10-01 中国矿业大学(北京) Unit method based mined and reclaimed topsoil stripping time determining method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
Авторское свидетельство СССР № 929842, кл.Е 21 С 41/02, 1980. Временные методические указани по рекультивации нарушенных земель в угольной промышленности, ВНИИОСуголь, Пермь, 1980, с.46-57. *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2478165C2 (en) * 2011-07-01 2013-03-27 Алексей Тимофеевич Лавриненко Formation method of root layer of surface of dumps formed with open mining of mineral deposits for biological reclamation
CN102877846B (en) * 2012-09-18 2014-10-01 中国矿业大学(北京) Unit method based mined and reclaimed topsoil stripping time determining method

Similar Documents

Publication Publication Date Title
Gunn et al. Limestone quarrying and quarry reclamation in Britain
RU2344291C2 (en) System of deposit development
SU1723326A1 (en) Method for recultivation of land broken by open-pit mining
RU2428567C1 (en) Ecogeotechnological method of repeated underground development of technogenic gravel deposits of permafrost zone
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits
Bartle et al. Mining and rehabilitation
RU2285121C1 (en) Method for open underground extraction of series of slightly inclined coal beds
RU2099524C1 (en) Combined method of mining of formation of steeply dipping coal seams
RU2239066C1 (en) Method for extraction and primary concentration of diamond-placers
RU2762170C1 (en) Method for developing thin and low-powered steel-falling ore bodies
RU2091583C1 (en) Method of mining of mineral upper horizons
RU2010953C1 (en) Method of determination of cracks spreading height in basic zone of working
RU2086767C1 (en) Method for development of flat deposits
SU1083662A1 (en) Method of mining steep-slope ore-bodies
Evans The Opencast Mining of Ironstone and Coal
RU96109970A (en) COMBINED METHOD FOR DEVELOPING STEPS OF STEEP COAL COAST
RU1774996C (en) Method of forming terraces
SU796428A1 (en) Method of working gently sloping and sloping adjoining coal beds
SU1452992A1 (en) Method of remining of mineral deposits
RU2182664C2 (en) Method of mining solid mineral deposits
SU1490282A1 (en) Method of preventing floodings of undermined surfaces area with subsoil and surface water
SU1097793A1 (en) Method of strip mining of horizontal and gently-sloping beds of minerals
SU732531A1 (en) Method for open mining of mineral deposits
SU1122828A1 (en) Method of combination mining of seam deposits
SU1831569A3 (en) Mining of mineral deposits